PAGE
1 of 5
                                                                       DOCUMENT NO. :
                                                                            P-T3109-EI-017
                            CABLE PULLING PROCEDURE                    ISSUED DATE :
                                                                              26-2-2009
UNIT ISSUING :    APPROVED BY :                                             PAGE      REVISION
E & I Dept                               Site Manager                       2 of 5       00
                         CABLE PULLING PROCEDURE
                                   FOR
                       3X330 MW POWER PLANT PROJECT
                           INDRAMAYU- WEST JAVA.
                                  DOCUMENT NO : P-T3109-EI-017
ORIGINATED BY                     REVIEWED BY           APPROVED BY     DISTRIBUTION
                                                                      - SDCC         : Original
                                                                      - CNEEC : Copy
                                                                      - All Dept. : Copy
   Nurana hadi            M. Arifin          Iman P         Agus S
                 ISSUED     EFFECTIVE
 REV. NO                                                BRIEF OF REVISION
                  DATE        DATE
                                                                                     DOCUMENT NO. :
                                                                                       P-T3109-EI-017
                                 CABLE PULLING PROCEDURE                             ISSUED DATE :
                                                                                          26-2-2009
UNIT ISSUING :         APPROVED BY :                                                   PAGE      REVISION
E & I Dept                                     Site Manager                            3 of 5       00
     00            09/2/26         09/2/26
      1.         TITLE
                 Procedure for cable pulling
      2.         SCOPE
                 This procedure is to describe the minimum requirements for cable
                 installation during receiving of materials, storing, fabrication and Installation
                 work.
      3.         OBJECTIVE
                 This is to assure that the requirements of electrical installation works are
                 meets the codes requirements and contract specifications. To make sure,
                 the works are carried out in acceptable workmanship and follow the
                 requirements in the quality manual.
      4.         REFERENCE
                 4.1     Project Quality Plan / PQP (Q-T3109-119)
                 4.2     Contract document (CT3109-703)
                 4.3     Construction Drawing / Cable schedule list
                 4.4     Standards, codes and recommended practices
                 4.5     Client Cable schedule
                 4.6     Client Cable drum schedule
                 4.7     Power / Control Cable lay-out
                 4.8     Prosedur Pengelolaan Sistem Management K3 (P-HSE-001)
                 4.9     Standart Identifikasi Aspek K3L, Pengujian & Pengendalian Resiko
                         (W-HSE-001)
      5.         RESPONSIBILITY
                                                                                      DOCUMENT NO. :
                                                                                         P-T3109-EI-017
                                 CABLE PULLING PROCEDURE                              ISSUED DATE :
                                                                                           26-2-2009
UNIT ISSUING :         APPROVED BY :                                                     PAGE     REVISION
E & I Dept                                     Site Manager                              4 of 5      00
                 5.1     The Electrical Engineer at site shall be responsible for the planning
                         scheduling and coordination, record and monitor progress of electrical
                         works. To guide the supervisors in the field in terms of engineering
                         and technical problems.
                 5.2     The Electrical Superintendent shall be responsible for the daily
                         construction activities to coordinate with Area Supervisors and
                         support The Supervisors in terms of technical matters.
                 5.3     The Electrical Supervisors shall be responsible to the respective
                         superintendents and carry out the direct field activities through the
                         skilled and unskilled workers according to the installation procedures
                         and drawings and applicable procedures for electrical installations.
      6.         WORK PROCEDURE
                 6.1     GENERAL
                         1. The field installation, inspection and test of electrical facility shall
                            be executed under the responsibility of contractor according to the
                            relevant drawings and documents specified in paragraph 4.0.
                         2. The work shall be done according to good workmanship and by
                            using the suitable tools and material as stated in the construction
                            drawings, approve documents, and procedures and it shall be
                            studied before carry out any electrical works.
                         3. Field Engineers will ensure that they are in possession of the
                            following documents, prior to the commencement of the works:
                         4. Safety and Sanitation.
                            Full care and pre-caution shall be given by the field management
                            for the safety and sanitation of workman in the field to prevent
                            accidents during execution of the works.
                 6.2     INSTALLATION OF CABLE
                         General
                         a) Cup the cable tip with PVC insulation tape for water protection.
                            Mark the cable end according to cable number and wrap the
                            marking with transparent tape to prevent loosing the mark.
