NLC Tender

This document summarizes a tender notice for the installation of a 2 x 10 MW grid interactive solar PV power project integrated with an 8 MWh battery energy storage system in Andaman, India. It includes operation and maintenance of the system for 10 years. The key details are: - The tender is for a 20 MW solar PV project with 8 MWh battery storage to be installed in Andaman, India. It includes 10 years of operation and maintenance. - The bid submission includes an online process, physical forms, and potential e-reverse auction. The bid due date is March 27, 2018. - A bid guarantee of 1.63 crores Indian rupees is required. The pre-

Uploaded by

Sakthi Ganesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
381 views328 pages

NLC Tender

This document summarizes a tender notice for the installation of a 2 x 10 MW grid interactive solar PV power project integrated with an 8 MWh battery energy storage system in Andaman, India. It includes operation and maintenance of the system for 10 years. The key details are: - The tender is for a 20 MW solar PV project with 8 MWh battery storage to be installed in Andaman, India. It includes 10 years of operation and maintenance. - The bid submission includes an online process, physical forms, and potential e-reverse auction. The bid due date is March 27, 2018. - A bid guarantee of 1.63 crores Indian rupees is required. The pre-

Uploaded by

Sakthi Ganesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 328

NLC INDIA LIMITED

(FORMERLY NEYVELI LIGNITE CORPORATION LIMITED)


(A“Navratna” -Government of India Enterprise)
Block – 1, NEYVELI – 607 801, Cuddalore Dist. Tamil Nadu, INDIA.

OFFICE OF THE CHIEF GENERAL MANAGER / CONTRACTS


CORPORATE OFFICE

Volume-1 of 2
TENDER DOCUMENT
FOR
Installation of 2 x 10 MW (AC) Grid interactive Solar PV Power Project integrated with
8 MWhr. Battery Energy Storage System at Andaman includes Operation and
Maintenance of the entire system for ten years after one year warranty period

INTERNATIONAL COMPETITIVE BIDDING


Through e-Tender and e-Reverse auction
Tender No. CO CONTS/ 0006G / PV Solar - BESS /ICB/Andaman/e-conts/ 2018, dt.24.02.2018
Pre bid conference : 14.03.2018 at 11.00 Hrs.
Last Date & Time for submission of Bid : 27.03.2018 at 14.30 Hrs.
Date & Time of Opening (Cover-I& II) : 27.03.2018 at 15.00 Hrs. (IST)

Phone No:04142/252210,251620 Fax No.04142-252026/252645/252646


Web site: WWW.nlcindia.com Email:gmconts_co@nlcindia.com

Registered Office: First Floor, No.8,Mayor Sathyamurthy Road,


FSD, Egmore Complex,Chetpet, Chennai-600 031.

Page 1 of 328 This Document has been digitally signed.


SCHEDULE OF TENDER (SOT)

NLCIL TENDER No. CO CONTS/ 0006G / PV Solar-BESS/ICB/


Andaman/e-conts/ 2018, dt.24.02.2018.

MODE OF TENDER Physical forms in sealed Cover and


e-Tendering System (Online QR, Techno-
Commercial Bid &Price Bid and e-Reverse
auction)

Date of Tender document available to Bidders 02.03.2018 to 26.03.2018


for downloading.
Tender Fee Rs.30,000/- or
USD 463 or
Euro 376
Non-refundable
Bid Guarantee Amount Rs. 1,63,00,000/-or
USD 2,51,455 or
Euro 2,04,352
Date of Pre Bid Conference& Venue 14.03.2018 at 11.00 Hrs. (IST) at Conference
Hall of Corporate Contracts Division,
Corporate Office, Block –1, Neyveli 607801.
Date of Starting of e-Tender for submission of From 14.03.2018 at 11.00 Hrs. IST
on line QR, Techno-Commercial Bid and
Price Bid

Last date of Remitting Tender fee & 23.03.2018 at 16.00 hrs. IST
Registration

Date of closing of online e-tender for 27.03.2018 at 14.30 hrs. IST


submission of QR documents, Integrity pact,
Techno-Commercial details and Price
schedule

Last Date & Time of submission of Physical 27.03.2018 at 14.30 hrs. IST
forms in sealed cover (i.e. Bid Guarantee,
Letter of undertaking and Check list for
compliance of important Tender Conditions.)

Date & Time of opening of Physical forms 27.03.2018 at 15.00 hrs. IST
sealed in sealed Cover.

Date & time of opening of e-Bids (Cover – II) 27.03.2018 at 15.00 hrs. IST
(i.e. QR documents ,Integrity pact, Techno-
Commercial details and Price schedule)

Date of e-Reverse Auction To be informed later

Page 2 of 328
INDEX

Sl. Details Page No.


No
SECTION – A
1. Notice Inviting Bids 5
SECTION – B
1. Qualifying Requirements 14
SECTION - C
Instruction to Bidders for submission of online Bids through
e-Tender and e-reverse auction.
1. Pre requisites for accessing NLCIL Website 18
2. Registration 18
3. Payment of Tender Fee 19
4. Bidding process 19
5. Process of e-tender 20
6. Bidding in e-Tender & reverse auction 20
SECTION - D
Invitation to Bid
1. Invitation 23
2. About NLCIL 23
3. Scope of Work 23
4. Bid Guarantee 24
5. Tender Documents 24
6. Bid Submission and Opening 25
7. General 28
8. Effect and Validity of Bid 29
9. Clarification 29
10. Latest hour for receipt of Bids 29
11. Single Bidder Responsibility 30
12. No claim for compensation for submission of Bid 30
13. Policy of Bids under consideration 30
14. NLCIL’s Right to accept Bid 30
15. Deputation of Representatives for discussion 30
16. Evaluation of Bids 31
17. Local conditions 33
18. Signature of Bids 33
19. Award of Criteria 34
20. Integrity Pact Programme 34

Page 3 of 328
21. Agency commission 35
22. Vital Clauses 35
23. Conditions of Contract 35

Section - E
Specimen of Formats

Annexure-A - Schedule of Prices

01. Schedule of Prices – General Instructions to Bidders. 37


02. Schedule of Prices 38-46

Annexure-B - Rules for Reverse Auction. 47


Annexure-C - Letter of Undertaking 49
Annexure-D - Check list for compliance of Important Tender conditions 50
Annexure-E - Bid Guarantee form& Integrity Pact 51-57
Annexure-F - List of Forms 58-72

Page 4 of 328
SECTION - A

(Newspaper)
NLC INDIA LIMITED
(FORMERLY NEYVELI LIGNITE CORPORATION LIMITED)

OFFICE OF THE CHIEF GENERAL MANAGER / CONTRACTS


CORPORATE OFFICE, NEYVELI - 607 801
INTERNATIONAL COMPETITIVE BIDDING
Through e-tender and e-reverse auction

NOTICE INVITING BIDS

1.0 Online Bids in English are invited by NLC INDIA LIMITED, NEYVELI for the
following:
Tender No. CO CONTS/0006G/ PV Solar- BESS/ICB/Andaman /e-conts/2018,
dt.24.02.2018.
Name of the work Installation of 2 x 10 MW (AC) Grid
interactive Solar PV Power Project
integrated with 8 MWhr. Battery
Energy Storage System at Attam Pahad and
at Dolly Gunj, Port Blair, South Andaman.
The scope of work also includes Operation
and Maintenance of the entire system for
ten years after one year warranty period.

Date of NIB available to parties to 02.03.2018 to 26.03.2018


download
Bid Guarantee Amount 1,63,00,000/- or
USD 2,51,455 or
Euro 2,04,352
Tender Fee 30,000/- or
USD 463 or
Euro 376
Last date and time for receipt of bids 27.03.2018 upto 14.30 Hrs. (IST)
Date & Time of Bid Opening 27.03.2018 at 15.00 Hrs. (IST)
Date of Pre-Bid Conference 14.03.2018 at 11.00 Hrs. (IST)

2.0 For further details such as Qualifying Requirements, Detailed Scope of work etc. and
Tender Document please log on to our website: www.nlcindia.com or Central Public
Procurement Portal (CPPP) of Government of India, web site : www.eprocure.gov.in or
contact the Chief General Manager / Contracts, NLC India Ltd., Corporate Office,
Block-1, Neyveli - 607 801, Cuddalore District, Tamil Nadu, India. Phone: 04142-
252210, 251620, Fax: 04142-252026 / 252645/ 252646.

CHIEF GENERAL MANAGER /CONTRACTS

Page 5 of 328
(Web)
(Newspaper)
NLC INDIA LIMITED
(FORMERLY NEYVELI LIGNITE CORPORATION LIMITED)
OFFICE OF THE CHIEF GENERAL MANAGER / CONTRACTS
CORPORATE OFFICE, NEYVELI - 607 801
INTERNATIONAL COMPETITIVE BIDDING
Through e-tender and e-reverse auction
NOTICE INVITING BIDS

1.0 Online Bids in English are invited by NLC INDIA LIMITED, Neyveli for the
following:

Tender No. CO CONTS/0006G/ PV Solar- BESS/ICB/Andaman /e-conts/2018,


dt.24.02.2018.
Name of the work Installation of 2 x 10 MW (AC) Grid
interactive Solar PV Power Project
integrated with 8 MWhr. Battery Energy
Storage System at Attam Pahad and at
Dolly Gunj, Port Blair, South Andaman.
The scope of work also includes Operation
and Maintenance of the entire system for
ten years after one year warranty period.

Date of NIB available to parties to 02.03.2018 to 26.03.2018


download
Bid Guarantee Amount 1,63,00,000/- or
USD 2,51,455 or
Euro 2,04,352
Tender Fee 30,000/- or
USD 63 or
Euro 376
Last date and time for receipt of bids 27.03.2018upto 14.30 Hrs. (IST)
Date & Time of Bid Opening 27.03.2018at 15.00 Hrs. (IST)
Date of Pre-Bid Conference 14.03.2018 at 11.00 Hrs. (IST)

1.1.3 The points for discussion during Pre-Bid Conference shall be furnished in advance, at
least two days before the scheduled date of pre-bid Conference, both in hard and soft
copy (editable copy) to the undersigned and also to the following E-mail ID:
gmconts_co@nlcindia.com, gmconts@gmail.com,gmconts_co@rediffmail.com.
Note:
i. For further details such as Qualifying Requirements, Scope of work, etc. and Tender
Document please visit our website: www.nlcindia.com or Central Public Procurement
Portal (CPPP) of Government of India, website : www.eprocure.gov.inor contact Chief
General Manager / Contracts, Corporate Office, NLC India Ltd., Block-1,
Neyveli - 607 801. Phone: 04142 - 252210, 251620, Fax 04142 – 252026 /
252645/ 252646. E-Mail ID: gmconts_co@nlcindia.com, gmconts@gmail.com,
gmconts_co@rediffmail.com.
.
6

Page 6 of 328
ii) Amendments /Errata /corrigendum/clarifications, if any issued for the tender
shall form part and parcel of the tender document. Amendments/Errata/
corrigendum/clarifications will be posted in NLCIL’s web site:
www.nlcindia.com and Central Public Procurement Portal (CPPP) of
Government of India, website: www.eprocure.gov.in. Bidders are requested to
visit NLCIL’s web site: www.nlcindia.com or Central Public Procurement
Portal (CPPP) of Government of India, website: www.eprocure.gov.inand note
the amendments before submission of offer. Any ignorance on the part of the
firms in not seeing the website will not be an excuse. NLCIL shall not be
responsible if any Bidder omits to notice any amendments/Errata / corrigendum
/ clarification. Amendments /Errata / corrigendum / clarification will be
numbered serially. The bidders are requested to sign all the Amendments /
Errata / Corrigendum / Clarifications issued for the tender and enclose along
with the bid as these form part and parcel of tender document.
2.0 QUALIFYING REQUIREMENTS
PRE-QUALIFICATION REQUIREMENTS (PQR) :
2.1(a) Bidder should have executed contracts of Design/Engineering, Supply,
Erection/Supervised erection, commissioning of Solar PV Power Plant(s) with
cumulative capacity of 10MWp or above as on the original scheduled date of tender
opening and out of which at least one Solar PV Power Plant shall be of minimum
5MWp capacity or above and should be in successful operation for at least one year
within the last 7 years as on the original scheduled date of tender opening.
AND
2.1(b) Bidder should have executed contracts of Design/Engineering, Supply,
Erection/Supervised erection, commissioning of Battery Energy storage system with
cumulative capacity of 1.0MWhr. or above as on the original scheduled date of tender
opening and out of which at least one Battery Energy Storage System shall be of
minimum 0.5MWhr. capacity or above and should be in successful operation for at
least one year within the last 7 years as on the original scheduled date of tender
opening.

2.2 Bidder who doesn’t fulfill the qualifying requirements stipulated in clause 2.1 (a) and
(b) above by himself can also participate provided the bidder collaborates with not more
than two firms and together they fully meet the qualifying requirements stipulated in
clause 2.1 (a) and (b) above and the Collaborator (s) should furnish along with the bid
valid collaboration agreement to execute this project and a back-up Bank Guarantee as
required in the relevant clauses.
OR
Bidder can also be a leader of a consortium consisting of not more than three firms,
such that together they meet the Qualifying Requirements stipulated in clause 2.1 (a)
7

Page 7 of 328
and (b) above and the members of the consortium should furnish back-up Bank
Guarantee as required in the relevant clauses. In case of bidding by a Consortium, the
consortium partners shall necessarily identify a leader of the Consortium who will
furnish the Consortium Agreement and the consortium partners shall execute a Joint
Deed of Undertaking in which the partners are jointly and severally liable to the Owner
for successful performance of the contract.
OR
Bidder can also be a Joint Venture Company, provided the qualifying requirement in
clause 2.1 (a) and (b) above is met by any one or more partners of the Joint Venture
(JV) Company. Each partner of the JV Company on the basis of whom the JV
Company gets qualified shall have minimum 26% equity in the JV Company and
should furnish back-up Bank Guarantee as required in the relevant clauses.
2.3 The Bidder or the Leader of the Consortium or the major partner of JV Company shall
have Positive Net Worth as per the latest audited financial statements.
2.4 Average Annual Turn Over of the Bidder, combined Average Annual Turn Over of the
Bidder and Collaborator(s), combined Average Annual Turn Over of the Consortium
partners and the combined Average Annual Turn Over of all the promoters of the Joint
Venture Company, as the case may be, shall not be less than Rs.48.648 Cr. in the
preceding three (3) consecutive financial years as on the original scheduled date of
tender opening.
3.0 Other Conditions:

3.1 The Bidder or the Bidder with Collaborator(s) or the Consortium or the Joint Venture
Company, as the case may be shall attach documentary evidence to prove that the
qualifying requirements mentioned in Clause 2.1 (a) and (b) above are met by him /
them, along with the bid in the form of end user certificate together with full contact
details for verification. The Bidder shall submit End User Certificate which is subject
to verification for qualification. The end user certificates showing the experiences of
their own installations or subsidiary or group companies or companies under the same
Management is also acceptable. A confirmation from the firm which is having the
experience in this regard is to be enclosed along with end user certificate.

In case the bidder furnishes the end user certificates of their subsidiary or group
companies or companies under the same Management, in addition to End User
Confirmation, NLC reserves the right to inspect such installations where such
certificates are obtained by the Bidder, only if the Bidder facilitates necessary

Page 8 of 328
inspection of such installation by the purchaser. However, cost pertaining to the
purchaser’s personnel for such inspection shall be borne by the purchaser.
3.2 In case of participation by the Bidder with Collaborator(s), the bidder shall furnish a
copy of valid Collaboration Agreement along with the bid, for the services offered
jointly and such agreement shall be valid till completion of all the contractual obligations
including O&M Contract. In case of participation by the Bidder as a Consortium, the
bidder shall furnish a copy of valid Consortium Agreement and Joint Deed of
Undertaking along with the bid, for the services offered jointly and such agreement shall
be valid till completion of all the contractual obligations including O&M Contract. In
case of participation by the Bidder as a Joint Venture Company, the bidder shall furnish a
copy of valid Joint Venture Agreement along with the bid, for the services offered jointly
and such agreement shall be valid till completion of all the contractual obligations
including O&M Contract. In all the above cases, the percentage value of the respective
portion of the work is to be indicated in the Techno commercial bid.
3.2(a) The successful bidder meeting the Qualifying Requirements, shall furnish a Contract
Performance Guarantee (CPG) in the form of an on-demand Bank Guarantee for the
faithful performance of the contract for a value of 10% of the total contract value
after the award of LOA.
3.2(b) If the successful bidder is meeting the Qualifying Requirements with
Collaborator(s), in addition to the CPG as mentioned in Cl. 3.2(a) above, each
Collaborator shall also furnish a back up Bank Guarantee for 5% of their respective
portion of the scope of work. In case the respective portion of the scope of work is
less than 1% of the total contract value, then back up Bank Guarantee for a minimum
of 0.05% of the total contract value shall be furnished.
3.2(c) If the successful bidder is the leader of a consortium, in addition to the CPG as
mentioned in Cl. 3.2(a) above, each of the consortium partners other than the leader
shall furnish a back up Bank Guarantee for 5% of their respective portion of the
scope of work. In case the respective portion of the scope of work is less than 1% of
the total contract value, then back up Bank Guarantee for a minimum of 0.05% of
the total contract value shall be furnished.
3.2(d) If the successful bidder is a JV Company meeting the Qualifying Requirement, in
addition to the CPG as mentioned in Cl. 4.5.3(a) above, each partner of the JV
Company on the basis of whom the JV company gets qualified shall also furnish a
back up Bank Guarantee for 5% of their respective portion of the scope of work. In
case the respective portion of the scope of work is less than 1% of the total contract
value, then back up Bank Guarantee for a minimum of 0.05% of the total contract
value shall be furnished.

Page 9 of 328
3.3 The bidder or the bidder with collaborator(s) or all individual firms in the
Consortium or all partners in the Joint Venture Company, as the case may be, shall
furnish their audited profit and loss accounts and balance sheets for the preceding
three (3) financial years from the original scheduled date of tender opening.
3.4 NLCIL reserves the right to ask the bidders to furnish the experience certificate
authenticated by the Indian Embassy in that country for installation outside India and
to furnish the experience certificate attested by a Notary Public for installation
within India.
3.5 NLCIL reserves the right to consider any foreign installations as experience, only if
the Bidder facilitates necessary inspection of such installation by NLCIL. However,
cost pertaining to the purchaser’s personnel for such inspection shall be borne by the
purchaser.
3.6 NLCIL reserves the right to inspect the plant(s) referred to by the bidders as well as
the original documents submitted in support of their claim to assess its veracity.
3.7 The bidder shall furnish major legal cases and their statutory liabilities if any.

4.0 OTHER REQUIREMENTS:


The Bidder shall take note of the following, but not limited to, as per Department of
Industrial Policy and Promotion (DIPP), Ministry of Commerce and Industry, Govt.
of India, Public Procurement (Preference to Make in India) Order 2017 dated
15.06.2017. The Bidder shall confirm compliance to the requirements indicated
below:
4.1 DEFINITIONS:
i. ‘Local content’ means the amount of value added in India which shall, be the total
value of the item procured (excluding net domestic indirect taxes) minus the value
of imported content in the item (including all customs duties) as a proportion of the
total value, in percent.
ii. ‘Local supplier’ means a supplier or service provider whose product or service
offered for procurement meets the minimum local content as prescribed.

iii. ‘L1’means the lowest tender or lowest bid or the lowest quotation received in a
tender, bidding process or other procurement solicitation as adjudged in the
evaluation process as per the tender.

iv. ‘Margin of purchase preference’ means the maximum extent to which the price
quoted by a local supplier may be above the L1 for the purpose of purchase
preference.
Minimum local content: The minimum local content shall be 50%.
Margin of Purchase Preference: The margin of purchase preference shall
be 20%.

10

Page 10 of 328
4.2 Verification of local content:

i. The local supplier at the time of tender, bidding or solicitation shall be required to
provide self-certification that the item offered meets the minimum local content and
shall give details of the location(s) at which the local value addition is made.

ii. The local supplier shall be required to provide a certificate from the statutory auditor or
cost auditor of the company (in the case of companies) or from a practicing cost
accountant or practicing chartered accountant (in respect of suppliers other than
companies) giving the percentage of local content.

iii. False declarations will be in breach of the Code of Integrity under Rule 175(1)(i)(h) of
the General Financial Rules-2017, Ministry of Finance, Govt. Of India for which a
bidder or its successors can be debarred for up to two years as per Rule 151 (iii) of the
General Financial Rules-2017, Ministry of Finance, Govt. Of India along with such
other actions as may be permissible under law.

iv. A supplier who has been debarred by any procuring entity for violation of this Order
shall not be eligible for preference under this Order for procurement by any other
procuring entity for the duration of the debarment. The debarment for such other
procuring entities shall take effect prospectively from the date on which it comes to the
notice of other procurement entities”.

5.0 SCOPE OF WORK

The scope of work for installation of 2 x 10 MW (AC) Grid interactive Solar PV Power
Project integrated with 8 MWhr. Battery Energy Storage System at Attam Pahad and at
Dolly Gunj, Port Blair, South Andaman with associated 33 KV Switchyard and grid
interconnection at the take off points of Electricity Department of Andaman & Nicobar
Administration including Design, Engineering, Manufacture, Inspection at supplier’s
works, supply, insurance, transport, storage, erection, testing, commissioning.

The scope of work also includes Operation and Maintenance of the entire system for
ten years after one year warranty period.

(Detailed scope of work is available in the Vol. II, Technical Specification.).

5.1 The detailed scope of work is given in Vol.II, Technical Specification.

11

Page 11 of 328
6.0 TIME SCHEDULE:

The scope of work, covered under this tender shall be performed as per the time
schedule given below, reckoning from the date of Letter of Award.

Details From the date of


Letter of Award
The scope of work for installation of 2 x 10 MW
(AC) Grid interactive Solar PV Power Project 18 months
integrated with 8 MWhr. Battery Energy Storage
System at Attam Pahad and at Dolly Gunj, Port Blair,
South Andaman with associated 33 KV Switchyard
and grid interconnection at the take off points of
Electricity Department of Andaman & Nicobar
Administration including Design, Engineering,
Manufacture, Inspection at supplier’s works, supply,
insurance, transport, storage, erection, testing,
commissioning.

7.0 All other terms and conditions along with technical details regarding qualifying
requirements, time schedule, bid guarantee, validity of bids and instruction to bidders,
etc., are contained in the Tender Documents.
8.0 Bids submitted by Tele-fax or E-Mail and the off line bids received shall be rejected.

9.0 NLCIL reserves the right to reject any tender or all tenders received at its discretion
without assigning any reason whatsoever.
10.0 Collaborator / Consortium Partner/JV Partner/ of a Bidder for this tender cannot be a
Bidder for this Tender.
11.0 The Micro and small scale Units registered under single point registration scheme of the
NSIC/covered under MSMED Act,2006/MSME are permitted to participate without
Tender fee, provided that the request for the same is received in time with a copy of
valid certificate of registration and the product range mentioned in the certificate is the
same or similar to our requirements. Copies of necessary certificates duly attested by
any Notary public (or) Gazetted Officers (or) practicing Chartered Accountant with
seal and date shall only be accepted. They are also are exempted from furnishing Bid
Guarantee, provided that such Micro and Small Scale Units are registered under single
point registration scheme of NSIC/covered under MSMED Act, 2006/MSME and the
same is valid on the scheduled date of tender opening and the product range mentioned
in the certificate is the same or similar to our requirements.

CHIEF GENERAL MANAGER / CONTRACTS

12

Page 12 of 328
SECTION - B

QUALIFYING REQUIREMENTS

13

Page 13 of 328
SECTION - B
QUALIFYING REQUIREMENTS:

1.0 Qualifying Requirements

1.1(a) Bidder should have executed contracts of Design/Engineering, Supply,


Erection/Supervised erection, commissioning of Solar PV Power Plant(s) with
cumulative capacity of 10 MWp or above as on the original scheduled date of tender
opening and out of which at least one Solar PV Power Plant shall be of minimum 5
MWp capacity or above and should be in successful operation for at least one year
within the last 7 years as on the original scheduled date of tender opening.
AND
1.1(b) Bidder should have executed contracts of Design/Engineering, Supply,
Erection/Supervised erection, commissioning of Battery Energy storage system with
cumulative capacity of 1.0 MWhr. or above as on the original scheduled date of tender
opening and out of which at least one Battery Energy Storage System shall be of
minimum 0.5 MWhr. capacity or above and should be in successful operation for at
least one year within the last 7 years as on the original scheduled date of tender
opening.

1.2(a) Bidder who doesn’t fulfill the qualifying requirements stipulated in clause 1.1 (a) and
(b) above by himself can also participate provided the bidder collaborates with not
more than two firms and together they fully meet the qualifying requirements stipulated
in clause 1.1 (a) and (b) above and the Collaborator (s) should furnish along with the
bid valid collaboration agreement to execute this project and a back-up Bank Guarantee
as required in the relevant clauses.
OR
Bidder can also be a leader of a consortium consisting of not more than three firms,
such that together they meet the Qualifying Requirements stipulated in clause 1.1 (a)
and (b) above and the members of the consortium should furnish back-up Bank
Guarantee as required in the relevant clauses. In case of bidding by a Consortium, the
consortium partners shall necessarily identify a leader of the Consortium who will
furnish the Consortium Agreement and the consortium partners shall execute a Joint
Deed of Undertaking in which the partners are jointly and severally liable to the Owner
for successful performance of the contract.
OR
Bidder can also be a Joint Venture Company, provided the qualifying requirement in
clause 1.1 (a) and (b) above is met by any one or more partners of the Joint Venture
(JV) Company. Each partner of the JV Company on the basis of whom the JV
Company gets qualified shall have minimum 26% equity in the JV Company and
should furnish back-up Bank Guarantee as required in the relevant clauses.

1.3 The Bidder or the Leader of the Consortium or the major partner of JV Company shall
have Positive Net Worth as per the latest audited financial statements.

1.4 Average Annual Turn Over of the Bidder, combined Average Annual Turn Over of the
Bidder and Collaborator(s), combined Average Annual Turn Over of the Consortium
partners and the combined Average Annual Turn Over of all the promoters of the Joint
Venture Company, as the case may be, shall not be less than Rs.48.648 Cr. in the
preceding three (3) consecutive financial years as on the original scheduled date of
tender opening.

14

Page 14 of 328
1.5 OTHER CONDITIONS:

1.5.1 The Bidder or the Bidder with Collaborator(s) or the Consortium or the Joint Venture
Company, as the case may be shall attach documentary evidence to prove that the
qualifying requirements mentioned in Clause 1.1 (a) and (b) above are met by him /
them, along with the bid in the form of end user certificate together with full contact
details for verification. The Bidder shall submit End User Certificate which is subject
to verification for qualification. The end user certificates showing the experiences of
their own installations or subsidiary or group companies or companies under the same
Management is also acceptable. A confirmation from the firm which is having the
experience in this regard is to be enclosed along with end user certificate.

In case the bidder furnishes the end user certificates of their subsidiary or group
companies or companies under the same Management, in addition to End User
Confirmation, NLC reserves the right to inspect such installations where such
certificates are obtained by the Bidder, only if the Bidder facilitates necessary
inspection of such installation by the purchaser. However, cost pertaining to the
purchaser’s personnel for such inspection shall be borne by the purchaser.

1.5.2 In case of participation by the Bidder with Collaborator(s), the bidder shall furnish a
copy of valid Collaboration Agreement along with the bid, for the services offered
jointly and such agreement shall be valid till completion of all the contractual
obligations including O&M Contract. In case of participation by the Bidder as a
Consortium, the bidder shall furnish a copy of valid Consortium Agreement and Joint
Deed of Undertaking along with the bid, for the services offered jointly and such
agreement shall be valid till completion of all the contractual obligations including
O&M Contract. In case of participation by the Bidder as a Joint Venture Company, the
bidder shall furnish a copy of valid Joint Venture Agreement along with the bid, for the
services offered jointly and such agreement shall be valid till completion of all the
contractual obligations including O&M Contract. In all the above cases, the percentage
value of the respective portion of the work is to be indicated in the Techno commercial
bid.

1.5.3(a)The successful bidder meeting the Qualifying Requirements, shall furnish a Contract
Performance Guarantee (CPG) in the form of an on-demand Bank Guarantee for the
faithful performance of the contract for a value of 10% of the total contract value after
the award of LOA.

1.5.3(b)If the successful bidder is meeting the Qualifying Requirements with Collaborator(s),
in addition to the CPG as mentioned in Cl. 1.5.3(a) above, each Collaborator shall also
furnish a back up Bank Guarantee for 5% of their respective portion of the scope of
work. In case the respective portion of the scope of work is less than 1% of the total
contract value, then back up Bank Guarantee for a minimum of 0.05% of the total
contract value shall be furnished.

1.5.3(c)If the successful bidder is the leader of a consortium, in addition to the CPG as
mentioned in Cl. 1.5.3(a) above, each of the consortium partners other than the leader
shall furnish a back up Bank Guarantee for 5% of their respective portion of the scope
of work. In case the respective portion of the scope of work is less than 1% of the total
contract value, then back up Bank Guarantee for a minimum of 0.05% of the total
contract value shall be furnished.

15

Page 15 of 328
1.5.3(d) If the successful bidder is a JV Company meeting the Qualifying Requirement, in
addition to the CPG as mentioned in Cl. 1.5.3(a) above, each partner of the JV
Company on the basis of whom the JV company gets qualified shall also furnish a back
up Bank Guarantee for 5% of their respective portion of the scope of work. In case the
respective portion of the scope of work is less than 1% of the total contract value, then
back up Bank Guarantee for a minimum of 0.05% of the total contract value shall be
furnished.

1.5.4 The bidder or the bidder with collaborator(s) or all individual firms in the Consortium
or all partners in the Joint Venture Company, as the case may be, shall furnish their
audited profit and loss accounts and balance sheets for the preceding three (3) financial
years from the original scheduled date of tender opening.

1.5.5 NLCIL reserves the right to ask the bidders to furnish the experience certificate
authenticated by the Indian Embassy in that country for installation outside India and to
furnish the experience certificate attested by a Notary Public for installation within
India.

1.5.6 NLCIL reserves the right to consider any foreign installations as experience, only if the
Bidder facilitates necessary inspection of such installation by NLCIL. However, cost
pertaining to the purchaser’s personnel for such inspection shall be borne by the
purchaser.

1.5.7 NLCIL reserves the right to inspect the plant(s) referred to by the bidders as well as the
original documents submitted in support of their claim to assess its veracity.

1.5.8 The bidder shall furnish major legal cases and their statutory liabilities if any.

16

Page 16 of 328
SECTION – C

INSTRUCTIONS TO BIDDERSFOR SUBMISSION OF ONLINE


BIDS THROUGH e-TENDER and e-REVERSE AUCTION

17

Page 17 of 328
SECTION – C

INSTRUCTION TO BIDDERS FOR SUBMISSION OF ONLINE BIDS


THROUGH e-TENDER and e-REVERSE AUCTION
Bidders are requested to read the terms & conditions of this tender before submitting their
online bids.

1.0 Pre requisites for accessing NLCIL Website

A.Software Requirements
Refer to NLCIL’s portal (econts.nlcindia.com) for System Requirements

 Operating system: Windows XP-- SP3 & above.


 Web browser: Internet Explorer 9/10/11
 Java: JRE6/JRE 1.7.45 or above.
 PDF reader: Adobe Acrobat Reader 8 or above.

B. Digital Certificate
 Bidder should have a legally valid CLASS III Digital Certificates (i) Digital
Signature, non-repudiation certificate (used for Signing) and (ii) Key
Encipherment Certificate (used for encrypting Bid Document) with
Organisation name from any of the licensed Certifying Authorities (CA)
operating under the Root Certifying Authority of India (RCAI), Controller of
Certifying Authorities (CCA) of India.

Ensure that all necessary trust certificates and drivers are installed as per CA’s
instruction and working properly.For detailed guidance about browser and Java
configuration the bidders are advised to go through the guide available in the
portal.

2.0 Registration:
The process involves Bidder registration with NLCIL website under e-contracts portal.
Only after successful registration, the Bidder(s) can submit his/their bids electronically.
Bidders are required to make their own arrangement for bidding from a computer
connected with Internet. NLCIL shall not be responsible for making such
arrangements.
Interested bidders are required to pay the Tender fee and register in the URL and click
on “New Bidder” and fill up the registration form with their details like Bidders
address, user ID and Password, Tender fee details etc., and attach a scanned copy of
Tender fee details with UTR No., Remitted Bank, Amount, Date etc., and submit.
Kindly note that Bidder name will be captured from Digital Signature Certificate
(DSC). Bidders are advised to keep note of the same. It may be noted that no separate
user id and password will be provided by NLCIL. However, the bidders who have
already participated in this portal can directly login with their valid user id and
password and fill up the registration form with details of Tender fee etc.Acceptance or
Rejection of Registration request for the Tender will be intimated by a separate e-mail
message.
After the Tender fee payment and successful registration, the bidder can login with
their user ID, password & DSC and participate in the e-Tender. Tender fee is non-
refundable.
18

Page 18 of 328
3.0 Payment of Tender Fee
The payment towards Tender fee is to be remitted in favour of NLC India Limited by
NEFT/RTGS or e-payment to NLCIL’s bank account as per following detail.
Bank Details : State Bank of India, Branch: Neyveli Main
Account Details :NLCIL Account No.10895129204,
Beneficiary Name : NLC India Limited. Estt.A/c in State Bank of India,
Branch: Neyveli Main
IFSC Code No. : SBIN0000958
Tender fee will be deemed to have been submitted by the bidder if and only if the same
is received (credited) in the above bank account within the stipulated time. Cash
payments will not be accepted.
4.0 Bidding Process:
The entire bidding process is divided into Two Stages i.e. Stage-I and Stage-II.
Stage-I bidding will be through e-Tender, in addition to submission of Physical forms
in sealed cover as brought out in clause 6.1.1 of Invitation to Bid and Stage-II bidding
will be through e-reverse auction.
Stage-I, e-Tender
 Preparation of Bid
The Bidder will be able to prepare his Pre Qualifications Bid, TECHNICAL BID,
COMMERCIAL BID and Initial PRICE BID online using the respective forms. For
Guidelines please refer to the help in the Portal.
Bidder can edit and save his offer any number of times till closing time of the bid.
However, once he submits his bid he will not be able to edit it.
If bidder wants to edit his submitted bid then he has to first delete his submitted offer
and then edit his offer and resubmit. Only submitted bids will be considered for
evaluation. Any saved bids that are not submitted will be deleted by the system after the
due date of opening.
Bidder can attach files containing company profile details, scanned copies of dealership
certificate, scanned copies of technical drawings, etc., which are required for the
enquiry. The documents attached should be in PDF format.
File Size: 5MB is the maximum size of a single file that can be attached.
e-bid Submission and Signing
Submission of e-bids onlineis a two-step process. In the first step, the Techno
Commercial bid and Initial Price Bid have to filled and submitted. In the second step,
these bids have to be digitally signed using Bidder’s Digital Signature Certificate.
 Bidder cannot submit any offer after the due date and time stipulated in the e-Tender.
All bids submitted by Bidder can be viewed by clicking on the link Submitted bids
provided in the left menu of the corresponding Bidder's home page.
All notices and correspondence to the bidder(s) shall be sent by email message during
the process till finalization of tender. Hence the bidders are required to ensure that their
email address provided at the time of registration is valid and updated. Non receipt of
email will not entitle any bidder to lodge any claim and no complaint in this regard
shall be entertained. Bidders are also requested to ensure validity of their DSC (Digital
Signature Certificate).

19

Page 19 of 328
Bidders are advised to see the web site regularly to remain updated with latest
information to ensure that they do not miss out any corrigendum / addendum uploaded
against the said e-tender after downloading the e-tender document. The responsibility
of downloading the related corrigendum, if any, will be that of the bidders.
5.0 Process of e-Tender:

5.1 On the scheduled date and time of tender opening, Tender Opening Committee will
open the Physical forms in sealed coverfirst and shall confirm details of payment
towards cost of Tender document (Tender fee), Bid Guarantee as in NIB, compliance of
Letter of Undertaking. The bids confirming to all the above is treated as Responsive
bids and Cover -II of the responsive bidders only will be opened.

5.2 Cover-II will be opened on the same day. For evaluation purpose, prices quoted in
Schedule of Prices alone shall be taken into consideration. Price Bids will be checked
by NLCIL for arithmetical accuracy. Errors, if any, will be resolved in the following
manner, and it shall not be necessary to make a reference to the concerned Bidder(s) for
such purpose:

(i) where there is a discrepancy between the unit rate and the line item total
resulting from multiplying the unit rate by the quantity, the unit rate as quoted
will govern.

(ii) where there is a discrepancy between figures and in words of an unit rate, the
unit rate as quoted in words will govern.

(iii) If there is any discrepancy between the amount quoted in words and figures, the
amount quoted in words will be considered.
5.3 If a bidder desires to be present at the time of Tender Opening, he shall depute his
representative(s) (not more than two persons) in time with due authorization for
participating in the Tender Opening

5.4 Stage-II : E-Reverse Auction :The Reverse Auction, if required, will be conducted
among the shortlisted bidders with a start price and decremented value. The Reverse
auction procedure is detailed under the heading “Reverse auction” (Annexure - B).
6.0 Bidding in e-Tender & Reverse auction:
a. In all cases, bidder should use their own ID and Password along with Digital
Signature at the time of submission of their bid.
b. The e-tender floor shall remain open from the pre-announced date & time and for as
much duration as mentioned above.
c. All electronic bids submitted during the e-tender and e-reverse auction process shall
be legally binding on the bidder. Any bid will be considered as the valid bid offered
by that bidder and acceptance of the same by the Purchaser will form a binding
contract between Purchaser and the Bidder for execution of work.
d. It is mandatory that all the bids are submitted with digital signature certificate
otherwise the same will not be accepted by the system.
e. NLCIL reserves the right to cancel or reject or accept or withdraw or extend this
bidding process (e-tender and e-reverse auction) in full or part as the case may be
without assigning any reason thereof.
20

Page 20 of 328
f. The server time shall be treated as final and binding. Bids recorded in the server
before the bid closing time will only be treated as valid bid. Bidders are, therefore,
advised to submit their bids well before the closing time of e-tender / e-reverse
auction. If any bid reaches the server after the bid closing time as per server time,
the same will not be recorded and no complaint in this regard shall be entertained.
g. Bidders are advised to exercise caution in quoting their bids in e-tender and
e-reverse auction to avoid any mistake. Bids once submitted can’t be recalled.
h. Any order resulting from this bidding process shall be governed by the terms and
conditions mentioned in the NIB.

21

Page 21 of 328
SECTION –D

INVITATION TO BID

22

Page 22 of 328
SECTION –D

INVITATION TO BID

1.0 INVITATION:
NLC India Limited, Neyveli a Navratna Government of India Enterprise registered
under Indian Companies Act 1956 hereinafter referred to as “PURCHASER” invites
Sealed bids in English (one original and six identical copies) for installation of 2 x 10
MW (AC) Grid interactive Solar PV Power Project integrated with 8 MWhr. Battery
Energy Storage System at Attam Pahad and at Dolly Gunj, Port Blair, South Andaman
with associated 33 KV Switchyard and grid interconnection at the take off points of
Electricity Department of Andaman & Nicobar Administration including Design,
Engineering, Manufacture, Inspection at supplier’s works, supply, insurance, transport,
storage, erection, testing, commissioning.
The scope of work also includes Operation and Maintenance of the entire system for
ten years after one year warranty period.

2.0 ABOUT NLCIL:


2.1 NLC India Limited (NLCIL), a Navratna Government of India Enterprise, functioning
under the administrative control of Ministry of Coal is an integrated complex involving
in Lignite Mining and Thermal Power Generation. NLCIL operates four lignite mines
of total capacity 30.6 Million Tonnes per annum (MTPA) and four Thermal Power
Stations of total capacity of 2740 MW including Barsingsar (Rajasthan) Mine Project
of capacity 2.1 MTPA linked with Thermal Power Station of capacity 2 X 125 MW
and a coal based Thermal Power Project of capacity ( 2 x 500 MW) called NLC Tamil
Nadu Power Limited (NTPL) at Tuticorin, Tamil Nadu, as a joint venture between
NLC India Limited (NLCIL) and Tamil Nadu Generation and Distribution Company
(TANGEDCO). Further NLCIL has also commissioned 51 MW Wind Power Project at
Kazhuneerkulam, Tirunelveli District, Tamil Naduand 10 MW Solar Power Project and
130MW Solar Power Project at Neyveli.
2.2 The Lignite based power project under execution at Neyveli is “New Neyveli Thermal
Power Station 2x 500 MW”. NLCIL with its excellent performance, figures among the
top profit making Public Sector Undertaking. For more details, Kindly visit NLCIL’s
Web site: www.nlcindia.com

3.0 SCOPE OF WORK:

3.1 The scope of work for for installation of 2 x 10 MW (AC) Grid interactive Solar PV
Power Project integrated with 8 MWhr. Battery Energy Storage System at Attam Pahad
and at Dolly Gunj, Port Blair, South Andaman with associated 33 KV Switchyard and
grid interconnection at the take off points of Electricity Department of Andaman &
Nicobar Administration including Design, Engineering, Manufacture, Inspection at
supplier’s works, supply, insurance, transport, storage, erection, testing,
commissioning.

The scope of work also includes Operation and Maintenance of the entire system for
ten years after one year warranty period as detailed under Technical Specification (Vol.
II).

23

Page 23 of 328
4.0 BID GUARANTEE:
4.1 The amount shall be as specified in the Notice Inviting Bid and in the form of Demand
Draft or Banker’s cheque drawn in favour of NLC India Ltd., on any Bank in Neyveli or
payable at par by a Bank in Neyveli or NEFT/RTGS mode to NLCIL’s Account No.
10895129204, Beneficiary Name: NLC India Limited, Estt.A/c in State Bank of India,
Branch: Neyveli Main (IFS Code No. SBIN0000958) and the remittance details with
UTR No./DD/ Banker’s cheque shall be enclosed with the bid in Part I failing which the
offer is liable for rejection. The Bidder is to note that the Bank Commission charges
will be to the account of the bidder and the net amount transferred to NLCIL’s account
shall be equal to the amount specified in the Notice Inviting Bid.

4.2 The Bid Guarantee can also be in the form of an Irrevocable Bank Guarantee from any
Nationalised Bank / Scheduled Bank in India except Bank of China.
4.3 The Bid Guarantee shall be valid for 10 (ten) months from the date of tender opening
Part -I.
4.4 The Bid Guarantee deposited in any manner shall not bear any interest.

4.5 The Bid Guarantee furnished in the form of Demand draft / Banker’s Cheque / Bank
Guarantee, the scanned copy shall be uploaded and the original copy of the same shall
be furnished as brought out in the Clause 6.1.1.
4.6 The firms registered with NSIC/covered under MSMED Act,2006/MSME are
exempted from furnishing Bid Guarantee, provided that such Micro and Small Scale
Units are registered under single point registration scheme of NSIC/covered under
MSMED Act, 2006/MSME and the same is valid on the scheduled date of tender
opening and the product range mentioned in the certificate is the same or similar to our
requirements. Copies of necessary certificates duly attested by any Notary public (or)
Gazetted Officers (or) practicing Chartered Accountant with seal and date shall only be
accepted.

5.0 TENDER DOCUMENTS:

5.1 Tender document Volume-I Consists of


i SECTION – A : Notice Inviting Bids (NIB)
ii SECTION - B : Qualifying Requirements
iii SECTION - C : Instructions to Bidders for submission of online Bids
in e-tender & e-Reverse Auction.
iv SECTION - D : Invitation to Bid
v SECTION - E : Specimen Formats
vi SECTION - F : Draft Contract Agreement and Commercial
Conditions of Contract
vii Volume-II : Technical Specification

24

Page 24 of 328
6.0 BID SUBMISSION AND OPENING:

6.1.1 All bids, including all attachments / enclosures shall be prepared in English language
only and submit online in the NLCIL web site.

Bidders are requested to furnish the following documents in Original in a sealed cover
(Physical Forms) within the last date of receipt of Bids.
(i) Details of payment towards Tender fee
(ii) Bid Guarantee
(iii) Letter of undertaking
(iv) Check list for compliance of important Tender Conditions.

6.1.2 The above sealed cover shall be superscribed as under:


Name of the Bidder:
Tender No.
Opening Date ………..Time………..
Proposal for---------------------------- and submitted
To
The Chief General Manager / Contracts,
Corporate Office,
NLC India Limited,
Neyveli - 607 801, Cuddalore District,
Tamil Nadu, INDIA.
6.1.3 Submission of a valid bid guarantee or DD for the stipulated sum in full along with the
bid and acceptance of the bid guarantee/DD or NEFT/RTGS by NLC India Limited is a
condition-precedent for such Bid to be eligible for consideration by NLC India Limited.
6.1.4 An offer without Bid Guarantee, or with bid guarantee for a lesser amount, or bid
guarantee in a form other than specified herein above, shall be liable to be rejected
without further reference to the Bidder(s) or to the concerned Bank. No interest shall be
payable on the Bid Guarantee amount.
6.1.5 The bid guarantee shall
a. be executed only on behalf of the bidder on whose name the tender documents has
been hdownloaded from the website.
b. be submitted only by the bidder on whose name the tender documents have been
downloaded from the website.
c. be executed only as per the format prescribed by NLCIL.

6.1.6 The bid guarantee shall also have provision for extension by the banker upon request by
the bidder. The bidder shall arrange for extension of validity upon request from NLC
India Ltd., Neyveli.

25

Page 25 of 328
Confirmation of BG under the through “Structured Financial Messaging System (SFMS)”
“The Bank Guarantee issued by the issuing Bank of Behalf of Bidder/ Contractor / Supplier in
favour of “Name of Company” shall be in paper form as well as issued under the “Structured
Financial Massaging System”. The details of beneficiary for issue of BG under SFMS
platform is furnished below:-

Name of Beneficiary & its Name NLCIL


details
Unit/ Contracts
Area/ Division branch
/Corporate
Office
Beneficiary Bank, Branch & State Bank of
Address India
Block-2,
Neyveli – 607801
IFSC Code SBIN0000958

The above particulars are to be incorporated by the issuing bank properly while issuing
BG under SFMS mode to avoid any problem in future.
6.1.7 The Bid Guarantee shall be forfeited if:
a. the bid is unilaterally revoked /revised / modified / withdrawn before expiry of
bid validity period ,by the bidder(s); or
b. the price(s) have been unilaterally increased or altered after the bid opening and
during validity of offer, by the bidder; or
c. In case, any certificate submitted by the Bidder(s) is found to be not genuine, or
forged / bogus; or
d. on issue of LOA by NLCIL to the bidder, the bidder omits or refuses to accept
the said LOA within the stated period and /or execute the Contract agreement;
or
e. the successful bidder, after issue of LOA, omits or fails to submit Contract
Performance Guarantee within the specified period.
6.1.8 Without prejudice to any other remedies available at law,
i. in the event of any of the contingencies mentioned in Clause 6.1.7(a) to (c),
NLCIL shall have the right, at their discretion, to reject the bid without notice to
the Bidder(s);
ii. in the event of the contingency mentioned in Clause 6.1.7 (d) & (e),NLCIL shall
have the right to cancel the LOA/Contract, without notice to the Bidder
iii. in addition on (i) and (ii) above, NLCIL shall also have the right to de-bar the
defaulting Bidder(s) for a period to be specified, from participating in any of
NLCIL tenders and NLCIL reserves the right to inform the matter to other
PSUs/statutory Bodies and the decision of NLCIL in this regard shall be final
and binding on the Bidder(s).

26

Page 26 of 328
6.1.9 Return of Bid Guarantee
(i) For unsuccessful Bidders:
For unsuccessful bidders, bid guarantee /EMD shall be returned to such Bidders
within 15 days from the date of approval for placement of order on the
successful Bidder. If any bidder who does not agree to extend the validity of
the bid, bid guarantee shall be returned on request.

(ii) For successful Bidder:

For successful bidder whose bid has been accepted and LOA is issued, the bid
guarantee / EMD shall be returned within fifteen days from the date of
acceptance of Bank Guarantee for Contract Performance.

(iii) In all the above transactions, the documents shall be sent by Registered post
/Speed Post.

6.1.10 All Bank Guarantees except Bid Guarantee are to be furnished directly by the Banker
to NLCIL either by Reg. Post/Speed Post/Courier.
6.1.11 The Online bid with regard to Technical and Commercial aspects shall contain the full
details of the profile of the bidder(s) in addition to the following:
(i) Duly filled in online forms.

(ii) Audited Annual reports for the last 3 years comprising of Audited Balance
Sheets and Profit and Loss Accounts, duly certified by the statutory auditors and
the documentary evidence with respect to Annual turnover.

(iii) Any amendment / corrigendum / errata for the Tender Document shall also be
signed by the Bidder as a token of acceptance of the same and enclosed in
Cover-II of the Bid.

(v) Bidders who offer for complete equipment in collaboration/Joint


Venture/consortium shall furnish the details of the collaboration agreement, JV
agreement, consortium agreement etc.
.
(vi) Integrity Pact duly signed.

6.1.12 If the Audited Annual Reports are not in English language, certified English translated
copies be attached duly signed by the Company Auditor.

6.1.13 To assist in the scrutiny, evaluation and comparison of bids, the Purchaser may, at its
discretion, seek from any or all bidders, clarification(s) of his / their Bids, including
break-downs of unit rates, technical information, documents and materials after the
Tender Opening. No change in the final price or substance of the Bid shall be
permissible.

6.2. PRICE

6.2.1 The ‘Schedule of Prices’ duly and correctly filled in by the bidder shall be submitted
online in the Specified Form.

27

Page 27 of 328
6.2.2 Price given should cover the entire scope of work and should be as per price format.
The bidder shall quote his price for entire scope of work on firm price basis only. The
bidder quoting a system of prices other than that specified, run the risk of summary
rejection of the bid.
6.2.3 The Bidder shall quote his price against each item of the schedule as indicated in the
price format. The bidder shall quote the prices only once after considering all the pros
and cons.
6.2.4 All entries shall be in English language only.

6.2.5 The price shall be quoted in Indian Rupees/ USD / Euro and shall remain valid till the
completion of entire work.
6.2.6 Price Bids will be checked by Purchaser for arithmetical accuracy. Errors, if any, will
be resolved in the following manner, and it shall not be necessary to make a reference
to the concerned Bidder(s) for such purpose:

i) where there is a discrepancy between the amounts in figures and in words, the
amount in words will govern; and
ii) where there is a discrepancy between the unit rate and the line item total resulting
from multiplying the unit rate by the quantity, the unit rate as quoted will govern.
iii) where there is a discrepancy between figures and in words of an unit rate, the unit
rate as quoted in words will govern.

7.0 GENERAL

7.1 In general, no request for postponement or extension of time shall be permitted for the
last date for remitting Tender fee, date of closing of online e-tender, Date of submission
of physical forms (Cover-I), Date of opening of physical forms (cover – I), Date of
opening of e-bids (Cover- II), etc. However, the Purchaser has the right to decide.
7.2 Bids received in incomplete shape shall be liable for rejection.
7.3. NLC India Limited takes no responsibility for transmission delays, loss or non-receipt
of bid documents or any letters sent by post / courier, either way, and also reserve the
right to reject any bid in part or full without assigning any reasons therefore.

7.4. Notwithstanding any information and data, which may be contained in these tender
documents, the bidder has to make independent inquiries and generally obtain his own
information on all matters that may in any way affect prices, risks and obligations of the
Contractor under the Contract.

7.5. The submission of any bid connected with these documents and specifications shall
constitute an agreement that the Bidder shall have no cause of action or claim against the
Purchaser for rejection of his Bid. The Purchaser shall always be at liberty to reject or
accept any bid or bids or part thereof at his sole discretion and any such action will not
be called into question and the bidder shall have no claim in that regard against the
Purchaser.

7.6. Bids once submitted shall not be returned and shall remain property of the Purchaser.

7.7 Unilateral revision or withdrawal of offer by the bidder within the subsistence of the
validity period of offer shall not be permitted. Violation of this condition shall result in
rejection of the bid without notice, besides forfeiture of EMD/ Bid Guarantee as the
case may be. In addition to the above, such bidder shall also be debarred either
28

Page 28 of 328
permanently or for a fixed period, at the discretion of NLCIL from participating in any
of the NLCIL’s future tenders.

8.0 Effect and Validity of Bid


The bid shall be kept valid for acceptance for 08 (Eight) months from the date of
opening of the bid and has to be extended from time to time if situation warrants due to
administrative procedures in vogue.
9.0 Clarifications
A bidder, who has been issued the tender document may seek clarifications, if found
necessary, in respects of any printed portion of the tender documents. But such request
in writing should reach the General Manager/ Contracts within two weeks of the date
of issuance of the tender document by the Purchaser. In response to such a request or
even otherwise, Purchaser shall have the right to provide clarifications as may be
considered necessary to all those who have been issued the tender documents. In any
case, Purchaser shall not be liable to entertain any request for clarifications received not
less than seven days prior to the scheduled tender opening date.

9.1 Requests for clarifications received after the stipulated time as indicated in 10.2 shall
not be considered. The NLCIL shall endeavor to render / communicate their
clarifications in writing to the bidder without delay. After receipt of such clarifications,
the bidder may submit his bid but within the time and date as indicated in the tender.
All such clarifications and the relevant exchange of correspondence between the parties
in this regard shall form part of the tender specifications and contract documents.

9.2 Address of the Technical department is given below:

The General Manager/PBD Telephone No.04142-252496


NLC India Limited,
Corporate Office, Block -1,
NEYVELI – 607 801.

10.0 Latest Hour For Receipt of Bids


10.1 Online / Electronic Bid shall be submitted through NLCIL web site under e-Contracts
Portal i.e. econts.nlcindia.com

10.2 Physical sealed cover as brought out in Para6.1.1must be received / deposited /


delivered to any one of the officer at the office mentioned below, not later than 14.30
Hrs. IST on the date fixed for tender opening. The sealed cover deposited / delivered
after the time & date fixed for the receipt of the bids shall be rejected.
a) Shri P. Seshadri, Addl. Chief Manager / Contracts,
b) Shri S.Gothandaraman, Addl. Chief Manager / Contracts,
c) Shri C. Venkatraman, Manager / Contracts,

O/o The Chief General Manager / Contracts


Corporate Office, Block-1,
NLC India Limited
Neyveli – 607 801,Cuddalore District.
Tamil Nadu, India.

29

Page 29 of 328
11.0 Single Bidder Responsibility
The bidder shall specifically indicate in his bid that he assumes full responsibility for
the scope of work in accordance with specifications, quality and time schedule of the
complete tender and guarantee the satisfactory performance as a whole.
12.0 No Claim for Compensation for Submission of Bid
12.1 The submission of any bid connected with these documents and specifications shall
constitute an agreement that the Bidder shall have no cause of action or claim against
the NLCIL for rejection or non-acceptance of his Bid. The Purchaser shall always be at
liberty to reject or accept any bid or bids or part thereof at his sole discretion and any
such action will not be called into question and the bidder shall have no claim in that
regard against the Purchaser.
12.2 The Bidder whose bid is not accepted shall not be entitled to make any claim on
account of costs, charges and expenses incidental to or incurred by such Bidder, as a
result of or in connection with his submission of bid or the consideration of the bid by
NLCIL, even if NLCIL elects to modify/withdraw/abandon the Invitation to Bid.
13.0 Policy of bids under consideration
Bids shall be deemed to be under consideration immediately after they are opened and
until such time the NLCIL makes official intimation of award/rejection to the Bidder.
While the Bids are under consideration, Bidders and/or their representatives or other
interested parties are advised to refrain from contacting, by any means, the NLCIL
and/or his employees/representatives on matters related to the Bid under consideration.
The NLCIL if necessary will obtain clarifications on the Bids, by requesting for such
information from any or all the Bidders either in writing or through official discussions.
The Bidder(s) will not be permitted to change the final price or substance of the Bid
after the same has been opened. Unilateral revision or withdrawal of bids by the bidder
within the subsistence of the validity period of offer shall not be permitted.

14.0 NLCIL ’s Right to Accept Bid

14.1 PURCHASER shall always be at liberty to reject or accept any bid or bids or part
thereof at his sole discretion and any such action will not be called into question and
the bidder shall have no claim in that regard against the PURCHASER.

14.2 The Purchaser does not pledge itself to accept the lowest bid, and reserves the right to
reject such bids for reasons to be recorded in writing. The other bids will be retained as
given. The decision of NLCIL in this regard shall be final and binding on the bidders
and the bidders shall not be entitled to any notice in this regard or to any compensation
whatever.

15.0 Deputation of Representatives for Discussion

After opening of the bid, if NLCIL desires to have discussion, the bidder shall be in a
position to depute, at short notice, his representative(s) having full authority for
finalizing technical parameters as well as Commercial Terms and Conditions of the
Contract.

30

Page 30 of 328
16.0 Evaluation of Bids
16.1 The following procedures would be followed for evaluation of bids.
16.2 On the scheduled date and time of tender opening, Tender opening committee will
open the Cover -I first and shall confirm, details of payment towards cost of Tender
document(Tender fee), EMD/Bid Guarantee as in NIB, compliance of Letter of
undertaking. The bids confirming to all the above is treated as Responsive bids and
online Cover-II of the responsive bidders will be opened on the same day.
16.2.1 In the Schedule of Prices, the Bidders shall quote against each activity.
16.3 For conversion of FC to INR, the B.C selling rate prevailing on the date of opening of
price bid shall be adopted.
The following procedure will be adopted regarding the loading:
i) For FOB supplies, payments made through Letter of credit, interest loading for the
60% payment for equipment shall be done for evaluation purpose at prime lending
rate of SBI together with statutory levies if any as on the date of price bid opening
for the duration of 3 months in case of imports from Asia, Africa, Europe,
Australia and 4 months in case of America. However if the bidder wants to take
FOB payment on receipt of materials at Indian Port, this loading will not be made
and the bidder shall indicate it specifically in their bid.
ii) For FOB supplies L.C opening charges and usance charges incurred in India will
be loaded.
The bids will be evaluated based on the total evaluated site cost per MW plus O&M
charges per MW for Ten years i.e., evaluated price. The bidders will be ranked
starting from the lowest evaluated price in the ascending order after bringing them to
the same platform.

iv. The summary price table i.e Schedule-1 to 7 submitted online will be considered
for evaluation. Any discrepancies arises between online price submitted and price
mentioned in the scan copy uploaded, the online price will be considered.

16.4 From the above ranking, the bidder whose bid becomes H1 with the highest evaluated
price shall be eliminated, subject to ensuring minimum four(4) bidders participation
in the reverse auction i.e., H1 will be eliminated if five (5) or more bidders participated
in the tender.

In case, participation is less than or equal to four(4), all the bidders will be qualified
for the reverse auction.
In case more than one bidder turn out to be H1 bidders (with the same evaluated
price), all H1 bidders will be eliminated subject to ensuring four (4) bidders
participation in the reverse auction. Due to such elimination of H1 bidders, if the
available eligible bidders get reduced to less than four (4), all will be included
without elimination.

All the short listed bidders for Reverse Auction will be intimated about their eligibility
for participation in Reverse Auction. Thereafter Reverse auction will be conducted.

31

Page 31 of 328
16.4.1 Terms and conditions of Reverse Bidding/Auction is enclosed as Annexure-D. The
date and time of Reverse Bidding/Auction will be intimated. At the end of Reverse
Auction, the price ranking status of bidders will be ranked as RL1, RL2, RL3…,
starting from the lowest offered price in the ascending order.

16.4.1.1 If RL1 is not from a local supplier, the lowest bidder among the local suppliers will be
invited to match the RL1 price subject to local supplier’s quoted price falling within
the margin of purchase preference and the contract shall be awarded to such local
supplier subject to matching the RL1 price.

In case such lowest eligible local supplier fails to match the RL1 price, the local
supplier with the next higher bid within the margin of purchase preference shall be
invited to match the RL1 price and so on and contract shall be awarded accordingly.
In case none of the local suppliers within the margin of purchase preference matches
the RL1 price, then the contract may be awarded to the RL1 bidder.

After completing the reverse auction, the lowest offered bidder (RL1) will be
evaluated for QR& Techno-commercial conditions.
If the lowest offered bidder (RL1) satisfies all QR / Techno-commercial conditions,
the bidder will be considered for placement of order.
If the lowest offered bidder (RL1) fails to qualify on QR / Techno-commercial
conditions, the next ranked bidder (RL2) will be evaluated for QR& Techno-
commercial conditions.

If the bidder RL2 satisfies all QR / Techno-commercial conditions, this bidder will be
considered for placement of order .This awarded price will be taken as the lowest
offered price.
This process will be repeated in the order of ranking till the eligible bidders are
exhausted.

16.4.2 The order value for the successful bidder shall be calculated as follows:

The closing price (CP) in the Reverse Auction is the lowest offered evaluated price per
MW of the successful bidder in the Reverse Auction.

The ratio (R), between this closing price and the originally evaluated price per MW of
the successful bidder (EP) will be calculated as R= CP/EP.

The order value for the successful bidder will be calculated in the above ratio(R) of the
quoted price of the successful bidder as below:

Order value = R * Grand Total (PART-A +PART-B)


Correspondingly the individual price schedules will be arrived based on the above
ratio (R).
16.4.3 In case, if any of the information / details /declaration furnished by the RL1 bidder is
not found to be in order with the tender conditions, the bid shall be rejected and action
as mentioned below will be taken on the bidder.

32

Page 32 of 328
(i) In case, the RL1bidder fails to submit requisite documents as per NIT or if any of the
information / declaration furnished by RL1 bidder is found to be wrong during
evaluation of documents submitted by the bidder, which changes the eligibility status
of the bidder (for the first time) consider as defaulted, then his bid shall be rejected
and EMD or Rs. 1 Lakh, whichever is lower of RL1bidder will be forfeited.
(ii) If the RL1 firm is disqualified in a subsequent tender, then the bids shall be rejected
and entire EMD amount will be forfeited.
16.4.4 If the bidder fails remit the amount as stipulated above in clause 16.4.3 (i) & (ii) they
will be either debarred or banned for a specific period as deemed fit.
17.0 Local Conditions

i) Minimum wages for Contract labour shall be paid as applicable in that region from
time to time. Claims and objections due to ignorance of site conditions will not be
considered after submission of Bid.
ii) The Bidder is required to carefully examine the Technical & General Specification,
Terms and Conditions, Commercial and Erection conditions of Contract, drawings
and other details relating to work given in the Tender Document and fully acquaint
himself as to all conditions and matters which may in any way affect the work or
the cost thereof. The Bidder shall be deemed to have on his own and independently
obtained all necessary information for the purpose of preparing the Bid and his bid
as accepted shall be deemed to have taken into account all contingencies as may
arise due to such information or lack of the same.

iii) The Bidder shall be deemed to have exhaustively examined the Tender documents,
to have obtained all information and clarifications on all matters whatsoever that
might affect the carrying out of the work and to have satisfied himself as to the
adequacy of his Bid. He is deemed to have known the scope, nature and magnitude
of the work and the requirements of materials and labour involved etc. and as to all
work he has to complete in accordance with the Contract whatever be the defects,
omissions or errors that may be found in the Tender/Bid Documents.

iv) The Bidder shall be deemed to have acquainted himself with the Indian Income Tax
Act, 1961, Indian Companies Act, 1956, Indian Customs Act, 1962, Indian
Electrical Act, Factories Act, Pollution Control Regulation and other related Acts &
Laws prevalent in India and as amended from time to time. The Purchaser shall not
entertain any request for clarifications from the Bidders regarding such local
conditions.

v) Any neglect or omission or failure on the part of the Bidder in obtaining necessary
and reliable information as stated above or on any other matter affecting the Bidder
shall not relieve him from any risks or liabilities or the entire responsibility for
completion of the work in accordance with the Tender Documents.

18.0 Signature of Bids

18.1 The Bid must contain the name, residence and place of business of the person or
persons making the Bid must be signed and sealed by the Bidder with his full signature.
The name of the person/persons signing should be typed or printed below the signature
and each page of the bid shall be properly authenticated by appending
signatures/initials and seals, if any.

33

Page 33 of 328
18.2 Bid by a Corporation/Company must be signed with the legal corporate name of the
Corporation/Company by the President, Managing Director or by the Secretary or any
other person or persons authorised to submit bid on behalf of such Corporation/
Company and shall contain the Official seal of the Company.
18.3 A Bid by a person who affixes to his signature the word ‘President’, ‘Managing
Director’, ‘Secretary’, ‘Agent’, or other designation without disclosing his Principal
will be rejected. Satisfactory proof of authority of the person signing on behalf of the
Bidder shall be furnished with the Bid.
18.4 The Bid/offer shall be submitted only in the real/registered/trading name of the Bidder
and anonymous/pseudonymous shall be rejected.
18.5 Any corrections or other changes in the bid documents shall be duly authenticated by
appending signatures/initials and seals, if any, of the person signing the Bid.
18.5.1 Bids not conforming to the above requirements will be disqualified.
19.0 Award of Criteria
[

19.1 The Purchaser will award the contract to the bidder who meets the Qualifying
Requirements, determined as substantially responsive and lowest evaluated price.

19.2 The Purchaser reserves the right to accept or reject any bid and to annul the bidding
process and reject all the bids at any time prior to Award of Contract, without thereby
incurring any liability to the affected Bidder/Bidders and not obliged to inform the
grounds of such action.
19.3 The Purchaser will be the sole Judge in this regard.
20.0 Integrity Pact Programme:
NLCIL is committed to have most ethical business dealing with the Vendors, Bidders
and Contractors of goods and services and deal with them in a transparent manner with
equity and fairness.

In order to achieve these goals, NLCIL is implementing the Integrity Pact Programme
in co-operation with Central Vigilance Commission (CVC) and renowned International
Non-Governmental Organisation, Transparency International India (TII).
The Integrity Pact Programme covers the following aspects:

i) Commitments and Obligations of NLCIL (Principal).


ii)Commitments and Obligations of Vendors / Bidders / Contractors (Counterparties).
iii) Violations and Consequences.
iv) Independent External Monitors.

As per the Integrity Pact Programme, an “Integrity Pact”, which envisages an


agreement between the prospective Vendors, Bidders & Contractors and NLCIL,
committing the persons / officials of both parties, not to exercise any influence on any
aspect of the contract. Only those Vendors / Bidders / Contractors, who have entered
into such an “Integrity Pact” with NLCIL would be competent to participate in the
bidding. In other words, entering into this Pact would be a preliminary qualification.
Hence the bidder shall submit the Integrity Pact agreement duly filled and signed in his
offer enclosed in Cover-II.

34

Page 34 of 328
As on date, the Independent External Monitors are:
Sl. Name and Address Phone No. and e-mail
No.
1 Shri. M.N. Krishnamurthy, I.P.S(Retd.) Ph.No.080 – 25427282 ((R )
Former DGP of Kerala, Mobile No. 9591110000
3C-910, HRBR Layout, Email:krishnamurthymn19@gmail.com
Kalyan Nagar, Bangalore- 560 043.
2 Shri Najib Shah, Ph.No.080 – 49518850
Ex.Chairman, Mobile No. 9311706358
Central Board of Excise and Customs, Email: najibshah@hotmail.com
32, Prestige Mayberry, Nagondanahalli
Main Road, Whitefield Main Road,
Bangalore – 560 066.
3 Shri S.Srinivasan, IAS (Retd.), Ph No. 080 – 22930107 (Res)
Former Secretary of GOI & Member Mobile 9483536100
(Finance), Dept. of Space / Atomic Email: s.srinivasan1980@gamil.com
Energy/ Earth Sciences,
Flat No. D-5-107, Block No.5,
V Floor KendriyaVihar, B B Road
(Bangalore – Bellary Road) Yelahanka,
Bangalore – 560 064.

21.0 Agency Commission


No Agency commission shall be payable under this Contract.
22.0 Vital Clauses
All the clauses in the Commercial conditions of Contract and Technical Specifications
and conditions of contract are vital and no deviations are permitted in these clauses.
23.0 Conditions of Contract
Subject to the conditions enumerated in the Commercial Conditions of Contract, the
tender will be governed by "Technical Specification and Conditions of Contract" as
detailed in the document. The Technical Conditions of Contract shall prevail over the
other conditions elsewhere specified in the tender document in case they differ from
other conditions to the extent they differ from the other conditions.
Yours faithfully,
For NLC INDIA LIMITED,

CHIEF GENERAL MANAGER/ CONTRACTS

35

Page 35 of 328
Section -E

SPECIMEN FORMATS

36

Page 36 of 328
SCHEDULE OF PRICES
GENERAL INSTRUCTIONS TO BIDDERS

ANNEXURE-A
1.0 The Bidder shall furnish their prices only in the online form ‘schedule of prices’.

1.0 PREAMBLE
1.1 This section covers the price schedule to be filled up by the BIDDER for the entire
scope of work.
1.2 After Reverse Auction, the BIDDER shall furnish price-breakup as per the format in
respective currency as per the ratio indicated in Section D, Cl.16.4.2.
1.3 The BIDDER shall carefully scrutinise the specification and drawings and include price
for all items of work in the price schedule. This is a turn key lump sum contract and
over and above the prices quoted, no extra claim will be admissible. All piping, cabling,
earthing, roads and pathways, with in the terminal points are deemed to have been
included within the quoted price.

1.4 Special Notice:

i) The BIDDER shall note that the list of items indicated in the price schedule are
not necessarily exhaustive and the price quoted shall be inclusive of all
necessary equipment, accessories, gauges, instruments, etc., labour, duly
supplied, constructed, installed, tested, commissioned and handed over to the
Purchaser in perfect working conditions.
ii) It is incumbent on the successful BIDDER to arrange for and obtain necessary/
approval from the concerned appropriate authority for the complete installation
included in the scope of supply, construction, installation and commissioning.
The installation will be deemed to have been completed only when all such
approval is obtained and handed over to NLCIL.
iii) The prices for supply items shall be quoted as delivered at site including
packing & forwarding, loading and freight up to door delivery at site. The
services provided at site shall be on turnkey basis. All prevailing applicable
taxes and duties shall be indicated separately along with the quoted price.
iv) The prices shall be firm throughout the contract period in force.
v) While quoting for taxes and duties, the bidders shall consider all prevailing laws
and concession available and quote accordingly. Where any concessional taxes
have been considered the same shall be considered in the bid. The rate of taxes
and duties adopted shall be indicated in Schedule -8 of prices.

vi) The price quoted in the schedule of price for 10 years operation and
maintenance for Solar PV Power Plant (Schedule 6) and the schedule of price
for operation and maintenance for BESS (Schedule 7) added together shall not
be less than 15% of the total quoted price.

If the schedule of price for 10 years operation and maintenance for Solar PV Power
Plant (Schedule 6) and the schedule of price for operation and maintenance for BESS
(Schedule 7) added together is less than 15% of the total quoted price, the offer will be
summarily rejected.

37

Page 37 of 328
SUMMARY OF PRICE TABLE
Note: This format of price tables are given for guidance and understanding to quote the
price. Bidders are requested to quote the price in the online price schedule form only.
PART - A : SUPPLY AND SERVIES
Sl.No. Description Item Total Price
(In Rupees/ FC)
1 SCHEDULE-1 Schedule of prices for Site
Preparation
2 SCHEDULE-2 Schedule of prices for Plant and
Equipment (Solar PV Plant and
33KV Switchyard)
SCHEDULE-3 Schedule of prices for Plant and
Equipment (BESS)
3 SCHEDULE-4 Schedule of prices for
Installation &commissioning
4 SCHEDULE-5 Schedule of prices for Civil and
structural works
SUB-TOTAL(A)

PART –B : O&M for 10 years after one year warranty period


Sl.No. Description Item Total Price
(In Rupees)
1. SCHEDULE-6 Schedule of prices for Operation
And Maintenance for 10 years
after one year warranty period
for Solar Plant
2. SCHEDULE-7 Schedule of prices for Operation
And Maintenance for 10 years
after one year warranty period
for BESS
SUBTOTAL(B)

GRAND TOTAL(Part-A+Part-B)

Signature:

Name:

Designation:

Company:

Date:

38

Page 38 of 328
Scan copy to be uploaded online
SCHEDULE OF PRICES-SITE PREPARATION - SCHEDULE-1

Sl. No. Details In Rupees.

1.0 Lumpsum and firm price basis for Site preparation


activities
1.1 GST on ceiling basis
(Details to be furnished in Schedule-8)
1.2 Total price for Site preparation(sum of items 1.0+1.1)

Signature:

Name:

Designation:

Company:

Date:

39

Page 39 of 328
Scan copy to be uploaded online
SCHEDULE OF PRICES FOR PLANT AND EQUIPMENT (Solar)
SCHEDULE-2

Sl. No. Details In Rupees/Foreign currency

Design, engineering, manufacture and supply of Solar PV


module, SMB, MMS, Cables Power collection Sub-Station
and Equipments, Transformers, Power Export Sub-station
and Equipments, SCADA& EMS and Switchyard
Equipments etc. as per details in Technical specification.
1.0 Lump sum and firm price basis for supply & delivery
items on FOB basis/ex-works including loading into
container, storage, assembly and commissioning.
(port of shipment to be indicated in case of FOB)
1.1 Customs Duty including basic CD, IGST etc., for
above items (Ceiling) (Details to be furnished in
Schedule-8)
1.2 All Transport charges including GST on lumpsum
and firm price basis for Supplies of all items from
Ex works to site storage Yard. This shall include
intercarting, storage at intermediate place and also
unloading at site and stacking.
1.3 Ocean Transport charges including GST on
lumpsum and firm price basis for Supplies of all
items on FOB basis from loading Port to site
storage Yard. This shall include intercarting, storage
at intermediate place and also Port handling etc.,
unloading at site and stacking.
1.4 Comprehensive marine insurance including GST on
lumpsum and firm price basis for the above items
1.5 C GST for Sl.No.1.0

2.0 Total Cost of equipment (1.0 to 1.5)

Signature:
Name:
Designation:
Company:
Date:

40

Page 40 of 328
Scan copy to be uploaded online

SCHEDULE OF PRICES FOR PLANT AND EQUIPMENT (BESS)

SCHEDULE-3

Sl. No. Details In Rupees/Foreign currency

Design, engineering, manufacture and supply of BESS


Equipments as per details in Technical specifications

1.0 Lumpsum and firm price basis for supply& delivery


items on FOB basis/ex-works including loading into
container, storage, assembly and commissioning.
(port of shipment to be indicated in case of FOB)
1.1 Customs Duty including basic CD, IGST etc., for
above items (Ceiling) (Details to be furnished in
Schedule-8)
1.2 All Transport charges including GST on lumpsum
and firm price basis for Supplies of all items from
Ex works to site storage Yard. This shall include
intercarting, storage at intermediate place and also
unloading at site and stacking.
1.3 Ocean Transport charges including GST on
lumpsum and firm price basis for Supplies of all
items on FOB basis from loading Port to site
storage Yard. This shall include intercarting, storage
at intermediate place and also Port handling etc.,
unloading at site and stacking.
1.4 Comprehensive marine insurance including GST on
lumpsum and firm price basis for the above items
1.5 C GST for Sl.No.1.0

2.0 Total Cost of equipment (1.0 to 1.5)

Signature:
Name:
Designation:
Company:
Date:

41

Page 41 of 328
Scan copy to be uploaded online

SCHEDULE OF PRICES FOR INSTALLATION &COMMISSIONING


SCHEDULE-4

Sl.No. Details In Rupees


1.0 Lumpsum and firm Price for erection, testing and
commissioning of all Equipments as per details in the
Technical Specifications.

1.1 Comprehensive storage and erection insurance including


GST on lumpsum basis

1.2 GST for Sl.No. 1.0 above on ceiling basis


(Details to be furnished in Schedule-8)

1.3 Total (1.0 + 1.1+1.2)

Signature:

Name:

Designation:

Company:

Date:

42

Page 42 of 328
Scan copy to be uploaded online

SCHEDULE OF PRICES FOR CIVIL & STRUCTURAL WORKS

SCHEDULE- 5

Sl.No Details In Rupees


1.0 Lumpsum and firm price basis for complete civil and
structural works including design and engineering.

1.1 GST for the above on ceiling basis

1.2 Total price for civil works (sum of items 1.0 + 1.1)

Signature:

Name:

Designation:

Company:

Date:

43

Page 43 of 328
Scan copy to be uploaded online
SCHEDULE OF PRICES FOR OPERATION AND MAINTENANCE,FOR 10 YEARS
AFTER ONE YEAR WARRANTY PERIOD FOR SOLAR POWER PLANT
SCHEDULE-6

Sl.No. Details Total

Lumpsum and firm GST on ceiling basis In Rupees


price for Operation and year wise in Rs. (I + II)
Maintenance for 10
years after one year (II)
warranty period in Rs.
(I)
1

Signature:

Name:

Designation:

Company:

Date:

44

Page 44 of 328
Scan copy to be uploaded online
SCHEDULE OF PRICES FOR OPERATION AND MAINTENANCE,
FOR 10 YEARS AFTER ONE YEAR WARRANTY PERIOD FOR BATTERY
ENERGY STORAGE SYSTEM (BESS)

SCHEDULE-7

Sl.No. Details Total


Lumpsum and firm GST on ceiling basis In Rupees
price for Operation and year wise in Rs. (I + II)
Maintenance for 10
years after one year (II)
warranty period in Rs.
(I)

Signature:

Name:

Designation:

Company:

Date:

45

Page 45 of 328
Scan copy to be uploaded online

RATES AND CLASSIFICATION OF TAXES AND DUTIES

SCHEDULE-8

The bidder shall give below the details of the prevailing rates and classification of component
in accordance with the CD/GST. The details of any other taxes and duties applicable shall be
furnished.

A)GST
-----------------------------------------------------------------------------------------------------------------
Sl.No. Materials GST Classification Rate of GST
adopted
-----------------------------------------------------------------------------------------------------------------

----------------------------------------------------------------------------------------------------------------

B) CUSTOMS DUTY
-----------------------------------------------------------------------------------------------------------------
Sl.No. Materials Classification Rate of CD
Adopted

C) In case of FOB offer indicate the port of shipment:

D) In case of FOB offer, FOB payment on receipt of : Yes/No


materials receipt of Indian Port

Signature:

Name:

Designation:

Company:

Date:

46

Page 46 of 328
Annexure – B

REVERSE AUCTION

1. RULES OF REVERSE BIDDING/AUCTION: From the ranking made as per Cl.


16.0, the bidder whose bid becomes the Highest Evaluated Price per MW (H1) shall be
eliminated, subject to ensuring minimum four bidders participation in the reverse
Auction. i.e., H1 will be eliminated if five or more bidders participated In case,
participation is less than or equal to four, all the bidders will be qualified for the
Reverse Auction. In case, more than one bidder turn out to be H1 bidders (within the
same evaluated price), all H1 bidders will be eliminated subject to ensuring four
bidders participation in the Reverse Auction. Due to such elimination of H1 bidders, if
the available eligible bidders get reduced to less than four, all will be included without
elimination.

2. Schedule for Reverse Bidding: After Price e-Bids are opened online, date and time of
start of Reverse Auction shall be intimated to all the eligible bidders. Scheduled
duration of Reverse Auction shall be normally one hour.

3. Auction extension time: If a valid bid is placed within Ten (10) minutes of End Time
of the Reverse auction (RA), then RA duration shall get automatically extended for
another Ten (10) minutes from the existing end time. It may be noted that the auto-
extension will take place only if a valid bid comes in those last Ten (10) minutes. If a
bid does not get accepted as the lowest bid, the auto-extension will not take place even
if that bid might have come in the last Ten (10) minutes. The above process will
continue till no bid is received in last Ten (10) minutes which shall mark the
completion of Reverse Auction. However, bidders are advised not to wait till the last
moment to enter their bid to avoid complications related to internet connectivity, their
network problems, system crash down, power failure etc.

4. Procedure of Reverse Auctioning:


i. Reverse Auction will be conducted based on Lowest evaluated bid price emerged
as per Clause 16.4 of Invitation to Bid.
ii. The ‘Opening Price’ i.e. Start Price for RA (Reverse Auction) shall be
Rs. 5,00,000/- lower than the lowest evaluated bid price per MW.
iii. Bid Decrement shall be Rs. 5,00,000/- of the Start Price for RA and its multiples.
iv. “RL1” Bid is the last offered rate i.e. further no bidders responds within the time
limit.
v. After completion of the online Reverse Auction, the Closing Price (CP) i.e. RL1
bid shall be available for further processing.
vi. After reverse auction, the price break up for all components shall be arrived as
follows:
(a)The closing price (CP) in the Reverse Auction is the lowest offered evaluated
price per MW of the successful bidder in the Reverse Auction.

(b)The ratio (R), between this closing price and the originally evaluated price per
MW of the successful bidder (EP) will be calculated as R= CP/EP.
47

Page 47 of 328
(c) T heorder value for the successful bidder will be calculated in the above
ratio(R) of the quoted price of the successful bidder as below:

Order value =
R * Grand Total
(PART-A +PART-B)
Correspondingly the individual price schedules will be arrived based on the above
ratio (R).

5. System Requirement

Refer to NLCIL’s portal (econts.nlcindia.com) for System Requirements:


6. Bidding in Reverse auction: In all cases, bidder should use their own ID and Password
along with Digital Signature at the time of submission of their bid.
7. During the entire e-reverse auction process, the bidders will remain completely
anonymous to one another.
8. The e-reverse auction shall remain open from the pre-announced date & time and for as
much duration as mentioned above.
9. All electronic bids submitted during the e-reverse auction process shall be legally
binding on the bidder. Any bid will be considered as the valid bid offered by that bidder
and acceptance of the same by the Buyer will form a binding contract between NLCIL
and the Bidder for execution of work.
10. It is mandatory that all the bids are submitted with digital signature certificate otherwise
the same will not be accepted by the system.
11. NLCIL reserves the right to cancel or reject or accept or withdraw or extend the e-
tender-e-Reverse Auction in full or part as the case may be without assigning any
reason thereof.
12. The prevailing/current lowest bid will be displayed on the bidding screen during the
course of e-reverse auction and all subsequent bids shall have to be quoted lower than
the prevailing/current lowest bid.
13. The server time shall be treated as final and binding. Bids recorded in the server before
the bid closing time will only be treated as valid bid. Bidders are, therefore, advised to
submit their bids well before the closing time of e-reverse auction. If any bid reaches
the server after the bid closing time as per server time, the same will not be recorded
and no complaint in this regard shall be entertained.
14. Bidders are advised to exercise caution in quoting their bids in e-reverse auction to
avoid any mistake. Bids once submitted can’t be recalled.
15. Any order resulting from this bidding process shall be governed by the terms and
conditions mentioned in the NIB. No deviation to the technical and commercial terms
& conditions are allowed.

