The Power Sector: Position Paper On
The Power Sector: Position Paper On
IN INDIA
December 2009
EXISTING SCENARIO
Generation
1. India is the fifth largest producer of electricity in the world and according to the
Planning Commission, while the State Governments account for 51.5% of the total
generation capacity, the central sector and the private sector account for 33.1% and
15.4% of the generation capacity respectively. In line with the respective power
generation share, while the government sector (both central and state) have contributed
85.5% of the total capacity addition of 45,295 MW during 1999-00 and 2008-09, the
private sector has contributed the balance 14.5%, almost at par with its share in the total
installed capacity in the country. Transmission of power is entirely looked after by
government utility companies and distribution too barring a few states are in the hands of
the government entities.
2. India’s current installed power generation capacity as on 30th June, 2009 is at 1,50,324
MW as against 89,103 MW during 1997-98 and 1,32,329 MW at the end of March,
2007. In addition to this, the captive power capacity has been pegged at over 24,000 MW
at present. The break up with respect to the fuel mix accounts for as per the following
(refer Table 1 and Graph 1 below)
Table 1
Current Installed Capacity in India: As on 30th June, 2009
Categories MW %
Coal 78,459 52.2
2
POSITION PAPER – POWER
Chart 1
2.7% 8.8%
Thermal
Hydro
24.6%
63.9% Nuclear
RES (MNRE)
Source: CEA
3. The category wise share of the current installed capacity of 150,324 MW as depicted in
Table I and Chart 1 respectively translates to shares of Central Sector – 33.1%
33.1%, States –
51.5% and Private Sector – 15.4%
However, during the 11th Plan the structure is sought to be changed with respect to
capacity additions. The Central
entral sector is expected to lead the charge in capacity additions
with accounting for as much as 49% of the new capacity additions, while the private
sector is expected to
o add 22% to the overall kitty, leaving the balance 29% to the state
sector under the reduced target of 68,504
68 504 MW, down from the already revised 90,000
MW as against the original target of over 78,000 MW. However as per the actual
physical progress on the ground till the end of the financial 2008-09,
2008 09, while the private
and the state sectors have achieved its targeted capacity addition figures, there is
considerable slippage with respect to Central sector figures. In the first two years of the
current plan period,
riod, additional capacity of 13,017 MW has already been realised with an
additional 2,733 MW of captive capacity and another 44,670
44 670 MW is under construction.
3
POSITION PAPER – POWER
Chart 2
30,092
25,962
24,554
21,222 21,355
19,797
8,737
4,740 4,757
5. Detailed status for requirement of capacity addition for the XIIth Plan are under
finalisation in Central Electricity Authority (CEA) and as per the preliminary studies, the
requirement of capacity additi
addition works out to about 1,00,000 MW. There appears to
be a need to set higher target for private sector participation for the XIIth Plan in
view of its performance during the XIth Plan.
6. During the Xth Plan, total investment in the power sector was US$ 60 bbillion out of
which the private sector contribution was US$ 13 billion.. The projected investment
during the XIth Plan period is US$ 133 billionn out of which, the private sector
contribution is expected to be around US$ 37 billion or 21%.
%. In physical terms, a target
4
POSITION PAPER – POWER
of 78,700 MW has been fixed during this plan period, which has now been finally
revised to 68,504 MW.
Table 2
Capacity Addition Break Up: (XIth Plan)
Chart 3
68,504
57,687
34,120
21,447 20,013
19,495 16,227
14,889
The achievements in the above chart include projects that are under construction in addition
to the ones that have been already commissioned in the first two year of the current plan. In
the central sector a total of 3,990
990 MW have been commissioned and another 17
17,457 MW are
under construction.
on. Similarly, in the state sector 7,094
7 094 MW have been commissioned as
5
POSITION PAPER – POWER
against 12,919
919 MW being under implementation. Finally, in the private sector, a total of
1,933
933 MW have been commissioned and 14,294
14 294 MW are under implementation. In terms of
analysis, it is clear that the state sector is definitely on course with respect to its targeted
capacity addition and while the private sector does seem to be in sight of its target, it will
depend on its ability
ty to implement the under construction projects on time. In retrospect, it
appears that one could have kept a higher target for private sector for the XIth Five Year Plan.
