100% found this document useful (1 vote)
156 views1 page

Panipat Refinery Daily Progress Report

This daily progress report from Technip India Limited provides updates on insulation work for hydrogen generation unit projects at the Panipat Refinery owned by IOCL. As of the reporting date of 11-Sep-18, piping lagging and cladding was 3.03% completed while reformer package lagging and cladding was 50.77% completed. The report also provides labor and equipment status.

Uploaded by

susanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
156 views1 page

Panipat Refinery Daily Progress Report

This daily progress report from Technip India Limited provides updates on insulation work for hydrogen generation unit projects at the Panipat Refinery owned by IOCL. As of the reporting date of 11-Sep-18, piping lagging and cladding was 3.03% completed while reformer package lagging and cladding was 50.77% completed. The report also provides labor and equipment status.

Uploaded by

susanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

BS-VI Projects for Panipat Refinery – Hydrogen Generation Unit (HGU)

Daily Progress Report

Owner IOCL, Panipat


PMC Engineers India Limited Progress Date 10-Sep-19
Contractor Technip India Limited Reporting Date 11-Sep-18
Sub Contractor Lloyd Insulation India Ltd Weather CLEAR
Dailey Progress Report

FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)

1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -

2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -

3 PIPING (LAGGING) M2 15,840.00 480.00 3.03 % 460.00 2.90 % 20.00 460.00 - 460.00 15,380.00 0.00 scaffolding is progress

4 PIPING (CLADDING) M2 15,840.00 480.00 3.03 % 460.00 2.90 % 20.00 460.00 - 460.00 15,380.00 0.00

5 REFORMER PACKAGE (LAGGING) M2 2,856.00 1,450.00 50.77 % 570.00 880.00 550.00 20.00 570.00 2,286.00 20.00

6 REFORMER PACKAGE (CLADDING) M2 2,856.00 1,450.00 50.77 % 75.00 1,375.00 45.00 30.00 75.00 1,300.00 20.00

Manpower and Machinery Status

Indirect Manpower Direct Manpower Equipment & Machinery

Sl No Description Available Sl No Description Available Description Available

1 Project Incharge 1 1 Foreman 1 ROLLING MACHINE 1

2 Planning Engineer 1 2 Fabricator 1 GROOVING MACHINE 2

3 QA/QC 1 3 Fitter 2 MACHINE BENCH VICE 1

4 Safety officer 1 4 Insulator 5 MACHINE SHEARING 1

5 Scaffolder supervisor 1 5 Helper 4 ELECTRIC DRILL MACHINE 8

6 scaffolder 2 BAND TIGHTENING MACHINE 1

MACHINE SEALER FOR STRIP TIGHT 1

CHOPSAW MACHINE 1

TOTAL 5 TOTAL 15 TOTAL 16