48

Page 48 of 328
Annexure - C
LETTER OF UNDERTAKING

From:
(Name & Address of Bidder)
……………………………
……………………………….
……………………………….

SUB: Tender for (Name of Work to be filled up). – Reg.

REF: Tender No______________________________.

1. With reference to the aforesaid tender for (Name of Work to be filled up) I/we,
____________________ Ltd., (the Company) having our Registered Office at
______________________________________________ hereby give the following
declarations and undertaking.

2. I/We have read and understood all the terms and conditions of the tender and hereby agree
and undertake to confirm all the technical and commercial conditions of this tender without
any deviation.

3. I/We also confirm and certify that all the relevant documents have been submitted in
conformity to the Qualifying Requirements specified in the tender.

4. I/We hereby agree and undertake that NLC India Limited shall have the right to reject the
offer and take penal action against us, if any deviation is noticed during evaluation of the
tender in contradictory to this letter of undertaking.

5. The information and documents provided by us are correct and authentic to the best of our
knowledge.

6. I/We attached duly filled in Check list for Compliance of Important Tender Conditions.

Authorized Signatory
(Name & Designation)
Encl.:- Check List.

Place:
Date :
Company Seal

49

Page 49 of 328
Annexure - D
Check list for Compliance of Important Tender Conditions
(to be attached with the Letter of Undertaking)

Bidders to submit their bid accepting all the terms and conditions of the Tender and the
required / relevant documents wherever required, as per the formats given below:

EMD, COST OF TENDER DOCUMENTS & INTEGRITY PACT:

Sl. Description Acknowledgement for Details if YES


No. enclosing
as per NIB (please tick)
1 Tender Fee details YES NO Cost :
Bank :

2 Bid Guarantee YES NO EMD


Cost :
Bank :
BG No :
Validity :

3 Integrity Pact YES NO ...............


4 Bid Validity as in NIB YES NO Date

PQR QUESTIONNAIRE:

Sl. Description Acknowledgement Details of


No. for enclosing as per documents
NIB submitted in
support of QR
conditions
1 PQR YES / NO

Signature of Bidder.

50

Page 50 of 328
ANNEXURE - E

Bid Guarantee Form


NOTE:

1. This guarantee should be furnished by a Nationalized Bank / Scheduled Bank (other than
Bank of China) authorized by Reserve Bank of India in the format as given below.

2. This bank guarantee should be furnished on stamp paper of value not less than Rs.80/- as
per Stamp Act.

3. The stamp paper should have been purchased in the Name of the Bank executing the
guarantee.

Bank Guarantee No……………


Date.: ……………….

Ref. Tender No…………………………..


To
NLC India Limited,
Block-1, Neyveli – 607 801.
Cuddalore District, Tamil Nadu, INDIA.

Dear Sirs,
In accordance with your ‘ Invitation to Bid’ under your Tender No.:…………………. dated
…………… M/s. ………………………….. hereinafter called the Bidder, having its
Registered Office/ Head Office at ………………………. with the following Directors on their
Board of Directors / partners of the firm.

1 …………………………… 2 ……………………………
3 …………………………… 4 ……………………………
5 …………………………… 6 ……………………………
7 …………………………… 8 ……………………………
9 …………………………… 10 ……………………………

wish to participate in the said bid for ………………………

As an irrevocable Bank Guarantee against Bid Guarantee for a sum of *…………………….


(in words and figures) valid for 10 months from …………………….. (the date of bid opening)
is required to be submitted by the Bidders as a condition precedent for participation in the said
bid, which amount is liable to be forfeited on the happening of any contingencies mentioned in
the bid documents.

We the …………………. Bank at …………………….. having our Head Office at


………………….. (local address) guarantee and undertake to pay immediately on demand by
NLC India Limited, stating that

51

Page 51 of 328
a the bid has been unilaterally revoked / revised / modified / withdrawn
before expiry of bid validity period, by the Bidder(s) ; or

b. The price(s) have been unilaterally increased or altered after the bid
opening and during validity of the offer, by the Bidder; or

c. On issue of LOA by NLC to the bidder, the bidder has omitted or refused
to accept the said LOA within the stated period and/ or execute the
Contract agreement; or

d. the Bidder, after issue of LOA, omitted or failed to submit Contract


Performance Guarantee within the specified period or

e. the Bidder furnished Forged/Bogus Certificates

the amount of …*…………..to the said NLC India Limited without any reservation, protest,
demur and recourse. Any such demand by the NLC India Limited shall be conclusive and
binding on the bank irrespective of any dispute or difference raised by the Bidder.

The guarantee shall be irrevocable and shall remain valid upto …@………………… If any
further extension of this guarantee is required the same shall be extended on receiving
instruction from M/s. ………………………….. on whose behalf this guarantee is issued.

In witness where of the Bank, through its authorized Officer has set its hand and stamp on
this………..day of ………….at………………..

Notwithstanding anything contained herein:


a. our liability under this bank guarantee shall not exceed ………… (in words)
b. this bank guarantee shall be valid upto ……………..; and
c. we are liable to pay the guaranteed amount or any part thereof under this bank
guarantee only and only if you serve upon us a written claim or demand on or
before ………………
WITNESS (Signature)

1. Signature Name in Block Letters


Name in Block letters
Occupation Designation
Address

2. Signature Staff code No.


Name in Block letters (Bank’s seal)
Occupation Attorney as per Power of
Address Attorney No………..
Dated…………….

* The amount shall be as specified in the tender documents

@ This date should be 10 months after the date of Bid Opening.

52

Page 52 of 328
(To be executed on plain paper and applicable for all tenders of value above Rs 1 crore)
INTEGRITY PACT:
Between
NLC India Limited (NLCIL) hereinafter referred to as "The Principal”
and
............................................. hereinafter referred to as ''The Bidder/ Contractor"

Preamble:

The Principal intends to award, under laid down organizational procedures, contract/s for
………………………… The Principal values full compliance with all relevant laws and
regulations, and the principles of economic use of resources, and of fairness and transparency
in its relations with its Bidder/s and Contractor/s.
In order to achieve these goals, the Principal cooperates with the renowned international Non-
Governmental Organization ''Transparency International" (TI). Following TI's national and
international experience, the Principal will appoint an external independent Monitor who will
monitor the tender process and the execution of the contract for compliance with the principles
mentioned above.

Definitions:
In pursuance of the above Pact, for the purposes of this provision, the Principal defines the
relevant terms set forth therein as under:

1) “Contract” means the contract entered into between the Principal and Bidder (or
Bidder) / Contractor for the execution of work mentioned in the preamble above.
2) “Contractor” means the bidder or Bidder whose tender (bid) has been accepted by the
principal or Company whose tender (bid) has been accepted and shall be deemed to
include his/its/their successors, representatives, heirs, executors and administrators
unless excluded by the Contract.
3) “Coercive practice” means harming or threatening to harm, directly or indirectly,
persons or their property to influence their participation in the procurement process or
affect the execution of a contract: In order to achieve these goals, the Principal
proposes to appoint one or more External Independent Monitor/s who will monitor the
tender process and the execution of the contract for compliance with the principles
mentioned above.
4) “Collusive practice” means a scheme or arrangement between two or more bidders, with
or without the knowledge of the Principal designed to establish bid prices at artificial,
noncompetitive levels; and
5) “Corrupt practice” means the offering, giving, receiving or soliciting of anything of
value to influence the action of a public official in the procurement process or in
contract execution;
6) “External Independent Monitor” means a person, hereinafter referred to as EIM,
appointed, in accordance with Section 7 below, to verify compliance with this
agreement.
7) “Fraudulent practice” means a misrepresentation of facts in order to influence a
procurement process or the execution of a contract to the detriment of the Principal and
includes collusive practices among Bidders (Prior to or after bid submission) designed
to establish bid prices at artificial, non competitive levels and to deprive the Principal of
the benefits of free and open competition;
8) “Party” means a signatory to this agreement.

53

Page 53 of 328
9) “Purchaser” means NLC India Limited, Neyveli, incorporated under the Companies
Act 1956, having their registered Office at Chennai, 600 010 and includes their
successors.
10) “Bidder or Bidders” means the person, firm or company submitting a tender (bid)
against the invitation to Tender (bid) and includes his/its/their staff, consultants, parent
and associate and subsidiary companies, agents, consortium and joint venture partners,
sub-contractors and suppliers, heirs, executors, administrators, representatives,
successors.

Section 1 - Commitments of the Principal

(1) The Principal commits itself to take all measures necessary to prevent corruption and to
observe the following principles:
1 No employee of the Principal, personally or through family members, will in
connection with the tender for, or the execution of a contract, demand, take a promise
for or accept, for him/herself or third person, any material or immaterial benefit which
he/she is not legally entitled to.

2. The Principal will, during the tender process treat all Bidders with equity and reason.
The Principal will in particular, before and during the tender process, provide to all
Bidders the same information and will not provide to any Bidder confidential/additional
information through which the Bidder could obtain an advantage in relation to the
tender process or the contract execution.

3. The Principal will exclude from the process all known prejudiced persons.

(2) If the Principal obtains information on the conduct of any of its employees which is a
criminal offence under the relevant Anti-Corruption Laws of India, or if there be a
substantive suspicion in this regard, the Principal will inform its Vigilance Office and
in addition can initiate disciplinary actions.

Section 2 - Commitments of the Bidder/Contractor

(1) The Bidder / Contractor commits itself to take all measures necessary to prevent
corruption. He commits himself to observe the following principles during his
participation in the tender process and during the contract execution.
1. The Bidder / Contractor will not, directly or through any other person or firm, offer,
promise or give to any of the Principal's employees involved in the tender process or
the execution of the contract or to any third person any material or immaterial benefit
which he/she is not legally entitled to, in order to obtain in exchange any advantage of
any kind whatsoever during the tender process or during the execution of the contract.
2. The Bidder / Contractor will not enter with other Bidders into any undisclosed
agreement or understanding, whether formal or informal. This applies in particular to
prices, specifications, certifications, subsidiary contracts, submission or non-submission
of bids or any other actions to restrict competitiveness or to form cartels in the bidding
process.
3. The Bidder /Contractor will not commit any offence under the relevant Anticorruption
Laws of India: further the Bidder /Contractor will not use improperly, for purposes of
competition or personal gain, or pass on to others, any information or document
provided by the Principal as part of the business relationship, regarding plans, technical
proposals and business details, including information contained or transmitted
electronically.
54

Page 54 of 328
4. The Bidder / Contractor will, when presenting his bid, disclose any and all payments he
has made, is committed to or intends to make to agents, brokers or any other
intermediaries in connection with the award of the contract.
5. The Bidder / Contractor of foreign origin shall disclose the name and address of the
Agents / representatives in India, if any. Similarly the Bidder / Contractor of Indian
Nationality shall furnish the name and address of the foreign principals, if any.

(2) The Bidder / Contractor will not instigate third persons to commit offences outlined
above or be an accessory to such offences.

Section 3. Disqualification from tender process and exclusion from future


contracts

If the Bidder, before contract award has committed a transgression through a violation
of Section 2 or in any other form such as to put his reliability or credibility as Bidder
into question, the Principal is entitled to disqualify the Bidder from the tender process
or to terminate the contract, if already signed, for such reason.

(1). If the Bidder / Contractor has committed a transgression through a violation of Section
2 such as to put his reliability or credibility into question, the Principal is entitled also
to exclude the Bidder /Contractor from future contract award processes. The imposition
and duration of the exclusion will be determined by the severity of the transgression.
The severity will be determined by the circumstances of the case, in particular the
number of transgressions, the position of the transgressors within the company
hierarchy of the Bidder and the amount of the damage. The exclusion will be imposed
for a minimum of 6 months and maximum of 3 years.
(2) A transgression is considered to have occurred if the Principal after due consideration
of the available evidence, concludes that no reasonable doubt is possible.

(3) The Bidder accepts and undertakes to respect and uphold the Principal's absolute right
to resort to and impose such exclusion and further accepts and undertakes not to
challenge or question such exclusion on any ground, including the lack of any hearing
before the decision to resort to such exclusion is taken. This undertaking is given freely
and after obtaining independent legal advice.

(4) If the Bidder / Contractor can prove that he has restored / recouped the damage caused
by him and has installed a suitable corruption prevention system, the Principal may
revoke the exclusion prematurely, provided such systems has been audited by an
independent agency.

Section 4 - Compensation for Damages

(1) If the Principal has disqualified the Bidder from the tender process prior to the award
according to Section 3, the Principal is entitled to demand and recover from the Bidder
liquidated damages equivalent to Earnest Money Deposit / Bid Security.
(2) If the Principal has terminated the contract according to Section 3 or if the Principal is
entitled to terminate the contract according to Section 3, the Principal shall be entitled
to demand and recover from the Contractor liquidated damages equivalent to Security
Deposit /Performance Bank Guarantee.

55

Page 55 of 328
Section 5 - Previous transgression
(1) The Bidder declares that no previous transgressions occurred in the last 3 years with
any other Company in any country conforming to the TI approach or with any other
Public Sector Enterprise in India that could justify his exclusion from the tender
process.
(2) If the Bidder makes incorrect statement on this subject he can be disqualified from the
tender process or the contract, if already awarded, can be terminated for such reason.
Section 6 - Equal treatment of all Bidders / Contractors/ Subcontractors

(1) The Bidder / Contractor undertakes to demand from all subcontractors a commitment in
conformity with this Integrity Pact, and to submit it to the Principal before contract
signing.
(2) The Principal will enter into agreements with identical conditions as this one with all
Bidders, Contractors and Subcontractors.
(3) The Principal will disqualify from the tender process all bidders who do not sign this
Pact or violate its provisions.

Section 7 - Criminal charges against violating Bidders/Contractor/ Subcontractors

If the Principal obtains knowledge of conduct of a Bidder, Contractor or Subcontractor,


or of an employee or a representative or an associate of a Bidder, Contractor or
Subcontractor, which constitutes corruption, or if the Principal has substantive
suspicion in this regard, the Principal will inform the Vigilance Office.
Section 8 – External Independent Monitor /Monitors (three in number depending
on the size of the contract) (to be decided by the Chairperson of the Principal)
(1) The Principal appoints competent and credible external independent Monitor for this
Pact. The task of the Monitor is to review independently and objectively, whether and
to what extent the parties comply with the obligations under this agreement.
(2) The Monitor is not subject to instructions by the representatives of the parties and
performs his functions, neutrally and independently. He reports to the Chairperson of
the Board of the Principal.
(3) The Contractor accepts that the Monitor has the right to access without restriction to all
Project documentation of the Principal including that provided by the Contractor. The
Contractor will also grant the Monitor, upon his request and demonstration of a valid
interest, unrestricted and unconditional access to his project documentation. The same
is applicable to Subcontractors. The Monitor is under contractual obligation to treat the
information and documents of the Bidder / Contractor / Subcontractor with
confidentiality.
(4) The Principal will provide to the Monitor sufficient information about all meetings
among the parties related to the Project provided such meetings could have an impact
on the contractual relations between the Principal and the Contractor. The parties offer
to the Monitor the option to participate in such meetings.
(5) As soon as the Monitor notices, or believes to notice, a violation of this agreement, he
will so inform the Management of the Principal and request the Management to
discontinue or heal the violation, or to take other relevant action. The monitor can in
this regard submit non-binding recommendations. Beyond this, the Monitor has no right
to demand from the parties that they act in a specific manner, refrain from action or
tolerate action.
56

Page 56 of 328
(6) The Monitor will submit a written report to the Chairperson of the Board of the
Principal within 8 to 10 weeks from the date of reference or intimation to him by the
'Principal' and, should the occasion arise, submit proposals for correcting problematic
situations.
(7) Monitor shall be entitled to compensation on the same terms as being extended to /
provided to Outside Expert Committee members / Chairman as prevailing with
Principal.
(8) If the Monitor has reported to the Chairperson of the Board a substantiated suspicion of
an offence under relevant Anti-Corruption Laws of India, and the Chairperson has not,
within reasonable time, taken visible action to proceed against such offence or reported
it to the Vigilance Office, the Monitor may also transmit this information directly to the
Central Vigilance Commissioner, Government of India.
(9) The word 'Monitor' would include both singular and plural.

10) The Monitor can be removed from his office, before the expiry of his tenure only with
the approval of the Board of the Principal.

Section 9 - Pact Duration

This Pact begins when both parties have legally signed it. It expires for the Contractor
12 months after the last payment under the respective contract, and for all other Bidders
6 months after the contract has been awarded.

If any claim is made / lodged during this time, the same shall be binding and continue
to be valid despite the lapse of this pact as specified above, unless it is discharged /
determined by Chairperson of the Principal.

Section 10 – Other provisions

(1) This agreement is subject to Indian Law. Place of performance and jurisdiction is the
Registered Office of the Principal, i.e. Chennai / Neyveli. The Arbitration clause
provided in the main tender document / contract shall not be applicable for any issue /
dispute arising under Integrity Pact.

(2) Changes and supplements as well as termination notices need to be made in writing.
(3) If the Contractor is a partnership or a consortium this agreement must be signed by all
partners or consortium members.

(4) Should one or several provisions of this agreement turn out to be invalid, the remainder
of this agreement remains valid. In this case, the parties will strive to come to an
agreement to their original intentions.
………………………………… …………………………….
For the Principal for the Bidder /Contractor
Place …………. Witness1 ……………………
Date ………….. Witness 2 …………

57

Page 57 of 328
ANNEXURE - F

LIST OF FORMS

58

Page 58 of 328
LIST OF FORMS
I. QUALIFICATION REQUIREMENT FORM
1. QUALIFICATION REQUIREMENT

Sl.No. Qualification Requirement Bidder


Response

1.0 The bidder shall meet the following qualifying requirements related to solar
PV Power Plants and Battery Energy Storage System. (a) Bidder should have
executed contracts of Design/Engineering, Supply, Erection/Supervised
erection, commissioning of Solar PV Power Plant(s) with cumulative capacity
of 10MWp or above as on the original scheduled date of tender opening and
out of which at least one Solar PV Power Plant shall be of minimum 5MWp
capacity or above and should be in successful operation for at least one year
within the last 7 years as on the original scheduled date of tender opening.
AND 2.1(b) Bidder should have executed contracts of Design/Engineering,
Supply, Erection/Supervised erection, commissioning of Battery Energy
storage system with cumulative capacity of 1.0MWhr. or above as on the
original scheduled date of tender opening and out of which at least one Battery
Energy Storage System shall be of minimum 0.5MWhr. capacity or above and
should be in successful operation for at least one year within the last 7 years as
on the original scheduled date of tender opening.
1.1 Whether bidder is submitting as his own or with Collaborator(s) or with
Consortium or is a Joint Venture Company?
1.2 Please specify the cumulative capacity of Grid Interactive Solar PV Power
Plants in MWp have executed for Design/Engineering, Supply,
Erection/Supervised erection, commissioning as on the original schedule date
of Tender opening
1.3 Out of 10 MWp cumulative capacity please specify the capacity of at least
one plant which is connected to Grid and in successful operation for at least
one year as on the original scheduled date of Tender opening and within the
last 7 years
1.4 Please specify the period in months of 5MWp capacity or above of Grid
Interactive Solar PV Power Plants is in successful operation.
1.5 Please specify the cumulative capacity of Battery Energy Storage System
executed contracts of Design/Engineering, supply, Erection/Supervised
erection, commissioning of Battery Energy storage system as an original
schedule date of Tender opening
1.6 Out of 1.0MW Hr please specify the capacity at least one Battery Energy
storage system is in successful operation for period of at least one year as on
the original schedule date of Tender opening and within last 7 years
1.7 Please specify the period in months of 0.5 Mwhr capacity of Battery Energy
storage system is in successful operation.
1.8 Upload documentary evidence along with the bid in the form of user
certificate together with full contact details for verification for having
executed cumulative capacity 10MWp and one plant which is connected to
grid of 5MWp capacity or above is in successful operation for at least one
year as on the original scheduled date of tender opening and within the last 7
years

59

Page 59 of 328
1.9 Upload documentary evidence along with the bid in the form of user
certificate together with full contact details for verification for having
executed cumulative capacity of Battery Energy storage system 1.0 MWhr
and one plant which is 0.5 MWhr capacity or above is in successful operation
for at least one year as on the original scheduled date of tender opening and
within the last 7 years

2.0 Bidder who doesn’t fulfill the qualifying requirements stipulated in clause 2.1
(a) and (b) above by himself can also participate provided the bidder
collaborates with not more than two firms and together they fully meet the
qualifying requirements stipulated in clause 2.1 (a) and (b) above and the
Collaborator (s) should furnish along with the bid valid collaboration
agreement to execute this project and a back-up Bank Guarantee as required in
the relevant clauses. OR Bidder
can also be a leader of a consortium consisting of not more than three firms,
such that together they meet the Qualifying Requirements stipulated in clause
2.1 (a) and (b) above and the members of the consortium should furnish back-
up Bank Guarantee as required in the relevant clauses. In case of bidding by a
Consortium, the consortium partners shall necessarily identify a leader of the
Consortium who will furnish the Consortium Agreement and the consortium
partners shall execute a Joint Deed of Undertaking in which the partners are
jointly and severally liable to the Owner for successful performance of the
contract. OR Bidder
can also be a Joint Venture Company, provided the qualifying requirement in
clause 2.1 (a) and (b) above is met by any one or more partners of the Joint
Venture (JV) Company. Each partner of the JV Company on the basis of
whom the JV Company gets qualified shall have minimum 26% equity in the
JV Company and should furnish back-up Bank Guarantee as required in the
relevant clauses
2.1 Whether bidder is with collaborator(s)?
2.2 If yes name of the Collaborator(s)
2.3 Please upload Collaboration Agreement obtained from each of the
Collaborator for this project
2.4 Whether bidder is a leader of a consortium consisting of not more than three
firms, such that together they meet the Qualifying Requirements
2.5 If yes mention name of the consortium partners
2.6 Please upload the Consortium Agreement and the consortium Joint Deed of
Undertaking in which the partners are jointly and severally liable to the Owner
for successful performance of the contract.
2.7 Whether bidder is a Joint Venture Company meeting QR by any one or more
partners of the Joint Venture Company
2.8 If yes name of the partners and indicate the equity share in the JV Company
3.0 The Bidder or Bidder with Collaborator or the Lead Member of Consortium
or major partner of JV company shall have Positive Net Worth as per the latest
audited financial Statements.
3.1 Whether the Bidder or Bidder with Collaborator or the Lead Member of
Consortium or major partner of JV company having Positive Net Worth as
per the latest audited financial Statement
4.0 Average Annual Turn Over of the Bidder, combined Average Annual Turn
Over of the Bidder and Collaborator(s), combined Average Annual Turn Over
of the Consortium partners and the combined Average Annual Turn Over of
all the promoters of the Joint Venture Company, as the case may be, shall not

60

Page 60 of 328
be less than Rs.48.648 Cr. in the preceding three (3) consecutive financial
years as on the original scheduled date of tender opening.
4.1 Upload audited profit and loss accounts and balance sheets for the precceding
three (3) financial years from the original schedule date of Tender opening of
the bidder or the bidder with collaborator(s) or all individual firms in the
consortium or all partners in the Joint Venture Company, as the case may be

61

Page 61 of 328
2.Schedule of places of Manufacture for Solar and BESS Equipment

Sl.No. Name Address Telephone Fax E- Country Place of Attachment


No. No. Mail Origin Manufacturer

62

Page 62 of 328
3. SCHEDULE OF BIDDER'S EXPERIENCE DETAILS OF SOLOR PROJECT
AND BESS

Sl. Purchaser/I Address Phone Fax Email Contract Exact Capacity of Scope of Date of Number of Whether Attach
No. nstitution No. No. id /PO ref. place/locati the PV work commissio years performance ment
Contact on of the Solar power covered ning successful certificate
name PV Solar plant / operation from the
Power BESS customer
Plant is in supplied enclosed
use

63

Page 63 of 328
4. BID GUARANTEE

Sl.No Description Bidder


Response

Bid Guarantee Type


BG Bank Guarantee
1 Bank Guarantee No.
2 Bank Guarantee Date
3 Details of Stamp paper
3.1 Stamp Paper Amount
3.2 Whether stamp paper purchased in the Name of the Bank
3.3 Stamp paper purchased address
3.4 Date of Purchase
4 Bank details
4.1 Banker's Name
4.2 Banker's Address
4.3 Bank email-id
4.4 Bank Phone No.
4.5 Bank Fax No.
4.6 Banker's Seal
5 Manager's Name & No.
6 Whether signed by two Witness
7 Whether overwriting/cutting if any on the BG authenticated under
signature & seal of executants
8 Whether the BG has been issued by a Nationalized/Scheduled Bank in
India
9 If the bank guarantee issued by a foreign bank. Whether it is in the
approved list of RBI.
10 Details of value and validity
10.1 Currency of BG
10.2 Value of BG
10.3 Validity upto
11 Whether Bank Guarantee is as per NLCIL Format
RTGS/NEFT RTGS/NEFT details
1 RTGS/NEFT UTR No.
2 UTR Date
DD Demand Draft / Pay order / Banker's Cheque
1 Demand Draft / Pay order / Banker's Cheque No.
2 Date of DD
3 DD in favour of
4 Payable at
MSME Micro, Small and Medium Enterprises (MSME) Details
1 MSME No.
2 Registration Date
3 Registration Category
NSIC National Small Industries Corporation Ltd. (NSIC) Details
1 NSIC No.
2 NSIC Expire Date
3 NSIC Category
Please attach supporting scanned document(s)
64

Page 64 of 328
II. TECHNICAL FORMS

1. TECHNICAL FORMS

S. DESCRIPTION BIDDER'S
No RESPONSE

1.0 Please confirm acceptance of the Scope of Work stipulated in the tender
document?
2.0 Please confirm acceptance of the time schedule stipulated in the tender
document?

65

Page 65 of 328
III. COMMERCIAL FORMS

1. DOCUMENT STRUCTURE

Code Description Type Bidder


Acceptance

Vol-1 Qualifying Requirement QR


S0_1 Qualifying Requirement
VOL_2 COMMERCIALCONDITIONS OF CONTRACT Commercial
SO_1 S1. Instruction to Bidders for submission of Online Bids in
e-Tender and e-Reverse auction. S2. Invitation to Bid S3.
The specimen Form of Bank Guarantee, Integrity Pact and
List of Forms S4.Commercial Conditions of Contract for
equipment S5. Commercial Conditions of Contract for
O&M.
VOL_3 TECHNICAL SPECIFICATION Technical
SO_1 Section 1.0, Section-2.1 to 2.9, Annexure-1 to 3 and
drawings etc.

66

Page 66 of 328
2. COMMERCIAL FORM

Sl.No Description Bidder


Response

1.0 Particulars of the firm


1.1 Bidder’s Name and Address
1.2 Telephone No.
1.3 Fax No.
1.4 E – Mail address
1.5 Name of Contact Person
1.6 Mobile Number of Contact Person
2.0 Bank Details
2.1 Name of the beneficiary
2.2 Bank A/c No.
2.3 Name of the Bank
2.4 Name of the Branch
2.5 IFS Code (For NEFT/RTGS Payment)
2.6 BANK ADDRESS
2.7 BANK FAX NO.
2.8 BANK EMAIL-ID
2.9 Bank Phone No.
3.0 PAN No.
4.0 GST Registration No.
5.0 Other Statutory Registration No., if any
6.0 Name and full address of Chief executives
7.0 Upload Supporting Documents

67

Page 67 of 328
3. CHECK LIST FOR BID SUBMISSION

Sl.No Description Bidder


Acceptance

1.0 Please ensure that all the attachments in the offer are only in English
language? If any document is in any other Language, the same shall be got
translated in English version duly authorized by the Notary Public or
Competent Authority by the Bidder and upload both the versions.
2.0 Have you read and filled all the forms?
3.0 Have you attached performance certificates?
4.0 Have you attached related work orders/agreements?
5.0 Have you attached audited annual reports?

68

Page 68 of 328
4. RATE OF TAXES & DUTIES

Sl.No. Description Bidder


Response

1 Port of shipment
2 GST rate adopted in %
3 Customs duty rate adopted in %
4 Whether FOB supplies payment is agreeable on receipt of materials at Indian
Port .
5 Upload scan copy of Schedule-8 (Rate of Taxes & Duties)

69

Page 69 of 328
5. FORM OF BID

Sl.No Description Bidder


Acceptance

1.0 Having carefully examined all the Tender Documents and its Amendments /
errata / Corrigendum / Clarifications issued till the date of tender opening,
we agree to Complete the WORKS in conformity with all the terms and
conditions stated in Tender Documents and its Amendments / Errata /
Corrigendum / Clarifications issued till the date of tender opening and as per
time schedule given in Tender Document. The Services offered are of best
and of latest technology and of international standards.
2.0 I / We declare and certify that I / We fully satisfy the Qualifying
Requirements and the documentary proof as called for, have been attached.
3.0 We undertake, in case our bid is accepted, to commence the work from the
date of Letter of Award and to complete and deliver the whole of the work
and responsibilities comprised in the contract within as per time schedule
given in Tender document.
4.0 We are submitting the Bid Guarantee as instructed by you. This Bid
Guarantee shall be governed as per the stipulations provided in the “
Invitation to Bid”.
5.0 We agree to abide by and keep our Bid valid initially for a period of 8 (eight)
months from the date of opening of Bid (Part I) by NLC India Ltd. (NLCIL)
formerly Neyveli Lignite Corporation Limited and it shall remain binding on
us and may be accepted at any time before the expiry of that period.
6.0 I/We, the undersigned have carefully examined and understood the Bidding
Documents including the amendments / errata / Corrigendum / Clarifications
issued till the date of tender opening. I / We hereby agree to carry out the
entire works as described in the specifications in conformity with the
specifications and Bidding documents, as per prices quoted by us in the
Schedule of Prices.
7.0 Should our Bid be accepted, we hereby agree to abide by and fulfill all
Terms and conditions of Tender Document as accepted by us and in default
thereof, to forfeit and pay to NLCIL or NLCIL’s successors, assignees or
authorized nominees such sum of money as are stipulated in conditions
contained in Tender Documents and agree to furnish Bank Guarantee for
Contract Performance as per the Proforma prescribed by NLCIL and
acceptable to NLCIL for a sum equal to 5% of the aggregate sum of contract
price within 30 days from the date of Letter of Award. We understand that
NLCIL is not bound to accept the lowest or any Bids received and NLCIL
has the right to reject any bid, without assigning any reason whatsoever.
8.0 This Bid together with written acceptance thereof shall constitute a binding
CONTRACT between NLCIL and ourselves till a formal contract is
executed.
9.0 We have noted the contents of clause2.6 in line with DIPP order dated
15.06.2017 and confirm compliance to the requirements.
10.0 We have enclosed necessary self-certification for local content furnishing the
details of the location(s) at ehcih the local value addition is made
11.0 We have enclosed a certificate from the statutory auditor / cost auditor of the
company (in the case of companies) or from a practicing cost accountant/
practicing charted accountant (in respect of suppliers other than companies)
giving the percentage of local content.
70

Page 70 of 328
6. SUMMARY OF PRICE TABLE

Sl. No Description Item USD EURO INR

PART SUPPLY AND


–A SERVIES
1 SCHEDULE-1 Schedule of prices for Site Preparation
Upload scan copy of
SCHEDULE-1
2 SCHEDULE-2 Schedule of prices for Plant and
Equipment (Solar PV Plant and 33KV
Switchyard)
Upload scan copy of
SCHEDULE-2
3 SCHEDULE-3 Schedule of prices for Plant and
Equipment (BESS)
Upload scan copy of
SCHEDULE-3
4 SCHEDULE-4 Schedule of prices for Installation
&commissioning
Upload scan copy of
SCHEDULE-4
5 SCHEDULE-5 Schedule of prices for Civil and
structural works
Upload scan copy of
SCHEDULE-5
SUB-TOTAL(Part -A)
PART O&M for 10 years after
–B one year warranty period
1 SCHEDULE-6 Schedule of prices for Operation And
Maintenance for 10 years after one
year warranty period for Solar Plant
Upload scan copy of
SCHEDULE-6
2 SCHEDULE-7 Schedule of prices for Operation And
Maintenance for 10 years after one
year warranty period for BESS
Upload scan copy of
SCHEDULE-7
SUBTOTAL(Part -B)
GRAND TOTAL(Part-
A+Part-B)

71

Page 71 of 328
Section - F
DRAFT CONTRACT AGREEMENT AND
COMMERCIAL CONDITIONS OF
CONTRACT

72

Page 72 of 328
SECTION - F
COMMERCIAL CONDITIONS OF CONTRACT
CONTENTS

CLAUSE TITLE PAGE


NO
NO.
CONTRACT AGREEMENT 75-77
SCHEDULE-1 DEFINITIONS 78-83
SCHEDULE-2 SCOPE OF SUPPLY & SERVICES 84-91
SCHEDULE-3 CONTRACT PRICE 92
SCHEDULE-4 TIME SCHEDULE 93-99
SCHEDULE-5 TAXES AND DUTIES 100-101
SCHEDULE-6 TERMS OF PAYMENT 102-111
SCHEDULE-7 FACILITIES TO BE PROVIDED BY THE 112
PURCHASER
SCHEDULE-8 CONTRACT SPECIFICATIONS 113
SCHEDULE -9 PERFORMANCE GUARANTEE 114-115
SCHEDULE –10 GENERAL TERMS AND CONDITIONS OF THE 116-154
CONTRACT
ANNEXURE-I GENERAL CONDITIONS FOR ERECTION WORKS 157-175
ANNEXURE-II GENERAL CONDITIONS FOR CIVIL WORKS 176-177
ANNEXURE-III SAFETY CODE FOR THE CONTRACTOR 178-181
ANNEXURE-IV COMMERCIAL TERMS & CONDITIONS FOR O&M 182-196
CONTRACT
APPENDIX-A TO F 197-214

73

Page 73 of 328
CONTRACT AGREEMENT

This contract No……………………………………………………………………… made this


……………… day of …………………….. between THE NLC INDIA Limited, a company
incorporated under the Companies Act, 1956 and having its registered office at First Floor,
No.8 Mayor Sathyamurthy Road, FSD, Egmore Complex, Chetpet, Chennai-600031, India
hereinafter referred to as the “PURCHASER” (which expression shall unless repugnant to the
context or the meaning thereof, be deemed to include its successors and permitted assignees),
of the ONE PART,
AND
M/s. …………………………………………………. a Company incorporated under the
Companies Act, 1956 and having its registered office at …………
……………………………………………………………………………………………………
………………… hereinafter referred to as the “CONTRACTOR” (which expression shall,
unless repugnant to the context or meaning thereof, be deemed to include its successors and
permitted assignees) of the SECOND PART,

WHEREAS, the purchaser invited the CONTRACTOR to submit tender for scope of work for
installation of 2 x 10 MW (AC) Grid interactive Solar PV Power Project integrated with
8MWhr. Battery Energy Storage System at Attam Pahad and at Dolly Gunj, Port Blair, South
Andaman with associated 33 KV Switchyard and grid interconnection at the take off points of
Electricity Department of Andaman & Nicobar Administration including Design, Engineering,
Manufacture, Inspection at supplier’s works, supply, insurance, transport, storage, erection,
testing, commissioning.

The scope of work also includes Operation and Maintenance of the entire system for twenty
five years including one year warranty period.

The scope is indicative only and detailed scope of work is contained in the tender specification.
AND
WHEREAS, the CONTRACTOR submitted tender to the Purchaser for execution of the work
in accordance with the tender documents including technical specifications, schedule of items
and tender drawings.
AND

WHEREAS, the Purchaser has accepted the tender submitted by the CONTRACTOR for the
construction and completion of the scope of work.

NOW IT IS HEREBY AGREED AND DECLARED BY AND BETWEEN THE PARTIES


AS FOLLOWS:
Article – 1
In consideration of the promises and the payments to be made by the Purchaser to the
Contractor, the Contractor hereby covenants with the Purchaser to perform the work as detailed
in schedule – 2 “Scope of work” and Technical specifications to this contract subject to and on
the terms and conditions contained herein.

It is clearly understood between the parties that the Contractor shall be solely responsible for
the completion of the scope of work.

74

Page 74 of 328
Article – 2

If the Contractor wishes to appoint Sub–Contractor during execution of the contract, the
Contractor shall take prior written approval of the Purchaser spelling out the scope of the work
proposed to be entrusted to the said Sub-Contractor together with the relevant experience and
other details of such proposed Sub-Contractor(s).

Notwithstanding the approval accorded by the Purchaser to the appointment of Sub-


Contractor(s), the Contractor shall be solely responsible for the completion of the works as per
specifications and within the time schedule agreed in this Contract. Approval of any Sub-
Contractor by the Purchaser shall not relieve the Contractor from any of his liabilities or
obligations under the Contract and he shall be responsible for the acts, defaults and neglects of
any Sub-Contractor(s) as fully as if they were the acts, defaults or neglects of the Contractor.

Article – 3

This Contract shall come into effect from the date of letter of Award.

Article – 4

The following schedules appended to this Contract shall be deemed to form and be read and
construed as part of this Contract:-

Schedule – 1: Definitions of Terms & Specification Documents


Schedule – 2: Scope of Supply & Services
Schedule – 3: Contract Price
Schedule – 4: Time Schedule
Schedule – 5: Taxes & Duties
Schedule – 6: Terms of Payment
Schedule – 7: Facilities to be provided by the Purchaser
Schedule – 8: Contract Specifications
Schedule – 9: Performance Guarantee
Schedule –10: General Terms & Conditions of the Contract

ANNEXURE-I to III
Article – 5

In addition to the aforesaid, the following documents shall be deemed to form and be read and
construed as a part of this Contract:-
Technical Specifications with drawings (Volume–II)
Quantities, quoted rate and amount quoted against each item
Bank Guarantee Proforma for Contract Performance Guarantee
Bank Guarantee Proforma for Advance Payment, LDBG, RMBG and Financial Back up
Guarantee
Schedule of References
Power of Attorney
Letter of Award
Quality Assurance Plan by the Contractor
Project Information

75

Page 75 of 328
Article – 6

All the words and expression used in this contract shall, unless repugnant to the context, have
the same meaning as are respectively assigned to them in Schedule – 1. All headings and
marginal notes to the Articles, Schedules, Annexure, Technical Specifications or to any other
part of the Contract are solely for the purpose of giving a concise indication and not a summary
of a contents thereof and they shall never be deemed to be part thereof or be used in the
interpretation or construction thereof.

Article – 7

The Contract shall be governed in accordance with the Law of India. The civil court having
original jurisdiction over Andaman& Nicobar Islands shall have exclusive jurisdiction to try
any matter arising out of this contract.

Article – 8

This Contract is executed in English language in two originals, each party receiving one duly
signed copy. Both these copies are authentic. The Contractor shall submit Twenty five (25)
photocopies of the entire Contract documents to the Purchaser for his use.

IN WITNESS WHEREOF THE parties hereto by representatives duly authorised have


executed the Contact on the day, month and the year first above written.

Name
Name
Designation
Designation

For and on behalf of For and on behalf of


(Contractor) NLC India Limited
Neyveli – 607 801

(Seal of the Office) (Seal of the Office)

In the presence of In the presence of

1. 1.

2. 2.

76

Page 76 of 328
SCHEDULE-I
1.0 DEFINITIONS

1.1 The following words and expressions as used in this Contract (as hereinafter defined)
shall have the meanings hereof assigned to them except where the context otherwise
requires
1.2 Acceptance shall mean the manifestations by the owner of his assent to the mutually
agreed terms of the offer by the bidder.
1.3 Agreement shall mean mutual understanding between the parties which creates
obligations between each other
1.4 ‘Approval of the Purchaser’ shall mean the written approval by the ‘Purchaser’ or
‘Consultant’ with respect to matters delegated to the consultant by the purchaser of a
document or drawing or other particulars or matters in relation to the Contract.
1.5 Base Date shall mean the working day of the calendar month, one month prior to the
date set for opening of tenders-Part-I.
1.6 Bid shall mean a valid offer made against any tender enquiry, indicating terms,
conditions and prices
1.7 Bidder / Tenderer shall mean a person/party/ firm/ company /consortium who
submits an offer/ bid against a tender enquiry.
1.8 Billing Schedule shall mean the item, description and Quantities arrived at after
detailed design and engineering are prepared. It generally occurs in lump sum Price
contracts, where rates are fixed up for such items, based on the Break up prices
indicated in the offer.
1.9 Codes and Standards shall mean such codes and Standards as prescribed in ISS/
DIN/ BSS as applicable to the equipments, components, plant, machinery,
consumables. ASM Test Codes –AIEE Codes– Indian Electricity Act, etc.
1.10 Commercial use' shall mean that use of the equipment for works, which the
`Contract' contemplates.

1.11 `Commissioning' shall mean subjecting the entire Solar Power Plant and BESS for
Preliminary operation, initial operation and carrying out adjustment/ modifications
necessary for smooth operation and exporting power to the grid.
1.12 Compensation shall mean anything as an equivalent as to make assessment for loss
or damage.
a. The consideration for services rendered by contract agreed or implied.
b. Remuneration for injury suffered, especially when it has resulted in measurable
loss or in expenditure Money paid for damage caused by any wrong or breach of
contract, to the person defrauded or injured.
1.13 ‘Completion of erection’ shall be defined as to be completion of erection of all the
materials and items of the equipment covered under the scope of Contract,
successful completion of functional tests

77

Page 77 of 328
1.14 Completion of Handing Over shall mean that completion certificate as indicated in the
technical specifications and conditions of contract.

1.15 Completion Time shall mean the period stated in the contract for the completion of
Works up to and including successful completion upto provisional takeover and shall
be reckoned from the date of Letter of Award.

1.16 Condition shall mean the conditions agreed between the parties and stipulated in the
Contract agreement.

1.17 Consequential damages means the damages, claimed in a tort or breach of contract
which do not normally follow from the tort or breach.

1.18 `CONSULTANT' shall mean the CONSULTANTS appointed by the PURCHASER


for the `Project’ or their duly authorised representatives.

1.19 `CONTRACTOR' shall mean the successful BIDDER whose bid has been accepted
by the PURCHASER and on whom the `Contract' or `Purchase order' is placed
by the Purchaser and shall include his heirs, legal representatives, successors and
permitted assignees.

1.20 Contract shall mean and include this contract between the owner and Contractor for the
execution of the works as per agreed terms, conditions, specifications prices and
enforceable as per law.

1.21 Contract period shall mean the period / time schedule agreed in the contract during
which period the Contracted work shall be performed / executed, inclusive of any
period covered by extension(s), duly issued.

1.22 ‘Contract Price’ in relation to particular contract shall mean the total consideration to be
paid by the Purchaser to the Contractor.

1.23 "Contractor's works “or "Manufacturer's works” shall mean and include the land and
other places which are used by the CONTRACTOR/SUB-CONTRACTOR for the
manufacture of equipment.

1.24 Day shall mean the period between midnight to next midnight.

1.25 Delivery shall mean delivery of only such equipment, materials and supplies specified
in the Contract and manufactured and/or supplied by the Contractor in accordance with
the sequence of delivery schedule of the Contract and in case of construction and
erection work, delivery shall mean the approval of the owner to the said construction
and erection work.

1.26 Dimensions shall mean length, area, Volume etc. all expressed in metric system.

1.27 Drawing shall mean such drawings provided along with bid documents / furnished
during the progress of work by the Contractor and approved.

78

Page 78 of 328
1.28 `Date of Contract' shall mean the calendar date on which PURCHASER and the
CONTRACTOR have signed the `CONTRACT'.

1.29 `Design Charges' shall mean the charges payable for design and engineering of the
equipment.

1.30 "Effective date of Contract" shall mean the date of Letter of Award.

1.31 `ENGINEER' / Project Manager shall mean the Officer nominated by the Purchaser for
the performance of the Contract.

1.32 The term `Equipment Portion' of the Contract Price shall mean the Ex-works. Price of
the equipment components and goods including charges for design, manufacture,
shop-testing, packing and forwarding and loading into containers / carriers.

1.33 Erection shall mean the putting up of structures and/or installation of plant and
equipment under the Contract by the Contractor and/or under the supervision of the
Contractor and will include any service which the Contractor is required to perform at
the site with his own and/or other staff and/or labour and/or Sub-Contractor for the due
fulfilment of the Contract.

1.34 The term `Erection Portion' of the `Contract Price' shall mean the value of field
activities of the `Works’ including unloading, handling, storage till erection, erection,
commissioning and testing including supervision to be performed at "site" by the
Contractor.

1.35 Final take over will occur when the following are achieved.
a) All supplies and services completed as per contract.
b) Final balance documentation, if any, incorporating latest modifications in as
built drawings has been submitted by the contractor in requisite copies.
c) The contractor has rectified in a definite manner all objections/observations /defects
mentioned in the ‘Provisional acceptance certificate.
d) Successful completion of Performance Guarantee Test for the plant and acceptance
of PG Test Repot submitted.
e) Taking over of the site and the completed works after issue of completion
certificate by the Purchaser.

1.36 ‘Functional tests’ shall mean all activities undertaken after completion of erection and
shall include mechanical and electrical check outs, safety checks, calibration of
instruments and protection devices and such other tests carried out to ensure
functional reliability of various sub-supporting systems.

1.37 Guarantee/ Warranty period shall mean the period of 12 (twelve) months from the date
of provisional take over.

1.38 Words ‘imparting’ person shall include firms, Companies, Corporation, associations or
body of individuals whether incorporated or not. Words imparting masculine gender or
singular number shall also include the feminine gender and plural number and vice-
versa where the context so required or permits.

1.39 ‘Inspector’/ ‘Inspecting Engineer’ shall mean any person or persons, or any firm
nominated by or on behalf of the Purchaser or his duly authorised agent or Consultant
to inspect equipment, supplies, materials or any type of work under the contract.
79

Page 79 of 328
1.40 `Instructions' shall mean any drawings and/or instructions, oral and/or in writing
details, direction and explanations issued by the CONSULTANT or the PURCHASER
from time to time during the `CONTRACT PERIOD'.

1.41 Initial Operation shall mean all operations undertaken as part of “Commissioning” after
completion of “Preliminary Operation” It shall be the first integral operation of the
complete plant/system/ equipment covered under the “Contract” and shall include first
startup on no-load and/or partial load and/or full load runs for PV arrays, inverter and
electrical equipments and gathering of operational data, calibration, setting and
commissioning of control systems, and shut-down inspection and adjustment after
running of the plant/system/equipment covered under the Contract.

1.42 Letter of Award (LOA) shall mean the official communication issued by the owner
notifying legally to the bidder that his bid has been accepted on mutually agreed terms,
conditions and prices.

1.43 Liquidated damages, not as a Penalty, is agreed upon between parties in the Contract
towards time delay. Liquidated damages can also be prefixed towards shortfall in
performance parameters agreed in a Contract.

1.44 Manufacturer shall mean a person firm/company who manufactures and/or produces
Plant, Equipment, Component Spare Parts etc.

1.45 Mechanical Completion shall be defined to be a state of readiness for “Preliminary


Operation” after due erection of all the materials and items of equipment covered under
the scope of the contract.

1.46 ‘Mobilisation’ shall mean establishment as per contract of sufficiently adequate


infrastructure by the Contractor at site inclusive of construction equipment, aides, tools
& tackles, setting up site offices with facilities such as power, water, communication
etc. establishing man power organisation consisting of Resident Engineers, Supervisory
personnel and an adequate strength of skilled, semi-skilled and unskilled workers, who,
with the so established infrastructure shall be in a position to commence execution of
work at site(s), in accordance with the agreed time schedule of completion of works.
‘Mobilisation’ shall be considered to have been achieved if the Contractor is able to
establish infrastructure as indicated above to begin work at site in accordance with
agreed schedule of work to the satisfaction of the Purchaser.

1.47 Month shall mean English Calendar month.

1.48 Notice shall mean any written Notice issued by the owner / Bidder / Contractor.

1.49 A Notice published by the owner with the intention to invite offer/ bid for his
requirements.
1.50 Particulars shall mean the following:
a) Specification
b) Drawing
c) Sealed pattern denoting a pattern sealed and signed by the Inspector.
d) Proprietary make denoting the product of an individual firm.
e) Any other details governing the construction, manufacture, supply and / or
erection as per the Contract.

80

Page 80 of 328
1.51 Performance Guarantee Test shall mean such tests as are prescribed in the Specification
to be done by the Contractor.

1.52 Preliminary Operation shall mean all activities undertaken, as part of


“Commissioning” after “Mechanical Completion” upto commencement of “Initial
Operation” and include mechanical and electrical checkouts, calibration of instrument
and protection devices, commissioning of sub/supporting system of the
plant/system/equipment covered under the Contract.

1.53 Plant, Equipment, Stores, Item or Material shall mean and include plant, equipment,
material, machinery or any part thereof to be provided for and the erection work to be
done by the Contractor under the Contract.

1.54 Price shall mean the price agreed in the contract between the parties towards the scope
of work.

1.56 Project shall mean the project specified in the tender documents and specification.

1.57 Purchaser/Owner shall mean and include NLC India Limited (NLCIL) and its different
functionaries entrusted with the responsibilities in relation to this contract in respect of
the area of responsibilities of such functionaries.

1.58 Provisional take over shall mean acceptance of prima facie and in principle subject to
completion of / fulfilment of certain conditions and entire plant is exporting power to
grid.. This is not a complete acceptance of work entitling the contractor to get full
payment or to assume that all the obligations and terms and conditions of the contract
have been fulfilled to the satisfaction of the Owner / Purchaser.

1.59 Site shall mean the land acquired and set for the location of the project / work.

1.60 Specification shall mean the Technical – Commercial specification including


modification set in the tender / contract documents.

1.61 Sub-contractor means a Contractor selected with the approval of the owner to carry out
certain part of the scope of work.

1.62 Sublet shall mean to let out the work to another.

1.63 Sub-supplier means the supplier selected with the approval of the owner to supply
certain items included in the Scope of Work.

1.64 Supervision shall mean the successive control and directions given by the Contractor in
relation to Contract work during execution of the Contractor’s and/or his sub-
Contractor’s work.

1.65 SUCCESSFUL BIDDER/TENDERER shall mean the bidder whose bid is considered
for acceptance.

1.66 `Supply' shall mean the goods to be supplied by the Contractor under the `Contract'.

1.67 Tender shall mean the bidder’s offer with his terms, conditions, Specifications and
prices to perform the scope of work.

81

Page 81 of 328
1.68 Test shall mean such test / tests stipulated or considered necessary by the Inspecting
Officers.
1.69 Time shall be reckoned by months, weeks, days and hours, month being equivalent to
the Calendar month according to the Gregorian Calendar. The day or days unless
herein otherwise expressly defined shall mean Calendar day or days of 24 hours each.
1.70 Time of completion shall mean the time / period stated / agreed for completing the
scope of work specified in the contract.

1.71 The term `Transport Portion' of the Contract Price shall mean charges on all the
mode of transport envisaged under Contractor's scope including inter-carting
storage at any intermediate point.
1.72 Warranty shall mean Contractor’s assurance to the Purchaser that the goods or property
is or shall be as represented and if not it will be repaired and reconditioned or replaced
by the Contractor at his cost or expenses.

1.73 Weight shall mean the calculation of a load. It is to be stated in ton (1 ton = 1000
kilogram) and / or kilogram (1 Kilogram = 1000 gram).

1.74 Works shall mean plant, non-plant, buildings, Structures, Foundations and all plants,
Equipment, Components to be provided and other construction/ erection services that
the contract requires the contractor to provide.

1.75 Words importing persons shall include firms, Companies, Corporation, Words
importing masculine gender or singular number shall also include the feminine gender
and plural number and vice-versa where the context so requires or permits.
1.76 Terms and expressions not herein defined shall have the same meaning as are assigned
to them in the Indian Sales of Goods Act (1930), failing that in the Indian Contract Act
(1872) and failing that in the General Clauses Act (1897) and such others as mentioned
from time to time.
1.77 `Writing' shall include any manuscript, typewritten or printed statement, under or over
signature and/or seal as the case may be.

1.78 When the words `Approved', `Subject to Approval' `Satisfactory', `Equal to',
`Proper', `Requested', `As requested', `Where directed', `When Directed', `Determined
by', `Accepted', `permitted', or words and phrases of like import are used the
approval, Judgement, direction, etc. is understood to be function of the PURCHASER
or the CONSULTANT.
1.79 The various Acts and Regulations are normally available for sale from the
following address:
`Deputy Controller -Publication Department,
Government of India,
Civil Lines, Delhi - 110 006.

and with leading authorised Government of India book sellers.

82

Page 82 of 328
SCHEDULE- 2
SCOPE OF SUPPLY AND SERVICES
2.1 SCOPE OF WORK:
The scope of work for supply and services Contract includes development of land,
design, engineering, manufacture, inspection at supplier’s works, supply, insurance,
transport, storage, erection, testing and commissioning of 2X10MW(AC) grid
interactive solar PV power project integrated with installed capacity of 8 MWhr. With
½ hr. backup Battery Energy Storage System to feed smoothened power to the grid
with associated 33kV switchyard and grid interconnection at the take off points of
Electricity Department of Andaman & Nicobar Administration (A&NA) with all
accessories at Attam Pahad and Dolly gunj areas in Port Blair, South Andaman.
The scope of work for O&M Contract includes Operation and Maintenance of the
entire system for ten years after one year warranty period.
a. The scope of Design, engineering, manufacture, inspection at supplier’s works,
supply, installation, testing and commissioning shall include
i) Solar PV Power Plant
 Adequate number of Solar PV modules with cables, connectors and
module junction boxes,
 module supporting structures,
 string monitoring and combiner boxes,
 power conditioning units,
 Auxiliary Transformers,
 Switchgears, cables,
 HT switchgear, CT, PT,
 Power Transformers,
 LT panels, protective relays, Control and Metering panels, UPS, DC
system- Battery, Battery chargers to cater the needs of DC loads.
ii) Battery Energy Storage System
 Battery cells /Modules
 Power Conversion System, Battery Management System, Control panels
and HMI interfaces
 Lightning Arrestor, CT, PT, Protective relays, Control and Metering
Panel, Surge Protection devices, Filters etc.
 Panels, Switch gears, cables and distribution boards
 Transformers
 Data communication units
 Auxiliary systems and ventilation systems
 Fire Protection system and suppression system, safety equipments
 Container unit
 Mounting structures
Civil foundation works and platform as per Battery Manufacturer requirement.
Dike structures surrounding the battery units to protect the environment during
ruptures of BESS units if required.
83

Page 83 of 328
iii) Power Export Switchyard
 33KV switchyard equipments,
 SCADA and Energy Management system
 Control room,
 Data/voice communication system,
 33KV transmission lines, towers, Metering station, 33KV cables,
 LT panels, UPS, DC system-Battery, Battery charger (DC loads
required for switchgear),
 Fire protection and suppression system, safety equipments,
 Reactive power control for grid inter connection at the take off points
of Electricity Department of Andaman & Nicobar Administration
(ANA)as per grid requirements.
b. The scope of work includes all cabling, auxiliary power supply and distribution,
lighting, air conditioners, weather monitoring unit, earthing and lightning
protection as defined in the relevant Technical Specification sections.
c. The scope of civil construction work includes land development, removal of trees,
vegetation removal, site survey, soil investigation, site preparation, Site grading,
fencing, foundations for Solar PV module mounting structures, RCC building for
Power Collection Sub Stations, construction of 33KV Power Export switchyard
and RCC Building for control room, approach roads, internal roads, peripheral
roads, path ways, cable trenches, drains, Main Gate and security buildings &
watch towers, Sign Board, etc. as defined in the relevant Technical Specification
sections.
d. The Scope of work also includes facilities for arrangement, storage, construction
as well as O&M water supply, Module water washing network system with proper
drainage/ sewage system and disposal and construction power supply.
e. The scope of work shall also include the following :
i. Furnishing of all relevant drawings, data sheets, technical catalogues of
equipments / devices, QAP, MQP, FQP, type test certificates, Inspection
reports etc. as required for construction and O & M of the Solar Power Project.
ii. Supply of all spares, Consumable materials, replacements, tools and tackles
and accessories etc. which are necessary or useful for satisfactory and trouble-
free operation and maintenance of the plant during the entire period of O&M of
ten years.
f. The works to be performed on all equipment and accessories shall include but not
limited to the following:
i. Insurance, Transportation, unloading, receiving and storage at site.
ii. Arranging to repair and/or re-order all damaged or short-supply items.

84

Page 84 of 328
iii. Final check-up of equipment, erection, testing and commissioning and putting
the entire system including the power evacuation facility into successful
operation.
g. The scope of work shall also include coordination activities with respect to Grid
connectivity and establishing Energy Management Centre being implemented by
A&N Administration Electricity Department, system study, alteration required in
the grid take off points of the existing Panther I and Panther II feeders towers,
termination and support structures, gantries etc.
Scope of Supply
Plant & Equipment
The scope of supplies and services of the Contractor for Plant and Equipment is
described in Technical Specification and the relevant Annexure subject to General
Terms and Conditions of Contract in Schedule-10.
Scope of Services
Technical Services
The Contractor shall be responsible for the following services including those Services
stipulated elsewhere in the Tender Specification:
a) Detailed design and engineering
b) Technical services related to planning, procurement, manufacturing, inspection,
expediting, packing, shipping, storing, etc.
c) Project management services and complete feedback of data and information to
Purchaser regarding Contractor's scope of supply and services.
d) Time bound project co-ordination relating to transportation, insurance, claim
settlement, inspection, construction planning and scheduling, erection planning, field
construction engineering, testing, start up, trial run, commissioning and performance
guarantee tests. The Contractor shall bring his own/Sub-contractor/Sub-vendor
Specialists for the performance of the above mentioned works.
e) Total day to day supervision of construction including erection and specialised services,
if any.
f) Technical consultation/liaison/guidance relating to detail design and plant engineering
by its sub-contractors.
g) Quality control and adherence to the time schedule control of site work and other
works.
h) Start-up trial runs and commissioning services.
i) Demonstration of performance guarantee tests by deputing commissioning
engineers/specialists.
j) Clearance for installations including power evacuation system from the statutory and
other concerned authorities on behalf of Purchaser. The Contractor shall also assist in
preparing application forms, providing necessary drawings, documents, test certificates
etc., including necessary co-ordination with statutory and other concerned authorities.
k) Submission of complete as built drawings/documents, O&M Manuals etc., approved by
NLCIL. .
The Contractor shall be responsible for supply of all the drawings and technical documents &
information in respect of the plant & equipment. The Contractor shall deliver the drawings,
technical documents and information to the Purchaser and their authorized agency.

85

Page 85 of 328
Supervision

The Contractor shall depute Technical personnel/ Specialists from various disciplines for
the supervision of construction work under his scope of work. The above mentioned
Technical personnel/Specialists shall supervise the construction and commissioning of the
project so as to establish to the Purchaser that the guarantees as agreed by the Contractor
are fully met.
Construction & Erection Works

1. The Contractor shall provide all necessary construction and erection tools & tackles,
small hand tools, instruments, all commissioning instruments, bolts, nuts, washers, jigs
and fixtures, winches, alignment tools etc. and the material handling equipments such
as cranes, hoists etc., welding equipment and accessories, measuring instruments,
temporary supports and staging, consumables (e.g. welding gas, electrodes etc),
erection packs etc for erection of steel structures, and other equipment which may be
required for carrying out the construction and erection work efficiently within the time
schedule provided herein in the Contract. The Contractor shall ensure that proper
documentation is followed at entry gate of the premises for such items which shall be
carried back by Contractor after completion of work.

2. The Contractor shall carry out any and all such works, as may be required, to build the
project complete in all aspects as per the Contract Specification.

3. The Contractor shall make all necessary arrangements to deliver the equipment at the
project site by wagons/trucks/trailers/Light motor vehicles/lorries/ships/boats etc build
his own stores (covered, uncovered, air-conditioned, if necessary) for the proper storage
of equipment, maintain the stores and all related documents and records, transport the
equipment to site for erection purpose. Necessary security arrangements also shall be
made by the Contractor. Arrangements shall be made available by the contractor for
construction of stores and construction site office, labour colony, etc.
4. The Contractor shall be responsible for proper and neat storage and also undertake
conservation of all consignments including damaged boxes. During storage of
equipment, the Contractor shall take into account deterioration and carry out the re-
conservation of the complete equipment/parts/supplies as may be necessary as per the
storage instructions of the Manufacturer of equipment/components. The Contractor
shall also supply the consumables required for such re-conservation work and
repair/replace parts required thereof for the proper functioning of the equipment after
erection and commissioning.
5. The Contractor shall unpack and do visual checking against physical damages to the
equipment/cases, clean equipment before start of erection. Damage/ shortage, if any,
will be reported to the Purchaser and shall be rectified/replaced expeditiously, so as not
to upset the erection and commissioning schedule. Delay on account of settlement of
insurance claims by the Contractor shall not be considered as an excuse for delay in
completion of erection and commissioning.
6. The Contractor shall provide all necessary erection equipments including material
handling equipment such as cranes and hoists, compressors and other equipment and
instruments and consumables, all commissioning equipment and instruments, welding
equipment, winches, alignment tools, precision levels, the odolite, etc. which may be
required for carrying out the erection and commissioning work efficiently. All
instruments shall be properly calibrated before use. Unless otherwise specified, the
86

Page 86 of 328
above erection equipment/ materials shall be the property of the Contractor. However,
Purchaser's prior permission shall be required for removal of these erection equipment/
materials from the site. The Contractor shall ensure that proper documentation is
followed at entry gate for such items which shall be carried back by Contractor after
completion of work.
7. The Contractor shall provide all temporary ladders, scaffolding materials, platforms,
supports and other necessary facilities required for handling, erection, testing and visual
inspection of supplies at the point of installation and shall also provide necessary
packing plates, wedges, shims, leveling screws etc. required for erection of equipment
and structures.

8. The Contractor shall provide erection consumables like oxygen gas, acetylene gas,
argon gas, welding rods, filler wire, solder lugs, oil, grease, kerosene, cotton waste, etc.
required for erection of equipment and steel structures and required items for
commissioning activities.

9. The Contractor shall erect and maintain his own site offices and stores, as required for
the work and arrange for proper house-keeping and up-keep of the area.
10. The Contractor shall provide sufficient fencing/barricade, notice boards, signage and
lighting to protect and warn others as may be considered necessary by the Purchaser.
All materials used for providing these facilities shall be the property of the Contractor.
11. The Contractor shall mobilise adequate material handling equipment such as mobile
cranes, forklifts, trailers, dozers, winches etc in addition to other erection tools &
consumables keeping in view the erection schedule. The Contractor shall provide as per
time schedule from the date of Letter of Award, his scheme for mobilisation with Bar
Chart indicating clearly the resources, manpower and machinery proposed to be
deployed to ensure timely completion of work and quality of workmanship.
12. Underground services, if any to be diverted / protected shall be the responsibility of the
Contractor and shall be informed to the Purchaser. Approval from authorities required
for such works shall be obtained by the contractor. The compensation / statutory
payments if any for such works shall be borne by the contractor.
13. The Contractor shall organise the work in such a manner that work being carried out
simultaneously at site is not impeded and the workmen not endangered and shall
arrange all temporary access as required for the erection work.
14. The Contractor shall carry out base/primer and final painting of all Plant & Equipment,
Structures, Pipelines, etc. supplied. The painting including its process shall be carried
out as specified in the detailed technical specification. Where not specified, the same
shall be as per the standard codes & practices normally applicable and adopted
internationally for the type of Plant & Equipment offered.
15. Grouting of the equipment and steel structures on the foundations with approved non-
shrink-grouting compound shall be the responsibility of the Contractor. The grouting
materials shall be supplied by the Contractor.
16. All safety, health and pollution control measures as required to be adopted as per the
statutory regulations, guidelines, etc., The safety codes for projects issued along with
the tender or otherwise required or implied by local statutory regulations or practices
shall be strictly followed by the Contractor during the entire duration of execution of
the Contract. The Contractor shall set up a suitable safety organization of its own at
site, in this regard.

87

Page 87 of 328
17. The Contractor shall not dispose of, transport or withdraw any tools, tackles,
equipment, and material provided by him for the "contract" without taking prior written
approval from the Purchaser.

Demonstration of Performance Guarantee

The Contractor shall undertake Performance Guarantee (PG) Test as defined in the relevant
clauses of the technical specification. In case the Contractor fails to demonstrate and prove
the Performance Guarantees and achieve the results as agreed in this Contract, the
Contractor shall rectify the Plant and Equipment and demonstrate the performance
guarantees failing which the Purchaser’s option of either to reject the equipment or to levy
LD will be exercised.

Water for Construction and for O & M

1. Water for Construction and for O & M shall be arranged at each location of project site by
the contractor. All payments towards arrangement and supply of water shall be borne by
the contractor. The Contractor shall make his own arrangements to lay and maintain
necessary distribution lines at his own cost. The contractor shall arrange for storage sumps,
pumps and distribution piping to various locations within the solar power plant. The
Contractor shall be responsible to store water in sufficient quantity to meet its requirements
in well built covered/protected water storage tanks / sumps.

The Contractor shall ensure that there is no wastage of water. He will also be responsible
for maintaining the taps, pipe lines etc. in proper condition. The Contractor shall obtain
prior approval of the Purchaser of his distribution scheme before laying the pipelines. Non
availability of water in the project site shall not be excuse for delay in completion of
Project. The contractor may at his own cost arrange suitable backup water supply.
Construction Power

1. The Contractor shall arrange construction power for the purpose of the construction and
erection for each location of project site /sites. All payments towards availing power
supply and usage charges and deposits shall be borne by the contractor. The Contractor
shall make his own arrangements for further distribution. The Contractor shall make his
own arrangements to lay and maintain necessary supply lines for temporary power. All
temporary wiring must comply with local regulations and relevant Indian Electrical Act
and will be subject to the Purchaser's inspection and approval before connection to supply
and later. Non-availability of power shall not be an excuse for delay in completion of
erection construction. Contractor may at his own cost arrange suitable back-up power.
2. The Contractor shall supply and install all distribution cables, wires and switches etc. of
rated capacity for the commencement of work from the source of power at his own cost.
The contractor shall employ Electricians having valid Electrical License for carrying out
the installations as well as for the maintenance works.
3. The Contractor shall facilitate the Purchaser or his authorised representative for inspecting
his temporary electrical installation as and when required. The Contractor will
immediately attend to the defects so pointed out during this inspection including
replacement of faulty cables, switches etc.
4. The Contractor shall be responsible for all damages, losses etc. due to fire or otherwise if it
is due to his negligence, improper installation, operation and/or maintenance of his part of
installations.

88

Page 88 of 328
Codes and Standards

All works to be executed and/or engineering services and technical services to be rendered
under this Contract, shall be completed in the manner set out in this Contract and in
accordance with the specified codes, Standards and best trade/ engineering practices.
Wherever the codes are not mentioned or in case of code discrepancies, relevant Indian
Standards / International Standards approved by Purchaser shall be followed.
Total Responsibility

The Contractor shall be solely responsible for the entire supplies, engineering services and
technical services, irrespective of whether supplies and services have been made/ rendered
by him directly or by his Sub-Contractor/ sub-vendors or all associates of this contract.

General

a) The bidder is required to carefully examine the Technical & General Specification,
Terms and Conditions of Draft Contract, drawings and other details relating to work as
given in the Tender Document and fully acquaint himself as to all conditions and
matters which may in any way affect the work or the cost thereof. The bidder shall be
deemed to have on his own and independently obtained all necessary information for
the purpose of preparing the Bid and his bid as accepted shall be deemed to have taken
into account all contingencies as may arise due to such information or lack of the same.

b) The bidder shall be deemed to have exhaustively examined the Tender documents
including the Draft Contract, to have obtained all information and clarifications on all
matters whatsoever that might affect the carrying out of the work and to have satisfied
himself as to the adequacy of his Bid. He is deemed to have known the scope, nature
and magnitude of the work and the requirements of materials and labour involved etc.
and as to all work he has to complete in accordance with the Contract whatever be the
defects, omissions or errors that may be found in the Tender/Bid Documents.

c) The bidder shall be deemed to have acquainted himself with the Indian Income Tax
Act, 1961, Indian Companies Act, 1956, Indian Customs Act, 1962, Indian Electricity
Act, CEA rules, A&N Electricity rules, CERC/JERC regulations, A&N regulations,
grid codes. MNRE guidelines, Factories Act, Pollution Control Regulation and other
related Acts & Laws prevalent in India and as amended from time to time. The
Purchaser shall not entertain any request for clarifications from the bidder regarding
such local conditions.
d) Any neglect or omission or failure on the part of the bidder in obtaining necessary and
reliable information as stated above or on any other matter affecting the bidder shall not
relieve him from any risks or liabilities or the entire responsibility of completion of the
work in accordance with the Contract.

Surplus materials and scrap

a) Surplus materials / defective materials available after commissioning of the project


shall be taken back free of cost by the Contractor with prior approval of the Purchaser.
The cost of removal shall be borne by the Contractor.
b) Contractor shall take back all crates, packing cases, all packing materials including
steel packing materials and other scrap materials then and there to keep the site free
from scraps.
89

Page 89 of 328
c) No imported material shall be allowed to be taken out other than imported tools and
tackles and instruments brought by the Contractor on draw back basis, provided he has
carried out necessary documentation at the time of bringing such items inside the Plant.
d) Replacements/ Disposal of materials during construction as well as O&M shall be
carried out by the contractor with utmost care without affecting the environment and all
the scrap shall be taken out by the contractor and shall be disposed as per the standards
and prevailing practices norms of A&N Islands.
e) Necessary permission from concerned authorities shall be obtained for disposal of any
item within the Island.

90

Page 90 of 328
SCHEDULE-3
3.0 CONTRACT PRICE:
3.1 The contract price shall be paid in currency or currencies in which the price has been
quoted. The contract price shall be firm till completion of contract period.
3.2 The total lumpsum prices quoted by the Contractor in his bid with additions and
deletions as may be agreed to before award of Letter of Award/ Contract, for the entire
scope of work, viz., design, manufacture, supply transportation, insurance, storage
Erection, commissioning and testing of the equipment etc. covered by detailed scope of
work of contract and in accordance with all terms, conditions, stipulations,
specifications, requirements and other conditions of the Contract and incorporated in
the Price Schedule and documents shall be treated as the Contract Price.
3.3 The Contract Price shall be deemed interalia to include and cover the cost of
deployment of construction equipment, temporary works, establishment of labour
camp, all materials and supplies, labour, insurance, fuel, stores, appliances, security
arrangements, safety and fire fighting arrangements (including those required
during construction, storage and erection) to be supplied/used by the Contractor and all
such other materials and services and actions that may be necessary or derived
or statutorily required in connection with the execution of the works as per the
Contract or any portion thereof complete in every respect and maintained as
detailed in the contract documents or as may be required in terms of the
Contract.
3.4 The Contract Price shall be deemed to include and cover the cost of all royalty and fees
for all articles, and processes, protected by letters patent or otherwise incorporated
in or used in connection with the work, also all royalties, rents and other payments
in connection with obtaining all materials for the work and the Contractor shall
indemnify and keep indemnified the Purchaser, which indemnity, the Contractor
hereby gives against all actions, proceedings, claims, damages, costs and
expenses arising from the incorporation in or use of work of any such articles,
processes or supplies.
3.5 Single Contract or Separate Contracts for Supplies, Services, Maintenance during
warranty period etc., may be entered with. However, the Separate Contacts shall have
necessary provisions to take care of Single Bidder responsibility, Liquidated Damages
(LD), Purchaser’s right to recover dues including LD from payment due under any of
the contracts, warranty and Performance Guarantee etc.,
In view of the above, any liabilities arising out of such Separate Contracts shall be
borne by the bidder/Contractors
However separate contracts will be entered in to for ten years operation and
maintenance.
3.6 The contract price shall be firm till completion of the contract period.
3.7 Contract Price Break-up
3.7.1 The Contract Price indicated in the Price Schedule shall be for the scope of work
and services detailed under scope covered under technical specification and for all
the contractual obligations of the Contractor if any, under the Contract.
3.7.2 The Contractor shall furnish the detailed billing break-up for each item for the
approval of Purchaser, which after the approval only, will be the basis for submission
of invoices for progress of payments.

91

Page 91 of 328
SCHEDULE-4
TIME SCHEDULE
4.1 TIME SCHDULE- Firm and Binding:
The basic considerations and the essence of the `Contract’ shall be the strict adherence
to the time schedule for performing the works in the contract. The time and the date of
completion of the project activities as stipulated in the Time Schedule of Tender
specification and accepted by the Purchaser shall be deemed to be the essence of the
Contract. The Contractor shall so organise his resources and perform this work as to
complete it not later than the date agreed to. The time to complete the Works contracted
for shall be reckoned from the date of issue of the “Letter of Award” to the
Contractor.

4.1.1Completion Time:
The contractor shall complete the design, engineering, manufacture, Inspection at
supplier’s works, supply, insurance, transport, storage, erection, testing and
commissioning of 2x10 MW (AC) grid interactive solar PV power project integrated
with installed capacity 8MWhr with ½ hr. backup BESS to feed smoothened power to
the grid associated 33 KV switchyard and grid interconnection at the takeoff points of
Electricity Department of Andaman & Nicobar Administration within 18 months from
the date of issue of LOA.

4.2 TIME SCHEDULE FOR SUBMISSION OF PROJECT DATA, DRAWINGS


AND DOCUMENTS:
4.2.1 The Contractor shall submit the various drawings and documents listed in
Technical Specification. Minimum four numbers of hard copies shall be submitted for
NLCIL approval. Additional copies, if any, required by Purchaser shall be furnished by
the Contractor, without any extra cost. The Contractor shall supply all
drawings/documents and the drawings/documents supplied will be the property of
Purchaser. In addition to hard copies, soft copy of all drawing/ documents shall be
submitted by the Contractor through NLCIL mail, details of which will be furnished
after issue of LOA.

Within one month from the date of issue of Letter of Award, the Contractor shall
submit to the Purchaser the list of all drawings and documents by title, using the
approved numbering system and indicating the schedule of submission of
drawings in conformity with the time schedule. This list of submission and approval
shall be updated and submitted by the Contractor at the end of every month.

4.2.2 All the drawings and documents shall be prepared in accordance with contractual
requirements and also as per the best engineering practices. Approval in respect of
drawings shall be accorded by the Purchaser within two weeks of receipt of the same.
In case drawing is not complete and/or is not approved, the comments shall be
furnished to the Contractor within two weeks of receipt of drawing. Any
submission with gross omissions and/or errors will not be considered as a valid
submission. If any document/drawing were commented by Purchaser, the Contractor
has to incorporate the comments and resubmit the document within one week for
approval by the Purchaser. This review and / or approval of the drawings by the
Purchaser will not relieve the contractor of any of his responsibilities under this
contract.

92

Page 92 of 328
4.2.3 The sequence of submission of feedback data, delivery of structural, mechanical
equipment and electrical equipment, instrumentation, submission of erection instruction
and erection drawings and other supplies and services by the Contractor shall be as per
the L1 PERT network schedule.

4.3 PERT NETWORK

4.3.1 Level-I PERT network of the project (submitted along with the bid) shall be
resubmitted by the Contractor for NLCIL approval and finalised within one month
from the date of Letter of Award. The approved L- 1 PERT will be annexed to at the
end of this schedule in the contract document.

4.3.2 Detailed Level-2 PERT network of all systems/sub systems/ discipline/ equipment etc.
incorporating activity-wise quantity shall be submitted and finalised within three
months from the date of Letter of Award. These-detailed networks shall be prepared
based on the milestones reflected in Level-I network, which shall be the basis for
performance of the Contract. The salient activities and their time schedule for the
project shall be as follows:

Sl No Description of Time Schedule Number of months from


LOA
1 Issue of LOA – Zero Date D
2 Land development and Site preparation for D+6
the entire project
3 Approval of all major Drawings D+9
4 Completion of all supplies D+14
5 Completion of Erection and Interconnection D+16
of all equipment and system for the entire
project including Power Export, Switchyard,
SCADA and ENS
6 Completion of Commissioning and exporting D+18
power to grid by capacity of the entire plant

4.3.3 The Contractor shall submit detailed construction resource planning along with Level-2
networks.
4.3.4 The Contractor shall submit estimates of quantities/volume of work sub-system
wise, discipline wise, list and weights of equipment
(mechanical/electrical/instrumentation) etc during execution stage as per requirement.
4.3.5 All PERT network shall be furnished in MS Projects both in Hard copies and
Softcopies.
4.3.6 Detailed assignment schedules of foreign specialists Experts for rendering
technical services shall be submitted by the Contractor for the approval of the Purchaser
within three months from the date of Letter of Award. The bio-data of key
personnel shall be submitted within one month from the date of Letter of Award
and for others, within three months before their deputation.
4.3.7 Drawings of equipments shall be supplied at least one month before the shipment of the
equipment.
4.3.8 All “as built drawings” shall be submitted by the Contractor before Final Take Over.

93

Page 93 of 328
4.3.9 Erection Instructions for the Plant and Equipment shall be submitted by the Contractor
at least one month before the shipment of the respective Plant & Equipment.
4.3.10 The delivery of equipment shall be deemed to be completed when all equipment
and drawings/documentations have been supplied by the Contractor.
4.3.11 Erection of the system / equipment shall be deemed to be completed when all
equipment for the normal functioning of the plant / system are erected at site.
4.3.12 Completion of successful commissioning of the system/ equipment shall be deemed to
have taken place when the system/ equipment has been successfully commissioned as
per relevant Clauses of Schedule-10.
4.3.13 Demonstration of performance guarantee tests shall be deemed to have completed when
the Contractor has demonstrated and has achieved PG parameters as per Technical
Specification and Schedule-9.
4.3.14 The Contractor shall render timely and adequate technical services through his
Specialists to ensure completion of entire work and demonstration of performance
guarantee tests.
4.3.15 The Contractor shall prepare and submit in a time bound manner necessary drawings of
proper standard with best engineering practices. The Contractor shall be responsible for
obtaining timely approval of the drawings from the Purchaser to ensure completion of
work within the time schedule. Any delay due to incomplete submission and
consequent delay in approval shall be to the account of the Contractor. The Contractor
shall not claim any time extension on this ground.
4.3.16 The Contractor shall ensure to send all letters with authentication through FAX/E-mail
and a confirmation copy of the same through courier/Speed Post/Hand delivery. All
drawings and documents shall be sent through Courier/ Speed Post/Hand delivery.
4.4DELIVERY OF EQUIPMENTS, ITEMS ETC.
The delivery periods shall be reckoned from the date of Letter of Award.
4.4.1 The delivery of imported equipment and components including the foundation bolts and
inserts in respect of the plant and equipment shall be completed on FOB basis, as
given in the Overall time schedule.
4.4.2 Delivery of all indigenous equipments, and items shall be completed on FOR site basis
as given in the Overall Time schedule.
4.4.3 Delivery of all supplies shall be made strictly in sequence of erection at site
unless otherwise differently agreed to by Purchaser.
4.5MAINTAINING SPARES
The required spares shall be maintained and shall be dispatched along with the
consignment of the respective equipment. The required Mandatory spares shall be
maintained by the contractor at the stores after the Provisional Takeover.

4.5 DELIVERY OFENGINEERING SERVICES


The delivery of the engineering services, drawings and documents will be completed as
per the time schedule mentioned herein before and will be delivered to the Purchaser.

4.7 Liquidated Damages for Delay:


The time stipulated in the Contract shall be deemed to be the essence of the Contract.
Incase the Contractor fails to adhere to the time specified in the Contract
Clause 4.1.1, then L.D. will be levied by the Purchaser.

94

Page 94 of 328
4.7.1 If the satisfactory commissioning of the entire capacity of the integrated system in the
manner prescribed is delayed beyond the stipulated dates, Liquidated Damages shall be
payable at the rate of 0.5% per week of delay or part thereof of supply and services
subject to a ceiling of 10% of the total value of contract for supply & services.

4.7.2 If the reason for the delay is solely attributable to the Purchaser, adequate time
extension will be given to the Contractor to the extent of delay attributable to
the Purchaser. Further in any delay in commissioning attributable to the contractor, the
losses incurred by NLCIL due to the withdrawal of subsidiary by GOI shall
compensated by the contractor.

4.7.3 If the reason for the delay is purely attributable to the Contractor, L.D. will be levied,
and extension of time may be granted.

4.7.4 If the decision regarding the reasons for the delay is required to be analysed
and the same can only be determined after completion of the work or if the
issue is likely to enter into dispute or requires in-depth study to fix the responsibility
for the delay, then extension of time will be given to the Contractor subject to levy of
L.D. if considered necessary. However, as a precaution the amount equivalent to
the maximum L.D. leviable would be withheld from the running bills at the
stage where the balance payment may not be able to cover the L.D. and other
obligations as per the provisions of the Contract.
4.7.5 In case this arrangement causes difficulty to the Contractor in cash flow and progress of
work, an amount up to 90% of the withheld amount can be released to the Contractor
against suitable Bank Guarantee for 100% of the withheld amount if requested
by Contractor.
4.7.6 However, 90% of the withheld/ leviable Liquidated Damage amount may be considered
by the Purchaser for release against submission and acceptance of LDBG as per
the format enclosed for 100% of the leviable LD amount.
4.8 Liquidated Damages for shortfall in Performance Guarantee values
For non-fulfilment of Performance Guarantee values the LD will be levied as indicated
in the Technical Specification.
4.9 Total Liability for Delay &shortfall in Performance Guarantee (PG) Values The
liquidated damages for (1) delay in commissioning (2)non-fulfilment of performance
guarantee values are independent and shall be applied separately. However, the
total liability of the Contractor towards delays and for shortfall in Performance shall be
limited to 17.5% of the total value of contract for supply & services.
4.9.1 The Purchaser may without prejudice to any method of recovery deduct the amount for
such Liquidated damages from any amount due or become due to the Contractor either
under this or any other Contract. Payment of Liquidated Damages shall in no
way relieve the Contractor from his Contractual obligations to complete the works or
from any of the obligations under this Contract. Any delay in the levy or recovery
of LD shall not constitute waiver of the right of the Purchaser under the Contract
towards levy and recovery of LD.