In Generation, private sector certainly seems to be more promising than what has bee
been
anticipated. The cause for concern however, is the central sector in which as much as 37% of
the targeted projects are yet to reach the implementation phase thereby leading to the
conclusion that the central sector may not be able to meet the target.
Chart 4
90
45
21 16 19 21
7th plan 8th plan 9th plan 10th plan 11th plan 12th plan
7. While most of the growth in capacity addition during the 11th Plan will be fuelled by
Government utility companies, the growth in the 12th Plan is expected to be driven by the
6
POSITION PAPER – POWER
private sector players1. In fact, private companies have already announced capacity
addition of nearly 100 GW in the next 6 to 7 years compared to a total private
present. Even if a third of such projects see the light of
capacity of around 20 GW at present.
the day, private sector’s
or’s contribution to the national capacity addition in the power sector
shall be around 35% compared to 17 to 20% at present.
Since, 2003, 30 private power projects with a total capacity addition of 22,038 MW have
achieved financial closure. In 2008-09,
2008 thee private sector has contributed 883 MW of the
454 MW2. In terms of their efficiency improvements, private
total capacity addition of 3,454
thermal power plants have realised improvements in their Plant Load Factor (PLF) from
68.9% in 1999-00
00 to 95.1% in 2008-09,
2008 09, which compares favourably against the PLF of
71.2% and 84.3% achieved by the States’ and Central power plants respectively.
Chart 5
101.2
35.45
28.2 26.8
11.3 7.4 15
10 9.6 9.9 7.5
2.05 4.6 4.3
1
Indicative list of big size private power projects expected in Eleventh and Twelfth Plan is provided in Annexure A
2
Expected capacity addition in 2009-10 10 is 7,208 MW and is reflected in Annexure B
7
POSITION PAPER – POWER
9. The financial closure scenario for private capacity additions for Eleventh Plan as per
government estimates is given below in Table 3
Financial Closure Scenario for private capacity as per 11th Plan
Table 3
10. Despite the expected strong growth in capacity addition, India’s power shortage is likely
to remain very high and may in fact draw to a reasonable level during the 12th Plan. On
the T&D side, government has come out with a revised APDRP (Accelerated Power
Development and Reform Program) which will provide support and financial incentives
for reduction in T&D losses3. This is crucial for a sustainable development of power
sector, as India has amongst the highest T&D losses in the world. 11th Plan investments
under this scheme are targeted to US$10 billion. Another US$10 billion is likely to be
spent on rural electrification to achieve the government’s target of “Power for All” by
2012. Private investment in transmission sector is also set to pick up.
Chart 6
3
Refer Annexure D for Revised APDRP features
8
POSITION PAPER – POWER
Japan 4
US 6
China 7
Brazil 17
Pakistan 26
India 31
11. India ranks fifth in the world in terms of total installed power generation capacity but it
ranks as one of the lowest in terms of per capita consumption of power. At the end of
December, 2008, the base load deficit stood at 11.7% while the peak load deficit stood at
13.9%. More than 18% of villages and 45% of total households in India still do not have
access to power. The peak power shortage, which was around 11 – 12% levels during
du the
9th Plan period and the first few years of the 10th Plan, is on an increasing trend and has
already crossed 14% in the current year.
Chart 7
9
POSITION PAPER – POWER
Electricity Consumption/Capita
Electricity Consumption/Capita
Canada 18,359
US 14,057
China 2,560
Brazil 2,346
India 631
Chart 8
14
12 11 11.5
9.5 9.5
10
POSITION PAPER – POWER
Table 4
Source: CEA
13. The 17th Electric Power Survey (EPS) which is conducted by Central Electricity
Authority (CEA) has forecasted that the peak demand will be growing at a CAGR of
7.8% in the 11th Plan and the supply is expected to notch up around 6.8 to 7% during
this period thereby continuing with the upward trend of power deficit.
