plantemoran.
com
TIA-942: Data Center Standards
Sri Chalasani
Merit 2010 Conference
May 25, 2010
Objectives
What are concerns in the data
center?
Data center standards & best
Practices
Data Center Definition
Computer facility designed for continuous use by
a n c y
several users, and well equipped with hardware,
u n d
R e d software, peripherals, power conditioning and
backup, communication equipment,
e r
security systems, etc. – businessdictionary.com
w
P o i n g includes redundant or backup
i o n
…..It generally
t supplies, redundant data
d i
power
con communicationsiconnections,
n g &
environmental
i to rcontrols (e.g., air
o n
conditioning,
M fire o
r l s
suppression) and security
n t
Co
devices. – wikipedia.org
Notice the common terminology
Levels of implementation set them apart
Why should we care?
DCs house mission-critical data &
equipment. In addition to protecting
this…
Challenges… increased demand for:
Applications / systems availability / SLA
Complex & heterogeneous systems
Service levels for uptime and responsiveness
Amount of data (live and retention)
Regulatory compliance and security
Changing business demands
Green practices & energy costs
Data Center Standards
Without standards… enormous variation
in data center designs
Three commonly known tier systems
Uptime Institute (1995)
Syska Hennessy Group
ANSI/TIA-942 or TIA-942 (2005, 2008, 2010)
Data Center Standards
Uptime and TIA-942
Neither addresses the challenges
Both provide a framework to alleviate
challenges
TIA-942
Requirements / guidelines for the design
& installation of a data center
Multidisciplinary Design Considerations
Intended Audience
TIA-942 Multidisciplinary Design
Design Considerations
1. Design Process 12. Access Providers
2. Space Planning 13. Telecom Spaces
3. Redundancy 14. Cabinets & Racks
Architectural Design
4. Sitefloor,
(space, Selection 15. Cabling Pathways
light, security etc.)
Structured
5. Architectural Wiring 16. Cabling Systems
Electrical
6. Structural 17. Cabling Field Testing
Cooling
7. Electrical 18. Telecom Administration
Operations
8. Mechanical/Cooling 19. Information Technology
9. Fire Protection 20. Commissioning
10. Security 21. Maintenance
11. Building Automation
TIA-942 – Discussion Topics
For today’s discussion, focus on…
1. Data Center Spaces.
2. Data Center Cabling
3. Electrical
4. Cooling
5. Tier System
Spaces
TIA-942 – 5-key functional areas:
(1) Entrance Room (ER)
(2) Main Distribution Area (MDA)
(3) Horizontal Distribution Area (HDA)
(4) Zone Distribution Area (ZDA), opt.
(5) Equipment Distribution Area (EDA)
Ideally separate rooms but not practical
for normal organizations; Can be
consolidated with defined areas
Source: Corning – Distribution in the data center
Spaces
(5) (3) (2) (1)
(4)
ZDA
Source: ADC’s Data Center Optical Distribution Frame: The Data Center’s Main Cross-Connect
Spaces
Source: Corning – Distribution in the data center
Spaces
Typical Data Center Requirements:
Location Ceiling Height
Avoid locations that restrict Min. 8.5’ from finished floor to
expansion any obstruction (sprinklers,
lighting fixtures, or cameras)
Redudnat Access
Cooling architecture may
Delivery of large equipment
dictate higher ceilings
Located away from EMI sources
Min. 18” clearance from water
No exterior windows (inc. heat & sprinkler heads
security risk)
Flooring / Walls
Provide authorized access &
monitored Anti-static properties
Size – no magic formula Sealed / painted to minimize
dust
Sized to meet the known
requirements of specific Light color to enhance lighting
equipment Min dist floor loading 150 lbf/
Include projected future as well Sq-ft, Reco. 250 lbf/Sq-ft
as present requirements
Spaces
Doors Operational parameters
3’ wide x 7’ high, no / Dedicated HVAC system preferred
removable center obstructions (68 – 77 F); measured every
10-30 ft at 1.5ft height
Lighting HVAC – min. 100 sqft/ton
Min. 500 lux in the horizontal Max. temp rate of change: 5 F/hr
plane and 200 lux in the
40% to 55% relative humidity
vertical plane
(reduces ESD)
Lighting on separate circuits/
Electrical - Signal reference grid
panels
(SRG)
Emergency lighting & signs
Sprinkler systems must be pre-
action system
Other Equipment
UPS, power dist. or conditioner Security
<= 100kVa inside room Camera monitoring (int./ext.)
> 100kVa in separate room 100-yr flood plain
Spaces – Best Practices
Locate ER outside of the DC for security
purpose; if inside DC, consolidate ER & MDA
MDA centrally located
Both MDA & HDA require separate racks for
fiber, UTP and coax cable
ZDA is optional, but provides additional flexibility
(pre terminated cables)
EDA – contains equipment only
Each space requires same power/cooling req.
