PMBOK standard – project management body of knowledge
A Project
- Goal
- Works project plan
- Resources (people, $, time, technologies, materials, info)
- Constraints ~limitations
Project – temporary endeavor undertaken to create new(unique) products, services, or
results
Operating activities – permanent repetition of the same operations in order to produce the
same product (or render the same service)
Examples: mass production, selling typical products, accounting transactions, etc
Difference between operating activities and project related activities
// breakeven point
If we don’t fit into time frame, LOST BENEFITS
A program refers to a group of related projects managed in a coordinated way to obtain
benefits and control not available from managing them individually для получения
преимуществ и контроля недоступных при индивид управлении
A portfolio refers to a collection of projects or programs and other work grouped together
to facilitate effective management for the purpose of reaching an organization’s strategic
business goals
Project success criteria
A project is successful if its completed
- On time
- On budget
- To the customer’s satisfaction
Project constraints : scope / cost / time
How successful are projects :
1. Successful 29%
2. Unsuccessful 53% (none of the projects goals have been achieved)
3. Failed 18% (projects either have not been completed at all or have been completed
but the results are not being used)
PROJECT MANAGEMENT STANDARDS best practices interaction certification systemic
picture
CLASSIFICATION OF PROJECT MANAGEMENT APPROACHES
1. Predictive (classic)
2. Iterative (flexible)
3. Hybrid
CLASSIC APPROACH – WATERFALL MODEL
The model assumes the transition to the next stage after the complete completion of the
previous stage and is characterized by a clear separation of data and processing processes
EXPENSIVE because of changing requirements and errors made at any of stages
FLEXIBLE APPROACH – INCREMENTAL MODEL
The series of releases is referred to as “increments”, with each increments providing more
functionality to the customer
1 increment – core product
HYBRID APPROACH = CLASSIC + FLEXIBLE
Key principles and elements defined in both flexible and traditional methods
One branch – using agile
Other branches – classic waterfall model
PROJECT MANAGEMENT INSTITUTE PMI
PMI certification
PMI STANDARDS
CONTENT OF STANDARD
PROJECT SHAREHOLDERS
FUNCTIONAL ORGANIZATION
PROJECTED ORGANIZATION
WEAK MATRIX ORGANIZATION
BALANCED MATRIX ORGANIZATION
STRONG MATRIX ORGANIZATION
MIXED MATRIX ORGANIZATION
PROJECT MANAGEMENT IN DIF ORGANIZATIONS
PROJECT LIFE CYCLE
The project is divided into phases (stages) each phase is to finish with a tangible
verifiable work product (deliverable) in the end of each stage, a decision is taken
whether to initiate a new phase or close (suspend) the project (kill point)
ITS CRUCIAL TO PROMPTLY CLOSE A PROJECT IN CASE OF ITS FAILURE
SAMPLE PROJECT LIFE CYCLE
DEPENDENCY OF COSTS AND HR INVOLVED UPON THE PROJECT PHASE
ABILITY TO INFLUENCE THE PROJECT DELIVERABLE AND COST OF CHANGE
PROJECT AND PRODUCT LIFE CYCLE
PROJECT MANAGEMENT PROCESS (PMP) GROUPS // initiating process - beginning /
planning – first part / executing – second part/ monitoring and controlling – all the time /
closing - ending
LEVEL OF ACTIVITY OF PMP IN THE PROJECT LIFE CYCLE
INTERACTION BETWEEN PHASES / KILL POINT BETWEEN THEM
PM AREAS OF KNOWLEDGE AND PROCESSES (dif types of management – integration,
scope, schedule, cost, quality, resource, communications, risk, procurement, stakeholders)
PROJECT INTEGRATION MANAGEMENT
1. Initiating processes – develop project charter
2. Planning – develop project management plan
3. Executing – direct and manage project execution, manage project knowledge
