Final Examination #1: Open Book Questions (1 50)
Final Examination #1: Open Book Questions (1 50)
API 570
A. Set A
B. Set B
C. Set C
D. Set D
2. A pipe is NPS 16, and is made from A 335 Grade P1 material. The design pressure is 1200 psig, and
the temperature is 750°F. What is the minimum thickness of this pipe, if a 1/16” corrosion allowance will
be maintained?
A. .734”
B. .675”
C. .480”
D. .970”
3. From the information in #2 above, what will the required PWHT be (if any), if this piping will be girth
welded in place, and the actual thickness used will be 1/16” over the required thickness (including the
corrosion allowance)?
A. 1100 - 1325°F
B. 1100 - 1200°F
C. 200° preheat in lieu of PWHT is allowable per API 570
D. No PWHT is required on this thickness
4. If a WPS is qualified using a base material that is 9” thick, the correct base metal thickness range
shown in the WPS should be:
399
5. A valve will be replaced in a line that has seen significant external corrosion. The new valve is heavier
than the old valve, and will be placed in a location 10’ away from the nearest supports. What would a
primary concern be to you, the Inspector, regarding this situation?
6. An NPS 1/2 Category M pipe will be replaced. Baseline UT thickness readings to API 570 were
waived by the owner/user. The most likely reason for this is:
7. The total linear thermal expansion of a 30’ long, A426 Grade CP5 pipe operating between 70° and
350°F is:
A. .63”
B. 2.10”
C. 3.4’
D. 47”
8. An A-135 Gr. B Category D service pipe is to be replaced. The pipe is NPS 8, and will be .875” thick.
The pressure on the system is 120 psi @ 300°F, and the minimum temperature is -20°F. T his piping:
A. owner/user
B. Engineer or Inspector
C. Only the Engineer
D. Both A & B above
A. Sizes
B. Materials
C. Welding
D. Hydro requirements
400
11. During impact testing of an A182 F321 base metal, a 3/4 size bar was used instead of a full size bar.
The design temperature is 30° below the allowable minimum temperature listed in B31.3. At what
temperature must the impact test be performed?
A. -325°F
B. -355°F
C. -360°F
D. -430°F
12. A Class 600 flange, NPS 14, has a bolt hole diameter of ______________.
A. 1.50”
B. 20.75”
C. 1.375”
D. Not given in any available literature
13. When conducting ultrasonic shear wave examination of metal pipe and tubing to a DAC, it is
required that:
14. Two types of impact testing are permitted in ASME IX. One of these is:
A. Charpy V-notch
B. Etch-notch
C. Drop weight
D. Either A or C, above
15. A NPS 16 pipe has externally corroded 1/8” uniformly around the circumference. The pipe was originally
1.031” thick, and the material is SA-106 B, seamless with a temperature of 650°F. The current operating
pressure is 875 psi. Per API 570 rules, can this piping continue to run at this pressure without inspection
for 10 years, assuming a continued external corrosion rate of .031” per year?
16. The gasket contact surface from a 600# flange (NPS 8) has a radial “ding” in the 125 RMS face surface
that is not deeper than the bottom of the serrations but is greater than 1/2 the depth of the serrations.
The length of the “ding” is 3/8”. This imperfection should be judged _________.
A. Acceptable
B. Rejectable
C. Not enough information given
D. Flange “dings” are not a concern to a piping inspector
401
17. The allowable unsharpness for a material that is 2” thick is:
A. .030
B. .020
C. .040
D. Unsharpness is not allowed in any ASME Code
18. A locally thin area is 1/2” away from a girth weld on an NPS 18 pipe. The thin area is found to be .725”
thick, and the original base metal is 1.23” thick. The pipe is A 369 Gr. FP9, and the temperature is
600°F. If the girth weld has not been radiographed, what is the current design pressure (or MAWP)
of this piping using the formula provided in API 570. (Not considering future corrosion or
inspections.)