95

Page 95 of 328
4.10 IMPLEMENTATION STRATEGY
4.10.1 Time Schedule
The heads to be covered in the L1 PERT network schedules broadly are:
Submission of basic engineering and approval, issue of ordering specifications,
placement of orders of equipment, submission and approval of drawings for
Mechanical/ Electrical/Instrumentation equipment, etc. manufacture and supply of
equipment, civil and structural works, submission of erection drawings and
manuals, erection of mechanical/electrical equipment, testing and commissioning
etc. The major milestones for the principal items are to be highlighted in the
schedule.
4.10.2 The Contractor shall submit:
i) Level- 2 PERT network schedule including details of pre-construction activities and
execution work.
ii) Estimates of quantities/volume of work and other details such as list of
specifications, list of drawings, quantum of work discipline wise, list of
equipment (mechanical/ electrical/instrumentation) etc.
iii) Updated level II networks along with progress reports (formats to be mutually
finalised) shall be furnished as and when required.
4.11 CONSTRUCTION/ERECTION PLAN
4.11.1 The Contractor shall submit a write-up for construction/erection plan for the
plant &equipment under his scope of supply.
i. The plan will indicate a broad outline:
ii. The construction/erection techniques to be employed.
iii. Resource planning for deployment of construction / erection of
equipment/machineries.
iv. List of various construction equipment such as cranes, dumpers, etc. planned to be
mobilized with quantity & rated capacity/specification.
v. List of machinery, tools and tackles such as welding transformers, welding
generators/sets, gas cutting sets, drilling machines, chain pulley blocks, survey
instruments, etc. and indicate specification and quantity of each item
4.11.2 Deployment of manpower
The Contractor shall submit a list showing deployment of manpower of the
following categories indicating number of personnel, schedule and duration of
their posting at site, educational background, and experience.
i) Engineers to be engaged for design and engineering coordination, follow up and
expediting.
ii) Engineers and supervisors are to be directly attached to site work i.e.
civil construction, erection, testing, commissioning and demonstration of
performance guarantee values.
iii) Organization for implementation of the project.
4.12 PROGRESS MONITORING
4.12.1 It is proposed to have an effective system of progress monitoring to ensure
timely completion of all project activities. The guidelines laid down herein shall
ensure progress monitoring by the Purchaser.

96

Page 96 of 328
4.12.2 The intention is to dwell upon the progress of the activities related to
Engineering Procurement, Manufacturing, Dispatch, Site Erection, testing,
Commissioning and PG Test.
4.12.3 In the interest of the timely completion of the project, the area of monitoring can be
altered in consultation by the Purchaser with the Contractor. The Contractor shall
furnish adequate information in the monthly progress reports on the formats to
be mutually agreed upon. The Contractor shall submit the requisite no. of progress
reports in five (5) copies.

4.12.4 The Purchaser will invite the Contractor for monthly/fortnightly meetings to
review the progress of each activity, and depute Purchaser’s authorized
representatives for ascertaining/ expediting progress at Contractor’s works and
suggest remedial actions to bridge-up time gap if any between planned progress and
observed progress.
4.12.5 Progress report
a) A monthly progress report with exception report showing current status
of various activities including status of ordered/yet to be ordered items
shall be submitted to the Purchaser by the Contractor in five hard copies,
referring to the schedule of order, reasons for not achieving it and
remedial measures proposed.
b) The Contractor shall submit programme of execution both in the form of
activities in ‘Network’ as well as quantitative programme in terms of
month wise physical targets for various disciplines of work.
c) The Contractor shall submit computerised updated time analysis report every
month along with progress report. The updated PERT network drawing (both
Level I and Level II) are to be submitted in requisite no. of copies at
least once in every month. The format of the submission are to be mutually
discussed and agreed.
d) The monthly progress report shall indicate progress of activities again
sttargeted dates and targeted quantities in proforma as per the
requirement of the Contract for maintaining consistency of reporting and
for maintaining database by the Purchaser. Reasons for shortfalls, if any,
shall be clearly brought out and proposed remedial measures to arrest the
delays shall be indicated by the Contractor in the progress report, wherever
applicable.
e) Quantitative programme which is termed as “Work Plan” shall be
updated regularly at a mutually agreed interval of time and Principal Contractor
shall submit the same for Purchaser’s approval keeping in view the
balance time available to execute the balance of activities. Once if
approved, subsequent progress report shall indicate the revised targets.
f) The Contractor shall furnish information on site activities viz. daily progress
report, weekly receipt of equipment, monthly erection plan, etc. The Contractor
has also to indicate resource deployment at site, highlights of critical
areas and constraints in the daily progress report once in a week.
g) Other information related to site activities as may be required by the
Purchaser, shall also be submitted by the Contractor.
h) The Contractor shall submit progress photographs in 5 copies and also in
a Compact Disc (CD) every month relating to the progress in sequence of work
of all major site activities. The Purchaser will arrange necessary permission
for the same.

97

Page 97 of 328
i) The progress report will also highlight inspection status. The Contractor shall
submit one copy of the inspection certificate duly signed by
representatives/authorized agencies after inspection along with the progress
report.
4.13 OVERALL TIME SCHEDULE
The overall time schedule shall be as follows:
1. The time schedule for the scope of work up to commissioning shall be 18
months.
2. The time schedule for PG test shall be one year after provisional take over
which shall be in concurrence with one year warranty period O & M.
3. After successful completion of PG test and final take over, O & M shall be
carried out for balance 10 years.
After completion of above overall time schedule, entire system shall be handed over
to NLCIL in working condition.
4.14 EXTENSION OF TIME
4.14.1 The Contractor shall not be allowed for any extension of time for completion
except in the following cases:
i) Force Majeure – As per details stated in the Contract.
ii) Major changes or substantial addition to work ordered by the Purchaser
adversely affecting the completion time.
iii) Any other circumstance of any kind whatsoever which may occur making
the Contractor entitled to an extension of time which, however, shall be in the
absolute discretion of the Purchaser.
4.14.2 The Contractor, upon the happening of any such event as stated above shall
immediately inform the Purchaser but nevertheless use constantly his best endeavors
to prevent or make good the delay and shall do all that may be reasonably
required to the satisfaction of the Purchaser to proceed with the work.
4.14.3 Request for extension of time shall be submitted by the Contractor in writing
and the Purchaser, based on the merit, shall consider the request and convey his
decision to the Contractor in writing within a reasonable time.
4.14.4 The Contractor shall not be eligible for any extension of time on account of any
delay in procurement of materials.

98

Page 98 of 328
SCHEDULE- 5
5.0 TAXES & DUTIES

5.1 GST/CD

i. GST wherever applicable shall be paid at actuals subject to ceiling indicated in


the schedule of price
ii. Any statutory variation on account of GST/Customs Duty arising beyond
delivery schedule shall not be payable for the reasons directly attributable to
contractor.

(a)any statutory variation on


account of GST arising between the date of submission of offer by the
Contractor and scheduled date of completion of supplies can be allowed for the
supplies made within the scheduled delivery period based on the rates
prevailing on the dates of supply.

(b)If there is any delay in supplies due to Contractor’s fault, the rate prevailing
on the scheduled date of completion of supplies will apply for the belated
supplies and upward revision after the scheduled date will be to the
Contractor’s account.

iii. Details of items, tariff no. with break-up values for despatches shall be
indicated separately in the PRICE SCHEDULE with rate of taxes in percentage
and total amount of taxes.

Any benefits arising out of application of GST shall be passed on to Purchaser


in full. Final claim will be settled only after certification by Chartered
Accountants that all benefits arising out of GST have been passed on to the
Purchaser.
Statutory variations due to imposition of new taxes, duties and levies or
reduction/ withdrawal of existing taxes, duties and levies by the Central or
State Government as may be applicable on the supply of Plant and Equipment
etc., shall be to Purchaser’s account to the extent applicable as direct liability
of the Indian Contractor in execution of this Contract with the Purchaser. In
the case of any upward revision, the same shall be reimbursed by the Purchaser
which shall not be within the ceiling quoted subject to production of relevant
documentary evidence. However, the same will be limited to the Contractual
delivery period/ execution schedule.

5.1.1 Customs Duty if any, shall be reimbursed at actuals subject to ceiling indicated in the
schedule of price. However, the purchaser shall not be liable to clear the goods at Port.

5.2 GST
The Contractor shall register with statutory / tax authorities wherever required.
i. The Supplier / Contractor has to provide a copy of the GST Registration Certificate and
also mention their GST Registration No. and Date in each of their invoices / bills without
fail. No invoice or bill will be paid unless the GST Registration No. is mentioned
therein.
99

Page 99 of 328
ii. While claiming the GST payment, the contractor should furnish the requisite details in the
invoice as per statutory requirements

5.5 Direct Tax (Income Tax):

5.5.1 The Purchaser shall not be liable towards income tax of whatever nature including
variations, arising out of this Contract, as well as tax liability of the Contractor and
his personnel. Deduction of tax at source at the prevailing rate shall be effected by the
Purchaser before remittance as a statutory obligation. The Certificate for the tax
deducted at source shall be furnished by the Purchaser indicating the amounts deducted.

5.6 Personal Income Tax and Cess:

5.6.1 Income tax and cess, if any payable by the Contractor's / Sub-contractor's employees
shall be paid by the said employees directly and the purchaser shall not be liable to pay
the income tax and cess payable by the employees of the Contractor/ Sub-Contractor
and the purchaser is not responsible for filing the tax return of the Contractor's
employees/experts. The Purchaser is not responsible for any tax arrears of Contractors
employees who have been associating their service, towards this scope of work on any
circumstances whether they are in service or otherwise.

5.7 Customs duties, Port handling, clearance and forwarding

5.7.1 For imported supplies on F.O.B. basis Customs Duty, Port handling, clearance and
forwarding if any, shall be reimbursed at actuals subject to ceiling indicated in the
schedule of price. However the purchaser shall not be liable to pay such charges in
respect of items supplied by the Contractor on free of charge basis. For the domestic
supplies all charges regarding customs duties, if any, shall be to the account of the
Contractor.

5.7.2 The Purchaser shall bear any statutory variation (±) in CD tariff rate (i.e. between the
CD rate prevailed at the time of submission of the offer and the CD rate paid at the time
of actual imports) and also the variation in CD due to exchange rate fluctuation (i.e
between the Exchange rate prevailed at the time of submission of offer and the
Exchange rate prevailed at the time of actual imports). The variation (±) in CD tariff
rate and variation in CD due to exchange rate fluctuation will be regulated based on the
Bill of Entries of actual imports made by the Contractor and the variation will be
considered for the imports made within the agreed delivery schedule.

100

Page 100 of 328


SCHEDULE- 6

6.0 TERMS OF PAYMENT:

6.1.1 GENERAL PROCEDURE:

The payment to the Contractor for the supply, services & works under the Contract
will be made by the Purchaser as per the guidelines and conditions specified herein.
All payments made during the Contract shall be on account payment only. The final
payment will be made on completion of all the works and on fulfillment by the
Contractor of all his liabilities under the Contract to the satisfaction of the
Purchaser.

6.2 DUE DATES FOR PAYMENT:

The Purchaser will make progressive payment as and when the payment is due as
per the terms of payment set forth herein. Payment will become due and payable by
the Purchaser within 30 days from the date of receipt of Contractor's
bill/invoice/debit note by the Purchaser provided the documents submitted are
complete and correct in all respects, and is accompanied with a checklist
substantiating the pay ability of the bill /invoice.

The Contractor shall certify the following in all the bills:


"Certified that no payment has been claimed and received before, for the
components for which payment has been claimed in this invoice".

PURCHASER reserves the right to deduct any un-payable claims admitted


inadvertently from any amount due to the CONTRACTOR.

6.2.1 Notwithstanding any amount becoming due and payable to the Contractor by the
Purchaser, the Contractor shall not be entitled to any interest on delayed / overdue
payments.

6.3 PAYMENT SCHEDULE:

6.3.1 The Contractor shall prepare and submit to the Purchaser for approval, a detailed
Billing Break Up (BBU) of the Contract Price component wise. This Contract Price
BBU shall be interlinked with the agreed detailed PERT Network of the Contractor
setting forth his starting and completion dates for the various key phases of works
prepared. Any payment except the advance payment under the Contract shall be
made only after the BBU is approved by the Purchaser. The aggregate sum of the
BBU shall be equal to the Lumpsum Contract Price. BBU shall be reviewed,
updated and submitted to the Purchaser, by the Contractor as and when required.

6.3.2 The Contractor shall submit to the Purchaser his Sequential delivery schedule for all
the equipment correlated to the sequence of erection within 1 month from the date
of Letter of Award (LOA). Such schedules shall be in line with the agreed detailed
PERT for all phases of the works of the Contractor. If required such schedules shall
be reviewed, updated and submitted to the Purchaser, by the Contractor as and
when required.

101

Page 101 of 328


6.3.3 Dispatches shall be as per such approved time schedule and payment shall be
regulated accordingly. No early payment shall be made for the 65% stage payment
and subsequent payment further indicated in the case of early dispatches effected.
6.3.4 All demurrages and wharfage if any arising out of any dispatches shall be to the
account of the CONTRACTOR only.

6.4. ADVANCE PAYMENT:


6.4.1 No advance payment shall normally be made. However if the contractor wishes to
claim advance payment for mobilization of work, equipments, materials etc., then
advance shall be paid limited to a maximum of 10% (Ten percent: First Down
Payment 5% of Contract price for supplies and site preparation work by 2 months
from the date of LOA subject to fulfillment of conditions laid down in clause No.
6.5 and Second Down payment of 5% of Contract price for supplies and site
preparation work by 3 months from the date of LOA subject to signing of Contract).

6.4.2. Except Initial Advance, all other payments shall be made only after signing the
contract. The terms of payment for the various price components of the Contract
price are detailed herein:

6.5 Payment Terms:


Advance payment:

6.5.1 All Advance Payment shall be made as per the terms of payment within 90 days
from the date of LOA for F.O.B. (imported portion) and Ex-works (Indian portion)
supply and Site preparation works on fulfilling the conditions specified below:
i) Acceptance of Letter of Award (LOA)

ii) Submission of an unconditional Bank Guarantee covering 110% of the


advance amount in the prescribed form and acceptance of the same by the
PURCHASER.
iii) Submission of Contract Performance Bank Guarantee and Financial Backup
Bank Guarantee, if any, as stipulated and acceptance of the same by the
PURCHASER.

iv)
On resubmission of detailed L1 PERT chart and acceptance thereof by
PURCHASER.
6.5.2 FOR SUPPLY, ERECTION, CIVIL WORKS, TESTING & COMMISSIONING
OF PV SOLAR:

6.5.2.1 The payment of contract price shall be regulated and paid as per price quoted in
various schedules i.e Schedule-1 to Schedule-5 in Volume-I and also as per break up
details furnished in their BBU.

6.6 Schedule-1: Site Preparation works:


6.6.1 90% (If advance payment availed) /100 % of price of each item on prorata basis quoted
in Schedule-1 shall be paid on certification of the same by the Project Manager.

102

Page 102 of 328


6.7. Schedule-2 and 3 : Plant and Equipment (for Solar and BESS):
6.7.1 50% (If advance payment availed) / 60% in case of not availing advance pro-rata value
of Contract price of F.O.B. supplies (as per agreed billing schedule) against shipping
documents as detailed out below in clause "Documents for Payments". In case of Ex-
works supplies, the same shall be against certificate of receipt of consignment at site
by the PURCHASER on Unit rate basis and after physical verification and
certification of the same by the Project Manager for having received and stored the
equipment at site. For this purpose the Contractor shall furnish a billing break up and
get it approved by the Project Manager. This stage payment will be made subject to
signing of the Contract.

6.7.2 Twenty five percent (25%) price of each item quoted in Schedule -2 and Schedule-3
shall be paid after installation of each item on Unit rate basis and certification of the
same by the Project Manager.

6.7.3 Ten percent (10%) price of Schdule-2 and Schedule-3 of the plant and Equipment shall
be payable on installation of the entire Solar PV Power Plant and BESS and after it is
tested and commissioned and exporting power to the Grid and against issue of
Provisional Acceptance Certificate by the Project Manager.

6.7.4 The final five percent (5%) price of Schdule-2 and Schedule-3 of the plant and
Equipment shall be payable on successful completion of Performance and Guarantee
tests as specified and issue of Final Acceptance Certificate by the Project Manager.

6.7.5 100% of Transport charges under price Schedule-2 and Schedule-3 shall be paid along
with 50% / 60% equipment charge against documentary evidence subject to the
lumpsum ceiling quoted.

6.7.6 100% Insurance charges shall be paid against documentary evidence and submission of
the Insurance Policy subject to the lumpsum ceiling quoted.

6.8 Advance Payment for Civil and Structural works and Installation and
commissioning:

6.8.1 If the Contractor willing to avail Advance Payment for Civil and structural works
storage, Installation and commissioning shall be paid as follows:

First 5% advance shall be paid as certified by the Purchaser

(i) on establishing office at Project Site preparatory for mobilisation of storage,


Installation and commissioning

(ii) on making ready the storage area before despatch of first consignment of supply
and

(iii) Submission of an unconditional Bank Guarantee covering 110% of the advance


amount in the prescribed form and acceptance of the same by the PURCHASER

103

Page 103 of 328


Second 5% second advance shall be paid

(i) after the Contractor moves the required construction plant and machinery and
commences at site the first installation activity as per PERT network subject to
certification by the engineer of the Purchaser and

(ii) Submission of an unconditional Bank Guarantee covering 110% of the advance


amount in the prescribed form and acceptance of the same by the PURCHASER
6.9 Schedule-4-Installation and commissioning:

6.9.1 80% / 85% (If advance payment avail)90% in case of not availing advance the price
of the installation services quoted in Schdule-4 shall be payable on pro-rata basis after
completion of installation of equipment of the Solar PV Power Plant and after it is
made ready for hooking up to the Grid

6.9.2 Five percent (5%) price of the installation services quoted in Schdule-4 shall be
payable on pro-rata basis after completion of installation of equipment of the Solar
PV Power Plant and after it is tested and commissioned and exporting power to the
Grid .

6.9.3 The final five percent (5%) price of the installation services quoted in Schdule-4 shall
be payable on successful completion of Performance and Guarantee tests as specified
and issue of final Acceptance Certificate by the Project Manager.

6.10 Schedule-5 Civil and Structural works:


6.10.1 80% / 85% (If advance payment avail)90% in case of not availing advance the price
component of the Schedule-5 shall be payable on Pro-rata basis after completion
of work and certification of the same by the Project Manager.

6.10.2 5% of price component of the Schedule -5 shall be payable after completion of work
and certification of the same by the Project Manager.

6.10.3 Five percent (5%) of price component of the Schedule-5 shall be payable on
successful completion of Performance and Guarantee tests as specified and issue of
Final Acceptance Certificate by the Project Manager.

6.11 Schedule-6 & Schedule-7 Operation and Maintenance charges for 10 years after
warranty period for Solar Power Plant and BESS respectively:

6.11.1 After completion of Warranty period as defined in bid documents, the Operation
and Maintenance charges quoted in Schedule-6 & Schedule-7 for 10 years shall be
payable on pro-rata on quarterly basis on the certification of work by the Project
Manager after completion of each quarter. The total compensation for shortfall in
net energy shall be calculated on annual basis and deduction if any shall be carried
out from the quarterly payment of the year.

6.12 The O&M during warranty period for Solar and BESS is the responsibility of the
Contractor.

104

Page 104 of 328


6.12 Taxes and Duties:

6.12.1 One hundred percent (100%) of GST/ Customs Duty shall be reimbursed against
invoices to the Contractor subject to ceiling quoted upon receipt of equipment at
site along with the 50%/ 60%payment of the respective items.

6.12.2 GST for the Operation and maintenance services and other applicable services will
be paid along with progressive payment subject to ceiling quoted in the price
schedule after completion of the respective portion of the works.

6.13 GENERAL:
6.13.1 The advance Bank Guarantee will be reduced progressively on quarterly pro-rata
basis as evidenced by the copy of invoice duly passed /approved by the Purchaser
for which the Contractor shall submit the request letters with necessary supporting
calculations.
6.13.2 All payments shall be paid only against submission of complete and correct
invoices and documents by the Contractor duly certified by the Purchaser except as
otherwise specified in the Contract. Payment shall be due and payable by the
Purchaser within a reasonable period, which will not normally exceed one month
from the date of receipt of complete and correct invoices. If it is not payable the
invoice will be returned to the Contractor stating the reasons for rejection within a
month from the date of receipt by the Purchaser.

6.13.3 All payments shall be released directly by the Purchaser to the Contractor except as
otherwise provided in the contract. If as per provisions of Contract any payments
are made directly by the Purchaser to the Associates, such payments shall constitute
a proper discharge of Purchaser's obligations for such payments to the Contractor.

6.13.4 All the progressive payments mentioned above shall be made by the Purchaser
based on the satisfactory progress of work as agreed.

6.13.5 All interim/progressive payments shall be regarded as payments by way of advance


against the final payment only and not as payment for work actually completed and
shall not preclude defective/imperfect/ incomplete work to be removed. It will not
be considered as an admission by the Purchaser of the due performance of the
Contract, or any part thereof by the Contractor nor shall it preclude, determine or
affect in any way the powers of the Purchaser under these conditions or in any other
way vary or affect the Contract.

6.13.6 The Purchaser reserves the right to encash Bank Guarantees if sufficiently
convinced of negligence and lack of dedication to work on the part of the
Contractor.
6.13.7 If the Contract is terminated due to default of the Contractor, the ‘Mobilization
Advance’ pay would be deemed as interest bearing advance at the rate applicable to
cash credit facility prevailing at the time of issue of NIT to be compounded
quarterly.
6.13.8 For delays in scope within the agreed time schedule, interest at the prevailing rates
applicable to cash credit facility will be charged on the unadjusted portion of
advance paid.

105

Page 105 of 328


6.14 PAYMENT PROCEDURE:
a. The successful Bidder shall submit the bills for claim in four copies. The
payment shall be made after the verification of the bill by concerned Accounts
Centre at NLC India Ltd., Neyveli.
b. It is expressly understood that the release of payment to the successful Bidder
in the manner specified will not be construed as the fulfillment of the
Bidder's obligations either in part or whole under the contract and that
the Bidder shall continue to remain responsible to NLCIL until all the
obligations under the agreement have been fulfilled.

6.15 PAYMENT OF CONTRACTORS BILLS THROUGH ELECTRONIC


FUND TRANSFER (EFT)
The Bidder should submit the consent in a mandate form for receipt of payment
through NEFT and provide the details of bank A/c in line with RBI guidelines
for the same. These details will include bank name, branch name & address, A/c
type, bank A/c no., bank and branch code as appearing on MICR cheque issued
by bank. Further, the Bidder should also submit certificate from their bank
certifying the correctness of all above mentioned information in the mandate
form.

6.16 Payment for Ocean freight and Inland Transport

6.16.1 Ocean Freight

100% ocean freight charges for respective shipment shall be reimbursed at


actual on production of documentary evidence. Total claim shall not exceed the
ceiling price quoted in the price schedule for ocean freight.

6.16.2 Inland Transport

Inland transport charges for imported portion from Chennai port to the site will
be borne by the Contractor.
100% of the transport charges for indigenous supplies on pro-rata basis shall be
reimbursed on production of invoices and documentary evidence along with
50%/60% supply invoices after receipt of materials at site. However, the total
claim shall not exceed the ceiling quoted in the price schedule for inland
transport.
6.17 Insurance Charges
6.17.1 The Insurance premium in respect of Marine and inland transport shall be
prepaid by the Contractor and got reimbursed subject to production of
documentary evidence including the copy of respective policies.

6.17.2 The reimbursement of premium can be made at periodical intervals as per the
policy’s conditions. The premium receipt issued by the Insurance company shall
have to be produced for claiming reimbursement. After all the instalments of
premium are paid, the difference between lump sum insurance charges indicated
in the contract and the premium actually reimbursed to the contractor on
documentary evidence as referred above, shall be paid to the contractor on the
basis of invoices from the contractor, without supporting documents to

106

Page 106 of 328


compensate the service charges incurred by the contractor during the pendency
of the Insurance policy. However, the total claim shall be restricted to the lump
sum price quoted in the schedule of price.

6.18 Customs duties, Port handling, clearance and forwarding


For imported supplies on F.O.B. basis Customs Duty if any, shall be reimbursed
at actuals subject to ceiling indicated in the schedule of price along with
50%/60% payment. However the purchaser shall not be liable to pay such
charges in respect of items supplied by the Contractor on free of charge basis.
For the domestic supplies all charges regarding customs duties, if any, shall be
to the account of the Contractor.

6.19 Mode of Payment

6.19.1 Indigenous supply

The payment shall be made direct to the Contractor by the Purchaser through
e-payment only. Payment, will become due and payable by the Purchaser
within a reasonable period which will not exceed one month from the date
of receipt of Contractor's bill / invoice / debit note by the Purchaser provided
the documents submitted are complete and correct in all respects. If it is not
payable the invoice will be returned to the Contractor stating the reasons for
rejection within a month from the date of receipt by the Purchaser.
6.19.2 Imported supply
In case of stage payment (50%/60%) in foreign currency for the supplies of
Equipment, the Purchaser will establish irrevocable Letter of Credit in favour of
the Contractor through the Purchaser’s Bank in India and payment will be
effected through Letter of credit. The Balance payment for supplies will be
made through direct disbursement method.

The payment for indigenous supplies, the inland transportation, insurance and
other lump sum charges shall be made direct to the Contractor by the Purchaser
wherever applicable through E-payment.

6.20 Opening of Letter of Credit., Validity & Extension of Letter of Credit

6.20.1 The Purchaser shall open an irrevocable Letter of Credit at the State Bank of
India or any principal Bank of NLC and advice through its foreign branches/
correspondents to be specified by the Contractor in due course. The Letter of
Credit will be kept valid for 3 months covering 50%/60% value of equipment.
Letter of Credit will be opened after the receipt of information from the
contractor regarding readiness of the shipment.
6.20.2 The bank charges incurred in India shall be to the account of the Purchaser and
all bank charges incurred in abroad shall be to the Contractor's account. Should
the Contractor need confirmation of LC, charges there of is to be borne by the
Contractor. The Purchaser will bear all bank charges in India for establishing/
renewal of L/Cs with State Bank of India or any principal Bank of NLC.
However, if extension of Letter of Credit become necessary for delay due to

107

Page 107 of 328


reasons attributable to the Contractor then all bank charges for such extension
shall be borne by the Contractor.
6.20.3 In respect of all Ex-works supplies all payment will be made through e-
payment in INR and bank charges if any would be to the contractor’s account.

6.21 Documents for Payment


6.21.1 Invoice for imported supplies
6.21.2 For 50%/60% payment
The following documents in original are to be submitted to bank for payment.

i. Contractor’s signed commercial invoice showing100% FOB price for equipment


/components supplied, 25% to be received against receipt at site and
verification and 10% to be received on successful completion of commissioning
and final 5% payable on successful completion of Performance Guarantee test
50%/60% as amount falling due and a certificate confirming that delivery has
been effected according to the conditions of the Contract.
ii. 3 originals of marine Bill of Lading clean on board marked freight prepaid
consigned to NLCIL plus one non-negotiable copy, evidencing shipment to
Indian sea port.
iii. Copy of transit insurance declaration made by Contractor.
iv. Packing list / despatch note – one copy.
v. One copy of certificate of origin.
vi. One copy of Soundness certificate in the following form
"Certified that the materials shipped EX S.S./M.V .....................................
under B/L No. ............. dated ............ for the value of ................ against
Contract No. ........... were in sound condition at the time of shipment."

vii. One copy of Test certificate, if no such certificate is necessary,


confirmation by NLC to this effect.
viii. Certificate to the effect that liquidated damages have been deducted/ No L.D is
payable by Contractor.
ix. Confirmation by Contractor that the copy of the above documents have been sent
to NLC immediately after shipment.
x. In respect of last consignment in addition to the above documents the following
certificates and documents shall also be furnished.

a) Certificate by the Contractor that no further shipment will be made and the
supplies are completed in all respects.
b) Summary of all invoices for the equipment also showing the amount due and
amount claimed/received.
Two copies of each of the above documents shall be sent simultaneously to the Head of
Unit Finance / Neyveli.
In addition, 10 copies in each of the above documents shall be sent direct to the
GENERAL MANAGER/CONTRACTS after effecting the shipments, within 7 days
from the date of shipment.

108

Page 108 of 328


6.21.3 For 25% Payment
The documents in original to be submitted to Purchaser shall consist of the following:
i. Contractors signed commercial invoice, one copy showing 100% FOB price for
equipment / components supplied, deductions of 50%/60% of payment already
received, and 25%+15% of payment to be received on successful completion of
commissioning & PG Test and amount now falling due as 25% payment.
ii. Certificate of verification by Purchaser for components received directly at site.

iii. In respect of last consignment in addition to the above documents the following
certificate and document shall also be furnished.
a) Certificate by the Contractor/that no further shipment will be made and the supplies
are completed in all respects.

b) Summary of all invoices for the equipment also showing the amount due and
amount claimed/received.

6.21.4 For 10% Payment


Documents in original to be submitted to the purchaser shall consist of the following:

i. Contractor’s signed commercial invoice, one copy showing 100% FOB price for
equipment/components supplied, deductions of 85% of payment already received,
and the balance 10% amount falling due provisional take over.
ii. Purchaser’s Certificate of successful completion of commissioning of the equipment.

6.21.5 For final 5% Payment


Documents in original to be submitted to the purchaser shall consist of the following:
i. Contractor’s signed commercial invoice, one copy showing 100% FOB price for
equipment/components supplied, deductions of 95% of payment already received,
and the balance 5% amount falling due after Performance Guarantee Test..(PG
Test).
ii. Purchaser’s Certificate of successful completion of PG Test of the equipment
6.21.6 Invoice for indigenous supplies:

The following documents in original shall be sent by Registered Post to the Head of the
unit Finance/New Project/CO,the General Manager/PBD as applicable within 10 days
from the date of despatch to enable the Purchaser to make progressive payment to the
indigenous supplier.
6.21.7 For 50%/60% payment
i. Certificate of receipt of materials at site as certified by the Purchaser-1 original +
two copies.
ii. Supply invoice -1 original + 2 copies

iii. Packing list (despatch note)- 2 copies

iv. Soundness certificate -1 original + 2 copies


The Certificate of soundness referred to above will be furnished in the following
form:
"Certified that the materials despatched in RR dated …............ for the value of
109

Page 109 of 328


Rs. ................ against Contract No. ........... were in sound condition at the
time of despatch.

v. Test certificate if applicable and/or inspection certificate of the Contractor- 1


original + 2 copies

vi. Freight invoice of the Contractor - 1 original + 2 copies

vii. RR/lorry way bill /delivery note - 1 original + 2 copies

viii. Transit insurance declaration- 1 original + 2 copies

ix. In respect of last consignment in addition to the above documents the following
certificate and document shall also be furnished:

a. Certificate by the Contractor that no further supplies will be made and supplies
are complete in all respects.

b. Summary of all invoices for the equipment also showing the amount due and
amount claimed / received.

6.21.8 For 25% stage payment

i. Invoices – 1 Original + 3 Copies


ii. Certificate of verification by the Purchaser of the equipment received at site.
iii. In respect of last consignment in addition to the above document the following
certificate and document shall also be furnished:

a) Certificate by the Contractor that no further supplies will be made and the
supplies are completed in all respects.
b) Summary of all invoices for the equipment also showing the amount due and
amount claimed/received.

6.21.9 For balance 10% payment:


i. Invoices 1 Original + 3 Copies.
ii. Purchaser’s Certificate of successful completion of commissioning.
For balance 5% payment:
i. Invoices 1 Original + 3 Copies.
ii. Purchaser’s Certificate of successful completion of PG Test.

110

Page 110 of 328


SCHEDULE - 7

FACILITIES TO BE PROVIDED BY THE PURCHASER

Covered in Technical Specification

111

Page 111 of 328


SCHEDULE -8

CONTRACT SPECIFICATIONS
The Technical Specifications issued along with the Tender Specifications duly
modified and up-dated based on the changes/modifications agreed between the
Purchaser and the successful Bidder shall constitute Schedule-8 "Contract
Specifications" of this Contract and shall form an integral part of the Contract for all
purposes.

112

Page 112 of 328


SCHEDULE-9

9.0 PERFORMANCE GUARANTEE


General
1. The contractor shall guarantee that the equipments offered shall meet the ratings
and performance requirements stipulated for various equipments covered in the
Technical / Contract specifications.
2. The contractor shall demonstrate and achieve guaranteed values during the one
year, performance guarantee test period as per Contract Specification, at site in
the presence of the Purchaser for the complete system.
3. Details of performance guarantee test and method of computation of
performance values shall be as per Technical Specification.
4. The Contractor shall supervise and direct the operation during performance
guarantee test and shall take complete responsibility in this regard.
5. During performance guarantee test, the Contractor shall make available
necessary experienced operating & maintenance personnel.
6. The Contractor shall provide and install all measuring instruments with required
calibration for checking the guaranteed generation during performance
guarantee test.

Demonstration of Performance Guarantee Test and LD for Shortfall


in net energy export due to Non-Performance
1. The guaranteed net energy export furnished by the bidder in his offer, shall be
without any tolerance values and all margins required for instrument
inaccuracies and other uncertainties (permitted as per Technical Specification)
shall be deemed to have been included in the guaranteed figures.
2. Bid price quoted by the Bidder shall include all costs associated with the tests.
No credit shall be given to the Bidder, in the bid evaluation or in the evaluation
of the results of the guarantee tests for performance predictions / guarantee etc.
if the values considered by the bidder are better than those furnished by the
bidder in their offer.
3. The performance guarantee tests shall be conducted by the successful Bidder/
Contractor for the whole system including grid tie up and LD shall be levied for
any shortfall in energy export as specified in the Technical Specification.

Performance Guarantee Test


1. The performance guarantee test shall be conducted at site by the Contractor in
presence of the Purchaser. Such test will be conducted for one year after the
successful commissioning and provisional take over of the plant.
2. Instrumentation used, their accuracy class, their numbers & location etc. for
carrying out performance guarantee test shall be as per relevant Technical
Specification and shall be subject to Purchaser’s approval. In addition the values
of parameters shall be logged for the entire period in the Data Acquisition
system provided under SCADA.
113

Page 113 of 328


3. Any special equipment, tools and tackles required for the successful completion
of the performance guarantee test shall be provided by the contractor at his cost.
4. If equipment / system fail in the PG test, all necessary modifications and / or
replacements shall be carried out by the successful bidder (contractor) without
any extra cost to the Purchaser so that the equipment / system comply with the
guaranteed requirements. However, if even after above modifications /
replacements, the contractor is not able to successfully complete the PG test
within a reasonable period allowed by the Purchaser, Purchaser will have the
right to the following:
(a). To reject the equipment / system / plant and recover the payment already
made
OR
to accept the equipment / system / plant after levying for shortfall in
energy export as specified in the Technical Specification `

Schedule of Performance Guarantees


Details of performance guarantee tests and method of computation of
performance values shall be as per Technical Specification.
Necessary write ups, schemes, instruments, schedules, logs, detailed procedures
clearly indicating period of tests, frequency of observations, etc. shall be
prepared and submitted for Purchaser’s review and shall be got specifically
approved from the Purchaser at least one month before the tests are carried out.

LD for Shortfall in Net Energy Export.


1. Should the results of the performance guarantee test show that the Solar PV
system along with grid tie up has failed to meet its guarantee values, the
Contractor shall carry out necessary modification at their own cost, to meet the
guaranteed values. In such a case the performance guarantee test shall be
repeated by the Contractor within one (1) month from the date the equipment is
ready for retest. If the specified guarantees are not established again, the
Purchaser may at his discretion reject the equipment and recover the payments
already made or accept the equipment after assessing the LD at the rates
specified in the Technical Specification. The recovery of such amount shall be
from the amounts due to the Contractor.
2. The Bidder shall furnish declarations in the formats prescribed in the Technical
Specification for these guarantees.

PG test report
On successful completion of demonstration of performance guarantees for the
plant following shall be supplied:
a) Performance Guarantee Evaluation Report.
b) Operation log book for 1 year
c ) Power export log for 1 year

114

Page 114 of 328


SCHEDULE- 10
GENERAL TERMS AND CONDITIONS OF THE CONTRACT

10.1 BANK GUARANTEES

10.1.1 GENERAL

i) All the Bank Guarantees shall be irrevocable. The Bank Guarantee shall be from
any Nationalised Bank or any Scheduled bank in India (other than Bank of China)
authorised by Reserve Bank of India to issue such Bank Guarantee. Except bid
guarantee, all bank guarantees are to be furnished directly by the banker to
NLCIL by RPAD/Courier to the following address:

The Chief General Manager/Contracts,


Corporate Office, NLC India Ltd., Block-1,
Neyveli - 607 801.

ii) The Bank Guarantee shall be furnished as per respective format prescribed by the
Purchaser and shall be submitted on Non-judicial stamp paper of value Rs.80/-
and the stamp paper shall be in the name of the Bank.

iii) All the Bank Guarantees shall be payable on first demand, without demur,
irrespective of any dispute between the Bank and the Contractor to the
Purchaser without any condition or dispute whatsoever.

iv) The Contractor shall arrange to keep the several bank guarantees referred to
herein valid for the requisite duration by making timely request to the Bank or
Banks concerned. All the extension for Bank Guarantees also shall be on non-
judicial stamp paper of value Rs.80/- obtained in the name of Bank. All charges
connected with the bank guarantees shall be to the account of the
CONTRACTOR.

v) No interest shall be payable by the Purchaser on the Bank Guarantee on amount


of Bank Guarantee encashed.

vi) The Purchaser shall have the right to encash the Bank Guarantees for non-
compliance of any or all the terms and conditions of the contract and also in terms
of the Joint Deed of Undertaking, if any, which the Contractor may enter into
along with other parties with the purchaser. Non -compliance of any or all the
terms and conditions of the contract by the Contractor, will be intimated to the
Contractor, specifying the reason with supporting documents, before encashment
of the Bank Guarantee.
vii) Confirmation of BG under the through “Structured Financial Messaging
System (SFMS)”
a. The Bank Guarantee issued by the issuing Bank of Behalf of Bidder/ Contractor
/ Supplier in favour of “Name of Company” shall be in paper form as well as
issued under the “Structured Financial Massaging System. The details of
beneficiary for issue of BG under SFMS platform is furnished below:-

115

Page 115 of 328


Name of Beneficiary & its details Name NLCIL

Unit/ Contracts
Area/ Division branch /Corporate
Office
Beneficiary Bank, Branch & Address State Bank of India
Block-2,
Neyveli – 607801
IFSC Code SBIN0000958

The above particulars are to be incorporated by the issuing bank properly while issuing
BG under SFMS mode to avoid any problem in future.

10.1.2 Bank Guarantee for Advance Payment:

The advance stipulated in the payment terms shall be made to the CONTRACTOR
by the PURCHASER subject to the CONTRACTOR providing a bank guarantee
for 110% of the advance amount as per the stipulations and on acceptance of
the said bank guarantee. This bank guarantee shall be valid till completion of the
supplies/ commissioning / scope of work, as the case may be with a grace period of 2
months thereafter.

All Bank Guarantees against advance payments shall be progressively reduced in


value on prorata basis after attainment of progress and payment made, once in every
quarter only on approval by the Purchaser for which the Contractor shall submit the
request letters with necessary supporting calculations.

10.1.3 CONTRACT PERFORMANCE BANK GUARANTEE (CPG)

i) The CONTRACTOR guarantees the successful and satisfactory operation of the


equipment supplied under the Contract as per specifications and documents. The
CONTRACTOR further guarantee that the equipment supplied and installed shall
be new and free from all defects in design, material and workmanship. The
CONTRACTOR shall, upon written notice from the PURCHASER, fully
remedy free of expenses to the PURCHASER such defects as may develop in
the normal use of the said equipment within the warranty period as specified in
the Contract.

ii) As a contract security, the successful Bidder to whom the work is awarded, shall be
required to furnish Contract Performance Bank Guarantee(s) covering the warranty
period in the form stipulated subject to approval of the Owner in-favour of the
Owner within 30 (Thirty) days from the date of Letter of Award. The Guarantee
amount shall be equal to 10% (Ten Percent) of the total contract price for supply
and services excluding O&M charges for 10 years and it shall guarantee the
faithful performance of the contract in accordance with the terms and conditions
specified in these documents and specifications. The guarantee shall be valid till the
expiry of 90 days beyond the actual date of final take over or after the end of the
116

Page 116 of 328


warranty period or after the end of the Performance Guarantee test whichever is
later. The Guarantee amount shall, on demand, be payable without demur in
respective of any legal dispute between bank and the contractor and between the
contractor and the owner without any condition or dispute whatsoever.

iii) The PURCHASER shall have the right to encash the Contract Performance
Guarantee in full or part thereof for non-compliance of any or all the terms and
conditions of the contract and to recover any Liquidated Damages under the
contract as well as against defects in the equipment/ shortfall in guaranteed
generation and for failure to comply with any of the warranty obligations as
enumerated in the Contract.

iv) In case of part encashment, CPG shall be valid for the remaining period as per
contract for the balance amount or for the period as requested by owner.

v) The Contract Performance Bank Guarantee value shall be suitably adjusted towards
the variation in the Contract price.

vi) The 90% of Contract Performance Bank Guarantee value will be allowed to reduce
on the expiry of warranty period or after date of final take over or after the end of
the warranty period or after the end of the Performance Guarantee test whichever is
later subject to submission of CPG for O&M Contract. The remaining 10% of the
CPG value will be retained till the completion of 10 years O&M Contract and will
be returned to the contractor without any interest after 90 (ninety) days from
completion of 10 years O&M contract period.

10.1.4 LIQUIDATED DAMAGES BANK GUARANTEE (LDBG)

If the delay is not purely attributable to the Contractor and requires detailed analysis,
the amount equivalent to the maximum L.D leviable would be withheld from the
running bills as indicated in Schedule 6. In case the Contractor faces difficulty in
cash flow and progress of work, an amount up to 90 % of the withheld amount shall
be released to the Contractor against a Bank Guarantee as per the format enclosed for
100 % of the withheld amount, if requested by the Contractor. The Bank Guarantee
shall be initially valid for 6 months and shall be suitably extended by the Contractor
till the LD issue is settled.

10.1.5 RETENTION MONEY BANK GUARANTEE (RMBG)

i) The final five percent (5%) payment of price indicated in Schdule-1, 2 &3 and final
five percent(5%) payment of the price indicated in Schdule-4 shall be payable on
successful completion of Performance Guarantee tests as specified and issue of
Final Acceptance Certificate by the Purchaser.

ii) In case of delay in Performance Guarantee test for reasons not attributable to the
Contractor, the final five percent (5%) payment of price indicated in
Schdule-1,2&3 and final ten percent (5%) payment of the price indicated in
Schdule-4 will be released at the latest by 6 months from the scheduled date of
completion of Performance Guarantee test against furnishing of RMBG and
acceptance of the same by the Purchaser.

117

Page 117 of 328


iii) The Retention Money Bank Guarantee shall be initially valid for 6 months and shall
be extended suitably in such a way that the Bank Guarantee is valid up to the actual
date of successful completion of Performance Guarantee test.

iv) The Purchaser shall have the right to encash the RMBG for deficiency and default
in supplies and also for the recovery of L.D. in terms of the Contract.

10.1.6 FINANCIAL BACK UP BANK GUARANTEE ( if applicable)

i) In case of bidder who undertakes to execute the Contract on the basis of a


collaboration agreement the bidder shall furnish an agreement to work together for
this project with his collaborator. The same shall be backed up with a financial
guarantee by the collaborator directly furnished (format enclosed vide Appendix-
B) to the Purchaser for a value of 5% of their respective portion of the contract
value to be made by the collaborator and initially valid for 15 months beyond
the scheduled date of Performance Guarantee Test and shall be extended suitably
to be valid till the expiry of 90 days beyond the actual date of completion of
performance test or after the end of the warranty period, whichever is later.

ii) In case of bidder who undertakes to execute the Contract on the basis of a
consortium agreement the bidder shall furnish an Agreement/Letter of consent/Joint
deed of under taking in which the partners are jointly and severally liable to the
Owner for successful performance of the contract. The same shall be backed up
with a financial guarantee by the consortium partner/s directly furnished (format
enclosed vide Appendix-B) to the Purchaser for a value of 5% of their respective
portion of the contract value to be made by the consortium partner and initially
valid for 15 months beyond the scheduled date of Performance Guarantee Test
and shall be extended suitably to be valid till the expiry of 90 days beyond the
actual date of completion of performance test or after the end of the warranty
period, whichever is later.

iii) In case of bidder is Joint Venture Company, each partner of JV company shall
furnish Financial Back-up Bank Guarantee for a value of 5% of their respective
portion of the contract value to be made by the JV partner/s and initially valid
for 15 months beyond the scheduled date of Performance Guarantee Test and
shall be extended suitably to be valid till the expiry of 90 days beyond the actual
date of completion of performance test or after the end of the warranty period,
whichever is later.

iv) In case the respective portion of work of the Collaborator/Consortium partners/Joint


Venture partners is less than 1% of the total contract value, then Financial back up
Bank Guarantee for a minimum of 0.05% of the total contract value shall be
furnished.

v) The Purchaser shall have the right to encash the financial backup bank
guarantee for non-compliance of any or all the terms and conditions of the Joint
Deed of Undertaking as well as for shortfall in guaranteed output as enumerated in
the Contract.
10.2 INSURANCE
10.2.1 The Bidder shall at his own expense take out necessary insurance to-the supplies,
transit, personnel and all other related to the satisfaction of the NLCIL including all
third party risks as detailed below:
118

Page 118 of 328


i) Insurance to cover
a. marine transit
b. storage
c. erection
d. commissioning policy
ii) Insurance to cover third party liability and surrounding property
iii) Workmen compensation and/or group personal accidents Insurance policy
covering all its employees and works including of the Sub- Contractor.

10.2.2 It is the responsibility of the Contractor to enter in to an agreement to operate and


maintain the Solar PV Power Plant along with power evacuation system and its all
equipment and facilities in perfect condition for the entire period of 25years O & M
after final take over for which NLCIL shall pay the agreed Comprehensive O&M
charges only. The replacement / repair / modification of any or all equipment have to
be carried out by the Contractor at his own cost for the entire period of contract.
NLCIL shall not be responsible for any break down /failure of any equipment to any
reason thereof. After Provisional Take Over, comprehensive insurance coverage for
the entire system shall be taken by the contractor in the name of NLCIL on yearly
basis.
10.2.3 SCOPE OF INSURANCE
The Contractor shall take out a composite and comprehensive Marine-cum-Erection
Insurance Policy with a Nationalised Indian Insurance Company/company regulated by
IRDA which shall cover total erected value of the Facilities (115% of Contract price)
and all risks specifically inclusive of the following:

i) All Risk Insurance: The policy shall cover all risks and escalations, and revisions
without ceiling.
ii) Cargo Insurance: For supplies, the policy shall insure the goods originating from
the Contractor's / Supplier's warehouse to Plant's warehouse and up to completion
of erection and commissioning. This will be inclusive of supplies to and from
warehouse / factory of intermediate processors / suppliers. This policy will also
cover the replacement items, if any.
iii) Third Party Liability Insurance: The policy shall cover third party liability. The
third party liability shall cover the loss / disablement of human life (persons not
belonging to the Contractor) and also cover the risk of damages to others'
materials/equipment/ properties during construction, erection and commissioning
at site. The value of third party liability for compensation for loss .of human life
or partial / full disablement shall be of required statutory value but not less than
Rs.2 lakh per death, Rs.1.5 lakh per full disablement and Rs.1 lakh per partial
disablement and shall nevertheless cover such compensation as may be awarded
by a Court of Law in India or abroad and cover for damage to others' equipment
/surrounding property as approved by NLCIL.
iv) Automobile Liability Insurance: Covering use of vehicles / mobile equipment
used by the Contractor or its Sub Contractors (whether or not owned by them) in
connection with the-execution of the Contract
v) Contractor shall ensure that where applicable, its Sub-Contractor(s) shall take out
and maintain in effect adequate insurance policies for their personnel and
vehicles and for work executed by them under the Contract, unless such Sub-
Contractors are covered by the policies taken out by the Contractor.

119

Page 119 of 328


vi) NLCIL shall be the principal beneficiary of the policy along with the Contractor.
Sub-Contractors of the Contractor shall not be holders or beneficiaries in the
policy nor shall they be named in the policy.
vii) At no time shall goods and services required to be provided by the Contractor
shall remain uninsured.
viii) A copy of the 'Marine-cum-Erection' Insurance policy shall be made available to
NLCIL within 60 days of signing of the Contract and policy shall be kept alive
and valid at all times up to the stage of Commissioning Certificate.
ix) NLCIL reserves the right to take out whatever policy that is deemed necessary by
him if the Contractor fails to keep the said policy alive and valid at all times and /
or causes lapses in payment of premium there by jeopardising the said policy.
The cost of such policy(s) shall be recovered / deducted from the amount payable
to the Contractor.
x) The Contractor while taking out such 'Marine-cum-Erection' policy shall avail
the best premium rates with the maximum discounts available.
xi) In cases where the erection, modification etc., are to be carried out in the existing
site of NLCIL the 'surrounding value' shall be intimated by NLCIL to the
Contractor, who shall, ensure that this value is included in the policy.
xii) Upon arrival of plant and Equipment / materials at site the-Contractor shall
assume custody thereof and remain responsible thereafter for safe custody until
the whole plant is successfully commissioned.
xiii) In order to adequately cover the works under such composite and comprehensive
insurance, the Contractor shall fulfill the necessary requirements / obligations
which will inter-alia include the following:
a. Adequate fire-fighting equipment and extinguishing agents of sufficient
capacity and quantity must always be available at site and kept ready for
immediate use.
b. Sufficient number of workmen must be fully trained in the use of such
equipment and must be available for immediate intervention at all times.
c. For storage of materials and equipment for the construction and erection
work, storage must be subdivided into storage units and the distance
between such storage units shall be as acceptable to the Insurance Company.
All inflammable materials and especially all inflammable liquids and gases
must be stored at a sufficient large distance from the property under
construction or erection and from any hot work.
d. Welding, soldering or the use of an open flame in the vicinity of
combustible material is only permitted if at least one workman suitably
equipped with extinguishers and well trained in fire-fighting is present. At
the beginning of preliminary acceptance test & pre-commissioning of Plant
& Equipment all fire-fighting facilities must be rechecked thoroughly.
e. Observation of all safety rules and regulations.
xiv) The Contractor shall arrange Accident Insurance Policy for all his personnel
including Experts / Specialists / Personnel deputed to site and Contractor's / his
sub-contractors' manufacturing works as well as for his engineers & supervisory
staff. The Contractor shall also take out for his workmen a separate policy as per
Workmen's Compensation Act.
120

Page 120 of 328


xv) The details of consignment along with its value and vessel's name and other
shipping particulars shall be intimated to NLCIL by the Contractor by cable / E-
mail immediately after shipment of the consignment.
xvi) The Contractor shall intimate by E-mail / Fax to the Underwriter in giving the
above particulars immediately after dispatch with a copy to NLCIL.
xvii) In all Cases, the Contractor shall lodge the claims with the Underwriters and also
settle the claims. However, the Contractor shall proceed with the repairs and / or
replacement of the equipment / components without waiting for the settlement of
the claims. In case of seizure of materials by concerned authorities, the
Contractor shall arrange prompt release against bond, security or cash as
required. NLCIL will extend all assistance to the Contractor in such a case.
xviii) All the insurance claims shall be processed by the Contractor and the items
which are missing / damaged in transit or during handling, storage, erection and
commissioning, shall be replaced / repaired by them without any extra cost to
NLCIL and without affecting the time for completion.
xix) Before commencing the execution of the work the contractor (but without
limiting his obligations and responsibility) shall, insure against any damages loss
or injury which may occur to any property (including that of NLCIL) or to any
person (including any employee of NLCIL) by or arising out of the execution of
the works of temporary works or in the carrying out of the contract otherwise
than due to the matters referred to in the provisions of Clause 10.2.3 thereof.

10.3 Packing, Forwarding and Shipment

i) The Contractor wherever applicable after proper painting, pack and crate all
equipments in such a manner to protect them from deterioration, damage, pilferage
etc., during transportation to Site. The Contractor shall be held responsible for any
damage caused due to improper packing.
ii) The Contractor shall notify the Purchaser about the date of each shipment from his
works and expected date of arrival at site furnishing the weight, dimensions and
contents of each packing.
iii) The Contractor shall be responsible for making necessary loading, unloading and
handling arrangements from port / his Works to site.

10.4 Marking
i) The equipment shall be packed suitably for marine transport /inland transport as
the case may be. The packages shipped by the foreign supplier shall be addressed
to the General Manager / Contracts, Corporate office, NLC India Limited,
Neyveli-607 801, Tamil Nadu, India.
ii) The Indian suppliers shall address the packages to the General Manager/PBD,
NLC India Limited, Neyveli- 607 801, Tamilnadu, India.
iii) In case of packaging and grating the under noted markings shall be stencilled , or
otherwise conspicuously marked on to opposite sides - case No, Gross Wt./ Nett
Wt., Order No. and Date.

iv) The contractor shall keep in each case the packing list fully item wised to show
case No., content, Gross Wt./ NettWt,. Machinery, Contract/ Supply Order No.
and date.

121

Page 121 of 328


v) The packages shall have to be marked as stipulated in the Contract / Supply
Order.
10.5 Transport

10.5.1 Ocean Transportation - Imports

i) The Contractor shall inform the Purchaser about the programme of despatches as
contemplated by the Contractor to enable the Purchaser to have an effective
follow up. Part shipment is permitted. Transhipment is prohibited.

ii) The Contractor shall furnish a list of items with value of goods imported through
Ports in India and furnish detailed information.

iii) The terms of the contract shall be on FOB / CIF basis. The Contractor shall make
shipping arrangements on behalf of the Purchaser upto destination port (Port Blair at
Andaman). The Contractor shall give notice about readiness of cargo for shipment to the
Purchaser. While giving such notice of readiness of shipment, the Contractor shall
furnish the following to the Purchaser.
a. Contract No.
b. Brief description of material to be shipped.
c. Gross weight.
d. Net weight.
e. Dimensions of the Packages to be shipped.
f. Number of Packages.
g. Import Licence No., if any and L/C particulars.
.
iv) If situation warrants, the contractor can arrange air freight with prior approval of
the Purchaser. In such case the increase in freight and customs duties thereof
shall be to the account of Contractor.
v) All shipments will be done through approved vessels as per the `Institute of
London Classification Clause' of the Institute of London Underwriters as given
below.

Institute Classification Clause


The Marine Transit rates agreed for this insurance apply only to cargoes and/or
interests carried by mechanical self-propelled vessels of steel construction,
classed as below by one of the following classification societies.

Lloyds Register -- 100A1 or B.S.*


American Bureau of shipping -- *A1 R
Bureau veritas -- 13/3E * V
Germanischer Lloyd --* 100 A4 G
Korean Register of shipping -- *KR S1 J
Nippon KaijiKyokai -- NS*N
Norske verites -- 1A1 N
Registro Italiano -- *100A 1.1 Nau. L
Register of shipping of the USSR -- KM * S
Polish Register of shipping --*KM P
Provided such vessels are:
122

Page 122 of 328


i) Over 15 years of age but not over 25 years of age and have established and
maintained a regular pattern of trading on an advertised schedule to load and
unload at specified ports.
ii) Chartered vessels and also vessels under 1000 GRT which are mechanically
self propelled and of steel construction must be classed as above and not over
15 years of age. And for the Chartered vessels of 15 years of age the
Contractor shall produce a certificate as follows:
"The shipment by sea-worthy vessels classed 100 A1 Lloyds or equivalent
classification society and approved by General Insurance Company of India".
If the suppliers do not adhere to the above condition and if the insurers charge
extra premium due to overage or non-classification of vessels, the suppliers
may have to be held liable to pay the extra premium incurred.

iii) The bills of lading should be drawn so as to show:

SHIPPERS The NLC India Limited


CONSIGNEE GENERAL MANAGER / CONTRACTS
NLC INDIA LTD.,
NEYVELI-607 801,
TAMIL NADU, INDIA

PORT CONSIGNEE ADDRESS OF CONTRACTOR /


CLEARING AGENT OF CONTRACTOR
IMPORTER/ GENERAL MANAGER/ CONTRACTS
NOTIFY PARTY NLC INDIA LTD.,
NEYVELI-607801, TAMIL NADU, INDIA

iv) The Contractor shall send the following shipping documents With the Cargo -
Quality certificate (one copy) Packing list (6) copies comprises 2 copies in case
No.1 of each consignment of the goods and 4 copies in each case (three inside
the Box and one copy in a special packet at the outer side of the Box).

v) Whereas shipments are effected by FCL containers at the request of the


consignee/agent/shipper the number of free days time granted shall be 10 days
(Excluding Holidays).

10.5.2 Inland Transport

i) All Ex. works supplies with in India shall be handled and transported
including inter-carting, storage at any intermediate point from the shops of the
manufacturers' works to site/ stores through accredited/registered, reliable
dependable transport carriers.

ii) The Contractor shall assume complete, full and total responsibility for inland
transport of these items and charges thereof shall be indicated separately as a
fixed lump sum in the schedule of prices.

iii) The Contractor shall thoroughly study the transportation routes and available
transportation facilities and the Contractor shall take full responsibility for
transport of all supplies.

iv) For FOB items i.e., items imported, the inland transport from ports in India to
project site shall be the scope of the Contractor.
123

Page 123 of 328


10.5.3 Demurrage and Wharfage
i) The Purchaser shall not be responsible for any demurrage penalties etc. that
may be incurred due to reasons attributable to the Contractor for delayed
sending of despatch /shipping documents, Bill of Lading, domestic invoices.

ii) The Purchaser shall not be responsible for any detention enroute of any
consignment arranged through any mode of transport and shall not also bear any
charges thereon. It shall be the responsibility of the Contractor to make
expeditious alternative arrangement, ensuring safety to the consignment in the
event of any such detention and the Contractor shall bear the complete charges
thereon.
10.6 Licences
10.6.1 Import Licence
For any portion of the supplies to be imported by the Contractor for incorporation in
manufacture of the equipment, the Contractor shall arrange the necessary import
including arrangements of licenses and Foreign Exchanges as may be required, on his
own.

10.6.2 Export Licence


In case of foreign Contractor, he shall obtain and maintain the necessary Export licence
from the competent authorities and shall pay at his cost any fee connected therewith.
Failure to obtain and maintain export Licences shall not be considered as Force
Majeure. In case the Contractor fails to obtain or maintain the Licences, or if the
licences are withdrawn, he shall restore them within two months from the date of
cancellation/withdrawal. However, the delay due to restore of Licence is attributable to
the Contractor, the Purchaser has the right to cancel the Contract and the Contractor
shall forthwith return the Purchaser all the amounts paid by the Purchaser to the
Contractor.

10.7 RESPONSIBILITY FOR PERFORMANCE OF CONTRACT


The Contractor shall be responsible for the due and faithful performance of the Contract
in all respects according to the drawings, specifications and all other documents
referred to in this Contract. Any approval which the Purchaser/ Consultant may have
given in respect of the materials, supplies or other particulars and the work or the
workmanship involved in the Contract (whether with or without test carried out by the
Contractor or the Purchaser) shall not relieve the Contractor from his obligations and
notwithstanding any approval or acceptance given by the Purchaser/ Consultant, it shall
be lawful for the Purchaser to reject the material on arrival at site, if it is found that the
materials supplied and/or erection and/or construction work carried out by the
Contractor are not in conformity with the terms and conditions of the Contract in all
respects.

10.8 COMPLETENESS OF WORK


The Contractor shall expressly undertake full responsibility for the quality of
supplies, timely deliveries as per the stipulated schedule of deliveries the faultless
operation of the equipment, the warranty for the design of the equipment and
manufacture of the complete equipment, including the Indian portion of supplies free
of any defects and faults.

124

Page 124 of 328


In the event of replacements becoming necessary on account of short deliveries and
wrong supplies on account of short landing, loss/ damages during transit, storage,
erection and commissioning the Contractor shall take special steps to make such
replacements free of cost for timely commissioning of the equipment. The charges
towards, freight, insurance, port handling clearance customs duty and all other
incidentals including transport to site in respect of such replacements will be to the
account of the Contractor. The Contractor shall take special steps to arrange for most
expeditious manufacture and supply of these items to enable timely commissioning of
the equipment.

Equipment furnished shall be complete in every respect with all mountings, fittings,
fixtures and standard accessories normally provided with such equipment, and/or
needed for erection, completion and safe operation of the equipment. They may
not have been specifically detailed in the respective specifications, unless included in
the list of exclusions. All similar standard components/parts of similar standard
equipment provided, shall be interchangeable with one another. The Contractor shall
not be eligible for any extra payment in respect of such mounting, fixtures and
accessories.

10.9 TYPE, QUALITY OF MATERIALS AND WORKMANSHIP:


i) The Contractor shall be deemed to have carefully examined and to have
knowledge of the equipment, the general and other conditions, specifications,
schedules, drawings, etc. forming part of the Contract and also to have satisfied
himself as to the nature and character of the work to be executed and the type of
the equipment and duties required including wherever necessary of the site
conditions and relevant matters and details. Any information thus procured or
otherwise obtained from Purchaser/ Consultants shall not in any way relieve the
Contractor from his responsibility and contractual obligations for designing,
manufacturing and supplying the Plant and Equipment at site and executing the
work in terms of the Contract. If the Contractor shall have any doubt as to the
meaning of any portion of the Contract, he shall before signing it set forth the
particulars thereof and submit to Purchaser in writing in order that such doubt
may be removed.
ii) The Equipment under scope of supply shall be of the best quality and
workmanship according to the latest engineering practice and shall be
manufactured from materials of best quality considering strength and durability
for their best performance. All material shall be new. Substitution of specified
material or variation from the method of fabrication may be permitted with the
prior written approval of the Purchaser.
iii) The Contractor shall procure and/or fabricate all materials and equipment in
accordance with all requirements of Central and State enactments, rules and
regulations governing such work in India and at site. This shall not be construed
as relieving the Contractor from complying with any requirement of Purchaser as
enumerated in the Contract Specifications which may be more rigid than and not
contrary to the above mentioned rules, nor providing such construction as may be
required by the above mentioned rules and regulations. In case of variance of the
Contract Specification from the laws, ordinance, rules and regulations governing
the work, the Contractor shall immediately notify the same to the Purchaser. It is
the sole responsibility of the Contractor, however, to determine that such variance
exists. Wherever required by rules and regulations, the Contractor shall also
obtain the Statutory Authorities' approval for the plant, machinery and equipment
to be supplied by the Contractor.
125

Page 125 of 328


iv) Codes and standards referred in Contract documents shall be followed. Codes
and standards of other countries can be followed with the prior written approval
of Purchaser, provided materials, supplies & equipment according to the standard
are equal to or better than the corresponding standards specified in the Contract.
v) All meters, gauges, recorders and other types of indicating, integrating or
recording devices shall be calibrated in metric system and degree celsius. Where
vernier attachments are related, English system gearing must be changed to
produce result on a true decimal (metric basis). Functional and instruction plate
shall be in English language.
vi) Brand names mentioned in the Contract documents are for the purpose of
establishing the type and quality of products to be used. The Contractor shall not
change the brand name and qualities of the bought-out-items without the prior
written approval of the Purchaser. All such products and equipment shall be used
or installed in strict accordance with original manufacturer's recommendations,
unless otherwise directed by the Purchaser.

10.10 ENGAGEMENT OF CONSULTANT

The Purchaser has the option to engage a consultant to follow up the progress, inspect
and examine the work during design, manufacture, supply, erection, functional tests
and safety checks, take over test and output guarantee tests or for any other purpose
in connection with the supply and services covered by this Contract. The Contractor
shall properly coordinate with the consultant in the execution of the contract.

10.11 DRAWINGS AND DOCUMENTS

The Contractor shall supply all drawings and documents to the Purchaser / Consultants
as per technical specification.

10.12 DISCREPANICES, ERROR AND OMISSION

i) The Contractor shall be responsible for and shall pay for any alterations of the
works due to any discrepancies, errors or omissions in the drawings,
documents or other particulars supplied by him, whether such drawings or
particulars have been approved by the Purchaser or not, provided that such
discrepancies, errors or omissions be not due to inaccurate information or
particulars furnished to the Contractor by the Purchaser. If any dimensions
figured upon a drawing or plan differ from those obtained by scaling the drawing
or plan, the dimensions as figured upon the drawing or plan, shall be taken as
correct.

ii) The Contractor shall take all corrective measures arising out of discrepancies,
errors and omissions in drawings and other information within the time schedule
and without extra cost to the Purchaser.

iii) The Contractor shall also be responsible for any delay and/or extra cost if any, in
carrying out engineering and site works by other agencies arising out of
discrepancies, errors and omissions as well as of any late revision/s of drawings
and information submitted by the Contractor.

126

Page 126 of 328


10.13 SUB- CONTRACT
i) The Contractor shall not sub-contract the Contract Work in whole to third parties
for the performance of this Contract.
ii) The Contractor may propose a panel of Sub- Contractors as stipulated in the
Technical specification for the part of scope of works. The Contractor shall
thereafter select any sub-Contractor out of this panel subject to the approval of the
Purchaser. Any such assignment shall not relieve the Contractor from any
obligation, duty or responsibility under the contract. Any assignment as above
without the prior concurrence of the Purchaser shall be void.
iii) The Contractor shall be responsible for transmitting all the pertinent data of all
Contract terms and conditions with his Sub-Contractors. The Contractor shall also
furnish the specification, place of manufacture, delivery schedule and adequate,
unpriced copies of supply orders/contract he has entered into in respect of
imported items and adequate copies of un-priced supply order/contract in the case
of indigenous items.
iv) The Purchaser shall give approval for Sub- contractor or shall refuse approval in
writing within 15 days of receipt of request along with all supporting details.
v) Bought-out items, critical components, proprietary items and equipment
manufactured and supplied by specialised manufacturers which the Contractor
intends to incorporate in the Contract Work shall also be subject to the written
approval of Purchaser
vi) The approval extended by the Purchaser in selecting Sub-Contractors
recommended by the Contractor shall not discharge/relieve the later from his
Contract obligations. The Contractor shall remain solely liable for any action,
deficiency, and/or negligence on the part of his Sub-Contractors/sub-suppliers.
vii) In the event certain obligations extended by a Sub-Contractor to the Contractor
should extend beyond the guarantee period specified in the Contract, the
Purchaser shall automatically be entitled to the benefit thereof.
viii) In no event shall the Purchaser be deemed to have any Contractual obligations
whatsoever in respect of Contractor's/ Sub-Contractors and/or title-holders of any
sub-orders placed by the Contractor.

10.14 INSPECTION AND TESTS AT CONTRACTOR'S/MANUFACTURER'S


PREMISES

10.14.1 The Purchaser or his authorised agent / Consultant shall have the right of inspecting
and testing the contract work or any part thereof at any stage during the manufacture
and the Contractor on demand from the Purchaser shall carry out such tests in
appropriate manner in the presence and free of charge to Purchaser. Should the
Contractor himself not be in a position to carry out the tests, he shall, on the
Purchaser's demand prepare specimen and samples and send them at his own cost to
such testing stations as the Purchaser may specify and the cost of the test so effected
shall be to the Contractor's account. However, cost pertaining to the Purchaser's
inspection personnel shall be borne by the Purchaser.
10.14.2 The inspection, examination or testing carried out by the Purchaser shall not relieve
the Contractor from any of his obligations under this Contract. The inspection
procedure will be discussed and finalised.

127

Page 127 of 328


10.14.3 The Contractor shall bear all costs of any and all inspections and tests. Where special
tests in addition to agreed tests are required by the Purchaser, the Contractor shall
bear the cost of the testing provided the Contractor is convinced that within
this/these special test(s) the quality of the equipment in accordance with the
specification can not be proved. If such special tests are necessary based on the
results of the agreed test, then cost of all such special tests shall be to the account of
the Contractor in all cases.
10.14.4 The Purchaser upon giving 7 days notice in writing and stating any grounds of
objection, shall have the right to reject any or all equipment or demand rectification
or replacement thereof.
10.14.5 The Contractor shall give the Purchaser a minimum of 21 days clear notice of any
work being ready for inspection and tests specifying the period likely to be required
for such inspection and tests. Thereafter, the Purchaser or his inspector shall, unless
inspection or test is voluntarily waived, attend at the contractor's or his sub-
contractor's premises, such inspection and tests within 7 days of the date on which
the equipment is notified as being ready for inspection and test. Should the Purchaser
fail to attend such inspection and test, the Contractor may proceed with the
inspection and test at his option and shall forthwith forward to the Purchaser copies
of inspection/test certificates for acceptance by the Purchaser. The proforma and
number of copies for inspection/test certificates shall be mutually agreed. However,
if the Purchaser requests the Contractor for a revised date of inspection but within 15
days of the date of inspection as communicated by the Contractor, the Contractor
shall arrange the inspection on the revised date as requested by the Purchaser.
10.14.6 Necessary facilities shall be provided by the Contractor to the Purchaser and their
Consultants to carry out the inspection. The facilities to be provided shall not
include travel expenses, boarding and lodging.
10.14.7 If during the design stage the Purchaser desires that any modifications are necessary,
the Purchaser shall refer the same to the Contractor and if the Contractor also agrees
that such modifications are necessary, the Contractor shall carry out the same
without any extra cost to the Purchaser. Such modifications which are agreed to
shall be recorded and signed by both the Contractor and the Purchaser.
10.14.8 If the tests were not witnessed by the Purchaser or his representative, the Contractor
can arrange despatch along with the certificate as stated in 10.14.5 with the clear
understanding that if the Purchaser reject such equipment at a later date, the
contractor shall rectify the same at his own cost to the Purchaser's satisfaction. No
equipment shall be shipped or left or otherwise despatched before such certificate
has been issued. The satisfactory completion of these inspection and tests or the
issue of the certificate shall not bind the Purchaser to accept the work, should it on
further tests during or after erection be found not to comply with the Contract.
10.14.9 In case any equipment fails in inspection/tests, re-inspection/retest shall be carried
out only after necessary rectification work/replacement by the Contractor.
10.14.10 In the case of mandatory spares the same shall be offered for inspection along with
the main equipment or after the main equipment has been satisfactorily inspected
and tested.
10.14.11 In the case of such equipment, structurals etc. where tests set forth above cannot be
conducted either partially or fully in Contractor's/ Sub- Contractor's premises but
have to be conducted at site only after erection, the provisions under this schedule
shall also apply. However, in such cases prior approval of the Purchaser shall be
obtained by the Contractor prior to despatch.

128

Page 128 of 328


10.15 STATUTORY AND OTHER REGULATIONS
10.15.1 The Contractor shall comply with all the statutory obligations of Government of
India/State Government applicable at project site and the Purchaser shall not be
liable for any action of the statutes applicable due to non-fulfillment of statutory
obligations by the Contractor.
10.15.2 The Contractor shall give all notices and conform in all respects with the provisions
and pay all fees required to be given or paid under any Central or State statute,
ordinance or other law or any regulation or by-law of any local or other duly
constituted authority in relation to the execution of the Contract Work. The
Contractor shall keep the Purchaser indemnified against all penalties and liabilities of
every kind for breach of any such statute, ordinance, law, rule, regulation or by-law.

10.16 SECRECY TITLES


10.16.1 All maps, plans, drawings, specifications, schemes and the subject matter contained
therein and all other information given to the CONTRACTOR by the Owner in
connection with the performance of the Contract Work shall be held confidential by
the CONTRACTOR and shall remain the property of the Owner and shall not be
used or disclosed to third parties by the CONTRACTOR for any purpose other than
for which they have been supplied or prepared. The CONTRACTOR may disclose to
third parties, upon execution of secrecy agreements satisfactory to the Owner, such
part of the drawings, specifications or information if such disclosure is necessary for
the performance of the Work Contract.

10.16.2 Maps, layouts and photographs of the work or any part thereof including its
surrounding regions showing vital installation for national security of Owners
country shall not be published or disclosed to the third parties or taken out of the
country without prior written approval of the Owner and upon execution of secrecy
agreements satisfactory to the Owner with such third parties prior to disclosure.

10.16.3 The provisions of para 10.16.1 & 10.16.2 shall not apply to information:
i) Which at the time of disclosure are in the public domain- or which later on
become part of public domain through no fault of the party concerned.

ii) Which were in the possession of the party concerned prior to disclosure to him
by the other party, or

iii) Which were received by the party concerned after the time of disclosure without
restriction on disclosure or use from a third party who did not acquire such
information directly or indirectly from the other party.
10.17 REJECTION OF DEFECTIVE WORKS OR OTHER INSTALLATION
10.17.1 If the Contract work or any portion thereof, before it is accepted or taken over, be
defective or fails to fulfill the requirements of the Contract, the Owner shall give the
CONTRACTOR notice setting forth particulars of such defects or failure and the
CONTRACTOR shall forthwith make good the defects or alter the same to make it
comply with the requirements of the Contract. Should he fail to do so within a
reasonable time the Owner may reject and replace at the risk and cost of the
CONTRACTOR the whole or any portion of the work as the case may be, which is
defective or fails to fulfill the requirements of the Contract. However, such rejection/
replacement by the Owner shall not absolve the CONTRACTOR of his
responsibilities under this Contract.

129

Page 129 of 328


10.17.2 Any materials, equipment, etc. brought to site and found to be not in accordance with
the contract, shall be rejected by the Owner and the CONTRACTOR shall remove
the materials from site within the period specified by the Owner. Should the
CONTRACTOR fail to do, the Owner may remove the same at the risk and cost of
the CONTRACTOR.
10.17.3 In the event of such rejection, the Owner shall be entitled to the use of the work in a
reasonable and proper manner for a time reasonably sufficient to enable him to get
the replacement.

10.17.4 The CONTRACTOR shall not be entitled to any extension of time or extra cost for
rejection as per 10.17.1 and 10.17.2 above.
10.18 NEGLIGENCE
10.18.1 If the CONTRACTOR shall neglect to execute the work with due diligence or
expedition or shall refuse or neglect to comply with any reasonable order given to
him in writing by the Owner in connection with the work or shall contravene the
provisions of Contract, the Owner may give notice in writing to the CONTRACTOR
calling upon him to make good the failure, neglect or contravention complained of
within such time as may be deemed reasonable and in default of this compliance
with the said notice, the Owner without prejudice to his rights under clause 10.18.2
hereto, may rescind or cancel the Contract as provided in Cl.10.36 holding the
CONTRACTOR liable for the damages that the Owner may sustaining this behalf.
The making good of the failure, neglect or contravention hereunder will be governed
by clause 10.17.1. In addition the Contractor shall refund all the amounts paid to him
by the Purchaser for all such work which may become in fructuous due to such
cancellation.
10.18.2 Should the CONTRACTOR fail to comply with such notice within a reasonable
period from the date of serving the Notice thereof in the case of failure, neglect or
contravention capable of being made good within that time or otherwise within such
time as may be reasonably necessary for the same making good then and in such case
without prejudice to the Owner's right under clause 10.18.1 hereto the Owner shall
have at his option the right to take the work wholly or in part out of the
CONTRACTOR's hands and may complete the work envisaged in the contract either
departmentally or by awarding a fresh Contract at a reasonable price with any other
persons to execute the same or any part thereof and provide other materials, tools,
tackle or labour for the purpose of completing the work or any part thereof
10.18.3 In such event the Owner shall, without being responsible to the CONTRACTOR for
fair wear and tear of the same, be entitled to seize and take possession and have free
use of all materials, tools, tackle or other things which may be on the site for use at
any time in connection with the work to the exclusion of any right of the
CONTRACTOR over the same and the Owner shall be entitled to retain and apply
and balance sum which may otherwise be then due on the Contract by him to the
CONTRACTOR or such part thereof as may be necessary to the payment of the cost
of execution of such work as aforesaid
10.18.4 If the cost of executing the work as aforesaid shall exceed the balance due to the
CONTRACTOR and the CONTRACTOR fails to make good the deficit the said
materials, "tools, tackle, construction plant or other things, the property of the
CONTRACTOR as may not have been used up in the completion of the works, may
be sold by the Owner and the proceeds applied towards the payment of such
difference and the cost of and incidental to such sale, any outstanding balance
130

Page 130 of 328


existing after crediting the proceeds of such sale be paid by the CONTRACTOR on
the certificate of the Owner, but when all expenses, cost and charges incurred in the
completion of the work are paid by the CONTRACTOR, all such materials, tools,
tackle, construction plant or other things not used in the completion of the works and
remaining unsold shall be removed by the CONTRACTOR.
10.19 Indemnity Bond
For the equipment handed over to Contractor, for performing the work under this
contract, Contractor shall execute a custody and indemnity bond in favour of
Purchaser as per Appendix-E. The endorsement and handing over of despatch
documents by purchaser to Contractor shall be construed as having handed over and
entrusted to the Contractor all the equipments covered in such despatch documents.

10.19.1 The Contractor shall hold the equipments handed over to him by Purchaser, as
trustee on behalf of the Purchaser without having any lien or charge against the
equipment at any stage. For any loss or damage to the equipment and material till
these are finally taken over by Purchaser, the Contractor shall immediately
replace/repair the loss or damaged equipment entirely at his cost irrespective of the
extent and/or time of realisation of claims by him from the insurer/underwriters.

10.19.2 The title of ownership and property to all goods materials equipment etc. originating
in India shall pass to the purchaser as per the terms and conditions of this contract
after the Contractor has effected the despatch of the same to Project site and the
Contractor has prepared necessary documentation for handing over the same to
NLCIL's authorised representative provided however, such passing of titles of
ownership and property to the Purchaser shall not in any way absolved, dilute or
diminish the responsibility and obligations of the Contractor under this Contract
including loss or damage and all risks which shall vest with the Contractor till the
successful commissioning and final Take over as per the Contract.

10.20 Indemnity
10.20.1 The Contractor shall at all times indemnify and keep indemnified the Purchaser
against all claims which may be made against the Purchaser in respect of any
infringement of any rights protected by patent registration of design of trade mark. In
this connection, the Purchaser shall pass on all claims made against him to the
Contractor for settlement.

10.20.2 The Contractor assumes responsibility for and shall indemnify and save harmless the
Purchaser from all liability, claims, costs, expenses, taxes and assessments including
penalties, punitive damages, attorney's fees and court costs which are or may be
required to be paid by the Purchaser arising from any breach of the Contractor's
obligations under the Contract or for which the Contractor has assumed
responsibilities under the Contract including those imposed under any Contract local
or national law or laws, or in respect to all salaries, wages or other compensation or
all persons employed by the Contractor or his Associate(s)/Sub-Contractors or
suppliers in connection with the performance of any work covered by the Contract.
The Contractor shall execute, deliver and shall cause his Sub- Contractor and
suppliers to execute and deliver, such other further instruments and to comply with
all the requirements of such laws and regulation as may be necessary there under to
conform and effectuate the Contract and to protect the Purchaser.

131

Page 131 of 328


10.21 INDEMINITY BOND FOR O&M
i) The successful bidder shall execute indemnity bond against loss or damage of the
Solar PV Power Plant with all associated materials/equipments after 12 (Twelve)
months of provisional take over and before the expiry of warranty period for an
amount equivalent to the project cost which is valid till the expiry of the O&M
period (10) Ten years. The Indemnity Bond has to be executed by the successful
Bidder in the manner specified by Purchaser.

ii) The said contractor hereby agreed to maintain the Solar PV Power Plant as per
conditions of O&M agreement and his possession in trust for the Purchaser as
their property until such time the O&M period is completed and the plant is
handed over back to the authorised representatives of the Purchaser as per the
terms of the Agreement.
iii) The said contractor further agree to hold the Purchaser harm less and free from all
liabilities for all losses, damages, etc., arising from any cause, whatsoever to the
material while in his possession, and further under takes to indemnify and
reimburse the Purchaser to the extent of loss or damage caused to the materials or
any loss or any claims to the Purchaser in respect of the said material during
O&M period.

10.22 ACCEPTANCE OF THE SYSTEM


10.22.1 Mechanical Completion
1. On completion of erection of all the materials / items of equipment covered
under the scope of the Contract, a joint inspection shall be carried out by the
Purchaser and the Contractor to verify physically that all materials /items /
equipment have been placed and erected properly and the system is ready for
commissioning. A defects list shall be prepared jointly.
2. On liquidation of the defects (except minor defects which shall be mutually
discussed and agreed between the Purchaser and Contractor and which shall not
affect the commissioning of the system), Mechanical Completion Certificates
shall be issued by the Purchaser.

10.22.2 Commissioning & PG Testing


1. Commissioning shall include testing of individual sub systems till the
successful completion of commissioning of the entire Solar PV Power plant
along with power evacuation system and exporting power to the grid.
2. Commissioning shall include all activities after mechanical completion up to
commencement of power export and shall include mechanical and electrical
checkouts, calibration of instruments and protection devices, commissioning of
sub/supporting system and charging the Plant/System/Equipment after getting
statutory clearance(s), safety certificate etc., by the contractor from State/
Central Government authorities covered under the Contract.
3. Commissioning shall include all activities after completion of testing and shall
be the integral operation of the complete System / Equipment covered under the
Contract which shall include no-load / partial load / full load runs for
mechanical/electrical try-out and gathering of operational data, calibration
setting and commissioning of control systems and shut-down inspection and
adjustment after running trial of the System / Equipment covered under the
Contract.