4. Monitoring and controlling – perform integrated change control, monitor and
control project work
5. Closing – close project (phase)
DEVELOP PROJECT CHARTER
INPUTS :
Business documents
Agreements
Enterprise environmental factors
Organizational process assets
Tools :
Expert judgment
Data collection
Interpersonal and communication skills
Meetings
Outputs
Project Charter
Assumptions Log
ENTERPRISE ENVIRONMENTAL FACTORS
- Governmental and industry standards
- Organization infrastructure
- Marketplace conditions
ORGANIZATIONAL PROCESS ASSETS : policies / templates / historical info / lessons
THE PROJECT CHARTER INCLUDES
Business case / project objectives / success criteria / requirements, risks / schedule / budget
/ approval requirements / responsibility, assigned project manager / project sponsor
SMART OBJECTIVES – specific, measurable, achievable, result-oriented, time-bounded
THE CHARTER AUTORIZES THE PROJECT
DEVELOP PROJECT MANAGEMENT PLAN
INPUTS:
Project charter
Outputs from planning processes
Enterprise environmental factors
Organizational process assets
TOOLS:
Expert judgment
OUTPUTS:
Project management plan
The development of a project plan is an iterative & integration process
THE SCALE AND COMPOSITION OF THE PLAN ARE TO BE IN LINE WITH THE SCALE AND
IMPORTANCE OF THE PROJECT
DIRECT AND MANAGE PROJECT WORK
INPUTS:
Project management plan
Approved change requests
Enterprise environmental factors
Organizational process assets
TOOLS:
Expert judgment
Project management information system PMIS
OUTPUTS:
Deliverables
Work performance data
Change requests
Project management plan updates
Project document updates
Project execution – the major process in the project implementation
THE PROJECT MANAGEMENT PRINCIPAL DUTIES :
MANAGE PROJECT KNOWLEDGE
INPUTS:
Project management plan
Project deliverables
Enterprise env factors
Org process assets
TOOLS:
Expert judgment
Manage knowledge
Interpersonal and communication skills
PMIS
OUTPUTS:
Lessons learned update
Project management plan updates
Project document updates
MANAGE PROJECT KNPWLEDGE includes creation of conditions ensuring effective usage of
project team and stakeholders experience and competencies through the whole project life
cycle and after it’s completion
MONITOR AND CONTROL PROJECT WORK
INPUTS:
Project management plan
Performance reports
Enterprise env factors
Organizational process assets
TOOLS:
Expert judgment
OUTPUTS:
Change requests
Project management plan updates
Project document updates
MONITORING – OBSERVING
CONTROL – COMPARING the project CURRENT STATUS against what it SHOULD BE
If the project status doesn’t comply with the plan – there is a VARIANCE
// Change request – changes may include: corrective actions, preventive actions, defect
repair
Changes may have an impact on product and project scope
PERFORM INTEGRATED CHANGE CONTROL
INPUTS:
Project management plan
Work performance data
Change requests
Enterprise env factors
Org process assets
TOOLS:
Change control meetings
Expert judgment
OUTPUTS:
Change request status update
Project management plan updates
Project document updates
Depending upon their impact on the project, changes may be approved or rejected by the
PROJECT MANAGER, the SPONSOR, the CUSTOMER or the CHANGE CONTROL BOARD
// project process adjustment // virance
If it’s too big than change is necessary !!! CHANGE CONTROL BOARD
CLOSE PROJECT OR PHASE
INPUTS:
Project management plan
Accepted deliverables
Org process assets
TOOLS:
Expert judgment
OUTPUTS:
Final product, service, result transaction
Organizational process assets updates
PROJECT SCOPE MANAGEMENT
Panning – plan scope management, collect requirements, define scope, create WBS
Monitoring and controlling – verify scope and control scope
