PRE-EXCAVATION GROUTING
I.      Introduction
       The excavation of a tunnel always involves risks of unpredicted ground conditions, including
the chance of meeting a body of high-pressure ground water. Ground water can cause problems to
the tunnel and the surrounding area, even only in smaller volumes, creating ground water leakage
and seepage. These problems can be maintained using drainage and grouting.
         Grouting is the process of injecting grout materials into a borehole with the purpose of
sealing fissures and joints that intersects with the borehole. The most common grouting material is
based on cement (Emmelin et al., 2007). Other material used in grouting is micro-cement and
colloidal silica. The grout slurry is a mixture of cement and water, it may contain additives such as
superplasticizer to control its viscosity.
        Grouting can be done in two different methods, post-grouting and pre-grouting. Post-
grouting, or post-excavation grouting, is done in an excavated opening. While pre-grouting, or pre-
excavation grouting, is done ahead of the face. In general, pre-grouting is easier than post-grouting,
because the difficulty and cost implications of handling a significant water inflow in an already
excavated tunnel can be extreme compared to the cost of the probe drilling and injection works
carried out ahead of the tunnel face.
         In grouting, using high pressure injection may be fundamental to a good result, i.e. much
reduced water inflow and improved stability. The reasons for performing high pressure (50 to 100
bar) injection when pre-grouting ahead of tunnels is that grout pressure ground water pressure have
to be controlled. It is necessary to monitor the intended pressure and volume of the grout slurry in
order to get a good sealing of ground water around the tunnel. There are several criteria used for
deciding when to stop grouting in order to have the intended grouting results, such as stop criteria
(Houlsby, 1990). Stop criteria limits the pressure, volume, and flow of grouting. In order to control
fracture deformation, Lombardi and Deere (1993) suggested to consider a combination of injection
pressure and injected grout volume (The Grout Intensity Number or GIN-value).
II.     Material                                               microcement with a w/c ratio of 1 will
                                                               give the same marsh funnel time, but
             The most common material used
                                                               a bleeding of only 0-2%.
        in grouting is cementitious material.
        Generally, for the grout mix, w/c ratio                     The properties of grout can be
        starts at 3:1 and is gradually                         changed with different kinds of
        thickened to 2:1, 1:1 and 0.5:1. The                   additives, such as superplasticizers
        w/c ratio should be as high as possible                and accelerators. Superplasticizers are
        without giving too much bleeding.                      used to control grout viscosity,
        Bleeding should be as low as possible,                 flowability,      and       dispersion.
        around 2-5% bleeding maximum. A                        Accelerator is added to the grout in a
        normal fine cement with a w/c ratio                    nozzle on the injection lance. In this
        of 1 will give a marsh funnel time of                  way, it is possible to adjust the open
        about 33 seconds and a bleeding of                     time of the grout to only around 5-20
        around 10-15%. While a good                            minutes.
              The particle size of the grout         IV.    Methodology
        material is selected based on the
                                                                 According to Houlsby (1990), to
        fissure size in the rock mass of the
                                                            perform grouting work, a set of main
        tunnel. Generally, to achieve cost
                                                            steps should be followed:
        effectiveness,     locally      available
        Ordinary Portland Cement (OPC) is            a. Investigation: Geology of the area and
        used. This cement has an average                permeability situation are investigated.
        particle size of 45 μm. Micro-cement            Spacing, width, inclination of joints, and
        is used on fissures with a smaller size.        strength of rock are among the important
        Micro-cement is finely grounded                 geological factors. Knowledge             of
        ordinary cement with a large surface            permeability is important for controlling
        area and fine particle size of about 15         seepage. Lugeon test is the most
        μm. As an alternative to cement-                common         way   to    quantify      the
        based materials, various solutions              permeability of rock mass. The most
        have been used as grouting materials            important outcome of this investigation
        such as colloidal silica. Colloidal silica      is size of cracks.
        is an aqueous dispersion of silica           b. Design of grouting: Spacing and length of
        particles, with a particle size of less         boreholes, properties of required
        than 0.015 μm. A schematic                      material, and injection pressure are
        illustration of different cement                decided using the data obtained from
        particles (µm) with respect to rock             investigation.
        aperture is portrayed in Figure 1.           c. Execution: The main work in this phase is
                                                        preparing machineries and facilities,
                                                        preparing grout mix material, drilling
                                                        boreholes, and injecting grout material
                                                        into fissures and fractures of the rock
                                                        mass.
