DIVISIO 2000 Series – SIMPLEX – Maintenance
Author: Thomas Keim
18.08.2018 1
Maintenance – Status Message
Status messages are important for
the current state of the machine, e.g.
no compressed air, doors not closed,
machine not equipped, etc. Only
visible when Temporary parameter
are folded.
2
Maintenance – Vacuum Cleaner
Weekly
1.) Check if the vacuum cleaner runs.
Manual cleaning
3.) If the black pointer is moving left to
the red limit pointer, the pressure
between the motor and the filter is
becoming too high. The filter has to be
cleaned manually or with an integrated
filter motor.
3
Maintenance – Check Pressure
Weekly
1.) If the device is equipped with
components that need compressed
air, check the manometer for the
prescribed pressure of 5 to 6 bar.
3.) If necessary, drain condensed
water by using the release vent.
It is not necessary to remove the
pressure from the system, but
2.) Check the inspection open the vent slowly.
glass on the maintenance
unit for condensed water.
4
Maintenance – Check Spindle Chuck
Weekly
1.) Check the routing spindle for dirt Never use
compressed air to
clean the chuck!
2.) Put the router bit out
of the chuck by going
into the Manual Mode.
Chuck already
without a bit
5
Maintenance – Get Tool Out
Weekly
3.) Select Tool out
2.) Select Tool/Extraction
1.) Go to Manual Mode
-> Processing
5.) The bit will be deposited in the magazine
and the NC-axis goes to it’s basic position. 4.) Start
The spindle cannot be rotated any more.
6
Maintenance – Clean Spindle Chuck
6.) Turn the key switch “Interlock bypassed” to it’s Weekly
‘1’ Position to the right and press “Release
Interlock” at the device. The rear side door now
can be opened. The brush should be removed.
7.) Unscrew the chuck simply with your
hands.
7
Maintenance – Clean Spindle Chuck
8.1) Clean the chuck with a pipe cleaner, what is Weekly
inside the maintenance suite bag.
8.2) The spindle inner area has also to
be cleaned with the pipe cleaner.
8
Maintenance – Clean Spindle Chuck
10.) Screw in the
Weekly
chuck back into the
spindle.
Never lubricate the
chuck with oil or grease,
9.) Give only a small because in combination
oil film onto the shaft of with dust, it will be
the chuck. baked hard like stone.
9
Maintenance – Ionisation
Monthly
The air nozzles must be clean. For
cleaning simply use a vacuum
cleaner. Never touch the
ionization tips,
when the machine
is running.
Check the air nozzles
and high voltage wires
for damages.
10
Ionisation – Switch Off High Voltage
Quarterly
1.) PLC controller with
connections to
camera und PC
By performing maintenance
jobs at the ionisation system,
the power switch of the main
ionisation unit must be 3.) Main ionisation unit with
switched off necessarily! power switch. The green
LED must be on, fault when
it is red.
11
Maintenance – Control Cabinet
► Every single component is Every six
working? month
► All fuses are on?
► All cable plugs are connected
well?
PLC
Safety chain (Interlock)
Phase monitoring,
control the rotation of
the vacuum cleaner,
voltage too high or
too low.
12
Maintenance – Cabinet Filter
Remove the dirt and dust from the Every six
ventilator filter in the control cabinet. 2.) Check the filter or clean it
month
with the upright vacuum
cleaner.
Air
1.) To remove the cover use a screw driver. 3.) Replace it at least
Remove the cover from outside the cabinet. every six month.
13
Maintenance – Lubrication of the Linear Axes
According to
plan
Lubrication points for the
axes: Remove the red plastic
copings and inject the grease
with the supplied grease gun.
Spindle with brush
14
Tool Kit for Maintenance
Grease cartridge
Grease gun
15
Maintenance Tool Kit
Pipe cleaner blanks
Replacement brushes
16
Maintenance Tool Kit Spindle
1.) Clean the inner cone of the
spindle. The inner cone must be free
of chips and dust.
2.) Lubricate spindle shaft only
with a thin oil film.
3.) Hexagon screw-wheel, only
for the opening of too tight
chucks. Not to screw in with it.
17
Maintenance Items
Lubricate bearing
after 4800 operation
hours, or twice a year.
Engine runtime means the
machine is switched on.
Empty the dust
container after 5000 m
of cutting length.
18
Maintenance Items
Red symbol would mean
‘Lifetime has expired.
Create a Backup at
least after 168 hours
or one week.
After a spindle idle time of
168 hours a spindle run-in
must be performed.
19
Reset Maintenance Entries
1.) Select an entry
2.) Reset the entry after the
work is done. For that mark the
line completely.
20