A. 812 psi
B. 947 psi
C. 1150 psi
D. 1350 psi
19. A 12 NPS pipe is repaired by butt welding a replacement piece into the line using machine
GMAW. The welding operator is qualified by radiography on the first butt weld. What criteria
should be used to determine the acceptability of this radiograph?
A. ASME IX
B. ASME V
C. ASME B31.3
D. API 570
20. A hole-type IQI is observed on a RT film for an aluminum weld. The IQI body is placed across the weld,
but the lead letter “F” and the I.D. markers are not in the area of interest. Per ASME V, this condition is:
A. Acceptable as shown
B. Unacceptable - wrong placement for aluminum welds
C. Unacceptable - hole IQI’s cannot be used on this material
D. Unacceptable – hole type IQI’s cannot be used across the weld when a film-side set-up is used.
22. A B564 GR NO 6600 Class 2500 flange is installed in a piping system that will be hydrotested at 9500
psi. This condition will be:
A. Acceptable
B. Unacceptable - exceeds flange hydro-rating
C. Acceptable, provided the test medium is water, and not air
D. Unacceptable if the system will operate above 10,000 psi
402
23. A piping system will be hydrotested after a re-rating. The new design is for 600 psi @ 800°F, and
material is A376 TP 304H. The test will be run with condensate at 400°F. What is the required test
pressure on this system?
A. 900 psi
B. 1184 psi
C. 1107 psi
D. 1200 psi
24. If a carbon steel piping system is A-106B and is .125” thick with a minimum design temperature of -
55°F, the piping must be:
A. Normalized
B. Annealed
C. Impact tested
D. Radiographed
25. One of the items that must be marked on every B16.5 flange is:
A. 3 inlets/outlets instead of 4
B. 2 inlets and 2 outlets instead of 6
C. Flow is allowed to go only one way in a cross
D. A “cross” can be used as a reducer - a “tee” cannot
28. During a pneumatic leak test of a 160 psi design pressure system, the pressure shall be gradually
increased until ________ psi is reached, and then a preliminary check of the system shall be made:
A. 25
B. 88
C. 176
D. 80
29. The maximum miter bend angle permitted in severe cyclic conditions is:
403
30. A 600# flanged fitting is NPS 6 (6.625” O.D.) and is made from A-48 Grade 55 gray cast iron. The fitting
is installed in a system operating at 200 psig @ 300°F. The fitting is seamless, and is currently in use in
an underground piping system. What is the minimum thickness of this fitting?
A. .250
B. .120
C. .350
D. .180
32. SCC of Austenitic stainless steels is classified as ___________ per API 570, when it does not occur
under insulation.
A. Environmental cracking
B. Creep
C. CUI
D. Erosion
33. A welding procedure is qualified on P5A to P5A steel. This WPS is then qualified to weld on:
A. P5A - P4 steels
B. P5A - P5B steels
C. P4 - P4 steels
D. All of the above
A. Contact pyrometers
B. Infrared thermography
C. Temper sticks
D. Feeling with your hand
35. A pipe is thickness checked in 1997 and found to be .380” thick. The pipe was previously checked in
1991 and was found to be .466” thick. The pipe is 16 NPS and is made from API 5L Grade X-42 ERW
pipe. Assuming the same corrosion rate continues, can the piping MAWP rating of 150 psi @
400°F be continued if the next inspection is set for 10 years?
404
36. When inaccessibility prevents placing of RT location markers on the source or film side, a
___________ shall accompany the radiographs to show full coverage has been obtained.
A. Narrative report
B. Inspector’s certification
C. Dimensioned map
D. Photograph
37. A girth weld is UT inspected to Normal Fluid Service and is found to have an indication that is
characterized as a slag inclusion. The inclusion is 3/8” long and the piping is 1/2” thick. The width is
3/8”. This indication is characterized as a ______________ per B31.3.
A. Imperfection - acceptable
B. Discontinuity - acceptable
C. Defect - unacceptable
D. Indication - acceptable
38. When will the next UT thickness inspection be required on a Class 2 piping system with the following
information:
A. 1995
B. 1998
C. 2000
D. 2013
39. An NPS 4 branch connection is made from A-106 Gr B, and is installed in an NPS 16 header that is
A671-CC70. The installation is similar to Fig. 328.5.4D, Sketch 4. The branch is .281” thick. The header
is .535” thick, and the repad is .200” thick. The fillet weld leg is .500”.
