Gantt

The document outlines a project schedule with various tasks, their start times, owners, and durations from April 2 to May 1, 2017. Key tasks include office itinerancy, product launch activities, and employee relocation, with specific workloads assigned to materials like recycled, rubber, polymer, and plywood. It also details the workload distribution across the specified dates for different materials involved in the project.

Uploaded by

WRGamerChannel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
168 views1 page

Gantt

The document outlines a project schedule with various tasks, their start times, owners, and durations from April 2 to May 1, 2017. Key tasks include office itinerancy, product launch activities, and employee relocation, with specific workloads assigned to materials like recycled, rubber, polymer, and plywood. It also details the workload distribution across the specified dates for different materials involved in the project.

Uploaded by

WRGamerChannel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Task name Start time Owner Duration 02 Apr 03 Apr 04 Apr 05 Apr 06 Apr 07 Apr 08 Apr 09 Apr 10 Apr

05 Apr 06 Apr 07 Apr 08 Apr 09 Apr 10 Apr 11 Apr 12 Apr 13 Apr 14 Apr 15 Apr 16 Apr 17 Apr 18 Apr 19 Apr 20 Apr 21 Apr 22 Apr 23 Apr 24 Apr 25 Apr 26 Apr 27 Apr 28 Apr 29 Apr 30 Apr 01 May

Office itinerancy 2017-04-03 27 Office itinerancy

Office facing 2017-04-03 7 Office facing

Interior office 2017-04-03 Rubber 7 Interior office

Air conditioners chec 2017-04-03 Polymer 7 Air conditioners check

Furniture installation 2017-04-12 8 Furniture installation

Workplaces preparat 2017-04-12 Paper 8 Workplaces preparation

The employee relocatio 2017-04-14 16 The employee relocation

Preparing workplaces 2017-04-14 Carton 5 Preparing workplaces

Workplaces importat 2017-04-21 Polymer 4 Workplaces importation

Workplaces exportat 2017-04-27 Plywood 3 Workplaces exportation

Product launch 2017-04-03 17 Product launch

Perform Initial testing 2017-04-03 Polymer 5 Perform Initial testing

Development 2017-04-03 14 Development

Develop System 2017-04-03 Plywood 2 Develop System

Beta Release 2017-04-06 Recycled 0

Integrate System 2017-04-10 Rubber 2 Integrate System

Test 2017-04-13 Rubber 4 Test

Marketing 2017-04-13 Plywood 4 Marketing

Analysis 2017-04-03 Recycled 6 Analysis

Design 2017-04-03 5 Design

Design database 2017-04-03 Rubber 4 Design database

Software design 2017-04-03 Plywood 4 Software design

Interface setup 2017-04-03 Plywood 5 Interface setup

Documentation creation 2017-04-03 Polymer 7 Documentation creation

Release v1.0 2017-04-20 Recycled 0

Name Workload 02 Apr 03 Apr 04 Apr 05 Apr 06 Apr 07 Apr 08 Apr 09 Apr 10 Apr 11 Apr 12 Apr 13 Apr 14 Apr 15 Apr 16 Apr 17 Apr 18 Apr 19 Apr 20 Apr 21 Apr 22 Apr 23 Apr 24 Apr 25 Apr 26 Apr 27 Apr 28 Apr 29 Apr 30 Apr 01 May

Wood 0h

Metal 0h

Plastic 0h

Concrete 0h

Recycled 48h 8 8 8 8 8 8

Rubber 136h 16 16 16 16 8 8 8 8 8 8 8 8 8

Polymer 184h 24 24 24 24 24 16 16 8 8 8 8

Plywood 144h 24 24 16 16 8 8 8 8 8 8 8 8

Carton 40h 8 8 8 8 8

Paper 64h 8 8 8 8 8 8 8 8

This document is created with dhtmlx library: http://dhtmlx.com