132

Page 132 of 328


After completion of the commissioning, the Contractor has to intimate the
Purchaser in writing regarding the readiness of the system for PG Testing.
However, Contractor has to furnish sufficient records/documents to satisfy the
Purchaser that all the equipment including services, metering and
instrumentations are tested and ready for PG testing.
Before the commissioning of the plant, the power evacuation system along with
the billing and metering with grid tie up shall be on operation. During the
commissioning, the Contractor shall be allowed to make minor adjustments as
may be necessary, provided that such adjustments do not interfere with or prevent
the operation of the plant.
During PG testing period, the contractor shall post sufficient number of qualified
personnel. The onus of proving that any failure is not due to faulty design,
materials and workmanship shall lie with the Contractor.
4. A commissioning report comprising observations and recordings of various
parameters measured in respect of the ‘reliability operation’ shall be prepared
and submitted to the Purchaser. This report, besides recording the details of
various observations during operation shall also include the dates of start and
finish of the operation and shall be signed by the representatives of both the
parties. The report shall have recordings of all details of interruptions that
occurred, adjustments made and any repairs done during the commissioning.
The commissioning shall be considered successful, provided that each item of
plant can meet the specified requirements.
5. On successful completion of commissioning, the Solar PV Power Plant along
with Power Evacuation system shall be Provisionally Taken over with a list of
major and minor defects and non conformities prepared jointly by the Purchaser
and the Contractor. Differentiation of defects as major and minor shall be jointly
discussed and agreed by the Purchaser and Contractor and recorded. Upon the
completion of commissioning, as soon as practicable, or at such time as may be
otherwise agreed to by the parties concerned, the Contractor Shall notify in
writing to the Purchaser /Consultant that the plant is ready for Performance
Guarantee Test only after liquidating all the major defects.
6. Readiness for "Performance Guarantee Test" shall be intimated to the
Purchaser in writing at least 15 days before commencement of "Performance
Guarantee Test". However, Contractor shall be allowed to conduct
"Performance Guarantee Test" only after liquidating all the major defects.
7. The Performance Guarantee Test shall be conducted at site for the entire system
by the Contractor. The Contractor shall make the plant ready for such test and
carry out all operation and maintenance activities during the test. The test shall
be commenced after the ‘Plant / Equipment’ has attained stable operation The
date of commencement of the Performance Guarantee Test shall be after
attending all the pending works if any and major/minor defects or as may be
mutually agreed upon between the Contractor and Purchaser. The defects / non-
completion of work which will directly affect the power generation,
performance / safety of the equipment, safety of the personnel will be included
under major defect / major work and the other will be included in the minor
defect / minor work. The tests shall be binding on both the parties of the
‘Contract’ to determine compliance of the ‘Plant’ / ‘Equipment’ with the
performance guarantee. The purpose of the Performance Guarantee Test is not
only to check whether the plant meets the guaranteed generation but also
provide a stable operation of the whole plant and exporting power to the grid

133

Page 133 of 328


which shall serve as reference to evaluate the plant performance in future over
the plant life.
8. In case of delay in conducting the Performance Guarantee Test due to reasons
attributable to the Contractor, ageing factor shall not be considered during
"Performance Guarantee Test". However, the contractor has to commence the
performance guarantee test within one year from the date of completion of
commissioning, failing which, it shall be construed that the guaranteed
generation has not been met and liquidated damages for shortfall in generation
shall apply in full subject to the condition that delay in carrying out performance
guarantee test is attributable to the contractor. However, the purchaser shall
retain the option to reject the equipment, if necessary. Results of the
Performance Guarantee Test shall be submitted within 15 days of completion of
Performance Guarantee Test to the Purchaser for review and approval. The
approval shall be given within 30 days of submission of results.
9. The Performance Guarantee Test procedure, including the definition of the
calculation method to be used, the instrumentation to be installed and indicated
in the schemes, the instrument accuracy classes, and calibration of instruments
during the test period, the areas of responsibility and the items which
specifically require preparation and agreement shall be submitted by the
Contractor for review and approval by the Purchaser /Consultant during detail
engineering phase. Schematics identifying the guarantee test instrumentation
shall be submitted along with procedure. It shall be ensured that necessary test
points are indicated in the schemes during the detail engineering phase and also
identified in the instrumentation and metering drawings. Contractor shall
furnish detail program during detail engineering stage.
10. The Performance Guarantee Test instruments shall be of precision type with
instrument accuracy limits as required and defined in the Technical
specification. The Performance Guarantee Test shall be carried out as per test
procedures and codes agreed in the Technical specification of performance
guarantees.
11. All test instrumentation for the Performance Guarantee Tests as required shall
be supplied by the Contractor. Data loggers shall be used for performance test.
All costs associated with the supply, calibration, installation of the test
instrumentation / data loggers / computers etc. are deemed to have been
included in the contract price. The test shall be in accordance with those
specified in the Technical specification.
12. Any special equipment, tools and tackles required for successful completion of
the Performance Guarantee Test shall be provided by the Contractor.
13. It is the Contractor’s responsibility to co-ordinate for suitably carrying out the
Performance Guarantee Test.
14. The plant parameters during the Performance Guarantee Test shall be adjusted
as far as practicable to the guaranteed Performance Guarantee Test conditions.
The test shall be conducted to prove guaranteed generation as defined in the
Technical specification.
15. The Performance Guarantee Test results shall be reported as computed from the
Performance Guarantee Test observations.
16. Within one week after the conclusion of the Performance Guarantee Test the
Contractor shall submit a test report to the Purchaser with a copy submitted to
the Consultant stating:
(a). In the case of a Performance Guarantee Test, whether the Solar PV
power plant passed or failed such test, accompanied by sufficient test
134

Page 134 of 328


data and calculations to demonstrate the level of performance attained
with respect to each of the tested parameters.
(b). The reports shall include as a minimum, the following:
(i). Description of the test procedures
(ii). Standards that were used
(iii). Instrumentation details and calibration
(iv). Full schematic diagrams with indication of instrument test
location and identification tag of same.
(v). Test logs and summary of test readings used for performance
calculations
(vi). Full set of data logger readings
(vii). Computation of test results.
(viii). Conclusions of Performance Guarantee Tests : test passed or not
17. Within two weeks of receipt such test report, the Purchaser /Consultant shall
either:
(i). Concur with the information provided in the Contractor’s test report, or
(ii). Disputes some or all of the information provided in the Contractor’s test
report, the areas being disputed, and the levels of performance being
disputed.
18. If the tests could be carried out but are being unduly delayed by the Contractor
the Purchaser may, by notice require the Contractor to make the tests within 14
days after the receipt of such notice. The Contractor shall make the tests on such
days within that period as the Contractor may fix and of which he shall give
notice to the Purchaser.
19. If the Contractor fails to make the tests within 21 (twenty one) days of such
notice the Purchaser may himself proceed with the tests. All tests so made by
the Purchaser shall be at the risk and cost of the Contractor and the cost thereof
shall be deducted from the contract price or charged to the Contractor. The tests
shall then be deemed to have been made by the Contractor.
20. If the Purchaser /Consultant and the Contractor disagree on the interpretation of
the test results, each shall give a statement of his views to the other within 14
(fourteen) days after such disagreement arises. The statement shall be
accompanied by all relevant evidence. If Purchaser disputes any or all of the
results contained in the Contractor’s test report, representatives of the
Contractor, Purchaser and the Consultant shall meet after the receipt of the
Purchaser’s notice at a mutually acceptable date & location to review and
discuss the dispute. Mutual discussions will be held and agreed to determine the
interpretation of the test results.
10.22.3 Final Take Over
1. After successful completion of Performance Guarantee Test, the Entire Plant
shall be taken over and 10 years (Ten years) O & M period starts from this date
of Final Take Over.
2. Till the ‘Final Take Over’ the Contractor shall carry out O & M of the Entire
Plant.
3. Any non-conformity arising in the system and any rectification in the
dismantling works till ‘Final Take Over’ shall be rectified by the Contractor at
his own cost Purchaser shall not be held responsible for any such non-
conformities arising during this period.
4. In case any stoppages are required for repairing/ replacing the parts of the
135

Page 135 of 328


system by the Contractor, the same shall be carried out within a reasonable time.
5. Certificate for "Final Take Over" shall be issued by the Purchaser when
(a) All supplies and services have been completed as per Contract.
(b) The Contractor has met any and all obligations under this Contract.
(c) Final balance documentation, if any, incorporating latest modifications in
‘as built’ drawings has been submitted by the Contractor in requisite
copies.
(d) The Contractor has rectified in a definite manner all objections /
observations mentioned in the "Commissioning Certificate" and ‘Final
Project Punch List’
10.24 REPLACEMENT OF DEFECTIVE PARTS AND MATERIALS
10.24.1 If during the progress of the supplies / works the Purchaser or the Consultant shall
decide and inform in writing to the Contractor that the Contractor has
manufactured any plant /machine or part of the plant machine unsound or imperfect
or has furnished any plant /machine inferior to the quality specified, the
Contractor, on receiving details of such defects or deficiencies shall at his own
expense, within 7 days of his receiving the notice, or otherwise, within such
time as may be reasonably necessary for making it good proceed to alter,
reconstruct or remove such work and furnish fresh equipment upto the standards
of the specifications. In case the Contractor fails to do so, the Purchaser may on
giving the Contractor 7 days notice in writing of his intentions to do so, proceed to
remove the portion of the work so complained of and at the cost of the
Contractor, perform all such work or furnish all such equipment provided that
nothing in this clause shall be deemed to deprive the Purchaser of or affect any
right under the Contract which the Purchaser may otherwise have in respect of
such defects and deficiencies.
10.24.2 As the 50%/60% of Contract price of the components that were found defective
has already been received by the Contractor, the Contractor shall pay interest for the
entire amount received for the defective components noticed at the prevailing
bank rate for the duration of such rectification/ replacement of the defective part
i.e., for the period between the date of intimation by the Purchaser about the
defective part and the date of effecting the corrected supplies after rectification/
replacement to the satisfaction of the Purchaser. This will be in addition to the
Liquidated Damages for delay in supplies and/or commissioning envisaged
elsewhere in this Contract, if applicable and also the extra expenditure incurred as
per Cl.10.24.1
10.24.3 The Contractor's full and extreme liability under this clause shall be satisfied by
the Payment to the Purchaser of the extra cost, of such replacements procured
as provided for in the Contract, such extra costs being the ascertained difference
between the price paid by the Purchaser for such replacements and the Contract
price portion for such defective plants and repayments of any sum paid by the
Purchaser to the Contractor in respect of such defective plant. Should the
Purchaser not so replace the defective plant, the Contractor's extreme liability under
this clause shall be limited to repayment of all sums paid by the Purchaser under the
Contract for such defective Plant.
10.24.4 If the material/equipment or any portion thereof is found damaged or not received at
site, on verification jointly by the Purchaser and Contractor of the materials received
and stored the replacement of such material/equipment shall be effected by the
Contractor within a reasonable time to avoid unnecessary delay in the
commissioning of the equipment.
136

Page 136 of 328


10.25 HINDRANCES
10.25.1 Events that caused hindrance to proceed and progress with the work shall be
recorded daily and signed by the Construction Dept and the Contractor. The Project
Coordination Committee shall take these data for settling the issues.
A record of events shall be maintained by the contractor as under with the Signature
of the Contractor and the NLCIL against each case.

HINDRANCE RECORD REGISTER


Name of work: Value of Contract:
Name of Contractor: Scheduled date of Completion:

Signature of the

Period (if any)


Description of

Over lapping

Contractor/

Contractor
Hindrance

Purchaser

Purchaser
Duration

Delay by
Remedy
Sl. No.

10.25.2 The details of Hindrance Register along with the relevant factors will be taken into
consideration for determining extension of time to the contract /LD.

10.26 FORCE MAJEURE:

10.26.1 Definition: “Force Majeure” means any act, circumstance or event or a combination
of acts, circumstances and events which wholly or partially prevents or delays the
performance of obligations arising under this Agreement if such act, circumstance or
event is not reasonably within the control of and not caused by the fault or
negligence of the non-performing Party, and provided that such act, circumstance or
event is in one or more of the following categories:

i) Flood, drought, lightning, cyclone, earthquake, Tsunami or geological


disturbances, eruption of gases and such like natural occurrences.

ii) Major explosion, fire and contamination of atmosphere by radio active or


hazardous substances. Accidents and disruptions including but not limited to
fires, explosions.

iii) Transportation delay due to force majeure.

iv) Civil disturbance including riot, terrorism, rebellion, sabotage and communal
clashes, war, civil commotion, Acts of God or the public enemy.

v) Piracy.

137

Page 137 of 328


vi) Any law, ordinance or order of the Central or State Government, or any
direction of a statutory regulatory authority that prohibits or restricts
performance of the obligations hereunder

Provided that a Force Majeure act, circumstance or event shall not include economic
hardship, equipment failure/breakdown, or power failure/breakdown, or failure in
water supply other than as specifically set forth above.

10.26.2 Burden of Proof


The issue as to whether there is a Force Majeure condition or not and whether
extension of time shall be granted or not shall be mutually discussed and agreed
upon. However, the decision of NLCIL shall be final. The burden of proof as to
whether a Force Majeure act, circumstance or event has occurred shall be upon the
Party claiming the occurrence or existence of such Force Majeure act, circumstance
or event.

10.26.3 Effect of Force Majeure

If either Party is rendered wholly or partially unable to perform its obligations under
this Agreement because of a Force Majeure act, circumstance or event, that Party
shall be excused from whatever performance is affected by the Force Majeure act,
circumstance or event to the extent so affected, provided that

(a) Within five (5) Business Days after the occurrence of the inability to perform
due to a Force Majeure act, circumstance or event, the non-performing Party
provides a written notice to the other Party of the particulars of the occurrence,
including an estimation of its expected duration and probable impact on the
performance of its obligations hereunder, and continues to furnish periodic
reports with respect thereto, every 7 days, during the period of Force Majeure;
(b) the non-performing Party shall use all reasonable efforts to continue to perform
its obligations hereunder and to correct or cure as soon as possible the act,
circumstance or event constituting the Force Majeure;
(c) The suspension of performance shall be of no greater scope and no longer
duration than is reasonably necessitated by the Force Majeure act, circumstance
or event;
(d) The non-performing Party shall provide the other Party with prompt notice of
the cessation of the Force Majeure act, circumstance or event giving rise to the
excuse from performance and shall thereupon resume normal performance of
obligations under this Agreement with utmost promptitude;
(e) The non-performance of any obligation of either Party that was required to be
performed prior to the occurrence of a Force Majeure act, circumstance or event
shall not be excused as a result of such subsequent Force Majeure act,
circumstance or event.
(f) The occurrence of a Force Majeure act, circumstance or event shall not relieve
either Party from its obligations to make any payment hereunder for
performance rendered prior to the occurrence of Force Majeure or for partial
performance hereunder during periods of Force Majeure;
(g) The Force Majeure act, circumstance or event shall not relieve either Party from
its obligation to comply with Applicable Laws;

138

Page 138 of 328


(h) The non-performing Party shall exercise all reasonable efforts, at their own
expense, to mitigate or limit damages to the other Party;
(i) No increase in Contract Price shall be payable due to Force Majeure act, event,
etc. However any benefit of price fall shall be passed on to the NLCIL.
10.27 DEFENCE OF SUIT

10.27.1 If any action in court is brought against the Purchaser or any officer or agent of
the Purchaser for the failure, omission or neglect on the part of the Contractor to
perform any acts, matters, covenants or things under the Contract or for damage or
injury caused by the alleged omission or negligence on the part of the Contractor,
his agents, representatives or his sub-Contractors or in connection with any claim
based on lawful demands of sub-Contractors, workmen, suppliers or employees,
the Contractor shall in all such cases indemnify and keep the Purchaser and/or his
representatives harmless from all losses, damages, expenses or decrees arising out
of such action.

10.27.2 The Purchaser shall have full power and right at his discretion to defend or
compromise any suit or pay claims or demand brought or made against him as
aforesaid whether pending or threatened, as he may consider necessary or
desirable and shall be entitled to recover from the Contractor all sums of money
including the amount of damages and compensation and all legal costs, charges
and expenses in connection with any compromise or award which shall not be
called into question by the Contractor and shall be final and binding upon him. If
the Purchaser decides not to defend or decides to compromise any suit or pay claim,
the Contractor will be kept advised before such action by the Purchaser.

10.28 LIMITATIONS OF LIABILITY

10.28.1 Except in case of Criminal Negligence or Willful Misconduct,


i) The Contractor shall not be liable to the Purchaser, whether in Contract, tort, or
otherwise, for any indirect or consequential loss or damage, loss of use, loss of
production or loss of profits or interest, costs, provided that this exclusion shall
not apply to any obligation of the Contractor to pay liquidated damages to the
Purchaser
and
ii) The aggregate liability of the Contractor to the Purchaser, whether under the
Contract, in tort or otherwise, shall not exceed the total Contract Price, provided
that this limitation shall not apply to any obligation of the Contractor to
indemnify the Purchaser with respect to Patent infringement’.

10.29 SECRECY, TITLES AND RELEASE OF INFORMATION

10.29.1 All maps, plans, drawings, specifications, schemes and the subject matter contained
therein and all other information given to the Contractor by the Purchaser in
connection with the performance of the Contract Work shall be held confidential by
the Contractor and shall remain the property of the Purchaser and shall not be used
or disclosed to third parties by the Contractor for any purpose other than for which
they have been supplied or prepared. The Contractor may disclose to third parties,
upon execution of secrecy agreements, such part of the drawings, Specifications or
information if such disclosure is necessary for the performance of the Work.

139

Page 139 of 328


10.29.2 The Contractor shall not communicate or use in advertising, publicity, sales,
releases or in any other medium, photographs or other reproduction of the `Works'
under this `Contract' or descriptions of the `Site' dimensions quantity, quality or
other information concerning the `works' unless prior written permission has
been obtained from the Purchaser.

10.30 ENFORCEMENT OF TERMS


10.30.1 The failure of either party to enforce at any time any of the provisions of this
Contract or any rights in respect thereto or to exercise any option herein
provided, shall in no way be construed to be a waiver of such provisions, rights or
options or in any way to affect the validity of the Contract. The exercise by either
party of any of its rights herein shall not preclude or prejudice either party from
exercising the same or any other right it may have hereunder.
10.30.2 The validity of the Contract shall not be affected, should one or more of its
stipulations be or become legally invalid and such stipulation is severable from and
not fundamental to the obligations of either party to this Contract. In such a case, the
parties shall negotiate in good faith to replace the invalid clause by an agreed
stipulation which is in accordance with the applicable law and which shall be as
close as possible to the parties original intent.

10.31 NO WAIVER OF RIGHTS

10.31.1 Neither the inspection by the Purchaser or the Consultant or any of their officials,
employees, or agents nor any order by the Purchaser or the Consultant for
payment of money or any payment for or acceptance of the whole or any part of the
`works' by the Purchaser or the Consultant, nor any extension of time, nor any
possession taken by the Purchaser shall operate as a waiver of any provision of the
`Contract' or of any power herein reserved to the Purchaser or any rights to damages
herein provided nor shall any waiver of any breach in the `Contract' be held to be a
waiver of any other or subsequent breach.

10.32 POWER TO VARY OR OMIT


10.32.1 No alterations, amendments, omissions, suspensions or variations of the works
(hereinafter referred to as `variation') under the Contract as detailed on the
Contract documents shall be made by the Contractor except as directed in writing
by the Purchaser but the Purchaser shall have full power subject to the provision
hereinafter contained from time to time during the execution of the Contract by
notice in writing to instruct the Contractor to make such variation without
prejudice to the Contract. The Contractor shall carry out such variation and be
bound by the same conditions as far as applicable as though the said variations
occurred in the Contract documents. If any suggested variations would, in the
opinion of the Contractor, if carried out prevent him from fulfilling any of his
obligations or guarantees under the Contract he shall notify the Purchaser thereof
in writing and the Purchaser shall decide forthwith whether or not, the same shall
be carried out and if the Purchaser confirms his instructions the Contractor`s
obligations and guarantees shall be modified to such an extent as may be
mutually agreed. Any agreed difference in cost occasioned by any such variation
shall be added to or deducted from the Contract price as the case may be.

140

Page 140 of 328


10.32.2 In the event of the Purchaser requiring any variation, such reasonable and proper
notice shall be given to the Contractor to enable him to work his arrangements
accordingly and in cases where goods or materials are already prepared or any
design, drawings, or pattern made or work done requires to be altered, a reasonable
and agreed sum in respect thereof shall be paid to the Contractor.

10.32.3 In any case in which the Contractor has received instruction from the Purchaser
as to the requirement of carrying out the altered or additional substituted work
which will in the opinion of the Contractor, involve a claim for additional
payments, the Contractor shall immediately and in no case later than 30 days after
receipt of the instructions advise the Purchaser to that effect. But the Purchaser
shall not become liable for the payment of any charges in respect of any such
variations, unless the instructions for the performance of the same shall be
confirmed in writing by the Purchaser within 30 days of such advice after mutual
discussion and agreement.

10.32.4 If any variation in the works results in reduction of Contract price the parties shall
agree so in writing to the extent of any change in the price before the Contractor
proceeds with the change.

10.33 PATENT RIGHTS AND ROYALTIES

10.33.1 Royalties and fees for patents covering materials, articles, apparatus, devices,
designs, equipment or processes used in the works shall be deemed to have been
included in the Contract Price. The Contractor shall satisfy all demands that may be
made at any time for such royalties or fees and he alone shall be liable for any
damages or claims for patent infringements and shall keep the Purchaser,
indemnified in that regard. The Contractor shall at his own cost and expenses
defend all suits or proceedings that may be instituted for alleged
infringements of any patent involved in the works and, in case of an award of
damages the Contractor shall pay for such award. In the event of any suit or other
proceedings instituted against the Purchaser, the same shall be defended at the
cost and expenses of the Contractor who shall also satisfy/comply any decree,
order or award made against the Purchaser. But, it shall be understood that no
such machine, plant, work, material or thing has been used by the Purchaser for
any purpose or any manner other than that for which they have been furnished and
installed by the Contractor and specified under these specifications. Final
payment to the Contractor by the Purchaser will not be made while any such suit or
claim remains unsettled. In the event of any apparatus or equipment or any
part thereof furnished by the Contractor is in such suit or proceedings held to
constitute infringement, and its use is enjoined, the Contractor shall at his option,
and at his own expense, either procure for the Purchaser the right to continue the
use of the said apparatus/ equipment or part thereof, replace the equipment or
modify it so that it does not constitute infringement.

10.33.2 The Contractor shall indemnify and keep indemnified the Purchaser, his successors
or assigns for and against any and all claims, suits, damages,, losses, actions,
demands, costs, charges, royalties and expenses arising from or for infringement.

141

Page 141 of 328


10.34 Warranty
1. The Contractor shall guarantee that the equipment shall be new and in
accordance with the Contract documents and be free from defects in design,
material and workmanship. The warranty period in general shall be 12 (twelve)
months from the date of Provisional Take Over. PG test period for one year and
Warranty period shall be in concurrence with each other. If the PG test results
fail and the test is carried out again, accordingly warranty period shall also get
extended accordingly. Warranty period will be getting extended till the
acceptance of PG test results. The Contractor's liabilities shall be limited to the
replacement of any defective parts in the equipment of his own manufacture or
those of his Sub-Contractors, under the normal use and arising from faulty
design, materials and/or workmanship. The plant shall be operated as per the
operating instructions and all records, log books and other information about the
operation shall be kept. Such replaced defective parts shall be taken back by the
Contractor. The Contractor shall carry out operation and maintenance of the
entire Solar PV Power Plant and Power evacuation system including Civil
maintenance, Horticulture maintenance and Security during the warrantee
period.
2. The Contractor shall carry out all the maintenance works including repairs and
/or replacement until acceptance of PG test results to fulfil the warranty
obligations. The Contractor shall provide O & M personnel as required to till
the completion of warranty period.
3. In the event of any emergency where, in the judgment of the Purchaser or the
Consultant, delay would cause serious loss or damage, repairs, replacements or
adjustments may be made by the Purchaser or the Consultant or a third party
chosen by the Purchaser or the Consultant with advance notice indicating the
reasonable time required to the Contractor and the cost of such work shall be
paid by the Contractor, or by the Surety. In the event of such action being taken
by the Purchaser or the Consultant, the Contractor shall be notified promptly
and he shall assist wherever possible in making the necessary corrections. This
shall not dilute the Contractor's liability under the terms and conditions of the
Contract.

4. If it becomes necessary for the Contractor to replace or renew any defective


portions of the plant under this clause, the provisions of this clause shall apply
to the portion of the plant so replaced or renewed until the expiry of 12 months
from the date of such replacement or renewal. If any defects be not remedied
within a reasonable time, the Purchaser or the Consultant may proceed to do the
work at the Contractor's risk and costs, but without prejudice to any other rights
which the Purchaser may have against the Contractor in respect of such defects.
5. The repaired or new parts shall be furnished and erected free of cost at site by
the Contractor. If any repair is carried out on his behalf at the site, the
Contractor shall bear the cost of such repair.
6. The cost of any special or general overhaul rendered necessary during the
guarantee period due to defects in the plant or defective work carried out by the
Contractor shall be borne by the Contractor.
142

Page 142 of 328


7. The acceptance of the equipment by the Purchaser or the Consultant shall not in
any way relieve the Contractor of his obligations under this clause.
8. In case of these defective parts which are not repairable at site but are essential
for the commercial use of the equipment, the Contractor and the Purchaser or
the Consultant shall mutually agree to a programme of replacement or renewal
which shall minimise interruption to the maximum extent, in the operation of
the equipment.
9. At the end of the warrantee period and on successful completion of PG test, the
Contractor's liability ceases except for latent defects.
“Latent Defect” means any repeated defect or repeated adjustment in the
equipment / system which was not revealed in the normal standard inspection
checklist of manufacture, erection and operation, but exhibits as observation or
as deviation in operation parameters or as repetitive failure of certain
components after Warranty Period and when variations in operating conditions
are experienced and ultimately could be solved only by replacement or repair /
correction of equipment or parts of equipment.”
For latent defects, the liability period shall be upto 3 (Three years) years after
the expiry of the guarantee period. In respect of goods supplied by the Sub-
vendors and Sub-Contractors to the Contractor where a longer guarantee (more
than 12 months) is provided by such Sub- vendors and Sub-Contractors, the
Purchaser shall be entitled to the benefit of such longer guarantee.
The equipment shall be operated as per the Original Equipment Manufacturer’s
O&M Manual and standard O & M practices being followed for Solar PV
Power Plants and power evacuation systems.
10. All costs on account of these warranty obligations shall be to the account of the
Contractor.
11. The Contractor should furnish an Indemnity Bond in the prescribed format as
enclosed for the equipment to be taken away from Project site for
repair/rectification.
12. Defect Liability for Civil Works
(a). The Contractor guarantees that within one year from the date of work
completion certificate or in the event more than one certificate having been
issued by the Purchaser from the respective date so certified, the contract
work shall not show any sign of defects, cracks, settlements, disfiguration,
shrinkage, leakage, dampness or any other faults.
(b). The Contractor shall maintain and satisfactorily execute at his own cost all
such works of repair, amendment, reconstruction, rectification, replacement
and any other work to make good any faulty work during the defect
liability period.
(c). The Contractor shall, if required by the Purchaser, search for the causes of
any defects, imperfection or fault under the direction of the Purchaser. The
cost of such work shall be borne by the Contractor.
(d). At intervals specified by the Purchaser, the Contractor along with the
Purchaser shall inspect the contract work to satisfy himself that no defects
have cropped up in the contract work. Should there be any signs of defects;
143

Page 143 of 328


the Contractor shall take immediate steps to rectify the same.
(e). At the end of the defect liability period, the Contractor along with the
Purchaser shall carryout final inspection of the contract work to prove that
no defects had appeared in the contract work or that all defects which
appeared in the contract work have been rectified to the satisfaction of the
Purchaser. If during the final inspection it is found that the defects still
remain in the contract work, the period of defect liability shall be extended
for further period, which will be mutually discussed and agreed, for
rectifying the defects and the Contractor shall be liable to make good the
defects and be responsible for the maintenance of the work till the defect
have been fully removed.
(f). To the intent that the works shall or as soon as practicable after the
expiration of defect liability period be handed over to the Purchaser in
perfect condition to the satisfaction of the Purchaser, all such repair works
as stated herein above, shall be carried out by the Contractor at his own
expense if the necessity thereof shall in the opinion of the Purchaser be due
to the use of materials or workmanship not in accordance with the contract
or failure on the part of the Contractor to comply with any obligation
expressed or implied on Contractor's part under contract.
(g). If the Contractor fails to commence rectification of such defects within 14
(fourteen) days from the date of Notice by the Purchaser or does not
complete the said rectification with diligence and within mutually agreed
time period, the Purchaser shall be entitled to carryout such work by his
own workmen or by other Contractors and if such work is the work which
the Contractor should have carried out at his own cost, the Purchaser shall
be entitled to recover from the cost thereof or may deduct the same from
any money due or that become due to the Contractor.
(h). Upon the successful completion of defect liability period, the Purchaser
shall issue final acceptance certificate to the Contractor along with the final
take over.
10.35 CONTRACTOR`S DEFAULT
10.35.1 If the Contractor shall neglect to execute the `Works' with due diligence and
expedition or shall refuse or neglect to comply with any reasonable orders given to
him, in writing by the Purchaser in connection with the `Works' or shall contravene
the provisions of the `Contract' the Purchaser may give notice in writing to the
Contractor to make good the failure, neglect or contravention complained of,
should the Contractor fail to comply with the notice within thirty (30) days from the
date of service thereof, then and in such case the Purchaser shall be at liberty to
employ other person /persons and forthwith execute such part of the `works' as the
Contractor may have neglected to do or if the Purchaser shall think fit it shall be
lawful for him without prejudice to any other right he may have under the
`Contract' to take the `Works' wholly or in part out of the Contractor’s hands
and re-contract with any other person or persons, complete the `works' or any part
thereof and in that event the Purchaser shall be free to use without hire charges, of
all Contractor’s equipment that may have been at the time on the `Site' in
connection with the `Works' without being responsible to the Contractor for fair
wear and tear thereof and to the exclusion of any right of the Contractor, over
144

Page 144 of 328


the same and the Purchaser shall be entitled to retain and apply any balance of
money which may otherwise due in the `Contract' by him to the Contractor or such
part thereof as may be necessary to the payment of the cost of executing the said
part of the `Works' or of completing the works as the case may be. If the cost of
completing the `works' or executing a part thereof as aforesaid shall exceed the
balance due to the Contractor, the Contractor shall pay such excess. Such
payment of excess amount shall be independent of the Liquidated Damages for delay
which the Contractor shall have to pay if the completion of `Works' is delayed.

10.35.2 In addition, such action by the Purchaser as aforesaid shall not relieve the Contractor
of his liability to pay Liquidated Damages for delay in completion of `Works'.

10.35.3 The termination of the `Contract' under this clause shall not entitle the Contractor to
reduce the value of the Performance Guarantee nor the time thereof. The
Performance Guarantee shall be valid for the full value and full period as originally
stipulated in the `Contract'.

10.35.4 In case the Contractor defaults in timely furnishing of engineering data specified in
the Contract and this delays the performance by the Purchaser his part of the
Contract and as a consequence the Contract execution schedule is delayed the
responsibility for such delay will be that of the Contractor and he will become
liable for all damages as per Contract.

10.36 SUSPENSION OF WORK

10.36.1 The Purchaser may suspend the work in whole or in part at any time by giving
Contractor notice in writing to such effect stating the nature, the date and the
anticipated duration of such suspension.
10.36.2 On receiving the notice of suspension as above, the Contractor shall stop all such
work which the Purchaser has directed to be suspended with immediate effect.

10.36.3 The Purchaser may at anytime cancel the suspension notice for all or any part of
suspended work by giving written notice to the Contractor specifying the part of
work to be resumed and the effective date of suspension withdrawal. The Contractor
shall resume the suspended work as expeditiously as possible after receipt of such
withdrawal of suspension notice.

10.36.4 In the event of suspension of work due to reasons attributable to (i) the Contractor or
(ii) Force Majeure Conditions the Purchaser will not be liable to the Contractor for
any cost-direct or indirect damage or loss or idle labour caused by such period of
suspension of work. The Purchaser shall not be liable to Contractor for any payment
towards watch & ward and any other expenditure, in such circumstances. If the
suspension is for reason attributable to the Purchaser, the Purchaser shall pay to the
Contractor, the cost as reimbursement to be agreed mutually.

10.37 TERMINATION OF CONTRACT

10.37.1 The Purchaser reserves the right to terminate the Contract either in part or in full due
to reason other than those mentioned under clause entitled Contractor's Default. The
Purchaser shall, in such an event, give 15 (fifteen) days notice in writing to the
Contractor of his decision to do so.

145

Page 145 of 328


10.37.2 The Contractor upon receipt of such notice shall discontinue the work on the date and
to the extent specified in the notice, make all reasonable efforts to obtain
cancellation of all order and Contracts to the extent they are related to the work
terminated and upon terms satisfactory to the Purchaser, stop all further sub-
Contracting or purchasing activity related to the work terminated and assist the
Purchaser in maintenance, protection and disposition of the works acquired under
the Contract by the Purchaser.

10.37.3 In the event of such a termination, the Contractor shall be paid compensation,
equitable and reasonable dictated by the circumstances prevalent at the time of
termination. No consequential damages shall be payable by the Purchaser to the
Contractor in the event of termination.

10.37.4 If the Contractor is an individual or a Proprietor concern and the individuals or the
proprietor dies and if the Contractor is a partnership concern and one of the
partners dies, then unless the Purchaser is satisfied that the legal representatives of
the individual Contractor or the Proprietor of the proprietary concern and in the
case of partnership, surviving partners, are capable of carrying out and
completing the Contract the purchaser shall be entitled to cancel the Contract as to
its incomplete part without being in any way liable to payment of any
compensation to the estate of deceased Contractor and/ or to the surviving
partners of the Contractor's firm on account of the cancellation of the Contract.
The decision of the Purchaser that the legal representatives of the deceased
Contractor or surviving partners of the Contractor's firm cannot carry out and
complete the Contract shall be final and binding on the parties. In the event of
such cancellation the purchaser shall not hold the estate of the deceased
Contractor and/ or the surviving partners of the estate of the deceased Contractor
and/ or the surviving partners of the Contractor's firm liable to damages for not
completing the Contract.

10.38 TERMINATION OF SERVICES OF CONTRACTOR'S PERSONNEL

10.38.1 In the event any of the Contractor or his Sub- Contractors, personnel, agents, sub-
agents, assistants, or other employees shall be guilty of any misconduct or be
incompetent or insufficiently qualified or negligent in the performance of their duties
or it is undesirable for any administrative reasons for such person to be employed,
the Contractor, if so directed, shall immediately remove such person or persons from
employment thereon. Any person or persons so removed shall not again be
employed in connection with this Contract without the written permission of the
Purchaser. Any person so removed shall immediately be replaced by a qualified and
competent substitute at the Contractor's cost and expenses. Should the Contractor be
requested to repatriate any person he shall do so and shall bear all costs and charges
in connection there with.

10.39 AMENDMENT

10.39.1 Any amendment to the terms of this Contract (including Schedules & Annexures)
shall be made in writing by both parties hereto and shall specifically state that it is an
amendment to this Contract.

10.39.2 No amendment as per above Clause shall have any effect until the Purchaser has
received such consent in writing (including that of the Contractor) as may be
necessary under and in terms of the loan/financial Agreements.
146

Page 146 of 328


10.40 NOTICES
10.40.1 All notices under this Contract shall be given in writing and shall be deemed
sufficiently given when delivered either in person or by telegram, telex, fax or by
registered mail addressed to the other party at its address setforth in the contract
agreement with a copy to the nominated representative at site.

10.40.2 If any such notice is delivered by hand, it shall be duly acknowledged and if given
by telegram, telex, fax it shall be confirmed by Registered Letter within seven days
of the date of such notice. Either party shall by notice in writing inform the other
party of any change of its address as stated under Clause 10.40.1 for receiving such
notices.

10.40.3 Date of notices under Clause 10.40.1 shall be the date of receipt of such notice by
the receiving party.

10.41 DEDUCTIONS FROM CONTRACT PRICE


10.41.1 The Contractor shall reimburse the Purchaser all costs, charges, damage or expenses
which the Purchaser may have paid or incurred, if and to the extent to which the
Contractor is liable under this Contract to pay within 30 days upon written request of
the Purchaser, failing which such costs, charges, damages or expenses shall be
deducted by the Purchaser from any money due or becoming due by him to the
Contractor under this Contract or any other Contract and such amounts shall be
considered as debt due from the Contractor to the Purchaser and shall be recoverable
accordingly.

10.42 ENTIRE CONTRACT


10.42.1 This Contract including the contract agreement, all the references included in all
schedules, Commercial Conditions of the Contract, Erection Conditions of Contract,
Technical Specifications and Special Terms and Conditions constitute the entire
agreement of the parties unless otherwise modified or superseded by the terms and
conditions of the Contract and after this contract is signed by both parties no
amendments modifications, variance or change in the provisions of the Contract shall
be made except in writing signed by the duly authorised representatives of the parties
hereto.

10.43 RESOLUTION OF DISPUTES AND ARBITRATION

10.43.1 Informal Dispute Resolution

The parties agree to use reasonable efforts to resolve all disputes equitably and in
good faith.

10.43.1.1 If any dispute between the Contractor and the Purchaser arises it shall in the
first instance be referred in writing to the Purchaser, who shall endeavour to
resolve the dispute amicably and render a decision within 30 days. The period of
30 days shall be reckoned from the date of intimation of the dispute is received by
the Purchaser.

10.43.1.2 Save as hereinafter provided, in respect of a dispute so referred, the decision of the
Purchaser shall be final and binding upon the Parties until the completion of the
147

Page 147 of 328


Contract and shall forthwith be given effect to by the Contractor who shall
proceed with the Contract with all due diligence, whether or not either Party has
sought arbitration of the dispute as hereinafter provided.

10.43.2 Conciliation
10.43.2.1 If the party is dissatisfied with the decision rendered by the Purchaser, or if the
Purchaser omits or declines to render a decision within the said period of 30 days,
then within a further period of 30 days, the dissatisfied Party shall require by a
notification that the dispute be referred to Conciliation in the manner as per
the ‘NLCIL Conciliation Rules’, copy of which is available with the NLCIL
offices and the Bidders/ Contractors shall abide by the NLCIL Conciliation Rules’
for resolving any dispute arising out of this contract. Such a notification shall be in
writing and it shall be duly served on the other party. Failure to invoke the
Conciliation within the time stipulated shall debar the party from seeking
reference to Conciliation.
10.43.2.2 Except as otherwise provided in this clause, any dispute arising out of or
relating to this agreement, or the breach, termination or validity thereof, shall
be settled by Conciliation in accordance with ‘NLCIL Conciliation Rules’. The
Conciliation shall be held at Neyveli or Chennai or in a place with in India
mutually agreed by the parties. The Conciliation proceedings shall be conducted,
and the award shall be rendered in English. The award shall state the reasons
upon which it is based.

10.43.2.3 Appointment and Number of Conciliators will be as follows:

Number of Conciliators
For thesum of Provisional Claim & Provisional Counter Claim

UptoRs. 3.0 Crores : One Conciliator


More than Rs.3.0 Crores : Three Conciliators

The Provisional Claim / Counter claim amount shall be indicated by the respective
parties while initiating / concurring for conciliation. However, number of
conciliators in the Settlement Advisory Committee will not be modified, even if
the Sum of Actual Claim and Actual Counter Claim amount vary from the sum of
Provisional Claim and Counter Claim amounts. Appointment of Conciliators:
Conciliator(s) will be appointed by CMD of NLC India Limited.

10.43.2.4 The Contract agreement / Purchase order conditions and the rights and obligations
of the Parties, shall remain in full force and effect during the Conciliation
proceedings. Supplies and / or services under the Contract shall, if reasonably
possible, continue during the Conciliation proceedings.

10.43.2.5 For the purpose of this clause, the term ‘dispute’ shall include a demand or
difference of any kind whatsoever, arising out of the Contract and respecting the
performance of the Contract, whether during the Contract period including
extensions if any, and whether before or after termination, abandonment or breach
of the Contract. (except as to any matter, the decision of which is specifically
otherwise provided for in any of these conditions).

10.43.2.6 Only in case of failure to resolve the dispute through Conciliation, Arbitration can
be resorted to or Judicial remedy can be sought for.
148

Page 148 of 328


10.43.2.7 Once the settlement agreement is signed with respect to a dispute, the same dispute
is not subject to further appeal through Arbitration or Judicial Proceedings.

10.43.2.8 Anything not found included in the ‘NLCIL Conciliation Rules’, but necessary to
conduct the conciliation proceedings will be dealt with as per the provisions of the
‘Arbitration and Conciliation Act 1996 -Part-III’ or as per the statutory provisions
modified from time to time.

10.44 Arbitration of Disputes.

10.44.1 BETWEEN NLCIL& ANOTHER PUBLIC SECTOR ENTERPRISE


In the event of any dispute or difference, relating to the interpretation and
application of the provisions of the Contracts, such dispute or difference shall be
referred by either party to the arbitration of one of the Arbitrators in the
Department of Public Enterprises. The Arbitration and Conciliation Act, 1996
shall not be applicable to the arbitration under this clause. The award of the
Arbitrator shall be binding upon the parties to the dispute, provided, however,
any party aggrieved by such award may make a further reference for setting aside
or revision of the award to the Law Secretary, Department of Legal Affairs,
Ministry of Law & Justice, Government of India. Upon such reference the
dispute shall be decided by the Law Secretary or the Special
Secretary/Additional Secretary when so authorized by the Law Secretary, whose
decision shall bind the parties finally and conclusively. The parties in the
dispute will share equally the cost of arbitration as intimated by the Arbitrator.
The procedure to be adopted in the above case shall be as per DPE guidelines
No. DPE OM No. 4(1)/2011-DPE(PMA)-GL dated 12.06.2013.

10.44.2 Between NLCIL & Contractor other than a Public Sector enterprise

10.44.2.1 If either party is dissatisfied with the decision rendered by the Purchaser, or if
the Purchaser omits or declines to render a decision within the said period of 30
days, then within a further period of 30 days, the dissatisfied Party may require
by a notification that the dispute be referred to arbitration in the manner
hereinafter provided. Such a notification shall be in writing and it shall be duly
served on the other party. Failure to invoke the arbitration within the time schedule
shall debar the party from seeking reference to arbitration.

10.44.2.2 Except as otherwise provided in this clause, any dispute arising out of or
relating to this agreement, or the breach, termination or validity thereof, shall be
finally settled by arbitration in accordance with the Arbitration and Conciliation
Act 1996 (the ``Act''). The arbitration shall be held at Neyveli or Chennai, Tamil
Nadu. The arbitration proceedings shall be conducted, and the award shall be
rendered in English. The award shall state the reasons upon which it is based.

10.44.2.3 There shall be three arbitrators of whom each Party shall appoint one. The Party
requesting that the dispute be referred to arbitration shall, within 30 days of the
notification in terms of Clause 10.44.2.1, appoint an arbitrator as also call upon
the other Party to appoint an arbitrator within 30 days. The two arbitrators so
appointed shall, within 30 days of the date on which the second of them is

149

Page 149 of 328


appointed, agree on the third arbitrator who shall act as the presiding arbitrator of
the tribunal.

10.44.2.4 The agreement and the rights and obligations of the Parties, shall remain in full
force and effect pending the award in any arbitration proceedings. Supplies and/ or
services under the Contract shall, if reasonably possible, continue during arbitration
proceedings.

10.44.2.5 For the purposes of this clause, the term `dispute' shall include a demand or
difference of any kind whatsoever, arising out of the Contract and respecting the
performance of the Contract, whether during the Contract period including
extensions if any, or after completion, and whether before or after termination,
abandonment or breach of the Contract (except as to any matter, the decision of
which is specifically provided for in any of these conditions).

10.44.2.6 The Arbitrators shall publish a speaking award which shall be binding on both the
parties. The party in whose favour the award is passed shall be entitled to recover
the entire cost of arbitration from the other party. The Arbitrators shall indicate the
above in their award clearly.

10.45 COMPLETENESS OF THE CONTRACT

10.45.1 The Contractor shall expressly undertake full responsibility for the quality
of supplies, timely deliveries as per the stipulated schedule of deliveries the
faultless operation of the equipment, the warranty for the design of the
equipment and manufacture of the complete equipment, including the Indian
portion of supplies free of any defects and faults.

10.45.2 In the event of replacements becoming necessary on account of short deliveries and
wrong supplies on account of short landing, loss/ damages during transit, storage,
erection and commissioning the Contractor shall take special steps to make such
replacements free of cost for timely commissioning of the equipment. The charges
towards, freight, insurance, port handling clearance customs duty and all other
incidentals including transport to site in respect of such replacements will be to the
account of the Contractor. The Contractor shall take special steps to arrange for
most expeditious manufacture and supply of these items to enable timely
commissioning of the equipment.

10.45.3 Equipment furnished shall be complete in every respect with all mountings,
fittings, fixtures and standard accessories normally provided with such
equipment, and/or needed for erection, completion and safe operation of the
equipment. They may not have been specifically detailed in the respective
specifications, unless included in the list of exclusions. All similar standard
components/parts of similar standard equipment provided, shall be
interchangeable with one another. The Contractor shall not be eligible for any extra
payment in respect of such mounting, fixtures and accessories.

10.46 GRAFTS AND COMMISSION


Any graft, commission, gift or advantage given promised or offered by on
behalf of the Contractor or his partner, agent, officers, Director, employee or
servant or any one on his or their behalf in relation to the obtaining or to the
execution of this or any other Contract with the Purchaser, shall in addition to

150

Page 150 of 328


any criminal liability which may it incur, subject the Contractor to the
cancellation of this and all other Contracts and also the payments of any loss or
damage to the Purchaser resulting from any cancellation. The Purchaser
shall then be entitled to deduct the amounts so payable from any monies otherwise
due to the Contractor under the Contract.

10.47 CERTIFICATE NOT TO AFFECT RIGHT OF PURCHASER AND


LIABILITY OF CONTRACTOR

No interim payment certificate of the Purchaser or the Consultant nor any sum
paid on account by the Purchaser nor any extension of time for execution of
the `works' granted by the Purchaser or the Consultant shall affect or prejudice the
rights of the Purchaser against the Contractor or relieve the Contractor of his
obligations for the due performance of the Contract or be interpreted as
approval of the `Works' done or of the equipment furnished and no certificate
shall create liability in the Purchaser to pay for alterations amendments,
variations or additional `Works' not ordered in writing, by the Purchaser or
discharge the liability of the Contractor for the payment of damages whether
due, ascertained, or certified or not or any sum against the payment of which
he is bound to indemnify the Purchaser nor shall any such certificate nor the
acceptance by him of any sum paid on account or otherwise affect or prejudice
the rights of the Contractor against the Purchaser.

10.48 INSOLVENCY, LIQUIDATION AND BANKRUPTCY ETC.

If the Contractor shall die, dissolve or become bankrupt or insolvent or cause or


suffer any receiver to be appointed on his business or any assets thereof with his
Creditors, or being a corporation commence to be wound up, not being a member's
voluntary winding up for the purpose of amalgamation or reconstruction, or carry
on its business under a Receiver for the benefits of its Creditors or any of them, the
Purchaser shall be at liberty:-

i) to terminate the Contract forthwith upon coming to know of the happening of


any such event as aforesaid by notice in writing to the Contractor or to the
Receiver or Liquidator or to any person to whom the Contract may become
vested to, or

ii) to give such Receiver, Liquidator or other person the option of carrying out the
Contract subject to his providing a guarantee up to an amount to be agreed for
the due and faithful performance of the Contract.Not withstanding the provision
of Cl.10.48 (i) in the event of Indian contractor undergoing liquidation or being
dissolved, become bankrupt as described above the principle contractor shall
directly assume the responsibilities of Indian contractor to the extent not
performed.

10.49 MANNER OF EXECUTION OF CONTRACT

10.49.1 After acceptance of the Letter of Award, the Purchaser shall draft the Contract and
shall provide one copy to the Contractor for checking. The Contract, in two
originals, prepared on a non judicial stamp paper shall be signed by the holders of
power of attorney on a suitable date and time but within 60 (Sixty) days of the
acceptance of the Letter of Award.

151

Page 151 of 328


10.49.2 Before signing the contract, the Purchaser and the Contractor are deemed to have
checked and verified all the Contract Documents for the completeness and
correctness.

10.49.3 Thereafter, within another 30 (Thirty) days, the Contractor shall supply 25
(Twenty five) copies of the Contract Agreement, to the Purchaser free of cost.

10.50 CONTRACT DOCUMENTS

10.50.1 The term `Contract' or `Contract Documents' shall mean and include the following
which shall be deemed to form an integral part of the Contract.

10.50.1.1 ‘Notice Inviting Tender’ and `Invitation to Bid’ issued by the Purchaser.

10.50.1.2 The Bid proposal offered by the bidder, including all correspondences relation to
the decision on the deviations, and on the clarifications sought for, exchange
between the bidder and their purchaser prior to the award of the Contract.

10.50.1.3 All the materials, literature, data and information given by the Contractor along
with his bid or later.

10.50.1.4 Minutes of all discussion between the Bidder and the Purchaser.

10.50.1.5 `Letter of Award’ issued by the Purchaser and its acceptance by the Contractor.

10.50.1.6 Contract agreement, general and technical terms and conditions and all other
documents exchanged.

10.50.1.7 Specifications of the equipment to be furnished under the Contract as mutually


agreed between the Purchaser and the Contractor.

10.50.1.8 Any agreed variation to the conditions of the documents and specifications and
special terms and conditions of Contract, if any.

10.50.2 In the event of any ambiguities and discrepancies between the above mentioned
documents, the decision of the Purchaser shall be final and binding.

10.51 JURISDICTION

The Civil Courts having ordinary original civil jurisdiction over Andaman &
Nicobar Islands shall have exclusive jurisdiction in regard to all questions of
disputes of whatever nature including the arbitration proceedings, if any arising
under the Contract with the Purchaser.

10.52 GOVERNING LAWS AND REGULATIONS

This Contract shall be governed and construed according to the Indian Laws and
Regulations.

10.53 SAFETY
The Contractor shall abide by the safety Code for Contractors which is enclosed.

152

Page 152 of 328


10.54 GENERAL CONDITIONS FOR ERECTION AND CIVIL WORKS

The Contractor shall abide by the General Conditions for Erection & Civil Works,
which is enclosed.

10.55 GENERAL

No director or official or employee of the Purchaser shall in any way be personally


bound or liable for the acts or obligations of the purchaser under the contract or
answerable for any default or omission in the observance or performance of any of
the acts, matters or things or conditions which are herein contained.

10.56 CORRESPONDENCE
All further correspondence in connection with this offer shall be addressed to:
The General Manager/Contracts
Corporate Office
NLC India Limited,
Block-1, Neyveli – 607 801.
Fax: 04241-252026/252645/252646
Cuddalore District, Phone: 04142 – 252215/252210
Tamil Nadu, INDIA

153

Page 153 of 328


ANNEXURE-I

GENERAL CONDITIONS FOR ERECTION WORKS


CONTENTS

CLAUSE TITLE PAGE


NO. NO.
GENERAL CONDITIONS FOR ERECTION WORKS
1.0 GENERAL 157
2.0 REGULATION OF LOCAL AUTHORITIES AND STATUTES 157
3.0 CONTRACTOR’S HEALTH AND SAFETY PROGRAM 158
4.0 PURCHASER’S LIEN ON EQUIPMENT 158
5.0 INSPECTION, TESTING AND INSPECTION CERTIFICATES 158
6.0 ACCESS TO SITE AND WORKS ON SITE 159
7.0 CONTRACTOR’S SITE OFFICE ESTABLISHMENT 159
8.0 CO-OPERATION WITH OTHER CONTRACTORS 160
9.0 DISCIPLINE OF WORKMEN 160
10.0 CONTRACTOR’S FIELD OPERATION 161
11.0 PHOTOGRAPHS AND PROGRESS REPORT 161
12.0 MANPOWER REPORT 161
13.0 PROTECTION OF WORK 161
14.0 EMPLOYMENT OF LABOUR 162
15.0 FACILITIES TO BE PROVIDED BY THE PURCHASER 163
16.0 FACILITIES TO BE PROVIDED BY THE CONTRACTOR 163
17.0 LINES AND GRADES 165
18.0 FIRE PROTECTION - NOT APPLICABLE 165
19.0 SECURITY 165
20.0 CONTRACTOR’S AREA LIMITS 165
21.0 CONTRACTOR’S COOPERATION WITH THE PURCHASER 166
22.0 COMMISSIONING 166
23.0 MATERIAL HANDLING AND STORAGE 166
24.0 CONSTRUCTION MANAGEMENT 168
25.0 FIELD OFFICE RECORDS 168
26.0 CONTRACTOR’S MATERIAL BROUGHT TO SITE 169

154

Page 154 of 328


27.0 PROTECTION OF PROPERTY AND CONTRACTOR’S 169
LIABILITY
28.0 PAINTING 170
29.0 INSURANCE 170
30.0 UNFAVOURABLE WORKING CONDITIONS 170
31.0 PROTECTION OF MONUMENTS AND REFERENCE POINTS 170
32.0 WORK & SAFETY REGULATIONS 170
33.0 ELECTRICAL SAFETY REGULATIONS 170
34.0 PURCHASER’S INSTRUCTIONS 171
35.0 RIGHTS OF THE PURCHASER/CONSULTANT 171
36.0 MEASUREMENT OF WORK AND PROGRESS PAYMENTS 173
37.0 ADHERENCE TO MANUFACTURER’S INSTRUCTION 174
38.0 MODIFICATIONS 175
39.0 DEFECTIVE WORK 175
40.0 WORK OF OTHERS 175

ANNEXURE-1I GENERAL CONDITIONS FOR CIVIL WORKS 176-177

ANNEXURE-1II SAFETY CODE FOR THE CONTRACTOR 178-181

ANNEXURE-IV COMMERCIAL TERMS AND CONDITIONS FOR OPERATION 182-196


AND MAINTENANCE CONTRACT

APPENDIX-A-F BANK GURANTEES FORMATS 197-214

155

Page 155 of 328


GENERAL CONDITIONS FOR ERECTION WORKS

1.0 General

1.1 The following shall supplement the conditions already contained in the other parts of
these specifications and documents and shall govern that portion of the work of this
‘Contract’ to be performed at ‘site’.

1.2 The Contactor upon issue of LOA shall, in addition to a Project Coordinator, nominate
another responsible officer as his representative at site suitably designated for the
purposes of overall responsibility and co-ordination of the Works to be performed at
site. Such person shall function from the site office of the Contractor during the
execution of ‘Contract’. This representative shall have full technical capability and
complete administrative and financial powers to expeditiously and efficiently execute
the work under this ‘Contract’.

1.3 The Contractor shall proceed with the work to be performed under this ‘Contract’ and
each and every part and detail thereof, in the best and most workman like manner by
engaging qualified, careful and efficient workers, and do the several parts thereof, at
such time and in such order as the Purchaser/Consultant may direct, and finish such
work in strict conformity with the plans, drawings and/or specifications, and any
changes, modifications or amplifications thereof made by the Purchaser/Consultant.

1.4 The Contractor shall not sell, assign, mortgage hypothecate or remove equipment or
materials or materials which have been installed or which may be necessary for the
completion of the ‘Contract’ without the written consent of the Purchaser.

2.0 REGULATION OF LOCAL AUTHORITIES AND STATUTES

2.1 The Contractor shall ensure compliance with all statutes, laws, rules and regulations of
the Central or State Government or any other authority such as the Workmen’s
Compensation Act 1923, Payment of Wages Act, Minimum Wages Act 1948,
Employees State Insurance Act, Employees Provident Fund Act, etc. and any and all
statutory modifications thereof in connection with employees engaged by him or his
Sub-Contractors in the work.

2.2 The Contractor shall conform to the provisions of MNRE, DISCOMS, Andaman &
Nicobar Islands Electricity authorities, Factory Laws, Indian Electricity Act and rules
made there under, and any other acts of legislature relating to the work and to the
regulations and bye-laws of any authority and of any water, lighting and other
companies and/or authorities with whose systems the plant/structure is proposed to be
connected and shall before making any variations from the drawings or specifications
that may be necessitated by so conforming, giving to the Purchaser/Consultant written
notice, specifying the variations proposed to be made and the reason for making it and
apply for instructions thereof.

2.3 The Contractor shall arrange to give all notice required by the said Acts, Regulations or
Bye-laws to be given to any Authority or to any Public Officer and pay all fees that
may be properly chargeable in respect of the ‘Works’ and lodge the receipts with the

156

Page 156 of 328


Purchaser/Consultant, unless otherwise, specified in the specification. Obtaining all
permits and licenses required there upon is the responsibility of the Contractor.

2.4 All registration and statutory inspection fees, if any, in respect of his work pursuant to
this ‘Contract’ shall be to the account of the Contractor. However, any registration,
statutory inspection fees and any other statutory laws and its amendments from time to
time during erection in respect of the plant and equipment ultimately to be owned by
the Purchaser shall be to the account of the Purchaser. Should any such inspection or
registration need to be re-arranged due to the fault of the Contractor or his Sub-
Contractor, the additional fees for such inspection and/or registration shall be borne by
the Contractor.

3.0 CONTRACTOR’S HEALTH AND SAFETY PROGRAM


Refer Technical specification.

4.0 PURCHASER’S LIEN ON EQUIPMENT

The Purchaser shall have lien on all equipment including those of the Contractor
brought to the site for the purpose of erection, testing and commissioning of the plant.
The Purchaser shall continue to hold the lien on all such equipment throughout the
period of ‘Contract’. No material brought to the site shall be removed from the site by
the Contractor and/or his Sub-Contractor’s without the prior written approval of the
Purchaser/Consultant.

5.0 INSPECTION, TESTING AND INSPECTION CERTIFICATES

5.1 The provisions of the clause entitled Inspection, Testing and Inspection Certificates
shall also be applicable to the erection portion of the ‘Works’. The Purchaser /
Consultant shall have the right to re-inspect any equipment (though previously
inspected and approved by him, at the Contractor’s works) before and after the same
are erected at Site. If by the above inspection, the Purchaser / Consultant rejects any
equipment, the Contractor shall make good for such rejections either by replacement or
modifications / repairs as may be necessary, to the satisfaction of the Purchaser /
Consultant. Such replacements will also include the replacements or re-execution of
such of those works of other Contractor’s and/or agencies, which might have got
damaged or affected by the replacements or re-work done to the Contractor’s work.

5.2 Any work, which proves faulty, shall be corrected by the Contractor without delay. The
fact that the Purchaser / Consultant or their representatives have not pointed out faulty
work or work which is not in accordance with plans and specifications shall not relieve
the Contractor from correcting such work as directed by the Purchaser / Consultant
without additional compensation.

5.3 When finished work is taken down for the purpose of re-inspection, the Contractor shall
bear the entire expenses incident thereto in the event that said work is found to be
defective. The Purchaser shall pay the cost incident thereto in the event that the work
inspected is found to be in accordance with the ‘Specification’. In the latter case, the
replacing of the covering or the making good of any of the parts removed shall be paid
for by the Purchaser at the Contract price for the class of work done and the uncovering
157

Page 157 of 328


or taking out of materials or parts shall be paid for on the basis of actual direct cost of
material, layout and incidental expense, plus reasonable rental prices for transportation
of equipment, except that no percentage for the Contractor’s fees shall be added to
actual direct cost of material, labour and incidental expenses. However, no extension of
time shall be given for completion of works on this account. If the Contractor shall fail
to repair any defective work or replace any defective materials after reasonable notice,
the Purchaser / Consultant may cause such defective work to be repaired or defective
material to be replaced and the expenses thereof shall be deducted from the amount to
be paid to the Contractor.

5.4 The Purchaser / Consultant, their representatives and employees shall, at all reasonable
times, have free access to the works and/or to the workshops, factories or other places
where materials are being prepared or constructed for the ‘Contract’ and also to any
place where the materials are lying or from where they are being obtained, and the
Contractor shall give every facility to the Purchaser / Consultant and his representatives
for inspection and examination and test of the materials and workmanship even to the
extent of discontinuing portions of the work temporarily, or of uncovering or taking
down portions of finished work.

6.0 ACCESS TO SITE AND WORKS ON SITE

6.1 Suitable access to and possession of the site shall be afforded to the Contractor by the
Purchaser in reasonable time.

6.2 The Purchaser shall have the necessary foundations to be provided by him ready, as per
the agreed schedule for the execution of the individual phases of ‘Works’.

6.3 In the execution of the ‘Works’, no persons other than the Contractor or his duly
appointed representative, Sub-Contractor and workmen shall be allowed to do work on
the site, except by the special permission, in writing of the Purchaser / Consultant or his
representative.

6.4 Access to the site at all times shall be accorded to the Purchaser / Consultant and other
authorized officials and statutory Public Authorities. Nevertheless, the Contractor shall
not object to the execution of the work by other Contractors or tradesmen whose names
shall have been previously communicated in writing to the Contractor by the Purchaser
/ Consultant and afford them every facility for the execution of their several functions
simultaneously with his own.

7.0 CONTRACTOR’S SITE OFFICE ESTABLISHMENT

7.1 The Contractor shall establish a Site Office at the site and keep posted an authorized
representative for the purposes of the ‘Contract’. Any written order or instruction of the
Purchaser / Consultant or his duly authorized representative, shall be communicated to
the authorized representative of the Contractor at the Site Office and the same shall be
deemed to have been communicated to the Contractor at his legal address.
158

Page 158 of 328


7.2 The Contractor shall employ at least one competent representative whose name or
names shall have previously been communicated in writing to Purchaser/Consultant by
the Contractor, to supervise the erection of the plant and to carry out the work. The said
representative or if more than one shall be employed, then one of such representatives
shall be present at the site during working hours, and any written orders or instructions
which the Purchaser/Consultant may give to the said representatives of the Contractor
shall be deemed to have been given to the Contractor. It is essential that the supervisory
personnel shall be capable of speaking and writing in English language.

8.0 CO-OPERATION WITH OTHER CONTRACTORS IF ANY

8.1 The Contractor shall cooperate with all other Contractors or tradesmen of the
Purchaser, who may be performing other works on behalf of the Purchaser and the
workmen who may be employed by the Purchaser and doing work in the vicinity of the
‘Works’ under the ‘Contract’. The Contractor shall also so arrange to perform his work
as to minimize, to the maximum extent possible, interference with the work of other
Contractors and his workmen. Any injury or damage that may be sustained by the
employees of the other Contractors and the Purchaser due to the Contractor’s work
shall promptly be made good at his one expense. The Purchaser/Consultant shall
determine the resolution of any difference or conflict that may arise between the
Contractor and other Contractors or between the Contractor and the Workmen of the
Purchaser in regard to their Work. If the ‘Works’ of the Contractor is delayed because
of any acts or omissions of another Contractor, the Contractor shall have no claim
against the Purchaser on that account.

8.2 The Purchaser/Consultant shall be notified promptly by the Contractor of any defects in
the other Contractor’s works that could affect the Contractor’s ‘Works’. The
Purchaser/Consultant shall determine the corrective measures, if any, required to rectify
this situation after inspection of the ‘Works’ and such decisions by the
Purchaser/Consultant shall be binding on the Contractor. If a part of the Contractor’s
work depends, for proper execution, upon the work of any other Contractor, the
Contractor shall inspect and promptly report in writing to the Purchaser/Consultant any
defect in such work of other Contractors that render it unsuitable for proper execution
of the work under this ‘Contract’. His failure to so inspect and report shall constitute an
acceptance of ‘Others’ work as fit and proper for the reception of his work, except as to
defects which may develop in the work of ‘Others’ after the proper execution of the
work. To ensure proper execution of his sub-sequent work, the contractor shall inspect
work already in place and shall at once report to the Purchaser/Consultant any
discrepancy between the executed work and the drawings.

9.0 DISCIPLINE OF WORKMEN

The Contractor shall adhere to the disciplinary procedure set by the


Purchaser/Consultant in respect of his employees and workmen at site. The
Purchaser/Consultant shall be at liberty to object to the presence of any representative
or employee of the Contractor at the site, if in the opinion of the Purchaser/Consultant
such employee has misconduct himself or be incompetent or negligent or otherwise
undesirable and then the Contractor shall remove such a person and provide in his place
a competent replacement at his own expense.

159

Page 159 of 328


10.0 CONTRACTOR’S FIELD OPERATION

10.1 The Contractor shall keep the Purchaser/Consultant informed in advance regarding his
field activity plans and schedules for carrying out each part of the ‘Works’. Any review
of such plan or schedule or method of work by the Purchaser/Consultant shall not
relieve the Contractor of any of his responsibility towards the field activities. Such
reviews shall also not be considered as an assumption of any risk or liability by the
Purchaser/Consultant or any of his representatives and no claim of the Contractor will
be entertained because of the failure or inefficiency of any such plan or schedule or
method of work reviewed. The Contractor shall be solely responsible for the safety,
adequacy and efficiency of plant and equipment and his erection methods.

10.2 The Contractor shall have the complete responsibility for the conditions of the work site
including the safety of all persons employed by him or his Sub-Contractor and all the
properties under his custody during the performance of the work. This requirement
shall apply continuously till the completion of his ‘Contract’ and shall not be limited to
normal working hours. The construction review by the Purchaser/Consultant is not
intended to include review of Contractor’s safety measures in, on or near the work-site,
and their adequacy or otherwise.

10.3 The work so far as it is carried out on the Purchaser’s premises shall be carried out at
such time as the Purchaser may approve consistent with the construction schedule and
so as not to interfere unnecessarily with the conduct of the Purchaser’s business and the
Purchaser will give the Contractor all reasonable facilities for carrying out the work.

11.0 PHOTOGRAPHS AND PROGRESS REPORT

Refer relevant Clauses of Technical Specification and Schedule-10 of Volume II.

12.0 MANPOWER REPORT

12.1 The Contractor shall submit to Purchaser/Consultant on the first day of every week, a
man-power schedule for the next week, detailing the man-power scheduled skill-wise
and area-wise.

12.2 The Contractor shall also submit to the Purchaser/Consultant on the first day of every
month, a manpower report of the previous month detailing the number of persons
scheduled to have been employed and actually employed, skill-wise and the areas of
employment of such labour.

13.0 PROTECTION OF WORK

13.1 The Contractor shall have total responsibility for protecting his ‘Works’ till it is finally
accepted by the Purchaser/Consultant. No claim will be entertained by the
Purchaser/Consultant for any damage or loss to the Contractor’s ‘Works’ and the
Contractor shall be responsible for the complete restoration of the damaged ‘Works’ to
its original condition to comply with the specifications and drawings. Should any such
damage to the Contractor’s ‘Works’ occur because of other party not under his
supervision or control, the Contractor shall make his claim directly with the party
concerned. If disagreement or conflict or dispute develops between the Contractor and
the other party or parties concerned regarding the responsibility for damage to the
160

Page 160 of 328


Contractor’s ‘Works’ the same shall be resolved as per the provisions of the Clause 8.0
above entitled ‘Cooperation with other Contractors’. The Contractor shall not cause any
delay in the repair of such damaged ‘Works’ because of any delay in the resolution of
such disputes. The Contractor shall proceed to repair the work immediately and no
cause thereof will be assigned pending resolution of such dispute.

13.2 The Contractor and his Sub-Contractors shall be responsible during work for protection
of the work, which has been completed by Others. Necessary care shall be taken to see
that no damage to the same is caused by his own men during the course of execution of
their work.

13.3 All other work completed or in progress as well as machinery and equipment that are
liable to be damaged by the Contractor’s work shall be protected by the Contractor and
such protection shall remain and be maintained until its removal is directed by the
Purchaser.

13.4 The Contractor shall effectively protect all the works from action of weather and from
damages or defacement and shall cover finished parts where required for their thorough
protection. Face work shall be perfectly clean and free from defects.

13.5 The work shall be carried out onto completion without damage to any work and
property adjacent to the area of his work, to whomsoever it may belong, without
interference with the operation of their existing machines or equipment.

13.6 The Contractor shall provide the necessary temporary roadways, footways, guards as
may be rendered necessary by reason of his work, for the protection and
accommodation of foot passengers of other traffic of the Purchaser or occupier of
adjacent property and of public. The Contractor shall at the times provide sufficient
temporary barriers, notice boards and lights to protect and warn the public and post
necessary watchman to guard the site and equipment. He shall take all precautions
necessary and shall be responsible for the safety of the work to be performed by him.
The Contractor shall also observe and display Safety First signs and shall have proper
safety and fire protection equipment.

13.7 Adequate lighting at and near all the storage, handling, fabrication, pre-assembly and
erection sites for properly carrying out the work and for safety and security shall be
provided by the Contractor. The Contractor’s work area would be adequately lighted
during nighttime also. The Contractor should also engage adequate
electricians/wiremen, helpers, etc., to carry out and maintain these lighting facilities. If
the Contractor fails to provide all the above listed facilities, the Purchaser may provide
such facilities as he may deem necessary and charge the cost thereof to the Contractor.
In any case the Contractor shall be liable for all damages and consequences arising out
of his neglect in this regard.

14.0 EMPLOYMENT OF LABOUR

14.1 The Contractor/Sub-Contractors will be expected to employ on the work skilled


employees with experience of his particular work. No person below the age of eighteen
years shall be employed.

161

Page 161 of 328


14.2 The Contractor shall furnish details of the qualifications and experience of his senior
supervisors and Consultants assigned to the work, including their experience in
supervising erection and commissioning of plant and equipment of comparable
capacity.

14.3 All traveling expenses including provisions of all necessary transport to and from site,
loading allowances and other payments to the Contractor’s employees shall be the sole
responsibility of the Contractor.

14.4 The hours of work on the site shall be decided by the Purchaser and the Contractor shall
adhere to it. Working hours for each employee will normally be eight (8) hours per day.

14.5 The Contractor’s employees shall wear identification badges while on work at site.

14.6 The Contractor shall ensure that he pays his men regularly their wages, overtime and
other compensations. The attendance register and the wage register shall be submitted
to the Purchaser for verification at regular intervals. The Contractor shall also furnish
the Purchaser at fortnightly intervals a certificate that he has paid all the dues to his
workmen. In case such payment is not made regularly by the Contractor, the Purchaser
will be in his right to make such payments and deduct the same from the Contractor’s
progress payments.

14.7 In case the Purchaser becomes liable to pay any wages or dues to the labour or to any
Government agency under any of the provisions of the Minimum Wages Act,
Workmen’s Compensation Act or any other law due to act of omission of the
Contractor, the Purchaser may make such payments and shall recover the same from
the Contractor’s bills.

14.8 None of the Contractor’s superintendents, supervisors, Consultants or labour may be


withdrawn from the work without due notice being given to the Purchaser/Consultant.
Further, no such withdrawal shall be made if, in the opinion of the
Purchaser/Consultant, it will jeopardize the required pace of progress and/or the
successful completion of the work.

14.9 In connection with the performance of work under this ‘Contract’, the Contractor shall
agree not to discriminate because of race, religion, colour or national origin. It is also
expected that the Contractor in his selection of personnel will give due regard to their
ability to co-operate with the Purchaser/Consultant. Suggestions and recommendations
made by the Purchaser/Consultant relating to the work and coordination thereof are to
be carefully and courteously considered.

15.0 FACILITIES TO BE PROVIDED BY THE PURCHASER

15.1 Refer relevant clauses in Technical Specification

16.0 FACILITIES TO BE PROVIDED BY THE CONTRACTOR

16.1 Tools, Tackles and Scaffoldings

16.1.1 The Contractor shall provide at his own expense, all the construction equipment, false
work, erection tools, machine tools, power tools, tackles, hoists, cranes, derricks,
162

Page 162 of 328


cables, slings, skids, scaffolding work benches, tools for rigging, cribbing and blocking,
welding machines preheating and stress relieving equipment, X-ray and all associated
protective equipment, instruments, appliances, materials, and supplies required for
unloading, transporting, storing, erection, testing and commissioning that may be
required to accomplish the work under the ‘Contract’ unless otherwise provided for.
Adequacy of such tools will be subject to final determination of the
Purchaser/Consultant. He shall submit a list of all such materials to the Purchaser /
Consultant before the commencement of pre-assembly at site. These tools and tackles
shall not be removed from the site without the written permission of the Purchaser/
Consultant.

16.1.2 The Contractor shall also furnish all necessary expandable devices like anchors,
grinding and abrasive wheels, raw plugs, hacksaw blades, taps, dies, drills, reamers,
chisels, files, carborandum stones, oil stones, wire brushes, necessary scaffolding,
ladders, wooden planks, timbers, sleepers and consumable material like welding
electrodes, oxygen, acetylene, argon, lubricating oils, greases, cleaning fluids, cylinder
oil, graphite powder and flakes, fasteners, gaskets, temporary supports, stainless steel
shims of various thickness as required, cotton waste, cheese cloth and all other
miscellaneous supplies of every kind required for carrying out the work under the
‘Contract’.

16.1.3 The Contractor shall provide all reasonable facilities including tools, personnel, etc. and
ensure coordination with the Purchaser / Consultant and the Sub-Contractor’s erection
supervisors to enable them to carry out all supervision, measurements, checks, etc. in a
satisfactory manner.

16.1.4 The Contractor shall not dispose of, transport or withdraw any tools, tackles, equipment
and material provided by him for the ‘Contract’ without taking prior written approval
from the Purchaser/Consultant, and the Purchaser/Consultant at all times shall have
right to refuse permission for disposal, transport or withdrawal of tools, tackles,
equipment and material if, in his opinion, the same will adversely affect the efficient
and expeditious completion of the ‘Project’.

16.2 Communication

The Contractor will make his own arrangement for all his communication needs such as
telephone, email etc. at his Site Office. The Purchaser will assist the Contractor in
getting the above facilities, in case he finds difficulty.

16.3 First-aid

16.3.1 The Contractor shall provide necessary first-aid facilities for all his employees,
representatives and workmen at the site.

16.4 Cleanliness

16.4.1 The Contractor shall be responsible for keeping the entire area allotted to him clean and
free from rubbish, debris etc. during the period of ‘Contract’. The Contractor shall
employ enough number of special personnel to thoroughly clean his work area at least
once in a day. All such rubbish and scrap material shall be stacked or disposed in a
place to be identified by the Purchaser / Consultant. Materials and stores shall be so

163

Page 163 of 328


arranged to permit easy cleaning of the area. In areas where equipment might drip oil
and cause damage to the floor surface, a suitable protective cover of a flame resistant,
oil-proof sheet shall be provided to protect the floor from such damage.

16.4.2 Similarly, the offices of the Contractor shall be kept clean and neat to the entire
satisfaction of the Purchaser/Consultant. Proper sanitary arrangements shall be
provided by the Contractor in the work areas and office of the Contractor.

17.0 LINES AND GRADES

17.1 All the ‘Works’ shall be performed to the lines, grades and elevations indicated on the
drawings. The Contractor shall be responsible to locate and layout the ‘Woks’. Basic
horizontal and vertical control points will be established and marked by the Purchaser /
Consultant at site at suitable points. These points shall be used as datum for the
‘Works’ under the Contract. The Contractor shall inform the Purchaser / Consultant
well in advance of the times and places at which he wishes to do work in the area
allotted to him, so that suitable datum points may be established and checked by the
Purchaser / Consultant to enable the Contractor to proceed with his ‘Works’. Any work
done without being properly located may be removed and/or dismantled by the
purchaser/Consultant at Contractor’s expense.

17.2 Where the Purchaser/Consultant had already established the base lines and bench marks
adjacent to the various sections of work, the same must be carefully preserved by the
contractor, and in case of their unnecessary destruction by him or any of his employees,
these will be re-established by the Purchaser/Consultant at the Contractor’s expense.

17.3 The Contractor shall be responsible for the accuracy of all dimensions within the
various sections of the work according to the figures of dimensions in the drawings.

18.0 FIRE PROTECTION

Refer relevant clauses in Technical Specification.

19.0 SECURITY

Watch towers shall be provided by the Contractor around the periphery of Solar PV
Power Plant and shall be designed and constructed considering the safety and security
requirements of the Solar PV Power Plant as per the Technical Specification.

20.0 CONTRACTOR’S AREA LIMITS

The Purchaser/Consultant will mark-out the boundary limits of access roads, parking,
spaces, storage and construction areas for the Contractor and the Contractor shall not
tress-pass areas not so marked out for him. The Contractor shall be responsible to
ensure that none of his personnel move out of the areas marked out for his operations.
In case of such a need for the Contractor’s personnel to work out of the areas marked
out for him, the same shall be done only with the written permission of the
Purchaser/Consultant.

164

Page 164 of 328


21.0 CONTRACTOR’S COOPERATION WITH THE PURCHASER

21.1 In cases where the performance of the erection work by the Contractor affects the
operation of the system facilities of the Purchaser/Consultant or other agencies such
erection work of the Contractor shall be scheduled to be performed only in the manner
stipulated by the Purchaser/Consultant and the same shall be acceptable at all times to
the Purchaser/Consultant. The Purchaser/Consultant may impose such restrictions on
the facilities provided to the Contractor such as electricity, water etc. as he may think fit
in the interest of the Purchaser and the Contractor shall strictly adhere to such
restrictions and co-operate with the Purchaser/Consultant. It will be the responsibility
of the Contractor to provide all necessary temporary instrumentation and other
measuring devices required during start-up and operation of the equipment systems,
which are erected by him. The Contractor shall also be responsible for consumables
required for the equipment furnished and erected by him, so as to make such equipment
ready for operation. The Contractor shall be responsible for supplying such
consumables.

21.2 The Contractor at all times shall work in coordination with the Purchaser’s Consultants
and offer them all reasonable facilities to become familiar with the erection, operation
and maintenance of the equipment.

21.3 In respect of observations of local rules, administrative orders, working hours and the
like, the Contractor and his personnel shall cooperate with the Purchaser.

22.0 COMMISSIONING

The ‘Commissioning’ of the equipment supplied and erected by the Contractor shall be
the responsibility of the Contractor as detailed in Tender specification. The Contractor
shall provide in addition, test instruments, calibrating devices etc. and the labour
required for the successful performance of these tests. If it is anticipated that the above
tests may prolong for a long time, the Contractor’s workmen required for the above
tests shall always be present at site during such tests.

23.0 MATERIAL HANDLING AND STORAGE

23.1 All the equipment furnished under the Contract and arriving at site shall be promptly
received, unloaded and transported and stored in the storage spaces by the Contractor.

23.2 The Contractor shall be responsible for examining all the shipment and notify the
Purchaser/Consultant immediately of any damage, shortage, discrepancy etc. for the
purpose of Purchaser’s / Consultant’s information only. The Contractor shall submit to
the Purchaser / Consultant every week a report detailing all the receipts during the
week. However, the Contractor shall be solely responsible for any shortages or damage
in transit, handling and/or in storage and erection of the equipment at the site (Any
demurrage, wharfage and other such charges claimed by the transporters, railways etc.
shall be to the account of the Contractor).

23.3 The Contractor shall maintain an accurate and exhaustive record detailing out the list of
all equipment received by him for the purpose of erection and keep such record open
for the inspection of the Purchaser/Consultant at any time.

165

Page 165 of 328


23.4 All equipment shall be handled very carefully to prevent any damage or loss. No bare
wire ropes, slings etc shall be used for unloading and/or handling of the equipment
without the specific written permission of the Purchaser/Consultant. The equipment
stored shall be properly protected to prevent damage either to the equipment or to the
floor where they are stored. The equipment from the store shall be moved to the actual
location at the appropriate time so as to avoid damage for such equipment at site.

23.5 All electrical panels, control gears, motors and such other devices, shall be properly
dried by heating before they are installed and energized. These equipments shall be
protected against moisture ingress and corrosion during storage and periodically
inspected. Heavy rotating parts in assembled condition shall be periodically rotated to
prevent corrosion due to prolonged storage and shall also be periodically inspected.

23.6 All critical electrical equipments shall be tested for insulation resistance at least once in
three months from the date of receipt till the date of commissioning and a record of
such measured insulation values shall be maintained by the Contractor. Such records
shall be open for inspection by the Purchaser/Consultant.

23.7 The Contractor shall ensure that all the packing materials, and protection devices used
for the various equipments during transit and storage are removed before the
equipments are installed.

23.8 The consumables and other supplies likely to deteriorate due to storage must be
thoroughly protected and stored in a suitable manner to prevent damage or deterioration
in quality by storage.

23.9 All the materials stored in the open or dusty locations must be covered with suitable
weatherproof and flameproof and flame proof covering material wherever applicable.

23.10 If the materials belonging to the Contractor are stored in areas other than those
earmarked for him, the Purchaser/Consultant will have the right to get it moved to the
area earmarked for the Contractor at Contractor’s cost.

23.11 The Contractor shall be responsible for making suitable indoor storage facilities to store
all equipment which require indoor storage. Normally all the electrical equipments shall
be stored in the closed storage space. The Purchaser/Consultant in addition, may direct
the Contractor to move certain other materials which in his opinion will require indoor
storage, to indoor storage areas which the Contractor shall strictly comply with.

23.12 The Contractor shall arrange for periodic inspection of material/equipment in his
custody until taken over by the Purchaser and shall carry out all protective and
preservative measures required thereupon.

23.13 The Contractor shall also keep a check on the deliveries of the equipment/material
covered in his scope of erection and shall advise the Purchaser well in advance
regarding possible hold-ups in his work due to expected delays in delivery of
equipment, to enable the Purchaser to expedite the deliveries if supplier is different
from the Contractor.

166

Page 166 of 328


23.14 All materials of Contractors should be received only during normal working hours.
Damage of any of the roads due to movement of heavy trucks, trailers, crane and other
equipment of the Contractor shall be made good by the Contractor. Otherwise same
shall be got rectified by the Purchaser at the risk and cost of the Contractor.

