M/S LLOYD INSULATIONS (I) LTD Date31-01-2020
DAILY PROGRESS REPORT
Client- M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat
COMPLETED AREA TODAY PROGRESS BALANCE AREA
RELEASE FOR
INSULATION NEXT DAY PLAN
S.N. Description TOTAL SCOPE UOM
LAGGING CLADDING LAGGING CLADDING LAGGING CLADDING
LAGGING CLADDING Remarks
1 EQUIPMENTS 2530 RMT 2530 2530 2530 0 0 0 0 0 0
2 REFORMER PACKAGE 2000 RMT 2000 1780 1460 60 160 540 50 40
3 PIPLINE-IH 10000 RMT 10000 9115 6930 80 885 3070 80 100 1500 was realsed on 08-01-2020
4 PIPLINE(VALVE & F) 1300 M2 Not released 0 0 0 0 0 0 Item are not available in work order
5 PIPLINE-IT 1000 RMT 1000 250 220 60 30 750 780 50 50 Released on 30-12-2019
6 PIPLINE-IS 1053 RMT 1053 30 20 20 1023 1033 0 0
FIREPROOFING SYSTEM
7 ON CABLE DUCTS/TRAYS 1038 RMT Not released 0 0 0 0 0 0 0 0
AND FITTING