Rencana Anggaran Biaya: NO Uraian Pekerjaan Harga Satuan (RP) Jumlah Harga (RP)

The document is a budget plan for the construction of an automotive skills practice room at SMK Negeri 1 Kuningan, West Java. It includes 7 sections - preparation work, building construction (foundations, concrete, walls, doors and windows, roof, ceiling, floor tiles) with details of materials, quantities, unit prices and total costs. The total projected cost is over Rp600 million.

Uploaded by

Rosyad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
241 views2 pages

Rencana Anggaran Biaya: NO Uraian Pekerjaan Harga Satuan (RP) Jumlah Harga (RP)

The document is a budget plan for the construction of an automotive skills practice room at SMK Negeri 1 Kuningan, West Java. It includes 7 sections - preparation work, building construction (foundations, concrete, walls, doors and windows, roof, ceiling, floor tiles) with details of materials, quantities, unit prices and total costs. The total projected cost is over Rp600 million.

Uploaded by

Rosyad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

RENCANA ANGGARAN BIAYA

Pekerjaan : Pembangunan Ruang Praktek Kompetensi Keahlian Tehnik Kendaraan Ringan


Lokasi : SMK Negeri 1 Kuningan Kabupaten Kuningan Provinsi Jawa Barat
TA : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME
(Rp) (Rp)
(1) (2) (3) (4) (5)