23.15 All the I& C electronic equipment shall be stored in Air-Conditioned storage.

24.0 CONSTRUCTION MANAGEMENT

24.1 The field activities of the Contractor working at site will be coordinated by the
Purchaser/Consultant and the Purchaser’s/ Consultant’s decision shall be final in
resolving any disputes or conflicts regarding scheduling and co-ordination of work.
Such decision by the Purchaser/Consultant shall not be a cause for extra compensation
or extension of time for the Contractor.
24.2 The Purchaser/Consultant shall hold weekly meetings at site with Contractor. The
Contractor shall attend such meetings and take notes of discussions during the meeting
and the decisions of the Purchaser / Consultant and shall strictly adhere to those
decisions in performing his ‘Works’. In addition to the above weekly meetings, the
Purchaser / Consultant may call for other meetings and in such a case the Contractor, if
called, will also attend such meetings.
24.3 Time is the essence of the ‘Contract’ and the Contractor shall be responsible for
performance of his Works in accordance with the specified construction schedule. If at
any time, the Contractor is falling behind the schedule, he shall take necessary action to
make good for such delays by increasing his work force or by working overtime or
otherwise accelerate the progress of the work to comply with the schedule and shall
communicate such action in writing to the Purchaser / Consultant satisfying that his
action will compensate for the delay. The Contractor shall not be allowed any extra
compensation for such action.
24.4 The Purchaser / Consultant shall however not be responsible for provision of additional
labour and/or materials or supply or any other services to the Contractor except for the
co-ordination work between various Contractors as set out earlier.
25.0 FIELD OFFICE RECORDS

25.1 The Contractor shall maintain at his site Office up-to-date copies of all drawings,
specifications and other Contract Documents and any other supplementary data
complete with all the latest revisions thereto. The Contractor shall also maintain in
addition the continuous record of all changes to the above Contract Documents,
drawings, specifications, supplementary data, etc. effected at the field and on
completion of his total assignment under the ‘Contract’ shall incorporate all such
changes on the drawings and other Consultant data to indicate as installed conditions of
the equipment furnished and erected under the ‘Contract’. Such drawings and
Engineering, data shall be submitted to the Purchaser / Consultant in required number
of copies. A record of all readings taken during the testing and inspection shall be
maintained by the Contractor. This shall be signed by the erection supervisor and the
Purchaser/Consultant as a token of their acceptance of the same. All such records shall
be handed over to the Purchaser on completion of the ‘Works’.

167

Page 167 of 328


26.0 CONTRACTOR’S MATERIAL BROUGHT TO SITE

26.1 The Contractor shall bring to site all equipment, components, parts, materials including
construction equipment, tools and tackles for the purpose of the ‘Works under
intimation to the Purchaser/Consultant. All such goods shall, from the time of their
being brought vest in Purchaser, but may be used for the purpose of the ‘Works’ only
and shall not on any account be removed or taken away by the Contractor without the
written permission of the Purchaser/Consultant. But the Contractor shall nevertheless
be solely liable and responsible for any loss or destruction thereof and damage thereto.
26.2 The Purchaser shall have a lien on such goods for any sum or sums, which may at any
time, be due or owing to him by the Contractor, under, in respect of or by reasons of the
‘Contract’. After giving a fifteen (15) days notice in writing of his intention to do so,
the Purchaser shall be at liberty to sell and dispose of any such goods, in such manner
as he shall think fit including public auction or private treaty and to apply the proceeds
in or towards the satisfaction of such sum or sums due as aforesaid.
26.3 After the completion of the ‘Works’, the Contractor shall remove from the site under
the direction of the Purchaser/Consultant the materials such as construction equipment,
erection tools and tackles, scaffolding, etc. with the written permission of the Purchaser
/ Consultant. If the Contractor fails to remove such materials, within fifteen (15) days
of issue of a notice by the Purchaser/Consultant to do so, then the Purchaser/Consultant
shall have the liberty to dispose of such materials as detailed under Clause 26.2 above
and credit the proceeds to the account of the Contractor.
26.4 On completion of the work, all rubbish materials and temporary structures of any sort
or kind used for the purpose or connected with the construction/erection work and
heaps are to be removed by the Contractor and all pits and excavations filled up and the
site handed over in a tidy and workmanlike condition and no final payment or
settlement of the account for the said work shall held or due shall be made to the
Contractor till such site clearance shall have been effected by him and such clearance
shall be made by the Purchaser at the expense of the Contractor in the event of his
failure to comply with this provision within 7 (seven) days after receiving notice in
writing from the Purchaser to that effect. If it becomes necessary for the Purchaser to
have the site cleared as indicated above at the expense of the Contractor, the Purchaser
shall under no circumstances be held liable for any losses of damages to such of
Contractors property as may be on such site due to such removal there from, which
removal may be effected by means of public sale of such materials and property in such
a way as deemed fit and convenient to the Purchaser.
26.5 The Contractor must take sufficient care in moving his construction/erection plant and
equipment from one place to another so that they may not cause any damage to the
property of the Purchaser, particularly of the existing structures and overhead and
underground services and in the event of the Contractors failure to do so, the cost of
such damages shall be borne by the Contractor.
27.0 PROTECTION OF PROPERTY AND CONTRACTOR’S LIABILITY

27.1 The Contractor shall be responsible for any damage resulting from his operations. He
shall also be responsible for protection of all persons including members of public and
employees of the Purchaser/Consultant and the employees of other Contractors and
Sub-Contractors and all public and private property including structures, buildings,
other plants and equipment and utilities either above or below the ground.
27.2 The Contractor will ensure provision of necessary safety equipment such as barriers,
signboards, warning lights and alarms, etc. to provide adequate protection to persons

168

Page 168 of 328


and property. The Contractor shall be responsible to give reasonable notice to the
Purchaser/Consultant and the Owner of public or private property and utilities when
such property and utilities are likely to get damaged or injured during the performance
of his ‘Works’ and shall make all necessary arrangements with such owners, related to
removal and/or replacement or protection of such property and utilities.
28.0 PAINTING
28.1 All exposed metal parts of the equipment including pipings, structures, railings, etc.
after installation, unless otherwise surface protected, shall be first painted with at least
one coat of suitable primer which matches the shop primer paint used, after thoroughly
cleaning all such parts of all dirt, rust, scales, greases, oils and other foreign materials
by wire brushing, scraping or sand blasting, and the same being inspected and approved
by the Purchaser for painting. Afterwards, the above parts shall be finished with two
coats of alloyed resin machinery enamel paints. The quality of the finish paint shall be
as per the standards of ISI or equivalent and to be of the colour as approved by the
Purchaser/Consultant.
29.0 INSURANCE
Refer relevant Clauses under Schedule – 10 of Volume – II
30.0 UNFAVOURABLE WORKING CONDITIONS
The Contractor shall confine all his field operations to those works which can be
performed without subjecting the equipment and materials to adverse effects, during
inclement weather conditions, like monsoon, storms, etc. and during other unfavorable
construction conditions. No field activities shall be performed by the Contractor under
conditions which might adversely affect the quality and efficiency thereof, unless
special precautions or measures are taken by the Contractor in a proper and satisfactory
manner in the performance of such works and with the concurrence of the
Purchaser/Consultant. Such unfavorable construction conditions will in no way relieve
the Contractor of his responsibility to perform the ‘Works’ as per the schedule.
31.0 PROTECTION OF MONUMENTS AND REFERENCE POINTS
31.1 The Contractor shall ensure that any finds such as relic, antiquity, coins, fossils, etc.
which he may come across during the course of performance of ‘Works’ either during
excavation or elsewhere are properly protected and handed over to the
Purchaser/Consultant.
Similarly the Contractor shall ensure that the bench marks, reference points, etc., which
are marked out either with the help of Purchaser/Consultant or by the
Purchaser/Consultant shall not be disturbed in any way during the performance of his
‘Works’. If any work is to be performed which may disturb such references, the same
shall be done only after these are transferred to other suitable locations under the
direction of the Purchaser/Consultant. The Contractor shall provide all necessary
materials and assistance for such relocation of reference points, etc.
32.0 WORK & SAFETY REGULATIONS
Refer Technical Specification.
33.0 ELECTRICAL SAFETY REGULATIONS

Refer Technical Specification.

169

Page 169 of 328


34.0 PURCHASER’S INSTRUCTIONS

34.1 The Purchaser/Consultant may, in his absolute discretion, from time to time, issue
further drawings and/or written instructions, details, directions and explanations, which
are collectively referred to as “Purchaser’s Instructions”, in regard to :
34.1.1 Any additional drawings and explanations to exhibit or illustrate details.
34.1.2 The variation or modification of the design, quality or quantity of work or the additions
or omission or substitution of any work.
34.1.3 Any discrepancy in the drawings or between the Schedule of Quantities and/or
specification.
34.1.4 The removal from the site of any materials brought thereon by the Contractor and the
substitution of other materials thereof.
34.1.5 The removal and/or re-execution of any work executed by the Contractor.
34.1.6 The dismissal from the work of any persons employed thereupon.
34.1.7 The opening up for inspection of any work covered up.
34.1.8 The amending and making good of any defects.
34.2 The Contractor shall comply with and duly execute any work covered in such
‘Purchaser’s Instructions’ provided always that verbal instructions, directions, and
explanations given to the Contractor or his foreman upon the work by the
Purchaser/Consultant shall, if involving a variation, be confirmed in writing by the
Purchaser/Consultant within seven (7) days.
34.3 If compliance with the ‘Purchaser’s Instructions as aforesaid involves work and scope
beyond that contemplated by the ‘Contract’, unless the same were issued owing to
some breach of this ‘Contract’ by the Contractor, the Purchaser shall pay to the
Contractor the price of the said work as hereinafter provided.
34.4 If the Contractor after receipt of written notice from the Purchaser/Consultant requiring
compliance, with such further drawings and/or ’Purchaser’s Instructions’ fails to
comply with the same within seven (7) days the Purchaser may employ and pay other
agencies to execute any such work whatsoever, as may be necessary to give effect
thereto, and all costs incurred in connection therewith shall be recoverable from the
Contractor by the Purchaser on a certificate by the Consultant as a debt or may be
deducted by the Purchaser from any money that may become due to the Contractor.
35.0 RIGHTS OF THE PURCHASER/CONSULTANT

35.1 Right to Illustrate and Explain Plans

35.1.1 The various parts of the ‘Contract’ are intended to be complementary to each other but
should any discrepancy appear or any misunderstanding arise as to the import of
anything contained therein, the explanation of the Purchaser/Consultant shall be final
and binding.
35.1.2 The correction of any errors or omissions of the Drawings and Specifications may be
made by the Purchaser/Consultant, when such correction is necessary to bring out
clearly the intention which is indicated by the reasonable interpretation of the Drawings
and Specifications as a whole.

170

Page 170 of 328


35.1.3 Whenever in the Specifications or on the Drawings which are a part of the ‘Contract’ or
which may be furnished to the Contractor for directing this work, the terms and
descriptions of various qualities of workmanship, material, structures, processes, plant
or other features of the ‘Contract’ are described in general terms, the meaning or
fulfillment of which must depend upon individual judgment, then in all such cases the
question of fulfillment of such specifications or requirements shall be decided by the
Purchaser / Consultant and said material shall be furnished, said work shall be done,
and said structure, process, plant or feature shall be constructed, furnished or carried on
in full and complete accordance with his interpretation of the same and to his full
satisfaction and approval, provided such interpretation is not in direct conflict with the
Drawings and Specifications and generally accepted good engineering practice.
35.1.4 Details shown either on the Drawings or in the Specifications shall be done and
furnished as if shown in both except where expressly excepted either in the
Specifications or on the Drawings. Figured dimensions shall in all cases be taken in
preference to scale measurements and detailed drawings consistent with general
drawings shall be taken in preference to the general drawings of the same part of the
work.
35.1.5 The Purchaser / Consultant may, from time to time, prepare for his own use estimates
of quantities or bills of materials required for the work. Copies of such estimates or
bills of materials which may be given to the Contractor for his convenience, or any
lists, weights or quantities of materials or structures which may appear on the drawings
may not be considered as finally correct, sufficiently complete or accurately covering
any portion or all of the work to be done under the ‘Contract’. Such bills or estimates
may be carefully assembled and prepared but their accuracy is not guaranteed. They
may not be accurate as to any particular details and are given only as the best
information available at the time of issue of the information. It is understood that any
such lists or estimates are furnished to the Contractor for his convenience only and not
as lists or estimates of work to be done and many necessary items of work might have
been omitted.
35.1.6 Additional drawings and explanations to exhibit or illustrate details may be provided by
the Purchaser / Consultant whenever necessary and if so provided, and if consistent
with the Drawings and Specifications, it shall be binding upon the Contractor to take
cognizance of the same. The written decision of the Purchaser / Consultant as to the
true construction and meaning of the Drawings and Specifications and of such
additional drawings and explanations shall be binding upon the Contractor.
35.2 Right to Direct Work
35.2.1 The Purchaser / Consultant shall have the right to direct the manner in which all work
under this ‘Contract’ shall be conducted, in so far as it may be necessary to secure the
safe and proper progress and the specified quality of the work, and all work shall be
done and all material shall be furnished to the satisfaction and approval of the
Purchaser / Consultant.
35.2.2 Whenever, in the opinion of the Purchaser / Consultant, the Contractor has made
marked departures from the schedule of completion laid down in the ‘Contract’ or when
untoward circumstances force a departure from the said schedule, the Purchaser /
Consultant, in order to assure the compliance with the schedule and the provisions of
the ‘Contract’, shall direct the order, pace and method of conducting the work, which
shall be adhered to by the Contractor.
35.2.3 If, in the judgment of the Purchaser / Consultant, it becomes necessary at any time to
accelerate the overall plant erection work, the Contractor, when ordered and directed by
the Purchaser / Consultant, shall cease work at any particular point and transfer his men
171

Page 171 of 328


to such other point or points, and execute such portion of his work, as may be required,
to enable others to hasten and properly engage and carry on their work, all as directed
by the Purchaser / Consultant.
35.2.4 Night work will be permitted only with prior approval of the Purchaser / Consultant.
The Purchaser / Consultant may also direct the Contractor to operate extra shifts over
and above normal day shift to completion of ‘Contract’ on schedule if, in his opinion,
such work is required.
35.3 Right to Order Modifications of Methods and Equipment
If at any time the Contractor’s methods, materials or equipment appear to the Purchaser
/ Consultant to be unsafe, inefficient or inadequate for securing the safety of the
workmen or the public, the quality of work or the rate of progress required, he may
order the Contractor to ensure their safety and increase their efficiency and adequacy,
and the Contractor shall promptly comply with such orders. If at any time, the
Contractor’s working force and equipment are in the opinion of the Purchaser /
Consultant, inadequate for securing the necessary progress, as herein stipulated, the
Contractor shall, if so directed, increase the working force and equipment to such an
extent as to give reasonable assurance of compliance with the schedule of completion.
The absence of such demands from the Purchaser / Consultant shall not relieve the
Contractor of his obligations to secure the quality, the safe conducting of the work, and
the rate of progress required by the ‘Contract’, and the Contractor alone shall be and
remain liable and responsible for the safety, efficiency and adequacy of his methods,
materials, working force and equipment, irrespective of whether or not he makes any
change as a result of any order or orders received from the Purchaser / Consultant.
35.4 Right to Perform
The Purchaser reserves the right to perform or have performed in and about the
‘Works’ during the time when the Contractor is performing his work hereunder, such
other work as the Purchaser desires, and the Contractor shall make all reasonable effort
to perform his work hereunder in such a manner as will enable such other work to be
performed without hindrance and shall make no claim for damage against the Purchaser
arising out of such other work to be performed against hindrance and shall make no
claim for damage against the Purchaser arising out of such other work or interference
there from. The Contractor shall work in harmony with such other Contractor’s
regardless of race, religion, colour or national origin and any dispute between
Contractors shall be arbitrated by the Purchaser / Consultant.
36.0 MEASUREMENT OF WORK AND PROGRESS PAYMENTS
36.1 The Purchaser / Consultant may, from time to time, intimate the Contractor that he
requires the works to be measured and the Contractor shall attend or send a qualified
agent to assist the Purchaser / Consultant or his representative in taking such
measurements and calculations and to furnish all particulars as may be required by him.
36.2 Where the erection of equipment, steel structures panels are involved, the basis of such
measurements and progress evaluation shall be weights specified in the shipping
documents or invoices or drawings as decided by the Purchaser / Consultant. Should
the Contractor not attend or neglect or omit to send such agents, then the measurement
taken by the Purchaser / Consultant or approved by him shall be taken to be the correct
measurements of the work. The Contractor or his Agent may, at the time of
measurement, take such notes of measurements as he may require.
36.3 When measurements are effected by conditions already established, the Contractor shall
take field measurements notwithstanding scale or dimensions shown on the drawings.

172

Page 172 of 328


36.4 The measurements so taken and certified correct by the Purchaser / Consultant shall be
the basis for the progress payment to the Contractor. Where the break-up of ‘Contract
on unit basis Price’ is difficult to arrive at, the Purchaser / Consultant and the
Contractor shall work out at the commencement of the ‘Contract’, the weightages or the
cost or the cost break-ups to arrive at a mutually agreeable basis for computation of the
progress estimates.
36.5 To the value so arrived at on the basis of the Contractor’s monthly progress evaluated,
shall be added the amounts earned by the Contractor under supplemental Contracts and
orders if any, till date of the progress estimate. From the total thus computed, all
previous payments plus any amounts due to the Purchaser in accordance with the terms
of this Contract shall be deducted. The remainder shall be paid by the Purchaser to the
Contractor under Interim Certificates from the Consultant.
36.6 In case work is nearly suspended or in case only unimportant progress is being made, or
in case it is apparent that Contractor is about to forfeit his ‘Contract’ or that the money
yet due to him shall not complete his ‘Contract’, the Purchaser may at his discretion
withhold any payment which may be due to the Contractor.
36.7 The Purchaser may withhold part or whole of any payment for erection claimed by the
Contractor, which in opinion of the Purchaser, is necessary to protect himself from loss
on account of :
a) Defective work not remedied or guarantees not met.
b) Claims filed against the Contractor.
c) Failure of the Contractor to make due payment for materials supplied or labour
employed by him.
d) Damage to other Agencie’s/Contractor’s or Purchaser’s or Others’ property.
e) Failure to meet the mutually agreed schedules.
36.8 When the grounds for withholding payments are removed, payments of the amount
due to the Contractor shall be made by the Purchaser within a reasonable period.
36.9 The Contractor shall not demand nor be entitled to receive payment for the work of
portion thereof, except in the manner set forth in this ‘Contract’ and only after the
Purchaser / Consultant shall have given a certificate for such payment.
37.0 ADHERENCE TO MANUFACTURER’S INSTRUCTION
Adherence to instructions of the Manufacturer’s supervisory Consultants, is
compulsory. The Contractor shall work under the guidance of the Manufacturer’s
supervisors to ensure that erection procedures adopted by the Contractor as well as
completed erection of equipment is such as not to interfere with or prevent equipment
from functioning as intended, as well as to the entire satisfaction of the Manufacturer’s
supervisor / Purchaser / Consultant. The Contractor shall also permit and provide all
facilities for the Manufacturer’s erection supervisors to carry out all checks that they
may wish to, and approve any erection procedure and/or final setting and alignment of
components, in order to satisfy themselves that erection has not been carried out as
intended by them. This shall, however, in no way relieve the Contractor of his
responsibility for providing adequate and competent supervision and quality
workmanship.

173

Page 173 of 328


38.0 MODIFICATIONS
The Contractor shall carry out all modifications at site as directed by the Purchaser /
Consultant to complete the work covered in this ‘Contract’. It is the responsibility of
the Contractor to get the prior approval for such modifications from the Purchaser /
Consultant before such works are taken up. The Contractor shall also get the estimates
and the actual time sheets certified by the Purchaser/Consultant, and these certified time
sheets will be the basis for processing his bills for such modification works which are
required to be carried out for no fault of the Contractor.
9.0 DEFECTIVE WORK
If the work or any portion thereof shall be damaged in any way excepting by the acts of
the Purchaser or if defects not readily detected by prior inspection shall develop before
the final completion and acceptance of the whole work, the Contractor shall forthwith
make good, without compensation, such damage or defects in a manner satisfactory to
the Purchaser / Consultant. In no case shall defective or imperfect work be retained.
40.0 WORK OF OTHERS
If any part of the Contractor’s work depends, for proper execution, upon the work of
any other Agency/ any other Contractor, the Contractor shall inspect and promptly
report in writing to the Purchaser / Consultant any defect in such work of other
agencies/other Contractors that render it unsuitable for proper execution of the work
under this ‘Contract’. His failure to so inspect and report shall constitute an acceptance
of the other agency’s/ other Contractor’s work as fit and proper for the reception of his
work, except as to defects which may develop in the work of other Agencies/other
Contractors after the proper execution of the work. To ensure proper execution of his
subsequent work, the Contractor shall inspect work already in place and shall at once
report to the Purchaser / Consultant any discrepancy between the executed work and the
drawings.

174

Page 174 of 328


ANNEXURE – II

GENERAL CONDITIONS FOR CIVIL WORKS

1.0 The Contractor shall make his own arrangement for all labour, construction
equipment, tools and tackles and construction materials. All temporary approach
roads to the site for carrying out construction work shall be constructed and
maintained by the Contractor at his own cost.
2.0 The Contractor shall take all necessary precautions to avoid damage to any
property of the Purchaser or any third party. The Contractor shall also ensure that
the progress of work of other Contractors in the adjoining areas is not hindered.
Any damage occurring should then be made good by the Contractor at his own
expense.
3.0 The Contractor shall take all precautions during execution, especially while
excavating to avoid interference with or, damage to underground works, such as
cables, pipe lines, drains etc. and provide all possible protection to these works
and in case they are damaged, rebuild/divert them at his own cost.
4.0 The Contractor shall carry out necessary precision survey to set out and check
the setting of all works including foundation & anchor bolts etc. to required
tolerances using the grid reference points available in the plant site. The
Contractor shall make and maintain proper bench mark and reference points and
check lines and levels periodically.
5.0 Materials brought to the site shall not be removed from the site without the
written consent of the Purchaser. The Contractor shall submit well in advance for
approval, all samples and specimens as the Purchaser may demand from time to
time. Any material brought to site and rejected by the Purchaser shall be
removed by the Contractor from the site of work immediately within the time
limit specified by the Purchaser. In case, the Contractor is not removing the
rejected materials, the same will be removed by the Purchaser and cost thereof
shall be recovered from the bills of the Contractor.
6.0 The Purchaser may during the progress of work, order the removal of part or
whole of the work executed, found not in accordance with the approved
drawings/ specifications/ written instructions. No extra claims shall be
entertained for removal & re-execution of such work.
7.0 No work shall be covered up or put out of view without the approval of the
Purchaser. In the event of failing to do so, the Contractor shall uncover any part
of the work or make openings in or through the works as the Purchaser may
direct and they shall be made good with materials approved by the Purchaser and
should match with workmanship of the surrounding work.
8.0 The Contractor shall dismantle and remove the stagings and other temporary
facilities like stores, offices, etc. on completion of work, clear and clean the site
where such temporary facilities were built and restore the same to original
condition at his own cost.
9.0 The Contractor shall provide all necessary storage at the site in specified areas
for all materials such as timber, cement, lime and such other materials which are
likely to deteriorate by the action of sun, winds, rain, coastal conditions or other
natural cause due to exposure in the open in such manner that all such materials
shall be duly -protected from damage by weather or any other cause. All such
stores shall be cleared away and the whole site left in good order on completion
175

Page 175 of 328


of the contract. All materials, shall be stacked in such a manner as to facilitate
rapid and easy checking of such materials. The Contractor will not be permitted
to store any of his material in the buildings under construction or already
constructed by him without prior approval of the Purchaser.
10.0 After completion of work, the Contractor shall carry out micro-levelling of the
site within plant area ensuring proper grades and slopes to achieve efficient
drainage of the site. The Contractor shall remove all debris, surplus earth etc. and
dump the same at places/place as directed by the Purchaser within a distance of 8
km from the site.
11.0 The Contractor shall be held responsible for proper performance for buildings
and structures including all other civil work during the guarantee period. Any
defect found during this period will be made good by the Contractor at his own
cost failing which the Purchaser reserves the right to take remedial measures at
the Contractor's risk and cost.
12.0 All excavated materials shall remain the property of the Purchaser. In case the
Contractor wishes to utilise the boulders excavated by him during the excavation
work at the site, the same may be issued to him at prevailing rates on cost
recovery basis. Percentage of voids on stack measurement shall be mutually
agreed. Contractor shall have to account for all excavated hard rock.
13.0 In respect of any portion of works which is to be embedded or covered up by
other works, the Contractor shall submit them to Purchaser for technical
inspection and have the necessary clearance certificates duly signed by the
Purchaser and Contractor before letting such portion to be embedded or covered.
14.0 Wherever works are to be carried out in proximity or within existing facilities,
contractor may have to adopt special methodology of construction suited to
prevailing conditions. He shall make necessary schemes in advance and finalise
the same with the approval of the Purchaser/Consultant.
15.0 On progressive completion of work, the Contractor shall submit to the Purchaser
the following documents for the passing of the work:
a) Certificate on control checking.
b) A copy of each of the concerned working drawings showing thereon all
approved additions and alterations, if any, in the process of execution.
c) Clearance certificates for embedded/covered up works.
d) Manufacturer’s certificates, guarantees and test certificates, as relevant.
16.0 The Contractor shall carry out structural load check with structure test, concrete
sieve test as per IS 456 for equipment foundation & pedestal at locations
specified by the Purchaser on any part of the building/structure at his own cost if
so directed by the Purchaser.
17.0 As the works under the contract are to be carried out within the protected area,
the Contractor shall abide by all the security regulations promulgated from time
to time by the Purchaser/other concerned authorities.
18.0 No blasting is allowed. If required it shall be done with prior approval of
Purchaser without any extra cost.
***************

176

Page 176 of 328


ANNEXURE-III

SAFETY CODE FOR THE CONTRACTOR

GENERAL

1.00 Safety is the responsibility of every employee individually and collectively.

1.01 The Contractor shall submit Safety Code and handed over a copy to all sub- Contractors
working under his control and he should in turn display all rules on the office notice
board for the benefit of all the men working under him.

1.02 The Contractor shall provide adequate guards, illumination, fencing and watching
wherever necessary at the construction site & working area, for the safety & convenience
of public or others.

1.03 Fire extinguishers adequate in number shall be kept by the Contractor at the site of works
where there is risk of fire hazard, especially near the site stores.

1.04 Adequate washing facilities with proper drainage shall be provided properly maintained
near the place of work but at a safe distance from approach roads, Electrical HT Lines
etc.

1.05 When work is to be done near any place, where there is risks of drowning, arrangements
to be made for safe barricading of such areas. All necessary equipment shall be provided
and kept ready for use and necessary steps taken for prompt rescue of any person in
danger and adequate provision shall be made for prompt first-aid treatment of all injuries
likely to be sustained during the course of the work in case of mishap.

1.06 To ensure effective enforcement of the rules and regulations relating to safety
precautions, the arrangements made by the Contractor shall be open to inspection by the
Safety Engineer, the Labour Officer, Engineer-in-charge of the department or their
representatives.

1.07 Notwithstanding the above clauses, there is nothing in those to exempt the Contractor
from the operation of any other Act or Rule in Republic of India for the safety of men and
materials.

1.08 An injury sustained in the plant, must be reported to the First-Aid Station no matter
how slight it is, the injured person will inform Supervisor/Officer in-charge.

1.09 In case of a fatal accident, the Contractor must inform the Engineer in-charge of the
department for which he is working and report in writing should be made in the form.

1.10 Smoking or keeping of naked light is strictly prohibited near gas lines, valves and any
other equipment connected with the gas distribution.

1.11 Smoking and carrying of matches, lighters and other spark producing devices is strictly
prohibited within the area where inflammable liquids are stored, handled or used or
where loading or unloading operations are performed. Any tank or container containing
flammable liquid should be properly grounded for preventing ignition due to static

177

Page 177 of 328


electricity spark. Contractor should ear-mark such areas and provide necessary warning
signals.

1.12 Contractors should ensure that employees do not come to work while still under the
influence of intoxicants. Any employee found on duty under the influence of liquor or of
intoxicating drugs, will be liable to severe disciplinary action.

1.13 Work surrounds should be kept clean, free from oil, grease and other obstructions or
fallen objects like nuts bolts etc.

1.14 After a job or work is completed, all left-over junk and other scrap materials should be
cleared from the area immediately.

1.15 Drums or other make-shift arrangement must not be used in place of ladders or as work
benches or supports for any job.

1.16 Employees must not walk through or across any systems that is brought into operation
unless their duties require them to do so or they are authorised to do so.

1.17 Compressed air should not be used for removing dust from one's clothes. Compressed air
should not be blown against anyone as it may injure or even kill him.

1.18 If an employee, in the course of his work, encounters condition of unusual hazard with
which he is not familiar, he should contact the supervisor for advice before proceeding
further. He should also inform the Contractor as well as the Engineer in-charge.

1.19 Contractors should particularly ensure that they or their employees do not meddle with
any equipment and see that they keep away from such equipment.

1.20 It should be ensured that no one takes rest/shelter below any under cut pit/excavation or
near any stock of materials or under Solar PV arrays.
1.21 i. For any work involving repair & maintenance underground work the Contractor shall
follow the safety procedural orders/instruction issued by the Purchaser.

ii The Contractor shall exercise supervision of such jobs by competent persons within
the meaning of factories act & rules.

iii All persons engage on such jobs shall have to have before hand proper training
instructions as required under Factories Act & Rules.

1.22 The site is in the vicinity of desert area with sand dunes. Contractor has to caution his
employees at site against the associated hazards. If considered necessary, he shall arrange
for a properly equipped team for taking care of contingencies.

2.0 SAFETY MEASURES IN CONTRACTUAL WORK


Whereas, it is necessary to take steps to ensure safety at work sites by the executing
contractual agency, it is incumbent of the Purchaser to introduce all measures to guide,
induce, train and bind the agencies concerned to adopt remedial steps to prevent accidents.
Problem gets aggravated in contractual zones due to lack of training, in-adequate supply of
personal protective equipment, shortage of skilled labour changing deployment of works
etc. Accordingly, the following measures are intended to be introduced and the salient
clauses will be included in the contract documents.

178

Page 178 of 328


2.1 The Contractor shall take all safety precautions and provide adequate supervision in order
to carryout the job safely and without damage to equipment.

2.2 Any special safety precautions, if required to be followed by the Contractor, such clauses
shall be added.

2.3 The executing department would take necessary shut-downs wherever there are hazards of
gases, electricity, moving machinery etc. The Contractor shall ensure that the
shut-down/clearance are taken before sending workers to such locations.

2.4 The Contractor shall supply safety appliance like shoes, safety belts, ladies chappals,
helmets, gloves etc. to his workers depending on working conditions and Life saving
jackets shall be kept in readiness always at the site. The Contractor shall not deploy any
workmen without safety boot and safety helmet and the safety applicable to the specific
work conditions.

2.5 Before starting the day's job, the Purchaser's Supervisor/representatives will ensure that
safety briefing has been done to the Contractor's supervisor who has been imparted safety
induction earlier.

2.6 HOD/Zonal in-charge will nominate Engineer in-charge of the contractual work under
reference who will be fully responsible for the safe execution of the work at site.

2.7 In case of injury to persons, the Contractors shall first take the injured person to the NLC
Dispensary hospital with the necessary forms. In no case the Contractors are allowed to
take injured persons directly to their own Doctors.

2.8 The Contractor shall abide by the provisions of Factories Act, State Factory Rules,
Workmen’s Compensation Act, Payment of Wages Act, Contract Labour (Regulation)
Act etc. and keep the Purchaser indemnified of provisions of the above Acts and Rules.

2.9 The Head of Deptt. Executing the contract upon the satisfaction that the Contractor is not
conforming to the Safety requirements may direct stoppage of work and require the
Contractor to remedy the defects. The Contractor shall not proceed with the work until he
has complied with each direction to the satisfaction of such Head of the Department.

2.10 The Contractor shall be fully responsible for accidents caused due to him or his agents or
workmen’s negligence or carelessness in regard to the observance of the safety
requirements and shall be liable to pay compensation for injuries.

2.11 Without prejudice to the right conferred by the clause 2.09 above for stoppage of work for
violations of safety requirements the Contractor shall be liable for penalty as deemed fit
for violation of safety rules & regulations upto first two instances. For the third violation
he shall be liable to be debarred from further contracts upto a period of one year from the
date of issue of debarring notice.

179

Page 179 of 328


2.12 The Head of the Safety Engg. Deptt. Or the Head of the Deptt. Executing the contract will
assess the penalty amount having regard to the circumstances, in particular, the nature and
gravity of the violation. After issuing a notice to the Contractor to show cause why the
amount specified therein shall not be imposed as a penalty and considering the cause
shown by the Contractors, if any, he shall pass final orders which shall then be final and
binding on the Contractor. The penalty amount will be recoverable from any bill and/or
EMD/SD of the Contractor without any further reference to him.

2.13 Whenever work, at height is involved, Contractor must obtain height passes from Safety
Engg. Deptt. For those persons required to do work at height.

2.14 Contractor must insure all the workmen against “Workmen Compensation Act.”

*******

180

Page 180 of 328


ANNEXURE-IV
COMMERCIAL TERMS AND CONDITIONS FOR OPERATION AND
MAINTENANCE CONTRACT

1.0 DEFINITION OF TERMS:

1.1 Codes and Standards shall mean all the applicable codes & standards as indicated in
the system specification.
1.2 `CONTRACTOR' shall mean the successful BIDDER whose bid has been accepted
by the PURCHASER and on whom the `Contract' or `Purchase order' is placed
by the Purchaser and shall include his heirs, legal representatives, successors and
permitted assignees.

1.3 Contract shall mean and include this contract between the owner and Contractor for the
execution of the works as per agreed terms, conditions, specifications prices and
enforceable as per law.

1.4 Contract period shall mean the period / time schedule agreed in the contract during
which period the Contracted work shall be performed / executed, inclusive of any
period covered by extension(s), duly issued.

1.5 ‘Contract Price’ in relation to particular contract shall mean the total consideration to be
paid by NLC to the Contractor.

1.6 `Date of Contract' shall mean the calendar date on which NLCIL and the
CONTRACTOR have signed the `CONTRACT'.

1.7 "Effective date of Contract for O&M” shall mean the date of final acceptance of installed
PV Solar Power Plant.

1.8 `Notice in Writing', `Written Notice' shall mean any notice in written, typed or printed
characters sent (unless delivered personally or otherwise proved to have been
received) by registered post to the last known private or business address or registered
office of the addressee and shall be deemed to have been received when in the ordinary
course of post it would have been delivered.

1.9 Purchaser/Owner shall mean and include NLC India Limited (NLCIL) and its different
functionaries entrusted with the responsibilities in relation to this contract in respect of
the area of responsibilities of such functionaries.

1.10 ‘Site ’ shall mean the place or places envisaged by NLCIL at which the services are to be
performed, as also such other places as may be specifically provided by NLCIL for the
stated purposes.

1.11 `Work' shall mean the services to be provided by the CONTRACTOR under the scope
of the ‘Contract'.

1.12 Writing' shall include any manuscript, typewritten or printed statement, under or over
signature and/or seal as the case may be.

181

Page 181 of 328


1.13 The various Acts and Regulations are normally available for sale from the following
address:
`Deputy Controller,
Publication Department,
Government of India,
Civil Lines, Delhi - 110 006.

and with leading authorised Government of India book sellers.

2.0 SCOPE OF WORK:

The detailed Scope of Work is indicated in Technical Specification and Conditions of


Contract.

3.0 PRICE BASIS FOR OPERATION & MAINTENANCE:

3.1 The Bidder shall quote “FIRM’ price in Indian rupee for the entire contract period of
ten (10) years after completion of warranty period.

3.2 Price quoted shall include cost of all spares and consumable, to meet NLCIL’s
requirement as specified in the tender specification.

3.3 Bidder are requested to quote their operation and maintenance charges as per the price
schedule (Schedule-7.)

4.0 TIME SCHEDULE:

4.1 The time schedule for operation and maintenance shall be for a period of ten (10) years
after one year warranty period.

5.0 CONTRACT PERFORMANCE BANK GUARANTEE:

5.1 As a contract security for faithful performance of the Contract in accordance with the
terms and conditions specified in the Operation and Maintenance Contract the
CONTRACTOR shall furnish a Contract Performance Bank Guarantee in the form
of irrevocable bank guarantee from any Nationalized Bank or Scheduled Bank
approved by RBI except banks from China in a non-judicial stamp paper for the value
of Rs.80/- 30 days before commencement of operation and maintenance for an amount
equal to 10% of the total Contract price of operation and maintenance contract. The
Contract Performance Bank Guarantee shall be valid for 10 years and shall be valid till
the expiry of 90 days beyond the actual date of successful completion of
operation and maintenance contract period.

5.2 NLC shall have the right to encash the Contract Performance Guarantee for non-
compliance of any or all the terms and conditions of the contract and non
performance with respect to availability, discontinues to do the work before the
completion of period mentioned in Cl. 4.0 above and for failure to comply with any of
the obligations as enumerated in the Contract.

182

Page 182 of 328


5.3 The 90% of CPG value will be allowed for reduction for supply and services
contract under contract No…………dt.………. only on receipt and acceptance of
CPG for this contract.

6.0 TERMS OF PAYMENT

6.1 The O & M charges quoted in Price Schedule-7 (Vol.1 of 3) shall be paid on pro-rata
quarterly basis on certification of work by the Project Manager at the end of every
quarter.

7.0 OPERATION & MAINTENANCE CHARGES

a. The O&M charges shall be inclusive of taxes and duties as applicable except
service tax. But any taxes, levies/fees newly imposed would be reimbursed
extra (with submission of documentary proof from concerned authority).
Similarly, due credit would be given to NLCIL in case of withdrawal or reduction
in applicable taxes/fees/duties. The O&M charges should be quoted for a period
of 10 years.

b. Payment will be made after all statutory deductions as applicable to such type of
contracts. The rate quoted shall deem to be inclusive of all salaries and other
cost, expenses of employees, cost of spares, cost of repair/replacement/
modification of any equipment or system for the entire quoted period of 4 years so
as to give maximum machine availability. The rates are also inclusive of tools &
tackles, etc. and liabilities of every description and all risk of every kind to be
taken in operation, maintenance and handing over the plant to NLCIL by the
contractor.

8.0 MODE OF PAYMENT

8.1 All Payments in Indian Rupees shall be made direct to the Contractor through E-
payment. For effecting E-Payment, Contractor shall furnish necessary details to the
Purchaser. All bank charges shall be to the account of the Contractor.

9.0 GST

9.1 The Contractor shall register with statutory / tax authorities wherever required.
i. The Supplier / Contractor has to provide a copy of the GST Registration Certificate
and also mention their GST Registration No. and Date in each of their invoices /
bills without fail. No invoice or bill will be paid unless the GST Registration No. is
mentioned therein.
9.1.1 i. The GST lumpsum indicated in the price schedule is as per the rates prevailing one
month prior to original schedule date of Tender Opening . Any statutory variation in
respect of GST within the agreed time schedule will be to the account of the
purchaser, at actuals based on the documentary evidence, independent of the ceiling
quoted. Statutory variation arising beyond agreed time schedule shall not be payable

ii. While claiming the GST payment, the contractor should furnish the requisite details
in the invoice as per statutory requirements.

183

Page 183 of 328


11.4 PERSONNEL INCOME TAX & CESS:

11.4.1 Income Tax and Cess, if any payable by the Contractors/ sub-Contractor's employees
shall be paid by the said employees directly, and the Purchaser shall not be liable to pay
the income tax & Cess payable by the employee of the Contractor/sub Contractor and
the purchaser is not responsible for filing the tax returns of contracts
employees/experts.

11.5 Deduction of Tax at source at prevailing rate shall be effected by the Purchaser before
payment as a statutory obligation wherever applicable

12.0 DEPLOYMENT OF QUALIFIED TECHNICAL STAFF IN EXECUTION:

12.1 The Contractor shall engage required qualified & trained persons for the above O&M
works for achieving the guaranteed output. The entire work shall be supervised by a
B.E Degree Holder with experience in similar nature of works.

12.2 The Contractor shall see that one of the technically qualified persons is always
available at the site of work, during working hours, to check all items of work.

13.0 SUSPENSION OF WORK:

13.1 NLCIL give directions from time to time in writing for any valid reasons, without in
any way violating this contract, to the Contractor to suspend the work or any part
thereof. The Contractor shall suspend the work till such time as indicated by NLC. The
Contractor shall not, after receiving such written notice proceed with the works therein
ordered to be suspended until he shall have received written notice or authority to the
effect from the NLC.

14.0 INSPECTION OF WORKS:

14.1 The Purchaser or his duly authorized person shall have at all times, full power to
inspect the Solar PV Power Plant where the Contractor is carrying out the Operation
and Maintenance. The Contractor shall properly carry out the written instruction issued
by the NLCIL.

15.0 TOOLS & TACKLES SPARES AND CONSUMABLES:

15.1 The Contractor shall arrange tools and tackles, spares, and consumables required for the
Operation & Maintenance of the Solar PV Plant. .

16.0 ASSIGNMENT AND SUBLETTING OF CONTRACT:

16.1 The Contractor shall not sublet, transfer or assign the contract or any part there of
without the written permission of NLC. In the event of the Contractor contravening
this condition Owner shall be entitled to entrust the work to other agencies at the
Contractor’s account and risk. The Contractor shall be liable for any loss or damage
which the Corporation may sustain in consequence of or arising out of such replacing
the contract notwithstanding any such permission to sublet, the Contractor shall always
be held responsible for the due fulfillment of the terms and conditions of contract.

184

Page 184 of 328


17.0 REGULATION OF LOCAL AUTHORITIES & STATUTES:-

17.1 The Contractor shall ensure compliance with all statutes, laws, rules and regulations of
the Central or State Governments or any other authority such as the Workmen's
Compensation Act 1923, Payment of Wages Act, Minimum Wages Act - 1948
Employees State Insurance Act, Employees Provident Fund Act, Mines Act Indian
Electricity Rules 1956, the Contract Labour and Regulation Act etc. and the general
rules there-under any and all statutory modifications thereof in connection with
employees engaged by him or his Sub- Contractors in the work.

17.2 The Contractor shall arrange to give all notices required by the said Acts, Regulations
or Bye-laws to be given to any authority or to any Public Officer and pay all fees that
may be properly chargeable in respect of the `works’ and lodge the receipts with NLC,
Obtaining all permits and licenses required thereupon is the responsibility of the
Contractor.

17.3 All registration and statutory inspection fees, if any, in respect of his work pursuant to
this `Contract' shall be to the account of the Contractor.

18.0 NLCIL'S LIEN ON EQUIPMENT:-

18.1 No material brought to the “site” shall be removed from the “site” by the Contractor
and/or his SUB- Contractor without the prior written approval of NLC.

19.0 CO-OPERATION WITH OTHER CONTRACTORS-

19.1 The Contractor shall co-operate with all other Contractor’s or tradesmen of NLC who
may be performing other works on behalf of the NLC and the workmen who may be
employed by NLCIL and doing work in the vicinity of the works under their respective
contracts. The Contractor shall also so arrange to perform his work as to minimize, to
the maximum extent possible interference with the work of other Contractor’s and his
workmen. NLCIL shall determine the resolution of any difference of conflict that may
arise between the Contractor and other Contractor or between the Contractor and the
workmen of NLCIL in regard of their work. If the works of this Contractor is delayed
because of any acts or omissions of another Contractor, the Contractor shall have no
claim against NLCIL on that account other than an extension of time for a completing
his works.

20.0 DISCIPLINE OF WORKMEN:

20.1 The Contractor shall adhere to the disciplinary procedure set by NLCIL in respect of his
employees and workmen at 'Site'. NLCIL shall be at liberty to object to the presence of
any representative or employee of the Contractor at the `Site' if in the opinion of
NLCIL such employee has misconducted himself or be incompetent or negligent or
otherwise undesirable and then the Contractor shall promptly remove such a person
objected to, and provide in his place a competent replacement at his own expenses.

21.0 MANPOWER REPORT:-

21.1 The Contractor shall submit to NLCIL on the last week of every month, a man-hour
schedule for the next month, detailing the man hours scheduled for the month, skill
wise and area wise.

185

Page 185 of 328


21.2 The Contractor shall also submit to NLCIL on the 7th day of every month, a manpower
report of the previous month detailing the number of persons scheduled to have been
employed and actually employed, skill-wise and the areas of employment of such
labour.

21.3 The Contractor shall also submit periodically such of the reports as NLCIL may call for
from time to time.

22.0 FIRE PROTECTION: -

22.1 The work procedures that are to be used during the maintenance shall be those, which
minimize fire hazards to the extent practicable. Combustible materials, combustible
waste and rubbish shall be collected and removed from the `Site' at least once a day.

22.2 The Contractor shall provide enough fire protection equipment of the types and number
for the warehouses, office, temporary structures etc. Access to such fire protection
equipment shall be easy and kept open at all times.

23.0 SECURITY:-

23.1 The Contractor shall have total responsibility for all equipment and materials in his
custody. The Contractor shall make suitable Security arrangements including
employment of Security personnel to ensure the protection of all materials, equipment
and `Works' from theft, fire, pilferage and any other damages and loss. All materials of
the Contractor shall enter and leave the Project `Site' only with the written permission
of NLC in the prescribed manner.

24.0 CONTRACTOR'S MATERIALS BROUGHT ON TO SITE:-

24.1 The Contractor shall bring to `Site' all the equipment, components, parts, materials,
including equipment, tools and tackles for the purpose of the `Works' under
intimation to NLCIL. All such goods shall from the time of their being brought may
be used for the purpose of the `Works' only and shall not on any account be removed
or taken away by the Contractor without the written permission of NLC. But, the
Contractor shall nevertheless be solely liable and responsible for any loss or destruction
thereof and damage thereto.

24.2 NLC shall have lien on such goods for any sum or sums which may at any time be
due or owing to him by the Contractor , under in respect of or by reasons of the
`Contract'. After giving a fifteen (15) days' notice in writing of his intention to do
so, NLCIL shall be at liberty to sell and dispose of any such goods, in such manner as
he shall think fit including public auction or private treaty and to apply the
proceeds in or towards the satisfaction of such sum or sums due as aforesaid.

24.3 After the completion of the `works' the Contractor shall remove from the `Site' under
the direction of NLCIL his own materials such as equipment, tools and tackles,
scaffolding, etc. which were brought by him with the written permission of NLC. If
the Contractor fails to remove such materials, within 15 (fifteen) days of issue
of a notice by NLCIL to do so, then NLCIL shall have the liberty to dispose off such
materials and credit the proceeds thereto the account of the Contractor .

24.4 On completion of the work, all rubbish, kilns, vats, tanks, materials and temporary
structure of any sort or kind used for the purpose or connected with the work are to be
186

Page 186 of 328


removed by the Contractor and all pits and excavations filled up and the site handed
over in a tidy and workmanlike condition and no final payment in settlement of the
account for the said work shall be held to be due or shall be made to the Contractor till
such site clearance shall have been effected by him and such clearance may be made by
NLCIL at the expenses of the Contractor in the event of his failure to comply with this
provision within 7 days after receiving notice in writing from NLCIL to that effect. If it
becomes necessary for NLCIL to have the site cleared as indicated above at the expense
of the Contractor, NLCIL shall under no circumstances be held liable for any losses or
damages to such of Contractor’s property as may be on such site due to such removal
there from, which removal may be effected by means of public sale of such materials
and property or in such a way as seems fit and most convenient to NLCIL.

24.5 The Contractor must take sufficient care in moving his equipment from one place to
another so that they may not cause any damage to the property of NLCIL, particularly
to the existing structures and overhead and underground services and in the event of
Contractor's failure to do so, the cost of such damages shall be borne by the Contractor.

25.0 MODIFICATION AND UPGRADATION

25.1 The Contractor shall advise NLC of any modifications or upgrades of the Solar PV
Power Plant for increasing safety and reliability, improved production performance.
25.2 If Contractor on his own initiative wishes to upgrade or modify the Solar PV Power
Plant then, the Contractor may carry out the upgrade at his own cost with the prior
written consent of NLCIL.

25.3 If any alteration or modification is required to be made in the Solar PV Power Plant to
comply with all provision of law for the time being in force on the Commencement
Date of this agreements the Contractor shall take necessary step to make Solar PV
Power Plant comply with the provisions of such law.

25.4 If modification is required in the Solar PV Power Plant to comply with the provisions
of any Law, which came into force after the commencement date of this agreement,
then such modification shall be taken up by NLCIL. The Contractor at the cost of
NLCIL on the terms & conditions as may be agreed by the parties and in such case the
time spent shall not be classified as down time hours.

25.5 Upgrading of Solar PV Power Plant will be done in consultation with O.E.M. (Original
Equipment manufacturer) & through the Contractor on mutually agreed terms &
conditions.

26.0 ACCIDENT / DAMAGE

26.1 If there is any damage to Solar PV Power Plant due to accident or otherwise and it is
established that the said accident and/or damage has been occurred due to the operators
faults or negligence, Contractor shall be responsible for payment towards rectification
of such damage of Solar PV Power Plant.

26.2 If any damage is caused to Solar PV Power Plant and / or accident occurred at the site
of the said Solar PV Power Plant, due to improper maintenance of the Solar PV Power
Plant by the Contractor, the Contractor shall be responsible and liable against all such
damage and compensation and indemnify Purchaser against such loss or damage
incurred or be incurred by NLCIL.

187

Page 187 of 328


26.3 The parties hereto are independent to each other where in NLCIL is a principal,
Contractor is a Contractor and all the relationships between NLC and Contractor under
this agreement are contractual in nature but none else.

26.4 Nothing in this agreement shall be deemed to constitute or form an employment,


partnership, agency or any other form of business relationship between the parties
except as stated above.

27.0 LIMITATIONS OF LIABILITY


27.1 Except in case of Criminal Negligence or Willful Misconduct,
i) The Contractor shall not be liable to the Purchaser, whether in Contract,
tort, or otherwise, for any indirect or consequential loss or damage, loss
of use, loss of production or loss of profits or interest, costs, provided that
this exclusion shall not apply to any obligation of the Contractor to pay
liquidated damages to the Purchaser
and
ii) The aggregate liability of the Contractor to the Purchaser, whether under
the Contract, in tort or otherwise, shall not exceed the total Contract Price,
provided that this limitation shall not apply to any obligation of the
Contractor to indemnify the Purchaser with respect to Patent
infringement’.

28.0 GENERAL:

28.1 Contractor shall meet the NLCIL authorised representative and receive instructions
regarding the works to be carried out. The Contractor or his representative shall be
available at all times in the site in order to execute any urgent work.

28.2 Decision of the NLCIL shall be final and binding in all matters regarding contract.

29.0 SAFETY:

29.1 The Contractor shall ensure the safety of his workmen against accidents and injuries
while at work as required by the relevant rules. It shall be the obligations of the
Contractor to pay compensation as per workmen compensation Act and to extend co-
operation to the officers in any enquiry conducted there on. No responsibility shall rest
with the corporation in this regard. The Contractor shall work in co-ordination and
close co-operation with the staff working in the area.
29.2 While doing works, all the safety precautions and safety rules should be followed and
failure to adhere to the same shall be viewed seriously and the contract shall be
terminated if required."
29.3 The Contractor shall arrange all safety gadgets for workmen engaged by him.
29.4 Before the Contractor connects any electrical appliances to any plug or socket
belonging to the other Contractor or NLCIL, he shall.
(a) Satisfy NLCIL that the appliance is in good working condition.
(b) Inform NLCIL of the maximum current rating, voltage and phases of the
appliances.
(c) Obtain permission of NLCIL detailing the sockets to which the appliances may be
connected
188

Page 188 of 328


29.5 NLCIL will not grant permission to plug-in until he is satisfied that the appliance is in
good conditions and is fitted with a suitable plug. the appliance is fitted with a suitable
cable having two earth conductors, one of which shall be an earthed metal sheath
surrounding the cores.

29.6 No electric cable in use by NLCIL will be disturbed without prior permission. No
weight of any description will be imposed on any such cable and no ladder or similar
equipment will rest against or be attached to it.

29.7 No work shall be carried out on any live equipment. The Equipment must be made safe
and a permit to work issued before any work is carried out.

30.0 WORKS:

30.1 The site of work shall be kept clean, free from rubbish and dismantled materials. All
rejected and unwanted materials, debris etc., shall be removed from the site then and
there. If the Contractor fails to do such clearance work, the work shall be got done
departmentally, two days after the issue of a single written notice to the Contractor and
the expenditure incurred there for shall be recovered from the Contractor 's bills.

30.2 Any faulty work noticed and pointed out by NLCIL shall be rectified by the Contractor

30.3 The Contractor shall Work in co-ordination and close co-operation with other
Contractor’s staff working in the area.

31.0 MATERIALS:-

31.1 The material used shall comply with the relevant standard specification and shall be
approved by NLCIL.

32.0 LABOUR:-

32.1 Under the provisions of the Contract Labour (Regulation and Abolition) Act 1970 the
Contract Labour (Regulation and abolition) Rules 1971 any Contractor who employs or
employed 20 or more men on any day of the preceding 12 months shall obtain a
licence. The licence so obtained shall be renewed every year.

32.2 The Contractor shall maintain the following registers.

Register of workmen in Form XIII as per rule 75 of the Contract Labour


(R & A Rule) central 1971.)
Muster Roll.
Register of wages
Register of deduction.
Register of over time.
Register of fines.
Register of Advances.
Wages slip.

32.3 The Contractor shall issue an employment card in Form XIV as per rule 76 of the
contract labour (Regulation and Abolition) Rules 1971.

189

Page 189 of 328


32.4 As per the provisions under Chapter IV of the Central Contract Labour (Regulation and
Abolition) Rules 1971 the Contractor should observe the rules strictly regarding the
payment of wages to the contract workmen.

32.5 Failure to comply with the statutory provisions will entail prosecution by the statutory
authorities beside black listing the Contractor .

"The Contractor should produce the following declaration along with their application
for issue of identity cards to the workmen. "Certified that the following contract
workers engaged by me bear good conduct, that their antecedents have been verified
and found satisfactory".
Sl. Name of the Contract Address Identification
No. Worker Marks

33.0 INSURANCE:-
33.1. The Contractor shall arrange for Workmen's Compensation Insurance, Comprehensive
Automobile Insurance and Comprehensive General Liability Insurance and till
completion of Operation & Maintenance period which shall also be the responsibility of
the Contractor.
33.2 The Contractor should take group insurance scheme for the workers under his contract,
which may or may not result in partial or permanent disablement. The first bill will be
passed after producing group insurance policy.
33.3 The above are only illustrative list of insurance covers normally required and it will
be the responsibility of the Contractor to maintain at his cost all necessary insurance
coverage to the extent both in time and amount to take care of all his liabilities either
direct or indirect in pursuance of the `Contract'.
33.4 Third Party Liability Insurance:
The policy shall cover third party liability. The third party liability shall cover the loss /
disablement of human life (persons not belonging to the Contractor) and also cover the
risk of damages to others' materials/equipment/ properties during O&M .The value of
third party liability for compensation for loss .of human life or partial / full disablement
shall be of required statutory value but not less than Rs.2 lakh per death, Rs.1.5 lakh per
full disablement and Rs.1 lakh per partial disablement and shall nevertheless cover such
compensation as may be awarded by a Court of Law in India or abroad and cover for
damage to others' equipment /surrounding property as approved by NLCIL.
34.0 RESOLUTION OF DISPUTES AND ARBITRATION:-
34.1 Informal dispute resolution:
34.1.1 The parties agree to use reasonable efforts to resolve all disputes equitably and in good
faith.
34.1.2 If any dispute between the Contractor and NLC arises it shall in the first
instance be referred in writing to NLC, who shall endeavor to resolve the dispute
amicably and render a decision within 30 days. The period of 30 days shall be
reckoned from the date of intimation of the dispute is received by NLC.
34.1.3 The agreement and the rights and obligations of the Parties, shall remain in full force
and effect pending the award in any arbitration proceedings. Supplies and/ or services
under the Contract shall, if reasonably possible, continue during arbitration
proceedings.

190

Page 190 of 328


34.1.4 For the purposes of this clause, the term `dispute' shall include a demand or
difference of any kind whatsoever, arising out of the Contract and respecting the
performance of the CONTRACT, whether during the CONTRACT period including
extensions if any, or after completion, and whether before or after termination,
abandonment or breach of the CONTRACT (except as to any matter, the decision of
which is specifically provided for in any of these conditions).
35.2 Conciliation:
35.2.1 If the party is dissatisfied with the decision rendered by the Purchaser, or if the
Purchaser omits or declines to render a decision within the said period of 30 days, then
within a further period of 30 days, the dissatisfied Party shall require by a
notification that the dispute be referred to Conciliation in the manner as per the
‘NLC Conciliation Rules’, copy of which is available with the NLC offices and the
Bidders/ Contractors shall abide by the NLC Conciliation Rules’ for resolving any
dispute arising out of this contract. Such a notification shall be in writing and it shall
be duly served on the other party. Failure to invoke the Conciliation within the time
stipulated shall debar the party from seeking reference to Conciliation.
35.2..2 Except as otherwise provided in this clause, any dispute arising out of or
relating to this agreement, or the breach, termination or validity thereof, shall be
settled by Conciliation in accordance with ‘NLC Conciliation Rules’. The
Conciliation shall be held at Neyveli / Chennai / Tuticorin / Barsingsar/ or in a place
with in India mutually agreed by the parties. The Conciliation proceedings shall be
conducted, and the award shall be rendered in English. The award shall state the
reasons upon which it is based.
35.2.3 There shall be three Conciliators, who will be appointed as per Section-5 of the ‘NLC
Conciliation Rules’.

35.2.4 The Contract agreement / Purchase order conditions and the rights and obligations of
the Parties, shall remain in full force and effect during the Conciliation proceedings.
Supplies and / or services under the Contract shall, if reasonably possible, continue
during the Conciliation proceedings.
35.2.5 For the purpose of this clause, the term ‘dispute’ shall include a demand or difference
of any kind whatsoever, arising out of the Contract and respecting the performance of
the Contract, whether during the Contract period including extensions if any, or after
completion, and whether before or after termination, abandonment or breach of the
Contract. (except as to any matter, the decision of which is specifically otherwise
provided for in any of these conditions).
35.2.6 Only in case of failure to resolve the dispute through Conciliation, Arbitration can be
resorted to or Judicial remedy can be sought for.
35.2.7 Once the settlement agreement is signed with respect to a dispute, the same dispute is
not subject to further appeal through Arbitration or Judicial Proceedings.

35.2..8 Anything not found included in the ‘NLC Conciliation Rules’, but necessary to conduct
the conciliation proceedings will be dealt with as per the provisions of the ‘Arbitration
and Conciliation Act 1996 -Part-III’ or as per the statutory provisions modified from
time to time.

35.3 Arbitration of disputes : (Other Contractors)


35.3.1 If either party is dissatisfied with the decision rendered by the NLCIL, or if the NLCIL
omits or declines to render a decision within the said period of 30 days, then within a
further period of 30 days, the dissatisfied Party may require by a notification that the
191

Page 191 of 328


dispute be referred to arbitration in the manner hereinafter provided. Such a notification
shall be in writing and it shall be duly served on the other party. Failure to invoke the
arbitration within the time schedule shall debar the party from seeking reference to
arbitration.

35.3.2 Except as otherwise provided in this clause, any dispute arising out of or relating to this
agreement, or the breach, termination or validity thereof, shall be finally settled by
arbitration in accordance with the Arbitration and Conciliation Act 1996 (the ``Act'').
The arbitration shall be held at Chennai, Tamil Nadu. The arbitration proceedings shall
be conducted, and the award shall be rendered in English. The award shall state the
reasons upon which it is based. Interest, if awarded by the arbitrators, shall be at a rate
not exceeding the Cash Credit rate prevailing on the date of the award. All interest
payments so awarded are subject to deduction of TDS at sources as applicable at
prevailing rates of Income Tax.

35.3.3 There shall be three arbitrators of whom each Party shall appoint one. The Party
requesting that the dispute be referred to arbitration shall, within 30 days of the
notification in terms of Clause 31.3.1, appoint an arbitrator as also call upon the other
Party to appoint an arbitrator within 30 days. The two arbitrators so appointed shall,
within 30 days of the date on which the second of them is appointed, agree on the third
arbitrator who shall act as the presiding arbitrator of the tribunal.

35.3.4 The agreement and the rights and obligations of the Parties, shall remain in full force
and effect pending the award in any arbitration proceedings. Supplies and/ or services
under the Contract shall, if reasonably possible, continue during arbitration
proceedings.

35.3.5 For the purposes of this clause, the term `dispute' shall include a demand or
difference of any kind whatsoever, arising out of the Contract and respecting the
performance of the Contract, whether during the Contract period including extensions if
any, or after completion, and whether before or after termination, abandonment or
breach of the Contract (except as to any matter, the decision of which is specifically
provided for in any of these conditions).

35.4 The party, in whose favour the Award is passed shall be entitled to reach the entire costs
of Arbitration from the other party. The Arbitration shall indicate the above in their
award clearly.

35.5 IN CASE OF PUBLIC SECTOR ENTERPRISES:

In the event of any dispute or difference, relating to the interpretation and application of
the provisions of the Contracts, such dispute or difference shall be referred by either
party to the arbitration of one of the Arbitrators in the Department of Public
Enterprises. The Arbitration and Conciliation Act, 1996 shall not be applicable to the
arbitration under this clause. The award of the Arbitrator shall be binding upon the
parties to the dispute, provided, however, any party aggrieved by such award may
make a further reference for setting aside or revision of the award to the Law
Secretary, Department of Legal Affairs, Ministry of Law & Justice, Government of
India. Upon such reference the dispute shall be decided by the Law Secretary or the
Special Secretary/Additional Secretary when so authorized by the Law Secretary,
whose decision shall bind the parties finally and conclusively. The parties in the

192

Page 192 of 328


dispute will share equally the cost of arbitration as intimated by the Arbitrator. The
procedure to be adopted in the above case shall be as per DPE guidelines No. DPE
OM No. 4(1)/2011-DPE(PMA)-GL dated 12.06.2013.

36.0 FORCE MAJEURE:

36.1 Force majeure herein defined is a cause which is beyond the control of the Contractor or
the Purchaser, which they could not foresee and which substantially affect the
performance of the “contract” such as

36.1.1 Natural phenomena, including but not limited to floods, droughts, Earthquakes and
epidemics

36.1.2 Acts of any government, domestic or foreign, including but not limited to war, declared
or undeclared priorities, quarantines, embargoes,

33.1.3 Strikes, lock outs and sabotage.

36.1.4 Piracy

36.1.5 Riots and civil commotions Provided either party shall within fifteen (15) days from the
occurrence of such a cause notify the other in writing of such cause.

36.1.6 However Power cut and failure in water supply shall not be considered under “Force
Majeure” condition.

36.2 The Contractor or the owner shall not be liable for delays in performing the
respective obligations resulting from any force majeure condition occurred. The date of
completion shall be extended by a reasonable time

36.3 If the performance as a whole or part by the Contractor or any obligations under the
Contract is prevented or delayed by “Force majeure” condition for a period exceeding
120 days, the Purchaser may at his option terminate the contract by notice in writing.

36.4 Force Majeure conditions prevailing at the works of the Sub-Suppliers / Sub-
Contractors other than 4 major sub-suppliers (the names of which to be indicated by the
contractor) shall not be recognized by the Purchaser on any account and it shall be upto
the Contractor to make necessary alternative arrangement to execute the Contract
within the agreed time schedule.

36.5 No increase or decrease in price shall be payable due to Force Majeure condition.

37.0 CONTRACTOR’S DEFAULT:

37.1 If the Contractor discontinuous to do the work before the completion of time indicated
in Cl.4.0 then in such case NLCIL may give notice in writing and shall be at liberty to
employ other person / persons and forthwith execute such part of the `works' as the
Contractor may have neglected to do or if NLCIL shall think fit it shall be lawful for
him without prejudice to any other right he may have under the `Contract' to take the
`Works' wholly or in part out of the Contractor’s hands and re-contract with any
other person or persons, complete the `works' or any part thereof and in that event
NLCIL shall be free to use without hire charges, of all Contractor’s equipment that
may have been at the time on the `Site' in connection with the `Works' without being
193

Page 193 of 328


responsible to the Contractor for fair wear and tear thereof and to the exclusion of
any right of the Contractor, over the same and NLCIL shall be entitled to retain and
apply any balance of money which may otherwise due in the `Contract' by him to the
Contractor or such part thereof as may be necessary to the payment of the cost of
executing the said part of the `Works' or of completing the works as the case may
be. If the cost of completing the `works' or executing a part thereof as aforesaid shall
exceed the balance due to the Contractor, the Contractor shall pay such excess.

37.2 In such a event NLCIL shall also have the right to encash the Contract Performance
Bank Guarantee for non-performance of Contract.

38.0 TERMINATION OF CONTRACT:-

38.1 NLC reserves the right to terminate the CONTRACT either in part or in full due to
reason other than those mentioned under clause entitled Contractor’s Default. NLC
shall, in such an event, give 30 (thirty) days notice in writing to the Contractor of his
decision to do so.

38.2 The Contractor upon receipt of such notice shall discontinue the work on the date and
to the extent specified in the notice, make all reasonable efforts to obtain cancellation of
all order and Contracts to the extent they are related to the work terminated and upon
terms satisfactory to NLCIL, stop all further sub-Contracting or purchasing activity
related to the work terminated and assist NLCIL in maintenance, protection and
disposition of the works acquired under the Contract by NLCIL.

38.3 In the event of such a termination, the Contractor shall be paid compensation, equitable
and reasonable dictated by the circumstances prevalent at the time of termination. No
consequential damages shall be payable by the NLCIL to the Contractor in the event of
termination.

38.4 If the Contractor is an individual or a Proprietor concern and the individuals or the
proprietor dies and if the Contractor is a partnership concern and one of the partners
dies, then unless the NLCIL is satisfied that the legal representatives of the individual
Contractor or the Proprietor of the proprietary concern and in the case of partnership,
surviving partners, are capable of carrying out and completing the Contract NLCIL
shall be entitled to cancel the Contract as to its incomplete part without being in any
way liable to payment of any compensation to the estate of deceased Contractor
and/ or to the surviving partners of the Contractor 's firm on account of the
cancellation of the Contract. The decision of NLCIL that the legal representatives of
the deceased Contractor or surviving partners of the Contractor’s firm cannot carry out
and complete the Contract shall be final and binding on the parties. In the event of
such cancellation NLCIL shall not hold the estate of the deceased Contractor and/ or
the surviving partners of the estate of the deceased Contractor and/ or the surviving
partners of the Contractor's firm liable to damages for not completing the Contract.

39.0 HANDING OVER OF THE EQUIPMENT AFTER COMPLETION OF


CONTRACT PERIOD:
39.1 The entire plant shall be handed over to NLCIL in good working condition after
completion of ten years of O&M contract. The Contractor shall attend the defects if
any or replacement of any worn-out parts before handing over of the plant to NLCIL.
If the Contractor fails to attend the defects or to replace the worn-out parts, NLCIL
shall recover the relevant cost from the payment due to the Contractor.

194

Page 194 of 328


40.0 MAINTENANCE OF HISTORY CARD:

40.1 The Contractor shall maintain a history register and submit to the NLCIL at the end of
each calendar year for review.

40.2 The history card shall contain all the works carried out including replacement of spares
& consumables etc.

41.0 COMPLETION OF CONTRACT PERIOD:

41.1 The contract period shall automatically cease to exist after ten years from the effective
date of O&M contract and the Contractor shall have no right to ask for any extension.
However, NLCIL at its discretion can extend this contract, for further period at the
mutually agreed price and terms & conditions.

42.0 JURISDICTION:

42.1 The Civil Courts having ordinary original civil jurisdiction over Andaman & Nicobar
Islands shall have exclusive jurisdiction in regard to all questions of disputes of
whatever nature including the arbitration proceedings, if any arising under the Contract
with NLCIL.

43.0 GOVERNING LAWS AND REGULATIONS:-

43.1 This Contract shall be governed and construed according to the Indian Laws and
Regulations.

195

Page 195 of 328


APPENDIX-A
Sheet 1 of 3
BANK GUARANTEE "FORMAT" FOR RELEASE OF
"LIQUIDATED DAMAGES AMOUNT"
Note:
1. This guarantee has to be furnished by a Nationalized Bank/Scheduled Bank authorised
by RBI except Bank of China.
2. The Bank Guarantee should be furnished on Stamp Paper of value not less than Rs.80/-.
3. The Stamp Paper should have been purchased in the name of the Bank executing the
Guarantee.

Bank Guarantee No…………….


Date: …………………………...
To
The General Manager/ Contracts
NLC India Limited,
Block-1, Neyveli- 607 801,
Cuddalore District, Tamil Nadu, INDIA.

Dear Sirs,

1.0 Pursuant to the Contract No………. ……………………………..dated ……………


herein after referred to as “ THE CONTRACT” with M/s……………………………..
herein after referred to as “THE CONTRACTOR” which expression shall, unless
repugnant to the context or meaning thereof, includes its successors, administrators
representatives and assignees have concluded with M/s. NLC India Limited, Neyveli,
hereinafter referred to as the “PURCHASER” (which expression shall, unless
repugnant to the context or meaning thereof, include its successors, administrators,
representatives and assignees vide Contract No. . . . . and the subsequent amendments
thereto the CONTRACTOR has undertaken to execute the work of……………. for a
Total Contract Value of Rs/FC……………. (Rupees/FC……………………………
only).

2.0 Whereas as per Clause …………, of the Contract the CONTRACTOR should have
completed the work of……………. by ……………. and as per the Clause ………… of
the Contract, the PURCHASER is entitled to levy Liquidated Damages for delays.

3.0 Whereas the CONTRACTOR failed to adhere to the Time Schedule or, stipulated in
the Contract for which, the PURCHASER has recovered a sum of Rs/FC……………..
(Rupees/FC………………………….only) towards Liquidated Damages for the delays
in the execution of works in accordance with the Clause………..of the Contract.

4.0 Whereas the CONTRACTOR has requested the PURCHASER for the release of the
said amount withheld towards Liquidated Damages for the delay in execution of work
to enable him to overcome the Liquidity problems. In consideration of the above
request, the PURCHASER has agreed to withheld 10% of the amount recoverable and
to release 90% of amount recovered towards Liquidated Damages subject to the

196

Page 196 of 328


Sheet 2 of 3
condition that the CONTRACTOR furnishes a Bank Guarantee for the 100% of amount
withheld towards Liquidated Damages.

5.0 We,………. (bank)…………………………………………….(address) having our


Head office at ………………hereinafter referred to as the “BANK”, which expression
shall include its successors, representatives, administrators, and assignees do hereby
irrevocably undertake that in the event of the PURCHASER deciding not to waive the
Liquidated Damages recovered from the CONTRACTOR and thereby deciding to
finally confirm the levy and recover the amount of Liquidate Damages provisionally
released, to pay the amount of Rs/FC…………….
(Rupees/FC…………………….only) due and payable under this guarantee to the
PURCHASER without any demur, merely on demand from the PURCHASER. Any
such demand made by the PURCHASER on the Bank shall be conclusive and binding,
absolute and unequivocal as regards the amount due and payable by the Bank under this
guarantee, notwithstanding any difference between the PURCHASER and the
CONTRACTOR or any dispute or disputes raised/ pending before any court, tribunal
arbitrator or any other authority.

6.0 This guarantee will not be discharged due to the change in the constitution of the Bank
or the CONTRACTOR(S).

7.0 The PURCHASER shall have the fullest liberty without affecting in any way the
liability of the Bank under this guarantee from time to time to extend the time of
performance by the CONTRACTOR. The Bank shall not be released from its liabilities
under these presents by any exercise of the PURCHASER of the liberty with reference
to the matter aforesaid.

8.0 We, the Bank also agree that the PURCHASER shall be entitled at his option to enforce
this Bank Guarantee against the Bank as a Principal debtor in the first instance
notwithstanding any other security or guarantee that it may have in relation to the
CONTRACTOR’S liabilities.

9.0 In any case our liability under this guarantee shall not exceed Rs/FC……………..
(Rupees/FC…………………………only). This guarantee will be valid upto………
(Scheduled date of completion of Contract) and shall be extended for such period as
may be desired by M/s. . . . . . . . . . . . on whose behalf this guarantee has been given.

10.0 The Bank further agrees that the decision of the PURCHASER as to the failure on the
part of the CONTRCTOR to fulfill the contractual obligations stipulated in the said
Contract and/ or to the amount payable by the Bank to the PURCHASER shall be final
conclusive and binding.

11.0 This guarantee is revocable only with the written consent of the PURCHASER.

12.0 This guarantee deed must be returned to us to upon the expiration of the guarantee or
after fulfilment of the obligations specified in the guarantee.

197

Page 197 of 328


Sheet 3 of 3

13.0 Notwithstanding anything contained herein:

a. Our liability under this bank guarantee shall not exceed ……………. (in words)
b. This bank guarantee shall be valid upto…………………..: and
c. We are liable to pay the guaranteed amount or any part thereof under this bank
guarantee only and only if you serve upon us a written claim or demand on or
before…………..

Dated this………….. day of…………………… 20

Witness (Signature)
Name in Block Letters
1 Designation
Signature Staff Code No.
Name in Block Letters
Occupation
Address

(Banker’s seal)
2 Attorney as per Power of
Signature Attorney No……………..
Name in Block Letters Dated:……………..
Occupation
Address

198

Page 198 of 328


APPENDIX-B
Sheet 1 of 3
FORMAT OF
RETENTION MONEY BANK GUARANTEE
NOTE.

1. This guarantee has to be furnished by a Nationalized Bank/Scheduled Bank authorised by


RBI except Bank of China. NLCIL reserves its rights to reject the Bank Guarantee if the
same is not in the specified format.

2. This bank guarantee should be furnished on stamp paper of value not less than Rs. 80.00

3. The stamp paper should have been purchased in the name of the Bank executing the
Guarantee.

4. In the case of foreign bidder the B.G may be furnished by an international reputed bank
acceptable to the PURCHASER/ RBI.

5. The Retention bank guarantee shall be valid till the actual date of completion of Take over
Test.

6. Any deviation in this format will not be acceptable.


RETENTION MONEY BANK GUARANTEE No.............
PLACE: ………
DATE : …..
Ref.

To
The General Manager/Contracts
M/s. NLC India Limited,
Neyveli - 607 801.
Cuddalore District, Tamil Nadu).

Dear Sirs,
1.0 In consideration of the NLC India Limited, Neyveli (hereinafter referred to as the
`Purchaser' which expression shall unless repugnant to the context or meaning thereof,
include its successors administrators, representatives and assignees),having awarded
to M/s................ with its Registered Office/Head Office at .........(hereinafter referred
to as the "CONTRACTOR", which expression shall, unless repugnant to the context
or meaning thereof, include its successors, administrators, executors, representatives
and assignees) a Contract/ Letter of Award herein after referred to as the
Contract/Letter of Award for `scope of work' on terms and conditions set out interlia in
the Purchaser's Letter of Award/Contract
No . . . . ......... dated . . . . . . ........... as well as contract document valued at
........................ . . . . ......at and the same having been unequivocally accepted by
the Contractor, and whereas the Purchaser under the terms contract has agreed to

199

Page 199 of 328


Sheet 2 of 3

make the payment of the final 10% value of the contract price of the..... Unit to the
Contractor amounting to........................ (in words) against Retention Money Bank
Guarantee to be furnished by the Contractor.
2.0 For this payment, we, the undersigned............. (Name) ............... (address) with Head
Office at ......... (address) (hereinafter referred to as the `Bank' which expression shall
unless repugnant to the context or meaning thereof include its successors,
administrators, executors, representatives and assignees)do hereby guarantee to the
effect that we irrevocably undertake to pay immediately upon the PURCHASER's first
demand without any previous notice and without any demur, reservations recourse,
contest or protest and/ or without referring to any other sources including the
Contractor, any and all monies, but not exceeding ................ (.....in words) at any
time upto....................... Any such demand made by the Purchaser on the Bank shall be
conclusive and binding notwithstanding any difference between the PURCHASER and
the CONTRACTOR or any dispute pending before any court, Tribunal, Arbitrator or any
other authority. We hereby agree that the Guarantee herein contained shall be irrevocable
and shall continue to be enforceable till the PURCHASER discharges this guarantee.

3.0 The Purchaser shall also have the right to encash the RMBG for the recovery of penalties
in terms of the contract.

4.0 The PURCHASER shall have the fullest liberty without affecting in any way the liability
of the Bank under this guarantee from time to time extend the time performance of the
contract by the CONTRACTOR. The Purchaser shall have full liberty without affecting
this guarantee to postpone from time to time the exercise of any powers vested in them
or of any right which they might have against the Contractor and to exercise the same at
any time in any manner, and either to enforce or to forbear to enforce any covenants
contained or implied in the contract between the Purchaser and the Contractor or any
other course or remedy or security available to the Purchaser. The Bank shall not be
released of its obligations under these presents by any exercise by the Purchaser or
its liberty with reference to matters aforesaid or any of them or by reason of any other
act or forbearance or other acts of omission or commission on the part of the Purchaser
or any other indulgence shown by the Purchaser or by any other matter or thing
whatsoever which under law would but for this provision have the effect of relieving the
Bank. The Bank shall not be released from its liability under these presents by an
exercise of the PURCHASER of the liability with reference to the matter aforesaid.

5.0 The Bank also agrees that the PURCHASER at his option shall be entitled to enforce
this guarantee against the Bank as a principal Debtor, in the first instance, without
proceeding against the Contractor and notwithstanding any other security or guarantee
that the Purchaser may have in relation to the Contractor's liabilities.

200

Page 200 of 328


Sheet 3 of 3

6.0 a. This guarantee will not be discharged due to the change in the constitution of the Bank
or the Contractor.

b. Notwithstanding anything contained herein above our liability under this guarantee
does not exceed ........ ......... .......... (in words)

c. This guarantee shall remain in force upto and including ...... ......and shall be
extended retaining the same terms and conditions from time to time for such periods
as may be desired by M/s ..........on whose behalf this guarantee has been given.

7.0 The Bank further undertakes not to revoke this guarantee during its currency without the
previous consent of the Purchaser in writing.

This guarantee deed must be returned to us upon the expiration of the guarantee.

8.0 Notwithstanding anything contained herein:

a. our liability under this bank guarantee shall not exceed ………… (in words)

b. this bank guarantee shall be valid upto ……………..; and

c. we are liable to pay the guaranteed amount or any part thereof under this bank
guarantee only and only if you serve upon us a written claim or demand on or
before ………………

Return of this document to us by any person before the aforesaid date will,
however, extinguish our liability as on the date of return.

Dated this ............ day of........... 20

WITNESS

1. Signature................. Signature.............
(Name in Block Letters)...... Printed Name..........
(Designation) Designation Staff Code No..........
Bank's Seal
2. Signature...................
(Name in Block Letters)........ (Designation)

201

Page 201 of 328


Appendix - C

FORMAT OF FINANCIAL BACK UP GUARANTEE

To be stamped in accordance with Indian Stamp Act.

Proforma for Bank Guarantee to be furnished by Associate / Collaborator/ Joint Venture


partner.

01. This guarantee should be furnished by a Nationalised Bank/ Scheduled Bank,


authorised by RBI except Bank of China to issue a Bank Guarantee excepting Bank of
China in the same format as given below.
02. The bank guarantee should be furnished on stamp paper of value not less than
Rs.80.00
03. The stamp papers should be purchased in the name of the Bank executing the
Guarantee.

Bank Guarantee No:


Dated
:
1.0 In consideration of NLC India Limited, hereinafter referred to as 'NLCIL' which
expression shall unless repugnant to the context or meaning thereof include its
successors, administrators, representatives and assignees, having awarded to M/s.
.................................................... (Bidder's Name) with its Registered Office at
........................... ................ hereinafter referred to as the Contractor a Contract for the
………………….vide its Letter of Award No ......................... dated ................and the
same having been unequivocally accepted by ................... (Bidder's Name) resulting
in a ‘Contract’ which was awarded on the strength of Deed of Collaboration
agreement/ Consortium agreement/Joint Venture Agreement dated ……. hereinafter
referred to as 'Undertaking' given by .....................(Bidder's Name) and by ..................
............. with its Registered Office at ................. .......... (hereinafter referred to as
Consortium partners /Collaborator/Joint Venture partner) which expression shall
unless repugnant to the context or meaning thereof include its successors,
administrators representatives and assignees) and CONTRACTOR having further
entered into with Consortium partner / Collaborator/J.V Partner a Contract
No....................... dated............. and the same having been unequivocally accepted
by Consortium partners / Collaborator/Joint Venture Partner resulting in a
Consortium Agreement/ Collaboration Agreement/Joint Venture agreement valued at
........ ......... for the scope of work between Contractor & Consortium partners
/Collaborator/Joint Venture Partner (hereinafter called Collaboration / Consortium
Agreement/Joint Venture Agreement)' and the Consortium partners/ Collaborator/Joint
Venture Partner having agreed to provide a financial back up guarantee amounting
to ......... ............. to NLCIL for the faithful performance of the contract on the terms
and conditions specified in the 'Undertaking' dated........

2.0 We,................ Bank........... ...... ....... (address) having its Head Office at .............
......... ......(hereinafter referred to as the 'Bank ' which expression shall, unless
repugnant to the context or meaning thereof, include its successors,
administrators, representatives and assignees) do hereby guarantee and undertake
to pay to NLCIL on on mere demand any and all monies to the extent of ...........
............. (currency and amount in figures) .......... ............ .......... ....... .......... as
aforesaid at any time upto ………….from the date of Letter of Award and till the
obligations under the Contract are completed without any demur, reservation, contest
202

Page 202 of 328


or recourse or protest and/or without any reference to Consortium partners /
Collaborator/Joint Venture Partner.