                                                                                     DOCUMENT NO. :
                                                                                       P-T3109-EI-017
                                 CABLE PULLING PROCEDURE                             ISSUED DATE :
                                                                                          26-2-2009
UNIT ISSUING :         APPROVED BY :                                                   PAGE      REVISION
E & I Dept                                     Site Manager                            5 of 5       00
                         b) Cable shall be run in one length. Cable should pulling in the same
                            layer according to the cable routing drawing.
                         c) If Cable run close and parallel to hot pipe lines or high
                            temperature surface, a 300 mm minimum clearance shall be
                            maintained.
                         d) Transfer the cable drums from warehouse and pool into near
                            starting point of pulling. Number of drums to be pull shall prepare
                            at least required number of pulling for one day pulling schedule,
                            considering the space of location.
                         e) Cable drum shall be mounted on cable pulling stand. Sufficient
                            cable roller shall be installed in pulling cable.      A swivel shall
                            always be inserted in the pull-in line to prevent twisting of the line
                            being drawn in.
                         f) The pulling tension shall be limited within the value recommended
                            by the cable manufacturer.
                         g) Cables on the cable trays / ladders shall be fastened securely to
                            transverse members of cable trays / ladders.
                         h) Bending radius of the cable shall be in accordance of the
                            manufacture installation guide.
                         i) The cables must not be laid directly on the floor. Minimum height
                            from the floor is 300 mm.
                         j) Before the terminal all the cables from the tray / ladder shall be
                            supported and clamped.
                         k) For single core cables on the same feeder, it must be arranged in
                            such manner so the cable with same phase are placed side by
                            side : RST – TSR – RST
                         Petroleum base grease shall not be used for lubricating of wires and
                         cable.
                 6.3     PREPARATION AND PRECAUTION FOR CABLING
                         a) All necessary precautions shall be taken to protect cable from
                            damage during installation.
                                                                                 DOCUMENT NO. :
                                                                                   P-T3109-EI-017
                              CABLE PULLING PROCEDURE                            ISSUED DATE :
                                                                                      26-2-2009
UNIT ISSUING :     APPROVED BY :                                                   PAGE      REVISION
E & I Dept                                  Site Manager                            6 of 5      00
                       b) Provide an adequate and suitable access to the cable trays /
                          ladders for install cables.
                       c) Cables shall be laid on the cable routing in a workmanlike manner.
                          Any visible damage to the cables during installation shall be
                          reported to the representative of Owner or Client.
                       d) Take all necessary precaution to assure that open trenches are
                          adequately barricaded or marked to avoid being a personnel
                          safety hazard.
                       e) Maintained excavated areas in manner to prevent entering of
                          surface water. Any water that does accumulate in an excavation
                          shall be removed continuously.
                       f) If excavation needed, hand excavation shall be required around
                          any underground piping or other below grade facilities.
                       g) After the cable being pulled and laid on the cable ladder, the cable
                          shall be properly secured with cable-tie to the rung of cable ladder
                          at the distance of max 1 m at horizontal laying and max 0.5 m at
                          vertical laying.
                       h) All document related to pulling cable work should be collected
                          before start of work.
                          -   Cable route drawing for power/control cable
                                   This drawing indicates the route of cable to be pulled
                                      from the origin to the destination.
                           - Cable schedule
                                   This cable schedule indicates cable identity to be pulled
                                      from the origin to the destination.
                           - Cable drum schedule
                                   This document indicates tag number cable drum,
                                      specification of cable, quantity of cable.
                       i) Before pulling the cable, all the cable drum must be supported.
      7.         SAFETY
                      Before installation work, supervisor have to make coordination with
                       safety department. JSA/HIERAC shall be available on site when job is
                       on going
                      Workmen wear proper PPE (helmet, safety shoes, safety belt, hand-
                       glove etc.).
                                                                           DOCUMENT NO. :
                                                                             P-T3109-EI-017
                           CABLE PULLING PROCEDURE                         ISSUED DATE :
                                                                                26-2-2009
UNIT ISSUING :   APPROVED BY :                                               PAGE      REVISION
E & I Dept                              Site Manager                         7 of 5       00
                    Safety line should be installed around excavation soil (for direct
                     buried cable system).
                    Safety sign board on the pulling cable work area.