ER: Entrance Room, MDA: Main Distribution Area, EDA: Equipment
Distribution Area, ZDA: Zone Distribution Area, DC: Data Center
Spaces – Raised vs. Solid Floor
Raised floor a very common notion, but...
Older equipment vs. newer Only place to go is creep into
equipment air flow (bottom-up cold aisle….warmer air at
vs. front to back) cabinet tops.
Hot aisle – Cold aisle air flow Typically see passive
dynamics components or open spaces
Cold air – want to fall, but we near top of cabinets
are pushing – requires Both use anti-static tiles or
pressure through perf. tiles flooring
Opening / leaks in flooring has Data & electrical cabling
impact on pressure restrictions
Equip. densities increase -> New build – more expensive
higher head load -> higher Have to look at your
pressure of cold air through environment to see if raised
restrictive space floor makes sense….do use this
What happens to hot air? – as the rule of thumb!
flows up, reduces temperature
and begins to fall down again
Cabling Systems
Structured vs. Unstructured Cabling
Horizontal cabling Horizontal cross-connect
(HC) in the
Backbone cabling
telecommunications
Cross-connect in the room, horizontal
entrance room or main distribution area or main
distribution area distribution area
Main cross-connect (MC) Zone outlet or
in the main distribution consolidation point in
area the zone distribution
area; and
Outlet in the equipment
distribution area
Cabling Systems
Source: Corning Cable Systems – Just the Technical Facts
Cabling Systems
Reduced Data Center Topology
Consolidated ER/MDA/HAD
Applicable to most enterprises
Source: Orthronics – Standards-Based Data Center Structured Cabling System Design
Cabling Systems – Transmission Media
100-ohm twisted-pair copper cable
Category 5e or 6, 6A
10GbE: Cat 6 – 37-55mts, Cat 6A – 100mts
Multimode fiber optic cable
62.5/125 µm or 50/125 µm
50/125 µm 850 nm laser optimized mmf
Singlemode optical fiber cable
75-ohm coaxial cable
Type 734 & 735 cable
Type T1.404 coaxial connector
Cabling Systems – Overhead / Under floor
Under Floor Cabling
Less expensive if raised floor than overhead
Cabling in cable trays to minimize airflow blocks;
consider multilevel trays for fiber/copper
Provide adequate capacity for growth
Separate fiber cords from copper cabling from
power
Typically placed in the hot aisle
Electrical – color coded PDU with locking
receptacle. Receptacles labeled with PDU/panel
ID & breaker #
Cabling Systems – Overhead / Under floor
Overhead
Can be used in raised floor environments also
Multi level cable tray system (3 Layer)
Bottom layer – copper
Middle layer – fiber
Top layer – power
Suspended from ceiling; min.12” clearance
above each ladder
Separation from fluorescent lights (5”) & power
Avoid blocking cooling ducts (overhead cooling)
Racks / Cabinets
Placement of racks / cabinets
Hot aisle / Cold aisle - arranged in an alternating
pattern (with fronts facing each other)
Cold aisles are front & Hot aisles are rear of
racks/cabinets –
If there is a raised floor, PDU cables are run in
cold aisle. Data cable trays for telecom cabling
are typically placed in hot aisle.
Common bonding network (CBN)
Racks / cabinets individually, cable trays, HVAC,
PDU, panel boards, raised floor structure, columns
Front clearance – min. 3ft, 4ft recommended
Raised Flooring vs. Traditional Flooring
Racks / Cabinets
Placement of racks / cabinets
Front rails recessed for wire management
Switch-Panel-Switch arrangement
Front edge of cabinet on edge of tile
Perforated tiles at front of cabinets
Provide blank panels in empty spaces
Electrical Considerations
Unfortunately no magic bullet!
Manual process for load configuration
APC ‘s “Calculating Total Power Requirements for
Data Centers” By Richard Sawyer – framework
for calculating req.
Color coded PDU with locking receptacle.