Project scope management focuses on defining and controlling all the required activities
aimed at successful completion and closure of the project
CONTINUES THROUGHT THE WHOLE PROJECT LIFE CYCLE
Project scope – the work that must be done to deliver the product / product scope –
features of a product
COLLECT REQUIRMENTS
INPUTS:
Project charter
Stakeholder register
TOOLS:
Interviews
Focus groups
Observations etc
OUTPUTS:
Stakeholder requirmerts documentation
Requirements management plan
Requirements traceability matrix
Collect requirments
Stakeholder requirements documentation
REQUIREMENTS MANAGEMENT PLAN
REQUIREMENTS TRACEABILITY MATRIX
DEFINE SCOPE
INPUTS:
Project charter
Stakeholder requirements documentation
Org process assets
TOOLS:
Expert judgment
Product analysis
Alternatives analysis
Facilitated workshops
OUTPUTS:
Project scope statement
Project document updates
The project management scope statement describes in detail the project deliverables and
the work required to create those deliverables
Scope statement – a detailed document describing project scope and prepared based on
the previously developed project charter and documented stakeholders’ requirements
SECTIONS OF THE PROJECT SCOPE STATEMENTS
SCOPE is a basis for any further plans and decisions
1. PRODUCT SCOPE DESCRIPTION
2. PRODUCT ACCEPTANCE CRITERIA
3. PROJECT DELIVERABLES
4. PROJECT BOUNDARIES // project in scope and out of scope
5. PROJECT CONSTRAINTS – factors limiting the project team work and the project
scope
6. PROJECT ASSUMPTIONS – factors considered to be true, real
CREATE WORK BREAKDOWN STRUCTURE (WBS)
INPUTS:
Project scope statement
Stakeholder requirements documentation
Organizational process assets
TOOLS:
Decomposition
OUTPUTS:
WBS
WBS dictionary
Scope baseline
Project document updates
Decomposition – subdividing of a project’s goals and works into smaller and more
manageable components
Baisis principle / the principle of work packages
WBS is a next step in developing and elaborating the project scope after the scope
statement
WBS lower level constitutes work packages
Breakdown continues down to the levels for which realistic evaluation is possible in terms
of
Timing
Cost
risks
WBS dictionary : owner, contractual info, quality requirements, technical specification etc
VERIFY SCOPE
INPUTS:
Project management plan
Stakeholder requirements documentation
Requirements traceability matrix
Validated deliverables
TOOLS:
Inspection
OUTPUTS:
Accepted deliverables
Change requests
Project document updates
Verifying scope – the process of formalizing acceptance of the project deliverables by the
stakeholders
CONTROL SCOPE
INPUTS:
Project management plan
Work performance data
Stakeholder requirements doc
Requirements traceability matrix
Org process assets
TOOLS:
Variance analysis
OUTPUTS:
Work performance measurements
Change requests
Org process assets updates
Project management plan updates
Project document updates
Any change of the scope should undergo an integrated change control
PROJECTS SCHEDULE MANAGEMENT
DEFINE ACTIVITIES
SEQUENCE ACTIVITIES
Precedence diagramming method // the most common technique nowadays
Mandatory dependencies / discretionary / external
4 KINDS OF DEPENDENCIES : finish to start, start to start, finish to finish, start to finish
ESTIMATE ACTIVITY DURATIONS
To estimate activity duration the following info is used:
Activity scope
Required resource types
Required resource quantities
Recourse calendars
Methods of activity duration estimating: expert judgment, analogous estimating,
parametric estimating, PERT estimation
DEVELOP SCHEDULE
// A critical path – early and late start and finish for each activity
ES=LS or EF=LF – on critical path
At least 1 critical path
RECOURSE-ADJUSTED CRITICAL PATH
Critical path / critical chain