This connection _____________________ per B31.3.
40. When conducting a bubble leak test, the temperature at the surface of the part should be within
_____°F to _____°F.
A. 60 - 125
B. 40 - 125
C. 30 - 100
D Above 70°F
405
# QUESTIONS ( 41 ~ 50 ) are based on WPS/PQR GMAW-2, attached:
41. The upper base metal thickness allowed on the WPS:
A. Is acceptable as shown
B. Should be .495”
C. Should be .900”
D. Should be .450”
A. Acceptable to B31.3
B. Should be 100°F min
C. Should be 160°F min
D. Not to B31.3 requirements - must be at least 175°F
43. The gas backing range shown on the WPS, as qualified on the PQR is:
A. Acceptable as shown
B. Unacceptable - should not be shown on the WPS
C. Unacceptable - should not be shown on the PQR
D. Unacceptable - material shown does not require a backing gas
A. Are acceptable
B. Are rejectable - T-1 fails
C. Are rejectable - T-2 fails
D. Are rejectable - not enough specimens were taken
46. The impact test results shown on the PQR for the weld:
406
47. If this procedure will be used for pipe inservice at -30°F design temperature, the impact tests
shown on the PQR for the HAZ are:
A. Acceptable as shown
B. Should be restricted to .495”
C. Should be restricted to .550”
D. Should be 1/8” only, as shown on the PQR for filler metal size
407
408
409
410
411
# CLOSED BOOK QUESTIONS ( 51 ~ 150 )
51. The radiographic density through an IQI is measured at 2.6 with a densitometer using gamma RT. The
allowable density through the weld will be _______, if no shim is used.
A. 2.0 - 4.0
B. 1.8 - 4.0
C. 2.21 - 3.38
D. 2.0 - 2.99
A. Hydraulic snubber
B. Shoe
C. “Can” spring hanger
D. Sway brace
54. A Class 3 pipe is UT thickness checked in 1990 and found to be .385” thick. The pipe is then checked
in 1994 and found to be .300” thick. Original thickness was .432” in 1981. If the required thickness is
.182”, how many years can pass before the next thickness inspection?
A. 5.6
B. 5
C. 10
D. 2.8
55. Mill Test Reports _____________ considered a substitute for PMI Testing.
A. can be
B. & X-Rays are
C. should not be
D. are
412
57. Austenitic stainless steel piping (for example A312 Type 304) is NPS 6 (.432” nominal wall
thickness). This piping will have a minimum wall thickness (new and cold) of:
A. .432”
B. .378”
C. .300”
D. SS piping is not supplied in “NPS”. It only comes in “min. wall”
58. Which of the following is an essential variable for the GMAW process?
A. Wire diameter
B. Travel speed
C. Interpass temperature
D. Electrical characteristics (short arc to spray or vice-versa)
59. A P-1 (carbon steel) piping system has originally been PWHT’d because of H2S Service. A flush patch
repair weld is required to one section of the pipe due to corrosion. This repair weld:
A. Must be PWHT’d
B. May be preheated to 300°F per API 570, and no PWHT applied
C. May be “Temper-bead” repaired per API 570
D. Can be stress relieved by peening and interpass heat control
A. .0400
B. .160
C. .020
D. .40
A. Pressure vessels
B. HF Alky piping
C. Bulk transfer lines at a dock
D. Both A & C above
A. SNT-TC-1A
B. CP-189
C. An in-house manufacturer’s program
D. No specific personnel qualifications are mandated by ASME V – per referencing code
413
64. A “TML” is utilized to provide thickness information on piping systems. This information must then
be used to establish:
A. Corrosion rates
B. Inspection Intervals
C. Metal loss
D. All of the above
65. An API 570 Inspector with a high school education must have _____ years experience to qualify as an
API 570 Inspector.
