0% found this document useful (0 votes)
52 views1 page

M/S Lloyd Insulations (I) LTD Date31-01-2020 Daily Progress Report Client-M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat

The document is a daily progress report from an insulation company working on a refinery project. It provides status updates on the completed and remaining work for insulating various equipment and piping areas of the project in terms of linear meters or square meters. The report includes a next day plan for continued work.

Uploaded by

susanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
52 views1 page

M/S Lloyd Insulations (I) LTD Date31-01-2020 Daily Progress Report Client-M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat

The document is a daily progress report from an insulation company working on a refinery project. It provides status updates on the completed and remaining work for insulating various equipment and piping areas of the project in terms of linear meters or square meters. The report includes a next day plan for continued work.

Uploaded by

susanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

M/S LLOYD INSULATIONS (I) LTD Date31-01-2020

DAILY PROGRESS REPORT


Client- M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat
COMPLETED AREA TODAY PROGRESS BALANCE AREA
RELEASE FOR
INSULATION NEXT DAY PLAN
S.N. Description TOTAL SCOPE UOM
LAGGING CLADDING LAGGING CLADDING LAGGING CLADDING

LAGGING CLADDING Remarks


1 EQUIPMENTS 2530 RMT 2530 2530 2530 0 0 0 0 0 0

2 REFORMER PACKAGE 2000 RMT 2000 1780 1460 60 160 540 50 40

3 PIPLINE-IH 10000 RMT 10000 9115 6930 80 885 3070 80 100 1500 was realsed on 08-01-2020

4 PIPLINE(VALVE & F) 1300 M2 Not released 0 0 0 0 0 0 Item are not available in work order

5 PIPLINE-IT 1000 RMT 1000 250 220 60 30 750 780 50 50 Released on 30-12-2019

6 PIPLINE-IS 1053 RMT 1053 30 20 20 1023 1033 0 0

FIREPROOFING SYSTEM
7 ON CABLE DUCTS/TRAYS 1038 RMT Not released 0 0 0 0 0 0 0 0
AND FITTING