RESOURCE LEVELLING
SCHEDULE COMPRESSION
Crashing / fast tracking
GRAPHICAL REPRESENTATION OF A SCHEDULE – network diagram / gantt network chart /
milestone chart
Approved schedule – BASELINE
CONTROL SCHEDULE
PROJECT COST MANAGEMENT
ESTIMATE COSTS
ESTIMATING THE COST OF RESOURCES NEEDED
Analogous estimating / parametric estimating / bottom-up estimating
Vendor bid analysis / reserve analysis / cost of quality
Types of estimates : order of magnitude / definitive estimate
DETERMINE BUDGET
1. Determine work (WBS and activities)
2. Develop Schedule
3. Develop cost baseline
4. Cost baseline
CONTROL COSTS
EARNED VALUE MEASUREMENT
Planned value (PV), earned value (EV), actual cost (AC)
Cost variance (CV), schedule variance (SV), cost performance index (CPI), schedule
performance index (SPI)
// example
MEASURE ANALYSIS (under/over budget, behind, ahead of schedule)
TO-COMPLETE PERFORMANCE INDEX – TCPI
numerator/denominator
PROJECT QUALITY MANAGEMENT
QUIALITY description
PMI’S KEY PRINCEPLES OF PROJECT QUALITY MANAGEMENT
customer satisfaction / prevention over inspection / continuous improvement
QUIALITY MANAGEMENT EQUALLY RELATES TO
- project management
- project’s product
PLAN QUALITY
AUDIT OF PROJECT WORKS AND CONTROL OF PROJECTS WORKS RESULTS
project scope – works – quality assurance / product scope – features – quality control
COST OF QUALITY – cost of conformance / cost of nonconformance
DECREASING COST DURING QUALITY MANAGEMENT
MANAGE QUALITY
Quality assurance examples:
- auditing the product creation process
- auditing project management quality
Performing quality assurance is the primary objective of independent quality experts in
charge of organizing a number of project reviews
Project contract review / project solution review / project implementation review /
project organization review
PERFORM QUALITY CONTROL
MAJOR QUALITY CONTROL TOOLS
1. Cause and effect diagram
2. Flowchart
3. Run chart
4. Control chart
5. Pareto diagram
6. Histogram
7. Scatter diagram
PROJECT RESOURCE MANAGEMENT
RESOURCE MANAGEMENT PLANNING
DEVELOP HUMAN RESOURCE PLAN
A human resource plan is a part of the project management plan describing when and how
human resource requirements will be met
INCLUDES : staff acquisiotion / timetable / staff release plan / complience etc
ROLES AND RESPONSIBILITY DEFINITION FORMATS
Hierarchical-type organization chart / text-oriented format
PROJECT HIERARCHICAL-TYPE ORGANIZATION CHART EXAMPLE
RESPONSIBILITY ASSIGNMENT MATRIX
ESTIMATE ACTIVITY RESOURCES
RESOURCE ESTIMATING
- What resources are to be used in activities?
- In what quantities will the resources be required?
- When will the resource be available ?
ACQUIRE PROJECT TEAM
SELECTION CRITERIA : professional knowledge and skills, professional experience / record,
candidate’s motivation, business competencies
DEVELOP PROJECT TEAM
In order to efficiently manage project personnel basic behavior motives are to be known
Maslow’s hierarchy of needs
MANAGE PROJECT TEAM
CONFLICTS AND THEIR ROLE
THE WAYS OR RESOLVING CONFLICTS WITHIN A PROJECT:
- Withdrawing/avoiding
- Smoothing/ accommodating
- Compromising
- Forcing
- Cooperating
- Confronting/ problem solving
Major reasons for conflicts in a project
QUALITIES A PROJECT MANAGER NEEDS TO POSSESS:
- Leadership
- Influence
- Effective decision-making
MAJOR TYPES OF POWER IN A PROJECT
Formal / reward / penalty / expert / referent
CONTROL RESOURCES
PROJECT COMMUNICATIONS MANAGEMENT
COMMUNICATION MANAGEMENT PLANNING
PLAN COMMUNICATIONS
Communication technology factors include
The communications management plan may include the following sections
MANAGING COMMUNICATIONS
DISTRIBUTE INFORMATION
Communication methods
LESSONS LEARNED KNOWLEDGE BASE
LESSONS LEARNED cover all the project areas