A. 3
B. 5
C. 8
D. 10
66. An API 570 Inspector with a high school education must have _________ years experience to
qualify as an ASME 31.3 Inspector
A. 3
B. 5
C. 8
D. 10
A. Hydrogen service
B. Catalyst lines
C. Sour water piping NPS 3/8”
D. Raw chemicals
68. Per API 570, CUI inspections on Class 2 systems _________ include _______ % of suspect areas
and _______% of damaged insulation areas for plants with no CUI experience or history.
A. P4X metals
B. P5A metals
C. P3X metals with GMAW-Spray Arc
D. P-1 metals with GMAW short-circuiting arc
414
71. Class 3 secondary SBP shall be UT inspected at which maximum intervals?
A. 10 years
B. 5 years
C. 3 years
D. None of the above
74. Underground piping may alternatively be pressure tested instead of inspected. If used, this pressure
test must be conducted at ___________ intervals on piping not cathodically protected in soil that has a
resistivity of 2,000 - 10,000 OHM/CM.
A. 5 year
B. 10 year
C. 15 year
D. 20 year
75. One of the procedural requirements for MT examination that must be addressed is:
A. Magnetizing time
B. Developer application
C. Type of particles, wet or dry
D. A and B above
A. Material considerations
B. Welding considerations
C. Design considerations
D. Inspector opinion
415
78. Cathodic protection systems shall be monitored at intervals in accordance with:
A. NACE RP 0169
B. API RP 651
C. Both A & B above
D. None of the above
79. Records of PMI Testing for new & existing piping systems should be kept?
A. SNT-TC-1A
B. AWS CWI
C. Manufacturer’s/contractor’s program
D. ACCP
81. Class 3 piping should be visually inspected at a maximum interval of _________ years.
A. 5
B. 10
C. 15
D. 1/2 RCL or 10 years
A. WPS only
B. PQR only
C. WPQ only
D. WPS and PQR only
83. After major repairs are completed on a piping system a pressure test shall be performed if:
84. If RBI is used to plan the frequency of detailed inspections on a Class 1 system, the RBI assessment
must be done at least every ____________.
A. 3 years
B. 10 years
C. 5 years
D. year
416
85. A piping system is Class 3 and is 1/2” thick carbon steel. The decision is made to replace a
corroded section of the piping by welding in an insert (flush) butt-welded patch. This patch will:
86. The required mill undertolerance on pipe is normally -12.5%, but some piping is made from plate which
has an undertolerance of ______________.
A. 12.5%
B. +16”, -0”
C. - .01”
D. + 9%
87. If environmental cracking is suspected on attached piping during internal inspection of pressure
vessels, the Inspector should:
88. A visual examination procedure must be qualified to prove the procedure is adequate. An artificial flaw
may be used for this demonstration that is __________.
89. Which of the following is not a tool for measuring corrosion of piping:
90. If the WPS shows a single “Vee” groove is to be used and the PQR was qualified with a double “Vee”
groove:
91. Welded repair of cracks occurring in-service should not be attempted without consulting the:
A. API Inspector
B. Contractor
C. Piping Engineer
D. Maintenance Foreman
417
92. If carbon steel piping is to be welded and the temperature is less than 32°F, the piping must be
preheated to a minimum temperature of ___________ °F per B31.3
A. 100°F
B. 75°F
C. 150°F
D. 50°F
93. Many problems found during in-service inspection of piping systems can be directly attributable to:
A. Hydrostatic testing
B. Lack of proper new-construction inspection
C. Cold winters
D. Lack of internal inspections
94. Of the types of stresses that are placed on a thin walled cylinder, the most severe is:
A. Longitudinal
B. Circumferential
C. Compressive
D. Radial
95. The ultimate load on a .510” diameter tensile specimen is 15,000 lbs. The ultimate strength of this
specimen is approximately:
A. 73,529 psi
B. 90,200 psi
C. 85,100 psi
D. 18,359 psi
96. At what temperatures does SE-797 provide guidelines for measuring the thickness of materials using
the contact pulse-echo method?