                                                     d. Compilation: Achieving maximum certain
                                                        pressure, maximum certain injected
                                                        volume or production of pressure and
                                                        volume (P.V) are among popular refusal
                                                        points. Based on theories developed by
                                                        Gustafson & Stille (2005), it is possible to
 Figure 1. Particle size distribution (Subash et        estimate penetration of the grout mix
                    al., 2016)                          analytically in real time, thus required
             Microcements       for   injection         penetration length can be set as the stop
        should be as fresh as possible, it              criterion.
        should not be older than 6 months. If        e. Assessment: The procedure should be
        the cement is too old, it will create           assessed to identify if grout has spread
        more bleeding, slower setting times,            enough around the borehole and not
        and a higher risk of cement lumps.              more than required. The other
        Also, cement should be stored in                considerable issue is the stresses induced
        ventilated rooms, not in the actual             to the rock mass due to grouting.
        tunnel. Because, the humidity in the            Prolonging the procedure, the induced
        tunnel will get to the cement,                  excess pressure may lead to larger
        resulting in a pre-hydrated cement.             deformation and in worse case cause
                                                        damages to the ground structures. Also,
III.    Equipment                                       the increase in the size of fracture
        aperture will lead to lower penetration
        length than expected, which will affect
        sealing efficiency of the grouting work.
IV.A.      Execution
                Pre-grouting is commonly done
           from inside the tunnel. The drilling
           and injection method of grouting
           depends on the site condition. In
           general, grouting methodology is
           carried out as follows (Subash et al.,
           2016):
                                                    Figure 2. Pre-grouting Methodology (Subash
1. Drilling of 40-75mm diameter hole to                              et al., 2016)
   required length and inclination as per the
                                                               The effectiveness of pre-grouting
   site condition. The pattern and spacing of
                                                          execution is controlled by some
   the grout holes will be based on
                                                          parameters, such as: grout design,
   groutability test.
                                                          including number of probe holes;
2. Installation of a pipe with internal
                                                          grout hole pattern and spacing;
   diameter to fit the expendable packers.
                                                          overlap length; grout materials and
3. Placement of packer at the very end of
                                                          grout properties; and grouting stop
   the pipe and injection of a cement-based
                                                          criteria.
   grout which fills the space between the
   rock and the pipe. Hardening for about 12
   hours.
4. When the grout is hardened, drilling
   through the pipe to feasible length.
5. Placement of packer and pressure
   injection with appropriate cement grout
   for penetration into the rock mass in
   drilled length of the hole. Stop criteria as
   per grout mix design.
6. After hardening of the injected grout, re-         Figure 3. Grout Screens with Overlaps
   drilling through the pipe and injected area            (Association of Geotechnical &
   to design length beyond last drilled             Geoenvironmental Specialists, Hong Kong)
   length.
                                                               Figure 3 shows an illustration of a
7. Placement of the packer in the pipe and
                                                          typical grout screens with overlaps
   inject (repetition of step 5).
                                                          around an underground space. The
                                                          screen also has to cover the invert,
                                                          because residual leakage in the invert
                                                          is more difficult to observe as well as
                                                          presenting problems for drilling for
                                                          post grouting.
                                                              Grout hole length is dependent
                                                          on the excavation diameter/span,
                                                          usually around 15 m - 25 m with a
                                                          grout hole centre to centre spacing of
        1 m - 1.5 m at collaring point, and a                  between subsequent grout fans
        lookout distance at the end of the                     should be 5 m or more. In extremely
        grout holes of 3 - 5 m from the                        poor ground up to 10 m may be
        theoretical tunnel surface. Control                    required. A large face area will require
        holes are usually located within the                   more overlap than the face area of a
        grout screen or even within the                        small tunnel.