3.0 The Bank do hereby undertake not to revoke this guarantee during its currency without
previous written consent of NLCIL and further agrees that the guarantee herein
contained shall continue to remain enforceable till NLCIL discharges this guarantee.

4.0 Any such demand made by NLCIL on the bank shall be conclusive and binding
notwithstanding any difference between NLCIL and Consortium partners /
Collaborator/Joint Venture Partner pending before any Court, Tribunal, Arbitrator or
any other Authority.

5.0 NLCIL shall have the fullest liberty without affecting in any way the liability of the
Bank under this Guarantee from time to time to extend the time for performance of
the contract of the Collaboration / Consortium Agreement/Joint Venture Agreement
by CONTRACTOR and the Consortium partners / Collaborator/Joint Venture Partner.

6.0 NLCIL shall have the fullest liberty without affecting this guarantee to postpone
from time to time the exercise of any powers vested in them or of any right which
they might have against the CONTRACTOR and the Consortium partners /
Collaborator/Joint Venture Partner and to exercise the same at any time, in any
manner, and either to enforce or to forbear to enforce any covenants, contained or
implied in the said contract or undertaking or any other course or remedy or security
available to NLCIL.

7.0 The Bank shall not be released of its obligations/liabilities under these presents by any
exercise by NLCIL of its liberty with reference to the matters aforesaid or any of
them or by reason of any other acts or omissions or commissions on the part of
NLCIL or any other indulgence shown by NLCIL or by any other matter or thing
whatsoever which under law would, but for this provision, have the effect of
relieving the bank from its obligations. The Bank also agrees that NLCIL at its
option shall be entitled to enforce this Guarantee against the Bank as a Principal
Debtor in the first instance without proceeding against the CONTRACTOR or
Consortium partners / Collaborator/Joint Venture Partner and notwithstanding any
other security or guarantee that NLCIL may have in relation to CONTRACTOR/
Consortium partner’s /Collaborator's/Joint Venture Partner’s liabilities.

8.0 Notwithstanding anything contained herein above our liability under this Guarantee
is restricted to Rs.................... (Rupees) in words and it shall remain in force
upto and including........... .............and shall be extended from time to time for such
period as may be desired by Consortium partners / Collaborator/Joint Venture Partner
on whose behalf this guarantee has been given.

203

Page 203 of 328


9.0 This guarantee shall expire on.............. unless NLCIL`s claim under this
guarantee in accordance with the above mentioned conditions has reached us by the
end of the said date.

Notwithstanding anything contained herein:

a. our liability under this bank guarantee shall not exceed ………… (in words)
b. this bank guarantee shall be valid upto ……………..; and
c. we are liable to pay the guaranteed amount or any part thereof under this bank
guarantee only and only if you serve upon us a written claim or demand on or
before ………………

Dated this ............ day of........... 20..

WITNESS

1. Signature................. Signature.............
(Name in Block Letters)...... Printed Name..........
(Designation) Designation Staff Code No..........
Bank's Seal
2. Signature...................
(Name in Block Letters)........
(Designation)

204

Page 204 of 328


Appendix -D

FORMAT OF CONTRACT PERFORMANCE GUARANTEE


Note:-

1. This guarantee has to be furnished by a Nationalised Bank / Scheduled Bank


Authorised by RBI except Bank of China.
2. The Bank Guarantee should be furnished on Stamp paper of value not less than Rs.80/-
as per Stamp Act.
3. The stamp papers should be purchased in the name of Bank executing the guarantee.

Bank Guarantee No…………….


Date: …………………………...
To
The General Manager/Contracts
NLC India Limited,
Block-1, Neyveli- 607 801,
Cuddalore District, Tamil Nadu, INDIA.

Dear Sirs,

1.0 In consideration of the NLC India Limited, Neyveli hereinafter referred to as the
PURCHASER, which expression shall, unless repugnant to the context or meaning,
thereof include its successors, administrators, representatives and assignees, having
awarded in favour of M/s. ............. ........... ........... ...... ........ having registered office
at ................ hereinafter referred to as the CONTRACTOR, which expression shall
unless repugnant to the context or meaning thereof include its successors,
administrators, representatives and assignees, a Contract, hereinafter "referred as the
CONTRACT" for the ........................ on terms and conditions set out interalia, in the
PURCHASER`s Contract /Letter of Award No......................... dated as well as
"CONTRACT" documents, valued at ........... ............ ........... (In words) and the
same having been unequivocally accepted by the CONTRACTOR and the
CONTRACTOR having agreed to provide a Contract Performance Guarantee for the
faithful performance of the entire "Contract" including the warranty obligations
/liabilities under the contract Equivalent to 10% of the said value of the Contract plus
…..% of the computed price adjustment, if any, to the PURCHASER amounting
to....................................... (In words) as Contract Security in the form of a Bank
Guarantee.

2.0 We, ..............(Name)..................(Address) hereinafter referred to as the "Bank which


expression shall, unless repugnant to the context or meaning thereof, include its
successors, administrators, representatives and assignees do hereby irrevocably
guarantee and undertake to pay the PURCHASER merely on demand without any
previous notice and without any demur and without referring to any other source, any
and all monies payable by the CONTRACTOR by reason of any breach by the said
CONTRACTOR of any of the terms and conditions of the said CONTRACT
including non-execution of the "CONTRACT AGREEMENT" to the extent of 10% of
the Contract price plus ….. % of the computed price adjustment, if any and adherence
to Time Schedule stipulated at any time upto....... (day/month/year). Any such demand
made by the PURCHASER on the bank shall be conclusive and binding, absolute
and unequivocal not withstanding any disputes raised/pending before any court,
205

Page 205 of 328


tribunal, arbitrator or any other authority. The Bank agrees that the guarantee herein
contained shall continue to be enforceable till this sum due to the PURCHASER is fully
paid and claims satisfied or till the PURCHASER discharges this Guarantee.

3.0 The Bank further irrevocably guarantees and undertakes to pay on mere demand,
without any demur, reservation, contest, recourse or protest any and all monies due and
payable by the CONTRACTOR by reasons of non-fulfillment of any of the following
obligations.

3.1 For the successful and satisfactory operation of the equipment furnished and erected
under the said Contract as per the specifications and documents.

3.2 That the equipment installed under the said Contract shall be new and in accordance
with Contract Documents and be free from all defects in design, material
workmanship and performance including modifications, improvements and
replacements for a period of 12 calender months, from successful completion of take
over test/commissioning of the equipment and that immediately upon intimation
/written notice from the PURCHASER, the CONTRACTOR shall remedy free of
expenses to the PURCHASER such defects as noticed and developed under the normal
use of the said equipment, within the said guarantee period.

4.0 The PURCHASER shall have the fullest liberty without affecting in any way the
liability of the Bank under this guarantee, from time to time, to extend the time of
performance by the CONTRACTOR. The Bank shall not be released from its liabilities
under these presents by any exercise of the PURCHASER of the liberty with reference
to the matter aforesaid.

5.0 The PURCHASER shall have the fullest liberty, without affecting this guarantee to
postpone from time to time the exercise of any powers vested in them or of any right
which they might have against the CONTRACTOR and to exercise the same at any
time in any manner, and either to enforce or to forbear to enforce any covenants,
contained or implied in the CONTRACT between the PURCHASER and the
CONTRACTOR or any other course or remedy or security available to the
PURCHASER and the BANK shall not be released of its obligations/ liabilities under
these presents by any exercise by the PURCHASER of his liberty with reference to
the matters aforesaid or any of them or by reasons of any other act or forbearance or
other acts of omission or commission on part of the PURCHASER or any other
indulgence shown by the PURCHASER or by any other matter or thing whatsoever
which under law would, but for this provision, have the effect of relieving the Bank
Guarantee. The Bank further undertakes not to revoke this guarantee during its currency
without the previous consent of the PURCHASER.

6.0 The Purchaser shall have the fullest liberty to lodge their claims for encasements of the
guaranteed sum in full or in part, in the manner suitable to them. However, payment
made for a sum lesser than the guaranteed amount, shall not relieve or discharge the
Bank from their obligations guaranteed hereunder, till the contractual obligation are
fully performed by the Contractor or the Bank Guarantee is discharged by the
Purchaser, as the case may be and the Bank Guarantee shall continue to be in force till
such time.

6.1 The Bank further agrees that the decision of the PURCHASER as to the failure on the
part of the CONTRACTOR to fulfill their obligations as aforesaid and/or as to the

206

Page 206 of 328


amount payable by the BANK to the PURCHASER hereunder shall be final, conclusive
and binding on the BANK.

7.0 The Bank also agrees that the PURCHASER shall be entitled at his option to enforce
this guarantee against the BANK as a principal debtor, in the first instance
notwithstanding any other Security or guarantee that it may have in relation to the
CONTRACTOR`s liabilities.

8.0 This guarantee will not be discharged due to the change in the constitution of the
BANK or the CONTRACTOR(S).

9.0 Notwithstanding anything contained herein:

a. our liability under this bank guarantee shall not exceed ………… (in words)

b. this bank guarantee shall be valid upto ……………..; and

c. we are liable to pay the guaranteed amount or any part thereof under this bank
guarantee only and only if you serve upon us a written claim or demand on or
before ………………

Witness SIGNATURE

1
Signature Name in Block Letters
Name in Block Letters
Designation
Occupation
Staff Code No.
Address

2
Signature
Name in Block Letters (Banker’s seal)
Occupation Attorney as per Power of
Address Attorney No…………dt.……………..

207

Page 207 of 328


Appendix -E

FORMAT OF CUSTODY CUM INDEMNITY BOND TO BE EXECUTED BY THE


CONTRACTOR FOR THE EQUIPMENT HANDED OVER AND TO BE HANDED
OVER IN INSTALMENT BY----------------------------------------- FOR PERFORMANCE
OF ITS CONTRACT.

(On non-judicial stamp paper of appropriate value)

CUSTODY CUM INDEMNITY BOND

This CUSTODY CUM INDEMNITY BOND is made this ..……......day of ……20…… a


Company registered under the Companies Act, 1956/Partnership firm/ proprietary concern
having its registered office at ……………………………………..(Hereinafter called as
“Contractor” or “obligor” which expression shall include its successors and permitted
assigns) in favour of NLC India Limited,, a company incorporated under the companies act,
1956 having at its registered office at Chennai

WHEREAS NLC India Limited, has awarded to the contractor a contract for
………………………………vide its Letter of Award/Contract No………………………….
date………………… .and its Amendment No.1 and Amendment No.2 (Applicable when
amendments have been issued ) (hereinafter called the “Contract”) in terms of which NLC
INDIA Limited, is required to hand over various equipment to the contractor for execution of
the contract.

AND WHEREAS by virtue of clause No…………………………………. of the said


Contract, the contractor is required to execute the Custody cum Indemnity Bond in favour of
Neyveli Lignite corporation for the Equipment to be handed over to it by NLC India
Limited, for the purpose of performance of the contract/ erection Portion of the contract
(hereinafter called “Equipment” ).

NOW, THEREFORE, this Custody cum Indemnity Bond witnessth as follows:

1. That in consideration of various Equipment as mentioned in the contract, valued at


Rs…………………….(Rupees …………….) to be handed over to the Contractor in
instalments from time to time for the purpose of performance of the contract, the
contractor hereby undertakes to indemnify and shall keep NLC INDIA Limited,
indemnified, for the full value of the Equipment. The contractor hereby acknowledges
receipt of the initial installment of the Equipment as per details in the schedule appended
hereto. Further, the contractor agrees to acknowledge receipt of the subsequent
instalments of the Equipment as required by NLC India Limited, in the form of
schedules consecutively numbered which shall be attached to this custody cum
Indemnity Bond so as to form integral part of this Bond. It is expressly understood by
the contractor that handing over the despatch title document in respect of the said
equipment duly endorsed by NLC India Limited, infavour of the contractor shall be
construed as handing over of the equipment purported to be covered by such title
documents and the contractor shall hold such equipment in trust as a Trustee for and on
behalf of NLC India Limited,

That the contractor is obliged and shall remain absolutely responsible for the safe transit/
protection and custody of the Equipment at NLC India Limited, project site against all
risks whatsoever till the Equipment are duly used/ erected in accordance with the terms
208
Page 208 of 328
of the contract and the plant/ package duly erected and commissioned in accordance with
the terms of the contract is taken over by NLC India Limited, The contractor undertakes
to keep NLC India Limited harmless against any loss or damage that may be caused to
the Equipment.

1. The contractor undertakes that the Equipment shall be used exclusively for the
performance /execution of the contract strictly in accordance with its terms and
conditions and no part of the Equipment shall be utilized for any other work or
purpose whatsoever. It is clearly understood by the contractor that non-observance of
the obligations under this, custody cum indemnity bond by the contractor shall
interalia constitute a criminal, breach of trust on the part of the contractor for all
intents and purposes including legal/ penal consequences.

2. That NLC India Limited is and shall remain the exclusive, owner of the Equipment
free from all encumbrances, charges or liens of any kind, whatsoever. The Equipment
shall at all times be open to inspection and checking by Engineer-in-charge/Engineer
or other employees / agents authorised by him in this regard. Further, NLCIL India
Limited shall always be free at all times to take possession of the Equipment in
whatever form the Equipment may be, if in its opinion, the Equipment are likely to be
endangered, misuitilised or converted to uses other than those specified in the
contract, by any acts of omission or commission on the part of the contractor or any
other person or on account of any reason whatsoever and the contractor binds itself
and undertakes to comply with the directions or demand of NLCIL to return the
equipment without any demur or reservation.

3. That this custody cum Indemnity Bond is irrevocable. If at any time any loss or
damage occurs to the Equipment or the same or any part thereof is misutilised in any
manner whatsoever then the contractor hereby agrees that the decision of the
Engineer-in-charge/ Engineer of NLCIL as to assessment of loss or damage to the
equipment shall be final and binding on the contractor. The contractor binds itself
and undertakes to replace the lost and/ or damaged Equipment at its own cost and/ or
shall pay the amount of Loss to NLCIL without any demur, reservation or protest.
This is without prejudice to any other right or remedy that may be available to NLCIL
against the contractor under the contract and under this custody cum Indemnity Bond.

4. NOW THE CONDITION of this bond is that if the contractor shall duly and
punctually comply with the terms and condition of this bond to the satisfaction of
NLCIL THEN, the above shall be void, but otherwise it shall remain in full force and
virtue.

5. IN WITNESS, WHEREOF, the contractor has hereunto set its authorised


representative under the common seal of the company, the day, the month and year
first above mentioned.

209
Page 209 of 328
Schedule No.1

Particulars of Qty. Particulars of Despatch Title Value of the signature


The Equipment documents equipment of Attorney in
Handed over RR/GR No. carrier Date, Bill token of
of lading receipt.

(please Number Subsequent Schedule)

For and on behalf on


M/S …………………….
Name …………………………..
Signature…………………………..
Designation…………………………..
Authorised Representative *
(Common seal)
(In case of company)
WITNESS

I Signature ……………………………….
Name………………………………….
Address……………………………..

II Signature……………………………
Name…………………………….
Address……………………………
Indemnity Bonds are to be executed by the authorised persons and (i) in case of contracting
company under common seal of the company or (ii) having the power of attorney issued
under common seal of the company with authority to execute Indemnity Bonds, (iii) in case
(ii), the original power of Attorney if it is specifically for this contract or a Photostat copy of
the power of Attorney if it is General power of Attorney and such documents should be
attached to Indemnity Bond.

210
Page 210 of 328
Appendix - F

DEED OF JOINT UNDERTAKING BY THE CONSORTIUM PARTNERS

This Deed of undertaking executed this .................... ....... day of ............ ........... ........
by ...................... .............. a Company incorporated under ............................ and having
its Registered Office at ...................... .............. ................ herein after called ......................
................ or Consortium partners which expression shall include its successors, executors
and permitted assigns and (Bidder's Name) .................................... a Company
incorporated under the Companies Act 1956 having its registered office at
................... .......... ................. hereinafter called ........... ...................... (Bidder's Name) or
'CONTRACTOR' which expression shall include its successors, executors and permitted
assigns) in favour of NLC India Limited, a company incorporated under the Companies
Act 1956 having its Registered Office at Chennai-600 010 (hereinafter called the
'PURCHASER'), which expression shall include its successors, executors and assigns.

WHEREAS the PURCHASER is desirous of getting work of the design, manufacture,


supply, transport and insurance, Port handling, Customs clearance, forwarding, storage,
erection, testing and commissioning of ............................. (herein after called as system) at
....... done as per its specification No ...................... dated .................... WHEREAS
................................ (Bidder's Name) submitted its technical proposal vide its Letter No.
........................ dated ...... ........ based on the association of M/s ..................................
(Consortium partners) AND WHEREAS it is a condition for the award of contract to
...................... (Bidder's Name) that ............................... (Bidder's Name) and its Consortium
partners M/s ......................... ........ would be jointly and severally bound and shall be
responsible to the PURCHASER for the successful performance of the system fully
meeting the parameters guaranteed as per the PURCHASER's specifications in terms of
the Contract. NOW, THEREFORE, THIS UNDERTAKING witnesseth as under:

1. That consideration of the award of Contract by the PURCHASER (herein after


referred to as the 'Contract') we, the Consortium partners and CONTRACTOR do
hereby declare and guarantee that we shall be jointly and severally bound unto to
the NLC India Limited, (PURCHASER) for the successful performance of the
system fully meeting the guaranteed parameters as per the contract and further
shall be fully responsible for the correctness of design, manufacture, supply,
transport, insurance, erection supervision, testing and commissioning of the system
in accordance with the Contract specifications. Further, we, the Consortium partners
and the CONTRACTOR hold ourselves jointly responsible for the timely execution of
all activities in accordance with the contract.

2. Without prejudice to the generality of the undertaking in para -1 above, the methods
of achieving the objectives setforth above shall be as follows:

a. The Consortium partners shall be responsible for the preparation of all


design, design calculation and manufacturing drawings for the system and
shall provide all additional necessary technical assistance to ...................
(Bidder's Name) for the portion of the work to be performed by
.................................. (Bidder's Name) in India. Further the Consortium partners
shall extend their quality surveillance to ................................ (Bidder's Name)
during manufacture at CONTRACTOR's work and/or at the PURCHASER's
project site. Without prejudice to the overall responsibility of the Consortium
partners as to the successful commissioning and performance of the system,
211
Page 211 of 328
the Consortium partners shall in addition despite his technical experts from time
to time to the CONTRACTOR's works/ PURCHASER and the
CONTRACTOR in accordance with the stipulation in the Contract.

b. The Consortium partners will be fully responsible for the quality of manufacture
and the timely delivery of all the major components of system manufactured at
his works or at his CONTRACTOR's work for incorporation in the equipment as
per the Contract Schedule.

c. The CONTRACTOR shall be responsible to manufacture that portion of the


equipment to be manufactured at his works or at the sub-Contractor’s works as
per the Consortium partners design and the Consortium partner’s quality
acceptance level. Further the CONTRACTOR shall supervise the erection,
commissioning of the system as per the contract in accordance with the Consortium
partner's advice, procedure and guidance.

3. In the event of any breach in the performance of the obligations setforth above, we
the collaborator and the CONTRACTOR, shall jointly and severally pay the loss
or damage to the PURCHASER on his demand. Further we the Consortium
partners and the CONTRACTOR, jointly and severally undertake to pay to
the PURCHASER the liquidated damages arrived at in accordance with the
provisions of the Contract, in the event of any delay in supply or in completion of
functional test including commissioning of the system without any demur,
reservations, protest and recourse. Further, any extension of time, relaxation or
indulgence by the PURCHASER to the CONTRACTOR/ Consortium partners
shall not prejudice the rights of the PURCHASER under this undertaking against the
Consortium partners of the CONTRACTOR.

4. We, the Consortium partners and the CONTRACTOR agree that this undertaking
shall be irrevocable and further agree that this undertaking shall continue to be
enforceable till the end of warranty period under the Contract. We further agree that
this undertaking shall without prejudice to the various liabilities of the
CONTRACTOR including his Contract Performance Guarantee as well as his other
obligations in terms of the Contract.

5. The Performance, rights and responsibility of the party shall be in accordance with the
Contract and further the liability of the CONTRACTOR/ Consortium partners under
this Undertaking shall not in any case exceed the limits as stipulated in the Contract.

6. As a security, the Collaborator, apart from the CONTRACTOR's Performance


Guarantee, shall furnish a Performance Guarantee from his Bank, in the form
acceptable to the PURCHASER, in favour of the PURCHASER, prior to signing of
the Contract. The value of the Guarantee shall be 5% 0.05%value of the supplies
/services to be made by the Consortium partners and it shall be guaranteed towards
the faithful performance/compliance of this Deed of Undertaking in accordance with
the terms and conditions specified herein. The Guarantee shall be irrevocable and
valid for the entire period of the contract, namely till end of the warranty period of the

212
Page 212 of 328
Contract or after three months. The guarantee amount shall be payable to the
PURCHASER on demand without any condition whatsoever.

IN WITNESS WHEREOF the Consortium partners and the CONTRACTOR have


through their authorised representatives executed this Undertaking and affixed
common seals of their respective companies, on the day, month and year first
above mentioned.

………………………………. For Consortium partners


(Signature) Name
Designation :
……………………………………….
(Name in Block Letters) Common seal of the company.

……………………………………….
(Official address)

……………………………….. For CONTRACTOR.


(Signature)
Name :
…….………………………………. Designation :
(Name in Block Letters)
Common seal of the
…………………………………………. Company.

(Official address)

213
Page 213 of 328
NLC INDIA LIMITED
(FORMERLY NEYVELI LIGNITE CORPORATION LIMITED)
(A“Navratna” -Government of India Enterprise)
Block – 1, NEYVELI – 607 801, Cuddalore Dist. Tamil Nadu, INDIA.

OFFICE OF THE CHIEF GENERAL MANAGER / CONTRACTS


CORPORATE OFFICE

Volume-2 of 2
TECHNICAL SPECIFICATION
FOR
Installation of 2 x 10 MW (AC) Grid interactive Solar PV Power Project integrated with
8 MWhr. Battery Energy Storage System at Andaman includes Operation and
Maintenance of the entire system for ten years after one year warranty period

INTERNATIONAL COMPETITIVE BIDDING


Through e-Tender and e-Reverse auction
Tender No. CO CONTS/ 0006G / PV Solar - BESS /ICB/Andaman/e-conts/ 2018, dt.24.02.2018
Pre bid conference : 14.03.2018 at 11.00 Hrs.
Last Date & Time for submission of Bid : 27.03.2018 at 14.30 Hrs.
Date & Time of Opening (Cover-I& II) : 27.03.2018 at 15.00 Hrs. (IST)

Phone No:04142/252210,251620 Fax No.04142-252026/252645/252646


Web site: WWW.nlcindia.com Email:gmconts_co@nlcindia.com

Registered Office: First Floor, No.8,Mayor Sathyamurthy Road,


FSD, Egmore Complex,Chetpet, Chennai-600 031.

Page 214 of 328


VOLUME 2 of 2

TECHNICAL SPECIFICATION

TABLE OF CONTENTS

S.No. DESCRIPTION PAGE

NO

1 Project Information 2

2.1 Design Basis 5

2.2 Solar PV Modules, Array yard and DC Systems 8

2.3 Electrical Power Collection & Export system 16

2.3.1 Power Collection Sub Station 16

2.3.2 Power Export Switchyard 40

2.3.3 SCADA and Energy Management System 65

2.4 Civil works and Structural Steel works 73

2.5 Battery Energy Storage System 83

2.6 Testing, Commissioning, Provisional Takeover and PG test 85

2.7 Quality Assurance, Inspection & Testing 90

2.8 Sub Vendors & Sub Contractors 91

2.9 Operation & Maintenance 94

Annexure-1 Guaranteed Month-Wise Net Energy Export at metering Stations of 98


33 KV Switchyard out going feeders
Annexure-2 Computation of Short fall in Net Energy Export (For PG Test Period) 105

Annexure-3 Computation of Net Energy Export During O & M Period 107

Drawings Drg. No. NLCIL/PBD/Andaman/01: General Block Diagram 109


Drg. No. NLCIL/PBD/Andaman/02: Attam Pahad Site map 110
Drg. No. NLCIL/PBD/Andaman/03: Dolly Gunj Site map 111

Page 215 of 328


SECTION 1.0
PROJECT INFORMATION

1.1 Project Site:


The project site for the installation of 2x10 MW (AC) Grid Interactive Solar PV
power plant integrated with Battery Energy Storage System (BESS) is situated in
Attam Pahad and at Dolly Gunj, Port Blair, South Andaman. General information of
the project site is as follows:
1. Project site area:
a. Attam Pahad Project site:
Refer Tender Drawing Number: NLCIL/PBD/Andaman/02
Sl No Area/village Survey No Area in Hectares
Garacharma (village) 1/1/2/2 12.3042
1 Port Blair (Tehsil) 1/1/6 4.4345
South Andaman (District) 1/502 4.5693
Total 21.3080 Hectares

b. Dolly Gunj Project Site:


Refer Tender Drawing Number: NLCIL/PBD/Andaman/03
Sl No Area/Village Survey No Area in Hectares
200/1/P 4.0946
200/1/P 0.1050
Dolly Gunj (Village) 200/1/P 0.3276
1 Port Blair (Tehsil) 200/1/P 1.1525
South Andaman (District) 200/1/P 0.2580
200/3/P 0.8103
393/2/P 1.9762
393/2/P 3.9400
Garacharma (Village) 393/2/P 0.7000
2 Port Blair (Tehsil) 393/2/P 0.6775
South Andaman (District) 393/1/P 0.3327
393/1/P 5.0330
393/1/P 0.0446
3 Pahargaon (Village)
Port Blair (Tehsil) 160/1/P 0.8000
South Andaman (District)
Total 20.2520 Hectares

2. Site Elevation: Varies from approximately 3 Meters to 30 Meters


3. Land Topography: Undulated ground and slopped terrain.
4. High tide level: 2 Meters
5. Low tide level: 0 Meters
6. Access road: 250 Meters away from Andaman Trunk Road (ATR- NH 4).
7. Nearest Airport: The distance from Veer Savarkar International Airport, Port Blair
to Attam Pahad/Dolly Gunj is 4.1 KMS.
8. Nearest Seaport: Port Blair is the main Harbour to receive all mainland vessels
9. Latitude of Attam Pahad site: 11.620N

Page 216 of 328


Longitude of Attam Pahad site: 92.70E
Latitude of Dolly Gunj site: 11.6279010N
Longitude of Dolly Gunj site: 92.711303 0E
10. Climate:
Monthly Average Maximum Temperature-29.890C
Monthly Average Minimum Temperature-22.420C
Relative Humidity: 90% (Maximum)
Relative Humidity: 70% (Minimum)
Average Annual rainfall: 254.75 cms
Basic Wind speed: 5.3 m/s
Seismic zone: V
1.2 Solar Insolation:
The estimated monthly average solar insolation on horizontal plane is as given
below, the bidder has to adopt these solar insolation data for guaranteed net energy
export calculations including other calculations.
Month Jan Feb Mar Apr May Jun
GHI (kWhr/m2/Day) 5.65 6.47 6.83 6.65 5.08 4.38
Month Jul Aug Sep Oct Nov Dec
GHI (kWhr/m2/Day) 4.45 4.45 4.64 4.99 4.86 5.19

1.3 Power Evacuation: (Refer Tender Drawing No: NLCIL/PBD/Andaman/01)


1. 33/11 KV Garacharma Substation is the nearest Grid Substation available.
2. 33 KV Tie Panther-I and Panther-II feeders are passing at a distance of 1KM
from the location at 33 KV Tower Spans and interconnecting Garacharma
Substation and Bambooflat substation.
3. As Per Site conditions 33 KV Transmission line and 33 KV UG cables shall be
installed by the contractor for Power Evacuation, by interlinking the Panther I &
II feeders with the 33 KV Power Export Switchyard of the project. Refer tender
drawing No: NLCIL/PBD/Andaman/01.

1.4 Site Inspection:


For detailed and more accurate information and for authenticated data, the bidder shall
collect and confirm data from authorised and authenticated sources.
The bidder is advised to visit and examine the sites of the project and its surroundings
and obtain for himself, on his own responsibility, all information that may be
necessary for preparing the bid and entering into contract (s). The bidder shall assess
and satisfy himself as to the adequacy of the local conditions such as approach roads
to the site, adequacy of existing culverts/bridges/roads/ports, harbour for the expected
traffic, water and power supply, nature of ground and sub soil condition, water table
level, accommodations required during the contract, climatic conditions, local terrain,
availability of labour, construction materials, details of taxes and levies as applicable
and may other information required. The cost of visiting the site shall be at the
bidder’s own expenses. Claims and objections due to ignorance of site conditions will
not be considered after submission of Bid.

Page 217 of 328


1.5 The site is under possession of the NLCIL and is deemed to be handed over to the
Contractor as is where basis from the date of issue of LOA . Widening of the approach
roads, strengthening of the sluice gate culvert across the back waters (if required),
strengthening of slopes by construction of retaining walls where ever required,
removal/shifting of permanent structures (over ground and underground) etc. as
required for project installation shall be in the scope of the contractor.

1.6 Mode of Execution:


The entire work shall be executed on Lump sum, turnkey, firm price basis. Any minor
item(s) not included in the schedule but required for completion of the work shall have
to be carried out/supplied without any extra cost. Such works, not listed in the schedule
of works but elaborately described to perform or to facilitate particular operation(s)
required for completion of the project shall be deemed to have been included in the
scope of this work and the contractor shall supply, install the same without any extra
cost to NLCIL.

Page 218 of 328


SECTION 2.1

2.1.1 DESIGN BASIS


The contractor shall submit detailed design report for NLCIL approval for the
2X10MW (AC) Grid interactive Solar PV project integrated with installed capacity
of 8MWhr with ½ hr backup Battery Energy Storage System. The entire design
shall be done taking into consideration of the long term, lump-sum, turnkey, firm
price basis EPC contract, uniqueness of the project, solar power generation
integrated with large size battery energy storage for power application so that
smoothened power can be injected into the 33 KV Grid, connected with the grid
which is mostly powered with DG sets / LNG based power generation. The entire
design shall be made taken into consideration of project site which is strategically
important, environmentally sensitive, remote and island location with challenges of
natural disasters, with limited resources etc. The present load demand in the existing
33KV South Andaman Grid is approximately 40 MW-peak load in the evening hours
and around 26 MW-average load in other times.

2.1.1.1 The 2x10MW (AC) of Grid interactive solar PV power project integrated with
installed capacity of 8 MWhr with ½ hr backup battery energy storage system shall
be designed in such a way that for minimum 11 years ( including 1st year PG period )
the entire system is capable of injecting the smooth power from the solar PV into the
grid and guaranteed net energy export to the existing 33 KV South Andaman Grid as
per requirements stipulated in the relevant clauses of this specification. The general
guiding principles for design basis shall be as follows:
 The month wise average solar Insolation values for the project site (Attampahad,
ANI) shall be based on considering the long term published data from NASA,
available for the location.
 The established efficiency of solar PV modules at different operating conditions
shall be as per international standards and as per the standards of the
manufacturer in India for the supply of solar cells / modules proposed for this
project.
 The design and selection of solar PV module, panel, array configuration, series
and parallel connections, orientation, inverter designs, transformer selection,
power export scheme etc., shall be such as to ensure maximum electric power
generation and minimum loss to the generated power results.
 The Contractor should carry out Shadow Analysis at the site along with the
topographic survey for designing strings & arrays layout for optimal usage of
space, material and labour. The Contractor shall submit Shadow Analysis Report
along with the array layout drawings to NLCIL for review and approval. The
Project site location is surrounded with back water from sea. To protect the

Page 219 of 328


structures from corrosion, apart from painting the structures, cathodic protection
shall also be envisaged if required.
 BESS scheme integrated directly with 33 KV system with point of common
connection shall be envisaged. The maximum MW that shall be discharged from
BESS to the 33 KV Grid during Solar hours shall be limited to 16 MW.
However the BESS shall be designed to meet the system requirements and to
meet the Annual Guaranteed Net Energy Export.
 Provision for seasonal tilt /fixed tilt/ tracking of solar modules and associated
auxiliary power feeding arrangements shall be designed to achieve the
guaranteed net energy export for the entire period of the contract.
 The design of entire system including PV array layout, general arrangement of
equipments, location of BESS equipments and Power Export switchyard,
location of Project Control Room etc. shall be such that the allotted project site
area shall not exceed in Attam Pahad site and Dolly Gunj site and as per the
contractors design approved by NLCIL. If any area is not utilized, the same
shall be handed over back to NLCIL.
 The design of the system shall aim for a fully automated power plant requiring
minimum operator intervention, with daily automatic startup and shutdowns,
optimized power generation features, grid monitored safety functions,
integration of Energy Management System with A & N Grid Energy
Management Centre, HMI interfaces, User friendly operation, ,solar forecasting,
solar smoothing, data management and remote function capabilities.
 Workmanship and finish shall be in accordance with the best and latest
engineering practices. All materials used for the manufacture of equipment by
the Contractor or his sub-suppliers or his sub-vendors and the workmanship
shall be of good quality and acceptable, as per Indian Standards or other
approved standards etc.
 Methods may be adopted for maximizing the quantum of power exported
especially during Solar Hours . The distribution losses shall be kept to the bare
minimum, by adopting high efficiency design for power transformers with
minimum core and copper losses, with liberal use of active materials namely
core and copper. The design shall also feature, use of such techniques and other
methods to minimize stray losses, reduce harmonics, cater required reactive
power loads, withstand all types of fault conditions etc.
 The Contractor shall submit the calculations of the Performance Ratio (PR) of
the Solar PV Power Plant for NLCIL approval. It may be noted that the PR
value will not be considered for the PG evaluation. With inputs received from
various input devices in the field, the PR shall be dynamically calculated and
displayed. Suitable software shall be incorporated in the SCADA for this
purpose.

Page 220 of 328


2.1.1.2 The DC power generated in the photo voltaic arrays will be fed through Array
junction box / combiner box and String monitoring unit and then fed to central
inverter in Power Collection Substation (PCSS). In case of string inverters/micro
inverters the DC Power generated shall be fed directly to the inverters. The inverter
to module ratio shall be minimum 1: 1.10. The rating of the inverter is chosen to
have minimum line loss on DC side for a typical array layout and optimum power
rating.
2.1.1.3 The inverters transform the DC power to 3 phase AC, 50Hz of suitable voltage. AC
power from the inverter output side shall be taken to power transformers. The power
transformers shall be located near the PCSS. The high voltage side of the
transformers shall be connected to the HV switchgear. The selection of the type of
PCSS shall be either indoor or outdoor or a combination with container unit, which
shall be finalised during detailed engineering to match the system requirements.
2.1.1.4 In the project control room Energy Management System, breaker, distribution board,
control and relay panels, metering panel, SCADA, DC and AC auxiliary control
power equipment, communication system; fire alarm panel, etc. shall be installed
suitably to meet the system requirements.
BESS design basis and specifications shall be as per section 2.5.
2.1.1.5 The following power system parameters for LT system and HT system shall be as
per the requirements of Electricity Department, Andaman & Nicobar Administration
and to meet the overall system requirements.
 Nominal system voltage
 Highest system voltage
 System frequency
 System Earthing
 Fault level (3 phase symmetrical)
 Short time current rating (For all current carrying parts)
 Power frequency withstand voltage
 Impulse withstand voltage
 Other Power System parameters

2.1.1.6 The Contractor shall design the entire system to meet the requirements of safety and
statutory regulations of the Andaman & Nicobar Administration authorities. If any
modifications are required to meet the Andaman & Nicobar Administration
regulations/requirements, the contractor shall carry out the same without any extra
cost to NLCIL.
2.1.1.7 The equipments and systems shall be designed, manufactured, assembled, tested,
shipped, installed and commissioned according to the applicable codes, standards
and regulations. The design and installation shall be fully in conformity with the
standards and codes as applicable but not limited to the following.
ANSI : American National Standard Institute
ASME : American Standard of Mechanical Engineers
AWS : American Welding Society
ASTM : American Standards for Testing Material
ISO : International Organization for Standardization
ASA : American Standard Association
DIN : Deutsche Industrie Normen
EN : European Standards

Page 221 of 328


BS : British Standards
BIS : Bureau of Indian Standards
IEC : International Electro-technical Commission
IEEE : Institute of Electrical and Electronics Engineers
ISA : Instrument Society of America
SI : International System of Units
2.1.1.8 Latest International / National codes and standards shall be followed for the design
of the entire system. It is the contractor’s responsibility to ensure the coherence of
the codes and standards chosen as reference.

SECTION 2.2
SOLAR PV MODULES, ARRAY YARD AND DC SYSTEMS

2.2.1 SOLAR PV CELLS AND MODULES


2.2.1.1 The bidder should adopt only Mono or Poly Silicon Crystalline type flat plate Solar
PV Module as detailed in this specification.

2.2.1.2 Solar PV Cells offered for this project shall be tested as per testing standards for its
characteristics, surface condition, surface profiling, thickness shape, flatness
measurements, etc. The modules using the solar cells described above shall conform
to latest IEC 61215 in all respects. The contractor shall furnish latest IEC 61215 Test
reports along with constructional data form for the offered PV modules to be
supplied during detailed engineering. The IEC 61215 test certificates and test reports
consisting of list of the Makes & Description of the each component including Solar
PV Cells used in the manufacture of Solar PV modules shall be furnished during
detailed engineering. The solar PV modules of same type and rating (above 240 Wp
rating) will be maintained at each string level. The exact type and rating of solar PV
modules at the respective inverter level will be finalised during detailed engineering.
The Contractor shall submitt IEC 61730 certificate and test reports (for safety
qualification testing) for the offered PV modules. In addition, the bidder shall also
furnish IEC 61701 certificate and test reports (for corrosion testing) for the offered
PV modules during detailed engineering. The Project site location is surrounded
with back water from sea. Any additional protective care in the manufacture of
modules shall be taken to ensure design life of 25 years.

2.2.1.3 All materials used in the Solar PV module shall have a proven history of reliability
and stable operation in external applications. It shall perform satisfactorily in high
relative humidity with atmospheric temperatures prevailing at the site and should
have lowest temperature coefficient and shall withstand gust prevailing at site on the
surface of the panel. Each and every SPV module shall be checked for conformity
with relevant standard. Modules shall not have negative tolerance and the same shall
be incorporated in manufacturing and inscribed in the name plate rating.

Page 222 of 328


2.2.1.4 The bidder shall provide the data sheet of technical specifications for the offered PV
modules. The bidder shall furnish electrical characteristics such as current-voltage (I-
V) performance curves and temperature coefficients of power, voltage and current
during detailed engineering.

2.2.1.5 PV modules after manufacture must be tested for random sample and approved by
one of the NABL accredited Test Centres in India/International Laboratory
Accreditation Cooperation (ILAC) Member Labs in abroad. Manufacturing Quality
Plan for PV modules shall be submitted for approval by NLCIL. Random sample
testing by NLCIL during manufacture of PV Modules shall be included in the MQP.

2.2.1.6 Solar PV Peak power rating of the module shall not be less than 240Wp. The module
conversion efficiency shall be minimum 15% and above under standard test
conditions. The cell should have minimum fill factor of 0.7. It shall be made of high
transitivity glass and front surface shall give high encapsulation gain.

2.2.1.7 The front surface of the module shall consist of impact resistant, low iron and high
transmission, toughened, plain/patterned glass.

2.2.1.8 The interconnected cells shall be laminated in vacuum to withstand adverse


environmental conditions.

2.2.1.9 The module frame shall be made of corrosion resistance materials, preferably having
aluminium anodized finish.

2.2.1.10 Minimum clearance between the lower edge of the modules and the developed
ground level shall be finalised during detailed engineering.

2.2.1.11 Bidder shall carefully design complete layout and arrangement of equipments in the
land available and requisite number of modules shall be installed to achieve the rated
power generation and guaranteed net energy export. The inter row distance between
solar PV arrays shall be sufficient for easy movement of men / materials for panel
cleaning, maintenance works, etc.

2.2.1.12 Solar PV Modules Material Warranty


Material Warranty is defined as: The manufacturer should warrant the Solar PV and
Modules to be free from the defects and/or failures specified below:
 Defects and/or failures due to manufacturing
 Defects and/or failures due to materials
 Non-conformity to specifications due to faulty manufacturing
and/or inspection processes.

If the solar PV Modules fail to conform to this warranty, the manufacturer will repair
or replace the solar modules as per contract terms.

Page 223 of 328


2.2.1.13 PV modules used in Grid Interactive Solar PV power plant integrated with Battery
Energy Storage System must be guaranteed for output wattage, which should not be
less than 90% at the end of 10 years and 80% at the end of 25 years.

2.2.1.14 Identification and Traceability


Each PV module used in solar power project must use an RF identification (RFID)
tag. The following information must be mentioned in the RFID used on each
module.
 Name of the manufacturer of Solar cells
 Name of the manufacturer of PV Module
 Month and year of the manufacture (separately for solar cells and
modules)
 Country of origin (separately for solar cells and module)
 I-V curve for the module
 Wattage, Im, Vm and FF for the module
 Unique Serial No. and Model No of the module
 Date and year of obtaining IEC PV module qualification
certificate
 Name of the test lab issuing IEC certificate
 Other relevant information on traceability of solar cells and
module as per ISO 9000.
The RFID label shall be placed either inside or outside the laminate.

2.2.1.15 Modules shall be provided with a Module junction box of minimum IP 65 rated
high quality enclosure with provision for external terminal connection and
adequate capacity by-pass diodes. The Module junction box should have
weatherproof lid, cable gland entry points and connecting copper cable with
MC4 type/equivalent/compatible connector.

2.2.2 ARRAY JUNCTION BOX / COMBINER BOX AND STRING MONITORING


UNIT
2.2.2.1 Array junction box and Combiner box shall be provided on the DC power side to
combine the electrical power from the strings. String Monitoring Units (SMU) shall
be provided for monitoring the DC power generation and other parameters at two
string level. In case of String Inverters, the string level monitoring of the inverters
shall be of 0.5 % high accuracy monitoring. If string inverters are made acceptable
PCSS of container type may be used to accommodate other PCSS equipment.The
Array junction box /Combiner box and String Monitoring unit shall be either
integrated into a single box enclosure as intelligent array junction /combiner box or
with individual box enclosures. However Array junction box /Combiner box and
String Monitoring unit shall be standalone units erected nearer to the module
mounting structures at an optimized distance to reduce the DC losses and shall be

10

Page 224 of 328


either integrated box enclosures or individual box enclosures. The box enclosure for
Array junction box/ Combiner box and String Monitoring Unit shall be dust, vermin
and water proof, impact resistant and made of polycarbonate/ERP/metallic
enclosures which should be sunlight/ UV resistive as well as fire retardant. The box
must have minimum protection to IP 65 degree of enclosure and Protection Class
II.The terminals inside the Array junction box/ Combiner box and String Monitoring
Unit shall be connected to copper bus-bar arrangement of proper sizes. The Array
junction box/ Combiner box and String Monitoring Unit shall have suitable cable
entry points fitted with cable glands of appropriate sizes for both incoming and
outgoing cables. Suitable markings shall be provided on the bus-bars for easy
identification and cable ferrules will be fitted at the cable termination points for
identification.

2.2.2.2 Each string shall have a suitable fuse to prevent the reverse current flow with
suitable arrangement for its connection. Y harness is allowed for paralleling two
strings. The Array Junction Box shall have suitable surge protection device (SPD)
and shall consist of Metal Oxide Variasters (MOV) which shall be provided between
positive and negative conductor and earth ground. DC photovoltaic fuses for positive
side for each string shall be provided and shall have fuse holder with fuse blown
indication, easy to isolate the string during fault conditions. It shall be so designed
that it should protect the modules from reverse current flow.

2.2.2.3 The Surge Protection Device shall have following minimum specifications.
Repetitive Surges x15(8/20 μS) In : 20kA
Surge Current (8/20 μS) Imax : 40kA
During earth fault and failure of MOV, the SPD shall be capable of safely
disconnecting the healthy system. SPD shall have thermal disconnector to interrupt
the surge current arising from internal and external faults. In order to avoid the fire
hazard due to possible DC arcing in the SPD due to operation of thermal
disconnector, the SPD shall be capable of extinguishing the arc by itself.

2.2.2.4 The String Monitoring Units shall be tested using automatic calibration tools so that
the accuracy of measured current and voltage reading shall be within +- 0.15%.

2.2.2.5 The Array Junction Box / Combiner box and String Monitoring Unit shall have
suitable arrangement for the following:
 Combine a cluster or group of modules into independent
charging string that will be wired through the String Monitoring
Unit.
 Provides DC Isolator of suitable rating for disconnection at the
outgoing.
 Provides a test point for each sub-group for quick fault location.

11

Page 225 of 328


 Means to measure voltage / current / power of individual and
total string as well as means to indicate the status of
disconnection, SPD and fuses
 The current carrying rating of Array Junction Box / Combiner
Box and String Monitoring Unit shall be suitable with adequate
safety factor to inter connect the Solar PV array.
 In each Array Junction box / Combiner box and String
Monitoring Unit, 5% spare terminals (along with cable glands)
rounded off to next higher integer shall be provided in Fuses and
glands.

2.2.2.6 The String Monitoring Units shall be Intelligent, multichannel, industrial grade,
reliable, field proven microprocessor based unit. Required operating power shall be
made available to the String Monitoring Units from the respective PCSS 110V DC,
UPS and 230 V AC Auxiliary power supply system through cable network. DC to
DC converter for String Monitoring Unit power supply is also acceptable. Solar
power shall be utilized to power the SMU by employing a suitably sized DC-DC
converter. The constructional, operational, connectivity and communication features
of the SMU are further elaborated in the control and automation section of this
specification.

2.2.3 ARRAY YARD AND WATCH TOWER LIGHTING

2.2.3.1 The offer shall include adequate array yard lighting including erection of poles,
fixtures and cables as per IS standards, keeping the general security in mind. Watch
Tower lightings shall be installed to cover the solar power plant boundary lighting. A
minimum illumination level of 10 lux shall be maintained in the internal roads /
pathways. It is preferable to adopt low height bollard type road / path way
illuminators to avoid shadow on adjoining solar PV modules where ever warranted.
The yard lighting and watch tower lighting shall be fed from the station auxiliary
power system of the nearest PCSS. The lighting power from each PCSS shall be
taken to surrounding road / yard lights and watch tower lights through buried cable
network. Automated switching control shall be made available for the yard / road
and watch tower lighting system. Array yard lighting schemes and design
calculations along with drawings shall be submitted for approval by NLCIL.

2.2.4 DC CABLES

2.2.4.1 DC cables used for inter connecting PV modules and for PV modules to array
junction boxes / combiner boxes shall be FRLS, copper conductor cables and shall
be electron beam cured with (+) and (-) colour identification, conforming to the
requirements of TUV Specification 2Pfg 1169/08.2007.

12

Page 226 of 328


DC cables used for connecting array junction boxes / combiner boxes to Inverters
shall be of suitable voltage DC grade. These cables shall have compacted
Aluminium conductor, XLPE insulated, Armoured, FRLS PVC outer sheathed
conforming to IS:7098 ( Part-1).

2.2.4.2 Sizing of DC cable for PV array shall be selected in such a way that the maximum
voltage drop at full power from the first PV module to inverter should be less than
+3% (Including voltage drop in module to module interconnecting cable).

2.2.4.3 The Contractor shall design the array yard such that module mismatch loss shall be
less than 2% loss in system power.

2.2.4.4 For inter connecting PV modules, no cable joints shall be used. MC4
equivalent/compatible connectors with necessary length of DC cables with positive
and negative ends, which are built in component of the PV Modules, shall be used
for interconnection of PV modules. DC cables for PV modules to Array junction
box/ Combiner box and String Monitoring Unit shall be provided without any cable
joints.

2.2.4.5 Cable terminations at Array JB, Combiner Box, SMU shall be made with suitable
cable lugs and sockets etc, crimped properly and passed through suitable type cable
glands (Double compression) at the entry and exit point of the cubicles. The panel
bottoms should be properly sealed to prevent entry of snakes/lizard etc. inside the
panel.

2.2.4.6 All cables shall be marked with good quality letter and number ferrules of proper
sizes so that the cables can be identified easily.

2.2.4.7 Cables shall be fixed to non-moving module mounting structure / column with
adequate looping for allowing tilt of the module frame. Bunching of cables and tying
to module frame with cable ties shall not be adopted as temperature rise of module
frame tend to increase cable power loss and reduce cable life. All cable routed in the
array yard shall be laid taking into consideration of undulated, sloppy terrain of the
project site. Cable duct bank/hume pipe shall be provided for road crossings. For
buried cabling necessary cable markers shall be provided along the route.

2.2.4.8 Cable selection and sizing calculations and detailed explanations along with
catalogues shall be submitted for approval by NLCIL.

2.2.5 ARRAY YARD LIGHTNING PROTECTION SYSTEM


2.2.5.1 The Array yard shall be provided with lightning protection system. The lightning
protection system must be completed prior to start-up of commissioning activities of
the project. The main aim of lightning protection is to protect PV Modules or other
sub-system components from any over voltage surge before it reaches the PV

13

Page 227 of 328


Modules or other sub-system components. The source of over voltage can be
lightning or other atmospheric disturbance.

2.2.5.2 The lightning conductors shall be designed as per Indian Standards in order to
protect the entire Array Yard from lightning stroke including PCSS structure.
Necessary concrete foundation for holding the lightning conductor and spike in
position shall be made after giving due consideration to its shadow on adjoining
solar PV modules, maximum wind speed and maintenance requirement at site in
future.

2.2.5.3 The lightning conductor shall be earthed through flats and connected to the earth
mats with earth pits as per applicable Indian Standards. Lightning protection of Early
Streamer Emission (ESE) type as per NFC 17-102 is also acceptable. The protection
class shall be minimum class II or higher as per NFC 17-102 (2011). Where ever
required, Air Terminals shall be provided at the highest point, especially in PCSS as
well as in watch towers. Each lightning conductor shall be fitted with individual
earth pit as per standards with earth electrode of 3M length including accessories and
masonry enclosure with cover plate as per IS 3043. The pit around the electrode
shall be treated with carbon based earth enhancement compound or conductive
concrete as per provisions of IS 3043. Test links shall be provided in the down
conductor as per standards.

2.2.5.4 Design calculations of the lightning system along with drawings shall be submitted
for approval by NLCIL.

2.2.6 ARRAY YARD EARTHING SYSTEM

2.2.6.1 The earthing for array yard shall be made with earth electrode of
3 M length including accessories and masonry enclosure with cover plate as per IS
3043. The pit around the electrode shall be treated with carbon based earth
enhancement compound or conductive concrete as required as per provisions of IS
3043. Necessary provision shall be made for bolted isolating joints of each earthing
pit for periodic checking of earth resistance. Soil resistivity measurement at the
project site shall be made by the contractor before commencing the earthing system
design.

2.2.6.2 Each Array structure of the Solar PV Yard shall be grounded properly. The array
structures are to be connected to earth pits as per IS standards.

2.2.6.3 The complete earthing system shall be mechanically and electrically connected to
provide independent return to earth. All equipments shall have two distinct earth
connections.

2.2.6.4 For each earth pit, necessary Test Point shall be provided.

14

Page 228 of 328


2.2.6.5 In compliance to Indian Electricity Rules, (as amended up to date), all non-current
carrying metal parts shall be earthed with two separate and distinct earth continuity
conductors to an efficient earth electrode.

2.2.6.6 The bidder shall ensure adequate earthing system protection to provide an acceptable
degree of protection as per IS 3043 for the array yard equipment. If necessary, more
numbers of earth pit and conductors may be provided to achieve earthing resistance
less than 1 Ohm. Design calculations along with drawings shall be submitted for
approval by NLCIL.

2.2.6.7 Earth resistance of the earth pits shall be tested in the presence of the NLCIL
officials.

2.2.7 SURFACE PROTECTION AND PAINTING

2.2.7.1 All structures, boxes, panels and all other items except Galvanized and non-metallic
items shall be provided with approved scheme of surface paint.

2.2.7.2 Surface preparation - The surface preparation procedure shall be done as per IS:
1477 Part-1C16.2.1.2 for power tool cleaning or equivalent DIN standard st.3 or as
per paint manufacturer’s recommendation.

2.2.7.3 Paint application


a) Paint shall be applied in accordance with paint manufacturer’s
recommendation.

b) Paint shall generally be applied by brushing for prime coats and


spraying for finish coats.

c) Paint shall not be applied in rain, wind, fog, or at relative


humidity of 80% and above or when the surface temperature is
below dew point resulting in condensation of moisture.

d) Each coat of paint shall be allowed to dry sufficiently before


application of the next coat to avoid damage.

e) After the erection of fabricated steel structures or panels at the


plant site, damaged and defective shop coats shall be touched up
with the same type paint as used for shop coat after cleaning.

15

Page 229 of 328


f) If powder coating is followed for the inverter panel and other
items, the application shall be in full conformity to paint system
of the supplier.

2.2.7.4 Suggested Paint system for Fabricated Steel Structures

No. of DFT/Coat in Total DFT


coat microns Paint System in microns
1P 70 Ethyl silicate inorganic zinc primer
1I 70 Epoxy MIO
1F 40 Epoxy paint two pack polyamide cured 220
2F 40 Aliphatic Acrylic Polyurethane
P-primer coat, I-intermediate, F-finish coat, DFT- Dry Film Thickness

The paint shall be applied immediately after surface preparation to the specified
quality, preferably within two hours. Prior approval shall be obtained from NLCIL
regarding type of paint and manufacturer

2.2.7.5 Colour code -The shade of finish paint coat to be applied shall be as per IS: 5.The
colour scheme shall be approved by NLCIL.

2.2.7.6 Cathodic protection may also be incorporated to achieve longevity of structures for
surface protection from corrosion.

2.2.8 OTHERS
2.2.8.1 Any array yard work which is not mentioned or included here but necessary for safe
operation, maintenance, longevity and improvement in performance of the plant
shall be included in scope and carried out.

SECTION 2.3
ELECTRICAL POWER COLLECTION& EXPORT SYSTEMS

2.3.1 POWER COLLECTION SUB STATION (PCSS)


2.3.1.1 The contractor shall provide Power Collection Sub Stations (PCSS) of indoor type
which will consist of Transformers, HT circuit breaker and, metering and protection
devices.

2.3.1.2 Cables of adequate size shall transfer the DC power for conversion in to AC in the
inverters. The location of each PCSS shall be selected in such a way to minimise
cable losses.

2.3.1.3 The indoor Power Collection Sub Station (PCSS), shall be RCC building as per
section 2.4.

16

Page 230 of 328


2.3.1.4 The indoor PCSS building shall have PCUs, HT Switch Gear, Auxiliary power
(AC&DC) system and other electronics for communication and shall be finalised
during detailed engineering in line with system requirement. Cable trench shall be
provided between the equipment for connecting external incoming / outgoing cables.
The oil cooled transformer which steps up LT power to HT shall be an outdoor
installation in a fenced area. HT power from transformer to the HT Switch Gear/
shall also be taken through cabling.

2.3.1.5 POWER CONVERSION UNIT (PCU)


The Power Conversion Unit (PCU) shall be Central inverter / string inverter
complying to the statutory norms / CEA regulations /ED/A&N Administration
requirements.

2.3.1.5.1 The Power Conversion Units shall consist of an electronic inverter along with
associated control, protection and data logging devices. The system shall incorporate
a unidirectional inverter and should be designed to supply the AC power to the grid
at load end. The power conversion unit shall adjust the voltage and frequency levels
to suit the grid. All three phases shall be supervised with respect to rise/fall in
programmable threshold values of frequency. The PCU shall conform to IEC 62109
or equivalent standards for safety certification. The PCU shall have provision to be
isolated from grid through Air Circuit Breakers which shall be inbuilt with the
inverter or separate standalone panel.

2.3.1.5.2 PCU shall confirm to IEC 60068-2 standards for Environmental Testing.

2.3.1.5.3 The efficiency of the PCU shall be equal to or more than 98 % at 75% load as per
IEC- 61683. The bidder shall submit the conversion efficiency curve on partial
output powers for the inverter in his offer. The bidder should specify the overload
capacity in the bid.

2.3.1.5.4 The inverter should be warranted for minimum 5 years and the service life of the
inverter shall not be less than 25 years under harsh environmental conditions.
.
2.3.1.5.5 The PCU inverter shall capable to supply or absorb the reactive power for the grid pf
0.95 lead-lag. The PCU inverter shall also support for grid dynamic power factor of
0.8 lag-lead within its rated KVA capacity. The PCU shall have internal protection
arrangement against any sustained fault in the feeder line and against lightning in the
feeder line.

2.3.1.5.6 The PCU inverter shall have the required protection arrangements against earth
leakage faults.

17

Page 231 of 328


2.3.1.5.7. Specifically, the PCU inverter should be three phase power conditioning unit using
static solid state components. DC lines shall have suitably rated isolators to allow
safe start up and shut down of the system. Isolators used in the DC lines must be
rated suitably for DC application..

2.3.1.5.8 The PCU inverter shall be transformer less design with necessary provision for
galvanic isolation. Each solid-state electronic device shall have to be protected to
ensure long life of the inverter as well as smooth functioning of the inverter.

2.3.1.5.9 The PCU inverter shall have special safety features like active anti islanding
detection and isolation facility as well as modular system features to harness solar
power during lesser irradiation conditions and to maintain equal aging of inverter
modular system. The PCUs shall conform to the latest edition of IEEE1547/UL
1741/ equivalent for protection against islanding of grid.

2.3.1.5.10 The PCU inverter must and be able to be successively switched “ON” and “OFF”
automatically based on solar radiation variations during the day.

2.3.1.5.11 Inverter system shall tend to balance unequal phase voltage (with 3-phase systems)
with reference to the red phase (line-1). Protection shall include negative sequence
protection also such that if the balancing of 3 Phase system failed, the protection
shall envisage isolation of the inverter from the circuit.

2.3.1.5.12 The PCU inverter front panel shall be provided with a display (LCD or equivalent/
LED + Mobile App Display) of all important parameters such as DC input voltage,
DC input current, AC output voltage, AC output current, AC output power, power
factor, frequency etc. In addition to the display in PCU panel, the same shall be
made available in the monitoring and controlling desk installed in the project
control room forming part of the supervisory control and data acquisition system
(SCADA) and EMS.

2.3.1.5.13 The PCU enclosure and internals including nuts, bolts etc shall have to be
adequately protected, taking into consideration the atmosphere and weather
prevailing in the area.

2.3.1.5.14 Dimensions and weight of the PCU shall be indicated by the bidder in the offer.

2.3.1.5.15 The PCU shall include appropriate self protective and self diagnostic feature to
protect itself and the PV array from damage in the event of PCU component
failure or from parameters beyond the PCU’s safe operating range due to
internal or external causes. The self-protective features shall not allow signals
from the PCU front panel to cause the PCU to be operated in a manner which
may be unsafe or damaging. Faults due to malfunctioning within the PCU,
including commutation failure, shall be cleared by the PCU protective devices.

18

Page 232 of 328


It should have local LCD (Liquid crystal display) and keypad for system
control, monitoring instantaneous system data, event logs, data logs and
changing set points. Control and read-out should be provided on an indicating
panel integral to the inverter. Display should be simple and self explanatory to
show all the relevant parameter relating to PCU operational data and fault
condition in front panel meters / LED’s or two line LCD Display.

2.3.1.5.16 PCU shall have arrangement for adjusting DC input current and should trip
against sustainable fault downstream and shall not start till the fault is rectified.

2.3.1.5.17 Operation and maintenance manual should be furnished by the Contractor


before dispatch of PCUs.

2.3.1.5.18 Bill of materials associated with PCUs should be clearly indicated while
delivering the equipment.

2.3.1.5.19 Standby Mode - The control system shall continuously monitor the output of the
solar power plant until pre-set value is exceeded and that value to be indicated.

2.3.1.5.20 Basic System Operation (Full Auto Mode) - The system shall automatically
“wake up” in the morning and begin to export power provided there is sufficient
solar irradiance and the grid voltage and frequency is in range.

2.3.1.5.21 Maximum Power Point Tracker (MPPT) – MPPT control algorithm shall adjust
the voltage of the SPV array to optimize energy fed into the grid.

2.3.1.5.22 Sleep Mode - Automatic “sleep” mode shall be provided so that unnecessary
losses are minimized at night. The power conditioner must also automatically
re-enter standby mode when threshold of standby mode is reached.

2.3.1.5.23 Maximum Power Point Tracking (MPPT) - Maximum power point tracker shall
be integrated in the power conditioner unit to maximize energy drawn from the
Solar PV array at all seasons and in varying solar insolation conditions. The
MPPT should be microprocessor based to minimize power losses. The details of
working mechanism of MPPT shall be furnished by the Contractor. The MPPT
must have provision for constant voltage operation. The MPPT unit shall
conform to IEC 62093 for design qualification. Multi MPPT and Master –Slave
configuration shall also be considered as applicable. The MPPT shall conform
to EN50530.

2.3.1.5.24 The inverter output shall always follow the grid in terms of voltage and
frequency. This shall be achieved by sensing the grid voltage & phase and
feeding this information to the feedback loop of the inverter. This control
variable shall then control the output voltage and frequency of the inverter, so

19

Page 233 of 328


that inverter is always synchronized with the grid. The inverter shall be self
commutated with pulse width modulation technology. The design and operation
of inverter shall be such as to limit the individual and total harmonic distortions
(THD) within the limits specified in IEEE 519 at HT level and the same shall be
demonstrated at site. Additional equipment, if any to meet the above
requirement shall be included as part of inverter / HT bus at Power Export
Switchyard. Inverter switching scheme shall have in built arrangement to
minimize the circulating currents between inverters and the transformer.
Low/High Voltage Ride-Through (LHVRT): The inverter should not get tripped
in the event of voltage drop for a pre determined time as per regulatory norms
and the inverter need not stay in grid after this pre determined time if the
voltage does not develop to a certain percentage of rated value as per regulatory
norms.
Low/High Frequency Ride-Through (LHFRT): Immediate disconnections when
momentary frequency disturbances should not occur. LHFRT shall allow
inverters to stay connected if such frequency excursions are for very short time
durations.
Power-frequency droop: Inverters shall not switch off abruptly. Inverters will be
required to stay connected when the grid frequency changes after which the
inverters are required to shut down.

2.3.1.5.25 Technical Parameters:


Nominal AC Output Power - Output at 0.95 PF :
Minimum 526.32 KVA for 500KW central inverter
Minimum 26.3157 KVA for 25 KW string inverter
VA rating of micro inverter shall be rating of inverter/ 0.95.
Nominal Output voltage : To suit.
Minimum Efficiency at 75%load : ≥ 98%
Output frequency : 50 Hz +3% to -5% Hz (Inverter to
follow grid frequency up to +3% to
/- 5% Hz of the nominal output
frequency during normal
operation)
Power Factor (Adjustable) : 0.8 Lead to 0.8 Lag
Maximum Input voltage : 1000 V DC or above
Total Harmonic Distortion (THD) : Less than 3 %
Ambient temperature : 0 to 50deg C
Humidity : 5% - 95%, non- condensing

2.3.1.5.26 The Inverter shall have following features:


a) No load loss<1% of rated power and maximum loss in sleep
mode shall be less than 0.05%
b) Sinusoidal current modulation with excellent dynamic response.
c) VAR control

20

Page 234 of 328


d) Unit wise and integrated data logging.
e) Dedicated Ethernet for networking
f) Protection against over current, loss of synchronization, over
temperature, DC bus over voltage, cooling fan failure
g) Power regulation in the event of thermal overloading
h) Set point pre-selection for VAR control
(i) Provision of Port and protocol for SCADA requirement:
Data Acquisition Systems (DAS) as a combination of a software
application programme and electronic hardware for monitoring
PV plants and reporting data is required. This can be considered
to be a subset of the Supervisory Control and Data Acquisition
(SCADA) programme to monitor different datas. This data
should be accessible as part of a central database for A&N
Electricity department etc. The required protocol for A&N
Electricity department is IEC 60870-5-104 protocol and shall be
finalised during detailed engineering as per system requirement
and A&N Electricity department requirement.
j) Remote control via SCADA and EMS
k) Integrated protection in the DC and three phase system
l) Insulation monitoring of the PV array with sequential fault
location.
m) PID monitoring if applicable.
n) Earth Fault Protection – through neutral CT. Alternatively, GFID
kit (Ground Fault indication device) is also acceptable.

2.3.1.6 AC BREAKER
2.3.1.6.1 AC converted in the PCUs shall be transmitted through an AC breaker. AC
breaker as part of PCU inbuilt is also acceptable. Outgoings of the AC breaker
shall be connected to the HT transformer through appropriate size aluminium
cables.

2.3.1.6.2 The AC Breaker shall consist of adequately sized ACBs conforming to IS


13947-Part 1&2 and IEC 947-Part 1&2 for circuit breakers of suitable rating for
connection and disconnection of PCU from Grid. Suitable capacity breakers
shall also be provided for the transformers. The control of the circuit breaker
shall be with microprocessor technology and with electro-magnetic
compatibility (EMC). The AC Breaker shall be equipped with adequate
protection relays, fuses, annunciations and remote operating and controlling
facility through SCADA and EMS.

2.3.1.6.3 The Contractor shall submit design calculations and drawings for the AC
Breaker for approval by NLCIL.

21

Page 235 of 328


2.3.1.7 HV POWER TRANSFORMER
2.3.1.7.1 The design, engineering, manufacture and testing of the oil cooled Power
Transformer in each PCSS and its related equipment shall be carried out as per
the latest Indian /International standards, Indian electricity rules, relevant code
of practices and requirement of Central Electricity authority. Salient standards
and code of practices are given below:

Power transformers : IS 2026, BS 171 and IEC


60076
Guide for loading of oil immersed
transformers : IS 6600 / IEC 354
Tap changer : IEC 60542
Fittings and accessories (if applicable) : IS 3639
Insulating oil for transformer : IS 335
Bushings for alternating voltages
above 1000 volts : IS 2099
Dimensions for porcelain
Transformer Bushings : IS 3347
Recommended practice for hot dip
Galvanizing of iron and steel : IS 2629
Methods of testing of coating of zinc
coated items : IS 2633
Colour for ready mixed paints and
Enamels : IS 5
Except where specified otherwise herein, all material, equipment and
construction shall confirm to all the acts, rules and standards indicated.

2.3.1.7.2 Technical Particulars


The transformer offered shall meet the following technical particulars:
Service : Outdoor
Rating : To suit.
Cooling : ONAN
Voltage ratio : To suit
Number of phase : 3
Primary Voltage : To suit
Secondary Voltage : HV as per requirement
Winding connection, Vector group : As per design requirement
of the solar PV plant and
actual requirements of
A&N Electricity
Department

Impedance voltage : To suit the system


requirement.

HT short circuit level : As per system requirement.


System earthing at HV : As per system requirement.

22

Page 236 of 328


System earthing at LV : As per system requirement.
Highest system voltage : As per system requirement
Insulation level HV : As per system requirement
Tap changers and Tapping : Off circuit type, with +/-2.5 %
and +/- 5% taps. (5 Positions)
Temperature rise, degree C
Top oil, by thermometer : 45 degree C
Winding, by resistance : 55 degree C
Terminal arrangement : Cable box on HV side for
terminating XLPE,
armoured, Al cable.
Cable box on LV side for
terminating XLPE,
armoured Al cable.
Neutral : As per ED/A&N Administration
requirements
/system requirements

2.3.1.7.3 The transformer shall be of proven design and robust maintenance free
construction featuring liberal use of active materials viz. core iron and copper to
keep down losses at low levels and consequently the operating temperature well
within the limits of oil cooled transformers.

2.3.1.7.4 Constructional Features


i) The transformer shall be designed to withstand the extremes of
all magnetic, electrical, mechanical and thermal stresses and gas
pressures which may be encountered during its normal and
abnormal operating conditions.
ii) The transformer shall be capable of withstanding the short circuit
stresses due to a terminal fault on any one winding with full
voltage maintained on the other windings for minimum period
for three (3) seconds.
iii) The transformer shall be capable of working at high efficiency in
both the directions of power flow.
iv) All materials used shall be new and of tested quality conforming
to applicable national or manufacturer's standards and Indian
Electricity Acts/rules. Equipment shall be transportable and
capable of installation at site with ease and without damage. It
shall give continuous reliable operation over long periods under
worst specified site conditions. All similar parts shall be
interchangeable.
2.3.1.7.5 Tanks
2.3.1.7.5.1 Tanks shall be welded construction and fabricated from tested quality
commercial grade carbon sheet steel of adequate thickness. The transformer
tank top shall be provided with detachable cover with bolted flanged gasket
joint. Lifting lugs shall be provided for removing the cover with core and coil

23

Page 237 of 328


assembly. Tank covers shall be welded from tested MS flats adequately
reinforced externally by structural steel stiffeners. Two side walls of the tank
shall be provided with extended finned tubes to act as a radiator. All seams,
flanges, lifting lugs, braces and permanent parts attached to tank shall be double
welded. Joints which may have to be opened for inspection and/or repairs shall
be machined surface and be made oil tight with renewable oil resistant gaskets
and seals. Guides shall be welded to the inner side of the tank to facilitate
tanking and un-tanking. Tank shall be suitable for full vacuum required during
drying out for oil filling and shall withstand the required pressure.
2.3.1.7.5.2 All removable covers shall be provided with weather proof, hot oil resistant,
resilient gaskets. The openings for all removable covers shall be made on
suitably elevated bosses/contour frames. The design shall be such as to prevent
any leakage of water into or oil from the tank.
2.3.1.7.5.3 Adequate space shall be provided at the bottom of tank for collection of
sediments.
2.3.1.7.5.4 After fabrication and welding of cooling fins, tank and its fittings with
respective valves shall be pressure tested with transformer oil to withstand
specified pressure. No valve shall drip and no weld or joint shall sweat.
2.3.1.7.5.5 All gasket joints shall be perfectly oil tight under all conditions of operations.
Gaskets shall be of neoprene or approved oil resistant material and so placed
that they will not be exposed to weather. Damaged gaskets shall not find way
into the tank.
2.3.1.7.6 Core
2.3.1.7.6.1 The core shall be constructed from high grade, cold rolled, non- aging, grain
oriented, silicon steel laminations to BS: 601. Core, its supporting steel and
insulation shall be of such design, material and construction that harmful
changes in electrical or physical properties shall not occur during the life of
transformer. Limbs and yoke shall have similar section to minimise effects of
transverse flux. Butt joints between yoke and limbs shall not be made. Generous
cooling ducts shall be provided for core heat dissipation.
2.3.1.7.6.2 Core and winding shall be strongly braced to prevent displacement or distortion
during transportation or abnormal electrical conditions in service. The core and
coil assembly shall be securely fixed in position so that no shifting or
deformation occurs during movement of transformer or under short circuit
stresses.
2.3.1.7.6.3 Each core bolt and parts of core clamping framework shall be insulated from the
core laminations and tested after assembly of core to withstand 2 kV RMS for
one (1) minute. Preference shall be given to such construction of core, which
does not involve use of core bolts. The core design shall be such as to limit the
flux density to 1.6 Tesla.
2.3.1.7.7 Windings
2.3.1.7.7.1 Each coil shall be wound of paper insulated, continuous smooth, high grade,
electrolytic copper conductor, without sharp corners or bends and shall be
adequately transposed to minimize eddy current losses and equalize current and
temperature distribution. Successive coils may be smoothly brazed or welded
in an accessible location. Abrasive damage and high dielectric stresses in
insulation shall not occur. Similar coils shall be interchangeable. Liberal
ducts shall be provided for oil circulation and prevention of ‘hot spots’ that may

24

Page 238 of 328


affect insulation life. Insulation of windings and other live parts should be
adequate to sustain 110% of rated operating voltage continuously.
2.3.1.7.7.2 An earthed screen shall be installed between the primary and secondary
windings to capacitatively decouple primary and secondary windings and
eliminate the effects of high frequency transients on the other winding
2.3.1.7.7.3 The coils shall be manufactured from electrolytic copper conductor. The
materials used in the insulation and assembly of the windings shall be insoluble,
non-catalytic and chemically in-active in the hot transformer oil and shall not
soften or otherwise be affected under the worst operating conditions. Insulating
material shall be of proven design, Coils shall be so insulated that impulse and
power frequency voltage stresses are minimum
2.3.1.7.7.4 Coil supports shall be by permanently secured, highly compressed and dried,
regularly spaced insulating spacers. Coil clamping rings, if made of steel shall
each be earthed by connection to core clamping structure and shall otherwise be
of insulating material built up from flat laminations.
2.3.1.7.7.5 Coil assembly shall be suitably supported between adjacent sections by
insulating spacers and barriers. Bracings and other insulation used in assembly
of winding shall be arranged to ensure free circulation of oil and to reduce the
hot-spot of winding.
2.3.1.7.8 Fasteners
2.3.1.7.8.1 Clamping bolts for current carrying parts inside oil shall be of oil acidity
resistant material. Terminal screws, studs, nuts and bolts shall be of non-ferrous
material, threaded to IS. All fasteners exposed to weather shall either be
nonferrous or hot dip galvanized or electroplated conforming to relevant IS.
2.3.1.7.9 Cooling
2.3.1.7.9.1 The transformer shall be provided with finned tube radiator panels on two sides
to cool the oil.
2.3.1.7.9.2 The finned tubes shall be of heavy gauge, corrosion resistant steel construction.
All internal surfaces of the tubes shall be pickled, free of all rust and scale and
passivated. External surfaces shall be sand blasted and required number of
coats of weather proof paint applied so as to prevent rusting.
2.3.1.7.10 Bushings
2.3.1.7.10.1 Oil communicating type porcelain bushing and its terminal fittings shall carry
full rated current continuously without exceeding temperature of any component
beyond 70oC. These shall operate satisfactorily in heavy sand storms, rain with
lightning and other site atmospheric conditions. Freedom from corona and radio
interference shall be ensured. Bushing shall be wet process porcelain with
uniformly brown external shell. All bushings shall be designed or equipped to
withstand arcing or flashover without damage to seals or any vital part.
Terminal bushing shall be oriented for the minimum clear distances in air as per
CBIP stipulation. Minimum distance between terminals of two windings of
different voltage shall equal the phase-to-phase distance of the HV winding.
2.3.1.7.10.2 Bushings shall be provided with terminal connectors of approved type and size.
Bushing location shall provide adequate phase and ground clearances. Bushings
shall be suitable for surrounding atmosphere and shall have creepage distance.
2.3.1.7.11 Cable box and disconnecting chamber
2.3.1.7.11.1 On the HV side cable box, disconnecting chamber shall be provided for
disconnecting and moving away the transformer without unsealing the
cables or draining oil from the main tank leaving the cable box and part
disconnecting chamber behind on external supports supplied by the vendor.

25

Page 239 of 328


2.3.1.7.11.2 The HV cable box shall be complete with other accessories including armour
and earthing clamps. The box shall be suitable for heat shrinkable type/push on
type/tapex type termination kits of proven design against short circuit levels of
as per standards for one second with a peak value as per standard.
2.3.1.7.11.3 The disconnecting chamber shall be air insulated, removable links and
removable covers shall be provided for the disconnecting chamber. Plates
through which high current carrying conductors pass, shall be of non- magnetic
materials.
2.3.1.7.11.4 Phase to phase and phase to ground clearances within the chamber shall be such
as to enable either the transformer or cable to be subjected to HV tests.
Clearances shall be subject to approval by NLCIL.
2.3.1.7.11.5 LV cable boxes shall be of steel plate construction, self-supporting weather
proof type complete with all accessories including brass cable glands & tubular
copper lugs to receive number of 1.1kv grade Aluminium XLPE cables to suit.
2.3.1.7.12 Marshaling box
2.3.1.7.12.1 The marshaling box shall be corrosion resistant sheet steel, weather proof, dust
and vermin proof construction conforming to degree of protection IP55 with 16
SWG thick sheet steel water tight hinged and padlocked doors, fully wired, for
terminating all wiring for control, protection and alarm circuits of the
transformer. All wiring shall be of 1100V grade, oil and fire resistant, multi core
copper cables. All devices and terminal blocks within the marshaling box shall
be identified by symbols corresponding to those used in applicable schematic or
wiring diagram.
2.3.1.7.13 Insulating Oil
2.3.1.7.13.1 Transformer shall be filled with mineral insulating oil conforming to IS: 335.
Material in contact with the oil shall be such as not to contribute to the
formation of acid in oil.
2.3.1.7.14 OFF Circuit Tap Changers
2.3.1.7.14.1 OFF circuit tap changers suitable for variation of secondary (constant flux
voltage variation) shall be provided on the primary Windings. The range of taps
shall be as specified. The transformer shall be capable of operation at its rated
KVA on any tap provided the voltage does not vary by more than ±10% of the
rated voltage corresponding to the tap. The winding including the tapping
arrangement shall be designed to maintain electromagnetic balance between two
primary and one secondary windings at all voltage ratios. The tap switches shall
be of robust construction, of adequate rating, capable of repeated operation and
of withstanding short-circuit forces. All contacts shall have ample area and shall
be held in position under strong contact pressure to avoid contact pitting.
2.3.1.7.15 Grounding
2.3.1.7.15.1 Two grounding pads, located on the opposite sides of the transformer tank, shall
be provided for connection to station ground mat. The core coil assembly shall
be directly connected to this ground bus by removable bolted link for effective
grounding. Ground terminals shall be provided on marshaling box, cable end
box etc. to ensure its effective earthing. For continuity of earth connection, all
gasket joints shall be provided with minimum two numbers braided copper
conductor jumpers of adequate size.
2.3.1.7.16 Fittings and Accessories
2.3.1.7.16.1 The transformer shall be complete with oil for first filling and all standard
fittings and accessories as per IS 2026 including the following:
1. First fill of oil as per IS2026 with 10% extra oil

26

Page 240 of 328


2. Oil conservator with filling hole, cap, and air cell
separator for the main and OLTC oil compartments
3. Drain plug for conservator
4. Magnetic oil level gauge with alarm contacts
5. Prismatic oil level indicator
6. Silica gel breather for conservator
7. Double float Buchholz relay with alarm and trip contact
8. Shut off valve for Buchholz relay on both sides
9. Dial type oil temperature indicator with alarm, trip
contacts and maximum temperature indicator
10. Dial type CT operated winding temperature indicator
with alarm, trip contacts and maximum temperature
indicator
11. Thermometer pockets
12. Pressure relief valve with trip and alarm contacts
13. Air release vent, drain plug for radiators.
14. Flanged filter valve at top and bottom
15. Lifting lug and jacking pads
16. Rating and terminal marking plate
17. Bi-directional flanged wheels
18. Detachable radiators complete with top and bottom
valves
2.3.1.7.17 Paint and Finish
2.3.1.7.17.1 All surfaces to be painted including interior and exteriors of tanks, mechanisms
and enclosures and other metal parts. These shall be shot or sand blasted or
chemically treated to remove all rust, scale, grease and other adhering foreign
matters. All steel surfaces in contact with hot insulating oil, shall be painted
with not less than two (2) coats of heat resistant and oil insoluble paint. Steel
surfaces, exposed to weather shall be given two (2) coats of zinc chromate and
two (2) coats of finishing paint light grey No. 631 of IS:5 with glossy finish
except for panels which shall have matt finish. The final finished thickness of
paint film on steel shall not be less than 100 microns and shall not be more than
150 microns

2.3.1.7.18 Tests and Inspection


2.3.1.7.18.1 The transformer shall be designed and manufactured to national and
international standards. After manufacture, it shall be subjected to inspection
and testing in the manufacturers’ works which should be accredited by the
National testing laboratory and tests as per MQP sampling shall be carried out
in the presence of the NLCIL Engineer. The various tests to be carried out shall
be as follows:
1. Assembly inspection
2. Measurement of winding resistance
3. Measurement of voltage ratio
4. Check of vector group

27

Page 241 of 328


5. Measurement of impedance voltage, short circuit impedance and
load loss
6. Measurement of no load loss and no load current
7. Temperature rise test
8. Separate source voltage withstand test
9. Inducted over voltage withstand test
10. Verification of type test reports for short circuit, impulse voltage
and partial discharge tests
The contractor shall furnish type test reports of the transformer for NLCIL
approval. The contractor shall also arrange to conduct site tests including ratio
test, etc. after installation.
2.3.1.7.19 Performance Guarantee
2.3.1.7.19.1 The transformers shall be guaranteed for workmanship, materials and
satisfactory performance in respect of voltage ratio, load / no load losses,
heating etc. for a minimum period of twelve (12) months from date of
Provisional take over. The guarantee for performance shall be inclusive of
individual component parts and the equipment as a whole for their
ratings/output as well as for the operation of the transformer. If it fails to meet
the performance requirements due to defective material and workmanship, the
same shall be replaced free by the contractor.

2.3.1.8 HT Breaker
2.3.1.8.1 Standards and Construction Features
The HT switchgear distribution board shall conform to IS 3427, IS 12729 and IS
13118 for all essential features of design, construction and testing. The board
shall be factory assembled and wired, totally enclosed, dead front, draw out
type, fully interlocked and compartmental design.

2.3.1.8.1.1 The switchgear must provide a maximum degree of personal safety and
operational security for the operators and others in the vicinity of the switchgear
under all operating and fault conditions. To fulfil the high safety requirement for
personnel, the switchgear insulation must be designed to provide the best
possible protection in the event of an arc fault. To ensure this condition, all
compartments of the switchgear shall satisfy the requirements of IEC 298.

2.3.1.8.1.2 The products of the arc shall not transport from one compartment to another.
There must be no danger to any person standing at the front or to the side of the
switchgear, caused by the venting of hot gases or the scattering of other
products of the arc. The circuit breaker compartment shall also meet the above
test requirement while the circuit breaker is being raked in or out of service.

2.3.1.8.1.3 The bus bars shall be of electrolytic grade copper, air insulated and housed in a
separate metal clad chamber at the top. The bus bars shall be provided with
insulation sleeving rated for full system voltage. Adequate electrical clearances
between live parts and between live part and earth shall be provided. The cross

28

Page 242 of 328


section of bus bars shall be adequate to limit the temperature rise to 45degC
over ambient of 50 deg C while carrying rated current.