A. Porosity
B. Lack of penetration
C. Tungsten inclusion
D. Overlap
418
98. If a probable corrosion rate cannot be determined from the same or similar service, estimated data, or
other methods, an initial thickness measurement shall be conducted after no more than _______ of
service using NDE thickness measurements.
A. 1000 hours
B. 3 months
C. 2 years
D. 5 years
99. A pressure test of a final closure weld is not required when a slip-on flange construction in service
piping is used, provided the new piping is pressure tested, a miter joint is not used, and ____________.
100. A welding electrode is marked E8018. The first two digits mean that the electrode has:
101. A standard hydrostatic test is to be run after an alteration on a piping system. The piping has a stress
value of 20 ksi at the test temperature and 17 ksi at design temperature. The design pressure is 720
psi. What is the calculated test pressure?
A. 1080 psi
B. 918 psi
C. 1270 psi
D. 792 psi
102. Before breaking a flanged connection to conduct an inspection, necessary precautions should
include:
103. After radiography of a piping girth weld, a dark image of a “B” is noticed on the radiograph. This is
probably caused by:
A. Backscatter
B. A welders I.D. stamp indented in the metal
C. A lead reference mark
D. An artifact of the film
419
104. A piping “scab” patch will be applied to correct a leak in an NPS 14 pipe. The pipe material is rated for
41 KSI SMYS. This “scab” patch is ____________.
105. Per ASME IX, a longitudinal bend test is only allowed when:
106. The scope of API 570 begins where a vessel terminates, specifically:
108. The two primary NDE methods referenced by API 570 for thickness examinations are:
A. RT, AET
B. ET, UT
C. MT, UT
D. UT, RT
110. A leak test of a buried piping system should be maintained for a minimum of _______ hours. After
________ hours the system pressure should be noted, and the system should be re-pressurized if
required.
A. 4, 4
B. 8, 8
C.` 8, 4
D. 4, 8
420
111. An API Piping Inspector’s duties may include:
112 A pipe is UT inspected in 1978 and found to be .370” thick. The pipe is next inspected in 1982 and
found to be .300” thick. The pipe is next inspected in 1990 and found to be .200” thick. The pipe is then
inspected in 1997 and found to be .180” thick. If the piping required thickness is .135”, when should
the next UT thickness inspection be conducted?
A. 4.5
B. 2.25
C. 5
D. 10
113. A ferritic stainless steel piping system will be hydrotested. The water used for this test must be:
A. Low in chlorine
B. Low in fluorine
C. Low in sulphur
D. None of the above
115. An ASME magnetic particle field indicator is made up of how many “PIE” sections furnace
brazed together?
A. 2
B. 8
C. 6
D. 4
A. Be qualified to SNT-TC-1A
B. Have 10 years experience
C. Have an annual vision test to J-1 standards
D. Have an annual vision test to J-2 standards
117. RP 578 applies to ________________ process piping systems covered by ASME B31.3 & API 570.
A. new
B. existing
C. covered
D. both A & B, above
421
118. CUI must be investigated for piping systems operating between _________ which may have had
moisture ingress.
A. 20 - 250°F
B. 250 - 600°F
C. -4 to 120°C
D. 65 to 204°C
A. RL = CA/ pressure
B. RL = t actual – t required/ corrosion rate
C. RL - t minimum/ corrosion allowance
D. RL = t actual - t min/ temperature
120. Which of the following should not be considered an alteration per API 570.
121. The allowable internal misalignment on a circumferential butt weld is ______ per ASME B31.3
requirements.
A. 1/16”
B. 1/8”
C. Per the Inspector’s judgment
D. Per the WPS allowances
A. PT examinations
B. RT examinations
C. MT examinations
D. AE examinations
123. A 1/4” leg fillet weld will have a throat dimension of:
A. .250”
B. .176”
C. .190”
D. .35”
124. Per API 570, the absolute minimum number of TML’s that any given piping circuit must be
assigned is _____________.