        excavation profile. The overlap
 Figure 4. Typical Grout Pattern (Association of Geotechnical & Geoenvironmental Specialists, Hong
                                                Kong)
      It has been found from recent Norwegian          Figure 5. Sources of Pressure Drop (Barton,
tunnelling projects that high pressure pre-                               2003)
injection may be fundamental to a good
                                                          One of the problems in grouting is high
result, i.e. much reduced inflow and improved
                                                     conductivity contrast. To reduce the effect of
stability (Barton, 2004). The reason for this is
                                                     high conductivity contrast, dual stop criteria
that while grout is still flowing, there is a
                                                     (pressure or volume) needs to be applied.
gradient of pressure from the start of the
                                                     Using stop criteria limits the grout material
injection holes to its end. Using high-pressure
                                                     consumption, while still achieving sufficient
grouting will minimize the risk of this pressure
                                                     grout penetration and distribution.
loss, which then leads to effective grouting.
                                                     IV.B.     Stop Criteria
                                                          During grouting execution, it must be
                                                     decided when to stop. The criteria for this are
                                                     called stop criteria. There are several types of
                                                     stop criteria that can be used (Emmelin et al.,
                                                     2007):
                                                            A maximum grouting time, where
                                                             grouting is stopped when it has
                                                             proceeded for a given length of time.
                                                            A maximum grouting volume, where
                                                             grouting is stopped when a certain
                                                             volume has been injected.
       A minimum grouting flow, where              Figure 6. Example of Grouting Path Curves
        grouting is stopped when the grouting              (Lombardi and Deere, 1993)
        flow is lower than a certain value.
    In order to control fracture deformation,
Lombardi and Deere (1993) suggested to
consider a combination of injection pressure
and injected grout volume (The Grout
Intensity Number or GIN-value) in addition to
the previously set stop criteria by Houlsby
(1990). This means that with respect to GIN
number, the maximum applicable pressure
should be decided by considering the amount
of injected volume (Rafi, J., Stille, H.,
Johansson, F, 2016)
                                                    Figure 7. Proposed Limiting Envelopes for
IV.C.     Grout Intensity Number (GIN)                Grouting (Lombardi and Deere, 1993)
     Lombardi and Deere (1993) suggest that            Figure 7 illustrates five suggested limiting
in a given grouting interval, the energy          envelopes for different intensities for
expended is approximately proportional to         grouting. The uppermost envelope represents
the product of the final grouting pressure p      a very high intensity of grouting with a GIN
and the grout volume injected V, giving a         value of 2500 bar.l/m, a very high limiting
product p.V (bar.litres/m). This p.V number is    pressure of 50 bar, and a very high limiting
called the Grouting Intensity Number (GIN).       volume of 300 l/m. The lowest envelope
                                                  represents a very low intensity, with a GIN
     By keeping the GIN value constant during
                                                  value of 5000 bar.l/m, a maximum pressure of
the grouting process for all grout intervals, a
                                                  15 bar and a limiting volume of 100 l/m. For
nearly constant reach of the grout will be
                                                  most conditions, it is recommended using the
obtained. It will also limit the volume in an
                                                  moderate intensity envelope with a given
open, wide fissure, but allowing pressures to
                                                  value of 1500 bar.l/m, a limiting pressure of
increase in zones of tighter and less groutable
                                                  30 bar, and a limiting volume of 200 l/m
fissures. Combinations of high pressure and
volume are eliminated, a condition that would           The complete limiting envelope thus
only lead to huge uplift or hydro splitting       consists of the limiting pressure line (in the
forces. Similarly, combinations of low            range of 15 to 50 bar), the limiting volume line
pressure with a low take are eliminated, that     (in the range of 100 to 300 litres per meter of
would inadequately grout the fine fissures        grouted interval), and a selected GIN curve
                                                  connecting the two limit lines (with GIN values
                                                  ranging from very low to very high, for
                                                  example, 500 to 2500 bar.l/m).
                                                           Figure 8. Grouting Process of a Single
                                                        Borehole Stage (Lombardi and Deere, 1993)
                                                           The GIN method requires close
                                                      monitoring by PC graphics of real-time curves
                                                      of pressure versus time, grout flow rate versus
                                                      time, grout flow rate versus time, and total
                                                      injected volume versus time, plus the derived
                                                      curve of penetrability (flow rate divided by
                                                      pressure, q/p) versus time. This latter curve is
                                                      of particular value in signifying the approach
                                                      of grouting refusal, or at least of diminishing
                                                      absorptions.