14. With respect to Transmission and Distribution, which are equally critically for the
overall success of the Power story in India, huge investments are required in these two
segments. Globally every dollar invested in generation has an equal amount invested in
T&D. However, in India, traditionally every dollar invested in generation has a
corresponding half a dollar invested in T&D. Importantly, as compared to the global
average of 50 to 60%, transmission lines in India are loaded to 90% capacity.
15. The planned implementation of Hydro Projects in the 11th Plan and their current status
is provided in the Table below:
Table 5
Sl# Type of CCEA Approved Hydro
Projects (11th Plan) Present Status
A NHPC Projects Out of 12 projects for 11th Five Year Plan
- Two projects (Omkareshwar &
13 NHPC projects approved by
Teesta V) with capacity of 1,030
CCEA out of which 12 projects
MW already commissioned in
with an aggregate capacity of 5,322
2007-08
MW are targeted for completion
- Sewa II for 120 MW likely to be
during 11th Five Year Plan
commissioned by December 2009.
- Six projects are likely to be
11
POSITION PAPER – POWER
completed in 2010-11
- One project to be completed by
2011-12
- Two projects with a capacity of
2,800 MW are likely to slip to 12th
Five Year Plan
th
The 13 project ie Kishanganga project of
capacity of 330 MW likely to be
completed by January 2016.
B Tehri Hydro Development The status is as follows
Corporation Project - Koteshwar 400 MW is likely to be
Three ongoing projects of the completed in March 2011
THDC - Tehri PSP project (1000 MW)
originally scheduled for 11th Plan
will slip to 12th Plan
- Pipalkoti HEP (444 MW)
originally scheduled in June 2013
will likely commence in July 2014
C NEEPCO projects Status
4 projects - Kameng (600MW) – slip to 12th
Plan
- Pare (110MW) – slip to 12th Plan
- Turial (60 MW) – slip to 12th Plan
- Monarchak Gas (100 MW) – to be
completed in Jan 2012
D NTPC on-going projects Achieved
Target of 17,760 MW in 11th Plan - 5 projects of 3,240 MW
involving 20 projects - 2007/08 & 2008/09 – 2740 MW
from five projects
- 2009/10 – 500 MW capacity
added
Slippages (11th Plan)
- Two projects aggregating to 2,580
MW
To make up this slippage additional
capacity of 2,790 MW have been added
in 11th Plan. Therefore, 11th Plan
capacity is 17,970 MW against 17,760
MW
E Satluj Jal Vidyut Nigam Completion Status
One project Rampur Hydro Electric The project is scheduled to be
Project for 412 MW is under commissioned by January 2012.
construction
(Source: Ministry of Power)
16. With a surge in generation capacity addition, India needs big growth in expenditure on
T&D networks to evacuate, transmit and distribute the power produced. Most of India’s
coal resources are concentrated in Eastern and Central India, while most hydro
12
POSITION PAPER – POWER
resources are in North East. Demand shortages are highest in Northern and Western
India. Huge investments are required to expand inter-regional grid capacity. Significant
investments are also required to upgrade the distribution infrastructure (to reduce T&D
losses) and for rural electrification. Government expects US$68bn investments in T&D
in the 11th plan. Actual investment is however expected to be around US$43bn, which
is around 135% growth over the 10th plan.