A. One
B. Two
C. 12
D. As required by the API 570 Inspector
422
125. The pressure classes given in ASME B16.5 include which of the following:
A. 100
B. 700
C. 900
D. 1200
126. If seal welds are employed on a threaded joint, the Code requires that:
A. Size
B. Diameter at the reduced end
C. Diameter at the large end
D. The geometry of the reduction
128. If welding procedures are to be “shared” between companies as allowed by ASME B31.3, a
number of conditions must be met. One of these conditions is:
A. P # limited to 1, 3, 4, 5, 6, 7, or 8
B. Material to be welded is not more than 3/4” thick
C. Lethal service is not permitted
D. The employer has at least two welders qualified with the new procedure.
129. A Class 1 piping system has been thickness checked in 1972, and was found to be .760” thick. The
required thickness is .428” (by calculation), and the piping was re-checked visually and for thickness in
1984 and 1995. The 1984 inspection showed .688” and the 1995 inspection shows .540”. Per API 570,
when should the next UT and visual inspection be conducted?
130. When weld hardness tests are required by ASME B31.3, at least __________% of the welds must be
tested when local PWHT is employed.
A. 5%
B. 10%
C. 25%
D. 100%
423
131. ___________ or ____________ may be used with UT instruments when checking pipe with
operating temperatures above 200°F.
132. The IQI image must be visible on _______ sides when using a shim, per ASME V.
A. 1
B. 2
C. 3
D. 4
133. A flared tubing joint has (essentially) 4 critical components, one of these components, by name could be
the:
A. Body
B. Nut
C. Sleeve
D. Both A & B above
134. Socket weld and threaded flanges are not recommended for service above ______°F or below _____
°F, per B16.5.
A. 500, -50
B. 300, -20
C. 200, -10
D. 100, -5
135. Which of the following welding documents must be certified by the test laboratory, per ASME IX?
A. WPS
B. PQR
C. PQR and WPQ
D. None of the above
137. The difference between an “examination” and an “inspection” per B31.3 is:
424
138. Shims may be placed under a hole IQI to simulate weld reinforcement to assure the density in the area
of interest is not more than ______ lighter than the density through the IQI.
A. -30%
B. +30%
C. -15%
D. +15%
139. The intensity of the black light at the surface shall not be less than ___________ when conducting a
fluorescent PT examination.
A. 100 μW/cm 2
B. 1000 μW/cm 2
C. 800 μW/cm 2
D. 400 μW/cm 2
140. By definition, a piping circuit is a section of piping that has all points exposed to an environment of
similar corrosivity and of similar ________ and _________.
141. When selecting TML’s for threaded connections, only those that can be _________ should be
selected.
A. UT’d
B. VT’d
C. RT’d
D. PT’d
142. A welder qualifies on a 3 NPS pipe in a 6G position. The piping is titanium, and the weld is made with
SMAW. How many bend tests are required for this test weld?
A. 2
B. 4
C. At least 3
D. RT is required for this weld in lieu of bend tests
143. How many individual examinations must be conducted on each area of interest when conducting MT
examination, per ASME V?
A. 1
B. 2
C. 3
D. 4
425
144. The recommended upstream limit of an injection point on an NPS 10 pipe in a Class 1 system is?
A. 12”
B. 20”
C. 18”
D. 30”
145. Rerating by changing temperature or pressure of a system can be done only if which of the
following is met?
146. An example of an essential variable using the SMAW process for procedure qualification is:
A. Change in PWHT
B. Change in backing
C. Change in pipe diameter
D. Change in amps/volts
147. If pipe leaks are clamped and re-buried, the location of the clamp ______ be logged in the
inspection record and ______ be surface marked.
A. Shall, shall
B. Shall, must
C. Shall, may
D. May, shall
149. Per ASME V, an examiner must be in a darkened room for at least _____ minutes prior to
performing a fluorescent PT examination.
A. 2
B. 1
C. 10
D. 15
150. Per ASME B16.5, bolt holes in flanges are all required to be placed in multiples of _______.
A. 2
B. 3
C. 6
D. 4
426
API 570 ANSWER SHEET
427