       Figure 9. Real Time Curves of a Single Stage Grouting Process (Lombardi and Deere, 1993)
V.       Quality Control                              moulds and stripped and immersed in lime
                                                      water until tested.
V.A.     Compressive Strength
                                                      V.B.    Shrinkage
     This test method covers determination of
                                                           This test method determines the change
the compressive strength of hydraulic cement
                                                      in length on drying of mortar bars containing
mortars, using 2 inch or 50 mm cube
                                                      hydraulic cement and graded standard sand.
specimens. The mortar used consists of 1 part
                                                      This test method establishes a selected set of
cement and 2.75 parts of sand proportioned
                                                      conditions of temperature, relative humidity
by mass. Portland or air-entraining Portland
                                                      and rate of evaporation of the environment to
cements are mixed at specified water/cement
                                                      which a mortar specimen of stated
ratios. Water content for other cements is
                                                      composition shall be subjected for a specified
that sufficient to obtain a flow of 110±5 in 25
                                                      period of time during which its change in
drops of the flow table. Two inch or 50 mm
                                                      length is determined and designated “drying
test cubes are compacted by tamping in two
                                                      shrinkage”.
layers. The cubes are cured one day in the
V.C.    Bleeding                                     ASTM C596. Standard Test Method for Drying
                                                        Shrinkage of Mortar Containing Hydraulic
     This test method determines the amount
                                                        Cement.
of expansion and accumulation of bleed water
at the surface of freshly mixed hydraulic-           ASTM C940. Standard Test Method for
cement grout used in the production of                  Expansion and Bleeding of Freshly Mixed
Preplaced-Aggregate (PA) concrete. Grout is             Grouts for Preplaced-Aggregate Concrete
placed in a graduated cylinder. Changes in              in the Laboratory.
total volume and accumulation of bleed
                                                     ASTM C953. Standard Test Method for
water, if any, on the surface of the grout are
                                                        Expansion and Bleeding of Freshly Mixed
observed over a period of time.
                                                        Grouts for Preplaced-Aggregate Concrete
V.D.    Setting Time                                    in the Laboratory.
     This method covers the determination            ASTM D6910. Standard Test Method for
test of time of setting of hydraulic cement             Marsh Funnel Viscosity of Clay
grout mixtures used in Preplaced-Aggregate              Construction Slurries.
(PA) concrete using the Vicat apparatus. The
                                                     Barton, Nick. 2004. The Why’s and How’s of
time of setting, initial and final, of a sample of
                                                         High-Pressure Grouting. Tunnels and
fluid grout is determined using the Vicat
                                                         Tunnelling International: 28-35.
apparatus.
                                                     Emmelin, et al. 2007. Rock Grouting: Current
V.E.    Flowability (Marsh Funnel)
                                                        Competence and Development for The
     This test method provides an indirect              Final Repository. Stockholm. Svensk
measurement of the viscosity of clay slurries           Kärnbränslehantering AB.
using a funnel (Marsh Funnel) and a
                                                     Lombardi, G., Deere, D. 1993. Grouting design
graduated cup of specific dimensions. This
                                                        and control using the GIN principle.
test method provides a practical indicator of
                                                        International Water Power & Dam
the viscosity on a routine basis. The result
                                                        Construction.
determined using the method is referred to as
the Marsh Funnel Viscosity.                          Melbye, T., Hognestad, H., Dimmock, R. Pre–
                                                         Injection Technology for Mines.
                                                     Subash et al. 2016. Pre-grouting for Leakage
VI.     References
                                                         Control and Rock Improvement. J Civil
Association     of      Geotechnical       &             Environ Eng Volume 6 Issue 3.
    Geoenvironmental Specialists (Hong
    Kong). Tunnel Construction Guidelines 05
    - Guidance Note on Pre-Excavation
    Grouting for Underground Construction
    in Hard Rock – Principles & Design
    Elements.
ASTM C109. Standard Test Method for
   Compressive Strength of Hydraulic
   Cement Mortars (Using 2-in. or [50-mm]
   Cube Specimens).