Transmission:
17. The XIth plan envisages an addition of over 60,000 MW of transmission network by
2012, designed to carry 60% of the power generated. The existing inter-regional power
transfer capacity is 17,000 MW which is to be further enhanced to 37,000 MW by 2012
through the creation of “Transmission Super Highways”. The guidelines for private
sector participation in transmission sector issued in January 2000 envisage two routes
for private sector participation:
• Through the Joint Venture route wherein the CTU/STU shall own at least 26%
equity and the balance to be contributed by the JV partner and
• Independent Private Transmission Company (IPTC) route wherein 100%
equity shall be owned by the private entity
INVESTMENTS
18. With the objective of meeting the rising demand of our growing economy and to
provide electricity to all by 2012, an ambitious target of 78,700 MW has been set for
the 11th Five Year Plan. Its sector-wise and source-wise break up in MW is as follows:
Table 6
(in MW)
Source / Hydro Thermal Nuclear Total % age
Sector
13
POSITION PAPER – POWER
The investments in the Power Sector over the 10 Plan (actual), 11 Plan (proposed and 12th
th th
Chart 9
133
111
96
60 60
47
37
13
19. In INR total investment in power sector in Xth plan was Rs 291,850
291 850 Cr or US$60
billion.. For the XIth plan, the INR figure is Rs 666,525
525 Cr out of which Rs 185
185,512 Cr
is private sector share.
14
POSITION PAPER – POWER
Chart 10
86
68
48
43
32
Generation T&D
20. Though the investment targets by the Government has been kept at around US$ 133
billion,
n, the actual investment is however, expected to be around US$ 86 billion
primarily on account of slippage in the target achievement by the central sector. A
power project implementation period is around 36 to 48 months from the date of
award of the mandate and hence only those projects which have been cleared up to
March 2008 would be in a position to meet the target date. One can keep the un
un-
awarded central projects out of the purview of the target achievement figures and on
that account alone, a total of over US$ 15 billionn will remain unrealised. Similarly
there could be slippages
ppages in the already awarded projects and therefore a shortage of
around US$ 20 to 25 billio
illion is expected during the XIth plan period.
21. Given the state of power infrastructure in the country and the overall requirement in
the next five year plans, the Government has taken some key initiatives. These are:
100% FDI permitted in generation, transmission and distribution
APDRP (Accelerated Power Development and Reform Programme) –
Investment of US$ 12 billion
b to reduce AT&C losses
sses to 15% from the existing
level of around 31%
%
15
POSITION PAPER – POWER
22. To attract large scale private investment, the Central Government has taken a number
of steps including the private sector to set up coal, gas or liquid based thermal, hydel,
wind or solar projects with foreign equity participation up to 100% under the
automatic route. The bulwarks of the new policy framework are the Electricity Act,
2003, National Electricity Policy 2006, Tariff Policy 2006, Rural Electrification
Policy 2006, New Hydro policy 2008 and Mega Power Projects 2008. In addition, the
Central Government has notified the National Load Dispatch Centre Rules, 2004.
Further, the Central Electricity Regulatory Commission (CERC) has notified several
important regulations including the regulations on tariff, open access in transmission
and licensing of transmission service providers and traders and the Indian Electricity
Grid Code, 2006. The Appellate Tribunal for Electricity was set up in 2004 to hear
appeals from Central and State Electricity Regulatory Commissions.
16
POSITION PAPER – POWER
The generation company or the transmission licensee, upon refinancing, would be allowed to retain
one-third of the net savings. In the past, net savings from any restructuring activity had to be entirely
passed on to the beneficiaries.
Source: Crisil Research
17
POSITION PAPER – POWER
Merchant Power Plants: Electricity Act 2003 allows developers to set up merchant
power plants which have no power purchase agreements. The tariff of these plants
will be market driven and not determined by the regulator but the entire risk will be
borne by the developer.
Allocation of captive coal blocks to public sector and private players
Even though a large part of the power generation will be coal dependent, it is
important that India moves away from sub-critical pulverised coal or ‘dirty’ coal.
There are no clear technology choices but their analysis suggests that commercial
supercritical combustion technology is the best option for India in the short-to-
medium term.
The supercritical coal based units have faster starting time and load changes and are
more suitable for daily start up/shut down operation and have better efficiency at part
load operation.
Discussions are on for the procurement of 7 units of 600 MW and 6 units of 800 MW
through bulk tendering, through International Competitive Bidding (ICB). The
selected bidders will have to set up manufacturing facilities in India with a Phased
Manufacturing Program.