Receptacles labeled with PDU/panel ID &
breaker #
Best Practices
Multiple power grid connects Intelligent PDU
Sub-breakers per relay rack Generator capacity to include
or lineup for cooling
Dual A-B cording UPS capacity to include
cooling and lights
Accommodate growth
Cooling Considerations
# 1 Mitigating Factor – heat removal
No specific guidelines; basic physics
Cooling reqd. = Heat Generated = Electrical load
Design Implications
Layout of racks in alternating Quantity and location of vents
rows Sizing of ductwork
Location of CRAC units Proper internal configuration of
racks
Cooling Considerations
Process
Determine critical heat load Determine cooling delivery
methodology(s)
Establish critical loads - watts-
per-RLU Room, Row, Rack
Determine the CFM Blank panels/short circuits
requirements per RLU Cold air containment
If possible, divide the room Special Considerations – high
into cooling zones by RLU BTU
Determine appropriate air Establish a floor plan
conditioner type(s)
Deploy a comprehensive
Equip. airflow (f->b / s->s) monitoring system
Cooling is not enough – airflow required
Cooling Considerations - Airflow
Supply &
Return
Based
source: apc.com
Fire Detection and Suppression
Significant risk of electrical fires
A comprehensive fire detection &
suppression system is mission-critical
Detection Suppression
Both heat and smoke detection Follow NFPA 75 standard firewalls
Interconnected with the fire Sprinkler systems — both flooded
suppression system, local and pre-action
alarms, monitoring system, etc Chemical systems or Clean Agent
Installed in accordance with (FM 200, Inergen, Ecaro-25(FE 25),
NFPA 72E Novec 1230)
Installed below raised floors Manual systems (Manual pull
and other areas stations, Portable fire extinguishers
Airflow patterns determines
location of detection units
Tier System – Uptime & TIA-942
4-Tier System based on
Resilience / Capacity of its MEP systems
16-pages of criteria
Primary Categories
Power and cooling delivery Support space to raised floor
paths ratio
Redundancy in components Raised floor height
Initial & ultimate watts/sqft Floor loading pounds/sqft
Utility voltage
Optimal Criticality – Choosing a tier
C Business characteristics Effect on system design
1
• Typically small businesses • Numerous single points of failure in all aspects of
• Limited online presence design
• Low dependence on IT • No generator if UPS has 8 minutes of backup time
• Perceive downtime as a tolerable • Generally unable to sustain more than a 10 minute
Inconvenience power outage
2
• Some online revenue generation • Some redundancy in power and cooling systems
• Multiple servers • Generator backup
• Phone system vital to business • Able to sustain 24 hour power outage
• Dependent on email • Minimal thought to site selection
• Some tolerance to scheduled downtime • Vapor barrier
• Formal data room separate from other areas
3
• World-wide presence • Two utility paths (active and passive)
• Majority of revenue from online business • Redundant power and cooling systems
• VoIP phone system • Redundant service providers
• High dependence on IT • Able to sustain 72-hour power outage
• High cost of downtime • Careful site selection planning
• Highly recognized brand • One-hour fire rating
• Allows for concurrent maintenance
4
• Multi-million dollar business • Two independent utility paths
• Maj. of rev from electronic transactions • 2N power and cooling systems
• Business model entirely dependent on IT • Able to sustain 96 hour power outage
source: apc.com
• Extremely high cost of downtime • Stringent site selection criteria
• Minimum two-hour fire rating; High phy. security
Balance cost of downtime and TCO • 24/7 onsite maintenance staff
Tier System
Attribute / Statistic Tier I Tier II Tier III Tier IV
Power and Cooling 1 Active 1 Active 1 Active 1 2 Active
Delivery Paths Passive
Redundant Components N N+1 N+1 2(N + 1)
Support Space to Raised 20% 30% 80 – 90% 100%
Floor Ratio
Initial Watts / sqft 20 – 30 40 – 50 40 – 60 50 – 80
Ultimate Watts / sqft 20 – 30 40 – 50 100 – 150 150+
Raised Floor Height 12” 18” 30 – 36” 30 – 36”
Floor Loading Pounds / 85 100 150 150+
sqft
Utility Voltage 208, 480 208, 480 12 – 15 kV 12 – 15 kV
Months to Implement 3 3–6 15 – 20 15 – 20
Year First Deployed 1965 1970 1985 1995
Construction $ / sqft $450 $600 $900 $1,100+
Annual IT Downtime Due 28.8 hrs 22.0 hrs 1.6 hrs 0.4 hrs
to Site
Site Availability 99.67% 99.75% 99.98% 100.00%
Source: The Uptime Institute
Next / Action Steps
Perform a risk assessment to determine
hourly cost of downtime
Determine current data center tier for
each subsystem in the data center –
you might not need tier-iv across the
board
Get IT and Facilities to work together on
issues
Work with finance to justify upgrades
Understand TIA-942 (requirement &
process)
Outsourced Data Center
Fits business model - consider
outsourcing
Affordable co-location/hosted DC and
99.995% uptime are NOT mutually
exclusive
Understand levels of redundancy and
the uptime SLA in order to get the best
combination of uptime and affordability
Balance between budget and availability
Outsourced Data Center
What to look for….
Hardened data center Availability of multiple
buildings carriers
Data center power & Physical security
cooling redundancy SAS 70 data center
Telecom entrance compliance
redundancy
Claims of Uptime Tiers – III or IV; most
are not certified
Review
TIA-942
Key design parameters
Tier System
Next Steps
Resources
Useful links
Excellent white papers from www.apc.com
TIA - http://www.tiaonline.org/
Green data center efficiency savings calculator
http://cooling.thegreengrid.org/namerica/WEB_APP/calc_index.html
The green grid (thegreengrid.org)
Department of Energy – DC Profiling Tool
http://www1.eere.energy.gov/industry/datacenters/software.html
…. and obviously Google or Bing it.
Questions
plantemoran.com
Contact Information
Sri Chalasani
sri.chalasani@plantemoran.com
248.223.3707