2.3.1.8.1.4 The cable compartment shall be located at the bottom and shall be accessible
through bolted cover plates at the rear. The current transformers shall also be
located in the cable compartment.

2.3.1.8.1.5 The HT switchboard shall be provided with earthing truck or earthing switch
with safety interlock features for bus earthing and outgoing cable earthing. The
earthing switch / truck shall be interlocked with the circuit breaker so that it can
be closed only when the circuit breaker is racked out to isolated position. The
interlock shall also ensure that the cable side or bus side is dead before earth
switch is closed through voltage metering facility, audio visual alarm and
holding solenoid.

2.3.1.8.1.6 A copper earth bus shall be provided at the bottom of the switchboard
throughout its length. The switchboard, devices and terminal blocks shall be
provided with legibly engraved inscription plates for identification. The
switchboard shall be provided with caution notice boards conforming to IS 2551
in the front and rear.

2.3.1.8.1.7 The circuit breaker compartment of the switchboard shall have a fixed and a
moving portion, fixed portion being part of the switchboard. The moving
portion shall contain the circuit breaker of horizontal draw out design mounted
on a truck. The circuit breaker compartment shall have a front hinged door after
opening of which the circuit breaker shall be accessible.

2.3.1.8.1.8 The design of the board shall permit the moving portions to be withdrawn and
provide for isolation of the main contacts by means of plug and socket
connections. Automatic safety shutters shall be provided over the isolating
contacts in the stationary portion and shall be so designed as to close firmly over
the contacts when the circuit breaker is in drawn out position. The draw out
mechanism of the circuit breaker shall have Service, Isolated and Test positions

2.3.1.8.1.9 In the design of the switchgear, the following positive inter-locking shall be
provided:
2.3.1.8.1.10 Interlock to prevent movement of truck to “Service” position without
engaging secondary plug socket connections.
2.3.1.8.1.11 Interlock to prevent disconnection of secondary plug socket connection in
“Service” position.
2.3.1.8.1.12 Interlock to prevent withdrawal of truck past “Isolated” position without
disconnecting secondary plug socket connection.
2.3.1.8.1.13 Interlock to prevent switching ON of breaker unless truck is properly engaged in
“Service” or “Isolated” positions.

29

Page 243 of 328


2.3.1.8.1.14 Interlock to prevent movement of truck to “Test” position
2.3.1.8.1.15 Interlock to ensure that the breaker truck is in “Isolated” position before closing
the integral earth switch if provided.
2.3.1.8.1.16 Interlock to prevent insertion of truck to “Service” position with earth switch
“ON”.
2.3.1.8.1.17 Interlock to prevent opening of cubicle door with the breaker “ON” while in
“Service” position.
It shall be possible to achieve “Service” and “Isolated” positions of breaker
truck with compartment door closed.

Front door shall be interlocked with the breaker such that the door cannot be
opened with the circuit breaker in service position or can the circuit breaker
inserted into the service position with door open. It shall be possible to defeat
the interlock with use of tools if this becomes necessary.

2.3.1.8.2 Technical particulars of HT Circuit Breaker


2.3.1.8.2.1 The circuit breaker shall be HT, required continuous 120% of load current and
short circuit rating required for 1 second rated, fully interlocked horizontal draw
out design. The circuit breaker shall be of vacuum design. The circuit breaker
shall have motorized spring charged closing mechanism of trip free design with
provision for manual closing, manual tripping and mechanical ON/OFF
indicators. The circuit breaker shall be of tested and proven design and the
bidder shall furnish type test certificates for short circuit making and breaking
capacities, electrical and mechanical endurance tests and power frequency and
impulse voltage withstand tests for the circuit breaker panel. The circuit
breakers and accessories shall conform to IEC- 62271-100 or equivalent Indian
Standard.

2.3.1.8.2.2 The duty requirement of the Circuit breaker shall be C2/M1class under all duty
conditions and shall be capable of performing their duties without opening
resistor. The circuit breaker shall meet the duty requirement of any type of fault
or fault location and shall be suitable for line charging and dropping when used
on HT effectively grounded or ungrounded systems and perform make and
break operations as per the stipulated duty cycles satisfactorily. The circuit
breaker shall be capable for breaking the steady & transient magnetizing current
corresponding to HV transformers. It shall also be capable of breaking line
charging currents as per IEC- 62271-100 with a voltage factor of 1.4. The rated
transient recovery voltage for terminal fault and short line faults shall be as per
IEC: 62271-100.

2.3.1.8.2.3 The Contractor shall indicate the noise level of breaker at a distance of 50 to
150 m from base of the breaker.

30

Page 244 of 328


2.3.1.8.2.4 The contractor may note that total break time of the breaker shall not be
exceeded under any duty conditions specified such as with the combined
variation of the trip coil voltage etc. While furnishing the proof of the total
break time of complete circuit breaker, the contractor may specifically bring out
the effect of non-simultaneity between same pole and poles and show how it is
covered in the guaranteed total break time. While furnishing particulars
regarding the D.C. component of the circuit breaker, the Contractor shall note
that IEC-62271-100 requires that this value should correspond to the guaranteed
minimum opening time under any condition of operation. The critical current
which gives the longest arc duration at lock out pressure of extinguishing
medium and the duration shall be indicated. All the duty requirements specified
above shall be provided with the support of adequate test reports.
2.3.1.8.2.5 Operating Mechanism - Circuit Breaker of vacuum type shall be with
electrically spring charged mechanism. The operating mechanism shall be
electrically and mechanically operated with anti-pumping and trip free (as per
IEC definition) under every method of closing. The mechanism of the breaker
shall be such that the position of the breaker is maintained even after the failure
in vacuum. The circuit breaker shall be able to perform the duty cycle without
any interruption. Electrical tripping shall be performed by shunt trip coil.
Provision shall also be made for local electrical control. “Local / remote”
selector switch and close & trip push buttons shall be provided in the breaker
control cabinet. Operating mechanism and all accessories shall be in control
cabinet.

2.3.1.8.3 The technical particulars of the switch board shall be as follows:


Nominal system voltage : HT
Highest system voltage : As per standards
Phase : 3
System frequency : 50Hz
System earthing : As per standards
Type of circuit breaker : Vacuum
Continuous rating of CB in enclosure: As per standards
Continuous current rating of bus bar : As per standards
Short circuit interrupting capacity of CB : As per standards
Power frequency withstand voltage : As per standards
Impulse withstand voltage : As per standards
Degree of protection of enclosure : IP 4X
Terminal arrangement : HT Cable on the outgoing
side, XLPE insulated , Al conductor armoured, PVC sheathed HT grade cable.
2.3.1.8.4 Accessories
Current transformer : Require sets of current transformers on the
incoming and outgoing feeders as per IS-2705/IEC-185, each having two
secondary cores of ratios as per system requirement.

31

Page 245 of 328


The primary and secondary current limits and other technical parameters of the
CTs shall be compatible with the protection relays.

One (1) additional CT core of 0.2 S class shall be provided in the outgoing
breaker as redundancy for metering.

Potential transformer : One set of PT as per IS-3156/IEC-186,


having two secondary cores of ratios and class of
accuracy as per standards. The PT shall be
mounted on the outgoing side and shall have fuse
protection. PT shall be accommodated in a
separate compartment in the breaker enclosure.

Instruments and meters : Electronic multi function energy meter to


read current, voltage, kW, kVA, kVAr, kWh,
power factor etc., in the incoming feeder and
ammeter with selector switch in case of outgoing
feeders.

Protective relays : Microprocessor based numeric protection relays


for multi characteristic inverse minimum time/current
type over current and earth fault protection with
numerical display of setting values, measured values,
memorized fault values and software self supervision
with auto diagnosis. The relays shall have communication
port for hooking up to PSS (pooling substation) SCADA.
The protection relays shall have the data transfer interface
conforming to the IEC 61850 communication protocol.
One set of trip circuit supervision relay and one set of
high speed trip relay shall also be provided. The
protection relays shall be provided with non-volatile
memory for preserving important data during
auxiliary supply breaks.

Other devices : Requisite number of LED type indication lamps, breaker


control switches, HRC fuses and other devices.
Control and trip power supply for the HT switchgear shall be
derived from 110 Volts DC and from the station auxiliary supply
switch board at 230V single phase AC to ensure availability of
trip supply at all times including when there is a terminal short
circuit.
2.3.1.8.5 Inspection and Tests

32

Page 246 of 328


After manufacture, the switchgear panel shall be subjected to inspection and
testing in the manufacturers’ works in the presence of NLCIL Engineer. The
various tests to be carried out shall be as follows.
1. Operation test
2. Power frequency voltage test
3. Measurement of resistance of main circuit
4. Functional test on control circuit.
5. Insulation Resistance (IR) value test.
6. Verification of type test reports for the following
tests:
 Short circuit making and breaking currents
 Peak withstand current and short time
current
 Small inductive breaking current
 Impulse voltage withstand
 Electrical endurance
 Internal arc test

2.3.1.8.6 Instruments and Meters


2.3.1.8.6.1 All instruments and meters shall be of robust design, vibration proof and
suitable for flush mounting on vertical panels.
2.3.1.9 PROTECTIVE RELAYS
The protective relays shall be as per CEA norms and it shall be designed to meet
system requirements and Grid requirements. It shall be finalized during detailed
Engineering.
2.3.1.10 110 V DC SYSTEM - PCSS
2.3.1.10.1 Each PCSS shall be provided with suitable capacity 110 V DC system for
meeting the power requirement of switchgears, control panels, Inverter
Monitoring Units (IMU), etc in each PCSS and respective String Monitoring
Units (SMU) in the yard. 110V (AC) UPS system instead of 110V DC system
shall also be acceptable to meet the system requirements.The battery together
with the charger and DCDB shall be suitable to meet the DC load. The basic
design data for battery and battery charger shall be as given below:

2.3.1.10.2 Battery
Type of cell : Valve regulated lead acid type (VRLA) only and the
battery shall be located in the ventilated room for RMU.
Nominal DC voltage : 110V DC
Load : To meet the requirements of breakers, ventilation fans, system
panels, IMU and SMU.
Battery capacity : Ah to suit based on 10 hour rate of
discharge
Duty : Sub Station duty
End cell voltage : 1.85 Volts (C10 or higher battery

33

Page 247 of 328


Shall be selected to achieve the same).
Ampere hour efficiency : Better than 90%
Watt hour efficiency : Better than 80%
Self discharge : Not to exceed 1% per week.
Accessories : Battery rack made of acid resistant paint coated steel
sheet
Set of lead coated heavy-duty copper strips with bolts and nuts as inter cell and
inter row connectors
Cell testing voltmeter
Thermometer with temperature correction chart
Back up: The 10 hours backup time for the 110V DC system in PCSS.

2.3.1.10.3 Battery Charger


2.3.1.10.3.1 The battery charger shall be designed for charging the battery in float as well as
boost modes and simultaneously supplying the continuous load current
indicated in the duty cycle. The charger shall be designed to operate with input
voltage from auxiliary power of 415V +10%, 3 phase, 50 Hz +5%/-3% with an
output voltage shall be 110VDC +1%.

2.3.1.10.3.2 The charger shall consist of input switchgears, two winding transformer, SCRs
and diodes, regulator, filter circuit, output switchgear, metering and protective
devices for under voltage, over voltage and earth fault, alarm indicator circuit
and integral DC distribution board. All necessary indications and meters like
AC voltmeter, DC voltmeter, DC ammeter etc. shall be provided. Indication for
DC battery connected to load shall also be provided.

2.3.1.10.3.4 Both float and boost chargers shall have control device to vary the voltage to
achieve the desired output.

2.3.1.10.3.5 The output voltage of bridge for float charger shall be 120V DC max. The
output voltage of the bridge for boost charger shall be 145V DC max.

2.3.1.10.3.6 The charger shall be provided with auto-changeover circuitry from float to boost
and vice versa in addition to manual changeover switch. The float circuit shall
be designed for supplying the continuous load current as well as charge the
battery. The boost circuit shall be suitable for delivering charging current
suitable for 110V, battery. RMS ripple factor in input voltage of the charger
shall not be more than 3%.

2.3.1.10.3.7 The charger shall be provided necessary communication port for interfacing
with plant SCADA for remote monitoring and control through Station Facility
Controller.

34

Page 248 of 328


2.3.1.10.3.8 DC Distribution Board (DCDB)
a) The DCDB shall form an integral part of main battery charger. It shall be
compartmentalized; dust & vermin proof and shall be equipped with main
incoming switch fuse unit and required number of double pole MCBs and
switch fuse units.

b) The utilization category of the DC switching devices shall be based on


the individual loads as recommended in IS 13947.

2.3.1.10.3.9 DC Battery, charger, DC power distribution system and remote control /


monitoring design, calculations and drawings shall be submitted for approval by
NLCIL.
2.3.1.11 Auxiliary AC Power Supply
2.3.1.11.1 For 110 V DC system battery chargers, lighting, UPS , operation of ventilation
fans, and other system loads, auxiliary power at 415 V 3 Phase 50 HZ power
will be obtained from a PDB in all PCSS with necessary metering.
To meet auxiliary power requirement of the plant such as lighting, water pumps,
battery charger, UPS, switchgear panels, AC & Ventilation etc., the contractor
has to provide auxiliary power supply to each PCSS. Auxiliary supply
arrangements shall be finalized during detailed Engineering in line with
approved design and system requirements.
2.3.1.11.2 The Control and trip power supply for the AC switchgear feeding the winding
transformer as well as the HT circuit breakers in each PCSS shall be derived
from DC supply. If the control and trip power supply is AC then the same shall
be derived from auxiliary power ACDB of the Inverter Room. To ensure
availability of trip supply at all times including when there is a terminal short
circuit, a storage capacitor power pack shall be provided. The sizing of capacitor
shall be such as to ensure adequate charge for at least 3 consecutive shots of
tripping without recharging.

2.3.1.12 Ventilation System


2.3.1.12.1 The Power Conversion Unit of PCSS shall be equipped with appropriate fan
powered ducted ventilation system for effective heat dissipation. The system
shall be designed to draw air from the compartment through filter and pass
through thyristor cubicle and exhaust to outside atmosphere through suitable
ducting arrangement such that the heat generated by the inverter is directly
evacuated without heating other equipment and panels in the compartment. The
battery bank shall also be enclosed and a separate ducted exhaust system shall
be provided to prevent acidic fumes to enter the compartment. Provision shall
be made to allow fresh air from outside to enter the compartment through
suitable filter capable of preventing entry of sand during severe sand storms.
The ventilation system fans shall be mounted on side walls with suitable sand
filter / louver having easy access for cleaning and maintenance. The Battery
bank shall have suitable exhaust system.

35

Page 249 of 328


2.3.1.12.2 Power for the Ventilation system shall be fed from the auxiliary power supply
system and will be automated to run during power generation period only. The
operation, control and status monitoring of ventilation system shall be feasible
from SCADA & EMS through HT kV / 415 V SS RTU. Ventilation system
design, scheme, calculations and drawings shall be submitted for approval by
NLCIL.
2.3.1.13 PCSS Lighting
2.3.1.13.1 LED lamp fixtures shall be indoor type and pre-wired comprising of Lamp(s)
with lamp holder(s), Electronic powering unit(s) and metal reflector(s). The
lamp fitting shall be covered by Glass or Perspex material.. The number of
lighting fixtures should be such that it should give sufficient luminance level for
comfortable operation as per BEE standards. All the switches shall be of
modular type

2.3.1.13.2 Lighting Power System in each PCSS for powering the lights inside PCSS, yard
lights and watch tower lights near each PCSS shall be derived from Auxiliary
power system PDB with necessary controls and cabling. All outdoor lighting
circuits will be controlled through industrial timers provided at LDBs.

2.3.1.13.3 PCSS Lighting and Lighting Power System design, calculations and drawings
shall be submitted for approval by NLCIL.

2.3.1.14 Cables and Wires


2.3.1.14.1 HT Cables
2.3.1.14.1.1 The HT cable used in the work shall be XLPE insulated aluminium conductor
flat steel armoured PVC insulated type rated for HT grade manufactured and
tested to IS: 7098 part 1 and 2- 1985.

2.3.1.14.1.2 The insulation for the conductor shall be of high quality XLPE compound. The
insulation shall be applied through an extrusion process and chemically cross
linked in continuous vulcanizing process. The cable shall be shielded with
metallic tape over the extruded semi-conducting shield. The cores shall be
identified either by colour tape along the insulated core or running a number
tape along the conductor. The cable shall be provided with inner sheath either
with suitable fillers in the interstices and covered with a common tape or an
extruded sheath of required thickness. Armouring over the inner sheath shall be
provided with flat steel strips or steel wire. Outer sheath for the cable shall be
provided with heat resistant PVC compound to IS: 5831. The outer sheath shall
also be extruded over the steel armouring. The colour of the outer sheath shall
be black or orange.

36

Page 250 of 328


2.3.1.14.1.3 The cable shall undergo the following type tests and copy of type test certificate
shall be submitted to NLCIL for approval and it shall be subjected to inspection
and testing in the manufacturer works in the presence of NLCIL engineers.
 Tensile test
 Conductor resistance test
 Physical test for insulation
 Physical Tests For PVC sheath
 Wrapping test
 Test for armour wire/ flat steel strip
 Test for insulation resistance test
 Dielectric power factor test
 High voltage test.
 Routine and acceptance test.

2.3.1.14.1.4 Manufacturer’s identification mark, NLCIL mark along with ISI certification
mark shall be printed on the outer sheath of the cable as stipulated in IS 7098
part1 and part 2 of 1985 as applicable.

2.3.1.14.2 LV Power Cables


2.3.1.14.2.1 All LV power cables used in the work shall be armoured cables unless otherwise
stated and of 1100 V Grade. All cables shall be of XLPE insulated and flat steel
or steel wire armoured cables manufactured to IS: 7098 1988 part I and PVC
insulated and PVC sheathed Armoured cable in conformity with IS: 1554 of
1988 part I. The cables shall be identified as XLPE/SWA or SFA/PVC for
XLPE cables and PVC/SWA/PVC for PVC insulated cables. The insulation
used in manufacturing the LV Power Cables shall be of flame retardant and low
smoke generating material.

2.3.1.14.2.2 The cable used in the work shall be as far as possible of one manufacturer only.
The cables used in the yard shall be delivered to the site as complete coiled
drums/coils with wrapping seals intact. The contractor shall provide
manufacturer’s test certificate and date of manufacture at the time of delivering
the cables to the site. All multi-core cable drums shall be from manufacturer and
unwound cables delivered to site shall not be approved for installation

2.3.1.14.2.2 The cable conductor shall be of electrolytic pure grade Aluminium conforming to
IS 8130 of 1984.

2.3.1.14.2.3 All cables shall be fitted with suitable compression or packing ring to protect the
same from ingress of water and moisture. All glands shall be provided with
locking nut, earth tag and PVC cable shoe/shroud. PVC insulated earth
continuity conductors of appropriate size in conformity with Indian Electricity
Rules shall connect all earth tags to the main earth bars at terminations of cables.

37

Page 251 of 328


The earth tags shall be individually connected to the Earth Terminals and
Looping of conductors through more than one tap is not permitted.

2.3.1.14.2.4 The compression type cable lugs shall be used for terminations. The Crimping
termination of the cables shall be carried out with the help of correct compression
type crimping tool with proper size dies. The compression tools and terminations
materials shall be from a single manufacturer and care shall be taken to adhere to
manufacturer’s recommendations. PVC shoe/ shroud shall be fitted to cable
terminations to prevent dust and moisture entry into terminations.

2.3.1.14.2.5 Only terminal cable joints shall be accepted. No cable joint to join two cable ends
shall be accepted.

2.3.1.14.2.6 All LV cables shall be tested for insulation resistance and continuity test at two
stages.
2.3.1.14.2.6.1 Insulation and continuity test before after laying but before backfilling.
2.3.1.14.2.6.2 Insulation and continuity test after backfilling.

In addition, Insulation resistance test shall be conducted to measure the


insulation resistance between phase conductors and between each phase
conductors and earth. The resistance shall be measured with the help of megger
by applying 1000 volts for duration as specified by relevant standards. Earth
continuity tests to confirm that the cable armouring has been properly bonded to
earth shall be carried out. Phase rotation test shall be conducted to prove that the
cables have been properly connected.

h) Cable shall be laid in the cable trench in PCSS building, routed in cable
trays on the module frames and Combiner box / Array JB support frames and
shall be buried in the yard with suitable protection. The type and specification of
the cable tray used and cable burying scheme shall be submitted for approval by
NLCIL before commencement of work.

2.3.1.14.3 LV Wiring Cables


2.3.1.14.3.1 The low voltage wiring cables shall be PVC insulated single core, colour coded,
stranded Copper conductor rated for 1100 V and conforming to IS 694 and IEC
227.Conductor strand diameter and resistance of the conductor shall be in
conformity with IS: 8130 of 1984. The insulation used in manufacturing the
cable/wires shall be of flame retardant and low smoke generating material.

2.3.1.14.3.2 The stranded conductor shall be made of thin strands of electrolytic copper not
less than 0.25mm. The number of strands shall be suitable for the size of the
cable. However the minimum number of strands shall be as follows:

38

Page 252 of 328


Size of the wire Thickness of the conductor No. of Strands.
1.5 Sq. mm 0.25 or 0.3 mm 32 or 22
2.5 Sq. mm 0.25 or 0.3 mm 50 or 36
4.0 Sq. mm 0.3 mm 56
6.0 Sq. mm 0.3 mm 84

2.3.1.14.3.3 All wiring for connecting various fittings shall be through steel conduits of
approved make. All Tees, Bends etc shall be of standard make. Approval for
materials should be obtained from NLCIL.

2.3.1.14.4 Control, Data, FAS and Communication cabling shall be selected to suit the
system configuration adopted by the contractor and as discussed further in
automation and control system of this specification. The cabling and
accessories for the same shall confirm to relevant IEC/ IS codes and practices.

2.3.1.14.5 Cable terminations shall be made with suitable cable lugs & sockets etc,
crimped properly and passed through brass compression type cable glands at the
entry & exit point of the cubicles. The panel bottoms should be properly sealed
to prevent entry of snakes/lizard etc. inside the panel.

2.3.1.14.6 All cable/wires shall be marked with good quality letter and number ferrules of
proper sizes so that the cables can be identified easily.

2.3.1.14.7 Cable sizing shall be based on voltage drop not exceeding 1% on DC side and
not exceeding 3% on AC side between source and load. Power and Control
cabling and wiring design and calculations with drawings shall be submitted for
approval by NLCIL.

2.3.1.15 Fire Protection and Control System


2.3.1.15.1 Each Power Collection Sub Station shall be provided with adequate number of
smoke / fire detectors forming part of Plant Fire Detection and Alarm System.
Zonal repeater panel shall be provided in PCSS with alarm and visual indication
facilities.
2.3.1.15.2 Suitable capacity portable DCP type fire extinguishers shall be provided in each
compartment of PCSS for fighting electrical fires.
2.3.1.16 Lightning Protection
2.3.1.16.1 The Power Collection Sub Station shall be provided with Lightning protection.
The lightning protection system must be completed prior to start-up of
commissioning activities of the project.

2.3.1.16.2 The Lightning protection system for PCSS shall comprise of lightning
conductors on the roof with spike rods at the highest point above roof. The
system shall be designed as per Indian Standards / IEEE in order to protect the
entire Power Collection Sub Station from Lightning stroke.

39

Page 253 of 328


2.3.1.16.3 The lightning conductor shall be earthed through flats and connected to the
Earth mats as per applicable Indian Standards with earth pits. Each Lightning
Conductor shall be connected to an individual earth pit as per required
Standards including accessories. Lightning protection of Early streamer
Emission (ESE) type as per NFC 17-102 (2011) with minimum protection class
II or higher is also acceptable.

2.3.1.16.4 The contractor shall ensure adequate lightning protection to provide an


acceptable degree of protection (minimum protection class 3) as per IS for the
substation including transformer. If necessary more numbers of Lightning
conductors may be provided. Theoretical lightning design calculations and
drawings shall be submitted for approval by NLCIL.
2.3.1.17 Earthing System
2.3.1.17.1 The earthing for LT power system of PCSS shall be made with an earth mat
connected with number of earth pit around PCSS. Each earth pit shall be
provided with an earth electrode of required diameter and minimum 3 M length
including accessories and masonry enclosure with cast iron cover plate as per IS
3043. The pit around the electrode shall be treated with carbon based earth
enhancement compound or conductive concrete as required as per provisions of
IS 3043.

2.3.1.17.2 The earthing for the power collection substation equipment shall be made as per
provisions of IS. Necessary provision shall be made for bolted isolating joints of
each earthing pit for periodic checking of earth resistance.

2.3.1.17.3 The complete earthing system shall be mechanically & electrically connected to
provide independent return to earth. All equipments shall have two distinct earth
connections.

2.3.1.17.4 For each earth pit, necessary Test Point shall have to be provided.
2.3.1.17.5 In compliance to Rule 33 and 61 of Indian Electricity Rules, 1956 (as amended
up to date), all non-current carrying metal parts shall be earthed with two
separate and distinct earth continuity conductors to an efficient earth electrode.

2.3.1.17.6 The contractor shall ensure adequate Earthing system protection to provide an
acceptable degree of protection as per IS for each PCSS. If necessary more
numbers of Earth pit & conductors may be provided. Theoretical earthing
design calculations with necessary drawings shall be submitted for approval by
NLCIL.
2.3.1.17.7 Earth resistance of the earth pits shall be tested in the presence of the
representative of NLCIL.

2.3.2 33 KV POWER EXPORT SWITCHYARD

40

Page 254 of 328


2.3.2.1 33KV Power Export Switchyard Equipments:
The 33 KV Power Export Switchyard shall be installed as Outdoor switchyard
and the details of 33KV Power Export Switchyard equipments shall be as
follows.
1. Required number of 33KV feeder bays which shall be connected
through UG cables / Transmission lines and Gantries from Solar PV
Power Plants, BESS, Auxiliary system and from Grid take off points
(existing Panther 1 & 2 feeders)
2. 33KV Outdoor switchyard shall be single bus arrangement with
suitable capacity sectionalizing isolator shall be provided within single
bus arrangement
3. One no. 33KV / 415V Auxiliary Power Transformer of required
capacity to feed the Auxiliary system.
The specification for UG cables / Transmission lines, termination,
gantries etc from Grid take off points (existing Panther 1 and 2 feeders)
shall be as per the existing practise and requirements of A & N
Electricity Department and shall be finalized during detailed engineering
and approved by NLCIL.

2.3.2.1 POWER SYSTEM PARAMETER


The power system parameters shall be as follows:

System Parameters LT System 33KV System


Nominal system voltage 415 33 KV
Voltage variation + or – 10%
Number of phases 3 3
System frequency 50Hz +3% / 50Hz +3% /
- 5% - 5%

To suit the Solar


System Earthing Solid Grounding power station 33KV
Power output.
Fault level (3 phase 31.5kA 25 kA
symmetrical)
Short time current rating 31.5kA for 1sec 25kA for 3 sec
(For all current carrying parts)
Power frequency withstand 2.5KV RMS 80KV RMS
voltage
Impulse withstand voltage - 170 peak

2.3.2.3 DRAWINGS AND LAYOUT

41

Page 255 of 328


The following drawings shall be submitted for approval by NLCIL / A & N
Electricity Dept
a) SLD of 33 KV Power Export Switchyard
b) Equipment Layout
c) Section Drawings
The Contractor shall finalize the location of the 33 KV Power Export
Switchyard at suitable site within the project boundary.

The plant equipment and systems shall be designed, manufactured, assembled,


tested, shipped, installed and commissioned according to the applicable codes,
standards and regulations. The design and installation shall be fully in
conformity with the following standards and codes as applicable.
ANSI : American National Standard Institute
ISO : International Organization for Standardization
ASA : American Standard Association
DIN : Deutsche Industrie Normen
EN : European Standards
BIS : Bureau of Indian Standards
IEC : International Electro-technical Commission
IEEE : Institute of Electrical and Electronics Engineers
SI : International System of Units
Nationally or internationally recognized codes and standards which meet or
exceed the qualities specified in the lists above may be used. It is contractor’s
responsibility to ensure the coherence of the codes and standards chosen as
reference.
2.3.2.4 The 33kv feeders shall be routed as per the overall layout. In the Project Control
Room protection relays, metering and control panels, SCADA and EMS and
control desk, Station DC control power system, Auxiliary AC power distribution
system, UPS, lighting power distribution system, Data and voice communication
facilities, Fire detection and alarm panel, interconnecting cabling, earthing and
lightning protection shall be installed.

2.3.2.5 The 33KV Outdoor Switchyard Equipments include Circuit breaker, Current
Transformers, Potential Transformers, Isolators, Surge arresters, Aluminium bus,
ACSR conductors, Clamps and connectors, Columns, beams, poles, Support
Insulators, String insulators, Bus post /Pole Insulators, earth wire, HV/LV power,
control cables, communication cables etc., as per the requirement of CEA rules
and norms and as per A & N Electricity Department requirements.

2.3.2.6 CONDUCTOR
This specification covers design, manufacture, testing before dispatch, supply
and delivery of Aluminum Conductors Steel Reinforced (ACSR) Conductors.
Bus bar conductor shall be ‘Zebra’ ACSR Conductor. Conductor sizing
calculation for 33KV bus bar shall be submitted to the purchaser for establishing

42

Page 256 of 328


the selected sizing of the conductor and any upward revision of conductor sizing
shall be done based on calculation.

APPLICABLE STANDARD FOR CONDUCTORS


The Conductor shall strictly comply with the following Indian Standard
Specification relevant to the conductor.

i. IS : 398- Aluminium Conductors for Overhead


Transmission Purposes (Part-I):Aluminium Stranded Conductors
ii. IS :398- Aluminium Conductors for Overhead
Transmission Purposes (Part-II): Aluminium Conductors Galvanised
steel reinforced

2.3.2.7 SWITCH YARD STRUCTURAL STEEL STRUCTURES

2.3.2.7.1 The structural work shall include design, fabrication and supply of all
switchyard structures, galvanized steel structural work for
equipment supports, towers and lightning masts. All structural
steel shall be of mild steel confirming to the latest edition of the
standard as stated hereunder.
2.3.2.7.2 I.S. 2062 / 226 Specification for structural steel and quality steel.
2.3.2.7.3 I.S. 802. Use of structural steel in over head transmission line.
2.3.2.7.4 I.S 806 Code of practice for use of steel tubes.
2.3.2.7.5 I.S. 808 Specification of rolled steel, channel, beam and angle sections

2.3.2.8 DESIGN REQUIREMENTS:


2.3.2.8 Following general guide lines shall be followed for verification of design:-
2.3.2.8.1 For design of steel structures loads such as dead loads, live loads, wind loads
etc. shall be based on IS 875 Part IV.
2.3.2.8.2 For materials & permissible stresses, IS 802 Part I Section 2 shall be followed in
general.
2.3.2.8.3 Maximum slenderness ratios of leg members, other stressed members and
redundant members for compressive force shall be as per IS
802.
2.3.2.8.4 In order to facilitate inspection & maintenance the structures shall be provided
with step bolts spaced not more than 450 mm apart, staggered
on faces on one leg extending from about 0.5 metre above
ground level to top of the tower. The step bolts shall conform to
IS: 10238.
2.3.2.8.5 All Structures shall be designed for worst condition of dead loads, live loads
wind loads etc. as per IS 875 Seismic forces as per IS: 1893,
loads due to deviation of conductor, loads due to un-balanced

43

Page 257 of 328


vertical and horizontal forces, erection loads, short circuit
forces.

2.3.2.8.6 Substation gantry structures shall be designed for 2 conditions i.e. Normal
condition & Short Circuit Conditions. Factor of safety of 2.0
under Normal conditions & 1.5 under Short Circuit condition
shall be taken.
2.3.2.8.7 Vertical levels of half the span of conductors/ string & the Earth wire on either
side of beam shall be taken for design.
2.3.2.8.9 The contractor shall furnish design, drawing, Bill of Material (BoM) of
structures on award of contract. The design drawing should
clearly indicate sections numbers and sizes of the bolts &
details of typical joints, member wise weights & total weight
of the structure.
2.3.2.8.10 There should be provision of connectivity of beam in the last feeder gantries for
future beam.
2.3.2.8.11 As designing is in the scope of contractor, supply/approval of design & drawing
shall not relieve the contractor from his responsibility for :–
2.3.2.8.11.1 Observing all the required clearances (phase to phase, phase to earth, sectional
clearances & ground clearances) as per tender specifications.
2.3.2.8.11.2 Calculation of force at all the joints/sections and their load carrying capacity
shall be as per details of design requirements given above.

2.3.2.8.12 Minimum thickness of members other than bracings shall be 5 mm and that for
bracings shall be 4 mm.

2.3.2.8.13 Switchyard structures shall be designed in accordance with IS 802-1977.


2.3.2.8.14 All fastening bolts and nuts shall conform to IS 1363/ IS 1367, all washers shall
conform to IS 2016/ IS 6610 and spring washers shall conform to IS 3063.
2.3.2.8.15 Minimum size of bolts for all bolted connections shall be 16 mm dia and
minimum two bolts shall be provided for each member connection in important
structures like towers and gantries. The center to center distance between bolts
shall be a minimum of 2.5 times the nominal diameter of the bolt.

2.3.2.8.16 All foundation bolts shall conform to IS 5624.


2.3.2.8.17 All embedded members shall be installed during concreting in accordance with
construction drawings.
2.3.2.8.18 The steel structure shall not be erected on the foundations until at east 7 days
after placing of the concrete in the foundations. All base plates shall be set level,
in exact position and shall be given full and even bearing grouted into place. All
anchor bolts and base plates shall be set accurately to the grade and alignment
designated on drawing or as directed.
2.3.2.8.19 All galvanized steel shall be handled with care to avoid bending or damage to the
galvanizing. Pieces bent in handling may be used only after they are straightened to

44

Page 258 of 328


the satisfaction of the engineer. Material on which galvanizing has been damaged
shall be repaired as specified.
2.3.2.8.20 All connectors of the steel structures shall be bolted. Welded or riveted joints shall
not be permitted

2.3.2.8.21 The structures may be erected by assembling in sections on the ground and hoisting
successive sections into place, or they may be built up in place by individual
members at the option of the contractor. If erected by assembling in sections, not
less than 50 percent of all bolting in place shall be done on each section before
starting another section.

2.3.2.8.22 All bolts shall be drawn up tight but not to such a degree as to endanger the strength
of the bolt. Wrenches approved by the engineer shall only be used on the work and
the use of any wrench, which may deform the nut or cut or flake galvanizing shall
not be permitted.

2.3.2.8.23 Reasonable amount of drift shall be allowed in assembling but reaming for
correction of mismatched holes shall not be permitted.
2.3.2.8.24 During structural erection inspection shall be carried out at every stage o identify all
loose bolts or other errors in erection are rectified in time.

2.3.2.8.25 All exposed structural steel shall be hot dip galvanized as per IS 4759. The
thickness of zinc coating shall not be less than 610 g/m².

2.3.2.8.26 All bolts, nuts and washers shall be hot dip galvanized as per IS 1367.

2.3.2.8.27 All spring washers shall be electro galvanized as per IS 1573.

2.3.2.8.28 All foundation bolts shall be galvanized as per IS 5624 up to a depth of 300 mm
(minimum) below top of pedestal.

2.3.2.9 CLAMPS AND CONNECTORS


2.3.2.9.1 The material of clamps and connectors shall be Aluminium alloy casting
conforming to designation A6 of IS: 617 for connecting to
equipment terminals and conductors of aluminium. In case the
terminals are of copper, the same clamps/connectors shall be
used with 2mm thick bimetallic.
2.3.2.9.2 The material of clamps and connectors shall be Galvanised mild steel for
connecting to shield wire. Bolts, nuts and plain washers shall be
hot dip galvanised mild steel for sizes M12 and above. For sizes
below M12, they shall be electro-galvanised mild steel. The
spring washers shall be electro-galvanised mild steel. Clamps &
Connectors technical requirements are furnished in 2.3.2.19.

45

Page 259 of 328


2.3.2.10 CIRCUIT BREAKERS
The circuit breakers shall conform in all respects to the highest standards of
engineering, design, workmanship, this specification and the latest revisions of
relevant standards at the time of offer and the purchaser shall have the power to
reject any work or materials, which, in his judgment, is not in full accordance
therewith. Circuit Breakers shall be outdoor type, comprising three identical
single pole units, complete in all respects with all fittings and wiring. The circuit
breakers and accessories shall conform to IEC- 62271-100 or equivalent Indian
Standard.
2.3.2.10.1 DUTY REQUIREMENTS
2.3.2.10.1.1 Circuit breaker shall be totally re-strike free under all duty conditions and shall
be capable of performing their duties without opening
resistor. The circuit breaker shall meet the duty requirement
of any type of fault or fault location and shall be suitable for
line charging and dropping when used on 33 kV effectively
grounded or ungrounded systems and perform make and
break operations as per the stipulated duty cycles
satisfactorily.
2.3.2.10.1.2 The circuit breaker shall be capable for breaking the steady & transient
magnetizing current corresponding to 33 kV transformers. It
shall also be capable of breaking line charging currents as
per IEC- 62271-100 with a voltage factor of 1.4.
2.3.2.10.1.3 The rated transient recovery voltage for terminal fault and short line faults shall
be as per IEC:62271-100.
2.3.2.10.1.4 The circuit breaker shall be reasonably quiet in operation. Noise level in excess
of 140 dB measured at base of the breaker would be
unacceptable. Contractor shall indicate the noise level of
breaker at distance of 50 to 150 m from base of the breaker.
2.3.2.10.1.5 The Contractor may note that total break time of the breaker shall not be
exceeded under any duty conditions specified such as with
the combined variation of the trip coil voltage, pneumatic
pressure etc. While furnishing the proof of the total break
time of complete circuit breaker, the Contractor may
specifically bring out the effect of non-simultaneity between
same pole and poles and show how it is covered in the
guaranteed total break time.
2.3.2.10.1.6 While furnishing particulars regarding the D.C. component of the circuit
breaker, the Contractor shall note that IEC-62271-100 requires that this value
should correspond to the guaranteed minimum opening time under any condition
of operation.
2.3.2.10.1.7 The critical current which gives the longest arc duration at lock out pressure of
extinguishing medium and the duration shall be indicated.

46

Page 260 of 328


2.3.2.10.2 Operating Mechanism – Circuit Breaker of vacuum type shall be with
electrically spring charged mechanism. The operating mechanism
shall be electrically and mechanically operated with anti-pumping
and trip free (as per IEC definition) under every method of closing.
The mechanism of the breaker shall be such that the position of the
breaker is maintained even after the failure in vacuum. The circuit
breaker shall be able to perform the duty cycle without any
interruption. Electrical tripping shall be performed by shunt trip
coil. Provision shall also be made for local electrical control.
“Local / remote” selector switch and close & trip push buttons shall
be provided in the breaker control cabinet. Operating mechanism
and all accessories shall be in control cabinet.
2.3.2.10.3 General Parameters for 33KV Circuit breaker:

Type of circuit breaker Vacuum


Highest system Voltage 36 kV
Rated frequency 50 Hz
Number of poles Three (3)
Type Outdoor
To suit system requirements

Continuous Max. current rating


Rated /Minimum Power Frequency withstand 70KV
voltage
Rated lightning impulse withstand voltage 170KV

Minimum creepage distance 25mm/KV of highest system


voltage
Rated operating duty cycle O-0.3 sec. –CO-3 min.-CO

Rated line charging/breaking current (Voltage As per IEC


factor 1.4)
Control Circuit Voltage 110V DC
Reclosing Three phase high speed auto
reclosing
Maximum fault level 25kA (rms) for 3 sec.
Total closing time Not more than 150msec.
Auxiliary contact As required plus 4NO and 4NC
contacts per pole as spare
Noise level Maximum 140db at 50M distance
from base of circuit breaker.

The VCB shall be suitable for one reclosing


followed by one delayed reclosing and lock
out.
Minimum clearances:-
(a)Between phases 360 mm
47

Page 261 of 328


(b)Between live parts & ground 3700 mm
(C) Creepage distance 900 mm or more
IR value live part to earth 50 Ohm

2.3.2.11 ISOLATORS
2.3.2.11.1 The isolators and accessories shall conform in general to IEC 62271-102 (or
equivalent Indian standard) except to the extent explicitly
modified in specification.
2.3.2.11.2 Earth switches shall be provided on isolators wherever called for.

2.3.2.11.3 General Parameters

Manually operated Double


break, upright mounting with
the movement of the blade in a
Operating mechanism of Isolator and earth horizontal plane suitable for
Switch outdoor installation
Nominal system voltage 33KV
Highest system voltage 36KV
Type Outdoor
To suit system requirements

Rated Normal Current

Rated short time current of isolator and 25kA (rms) for 3 sec
earth switch
Rated dynamic short time withstand current
of isolator and earth switch 62.5kA (peak)
Impulse withstand voltage with 1.2/50 170kVp to earth 195 kVp across
micro sec. wave isolating distance
One minute Power frequency withstand 70 kV (rms) to earth & 80kV (rms)
Voltage across isolating distance
Temperature rise As per Table-IV of IS: 9921
Rated mechanical terminal load As per 62271-102
Safe duration of over load
150 % of rated current 5 minutes
120% of rated current 30 minutes
Creepage distance (Total) 900 mm
Temperature rise Max.Temp deg.C
a. Copper contacts in air
Silver faced Copper 105
Bare copper 75
b. Terminal of isolator to be connected to
Silver faced copper 105
Bare copper 90

48

Page 262 of 328


2.3.2.11.4 Isolator shall be gang operated for main blades and earth switches. The
operation of the three poles shall be well synchronized and
interlocked.
2.3.2.11.5 The design of linkages and gears shall be such so as to allow one man to operate
the handle with ease for isolator and earth switch.

2.3.2.11.6 They shall be constructed such that they do not open under influence of short
circuit current and wind pressure together. The earth switches
wherever provided shall be constructional interlocked so that the
earth switches can be operated only when the isolator is open
and vice-versa.

2.3.2.11.7 In addition to the constructional interlock, isolator and earth switches shall have
provision to prevent their electrical and manual operation unless
the associated and other interlocking conditions are met.

2.3.2.12 INSTRUMENT TRANSFORMERS


2.3.2.12.1 General Requirement
2.3.2.12 .1.1 The instrument transformers i.e. current and voltage transformers shall be
single phase transformer units and shall be supplied with a common
marshaling box for a set of three single phase units.
2.3.2.12.1.2 The tank as well as top metallic shall be hot dip galvanised or painted Grey
color as per RAL 9002.

2.3.2.12.1.3 The instrument transformers shall be oil filled hermetically sealed units. The
instrument transformers shall be provided with filling and drain plugs.
2.3.2.12.1.4 Polarity marks shall indelibly be marked on each instrument transformer and at
the lead terminals at the associated terminal block.

2.3.2.12.1.5 The insulators shall have cantilever strength of more than 500 kg.
2.3.2.12.1.6 MARSHALLING BOX
The wiring diagram for the interconnection of three phase instrument
transformer shall be pasted inside the box in such a manner so that it is visible
and it does not deteriorate with time. Terminal blocks in the marshaling box
shall have facility for star/delta formation, short circuiting and grounding of
secondary terminals. The box shall have enough terminals to wire all control
circuits plus 20 spare terminals.

2.3.2.12.2 CURRENT TRANSFORMERS (CTs)


2.3.2.12.2.1 The CTs shall have single primary of either ring type or hair pin type or bar type.
In case of "Bar Primary" inverted type CTs, the following requirements shall be
met.
2.3.2.12.2.2 The secondaries shall be totally encased in metallic shielding providing a uniform
equi- potential surface for even electric field distribution.

49

Page 263 of 328


2.3.2.12.2.3 Different ratios shall be achieved by secondary taps only, and primary
reconnections shall not be accepted.
2.3.2.12.2.4The guaranteed burdens and accuracy class are to be intended as simultaneous for
all cores.
2.3.2.12.2.5 The instrument security factor at all ratios shall be less than five (5) for metering
core. If any auxiliary CT/reactor is used, then all parameters specified shall be
met treating auxiliary CTs/reactors as integral part of CT. The auxiliary
CT/reactor shall preferably be in-built construction of the CT. In case it is
separate, it shall be mounted in secondary terminal box.
2.3.2.12.2.6 The secondary terminals shall be terminated on stud type suitable no’s of non-
disconnecting and disconnecting terminal blocks inside the terminal box of
degree of protection IP:55 at the bottom of CT.
2.3.2.12.2.7 The CT shall have provision for measurement of capacitance and tan delta as
erected at site.

2.3.2.12.3 PARAMETERS FOR CURRENT TRANSFORMERS


GENERAL PARAMETERS

Highest system Voltage(Um) 36 kV


Rated frequency 50 Hz
System neutral earthing effective earthed
Installation Outdoor
Rated short time thermal current 25 kA for 1 sec
Rated dynamic current 63 kA (Peak)
Rated min power frequency withstand 70kV
voltage (rms value)
Rated lightning impulse withstand voltage 170kV
(peak value)
Partial discharge level 10 pico Coulombs max
Minimum Creepage distance 25 mm/kV of highest system voltage
Temperature rise As per IEC 60044
Type of insulation Class A
Number of cores As per requirement
Number of terminals in marshaling box All terminals of control circuits wired
up to marshaling box plus minimum 20
terminals spare

2.3.2.12.4 VOLTAGE TRANSFORMERS (VTs)


General Requirement of Voltage Transformer
2.3.2.12.4.1 Voltage transformers shall be electro-magnetic (EMU) type and shall comprise
of compensating reactor, intermediate transformer, and
protective and damping devices. The oil level indicator of
EMU with danger level marking shall be clearly visible to
maintenance personnel standing on ground.

50

Page 264 of 328


2.3.2.12.4.2 The secondaries shall be protected by HRC cartridge type fuses for all windings.
In addition fuses shall also be provided for protection and
metering windings for connection to fuse monitoring
scheme. The secondary terminals shall be terminated on
stud type non-disconnecting terminal blocks via the fuse
inside the terminal box of degree of protection IP55. The
access to secondary terminals shall be without the danger of
access to high voltage circuit.
2.3.2.12.4.3 The accuracy of metering core shall be maintained through the entire burden
range up to 50VA on all three windings without any
adjustments during operations.

2.3.2.12.5 PARAMETERS FOR VOLTAGE TRANSFORMERS

Highest System Voltage(Um) 36 kV


System neutral earthing effective earthed
Installation Outdoor
System Fault level 25 kA
Rated min Power frequency withstand voltage 70kV
(rms)
Rated lightning impulse withstand voltage (peak 170kV
value)
Standard reference range of Frequencies for 96% to 102% for protection and99%
which the accuracy are valid to 101% for measurement

Rated voltage factor 1.2 continuous & 1.5 for 30 sec


Class of Accuracy 0.2
Stray capacitance and stray Conductance of LV As per IEC:358
terminal Over Entire carrier frequency Range

One Minute Power frequency Withstand voltage 2 kV rms


for secondary winding

Temp. rise over an ambient Temp. of 500C As per IEC 60044


Number of terminals in control spare. All terminals of control circuits
wired Cabinet up to marshaling box
Partial discharge level 10 pico Coulombs max.

2.3.2.13 SURGE ARRESTOR


General Requirement
2.3.2.13.1 The surge arrestors (SAs) shall conform in general to IEC 60099-4 or IS:
3070 except to the extent modified in the specification. Arresters shall be of
hermetically sealed units, self-supporting construction, suitable for mounting on

51

Page 265 of 328


lattice type support structures. Contractor shall furnish the technical particulars of
Surge arrester.
2.3.2.13.2 The SAs shall be of heavy duty station class and gapless Metal Oxide type without
any series or shunt gaps. The SAs shall be capable of discharging over-voltages
occurring during switching of unloaded transformers, and long lines.
2.3.2.13.3 Arrestors shall be complete with insulating base for mounting on structure. Self-
contained discharge counters, suitably enclosed for outdoor use and requiring no
auxiliary or battery supply for operation shall be provided for each single pole unit
with necessary connection. Suitable leakage current meters should also be supplied
within the same enclosure. The reading of millimeter and counters shall be visible
through an inspection glass panel
2.3.2.13.4 The surge arrestors shall conform to type tests and shall be subjected to routine and
acceptance tests in accordance with IEC-60099-4
2.3.2.13.5 Technical Requirement for Surge Arrestor
Rated System Voltage 36Kv
Rated Arrester Voltage 30 kV
Nominal discharge current 10 kA of 8/20 micro-sec wave
5 kilo joule/kV(referred to rated arrestor
voltage corresponding to minimum
Minimum discharge capability discharge characteristics)
Maximum continuous operating 24 kV rms
Max. residual voltage (1 kA) 70 kVp
Max. residual voltage at 10 kA nominal
discharge current(8/20 micro sec wave) 85 kVp
Max. switching impulse residual Voltage at
500A peak 70 kVp
Max. steep current residual Voltage 93 kVp at 10kA
High current short duration test Value (4/10
micro-sec-wave) 100 kAp
Current for pressure relief test 25kA rms
One minute power frequency withstand
voltage of arrestor housing (dry and wet) 70 kV (rms)
Impulse withstand voltage of arrestor housing
with 1.2/50 micro sec. Wave 170 kV (Peak)
Radio interference voltage at156kV Not more than 1000 micro volt
Partial discharge at 1.05 MCOV(continuous
operating voltage) Not more than 50 p.c

2.3.2.14 TYPE TEST REQUIREMENTS FOR ALL 33KV SWITCHYARD


EQUIPMENTS

2.3.2.14.1 Type certificates and reports as per relevant standards shall be submitted for
NLCIL approval for Current Transformers, Voltage Transformers Breakers,
Isolators and Surge arrestors. These reports should be for the test conducted on
the equipment similar to those proposed to be supplied under this contract.

52

Page 266 of 328


2.3.2.14.2 All acceptance and routine tests as per relevant standards shall be carried out.

2.3.2.15 LIGHTNING PROTECTION SYSTEM – 33 KV POWER EXPORT


SWITCHYARD
2.3.2.15.1 The outdoor switchyard shall be provided with lightning protection to protect
the outdoor switchgear equipment and transformer against lightning. The
lightning protection system shall be designed based on IS 2319 code of
practice for protection of buildings and allied structures against lightning.

2.3.2.15.2 The lightning protection for switch yard shall comprise of vertical air
terminations mounted on steel tower. The system shall be designed as per
Indian Standards / IEEE in order to protect the entire switch yard and 33 KV
POWER EXPORT SWITCHYARD from lightning stroke. The towers shall
be interconnected using shield wire. The tower shall also be used for fixing
light fittings for illumination of switchyard.

2.3.2.15.3 The lightning conductor shall be earthed through flats and connected to the
Earth mats as per applicable Indian Standards with earth pits. Each
Lightning Conductor shall be connected to an individual earth pit as per
required Standards including accessories.

2.3.2.15.4 Theoretical lightning design calculations and drawings shall be submitted for
approval by NLCIL. The detailed requirement for lightning protection is
furnished under lightning and earthing section of this technical specification

2.3.2.16 33 KV POWER EXPORT SWITCHYARD EARTHING


2.3.2.16.1 The 33 KV POWER EXPORT SWITCHYARD earthing system shall be designed
to cover the system neutral earthing and earthing of non-current carrying metallic
parts of equipment, cable trays etc. The design shall ensure that the touch potential
and ground potential rise are within limits in accordance with the requirements
stipulated in IEEE 80-Guide for Safety in AC Substation Grounding. The earthing
system shall also conform to IS 3043.

2.3.2.16.2 The earthing for LT power system of 33 KV POWER EXPORT SWITCHYARD


shall be laid with an earth mat connected with number of earth pit around 33 KV
POWER EXPORT SWITCHYARD. Each earth pit shall be provided with an earth
electrode of low carbon steel rod with molecularly bonded copper on the outer
surface of required diameter and minimum 3 M length including accessories and
masonry enclosure with cover plate having. The pit around the electrode shall be
treated with carbon based earth enhancement compound or conductive concrete as
required as per provisions of IS 3043.

53

Page 267 of 328


2.3.2.16.3 The earthing for the power export substation equipment shall be made as per
provisions of IS. Necessary provision shall be made for bolted isolating joints of
each earthing pit for periodic checking of earth resistance.
2.3.2.16.4 The complete earthing system shall be mechanically & electrically connected to
provide independent return to earth. All equipment shall have two distinct earth
connections.

2.3.2.16.5 For each earth pit, necessary Test Point shall have to be provided.

2.3.2.16.6 In compliance to Rule 33 and 61 of Indian Electricity Rules, 1956 (as amended up
to date), all non-current carrying metal parts shall be earthed with two separate and
distinct earth continuity conductors to an efficient earth electrode.

2.3.2.16.7 The switch yard earthing shall consist of a mat buried in ground to cover the entire
substation yard area with spacing between conductors as per design based on IEEE
80. The contractor shall ensure adequate Earthing system protection to provide an
acceptable degree of protection as per IS / IEEE 80 for the switch yard. Individual
earth pits shall be used for transformer neutral earthing and earthing of lightning
arrestors. All the earth pits shall also be connected to the earth mat. If necessary
more numbers of Earth pit & conductors may be provided. Theoretical earthing
design calculations with necessary drawings shall be submitted for approval by
NLCIL.

2.3.2.16.8 Earth resistance of the earth pits shall be tested in the presence of the representative
of NLCIL.

2.3.2.16.9 The earth mat shall be designed considering the earth fault current and soil
resistivity value at site. For the purpose of estimating requirement of earth
conductor, the earth fault current on 33 KV side shall be taken as 31.5 kA for 1
second. The soil resistivity values shall be measured by the contractor at site during
detailing and the system shall be designed accordingly.

2.3.2.16.10 The earth mat shall consist of GI flats of adequate size for the fault current
magnitude. The conductor sizing shall also consider adequate allowance for
corrosion for a period of 25 years. To estimate the touch and step potentials, shock
duration of 0.5 seconds shall be considered. The risers and equipment connections
shall be using a minimum conductor size of 50x6& 75x12 mm galvanized steel
strip.

2.3.2.16.11 Each equipment in switch yard shall have a minimum of two earth connections
to the earth mat. The earth mat shall be buried at a depth of 600 mm from the
finished ground level. All structures in the switchyard shall also be bonded to the
earth mat. The installation of the earth mat shall be coordinated with the equipment
foundations and cable trench construction so as to avoid interference. All cable

54

Page 268 of 328


trays are to be earthed by 50x 6 mm GI flats at regular interval of 25 meters to the
earthing grid or nearest earthing pit.
2.3.2.16.12 The switchyard earthing shall also include earthing of the substation fence at
regular intervals. In addition the gate shall be earthed using flexible copper tape.

2.3.2.16.13 The detailed requirement for earthing scheme is mentioned under the section
‘Earthing and Lightning protection of Power evacuation scheme’.

2.3.2.17 SWITCH YARD STRUCTURAL STEEL WORKS

2.3.2.17.1 The structural work shall include design, fabrication and supply of all switchyard
structures, galvanized steel structural work for equipment supports, towers and
lightning masts. All structural steel shall be of mild steel confirming to IS 2062.

2.3.2.17.2 Minimum thickness of members other than bracings shall be 5 mm and that for
bracings shall be 4 mm.

2.3.2.17.3 Switchyard structures shall be designed in accordance with IS 802-1977.

2.3.2.17.4 All fastening bolts and nuts shall conform to IS 1363/ IS 1367, all washers shall
conform to IS 2016/ IS 6610 and spring washers shall conform to IS 3063.

2.3.2.17.5 Minimum size of bolts for all bolted connections shall be 16 mm dia and minimum
two bolts shall be provided for each member connection in important structures like
towers and gantries. The center to center distance between bolts shall be a minimum
of 2.5 times the nominal diameter of the bolt.

2.3.2.17.6 All foundation bolts shall conform to IS 5624.

2.3.2.17.7 All embedded members shall be installed during concreting in accordance with
construction drawings.

2.3.2.17.8 The steel structure shall not be erected on the foundations until at least 7 days after
placing of the concrete in the foundations. All base plates shall be set level, in exact
position and shall be given full and even bearing grouted into place. All anchor
bolts and base plates shall be set accurately to the grade and alignment designated
on drawing or as directed.

2.3.2.17.9 All galvanized steel shall be handled with care to avoid bending or damage to the
galvanizing. Pieces bent in handling may be used only after they are straightened to
the satisfaction of the engineer. Material on which galvanizing has been damaged
shall be repaired as specified.

55

Page 269 of 328


2.3.2.17.10 All connectors of the steel structures shall be bolted. Welded or riveted joints
shall not be permitted.

2.3.2.17.11 The structures may be erected by assembling in sections on the ground and
hoisting successive sections into place, or they may be built up in place by
individual members at the option of the contractor. If erected by assembling in
sections, not less than 50 percent of all bolting in place shall be done on each
section before starting another section.

All bolts shall be drawn up tight but not to such a degree as to endanger the strength
of the bolt. Wrenches approved by the engineer shall only be used on the work and
the use of any wrench, which may deform the nut or cut or flake galvanizing shall
not be permitted.

2.3.2.17.12 Reasonable amount of drift shall be allowed in assembling but reaming for
correction of mismatched holes shall not be permitted.

2.3.2.17.13 During structural erection inspection shall be carried out at every stage to
identify all loose bolts or other errors in erection are rectified in time.

2.3.2.17.14 All exposed structural steel shall be hot dip galvanized as per IS 4759. The
thickness of zinc coating shall not be less than 610 g/m².

2.3.2.17.15 All bolts, nuts and washers shall be hot dip galvanized as per IS 1367.

2.3.2.17.16 All spring washers shall be electro galvanized as per IS 1573.

2.3.2.17.17 All foundation bolts shall be galvanized as per IS 5624 up to a depth of 300 mm
(minimum) below top of pedestal.

2.3.2.18 INSULATORS AND FITTINGS


INSULATORS AND FITTINGS This specification covers post insulators and
insulators and fittings for 33 KV POWER EXPORT SWITCHYARD

2.3.2.18.1 CODES AND STANDARDS


2.3.2.18.1.1 The design, material selection, constructional features and testing of insulators and
fittings shall comply with all currently applicable statutes, regulations and safety
codes in the locality where these are proposed to be used.

56

Page 270 of 328


2.3.2.18.1.2 Insulators and fittings shall conform to the latest editions of standards specified
in enclosed Data Sheet - A. In case of withdrawal/revision of any of the
stipulated standards by issuing authorities prior to commencement of
fabrication, mutual agreement with Purchaser shall be reached for
compliance with applicable standard.

2.3.2.18.2 GENERAL REQUIREMENTS


2.3.2.18.2.1 Supporting insulators of circuit breakers, disconnecting switches and
lightning arrestors, bushing insulators for instrument transformers as well
as all post type insulators and string insulator assemblies for supporting
bus-work shall be made of best quality porcelain and shall be brown
glazed.

2.3.2.18.2.2 All insulators shall be suitable for heavily polluted atmosphere and shall be able
to withstand the duty requirements of the associated equipment.

2.3.2.18.2.3 When operating under normal rated voltage, there shall be no electric discharge
between the conductors and bushing which would cause corrosion or
injury to conductors, insulators or supports by the formation of substances
produced by chemical action.

2.3.2.18.2.4 No radio interference shall be caused by the insulators/bushings when


operating at the normal rated voltage.

2.3.2.18.2.5 All iron parts shall be hot dip galvanised and all joints shall be airtight. All
current carrying contact surfaces shall be silver plated.
2.3.2.18.2.6 The strain insulators shall be of ball and socket type. The socket shall be
malleable cast iron and the pin shall be of steel. After machining is completed,
the ball and sockets shall be hot dip galavanised.
2.3.2.18.2.7 Individual units of each strings shall be identical and interchangeable and shall
be suitable for forming either suspension or strain strings and shall be so
designed as to prevent formation of any defect due to expansion or contraction
in porcelain or metal fittings.

2.3.2.18.3 TESTING
All routine tests and acceptance tests shall be carried out as per the latest
applicable standards.
Type Tests : If type test report of equipment of same design is not available the
test shall also be carried out on equipment as per relevant standards.

2.3.2.18.4 MARKING AND PACKING


Marking on insulators and fittings and packing of fittings shall be as per
guidelines covered in applicable standards
2.3.2.19 Clamps and Connectors

57

Page 271 of 328


2.3.2.19.1 Clamps and Connectors
This specification covers requirements of Bus bars, clamps and connectors for
bus bars, transmission lines, Tubular Bus conductors, cable box terminals,
equipment terminals and support insulators.

2.3.2.19.2 CODES AND STANDARDS


The design, materials, construction, manufacture, inspection and testing of the
clamps and connectors shall comply with all currently applicable statutes,
regulations and safety codes in the locality where the Equipment shall be
installed. The equipment shall also conform to the latest applicable standards.
Nothing in this specification shall be construed to relieve the VENDOR of this
responsibility. The equipment shall conform to latest relevant standards.
2.3.2.19.3 CASTINGS
All castings shall be free from blow holes, surface blisters, cracks and cavities.

2.3.2.19.4 CONSTRUCTIONAL DETAILS


All sharp edges and corners shall be blurred and rounded-off.
No part of a clamp or connector shall be less than 10 mm thick.
Bolts and nuts shall have hexagonal heads and threads as per applicable
standards.
For bimetallic clamps or connectors, loose bimetallic strips or washers shall be
provided.
Flexible connectors, braids or laminated straps shall be made from tinned
copper sheets or aluminium laminates depending on the clamp.
Size of the terminal/conductor for which the clamp/connector is suitable, shall
be embossed/punched (i.e. indelibly marked) on each component of the
clamp/connector, except on the hardware.

Clamp shall be designed to carry the same current as the conductor as specified
in Data Sheet-A and the temperature rise shall be equal or less than that of the
conductor at the specified ambient temperature. The rated current for which the
clamp/conductor is designed with respect to the specified reference ambient
temperature, shall also be indelibly marked on each component of the
clamp/connector, except on the hardware.

Connector design shall permit easy checking to ensure that the connector is
installed correctly.

For parallel connector, power tied wedge pressure connectors (latest state of the
art technology) shall be used instead of conventional parallel groove clamp.

Bolts shall have M10 or M12 thread. Tightening torque shall be 45 Nm and 80
Nm for M10 and M12 respectively.

58

Page 272 of 328


Clamps shall be designed such that the support insulators are not subjected to
extra stresses by butt torsional action from the tubular conductor during
vibration, wind, ice load and short circuits.

2.3.2.19.5 Contact Paste


Contact paste shall be used on all contact surfaces during installation of non-
tensile, rigid and flexible connectors, both clamped and crimped types. Contact
paste shall effectively prevent corrosion occurring on the contact surfaces
between aluminium and copper throughout the service period.

Contact paste shall be easy to apply to the contact surfaces within temperature
range – 300o to +50oC, shall have good adherence and be chemically in relation
to both aluminium and copper conductors and other materials included in the
connector.

Contact paste shall not be poisonous or inflammable. Contact paste shall not
decay, evaporate, run away, harden or crack under the service conditions
described in the specification.
The clamps shall be light in weight and easy to handle. Suspension clamp shall
have ease of oscillation around horizontal axis and moment of inertia enabling it
to follow freely the movement of the conductor. The clamps shall have low
effective power loss.

The natural frequency of mechanical vibration of clamps shall be different from


that of the conductor, to avoid any effect of resonance. The clamp shall be
designed, manufactured and finished to give it a suitable shape without sharp
angles at the ends and radii of curvature so as to avoid any possibility of
hammering between the clamp and conductor due to vibrations.

Strain clamps for GI shield wires shall be made from hot dip galvanised
malleable cast iron, free from blow holes, cracks, etc.

Connectors used for copper to ACSR conductor connections shall be aluminium


alloy clamps with necessary bimetallic strips.

Clamps shall be corona free.

Where suspension clamps / strain clamps / dead-end-assemblies / bus post


clamps are procured separately, the VENDOR shall co-operate with the supplier
of clamps / dead-end assemblies to ensure that the same fits properly with the
hardware fitting supplied by him.

2.3.2.19.6 Spacers

59

Page 273 of 328


No magnetic material should be used in the fabrication of the spacers except for
the GI bolts and nuts.

Correct separation of conductors, as required shall be maintained by the spacer


without wear even if no lubrication or maintenance is carried out.

Spacer design shall take care of ease of fixing and removing during installation
and maintenance. Spacer shall have ultimate compression strength.

2.3.2.19.7 Grading / Corona Rings


Grading / corona rings shall be of such design that when added to suspension or
strain strings, the flashover values of complete insulator string shall not be
reduced below the following percentages of corresponding flashover values of
these assemblies without grading / corona rings.
i) Dry power frequency : 94%
ii) Wet power frequency : 100%
iii) 1.2 / .50 sec. impulse : 96% positive and negative
The grading / corona rings shall be of GI pipe / aluminium tube having outside
diameter as required for corona control and minimum wall thickness of 2.5 mm.
The brackets for supporting the rings shall be galvanised mild steel.

2.3.2.19.8 DESIGN
Bolted type of connector shall be designed to withstand normal assembly
stresses without suffering permanent deformation.
Connectors shall be designed to withstand stresses in service due to wind, ice,
vibrations, fluctuations in temperature and short-circuits, without suffering
permanent deformation or breakages. In addition, connectors for bundled
stranded conductors shall withstand short-circuit inertia forces.
Connector design shall be such that tensile bending and wrenching stresses
transmitted to the equipment terminals are minimum possible. Connectors shall
permit axial movement of the tubular conductor.
Parts of current carrying connectors which are in direct contact with the
conductor shall be designed so that dangerous galvanic corrosion in the contact
surface does not occur.
Flexible connectors shall be designed so that electric current during both normal
load and short circuiting is not transferred through mechanical support.
Current carrying connectors shall be designed so that hysteresis and eddy
current losses are small.

The shape of current carrying connectors shall be such that water collection is
eliminated. If this is not possible, the connector shall be supplied with drainage
holes of at least 6 mm.

60

Page 274 of 328


Tubes in flexible connector shall not rattle.

Tubes in flexible connectors shall be prevented from falling out of connector.

The bus post clamps shall be so dimensioned that clashing between the copper
tube and clamp does not occur during short circuit.
The bus post clamps shall be so dimensioned that it is not notably heated by
hysteresis and eddy current losses.

The bus support clamp shall with respect to partial discharge be designed with a
reliable electric contact between the copper tube, all parts in the clamp and
insulator fixing.

Bus support clamp intended for flexible current carrying conductors shall for
each copper tube allow a total axial movement of at least 60 mm.

Flexible conducting connectors between copper tubes shall be designed and


constructed in such a way that the copper tube movements resulting from
temperature changes and vibrations do not result in fatigue fracture.

2.3.2.20 BUS BARS


The bus bar for the 33KV bus shall be ACSR ‘Zebra’ conductor. Conductor
sizing calculation shall be submitted for the adequacy of conductor sizing to
NLCIL for approval.
Aluminium strands of ACSR conductor shall be hard drawn from 99.5% pure
electrolyte aluminium rods with 60% IACS conductivity. The VENDOR shall
specify the guaranteed minimum and average values of conductivity.
Chemical composition of the material shall comply with the requirements of
relevant Standards.

The surface of conductor shall be clean and dry and free from any excess grease
that may be used in its fabrication. The surface strands shall be smooth and free
from burrs and other projections which may be cause for increasing corona
losses when the conductor is used on extra high voltage lines.

The steel wire strands of ACSR conductor and steel conductor shall be hot dip
galvanised. Zinc coating shall be evenly and uniformly coated complying with
relevant standards
The steel core and the inner layer of aluminium wires, (where more than one
aluminium layer exists), shall be protected with a special grease in order to
provide additional protection against corrosion due to saline pollution. The

61

Page 275 of 328


grease shall fill the whole space between wires within circumscribed cylinder at
inner aluminium layer or at steel core, if the conductor has only one aluminium
layer.
The grease shall be chemically neutral with respect to aluminium, zinc and steel.
It shall withstand weather conditions given under (Project Data) and permanent
temperature of 85 deg C without alteration of its properties

2.3.2.20.1 TUBULAR BUS CONDUCTOR


Tubular Bus conductor wherever required may be provided and the same shall
be finalized during detailed engineering.

2.3.2.20.2 Material
Tube material shall be aluminium and shall comply with properties as specified
in Data Sheet A.
2.3.2.20.3 Constructional Features

For the inside diameter of the tube there shall be no plus tolerance and for the
outside diameter and thickness there shall be no minus tolerance.

Corona bells shall be provided wherever the bus extends beyond the clamps on
free ends for sealing the ends of the tubular conductor against rain and moisture
and to reduce the electrostatic discharge loss at the end points. There shall be a
small drain hole at the end of each tube.

2.3.2.20.4 Sleeves for straight through joints


Length of the jointing sleeves shall be six times the nominal size (diameter) of
the tube and the outer diameter of sleeve shall be suitable to fit snugly in the
main tube.

2.3.2.20.5 TESTS
All routine tests shall be carried out as per the latest applicable standards.

If Type tests reports of the components of same material are not available the
test shall be carried out as per relevant standards.

2.3.2.21 Protection Relays


2.3.2.21.1 Protective relays shall be microprocessor based numeric type conforming to IEC
60255, IEC 60259, IEC 60068, IEC 60801, IEC 60521 and IEC-CISPR22
standards. The protective relays scheme shall be designed to provide maximum
discrimination between faulty and healthy circuits and shall remain stable during
transient and switching disturbances in the system.

62

Page 276 of 328


2.3.2.21.2 The relay preferably shall be of withdrawable type to facilitate easy replacement
and testing. The withdraw-able module shall have facility for shorting CT
terminals when the relay is withdrawn. In case of non-withdrawable type,
means of isolating the relay circuitry shall be provided for testing purposes.
2.3.2.21.3 Alphanumeric display LCD screen shall be utilized as man machine interface
(MI) built onto the relays. The MMI shall be provided to visualize or display
parameter settings and to manually interrogate the relay in the case of relay
operation or tripping shall be made available on the screen.

2.3.2.21.4 Modbus protocol Communication ports shall be provided for remote connection
for control and indication. Relay and Control Panel shall interface with plant
SCADA and Energy Management system through RTU

2.3.2.21.5 The relays shall have indicators, such as LED indications, that show clearly and
unambiguously that the relay had operated for various functions. A
minimum of 3 indicators shall be provided for protection functions. The
indications shall be maintained until reset by the operator. Facilities to test
the indicators shall be available to indicate a healthy auxiliary power
supply. Suitable labeling shall be provided for each indicator.

2.3.2.21.6 The relay auxiliary supply shall be supplied from 110V DC system. The
functionality of the relay shall not be affected by the variation of DC
supply. The power supply module shall tolerate a variation of plus/ minus
30 % of the station DC supply and shall also withstand higher DC voltage
during rapid charging of station batteries. The power supply card or
module shall also be able to remain stable when transient dips in the DC
voltage occur.

2.3.2.21.6.1 The numerical relay shall be able to retain in a non-volatile memory all its latest
logics, algorithm, settings, registered values, events, oscillography and
operation indications in the event of DC power failure. The relay shall
also be able to continuously keep track of its internal clock (time and
date) in the event of DC power failure.

2.3.2.21.6.2 On-line changing of relay shall not affect the operational value until confirmed.
The relay shall have a minimum of two protection function group
settings and be able to be interchanged between the group settings. Any
changes of relay settings shall be authentically verified. To maintain the
level of security for relay operational setting, configurations, access to
these functions shall only be permitted through a system of passwords.
2.3.2.21.6.3 The relay shall be provided with necessary interrogation and fault analysis
software. The software shall be considered part of the relay and deemed
to be provided as part of the contract. Any hardware and accessories that

63

Page 277 of 328


is required to enable interfacing between relay and laptop shall also be
provided.

2.3.2.21.6.4 An internal watchdog or self-supervision functions shall be provided. In the


event of an internal relay failure, the relay shall trigger an alarm or
indication and identity any internal relay errors and failures. Self-
supervision separate alarm/trip contact shall be provided. The self-
supervision functions shall not affect the performance of any protection
functions.

2.3.2.21.7 Trip Relays and Auxiliary Relays


2.3.2.21.7.1 Auxiliary relays and High speed Trip relays shall be suitable for operation on
DC system in the range of 80% to 120% of the nominal 110 volts DC
for PSS. The relays shall be stable and not be affected by a slow decay,
surges, dips, ripples, spikes and chattering of the DC supply. High speed
trip relays shall utilize trip supply of the associated circuit breaker from
dedicated protection supply circuit. This DC supply shall be monitored
continuously and an alarm provided in event of failure.

2.3.2.21.7.2 Trip & Auxiliary relays shall be housed in dust and moisture proof cases and
shall be arranged so that adjustments, testing and replacement can be
effected with the minimum of time and labour.

2.3.2.21.7.3 Trip & Auxiliary relays shall be provided with LCD/ LED or flag indicators,
phase labeled/coloured, where applicable. Where two or more phase
elements or functions are included in one case, separate indicators shall
be provided for each element or functions.

2.3.2.21.7.4 Resetting facilities shall be made available, either electrically or manually,


without opening the front cover of the relay. All indicators shall be
clearly visible without opening of relay front cover or relay panel door.
Relays, with provision for manual operation from outside the case, other
than for resetting, shall not be accepted.

2.3.2.21.7.5 Relay contacts shall be suitably rated for tripping, control and indication
purposes. The contacts shall be suitable for making and breaking the
maximum currents, which they may be required to control in normal
service. Separate and sufficient number of contacts shall be provided for
tripping, control and alarm functions. Separate contacts shall be
provided for alarm tripping functions. Relay contacts shall make firmly
without bounce and the whole of the relay mechanisms shall be as far as
possible unaffected by vibration or external magnetic fields.
2.3.2.21.8 Instruments and Meters

64

Page 278 of 328


2.3.2.21.8.1 All instruments and meters shall be of robust design, vibration proof and
suitable for flush mounting on Control & Mimic panel /Relay panel.
2.3.2.21.8.2 Multifunction meters for all 33KV feeders: All Electrical parameters
shall be shown in the Multifunction digital meters for all 33kv feeders. All phase
current, voltage, Export /Import KW, KVAR, KWhr, Frequency, P.F, etc., shall
be available in the Multi-function meters The multifunction meters of all 33kV
feeders shall be suitably communicated to SCADA scheme for monitoring
scheme. The multifunction meter shall have accuracy class of 0.2.
2.3.2.21.8.3 Metering Station: HT outgoing feeders shall be provided in the Power
Evacuation Switchyard with metering stations with ABT billing energy meters
at take off points inside the plant boundary of each location. The 2 nos. ABT
energy meters (Main and check) as per ANI Electricity Authorities requirement
at take off point at along with Metering CTs and PTs in Power Evacuation
Switchyard with software shall be provided by the Contractor. The ABT energy
meters shall be microprocessor based multi function type and ABT meters shall
be suitable for billing purposes and shall have necessary sealing arrangement as
per the requirements of ANI ELECTRICITY AUTHORITIES Separate CTs,
PTs, ABT meters (Main and Check). The meters shall be capable of measuring
voltage, current, frequency, power factor, active and reactive power, real and
reactive energy, maximum demand etc. The meters shall have facility to monitor
power interruptions, run hour with power on time and off time with date. The
meters shall have crisp high visibility display and scrolling facility to display the
desired parameter. The meters shall further have communication port for
interface with plant automation system. The energy meters shall have class 0.2s
accuracy, meeting CERC/JERC norms and ANI ELECTRICITY
AUTHORITIES norms and requirements. The contractor shall obtain approval
from ANI ELECTRICITY AUTHORITIES for the Metering station. The
responsibility of arranging for the meters, its inspection/calibration/testing
charges etc. from Statutory authorities rests with the Contractor and all charges
incurred on Meter testing, shall be borne by the Contractor. The energy meters
shall be suitable for interfacing for synchronizing the built in clock of the meter
by GPS time synchronization equipment to be provided in SCADA & EMS
system. Meters must be provided with the necessary data cables.

2.3.2.22 Station DC control power system be installed in line with specification clause
2.3.1.10. Required capacity UPS shall be installed and UPS sizing and design
calculation shall be submitted for NLCIL approval. Auxiliary AC power
distribution system, Lighting power distribution system shall be installed to
meet the system requirements and drawings shall be submitted for NLCIL
approval.

2.3.3 SCADA AND ENERGY MANAGEMENT SYSTEM (EMS)

65

Page 279 of 328


2.3.3.1 The Solar PV power plant integrated with battery Energy Storage System and
Power Export system shall be provided with a comprehensive control
automation system consisting of SCADA and EMS and it shall acquire all data,
store, analyze and control the operation of various equipment and systems to
achieve the objectives specified in Design Basis. The Control Automation
system shall comprise of String Monitoring Units (SMU) connected to all Solar
PV panels, Array Junction Boxes, DC Bus panel etc., in a looping ring as the
first sub system at the field level.

2.3.3.2 All SMUs get connected to respective inverters of Power Conversion Unit
located in PCSS through Inverter Monitoring Unit (IMU) as second level sub
system. The third level sub system shall comprise of PCSS Control and
Monitoring units connected to Central Processer for interface with Supervisory
Control And Data Acquisition (SCADA) system and EMS. Other sub systems
integrated into the main control automation scheme are Switchyard RTUs,
Weather Monitoring Unit, RTUs of BESS, PCS, BMS etc. All three levels of
subsystems shall be connected through OFC either UG or OPGW in a redundant
ring network.

2.3.3.3 STRING MONITORING UNIT (SMU)

2.3.3.3.1 The String Monitoring Units shall be installed in each Combiner Box, Array JB
and DC Bus Panel and shall be connected to respective PCSS through the
Optical Fibre Cable (OFC) in a redundant ring network in order to have better
reliability with lesser field control cables.

2.3.3.3.2 The SMU shall be of Industrial Grade, reliable and field proven microprocessor
based unit having the following minimum specifications:

1. Set of field PV panels shall be interconnected in string to form a cluster


and multiple strings shall be interconnected to form an Array and
multiple arrays will be connected to the PCSS sub-system with DC Bus
panel. Each parallel string shall be monitored by the SMU and each
string data shall be transmitted through OFC network to PCSS and to
SCADA and EMS located in Project Control Room. Each string data
shall be used for attaining smooth power during Solar hours by issuing
commands for charging/discharging of BESS.

2. The system shall be designed to have a field bus connection from the PV
Junction box / combiner box and the measurements are made at the
initiation point and transmitted to the PCSS sub system as a digitalized
data signal. For Zoning of faults, measurements are also taken at higher
level Array JBs and DC Bus Panel and transmitted to PCSS sub system.

3. The SMU shall have multiple channels to interface the various strings of
the PCSS through a field bus type of connectivity conforming to IEC
60870 bus standards and protocols and remote I/Os shall be used to
achieve the same.

66

Page 280 of 328


4. Necessary DC or AC power distribution system from respective PCSS
shall be provided in the yard for meeting the operating power
requirements of SMUs.

2.3.3.3.3 The SMU shall be capable of monitoring the parameters like Voltage, Current,
and power as well as rate of rise /drop of parameters for each string and each
array along with diagnostic digital status signals from each combiner box to
provide adequate information with respect to the performance fluctuation and
efficiency of the PV arrays connected to it. It shall be possible to monitor and
identify the non-performing or underperforming PV panel strings from the
PCSS sub system so that the same can be attended or isolated easily.

2.3.3.3.4 The SMU unit shall be of RTU type to acquire data on continuous basis and
store the data in the SCADA. The SMU shall have logical capabilities to
perform any interlocking and protection logics as per the process requirement.
The SMU shall have other standard features like RTC, self-diagnostic routines,
event logging, alarms, fluctuation feedback etc. For electrical parameters like
voltage, current, etc., direct I/O modules without the usage of transducers shall
be preferred.

2.3.3.3.5 The components and interconnections of SMU shall be suitable for higher
service temperature within Array Junction box and Combiner box prevailing in
the project site.

2.3.3.4 INVERTER MONITORING UNIT (IMU)

2.3.3.4.1 Inverter Monitoring Units shall be installed in each PCCS for each Power
Control Unit (PCU) or Inverters. This inverter-monitoring unit shall be
industrial grade microprocessor based unit with direct digital interface to the
PCUs. The IMU can be built in to PCU / inverter itself or it can be a separate
unit for each PCU / inverter or common for both PCUs / inverters.

2.3.3.4.2 The IMU shall collect all the operating conditions of the inverter including
fluctuation parameters in AC side from the PCU / inverters and transfer the data
to the PCSS Control and Monitoring Units through the bus connectivity as
shown in the configuration diagram.

2.3.3.4.3 These monitoring units shall be connected through a redundant bus network to
the control and monitoring unit (PCSS-CMU) as part of the PCSS Sub – system.
Provision shall be made in PCSS to attach a portable HMI such as Lap Top
when required.

2.3.3.4.4 The IMU shall be capable of accessing real time downstream and upstream
performance values, analyzing dynamic PR, automatic changing of control
parameters based on trending and comprehensive monitoring the status of all
equipment connected to it along with its parameters. Commands from SCADA
and EMS shall be issued through IMU to inverters for controlling and
smoothing of the AC side output.

2.3.3.4.5 The IMU unit shall be of RTU type to acquire data on continuous basis and
store the data in the SCADA. The IMU shall have logical capabilities to perform

67

Page 281 of 328


any interlocking and protection logics as per the process requirement. The IMU
shall provide required information to SCADA for self-diagnostic routines, event
logging, alarms etc.

2.3.3.5 HT / 415 V SS RTU

2.3.3.5.1 The HT / 415 V SS RTU shall be industrial grade microprocessor based unit
with direct digital interface to the bus. This RTU is connected to different
substation systems such as HT Three winding Transformer, Tap Changer, HT
and 415 V Switchgears, voltage / current / Temperature measurement devices,
Position Sensors, Control and Automation Relays, 110 V DC system battery
status and charger functions, PCU Ventilation fan operating status, etc.

