MONITORING AND EVALUATION REPORT OF THE ANNUAL OPERATION PLAN (AOP)
ACTION TAKEN JUSTIFICATION
AOP Activities COMPLIED NOT COMPLIED Evidence of compliance Action plan if not REMARKS
complied
A. Faculty orientation on the alignment if the PVMGO to the curriculum
Activity: Complied Minutes of the
1. Orientation of faculty on the orientation
PVMGO
2. Conduct training and Complied Certificate of attendance
workshop on the preparation
of syllabus and lesson plan
with its alignment to the
PVMGO
3. Evaluation of the prepared Complied
curriculum maps and subject
syllabus on the alignment of
the PVMGO
4. Classroom observation on the Not complied Implemented when F2F Blended learning system
implementation of the is permitted of teaching not F2F
curriculum
B. Updating and upgrading instructional leaders and academic coordinators on current trends in curriculum
development, teaching and learning and instructional management.
Activity: Complied Certificate of
1. Sent/attended teachers to In- participation
set Training and Workshop
2. Re-echo the Training and Not complied Not applicable, all had All attended the training
Workshop participated the training because it was via Zoom
because it was via Zoom
3. Application and Complied
implementation of the
training outputs to the school
C. Academic Support and Student Development Services (Registrar, Guidance and Library)
Activity: Not complied On-going search for
1. Hire or appoint license license manager
personnel to manage each
department unit
2. Formulation of department Complied partially Ongoing formulation of Not all department with
handbook/manual manual to some manual
department
D. Physical plant and Instructional support facilities
Activity: Not yet complied To start the renovation Budget is not yet ready
1. Renovation of the school sooner
Library
2. Allocation of budget Not yet complied To start the renovation Budget is not yet ready
sooner
3. Bidding Not yet complied To start the renovation Budget is not yet ready
sooner
4. Implementation of the Not yet complied To start the renovation Budget is not yet ready
project & monitoring sooner
5. Completion and turning Not yet complied To start the renovation Budget is not yet ready
over of the completed sooner
project
NOTE:
The rest of the activity is not yet included in this report
MEDINA COLLEGE IPIL INC
Don Andres, Ipil, Zamboanga Sibugay
MONITORING AND EVALUATION REPORT OF THE STRUCTURE-BASED SCHOOL IMPROVEMENT PLAN (SSIP)
ACTION TAKEN JUSTIFICATION
SSIP Activities COMPLIED NOT COMPLIED Evidence of compliance Action plan if not REMARKS
complied
A. PHILOSOPHY, VISION, MISSION GOALS AND OBJECTIVES
Activity: Minutes of the
1. Alignment of PVMGO to the Complied orientation
curriculum
B. Curriculum Assessment and Instruction
Activity:
1. Intervention program of Complied Intervention straggles
students with learning and schedule is on file
difficulties
C. Instructional Leadership
Activity :
1. Communicate to Activity is done every
stakeholders the school Complied Minutes of the meeting PTA meeting
PVMGO, curriculum
development, assessment
and instruction
D. Faculty
Activity:
1. Sending teachers for In-set Complied Certificate of
Training and Workshop Participation
E.
Note:
Other items not yet monitored & evaluated