Source: Ministry of Power
18
POSITION PAPER – POWER
19
POSITION PAPER – POWER
20 The earliest effort on PPP in the Power Sector can be traced down to Dabhol Power
Project in Maharashtra. The project did not succeed. The Dabhol power plant was
initiated in 1992 and took nine years to commence operation. The total project cost is
$2.9 billion for 2,184 MW of power. Enron owned along with other American
corporations owned 85% and the Maharashtra State Electricity Board (MSEB) owned
remaining 15%. The plant closed in June 2001, due to a payment and contract dispute
between the Maharashtra state government and the plant owners. The reasons were
• Viability of the project – as per World Bank letter to MoF, GoI “proposed
plant would produce too much power at too high a price for the State”4.
Further, fuel supply was liquid natural gas which was much costlier than coal.
• Fuel supply drain on exchequer – As per GoI, the plant’s annual import of 3
million tons of gas would drain the at least US$ 250 million from India’s
foreign exchange reserves.
• Currency risk on MSEB for fuel supply import
• Environmental concerns of the Dabhol project
The key overall issue was that PPP project risks were not properly assessed, and
equitably allocated between MSEB and Dabhol. Further project feasibility was not
done to verify whether the project would independently run without the necessary
Central and State guarantees.
20 Also to encourage power projects through the PPP mode, standardised bidding
processes and model documents which include the Request For Qualification (RFQ),
Request For Proposal (RFP) and RFP for technical consultants in Transmission
Systems have been developed. The Model Transmission Agreement is expected to be
finalised soon by the Ministry of Power.
21 The recent surge in adding new capacity in the power sector has been primarily driven
by rising power shortages (demand), electricity reforms initiated in 2003, de-
regulation of the electricity sector and potential for higher returns, gradual
improvement in financial situation of some state utilities, allocation of captive coal
4
Fact Sheet: Background on Enron’s Dabhol Power Project
20
POSITION PAPER – POWER
blocks to private and government companies and initiatives like UMPP (Ultra Mega
Power Project) at central and state levels.
Launched in 2005, nine Ultra Mega Power Projects (UMPPs) each with an initial
capacity of 4,000 MW are expected to result in around US$ 35 to US$ 40 billion of
private investment. Four UMPPs have already been awarded. The current status of the
UMPPs is given below in Table 4
Table 4
SL UMPP Company Bid tariff Expected
No (Rs/kwh) commissioning year
01 Mundra, Gujarat Tata Power 2.26 2012
02 Sasan, Madhya Reliance 1.20 First two units in April,
Pradesh Power 2012
03 Krishnapatnam, Reliance 2.33 September, 2013 to
AP Power October, 2015
04 Tilaiya, Jharkhand Reliance 1.77 2015
Power
05 Sundargarh, Orissa Bidding yet to commence
06 Cheyyur, Bidding yet to commence
TamilNadu
07 Girye, Under Bidding
Maharashtra
08 Tadri, Karnataka Under Bidding
09 Akaltara, Bidding yet to commence
Chattisgarh
Source: Planning Commission
22 There has also been a sharp increase in the number of captive plants with installed
capacity of 1 MW or more. It is estimated that 45,000 MW or 25% of the total
installed capacity is generated by this sector. Captive generators are also being
encouraged to supply their surplus power to the grid and by March, 2008, 14,900 MW
of captive generating capacity was connected to the grid. The Central govt has
earmarked coal blocks with reserves of 3.2 billion tonnes of coal for allotment to
21
POSITION PAPER – POWER
Chart 10
19,485
14,866
9,081 7,270
7,148
2,928 5,524 4,619
1,933 2,059 1,746
869 59 36 23 147 99 48
IIFC Plc, the UK subsidiary of IIFCL, has already lent to several projects, including
two ultra
ra mega power projects (UMPPs) – Tata Power’s Mundra and Relaince
22
POSITION PAPER – POWER
Power’s Sasan. Further, IIFCL has also received permission from government to raise
Rs 400 billion through tax-free bonds.