2.3.3.5.2 The HT / 415 V SS RTU shall be capable of controlling the operations of circuit
breaker with intelligent interlocks and safety configurations from remote server
such as SCADA and EMS. All relay functions shall be programmable through
SCADA and EMS. Status abnormality of all equipment in Power Collection Sub
Station shall be monitored by the HT / 415 V SS RTU for providing necessary
alarm / alerts.

2.3.3.5.3 RTU shall be with built – in memory and extended removable type flash
memory cards to acquire data on continuous basis and store the data in the
memory modules .The RTU shall have logical capabilities to perform any
interlocking and protection logics as per the process requirement . The RTU
shall have other standard features like RTC, self-diagnostic routines, event
logging, alarms etc.

2.3.3.6 PCSS CONTROL MONITORING UNIT (PCSS CMU)

2.3.3.6.1 The PCSS CMU shall be an industrial grade microprocessor based unit which
shall act as bridge between each PCSS data network and main Optic Fibre Ring
Network. It shall be capable of handling all data and control functions of PCUs
as well as Substation RTUs. The constructional features of PCSS CMU shall be
similar to SS RTUs.

2.3.3.6.2 The other systems which shall be hooked up to the main OFR network at PCSS
are, phone communication, Fire alarm repeater panel and Station Facility
Controller. The Station Facility Controller shall handle all substation facilities
such as yard and building lighting, UPS / 110V DC system battery, battery
charger and access control.

2.3.3.7 OPTIC FIBER RING NETWORK

2.3.3.7.1 An optic fibre cable network in ring architecture is envisaged to connect the
entire plant for data transfers in a most economical manner. Single mode 6 or 12
core corrugated steel tape armoured Optical Fibre cable conforming to IEC
60794 shall be routed as buried at a depth of 600 mm below ground connecting
the entire plant.

68

Page 282 of 328


2.3.3.7.2 The optical fibre link shall be redundant and the ring network shall consist of
necessary splitter boxes, closure terminals, couplers, drop / patch cables,
attenuators, etc., of reputed make.

2.3.3.7.3 Where ever required the optical fibre link between site and SCADA/EMS shall
be connected through Optical Fibre Ground Wire (OFGW) installed on
Transmission line towers to avoid crossing of public roads and private areas.

2.3.3.8 CENTRAL PROCESSOR UNIT AND SUB NET

2.3.3.8.1 Central Processor unit connected to Optical Fibre ring network collects data and
interact with SCADA and EMS through sub net. The Central Processing unit
shall be a rugged industrial type microprocessor based unit with built in
redundancy.

2.3.3.8.2 The sub net in control room shall be a redundant data highway bus connecting
SCADA and EMS servers and weather monitor unit, HT RTU etc.

2.3.3.9 WEATHER MONITORING UNIT (WMU)

2.3.3.9.1 The WMU shall be an industrial microprocessor based unit capable of collecting
weather data from field instruments listed in Clause 2.3.3.13 below. Functions
of WMU are elaborated in Clause 2.3.13.15. Pyranometer data from WMS shall
be taken by SCADA and EMS for control operations of BESS charging and
discharging.

2.3.3.10 33 KV POWER EXPORT SWITCHYARD

2.3.3.10.1 The constructional and operational features of HT SS RTU shall be similar to


HT / 415V SS RTU of PCSS.

2.3.3.11 SUPERVISORY CONTROL AND DATA ACQUISITION SYSTEM


(SCADA) AND EMS

2.3.3.11.1 The computer aided SCADA and EMS shall be designed for simultaneous
monitoring and recording of various parameters of different sub-systems in the
solar power plant integrated with Battery Energy Storage System, power
generation on the DC and AC sides, capable of computing performance ratios
and efficiency of different sub system operations and implement corrective
action for achieving smoothend power output to grid and achieving maximum
plant output. SCADA and EMS shall be suitably connected with necessary
hardwares and softwares and proper linkages.

2.3.3.11.2 The SCADA and EMS shall be designed on reliable operating platform and time
tested software featuring, Energy Management, String level control if required
and inverter control, Battery management system control, DC & AC switch
gears, lighting automation system, security, alerts, analytical reporting, auditing
and data archiving functions etc.

2.3.3.11.3 SCADA and EMS shall be capable of providing different on screen dashboards
for overall / zone of the plant, combiner box monitoring, weather station
parameters, DC / AC SLD, Trend Charts, Alarm / Alert listing, Audit Reports,

69

Page 283 of 328


Equipment parameters, communication link monitoring, GIS based plant view
with dynamic change key performance indices and operating parameters,
Battery Management system parameters, Power Conversion Substation
parameters etc.,

2.3.3.11.4 Minimum of three operating stations with servers is envisaged for the SCADA
and EMS. Personal computer (PC) with monitor and key board shall serve as
servers. One server shall be Operating Station with data storage, second server
shall serve as back up data storage as well as Operating Station cum
Engineering Station and the third server shall be web connected to act as Web
Station with web data storage. The Data Acquisition System should be housed
in a desk made of sheet steel, powder coated.

2.3.3.11.5 The SCADA and EMS configuration, equipment details, software features, on
screen dashboards and other operational highlights shall be submitted for
NLCIL approval. Necessary design documents and drawings of SCADA and
EMS including Plant Monitoring Desk shall be submitted for approval by
NLCIL before commencement of supply.

2.3.3.11.6 Each PC shall be rugged & robust in nature to operate in a hostile environment.
The PC shall have minimum Intel Core i5 processor having 2 X 500 GB HDD
with minimum 4 GB RAM. The PC shall also have 21” or higher TFT Colour
monitor, DVD Drive with Writer, USB ports, Scroll Mouse and UPS for four
(4) hours power back up.

2.3.3.11.7 The printer shall be A4 and A3 colour laser type rugged & robust in nature and
of reputed make. The printer shall be equipped for printing, scanning, copying
and faxing and shall be hooked up to network.

2.3.3.11.8 The Data Acquisition System shall perform all measurements and continuous
recording of all data required for system operation.

2.3.3.11.9 SCADA and EMS shall provide fifteen (15) Minutes daily, monthly and annual
average of all parameters.

2.3.3.11.10 All data shall be recorded chronologically date wise. The data file should be MS
Excel compatible. The data logger shall have internal reliable battery backup
and data storage capacity to record all sorts of data simultaneously round the
clock. All data shall be stored in a common work sheet chronologically.
Representation of monitored data shall be available in graphic mode or in
tabulation form. All instantaneous data can be shown in the Computer Screen.

2.3.3.11.11 SCADA and EMS shall have feature to be integrated with the local system as
well remotely via the web using either a standard modem or a GSM/WIFI
modem. The bidder shall provide compatible software and hardware so that data
can be transmitted via. standard modem. Plant generation data shall be made
available for NLCIL web site for display in NLCIL intranet.

2.3.3.11.12 The SCADA and EMS shall enable automatic operation of entire solar PV
power plant in all modes, during power generation as well as in non-power
generation periods. Final out going breaker will be controlled by SCADA and

70

Page 284 of 328


EMS in coordination with Energy Management Centre of A & N Electricity
Department. SCADA and EMS shall be in addition to proprietary data logging
and control system provided by the Contractor and it shall be the responsibility
of the Contractor to ensure all system interfacings are properly matched to have
an integrated operation from SCADA and EMS.

2.3.3.11.13 The Solar PV Power Plant integrated with Battery Energy Storage System will
be requiring interface with the A & N Electricity Department for power export.
It is the responsibility of contractor to make provisions in SCADA and EMS to
have required networking with A & N Electricity Department. The Contractor
shall provide necessary hardware to meet these requirements and their
standards.

2.3.3.12 VOICE AND DATA COMMUNICATION SYSTEM

2.3.3.12.1 A Voice /Data Communication Network interconnecting all Power Collection


sub stations, BESS, Power Export switchyard and voice communication for
Security Building and watch-towers etc shall be provided for the Solar PV
Power Plant integrated with Battery Energy Storage System with necessary
hardware, software and optic fibre cable interface.

2.3.3.12.2 Suitable capacity electronic IP PBX shall be provided at Project Control Room
with cable network for IP phones inside the project site building.

2.3.3.12.3 Proposed Voice Communication System Scheme, exchange and phone data
sheet, number and location of hand sets, etc., shall be submitted for approval by
NLCIL.

2.3.3.13 FURNITURE

Adequate and appropriate ergonomically designed furniture of approved make


for the Office and SCADA rooms, AC and non AC stores shall be included in
the offer. The furniture should be chosen in such a way that it matches with the
décor of the rooms. Furniture shall be modular design. The furniture to be
included in the scope shall not be limited to the list given below. The type of the
furniture proposed to be supplied shall be submitted for approval by NLCIL.
After award of contract, Contractor shall arrange to get the modular furniture
arrangement as well as furniture types approved by NLCIL before proceeding
with the procurement.

Sl.No. Description of Furniture and Fittings Quantity

Executive steel table with glass top and 3 sliding


1 4 Nos.
drawers for office

Height adjustable cushioned chair with arm rest for


2 7 Nos.
office

3 Steel table with 3 sliding drawers for stores 3 Nos.

4 SCADA workstation table (Modular design) 1 Set

71

Page 285 of 328


Computer station chair with hand rest, back and height
5 3 Nos.
adjustment

6 Standard filing Cabinet 3 Nos.

7 Standard steel cupboard 3 Nos.

8 Slotted angle racks for stores 9 Nos.

9 Slotted angle racks for tools and tackles 5 nos.

10 Workers locker (6 compartment design) 3 Nos.

2.3.3.14 INSTRUMENTS AND WEATHER MONITORING UNIT (WMU)

2.3.3.14.1 Contractor shall provide all measuring instruments listed below for each site
location and with all necessary software & hardware to make it compatible with
SCADA and EMS.

1. Pyranometer -2 nos.

2 RTD/Thermister type ambient temperature measuring instrument


-2 nos.

3. Wind speed sensor- 1 no.

4. Wind direction sensor -1no.

5. Rain gauge – 1no.

6. Surface temperature sensor- 1 no in each PCSS zone.

7. Data logger – 1no.

2.3.3.14.2 Pyranometer: Typical specification for Pyranometers, for measuring incident


global solar radiation shall be as follows:

Spectral Response : 0.31 to 2.8 microns

Sensitivity : 7-14microvolt/ w/Sq. m

Time response (95%) : Max 15 s

Non linearity : ±0.5%

Tilt error : ±0.5%.

Zero offset thermal radiation : ±7 w/m2

Zero offset temperature change : ±2 w/m2

72

Page 286 of 328


Operating temperature range : - 40 deg to +80 deg.

Non stability : Max ±0.8%

Resolution : Min + / - 1 W/m2

Input Power for Instrument & Peripherals : 230 VAC (If required)

Output Signal : Analogue form


which is compatible
with the data

2.3.3.14.3 If any higher version is required to meet system requirements with the approval
of NLCIL the same shall be installed without any extra cost to NLCIL. Each
instrument shall be supplied with necessary cables. Calibration certificate with
calibration traceability to World Radiation Reference (WRR) or World
Radiation Centre (WRC) shall be furnished along with the supply of the
instrument.

2.3.3.14.4 The signal cable length shall not exceed 20m. Contractor shall provide
Instrument manual in hard and soft form.

2.3.3.14.5 Bidder shall install two RTD type ambient temperature measuring instruments
at suitable places in PV array. Instruments shall have a range of - 4 0 C to 70oC.

2.3.3.14.6 Weather Monitoring Unit: The WMU shall be an industrial microprocessor


based unit capable of collecting weather data from field instruments listed
above. Instruments with built in I/O modules and instruments connected through
analog – digital converters shall be connected to WMU through suitable data
network and shall be programmed to provide weather parameters continuously.
WMU shall be programmed to monitor the weather parameters obtained from
field instruments constantly to deduct abnormality, especially of Pyronometer
and give immediate warning for recalibration of instrument.

SECTION 2.4

CIVIL WORKS AND STRUCTURAL STEEL WORKS


2.4.1 GENERAL
2.4.1.1 The scope of civil works detailed below is only indicative. Any other civil &
structural steel work which is not mentioned or not included here but necessary for
the establishment and operation & maintenance of Solar Power Plant shall be
included in the scope and borne by the Contractor.

2.4.1.2 This specifications document is not exhaustive and the contractor shall be
responsible not only for the requirements specified herein but for the correct choice

73

Page 287 of 328


of materials, for proper fabrication and for the conformity to codes, regulations and
legal requirements and for supplying all the documentation of these materials.

2.4.1.3 In General, all civil works shall be carried out as per relevant latest BIS, unless
otherwise specified.

2.4.1.4 Minimum grade of RCC work shall be M30 as per IS code.

2.4.2 PRELIMINARY WORKS


2.4.2.1 LAND DEVELOPMENT AND SITE PREPARATION
Land Development activities shall include marking of boundaries with boundary
pillars in co-ordination with Andaman & Nicobar Administration Authorities.
Removal of trees including roots within the site boundary, vegetation removal and
stacking the usable materials within the boundaries for disposal are in the scope of
the contractor.

2.4.2.2 TOPOGRAPHICAL SURVEY


Topographical survey for the entire proposed site at a grid interval of 5m in both
directions shall be carried out by the contractor. All surveying Northing & Easting
co-ordinates shall be based on UTM (Universal Transverse Mercator of respective
Zone). After completion of field survey, the contractor shall submit contour layout
(contour interval 0.5m) along with spot levels for the total project. The Contractor
shall submit all data @ 5m Grid interval in both directions pertaining to the survey to
NLCIL in a CD/DVD including all levels & co-ordinates in X-Y-Z format for the
entire area.
On completion of field survey work, the contractor shall submit soft copy of Draft
Survey report to NLCIL for review. The draft report shall contain all relevant
documents and General layout drawing with clear demarcation showing boundary
pillars, finished ground levels (FGL) of Array Yard, Power Collection Sub Stations,
Power Export Sub Station, building sewage / drainage systems, fencing, approach
roads, peripheral roads, internal roads, storm water drains connecting to the nearest
Nallah or to the existing storm water drain, culverts, if any, watch towers etc.,

After attending NLCIL’s comments if any in the draft report, Six (6) sets of hard
copy and one (1) set of soft copy (in DVD/CD in editable AutoCAD format) of the
Final Survey report with all relevant drawings shall be submitted to NLCIL for
approval. The FGL should be got approved by NLCIL before commencement of
work at site.
Levelling and terracing works for the entire power plant area shall have to be done at
different levels & slopes based on the natural terrain and requirements. Hence
cutting, filling, levelling and other allied works are in the scope of the contractor.
The finished ground levels of array yard, sub stations, control room etc., shall be

74

Page 288 of 328


finalised taking into consideration all formation levels on completion of the above
survey work. Based on the contours, drainage system shall have to be designed.

2.4.2.3 SOIL INVESIGATION:


2.4.2.3.1 The Contractor shall carry out sub soil investigation at all locations through a
qualified soil consultant to ascertain the soil parameters of the proposed solar power
Plant. At the proposed sites, for design purpose, recommended value of Net safe
bearing capacity of the soil at a depth of 1.2 m may be taken as 8.00 T/m2. This Net
Safe Bearing capacity value is indicative only. After award of LOA, the contractor
shall have to carry out all necessary soil tests to ascertain actual soil parameters
including Net Safe Bearing capacity.

2.4.2.3.2 The scope of sub-soil investigation includes, execution of complete soil exploration
including boring according to the site requirement, drilling, collection of undisturbed
soil sample where ever possible, otherwise disturbed soil samples, SPT, Electrical
Resistivity test, etc., conducting laboratory test of samples to find out the various
parameters mainly related to load bearing capacity and settlement, ground water
table level, sub soil conditions such as chemical characteristics of soil. The soil test
also includes analysis of ground water sample.

2.4.2.3.3 On completion of field and lab test, the contractor has to submit soft copy of Draft
Soil investigation report to NLCIL for review. The draft report shall contain data for
each borehole, layout drawing showing all test locations (with UTM coordinates),
along with recommendation regarding suitable type of foundation for all the
structures as well as recommendation for soil improvement, wherever necessary. The
report shall include Safe bearing capacity of soil for different types of foundations
(Shallow/Pile) based on soil parameters and settlement characteristics defining
clearly, how these capacities were arrived at, based on the relevant latest BIS
standards.

2.4.2.3.4 After attending NLCIL’s comments if any in this regard, the contractor shall submit
one (1) soft copy (in the form of DVD/CD) and six (6) hard copies of Final Soil
Investigation Report to NLCIL and get them approved, before commencement of
foundation designs.

2.4.2.4 PLANNING AND DESIGN COORDINATION


The Contractor has to plan and design array yard infrastructure in a proper manner
based on the technological as well as functional requirements. Contractor shall
develop general layout drawing of array yard, internal roads, peripheral roads & path
ways, drainage system, etc ensuring no water logging takes place in the array yard
area or near boundaries. The work also includes leveling the entire Plant area and
grading to suit the topography of the area. All design & drawings have to be
developed based on technical specifications of the tender documents, approved soil
investigation report and relevant latest BIS unless otherwise specified. All details for

75

Page 289 of 328


water supply for module cleaning and the resultant drainage system shall be clearly
shown in the detailed drawings.

2.4.3 MODULE MOUNTING STRUCTURE

2.4.3.1 Foundation for Modules Mounting Structures (MMS) can be shallow foundation or
driven cast-in-situ Pile/Under reamed pile depending on the soil conditions. While
designing the foundations, due consideration shall be given for the self weight of
module assembly and maximum wind speed as per latest IS 875-Part-3. The size of
the foundation shall be based on design parameters & to prevent liftoff of structure
due to wind forces. Minimum pile diameter shall be 300mm. The Grade of concrete
for foundation shall be M30. Top of concrete/height of collar for MMS foundation
shall be minimum 150mm above FGL. In case of pile foundation, necessary
INITIAL TEST (Pullout & Lateral load) for piles – minimum 2 tests at each site
shall be done as per latest IS2911(Part-4) and accordingly the depth of pile shall be
firmed up. Foundation work of Module Mounting Structure shall commence only,
after the proper leveling / grading of the site

2.4.3.2 Seismic parameters Zone & Importance Factor for the project sites shall be based on
latest BIS: 1893(Part-1).

2.4.3.3 Members shall be fabricated by cold forming process and shall have minimum yield
strength of 345 MPa and shall conform to the physical specifications of ASTM A653
or latest IS 811 or any other relevant international standards. Light gauge structural
steel or structural aluminium members can also be proposed subject to approval of
NLCIL. Mild steel members with weather protection coating as per ASTM A792M
or IS:15961 (latest revision) standard Al-Zn alloy hot dip process with minimum 150
GSM on both sides are acceptable for purlins (structural member connected to
modules) with minimum 0.9 mm base metal thickness and yield strength not less
than 550 MPa. Inside coating of purlins should be ensured.
1. Fabrication and erection shall be carried out in accordance with latest IS 800 and
IS 801.
2. Dimensions of plates, flat bars shall conform to latest IS 1730. The minimum
thickness of 2.5mm for MMS column post and minimum 2mm for other members
shall be ensured.
3. Bolts, nuts, screws, washers etc… shall be of stainless steel SS 304 of class A2-70
and sizes as per latest relevant BIS provisions. All fasteners shall be provided
according to connection design requirement. All bolts shall be tightened with
designed torque mechanically.
4. All structural members shall be hot dip galvanized as per IS 4759 or relevant
Indian standards and the average coating thickness shall be 80 micron and local
coating thickness shall be minimum 70 micron. In case of aluminium, anodized
coating as per IS 1868 (AC25) shall be provided.
5. Structural design of MMS structure shall be as per provisions of latest IS 801.

76

Page 290 of 328


2.4.3.4 Design Parameters and Design Loads:
The structure shall be designed for loads and load combination as per Indian
Standards (latest revisions)
i. Dead load: Dead loads shall be self weight of all the modules, members and
fasteners.
ii. Wind Load: The wind load parameters shall be considered as per latest IS 875
(Part-3).
iii. Earthquake Load: The MMS structure shall be designed for Seismic forces.
Seismic parameters Zone & Importance Factor shall be based on latest BIS:
1893(Part-1).
iv. Vertical Deflection & Horizontal Sway Limits: The limiting permissible vertical
and horizontal deflection for structural steel members shall be as per latest IS
800: 2007.
For fixed/seasonal tilt MMS structure, bidder shall submit STAAD file & design
document for approval of MMS drawings. For tracking system, bidder can propose
wind tunnel test report/STAAD file & design document for approval of drawings. If
bidder is going for wind tunnel test for the design and analysis of solar tracking system
following has to be ensured.
i. It must be done from an institute of reputed (IITs in India).
ii. If test is done by any reputed international facility the test results must be
vetted by any of the IITs in India.
iii. Bidders must ensure that offered tracker has proven design with wind
tunnel test simulating actual site conditions.
iv. Test results and design must comply Indian codes.
v. The design shall be shown in STAAD pro for further checking of NLC
India Ltd. if asked to do so.

2.4.3.5 The contractor shall prepare array layout to suit their design and plan the total power
plant within the available land area without involving any major site modifications.

2.4.3.6 The structure shall be designed for simple mechanical and electrical installation. It
shall support Solar PV modules absorb and transfer the mechanical loads to the
ground properly. There shall be no requirement of welding or complex machinery at
site for installation of module mounting structure to the foundation.

2.4.3.7 The structure shall be designed to allow for easy replacement of any module as well
as easy access to the bottom of module by O&M staff.

2.4.3.8 General arrangement of Module mounting structures, array layout, and fabrication
drawing shall be submitted to NLCIL along with necessary supporting design
documents for approval, before commencement of fabrication/erection.

77

Page 291 of 328


2.4.3.9 Installation details of the Solar PV modules and the support structures with
appropriate diagrams and drawings shall be submitted for approval by NLCIL.

2.4.3.10 All building and other foundation drawings & designs shall be based on Final Soil
Investigation Report and to be submitted to NLCIL for approval, before starting the
work.

2.4.4 ROADS & PATH WAYS

2.4.4.1 The roads shall be designed and constructed based on the General layout of the Solar
Power Plant. The main approach road from the existing nearest road to the Solar
Plant shall be a single lane road, designed to carry the equipments as per relevant
specification of IRC along with connecting RCC culverts (M25) wherever required.
The approach road, peripheral road & all internal roads are to be designed to suit the
Solar Plant layout and shall be of single lane of 3.6 M width. These roads shall be
laid with
a) WBM – using 40 mm BG metal - two layers – each of 135 mm pre-
consolidated thick – rolled to 100 mm thick - consolidated thickness totaling to
200 mm which includes dry and wet rolling of each layers, spreading gravel
for blindage and consolidation with water, spreading sand/M.sand/quarry dust
to a thickness of 3 mm and top rolling and
b) Top coat – Top finishing coat shall be of Bituminous Toping using 12 mm
downgraded metal with consolidated thickness of 20mm and seal coat.

2.4.4.2 All roads shall be provided with 0.60 M wide berm on both sides with 150mm thick
well compacted BG boulders/ locally available natural rock boulders and trapezoidal
earthen drains as per the approved drainage layout. The area between the solar arrays
shall be leveled for carrying panels and materials, modules washing, easy movement
during O & M, etc. The layout and details drawing of all roads and culverts (if any)
shall be submitted to NLCIL and got approved, before commencement of work.

2.4.5 FENCING & SIGN BOARD


2.4.5.1 The entire Solar Power Plant array yard shall be provided with 2.1 M high Fencing
arrangement using Goose Neck RCC (M30 Grade) Fence Posts of 2.7m length (IS
4996) at a maximum spacing of 2.30 M with strut posts at every 15 M Spacing
(maximum) and at corners. The bottom portion of fencing shall be with 1.8 M height
PVC coated Chain link Fencing and the top 0.30 M with barbed wire fencing (2 rows
& one cross diagonal) which act as anti-climbing device for safety. PVC coated
Chain link Fencing & GI Barbed wire shall be of reputed make and shall be got
approved before use on works. Fencing details and layout drawings shall be
submitted to NLCIL for approval, before commencement of work.

2.4.5.2 Aesthetically designed sign board 2.4 M x 1.5 M shall be provided at the entrance of
approach road to Solar Power Plant at each plant site. The sign board shall contain
78

Page 292 of 328


brief description of the Power Plant. The Signboard shall be made of stainless steel
tubular frame with SS steel plate of not less than 3 mm. Necessary SS steel tubular
support column with concrete foundation shall be provided. Letters on board shall be
designed with proper colour scheme and fluorescent paint system / arrangement. The
design & size of the signboard shall have to be befitting the landscaping planned for
the main entrance to power Plant. The sign board design and drawing shall be
submitted to NLCIL for approval, before the commencement of manufacturing.

2.4.6 SECURITY BUILDING AND GATES


2.4.6.1 The Security Building shall be provided near the main entrance of each plant /project
site. The security building shall be of single storeyed RCC (M 30) framed structure
3m x 3.6 m (inner dimension) with an internal toilet provision for 1.5m x 1.2 m size
& front verandah for a minimum width 1.20 m. This building shall generally be
constructed as per the relevant specifications laid down for the Project Control Room
building. Security building shall be provided with necessary electrical fittings and
sanitary items along with adequate sewage disposal system. The design and
drawings of security building shall be submitted to NLCIL for approval, before
commencement of work.
2.4.6.2 The main entry to each plant/project area shall be provided with a main gate of size
5.00 x 2.40 M and a wicket gate of size 1.20 x 2.40 M (both using MS Structural).
RCC (M 30) gate pillars of required size shall be provided at the main entrance.
Apart from this main gate, additional gates of size 1.20 x 2.40 M shall be provided at
appropriate locations within each project site, wherever necessary. These gates shall
be designed aesthetically and the design and drawings of Gates & RCC Pillars shall
be submitted to NLCIL for approval, before commencement of manufacturing /
construction.

2.4.7 WATCH TOWERS


Adequate number of Watch towers (using MS Structural) to have coverage of the
entire plant/project site shall be provided around the periphery. Watch tower shall be
of height 3.50M up to the bottom of the cabin of size 2.00 x 2.00 x 2.40 M. The
cabin floor shall be provided with a platform of size 3.20 x 3.20 M, using 6mm thick
chequered plate over MS structural framework and the roof shall cover the entire
platform area. Cabin roof and sides shall be provided with double skin metal
cladding with 60mm thick Poly Urethane Foam (PUF) insulated sandwiched panel.
The cabin shall be provided with a steel door of size 0.80 x 1.80M on one side and
powder coated aluminium glazed sliding windows of size 1.20 x 1.20 M on all other
3 sides. Minimum 800 mm wide steel staircase with MS handrails on both sides as
per requirement shall be provided. Hand rail and toe guards shall be provided for
platform around cabin. These watch towers shall be designed and constructed
considering the safety and security requirements of the Solar Power Plant. Entire
structure of the watch tower shall be provided with proper surface treatment and
painting system. Watch towers shall be provided with necessary electrical

79

Page 293 of 328


arrangements. The location and design drawings of the Watch Towers shall be
submitted to NLCIL for approval, before commencement of fabrication.

2.4.8 WATER SUPPLY ARRANGEMENT FOR MODULE WASHING AND


DRAINS
2.4.8.1 Contractor shall provide necessary arrangement for module washing in the Solar
Power Plant. This shall include construction of a water storage sump, pump & motor
and routing buried ring main system using heavy duty rigid PVC pipe network
covering all areas of Solar arrays. Tap off points from the PVC supply pipe network
with manual isolating valves shall be provided at number of locations to enable the
cleaning of modules using hoses of adequate length. To the extent feasible, the run-
off from washing shall be designed to get absorbed in the soil below the solar arrays.
Excess water during rains shall be drained through storm water drains built in the
Plant area and finally let into the main storm water drain leading to the Nallah.
Construction of underground storage sump for module washing system with M30
grade concrete sump or field assembled buried FRP tank are acceptable.
2.4.8.2 The plant storm water drainage system shall be designed taken into account the
topography of the plant area, area drainage patterns and intensity of rainfall as per
Indian Meteorological data etc. For design of drains, the maximum recorded rainfall
intensity shall be considered. All internal drains shall be earthen drain, trapezoidal in
section and shall be of sufficient width at the base. Internal road cross over,
intersections and the drains near PCSS etc. shall be provided with removable RCC
slab covers of adequate thickness and reinforcement.

2.4.8.3 The Contractor shall submit to NLCIL the schematics of the wash water system with
location of pump, pipe work and tap off points as well as drains, module washing
accessories, etc., for review and approval.

2.4.8.4 The Contractor shall carry out chemical analysis of water independently to ascertain
the quality of supplied water and to size any equipment or system required for
treatment of raw water for successful operation of Plant for 11 years. Based on
chemical analysis of water, if any equipment/system is required for treatment of raw
water before it is used for module cleaning and the same shall be submitted to
NLCIL for approval.

2.4.9 POWER EXPORT SWITCHYARD AND TOWER LINES.


2.4.9.1 GENERAL REQUIREMENTS:
Civil and structural works for the Power Export Switchyard & Tower lines shall be
installed as per the technical requirements of Electricity Department, Andaman &
Nicobar Administration and CEA norms.

2.4.9.2 The scope of civil works for the PSS includes design, supply of materials and
construction of all equipment / tower / mast foundations, cable trenches, earth

80

Page 294 of 328


pits, and drains. Contractor will co-ordinate and supervises complete civil
construction and structural fabrication and erection for correctness as per the
requirements indicated in the design inputs.

2.4.9.3 All pedestals for towers/equipment will extend to a minimum of 300mm above
FGL.

2.4.9.4 Supplying and spreading with crushed BG metal comprising of average 40mm
(30mm to 50mm) normal size over the entire Switchyard area to 100 mm.
thickness (min.).

2.4.9.5 The safe touch & step voltage will be achieved considering crushed stone/gravel
resistivity for Substation. Beside this if any extension of earth mat outside Sub-
Station area is required to achieve safe earth mat design; the same will be within
the scope of the Contractor.

2.4.9.6 Contractor will submit the design of switchyard foundation and structures with
details of load combinations, factor of safety, sag tension basis, etc. to NLCIL for
review and approval.

2.4.9.7 The scope of civil works detailed above for the switchyard is only indicative.
Any other civil & structural steel work which is not mentioned or not included
here but necessary for the establishment and operation of 33KV Switchyard for
Power evacuation purpose will be included in the scope and borne by the
Contractor.

2.4.9.8 Cable Trench in Switchyard shall be constructed as per standards including


necessary provisions for road crossings.

2.4.10 PROJECT CONTROL ROOM BUILDING:


2.4.10.1 GENERAL REQUIREMENTS:
The project Control Room building shall be designed based on topographical survey
report & soil testing report, relevant BIS code and National Building Code of India.
The building shall have to house Control room equipments, SCADA & Energy
Management system (EMS) panels, LT panels, UPS, DC system-Battery, Battery
charger (DC loads required for switchgear), Lighting & Power Distribution Panel
etc.,
This building shall also have 20 sq.m. Office Room, AC and Non AC stores, and
other building facilities including pantry, separate toilets (Ladies& Gents), necessary
water supply & drainage system.
Office, AC stores and Control room equipments, SCADA & Energy Management
system (EMS) panels shall be air-conditioned and shall be provided with false
ceiling arrangement.

81

Page 295 of 328


Design details of all the facilities described above shall be submitted to NLCIL for
approval before execution.

2.4.10.2 DESIGN:
The Power Export Sub Station building shall be designed as RCC framed structure
with external staircase as per NBC. A portico with RCC slab for a minimum
dimension of 4.5mx3.6m shall also have to be provided at the main entrance. All
passages/corridors shall be provided with a minimum width of 2.0 m.

2.4.10.3 RCC WORK:


All RCC works shall be of M30 grade.
Cement:
Cement of the following Grades shall be used for all works. It shall conform to the
following standards.
 43 Grade OPC IS 8112
 53 Grade OPC IS 12269
 Portland - Pozzolana Cement IS 1489(Parts 1 & 2)

Steel Reinforcement:
All reinforcement steel used shall confirm IS 1786 and shall grade Fe 415/ Fe500.
The corrosion resistant steel bars alone shall be used in the concrete. The corrosion
resistant steel bars manufactured by SAIL/RINL/TISCO, JINDAL/VSPSAIL /SRMB/
SHYAM/ UDYOG/ TATASTEEL/ PULKIT/ TULSYAN/SURYADEV shall be used.

Mix Design & Strength of Concrete:


Before commencement of the concreting works, the Contractor shall get the approval
for Mix design. The strength of concrete shall be tested as per latest BIS.

2.4.10.4 MASONRY WORK:


Bricks/ solid/hollow blocks used in the works shall conform to relevant IS.

2.4.10.5 PLASTERING:
All internal and external surfaces of wall shall have 15 mm thick plastering in CM
1:4. Ceiling plastering shall be 12mm thick in CM 1:3

2.4.10.6 FLOORING:
Flooring for stores and HT Switchgear room shall be of cement concrete flooring as
per IS 2571. Flooring for office, pantry and SCADA room shall be approved quality
vitrified ceramic tile of approved colour and shade, minimum size 600 x600 mm
over PCC. Acid resistant tile flooring of 10mm thick confirming to IS4457 shall be
provided for Battery room. For pantry room platform, Polished Granite slab of
thickness 12 to 16mm shall be used.

82

Page 296 of 328


2.4.10.7 ROOFING - Roof of the Control Room Building shall be sloped Cast-in-situ RCC
slab (Grade M 30) treated with waterproofing system.
Concrete/ red clay tiles of approved quality, brand shall also have to be provide over
the RCC slab.

2.4.10.8 DOORS & WINDOWS - Doors, windows and ventilators shall be provided with
electro colour dyed (15 micron thickness) aluminium framework with glazing.
Minimum size of door shall be 1.2 m x 2.1 m. However for toilets minimum width
shall be 0.75 m. All doors of toilet areas shall be FRP frame and FRP shutter. All
windows and ventilators of all buildings shall be provided with suitable MS Grill.
Doors and windows on external walls of the buildings shall be provided with RCC
sunshade over the openings with 300 mm Projection on either side of the openings.
Projection of sunshade from the wall shall be minimum 600 mm over window
openings, 750 mm over door openings & 1000 mm for rolling shutters (other than at
main entrance). The Rolling Shutter shall confirm to IS6248 and the size based on
functional requirement.

GLAZING: All windows and ventilators shall be provided with 4mm thick tinted
glass. For aluminum doors, tinted glass of 6 mm thickness shall be used. All glazing
work shall conform to relevant BIS.

2.4.10.9 FALSE CEILING:


All A/C rooms (including office rooms) shall be provided with false ceiling of
suitable type using approved materials. The false ceiling shall be designed
aesthetically and shall be from reputed supplier. The false ceiling design & drawings
with light fittings shall be submitted by Contractor to NLCIL for approval, before
commencement of work.

2.4.10.10 PAINTING:
The emulsion paint for both internal & external walls shall be anti-fungal quality of
reputed brand suitable for masonry surfaces for the corresponding rainfall zone of
Project site. The ceiling & walls of the Battery room shall be painted with epoxy
based paint. All painting on masonry or concrete surface shall preferably be applied
by roller. If applied by brush then same shall be finished off with roller. All paints
shall be of approved make and quality. Minimum 2 finishing coats of paint shall be
applied over a coat of primer. For painting on concrete, masonry and plastered
surface IS: 2395 shall be followed. For painting on steel work and ferrous metals,
relevant BIS shall be followed.

2.4.10.11 PLINTH PROTECTION:


Plinth protection to a minimum width of 0.75m with 75mm thick of cement concrete
1:2:4 over 75mm bed of dry brick ballast 40mm nominal size well rammed and

83

Page 297 of 328


consolidated and grouted with fine sand/M Sand including finishing the top with
suitable slope & edge drain.

2.4.10.12 TOILET & WATER SUPPLY:


Heavy Duty Rigid PVC pipes of reputed manufacturer and high quality conforming
to IS: 4985 shall be used for all water supply and plumbing works in the building.
SINTEX make HDPE storage water tank conforming to IS: 12701 shall be provided
over the roof for a capacity of minimum 1000 litres with all required pipeline &
fittings.
Each toilet shall have the following minimum fittings.
 WC (Western type) of approved colour with seat cover, low level
flushing tank, paper holder, health faucet etc.
 Urinal for Gents Toilet
 Wash basin of approved colour with all fittings.
 Mirror with PVC beading
 Stainless steel towel rail with brackets
 Stainless steel soap holder and liquid soap dispenser.
 Stainless steel sink with drain board in the pantry.
The floor finish for washroom, pantry and toilet shall be vitrified anti-slip tiles and
Dado glazed ceramic tiles up to 2.1m shall be used.

2.4.10.13 SEWAGE SYSTEM


Adequate sewage disposal arrangements shall be provided. The septic tank shall be
designed as per NBC guidelines. The outfall of septic tank shall be led to soak-pit of
suitable dimensions for dispersion. The drainage system design and construction
drawings of sewage piping / septic tank shall be submitted to NLCIL for approval,
before commencement of work.

2.4.11 POWER COLLECTION SUB STATION (PCSS)

2.4.11.1 GENERAL REQUIREMENTS:


The PCSS building shall be designed based on topographical survey report & soil
testing report, relevant BIS code and National Building Code of India.
The building shall have to house PCUs, HT Switch Gear, Auxiliary power
(AC&DC) system and other electronics for communication.
Design details of all the facilities described above shall be submitted to NLCIL for
approval before execution.

2.4.11.2 DESIGN:
The Power Collection Sub Station building shall be designed as single storey RCC
framed structure.

84

Page 298 of 328


2.4.11.3 RCC WORK:
All RCC works shall be of M30 grade.
Cement:
Cement of the following Grades shall be used for all works. It shall conform to the
following standards.
 43 Grade OPC IS 8112
 53 Grade OPC IS 12269
 Portland - Pozzolana Cement IS 1489(Parts 1 & 2)
Steel Reinforcement:
All reinforcement steel used shall confirm IS 1786 and shall grade Fe 415/ Fe500.
The corrosion resistant steel bars alone shall be used in the concrete. The corrosion
resistant steel bars manufactured by SAIL/RINL/TISCO, JINDAL/VSPSAIL /SRMB/
SHYAM/ UDYOG/ TATASTEEL/ PULKIT/ TULSYAN/SURYADEV shall be used.
Mix Design & Strength of Concrete:
Before commencement of the concreting works, the Contractor shall get the approval
for Mix design. The strength of concrete shall be tested as per latest BIS.

2.4.11.4 MASONRY WORK:


Bricks/ solid/hollow blocks used in the works shall conform to relevant IS.

2.4.11.5 PLASTERING:
All internal and external surfaces of wall shall have 15 mm thick plastering in CM
1:4. Ceiling plastering shall be 12mm thick in CM 1:3

2.4.11.6 FLOORING:
Flooring, including preparation of surface, cleaning etc. shall be of cement concrete
flooring as per IS: 2571 with ironite hardener.

2.4.11.7 ROOFING - Roof of the Control Room Building shall be sloped Cast-in-situ RCC
slab (Grade M 30) treated with waterproofing system. Concrete/ red clay tiles of
approved quality, brand shall also have to be provide over the RCC slab.

2.4.11.8 ROLLING SHUTTER:


Rolling shutter of push pull type (Hand operated) shall be standard make and shall
confirm to IS: 6248 and the size based on functional requirement.

2.4.11.9 DOORS & WINDOWS - Doors, windows and ventilators shall be provided with
electro colour dyed (15 micron thickness) aluminum framework with glazing.
Minimum size of door shall be 1.2 m x 2.1 m.
Doors, rolling shutter and windows on external walls of the buildings shall be
provided with RCC sunshade over the openings with 300 mm Projection on either
side of the openings. Projection of sunshade from the wall shall be minimum 600
mm over window openings, 750 mm over door openings & 1000 mm for rolling
shutters (other than at main entrance)..

85

Page 299 of 328


GLAZING: All windows and ventilators shall be provided with 4mm thick tinted
glass. All glazing work shall conform to relevant BIS.

2.4.10.10 PAINTING:
The emulsion paint for both internal & external walls shall be anti-fungal quality of
reputed brand suitable for masonry surfaces for the corresponding rainfall zone of
Project site. All painting on masonry or concrete surface shall preferably be applied
by roller. If applied by brush then same shall be finished off with roller. All paints
shall be of approved make and quality. Minimum 2 finishing coats of paint shall be
applied over a coat of primer. For painting on concrete, masonry and plastered
surface IS: 2395 shall be followed. For painting on steel work and ferrous metals,
relevant BIS shall be followed.

2.4.10.11 PLINTH PROTECTION:


Plinth protection to a minimum width of 075m with 75mm thick of cement concrete
1:2:4 over 75mm bed of dry brick ballast 40mm nominal size well rammed and
consolidated and grouted with fine sand/M Sand including finishing the top with
suitable slope & edge drain.

2.4.12 TWO/ FOUR WHEELER SHED:


The contractor shall provide Two / Four wheeler parking sheds at each project site to
house minimum two 4wheelers and ten 2wheelers using MS structural framework
with colour coated metal /Galvalume sheet roofing.

SECTION 2.5
BATTERY ENERGY STORAGE SYSTEM (BESS)

The provision for a Battery Energy Storage System (BESS) with the Solar PV
Project has been incorporated in the Scheme with the objective of improving the
quality of power injected into the grid by Solar PV plants that rely on an intermittent
energy resource like Solar radiation and thus, contribute to stable and secure
operation of transmission grid. Specifically, the proposed Energy Storage System is
intended to be used for PV Power Smoothing application. The utility of BESS for
ancillary services including features such as Active Power Regulation services
(primary control or Frequency response) etc., shall also be included which is only for
demonstrative purpose.

The BESS shall remain connected to the grid as per Central Electricity Authority
Technical (standards for connectivity to the grid) regulation 2007 with all latest
amendments and its components shall be designed accordingly. BMS shall ensure
safe operation and mitigate fire risk. The BESS shall be configured to perform
multiple charge discharge cycles.

86

Page 300 of 328


2.5.1 PEAK SMOOTHING:-

The Prime application of BESS shall be smoothing of power output from the Solar
PV plant due to fluctuation in solar radiations. Peak smoothing shall be
demonstrated within the deployed battery capacity in MW, for above 75% of the
instances within the specified assessment window i.e., when a need for response is
detected. BESS should respond in a manner that the combined Solar PV and BESS
output at the Point of Common Coupling (PCC) targets the 15 minutes moving
average value of the Solar PV array output. BESS shall charge and discharge power
at appropriate ramp rate such that the smooth power output from the combined
BESS and Solar plant is injected into grid.

For the purpose of smoothing assessment, this BESS application shall be carried out
for during solar hours every day. The upper and lower SOC for BESS operation
shall be set as per the system requirements. The Battery manufacturer’s specification
and operating instructions shall be selected in such a way to suit the above
requirements. Temporal resolution of the data provided shall be minimum 1 second.

2.5.2 The PV smoothing Index Calculation shall be as follows:

Criteria
Description Criteria
Code
M1 Measure/Count of Instances Count those records in the 10
when the BESS is expected to hour assessment period
respond for the smoothing (Minimum temporal
application resolution of one second),
where BESS is expected to
respond

M2 Count of those instances out of Count of the instances when


M1 when the BESS power output at PCC (Solar
successfully responded as PV output + BESS output)
required lies within +/- 2% of the 15
minutes moving average of
Solar PV Power Output
M3 M2/M1 M3=Ratio between M2 and
M1

M4 PV Smoothing index, PVS: M3 value of above 0.75 shall


The metric for Smoothing be acceptable.
Assessment At least 90% of the days in a
Contract year shall have
M3 above 0.75
The PV smoothing Index shall be dynamically calculated in the EMS and if it is less
than 0.75, then alarm shall be initiated. As per grid operator requirement or under
special emergency grid condition requirement the smoothing of solar PV plant
output power intermittency. For this, the detailed control logic shall be submitted for
NLCIL approval and finalized during detail engineering.

87

Page 301 of 328


The BESS shall provide energy up to 30 min by providing immediate injection of a
large amount of energy for a short duration during the recovery period after any
sudden loss of generation within the power rating of BESS for example due to a
passing cloud cover.

2.5.3 FREQUENCY REGULATION:-

Frequency regulation provision shall be incorporated in BESS and the contractor


shall not consider any additional battery sizing for this application requirement. The
BESS shall be able to support grid during very low or high grid frequency by
supplying or absorbing power to/from grid. The power support shall be based on
power vs frequency droop characteristic for system frequency outside of the pre-
defined frequency dead band (say 49.5 to 50.5 Hz). The operation in this mode shall
be initiated by detection of low or high grid frequency while the BESS is in any
other mode. After normalization of grid frequency to normal operating range, the
BESS shall return to the mode in which it was operating at the start of frequency
regulation mode. Within the dead band frequency range the BESS do not have to
participate for frequency regulation operation. During detail engineering the actual
value of dead band frequency range shall be finalized based on CEA grid regulation.

2.5.4 ANTI-ISLANDING MODE:-

The BESS shall have anti-islanding protection as per IEC 62116 or equivalent
international standard

2.5.5 The digital inputs from Inverters, SMUs, Power Conversion System (PCS) of BESS,
Outgoing feeders, grid parameters and using other required inputs, the EMS shall
ensure that none of the solar fluctuation and intermittency shall affect the grid
parameters. Based on the history of data of various grid parameters available in Port
Blair including existing 5 MWp Solar Power Project , the forecast shall be finalised
during detailed engineering to achieve the above functions in a coordinated way.

2.5.6 Components required to support reactive power shall also be taken into
consideration for design of EMS and BESS

2.5.7 The critical parameters such as Response time, Discharge duration, Depth of
discharge, Frequency of Discharge, Cycle life, round trip cycle efficiency,
performance degradation, self discharge characteristics, short time discharge ratings,
transient response characteristics, auxiliary systems requirements etc. shall be
finalized during detailed engineering to meet system requirements.

2.5.8 Simulation studies shall be done for various conditions of Solar Generation, Grid
condition and fault conditions during detailed engineering. Necessary documents
required for obtaining the grid parameters available with Electricity Department.
ANI shall be provided by NLCIL. However it is the contractor’s responsibility to
carry out simulation studies based on available grid parameters and appropriate
assumptions. The simulation results shall be the basis for the design of the system
and it shall be submitted for approval by NLCIL and Electricity Department, ANI.

88

Page 302 of 328


2.5.9 The contractor shall submit complete design documents and expected performance
of the BESS calculations, drawings, reports and data and other submittals for NLCIL
approval during detailed engineering

2.510 Prior to the dispatch of BESS, a unit part of the system which shall represent the
final BESS system to be installed at site, shall be taken into Factory Acceptance Test
(FAT). It shall be arranged by the contractor in any test place of convenience in the
presence of NLCIL and Electricity Department, ANI authorities. This test is
envisaged with an aim to minimize malfunctions during installation at site. The tests
that cannot be built during FAT shall be simulated and tested as close as possible in
a manner corresponding to the final functioning.

2.5.11 Fire protection system (FPS) shall be designed for the BESS in line with NFPA or
international norms regulations and CBIP guidelines as applicable and system
requirements taking into consideration of the project site at island.

2.512 Power Conversion System (PCS) for BESS shall have efficient cooling and a more
compact housing concept. The housing concept must be a closed-concept with an
air-conditioning system or a ventilation system and shall be supplied either in a
separate compartment or integrated system. The BESS shall be able to supply power
at power factor of 0.95 lead-lag during normal operation and should be able to allow
grid power factor until 0.8 lead-lag. During the period of back down/surrender, grid
outage conditions, the BESS shall be capable of getting charged from Solar PV
Power plant on stand alone basis. .

2.5.13 The response of PCS shall be in such a way that it meets the requirements of Energy
Management System (EMS) which is in the scope of the contractor as well as
Energy Management Centre which is in the scope of Electricity Department, A & N
Administration. The Energy Management System (EMS) shall function as the main
command centre for the entire plant and receive inputs via SCADA, from Solar PV
strings, inverters, HT transformers, Feeders, Battery Management system, Power
conversion system, weather monitoring unit, grid parameters etc. the charging and
discharging commands shall be issued accordingly.

2.5.14 Test certificates and test reports as per IEC 62133, IEC 61959 and IEC 61960 or
other international equivalent standards applicable for the battery technology
selected shall be submitted by the contractor for NLCIL approval during detailed
engineering. All other test certificates and test reports as per international standards
and norms for large scale Battery Energy Storage System shall be submitted for
NLCIL approval during detail engineering.

2.5.15 BESS replacements, repairs, substitutions, maintaining spares and consumables etc.,
shall be programmed and carried out by the contractor so that the annual guaranteed
net energy export is achieved. The tie up arrangements including after sales service
support for the entire cycle life of the Battery shall be made by the contractor with
Battery supplier and the same shall be submitted to NLCIL.

2.516 Load banks devices with dummy loads of capacity suitable for a unit part of BESS
specially designed for battery discharge testing shall also be a part of BESS
maintenance and testing system at project site..

89

Page 303 of 328


2.5.17 The contractor shall install and integrate minimum 8MWhr with half hour backup.
BESS with 2 x 10 MW (AC) Solar Power Plant. The contractor shall install and
integrate more capacity to achieve the annual guaranteed net energy export if
required without any extra cost to NLCIL.

2.5.18 The BESS shall consists of components but not limited to the following:

 Battery cells /Modules/stacks


 Power Conversion System, Battery Management System, Control panels and
HMI interfaces
 Lightning Arrestor, CT, PT, Protective relays, Control and Metering Panel,
Surge Protection devices, Filters etc.
 Panels, Switch gears, cables and distribution boards
 Transformers
 Data communication units
 Auxiliary systems and ventilation systems
 Fire Protection system and suppression system, safety equipments
 Container unit
 Mounting structures and Dike structures
 Civil foundation works and platforms as per Battery Manufacturer’s requirement

2.5.19 The contractor shall submit detailed technical particulars, drawings and documents of
the above components for NLCIL approval.

2.5.20 BESS PARAMETER:

The following shall be the minimum BESS parameters. Bidder shall submit all
technical parameters to assess all BESS functionalities.

S.No Parameter Value

1 Installed capacity of BESS 8 MWhr

2 Rated AC power at PCC 16 MW (45 deg C ambient


temperature) at 0.95 PF

3 BESS Round trip AC/AC Efficiency at PCC To be specified by EPC


contractor as per their
BESS system

4 Depth of Discharge (DOD) To be specified by EPC


contractor as per their
BESS System

5 Battery Efficiency (DC-DC round trip) To be specified by EPC


contractor as per their

90

Page 304 of 328


BESS System

6 Guaranteed Minimum service life minimum 11 years


(including 1 year PG
period and 10 years
O&M)

7 Charging rate To be specified by EPC


contractor as per their
BESS system

8 Power factor (Measure at PCC) Four quadrant capability is


required. Operating power
factor shall be 0.95 lead or
lag

9 Response time: It is the time interval BESS shall have suitable


between need for response (a command or response time to support
grid event or Solar Plant power generation smooth injection of solar
PV plant output power
event, etc) is detected by the BESS and the
into grid to achieve PVS
time when power as measured at the grid has above 0.75 at least 90% of
attained that level. This shall include all the days in a Contract
intermediate response time of system year.
components

10 Positive and Negative Ramp Rate BESS shall have suitable


positive and negative
ramp rate to support
smooth injection of solar
PV plant output power
into grid

11 BESS design temperature 0 – 45 degC ambient

91

Page 305 of 328


Section 2.6
TESTING, COMMISSIONING, PROVISIONAL TAKEOVER
AND PG TEST

2.6.1 On completion of erection, Contractor shall carry out testing, commissioning,


operational checks, instrument and device calibrations, control loop checks, interlock
and trip checks, etc, based on a systematically planned procedure. All manufacturers’
specific recommendations for testing shall be included. All test results shall be
provided to NLCIL for verification and acceptance during commissioning of the
entire system.

2.6.2 The Contractor shall do clean up of all equipment and area within project site prior
to preparing the equipment for trial run and start-up. The start up and commissioning
of the entire system shall be executed by the Contractor in a planned coordinated
sequence.

2.6.3 Power and control cabling shall be done as per approved scheme and in sections,
taking adequate precautions against electrical shocks as the solar PV cells are
capable of producing power on exposure to light. Necessary covers shall be supplied
for covering the solar PV modules during cabling termination works. Safety
precautions and manufacturers recommendations shall be strictly followed for BESS
testing and commissioning activities.

2.6.4 Calibration and commissioning of all instruments and control equipment supplied
under this contract shall be executed by the contractor. Hardware required for
erection of all instruments and control equipment covered under this contract shall
be supplied by the contractor.

2.6.5 Pre-commissioning checks, individual loop checks, power initialization, back


charging, verification of system functioning, trouble shooting, final solutions to
application and / or instrument problems etc., are contractor responsibility. All the
required software and hardware changes shall be incorporated as required for
successful commissioning to NLCIL’s satisfaction. O&M activities from part
commissioning up to provisional take over shall be carried out by the contractor at
no extra cost to NLCIL. Part commissioning shall be planned in such a way that sub-
blocks of Solar PV Plant integrated with sub – blocks of BESS shall be
commissioned, interconnected and tuned with grid parameters. On any condition
grid power shall not be used for charging BESS, however grid power shall be used
for auxiliary system, during unavailability of solar power and BESS discharge power
to feed the auxiliaries. The drawl of grid power shall be deducted from the export
and the Net Energy Export can be calculated accordingly Energy required for initial
charging shall be drawn from Solar PV Power plant.

92

Page 306 of 328


2.6.6 Supply and erect metallic tags on the equipment / instruments and accessories
supplied by the Contractor. The tags and connecting wires shall be of stainless steel
and the size of the tags shall be adequate to accommodate tag number.

2.6.7 Follow up of all the required activities to obtain A&N Administration / Central
Electrical Inspectors approval for the installation and carrying out any changes called
for by the Inspector at no extra cost to NLCIL.

2.6.8 Provisional Take over: On successful completion of commissioning, the Solar PV


Power Plant integrated with BESS along with Power Evacuation System shall be
Provisionally Taken over with a list of major and minor defects and non conformities
prepared jointly by the Purchaser and the Contractor. Differentiation of defects as
major and minor shall be jointly discussed and agreed by the Purchaser and
Contractor. Upon the completion of commissioning, as soon as practicable, or at
such time as may be otherwise agreed to by the parties concerned, the Contractor
shall notify in writing to the Purchaser that the entire system is ready for
Performance Guarantee Test only after liquidating all the major defects
.
2.6.9 The Provisional Acceptance Certificate (PAC) will be issued after necessary checks
of works by NLCIL and the contractor fulfilling all contractual obligations. The
plant will be operated and maintained by the contractor for one year from the date of
issue of Provisional Acceptance Certificate i.e., Provisional Take Over under full
warranty conditions for which no payment will be made for the contractor.
Performance Guarantee test period of one year will be concurrent with the warranty
period of one year. O&M period for balance 10 years shall commence from the date
of Final take over i.e., after successful completion of PG test period for the entire
plant and other related conditions and the O&M payment will be made as per
corresponding price schedules. No O&M payment will be made for the PG test
period/warranty period.

2.6.10 PERFORMANCE GUARANTEE TEST (PG TEST)

Performance Guarantee Test shall be carried out for the entire system for one year
after provisional take over. Guaranteed Net Energy Export in Kwhr from BESS and
Solar plant combined measured at 33KV switchyard metering station of the Grid
interconnection take off points shall be as per the following table:

93

Page 307 of 328


Annual Guaranteed Net
Energy Export in Kwhr from
BESS and Solar plant
Year combined measured at 33KV
switchyard metering station of
the Grid interconnection take
off points
PG Period(one year) 268,64,000
1 st year O&M
2,65,95,360
nd
2 year O&M 2,63,26,720
3 rd year O&M 2,60,58,080
4th year O&M 2,57,89,440
5th year O&M 2,55,20,800
6th year O&M 2,52,52,160
7th year O&M 2,49,83,520
8th year O&M 2,47,14,880
9th year O&M 2,44,46,240
10th year O&M 2,41,77,600
The procedure for PG test shall be as follows:
a) Minimum two nos. (2) calibrated Pyranometers shall be installed
by the contractor at project location mutually agreed by the
Contractor and NLCIL. The test report for the calibration shall be
submitted by the Contractor for approval by NLCIL. The output
of these Pyranometers for the PG test period shall be made
available at data logger / SCADA and EMS.
b) “Net Energy Export” shall be recorded in the metering station
and shall be taken into account for all contract durations. For this
purpose, metering station shall be erected by the contractor as per
the requirements of A&N Administration Electricity Department
to measure the net energy export. Approval from the Andaman &
Nicobar Electricity Administration Authorities in this regard is in
the scope of the contractor.
c) “Base Net Energy Export” for a month is computed by correcting
the month wise guaranteed net energy export finalised during
detailed engineering in the Annexure-1 with a factor taking into
account the actual average global solar insolation measured by
the calibrated Pyranometer for the PG period as per sl.no. (a)
above. The procedure for computation of “Base Energy Export”
is detailed in Annexure-2.
d) The measured value of net energy export as per sl.no. (b) above
shall be compared with the "Base Net Energy Export" for

94

Page 308 of 328


arriving at the difference in net energy export for the PG period
for one year, which shall be reported as + ve (or) -ve.
If the sum of difference in net energy export for the PG
period is (-) ve, there is shortfall in net energy export, based
on which the LD for performance will be calculated at the
rate and levied as detailed in Annexure -2. No incentive will
be paid if there is excess net energy export.
e) The month wise target of net energy export for 11 years with
respect to the corresponding Global Horizontal Insolation of the
project site shall be submitted along with the calculations for
NLCIL approval as per Annexure 1 format during detailed
engineering and this shall be considered for the entire contract
period for computing the “Base Net Energy Export”.

2.6.11 Following factors shall be considered while computing the “Base Net Energy
Export”
i) Actual insolation level at the project site shall be considered
while computing the base net energy export. However, effect due
to variation of metrological parameters viz., ambient
temperature, wind speed, humidity etc., shall not be considered.
ii) During the period of grid outage, back down/surrender, the
measured global solar insolation (for the period of Grid outage)
shall be excluded to calculate average global solar radiation for
the PG period.
iii) During the O&M period due to Battery replacements /
substitutions if any shall fall occurs in Annual Net Energy Export
in that year/years then the short fall in Annual Net Energy Export
shall be limited to maximum three years
iv) Along with Battery replacements/substitutions to meet the Annual
Net Energy Export re-powering of Solar PV modules. If required
shall also be included in the scope of work without any extra cost
to NLCIL

2.6.12 The contractor shall furnish the following during detailed engineering in relation to
Annexure 1 for NLCIL approval.
a. The basis, reference standards and calculations used for arriving
at the guaranteed month-wise net energy export data.
b. PV System Design Report with simulation parameters / variants,
shading diagrams, production charts, loss diagrams, etc
correlating with the above year wise net energy export data.
c. Guaranteed month-wise net energy export into the grid as per
simulation carried out using PVSYST version 5.5 or higher
version /Sun simulator/equivalent software for correlating with
the guaranteed month-wise net energy export data.

95

Page 309 of 328


2.6.13 The procedure as in 2.6.10 & 2.6.11 shall be followed for the balance 10 years
O & M period to calculate the annual net energy export as per annexure 3. For
the balance 10 years O&M period, if the sum of difference in annual net energy
export for the O & M period is (-) ve, then there is shortfall in net energy export,
based on which compensation for shortfall will be calculated at the rate and
levied as detailed in Annexure - 3. No incentive will be paid if there is excess
net energy export. During 10 years O & M contract period if any repowering of
solar PV modules and battery replacement/substitution is required to meet the
annual net energy export, the same shall be included in the scope of work
without any extra cost to NLCIL.

SECTION 2.7
QUALITY ASSURANCE, INSPECTION AND TESTING

2.7.1 GENERAL
2.7.1.1 The documents related to Manufacturing Quality plan shall be submitted for NLCIL
approval.

2.7.2 QUALITY ASSURANCE AND QUALITY CONTROL


2.7.2.1 The Contractor shall submit technical documents along with, comprehensive QA &
QC documents proposed to be adopted for this project.
2.7.2.2 All major equipments shall be inspected in line with Manufacturing Quality Plan
(MQP) issued by OEM.
2.7.2.3 No dispatches shall be made by the supplier without obtaining clearance for dispatch
from NLCIL. Wherever reworks are involved re-inspections may be conducted and
all expenditure towards the same shall be borne by the Contractor.

2.7.3 FIELD INSPECTION & TESTING


2.7.3.1 Field Quality Plans (FQP) shall detail out all the site tests / checks to be carried out
during receipt, storage, erection of the equipments. The Contractor shall furnish
copies of the erection & commissioning manuals, reference documents and
inspection procedure through soft as well as hard copy. In the Field Quality Plans,
NLCIL will identify customer hold points (CHP), i.e. test/checks which shall be
carried out in presence of NLCIL officials and beyond which the work will not
proceed without consent of NLCIL in writing. After FQP finalization and approval,
the same shall be submitted in compiled form.

96

Page 310 of 328


SECTION – 2.8
SUB VENDORS & SUB CONTRACTORS

2.8.1 Sub Vendors

i. The Contractor is responsible for performance/guarantee of the complete project


including bought out items and outsourced processes. The Contractor shall supply
the equipment /Component system from the Sub vendors approved by NLCIL.

ii. Bidder shall furnish in their bid, the proposed list of sub vendors for each of the
bought out items.

iii. The proposed list of sub vendors furnished by the successful bidder will be
finalized before start of detailed engineering.

The categorization of Sub vendors are as follows:

a) Category – I: Sub vendors accepted:

The acceptance shall be based on past experience of NLCIL.


b) Category – II: Sub vendors enlisted for future acceptance:

Such acceptance shall be based on the various details regarding


capacity, capability, and experience etc. of the sub-vendor
proposed by the successful bidder. It is the responsibility of
successful bidder to get the details and credentials of the sub
vendors under category II, compiled and submitted to Purchaser for
scrutiny and acceptance. The acceptance criteria are mentioned
below. However, Purchaser reserves the right to accept or reject any
of the proposed sub vendors based on information available with
them.
iv. The consolidated list of sub vendors under category I and category II shall be
made available to the successful bidder before start of detailed engineering.
v. Purchaser may consider the bidders proposal for inclusion of new sub vendors,
if any, during the execution stage for approval, based on the merits, in the
overall interest of the Project, after establishing that the sub vendor proposed
meets the acceptance criteria specified. However, price advantage if any, arising
out of the inclusion of new sub vendor shall be passed on to the purchaser.
vi. For all other components/equipment/systems which are not figuring in the
bought out items list, bidder’s standard practice of selecting of vendors may be
carried out.
vii. Acceptance criteria for Sub Vendors:

97

Page 311 of 328


(a) For all Mechanical, Electrical and Control & Instrumentation:

1. For Class I Items:

Bidder to furnish documentary evidence to show that similar or


higher capacity component/equipment /system has been supplied
by the vendor or their associate/collaborator and the same has
been operating satisfactorily for minimum six months as on the
original scheduled date of Tender opening. The documentary
evidence shall be in the form of Performance certificates furnished
by the end user.

2. For Class II Items:

Bidder to furnish documentary evidence to show that similar or


higher capacity component/equipment /system has been supplied
by the vendor or their associate/collaborator. The documentary
evidence shall be in the form of Material Receipt Certificate/Site
Inspection Report/ Installation or erection report etc. from the end
user, site/purchaser premises for having received the material.

(b) For structural steel :

1. The structural steel should conform to relevant Indian /


International Standards.
2. It should be of reputed make and should have been used in
similar construction / infrastructure projects.
3. The Contractor should furnish documentary evidence to
prove (1) and (2) above.

(c) For Cement and reinforcement steel:


1. It should conform to Indian / International Standard
2. It should be of reputed makes supplied to similar
construction/ infrastructure projects
3. The Contractor should furnish documentary evidence to
prove (1) and (2) above if required.
1.8.2 List of Bought out Items for which bidder to propose sub vendors:
2.8.2.1 Class I items:

Sl.No Equipment list for Class I items Sub Vendor name

1 Power Conditioning Unit


2 Array junction Box/Combiner
Box with String Monitoring Unit
3 HT Oil filled Power Transformer
4 HT indoor switchgear

98

Page 312 of 328


5 HT CT
6 HT PT
7 UPS
8 33 KV outdoor breaker
9 33 KV outdoor CT
10 33 KV outdoor PT
11 Surge Arrestor
12 Isolator
13 LT Transformer
14 HT cables
15 LT power cables/Control Cables
16 DC Cables
17 SCADA
18 Energy Management System
19 Solar PV Modules
20 Battery cells(Modules)
21 Battery Management System
22 Power Conversion System for
BESS

2.8.2.2 Class II items:

Sl No Equipment list for Class II items Sub Vendor


name
1 DC isolator
2 DC contactor
3 Numeric Relays
4 ABT Energy Meter with software
5 Surge Protection device for SMU
6 Cable termination kits
7 LED lamp fixtures for indoor
8 Flood light fittings with LED for outdoor
9 Fire protection system
10 Fire detection alarm panel
11 HVAC
2.8.3 Acceptance Criteria for approval of Sub Contractors for
erection works.
For Mechanical, Civil, Electrical and Control & Instrumentation erection works are
as follows:
In case the bidder is engaging a sub contractor for Mechanical, Civil, Electrical and
Control & Instrumentation erection works, documentary evidence shall be furnished
in the form of contract award copy and performance certificate (End user’s
certificate) to show that similar works were carried out and the job has been
completed satisfactorily by the sub contractor as on the original scheduled date of

99

Page 313 of 328


Tender opening and approval shall be obtained from Purchaser, prior to engaging
them for Mechanical, Civil, Electrical and Control & Instrumentation erection works.

SECTION 2.9

OPERATION AND MAINTENANCE (O&M)

2.9.1 GENERAL

2.9.1.1 The Bidder shall carry out O&M activities for the entire System including its
associated civil structures, roads, Power export Switchyard and control room
buildings, Security of the plant Buildings, Garden etc. The O & M activities also
includes the entire power evacuation system comprising of UG Cables, transmission
lines of grid take off points of the existing 33kV feeders connection point, gantries
and allied equipments up to the terminal point of connectivity for a period of 11
years including one year warranty.

2.9.1.2 Operation work includes day-to-day operation of the entire system. The
responsibility of ensuring uninterrupted operation of the entire system lies with the
contractor or else it will attract penalty/loss of compensation as per relevant clauses
of the specification.

2.9.1.3 The contractor shall furnish proposed maintenance (preventive) schedule for the
operation and maintenance of the entire system for NLCIL approval. As the O&M
contract period is for 11 years including warranty period, the long term
maintenance/replacement schedule indicating the unit replacement of
parts/equipments, if any, shall also be furnished considering the life of such
parts/equipments. Equipment overhaul schedule indicating the loss of generation
during such periods, if any, and the proposed catch up plans for maintaining the
scheduled/committed generation shall also be furnished.

2.9.1.4 The maintenance staff for the Entire System shall be available at all times in the
plant premises.

2.9.1.5 The Contractor shall maintain attendance register for all their staff deployed for
carrying out jobs on regular basis and shall be produced for verification on demand
by authorized personnel of NLCIL.

2.9.1.6 The Contractor shall ensure that all safety measures are taken at the site to avoid the
accidents to his employees or his sub Contractor employees.

2.9.1.7 In order to ensure longevity, safety of the core equipment and optimum performance
of the system, the Contractor shall use only genuine spares of high quality standards.

100

Page 314 of 328


2.9.1.8 The O & M charges as per price schedule are inclusive of replacement of
parts/equipments, systems, spares, consumables, etc.

2.9.2 SCOPE

2.9.2.1 The Contractor shall provide his operation and maintenance staff for the entire
system for day-to-day operation and maintenance. The operation and maintenance
personnel shall be qualified, certified by competent authorities and well trained so
that they can handle any type of operational hazards quickly and timely. The
responsibility of providing suitable Personal Protection Equipments rests solely with
the contractor.

2.9.2.2 The security of the entire plant area shall rest with the contractor, till final take over
by NLCIL after completion of the contract period.

2.9.2.3 The maintenance personnel shall be in a position to check and test all the equipments
regularly, so that, preventive maintenance, could be taken well in advance to save
any equipment from damage. Abnormal behaviour of any equipment shall be
brought to the notice of NLCIL not later than 2 hours for taking appropriate action.

2.9.2.4 All repairing & replacement works are to be completed by the Contractor within
reasonable time from the time of occurrence of fault or defect If it is not possible to
set right the equipment within reasonable time, the Contractor shall notify NLCIL
indicating nature of fault & cause of damage etc. within 12 hours from the time of
occurrence of the fault.

2.9.2.5 During operation and maintenance, if there is any loss or damage to any component
of the power plant and the BESS due to miss-management/ miss-handling or due to
any other reasons, what so ever, the Contractor shall be responsible for immediate
replacement / rectification of the same. The damaged component may be repaired, if
it is understood after examination that performance of the components shall not be
degraded after repairing, otherwise the defective components shall have to be
replaced by new one without any extra cost to NLCIL.

2.9.2.6 The scope of maintenance work shall include the following:

2.9.2.6.1 Regular operation and maintenance of the entire System and submission of daily
performance to NLCIL. The Contractor shall maintain log book in this respect to
clearly record the date of checking & comments for action taken etc.

2.9.2.6.2 The scope of operation and maintenance includes all equipments/accessories of the
entire system and proper records of operation of the entire System shall be kept as
per direction of NLCIL.

101

Page 315 of 328


2.9.2.6.3 Cleaning of the entire areas, buildings, array yard, electrical panels, containers etc.
shall be carried out on regular basis.

2.9.2.6.4 Normal and preventive maintenance of the entire system shall be carried out on
regular basis.

2.9.2.6.5 Keeping & recording daily log sheet as per approved format shall be maintained
after commissioning of the entire system.

2.9.2.6.6 Under no circumstances, the contractor shall run the system in such a way that will
damage the grid.

2.9.2.6.7 The contractor shall submit monthly Performance report of entire system indicating
net energy export data as per approved format within three days of the following
month. The reporting shall also include any mismatch or abnormality in the
performance of the system based on SCADA and EMC details for review. Day to
day coordination with A & N Administration Electricity department and submitting
reports, details required by them shall also under the scope of the O & M contract.

2.9.2.6.8 The Contractor shall preserve all recorded data in both hard copy and soft copy
format and shall submit to NLCIL every month.

2.9.2.6.9 The Contractor shall develop & maintain gardens, which shall be developed by the
Contractor himself as per landscaping including daily watering and manuring as and
when necessary and on regular basis.

2.9.2.6.10 During operation and maintenance period, the Contractor shall refill the fire
extinguishers as per manufacturer’s recommendation before expiry.

2.9.3 TOOLS AND TACKLES

2.9.3.1 Tools and tackles is not a supply item. A list of tools and tackles which are required
for O & M of the entire system shall be maintained by the contractor for use during
the O & M period. The contractor shall maintain all regular/special O&M tools apart
from the tools and tackles.

2.9.3.2 Such special tools used by the contractor during operation and maintenance period
shall be handed over to NLCIL at the time of completion of 11 years O&M period
including warranty period.

2.9.4 TESTING INSTRUMENTS FOR ELECTRICAL & ELECTRONICS

2.9.4.1 The Contractor shall provide all details of onsite testing instruments / equipments.
Details of equipment / instrument, make, numbers, range, accuracy, etc shall be
furnished to NLCIL

2.9.5 SCOPE OF CIVIL MAINTENANCE

102

Page 316 of 328


2.9.5.1 Cleaning of surface drain, sewerage line, drainage outfall, down pipes, soil pipes,
water pipe lines.

2.9.5.2 Repairs, replacements, cleaning of all joineries etc as and when necessary shall be
carried out by the contractor.

2.9.5.3 Repairing or replacement, whatever necessary, of doors, window fixtures, toilet


accessories, etc in control room and other buildings as and when necessary.

2.9.5.4 Cleaning & maintaining of power plant area clearing all weeds, leaves and other
wood rejects. Vegetation removal inside the power plant and also vegetation removal
& cutting of trees/branches en route the transmission lines of the power evacuation
system up to Grid Connecting substation on periodical basis as directed by NLCIL.

2.9.5.5 Painting of iron parts of array structures posts once in a year.

2.9.5.6 Painting of the buildings, structures/PCSS, Security room, fencing posts, gates,
transmission towers, and extension bays etc once in two years.

2.9.5.7 All minor repair maintenance in case of buildings and all other structures as and
when required as per the instructions of Project Manager/NLCIL.

2.9.6 OTHERS

2.9.6.1 Any Electrical /Civil maintenance work which are not mentioned or included here
but necessary for the entire life of the project shall be carried out by the Contractor.

103

Page 317 of 328


ANNEXURE – 1
Guaranteed Month-wise Net Energy Export at metering station of 33KV switchyard outgoing feeders.

Guaranteed Net Energy Export during O&M


st
PG test period (1 Year) 2rd Year 3rd Year 4th Year
Estimated
monthly (kWh) (kWh) (kWh) (kWh)
average
Global Solar
Sl.No. Month Insolation on Annual Guaranteed Net Energy Annual Guaranteed Net Energy Annual Guaranteed Net Energy
Annual Guaranteed Net Energy
horizontal Export in Kwhr of the Export in Kwhr of the Export in Kwhr of the
Export in Kwhr of the smoothened
smoothened Power from BESS smoothened Power from BESS smoothened Power from BESS
plane and Solar plant combined and Solar plant combined and Solar plant combined
Power from BESS and Solar plant
(kWh / m2 / combined measured at 33KV
measured at 33KV switchyard measured at 33KV switchyard measured at 33KV switchyard
switchyard metering station of the
Day) metering station of the Grid metering station of the Grid metering station of the Grid
Grid interconnection take off points
interconnection take off points interconnection take off points interconnection take off points

1 January 5.65
2 February 6.47
3 March 6.83
4 April 6.65
5 May 5.08
6 June 4.38
7 July 4.45
8 August 4.45
9 September 4.64
10 October 4.99
11 November 4.86
12 December 5.19
Annual -

104

Page 318 of 328


Guaranteed Net Energy Export during O&M
th
5 Year 6th Year 7th Year 8th Year
(kWh) (kWh) (kWh) (kWh)
Estimated
monthly average
Global Solar Annual Guaranteed Net Energy Annual Guaranteed Net Energy Annual Guaranteed Net Energy Annual Guaranteed Net Energy
Sl.No. Month
Insolation on Export in Kwhr of the Export in Kwhr of the Export in Kwhr of the Export in Kwhr of the
horizontal plane smoothened Power from BESS smoothened Power from BESS smoothened Power from BESS smoothened Power from BESS
(kWh / m2 / Day) and Solar plant combined and Solar plant combined and Solar plant combined and Solar plant combined
measured at 33KV switchyard measured at 33KV switchyard measured at 33KV switchyard measured at 33KV switchyard
metering station of the Grid metering station of the Grid metering station of the Grid metering station of the Grid
interconnection take off points interconnection take off points interconnection take off points interconnection take off points

1 January
2 February
3 March
4 April
5 May
6 June
7 July
8 August
9 September
10 October
11 November
12 December
Annual -

105

Page 319 of 328


Guaranteed Net Energy Export during O&M
Estimated 9th Year 10th Year 11th Year
monthly (kWh) (kWh) (kWh)
average
Global
Solar
Sl.No. Month Insolation Annual Guaranteed Net Energy Annual Guaranteed Net Energy Annual Guaranteed Net Energy
Export in Kwhr of the Export in Kwhr of the Export in Kwhr of the
on
smoothened Power from BESS smoothened Power from BESS smoothened Power from BESS
horizontal and Solar plant combined and Solar plant combined and Solar plant combined
plane measured at 33KV switchyard measured at 33KV switchyard measured at 33KV switchyard
(kWh / m2 metering station of the Grid metering station of the Grid metering station of the Grid
interconnection take off points interconnection take off points interconnection take off points
/ Day)

1 January
2 February
3 March
4 April
5 May
6 June
7 July
8 August
9 September
10 October
11 November
12 December
Annual -

106

Page 320 of 328


Note for Annexure -1:
1) The basis and reference standards used for arriving at these data shall be furnished.
2) PV Syst Calculations, Design Report with simulation parameters / variants, shading diagrams, production charts, loss diagrams, etc. shall be furnished correlating with
the above month wise Guaranteed Net Energy Export data.
3) Design Report calculations and parameters of BESS shall be furnished correlating with the above month wise Guaranteed Net Energy Export data of the smoothened
power from BESS and Solar Plant combined, measured at 33KV switchyard metering station of the Grid interconnection take off points .

107

Page 321 of 328


ANNEXURE 2
COMPUTATION OF SHORTFALL IN NET ENERGY EXPORT (for PG test period)

Guaranteed Net Energy Measured Net Energy


Estimated monthly Export in Kwhr of the
Measured average Global
Export in Kwhr of the
average Global Solar smoothened power from smoothened power from Base Net Energy Export at
Solar Radiation on the Difference in Net energy
BESS + solar combined BESS+ solar combined metering stations of 33KV
Sl. Insolation on measured at 33KV
horizontal surface during
measured at 33KV switchyard outgoing feeders
export in KWhr for the
Month/ horizontal plane PG period at site by PG period,
switchyard metering station switchyard metering station in kWh
Pyrometer
Day/Time (kWh / m2 / Day) of the Grid interconnection of the Grid interconnection
take off points take off points

No. (b) kWh / m2 / day (d) (e) = (b) x (c)/(a) report as + ve (or) -ve

(a) (c) (f)=(d)-(e)

1 Jan 5.65
2 Feb 6.47
3 Mar 6.83
4 April 6.65
5 May 5.08
6 Jun 4.38
7 Jul 4.45
8 Aug 4.45
9 Sep 4.64
10 Oct 4.99
11 Nov 4.86
12 Dec 5.19
Annual -

108

Page 322 of 328


Note for Annexure - 2: (for PG test period)

1. The measured Net Energy export shall be calculated by adding all the net export values of the billing meters installed in the 33 KV Power Export
switchyard outgoing feeders.
2. If sum (f) is negative (-), there is shortfall in annual guaranteed Net Energy export during solar hours for PG test period
I. Short fall in Net Energy export for PG test period (Annually) : ________kWh
II. LD for shortfall in net energy export for PG test period : Rs. Per kWh
III. Total Penalty payable : Rs. ______ Item (i) x Item (ii)

109

Page 323 of 328


ANNEXURE 3
COMPUTATION OF NET ENERGY EXPORT DURING O & M PERIOD

Guaranteed Net Energy Measured Net Energy


Export in Kwhr of the Export in Kwhr of the
Estimated monthly smoothened power from Measured average smoothened power from
average Global Base Net Energy Export at
solar + BESS combined Global Solar Radiation solar + BESS combined Difference in Net energy
metering stations of 33KV
Sl. Solar Insolation on measured at 33KV on the horizontal surface measured at 33KV
switchyard outgoing feeders
export in KWhr for the PG
horizontal plane switchyard metering during PG period at site switchyard metering period,
Month/ Day/Time in kWh.
station of the Grid by Pyranometer station of the Grid
(kWh / m2 / Day) interconnection take off interconnection take off
points points

No. (b) kWh / m2 / day (d) (e) = (b) x (c)/(a) report as + ve (or) -ve

(a) (c) (f)=(d)-(e)

1 Jan
2 Feb
3 Mar
4 April
5 May
6 Jun
7 Jul
8 Aug
9 Sep
10 Oct
11 Nov
12 Dec
Annual -

110

Page 324 of 328


Note for Annexure 3 (For balance 10 years O & M period):

1. The measured Net Energy export shall be calculated by adding all the net export values of the billing meters installed in the 33 KV Power Export
switchyard outgoing feeders.
2. If sum (f) is negative (-), there is shortfall in annual guaranteed Net Energy export for balance 10 years O & M period.
I. Short fall in Net Energy export for O & M period (Annually ) : ________kWh
II. Compensation for shortfall in net energy export for O & M period : Rs. Per kWh
III. Total Compensation payable : Rs. ______ Item (i) x Item (ii)
3. During the O & M period due to Battery replacements/substitutions if any short fall in sum (f) occurs, the corresponding penalty as per 3(iii) shall be
deducted in that year/years. If the above shortfall is compensated in the subsequent years Annual Net Energy Export (which shall be limited to maximum
three years), then the corresponding amount of compensation shall be returned in the corresponding subsequent years

111

Page 325 of 328


10MW (AC) Battery Energy 10MW (AC) Solar
Solar PV Power Storage System PV Power Plant at Auxiliary system
Plant at Attam (BESS) Dolly Gunj
Pahad

Project Control
room

Metering Station

33kV 33KV
GARACHARMA Existing 33KV Grid feeders BAMBOOFLAT
SUBSTATION (Panther 1& Panther 2) SUBSTATION

Chatam Bay Power House IPP 20MW (DG sets-


(DG sets- 6x2.5MW) substation Bidder’s Scope 4x5MW)
Note: 1. This block diagram is tentative and for tender purpose only.
2. The entire scheme shall be finalised during detailed engineering to suit Grid/system requirement as per contract conditions.

NLC India Limited PROJECT: 2X10MW (AC) SOLAR


PV PROJECT INTEGRATED WITH Title Drawing No Rev No: 00
8MWHr BESS, AT ATTAM
PAHAD AND DOLLY GUNJ,
General Block Diagram NLCIL/PBD/Andaman/01 Date: 02.03.2018
PORT BLAIR, SOUTH ANDAMN

112

Page 326 of 328


FOR TENDER PURPOSE ONLY
NLC India Limited PROJECT: 2X10MW (AC)
SOLAR PV PROJECT Title
INTEGRATED WITH 8MWHr
Drawing number Rev No:00
BESS, AT ATTAM PAHAD
AND DOLLY GUNJ, PORT
BLAIR, SOUTH ANDAMN Attam Pahad Site map NLCIL/PBD/Andaman/02 Date: 02.03.2018

113

Page 327 of 328


FOR TENDER PURPOSE ONLY
NLC India Limited PROJECT: 2X10MW (AC)
SOLAR PV PROJECT
INTEGRATED WITH 8MWHr
Title Drawing number Rev No:00
BESS, AT ATTAM PAHAD
AND DOLLY GUNJ, PORT
BLAIR, SOUTH ANDAMN Dolly Gunj Site map NLCIL/PBD/Andaman/03 Date: 02.03.2018

114

Page 328 of 328