It’s useful to describe:
- What you’ve done right
- What you’ve done wrong
- What you would have done differently if it were possible to return into the past
MONITOR COMMUNICATIONS
REPORT PERFORMANCE – the process of collecting and distributing performance
information to provide stakeholders with reliable information on the activities performed
and resources spent
Performance reports may include the following:
PROJECT RISK MANAGEMENT
PROJECT RISK is an uncertain event or condition that, if it occurs, has a positive or negative
effect on at least one project objective, e.g time, cost, scope, quality
Known risks / unkown risks
PROJECT RISK MANAGEMENT CYCLE
PLAN RISK MANAGEMENT
A risk management plan describes how all risk management processes will be performed
RSIK BREAKDOWN STRUCTURE
IDENTIFY RISKS
SOURCES OF RISK-RELATED INFORMATION
- Product description
- Assumptions
- Historical information
INFORMATION GATHERING TECHNIQUES
- Brainstorming
- Delphi technique
- Interviewing
- Root cause analysis
CHECKLIST ANALYSIS
CONTENTS OF THE RISK REGISTER
- List of risks with the required level of detail
- List of potential response strategies for the identified risks
PERFORM QUALITATIVE RISK ANALYSIS
SAMPLE RISK SCORE MATRIX (critical, moderate, low risks)
RISK MIGRATION
PERFORM QUNTITIVE RISK ANALYSIS
PROCESS OUTPUTS:
COST RISK SIMULATION RESULTS
PLAN RISK RESPONSES
STRATEGIES FOR NEGATIVE RISKS AND THREATS TO THE PROJECT
Risk avoidance / risk transference / risk mitigation
STRATEGIES FOR POSITIVE RISKS AND OPPORTUNITIES TO THE PROJECT
Risk exploit, risk share, risk enhance
STRATEGY FOR BOTH THREATS AND OPPORTUNITIES
// acceptance – a strategy when the risk is accepted, the project team doesn’t try to
influence the risk
It is often used in situations with limited opportunities to influence and when the risk
impact is immaterial
IMPLEMENT RISK RESPONSES
MONITOR RISKS
PROJECT PROCUREMENT MANAGEMENT
PLAN PROCUREMENTS
MAKE-OR-BUY DECISION
MAJOR TYPES OF CONTRACTS
Fixed price or lump sum / cost-reimbursable / time and materials
The contract type and deliverable acceptance criteria
THE PROCESS MAJOR DELIVERABLE is THE PROCUREMENT MANAGEMENT PLAN, which
describes:
- What to procure and how much to procure?
- When to procure?
- How to procure? (contract type selection)
- The circle of potential suppliers
TYPES OF PROCUREMENT DOCUMENTS
CONDUCT PROCUREMENTS
Proposals – are the documents prepared by the seller and describing the seller’s intentions
and ability to provide products or services specified in procurement documents
- They are prepared in accordance with the requirements specified in procurement
documents
- They constitute official and valid offer
The following is used when selecting a seller:
- Weighting system
- Expert judgments
- Seller rating systems
- Screening system
MAJOR SECTIONS OF THE CONTRACT INCLUDE
CONTROL PROCUREMENTS
Project manager’s role in administering procurements:
PROJECT STAKEHOLDERS MANAGEMENT
IDENTIFY STAKEHOLDERS
Analysis of stakeholder groups
The stakeholder management strategy defines an approach to increase the support and
minimize negative impacts of stakeholders throughout the entire project life cycle
Stakeholder analysis matrix
STAKEHOLDERS MANAGEMNT PLANNING
Stakeholders management plan
MANAGING STAKEHOLDERS ENGAGEMENT
Interpersonal skills:
- Building trust
- Resolving conflict
- Active listening
- Overcoming resistance to change
Management skills:
- Presentation skills
- Negotiation skills
- Writing skills
- Public speaking
ISSUE LOG
STAKEHOLDERS’ REACTION TO THE PROJECT – support / expectation / counteraction
The project manager’s task is to win stakeholder’s support
ASPECTS THAT SHAPE STAKEHOLDERS’ ATTITUDE TOWARDS THE PROJECT
MONITOR STAKEHOLDERS ENGAGEMENT