CONSTRAINTS
24 Stimulation of PPP in the power sector will require a pro-active approach from the
project sponsors, particularly the State and the central Government. Some of the key
constraints from the recent attempts in developing power projects on PPP mode
include:
Lack of understanding on PPP structure
Land acquisition issues
Lack of standardized documents leading to diverse interpretation of issues at
the states (lack of knowledge of available standardized documents)
Tighter access to liquidity
Arbitrary norms of pre-qualification primarily adopted by state entities
Inability to stick to set deadlines by the state entities conducting project
development activities
Faster pace of development on evacuation of power to attract private
investment in generation
Lack of trained manpower – Human Resources issues
Others
23
POSITION PAPER – POWER
o Lack of skilled manpower – The Working Group on Power has estimated the
need for 0.34 million additional manpower (0.26 million technical and 0.08
million non-technical) during the XIIth plan.
o Liquidity problem in the market owing to global meltdown makes it difficult
for developers to raise equity. Crisil Research states”Our interactions with
various lenders led us to conclude that in the current scenario equity has
become a key issue as private projects are held up at the financial closure stage
for the requirement of equity. Lenders find reassurance in the promoter’s
equity being brought in through cash flows or owners funds compared to the
equity brought in through the foreign direct investment (FDI) route.”
o Unavailability of long tenure debt to private sector – High cost of
guarantees
o Equipment Supply - On the whole, boiler turbine generator (BTG) orders of
around 70.0 GW have been placed for the Eleventh Plan period. Out of this,
around 60 per cent has been placed with BHEL (42.5 GW). Despite BHEL
5
Refer “Recommendations of the Committee on Infrastructure Financing / Power Ministry on financing power projects that require
consideration” – Annexure C
24
POSITION PAPER – POWER
26 The gap between demand and supply in the Power Sector is still huge. Many of the
“B” and “C” category towns have daily power cuts of 5-6 hours even in the non-peak
months. The small and medium industries have to rely on their own generators to
continue production but that comes at higher recurring costs and more capital
investments. Thus, products of many of these industries become uncompetitive as
compared to cheaper imports from other countries. There is a need to involve private
sector more intensively in Power Sector to bridge the gap between demand and
supply.
27 Most large manufacturing companies in India have set up their captive power plants
(implying higher project investments) to ensure regular and economic power supply.
All major non-ferrous industries have setup their captive power plants and their
reliance on grid power is limited to less than 10% only.
Power intensive industries set up their own captive units because:
• Grid power is usually unreliable and the production losses are huge due to
frequent power cuts and repeated starting and shutting down of machinery. The
fluctuation in voltage in grid power also damages the critical electronic
components for which the owners won’t like to take a risk.
• Due to the cross subsidy of power in India the tariff for industrial consumers is
very high and the cost arbitrage of setting up of a captive power unit is huge
Captive power seems the way ahead for power intensive / power dependant
mission critical industries.
25
POSITION PAPER – POWER
28 Study of 2001 Census data shows that there is a high correlation between the GDP per
capita of the states and the status of rural electrification. Bihar, Jharkhand, Orissa,
Assam and Uttar Pradesh (these 5 states constitute 35% of the total population) which
have the lowest levels of GDP per capita also have a poor record in rural
electrification. Similarly states like Himachal Pradesh, Punjab, Haryana and Tamil
Nadu which have higher rates of rural electrification also have higher per capita GDP.
Five states of Bihar, Assam, Uttar Pradesh, Kerala and West Bengal, which together
constitute 38% of India’s population, have an average per capita consumption of
272kWh/annum (57% lower than the national average). The high variation in per
capita consumption of power within India is also an indicator of existing gap in power
generation in the lower consuming states. The addition in generation capacities in
these states should have a significant impact on overall per- capita consumption figure
for India.
29 As per the 2001 Census, only 44% of the total rural households in India are
electrified, as compared to the 88% of the urban households. With 72% of India’s
population living in villages this means that almost 40% of country’s population does
not have access to electricity. According to Central Electricity Authority (CEA), even
today more than 100,000 villages (18% of total number villages in India) have no
access to power at all. National Council of Applied Economic Research (NCAER) did
a study to find out the factors that contribute to the big difference in the penetration of
consumer durable goods in the rural and urban areas. The interesting take away from
this study was that while factors like income and lifestyle differences do contribute to
the penetration of consumer durables, the most dominant factor was lack of regular
electricity supply in the rural areas6. This supports the view that there is a lot of latent
demand for power in the country which is not captured in the official figures.
