BS-VI Projects for Panipat Refinery – Hydrogen Generation Unit (HGU)
Daily Progress Report
Owner IOCL, Panipat
PMC Engineers India Limited Progress Date 10-Sep-19
Contractor Technip India Limited Reporting Date 11-Sep-18
Sub Contractor Lloyd Insulation India Ltd Weather CLEAR
Dailey Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -
3 PIPING (LAGGING) M2 15,840.00 480.00 3.03 % 460.00 2.90 % 20.00 460.00 - 460.00 15,380.00 0.00 scaffolding is progress
4 PIPING (CLADDING) M2 15,840.00 480.00 3.03 % 460.00 2.90 % 20.00 460.00 - 460.00 15,380.00 0.00
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 1,450.00 50.77 % 570.00 880.00 550.00 20.00 570.00 2,286.00 20.00
6 REFORMER PACKAGE (CLADDING) M2 2,856.00 1,450.00 50.77 % 75.00 1,375.00 45.00 30.00 75.00 1,300.00 20.00
Manpower and Machinery Status
Indirect Manpower Direct Manpower Equipment & Machinery
Sl No Description Available Sl No Description Available Description Available
1 Project Incharge 1 1 Foreman 1 ROLLING MACHINE 1
2 Planning Engineer 1 2 Fabricator 1 GROOVING MACHINE 2
3 QA/QC 1 3 Fitter 2 MACHINE BENCH VICE 1
4 Safety officer 1 4 Insulator 5 MACHINE SHEARING 1
5 Scaffolder supervisor 1 5 Helper 4 ELECTRIC DRILL MACHINE 8
6 scaffolder 2 BAND TIGHTENING MACHINE 1
MACHINE SEALER FOR STRIP TIGHT 1
CHOPSAW MACHINE 1
TOTAL 5 TOTAL 15 TOTAL 16