Republic of the Philippines
Department of Education
REGION XI
Division of Davao del Sur
Matanao 1 District
PROGRAM OF WORKS
Detailed Estimate
Project: Construction of Pathway/Landscaping (Front of Administrative Bldg.)
School: Catalino G. Tampipi ES
Location: Sinaragan , Matanao, Davao del Sur
Source of Fund: MOOE Additional Amount FY 2020
For the Month of: April & May 2020
ITEM DESCRIPTION UNIT QTY. UNIT COST TOAL COST Grand Rem.
NO. Total
MATERIAL LABOR LABOR
MATERIAL
A. MATERIALS
1. COARSE SAND CU. M. 3 600 1800
2. CEMENT BAG 10 213.70 2137.00
3. CONCRETE HOLLOW PC. 200 10.00 2000.00
BLOCKS
4. ORNAMENTAL AND PAKYA 1,437.00 1437.00
FLOWERING PLANTS W
5. GARDEN SOIL BAG 100 100.00 2,000.00
MATERIAL COST 9,374.00
B. LABOR COST PAKYAW SYSTEM 2,500.0
0
C. TOTAL COST 11,874.00
Prepared by: NOTED BY:
JERSON A. SALE DAHLIA V. RELAMPAGO
School Facilities Coor. ESP 1
Checked and Reviewed by: APPROVED:
JIMMY M. ALCONERA ARIEL D. DUCO
MT 1/Asst. to the Div. Engineer E-III/ Division Engineer
Republic of the Philippines
Department of Education
REGION XI
Division of Davao del Sur
Matanao 1 District
PROGRAM OF WORKS
Detailed Estimate
Project: Repiping/Improvement of Water System
School: Catalino G. Tampipi ES
Location: Sinaragan , Matanao, Davao del Sur
Source of Fund: MOOE Additional Amount FY 2020
For the Month of: July, 2020
ITEM DESCRIPTION UNIT QTY. UNIT COST TOAL COST Grand Rem.
NO. MATERIAL LABOR LABOR Total
MATERIAL
A. MATERIALS
1. P.E Pipe SDR 11 roll 1 2300.00 2300.00
2. P.E. Tee 1/2 pc 2 150.00 300.00
3. Gate valve 1/2 pc 3 250.00 750.00
4. P.E. coupling1/2 Pc. 3 75.00 225.00
5. G.I. nipple 1/2x 3 pc 3 20.00 60.00
6. G.I. faucet Pc. 3 135.00 405.00
MATERIAL COST
B. LABOR COST PAKYAW SYSTEM 500.00
C. TOTAL COST 4,540.00 4,540.00
Prepared by: NOTED BY:
JERSON A. SALE DAHLIA V. RELAMPAGO
School Facilities Coor. ESP 1
Checked and Reviewed by: APPROVED:
JIMMY M. ALCONERA ARIEL D. DUCO
MT 1/Asst. to the Div. Engineer E-III/ Division Engineer