A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bouwplank 1.00 ls 500,000.00 500,000.00
2 Membersihkan lapangan dan perataan 1.00 ls 2,500,000.00 2,500,000.00
3 Persiapan steiger 1.00 ls 1,500,000.00 1,500,000.00
4 Mobilisasi dan demobilisasi 1.00 ls 1,500,000.00 1,500,000.00
6,000,000.00
B PEKERJAAN PEMBANGUNAN RUANG KELAS (4 RUANG KELAS)
I PEKERJAAN TANAH DAN PONDASI
1 Galian tanah 104.30 m3 60,000.00 6,257,700.00
2 Urugan pasir bawah pondasi setempat t= 5cm 6.52 m3 160,800.00 1,048,416.00
3 Urugan tanah kembali 34.77 m3 20,000.00 695,300.00
4 Urugan tanah dipadatkan 79.20 m3 88,800.00 7,032,960.00
5 Pas. Batu Kosong (Aanstamping) 16.69 m3 396,828.00 6,621,948.20
6 Pas. Batu Belah 1 : 5 71.72 m3 796,716.00 57,140,471.52
78,796,795.72
II PEKERJAAN BETON
1 Pasangan sloof beton bertulang 15/20
a. Adukan 1Pc: 2Ps: 3Kr 4.89 m3 1,056,653.17 5,167,034.02
b. Pembesian (4 Ø 12mm, Ø 8mm - 150 mm) 876.94 kg 18,589.00 16,301,437.66
c. Bekisting 32.60 m2 141,120.00 4,600,512.00
2 Pasangan kolom struktur beton bertulang 20/20
a. Adukan 1Pc: 2Ps: 3Kr 4.16 m3 1,056,653.17 4,395,677.21
b. Pembesian (8 Ø 12mm, Ø 8mm - 150 mm) 956.80 kg 18,589.00 17,785,955.20
c. Bekisting 20.80 m2 265,910.00 5,530,928.00
3 Pasangan kolom selasar beton bertulang 20/20
a. Adukan 1Pc: 2Ps: 3Kr 2.08 m3 1,056,653.17 2,197,838.60
b. Pembesian (8 Ø 12mm, Ø 8mm - 150 mm) 478.40 kg 18,589.00 8,892,977.60
c. Bekisting 10.40 m2 265,910.00 2,765,464.00
4 Pasangan kolom praktis beton bertulang 15/15
a. Adukan 1Pc: 2Ps: 3Kr 0.72 m3 1,056,653.17 760,790.29
b. Pembesian (4 Ø 12mm, Ø 8mm - 150 mm) 163.84 kg 18,589.00 3,045,621.76
c. Bekisting 0.80 m2 265,910.00 212,728.00
5 Pasangan balok litle beton bertulang 10/15
a. Adukan 1Pc: 2Ps: 3Kr 1.08 m3 1,056,653.17 1,141,185.43
b. Pembesian (4 Ø 12mm, Ø 8mm - 150 mm) 349.92 kg 18,589.00 6,504,662.88
c. Bekisting 6.30 m2 272,210.00 1,714,923.00
6 Pasangan ring balok beton bertulang 15/20
a. Adukan 1Pc: 2Ps: 3Kr 3.36 m3 1,056,653.17 3,550,354.67
b. Pembesian (4 Ø 12mm, Ø 8mm - 150 mm) 602.56 kg 18,589.00 11,200,987.84
c. Bekisting ( 2 x pakai ) 11.20 m2 272,210.00 3,048,752.00
7 Pasangan balok gantung beton bertulang 15/20
a. Adukan 1Pc: 2Ps: 3Kr 1.86 m3 1,056,653.17 1,965,374.90
b. Pembesian (4 Ø 12mm, Ø 8mm - 150 mm) 333.56 kg 18,589.00 6,200,546.84
c. Bekisting ( 2 x pakai ) 8.53 m2 272,210.00 2,320,590.25
109,304,342.15
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME
(Rp) (Rp)
(1) (2) (3) (4) (5)
III PEKERJAAN DINDING
1 Pasangan dinding bata merah 1pc : 5Ps 349.12 m2 107,629.00 37,575,436.48
2 Plesteran Dinding 1Pc : 5Ps tebal 15 mm 698.24 m2 56,545.20 39,482,120.45
3 Acian dinding dan beton 781.44 m2 34,050.00 26,608,032.00
4 Pengecatan dinding baru 781.44 m2 26,666.00 20,837,879.04
124,503,467.97
IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pekerjaan kusen pintu allumunium
a. Pekerjaan kusen allumunium 32.80 m1 138,706.00 4,549,556.80
b. Pasangan daun pintu allumunium panel kaca 5mm (lengkap) 8.00 unit 1,750,000.00 14,000,000.00
2 Pekerjaan kusen jendela Allumunium
a. Pekerjaan kusen allumunium 117.60 m1 138,706.00 16,311,825.60
b. Pekerjaan pasangan daun jendela allumunium panel kaca polos 5mm (lengkap)16.00 unit 620,000.00 9,920,000.00
b. Pasangan kaca polos 5 mm 27.04 m2 171,300.00 4,631,952.00
3 Pekerjaan kusen BV
a. Pekerjaan kusen allumunium 104.40 m1 138,706.00 14,480,906.40
b. Pasangan kaca polos 5 mm 21.84 m2 171,300.00 3,741,192.00
67,635,432.80
V PEKERJAAN ATAP
1 Pasangan rangka atap baja ringan profil C 0.75 mm 526.56 m2 174,500.00 91,884,526.56
2 Pasangan penutup atap genteng metal pasir 526.56 m2 135,840.00 71,527,759.82
3 Pasangan bubung genteng metal 55.00 m1 89,150.00 4,903,250.00
4 Pemasangan woodplank 0,8/20 100.00 m1 53,100.00 5,310,000.00
5 Pengecatan listplank 40.00 m2 74,370.00 2,974,800.00
176,600,336.37
VI PEKERJAAN PLAFOND
1 Pekerjaan rangka plafond GRC uk. 4/6 kayu kelas 2 456.00 m2 113,190.00 51,614,640.00
2 Pasangan penutup plafond gypsum board 456.00 m2 47,282.00 21,560,592.00
3 Pengecatan plafond 456.00 m2 26,666.00 12,159,696.00
4 Pasangan list plafond 288.00 m1 25,545.00 7,356,960.00
92,691,888.00
VII PEKERJAAN KERAMIK
1 Urugan pasir lantai kerja, t= 5 cm 17.70 m3 160,800.00 2,846,160.00
2 Pasangan keramik lantai uk. 40x40 354.00 m2 196,755.00 69,651,270.00
72,497,430.00
VIII PEKERJAAN LISTRIK
1 Pas. Instalasi titik Lampu 20.00 ttk 84,930.00 1,698,600.00
2 Pas. stop kontak + Instalasi 8.00 bh 25,930.00 207,440.00
3 Pas. Saklar ganda 8.00 bh 30,930.00 247,440.00
4 Pas. Saklar tunggal 4.00 bh 25,930.00 103,720.00
5 Pasang Kabel NYM 3 x 2 1/2 225.00 m 21,250.00 4,781,250.00
6 Pas. Lampu SL 18 w 20.00 bh 73,930.00 1,478,600.00
8,517,050.00
IX PEKERJAAN RABAT
1 Galian tanah biasa 4.00 m3 60,000.00 240,000.00
2 Urugan pasir bawah pondasi 0.60 m3 160,800.00 96,480.00
3 Urugan kembali bekas galian 1.33 m3 20,000.00 26,666.67
4 Urugan tanah dipadatkan 8.00 m3 88,800.00 710,400.00
5 Pasangan bata merah 1:5 (1/2 bata) dinding 25.00 m2 107,629.00 2,690,725.00
6 Plesteran dinding camp. 1:5 25.00 m2 56,545.20 1,413,630.00
7 Acian dinding dan beton 25.00 m2 26,666.00 666,650.00
8 Pembuatan lantai kerja beton tumbuk 1:3:5 (5 cm) 4.00 m3 857,358.92 3,429,435.66
9,273,987.33