6
Government has been pushing for electrification of villages. Refer “Rajiv Gandhi Grameen Vidyuthikaran Yojana
(RGGVY)” scheme in Annexure D
26
POSITION PAPER – POWER
7
One clear initiative is the enactment of The Electricity Act, 2003. Refer Annexure D on salient features of the same.
27
POSITION PAPER – POWER
28
POSITION PAPER – POWER
Annexure A
INDICATIVE LIST OF BIG SIZE PRIVATE POWER PROJECTS EXPECTED IN ELEVENTH AND TWELFTH PLAN
29
POSITION PAPER – POWER
Dhenkanal, Phase 1
30
POSITION PAPER – POWER
Annexure B
EXPECTED CAPACITY ADDITIONS IN 2009-10
31
POSITION PAPER – POWER
Private Gautami CCPP U3 Gautami Power Ltd Thermal Andhra Pradesh 174
32
POSITION PAPER – POWER
33
POSITION PAPER – POWER
Annexure D
During the 10th Plan, 235 projects were sanctioned for implementation. Additional 327
projects have been sanctioned under Phase I of the scheme during 11th Plan. The details of
sanctions and achievements so far are given below:
Targets and achievements during 2007-08 and quarterly targets during 2009-10 are as
follows:
35
POSITION PAPER – POWER
Qtr. IV 6,500
CCEA approved the “Restructured APDRP” for the 11th Plan on July 31, 2008. The objective
of the programme is reduction of AT&C loss to 15% in project areas through adoption of
information technology for energy accounting/ auditing and strengthening / upgradation of
distribution network. Projects under the schemes are to be taken up in urban areas – towns
and cities with population of more than 30,000 (10,000 in case of special category States)
Part A – is the projects for establishment of baseline data and IT applications for energy
accounting / auditing & IT based consumer service centres and
The R-APDRP program size is Rs 51,577 crores. The expected investment in Part–A
(Baseline System) would be Rs 10,000 crore and that in Part-B would be Rs 40,000 crore.
PFC is the nodal agency for operational zing the programme. Part ‘A’ & Part ‘B’ projects
can be implemented simultaneously with a gap of 3-6 months which is needed to establish the
baseline figure of AT&C loss of the project area through ring fencing by installation of
boundary (import/ export energy meters). Seventeen States have so far obtained the approval
for entire eligible towns under Part ‘A’. Under Part ‘A’ of R-APDRP, 1,130 projects with a
total cost of 4,183.93 crore has been sanctioned so far. Base line AT&C loss (figure) of the
project area is yet to be established.
36
POSITION PAPER – POWER
(in Rs crores)
4th Quarter Total
Sanctioned Project Target 1,100.00 1,100.00
Cost
Achievement 1,947.70 1,947.70
In the current year 2009-10, the balance projects of Part-A and some limited projects of Part-
B are targeted to be sanctioned and amount disbursed for implementation of projects
Salient Features
• The provisions of the Electricity Act except section 121 were brought into force with
effect from to 10th June 2003.
37
POSITION PAPER – POWER
Open Access
The Electricity Act mandates that non-discriminatory open access for inter-state as well as
intra-state transmission is to be provided by the Central Transmission Utility, State
Transmission Utilities as well as all transmission licensees. Open access on distribution was
to be introduced through regulation by SERCs such that by January, 2009 open access would
be available to all consumers who require a supply of electricity where peak power at any
38
POSITION PAPER – POWER
time exceeds 1 MW. Open access is expected to enable consumers to get power from any
source of their choice and induce improved service from existing utilities.
Open access in inter-state transmission has been effective but open access in intra-state
transmission and distribution has been largely restricted to captive consumers.
39
POSITION PAPER – POWER
References:
40