PROJECT:
LOCATION:
OWNER:
Arch:
Quotation:
      Item
        1
        2
        3
        2
        3
        4
        6
        7
        2
        3
        4
        5
6
7
1
2
3
3
4
5
1
2
3
4
5
6
SHFC Sodializad Housing
Magalang Pampanga
SHFC Sodializad Housing
Adrian Rutaquic
P2004-SHFC Social Housing Finance Corp.
                                      Description of Work
                                           SITE WORKS
                                         Excavation Works
                                          Gravel Bedding
                                Backfilling includimg Compaction
                               Sub-total for concreting Works
STEEL REINFORCEMENT WORKS (G40)(Fabrication & Installation
COLUMNS
                              Foundation - ground Level
                               Ground Level - Loft Level
                               Loft Level - Roof Framing
FOUNDATION
WALL FOOTING
SLAB ON FILL
                                     Ground Floor
                                      Septic Tank
SUSPENDED SLAB
                                     Ground Floor
                                      Septic Tank
FOOTING TIE BEAMS
SUSPENDED BEAMS
                                       Loft Level
                                      Roof Beam
                                      Septic Tank
MISCELLANEOUS
                                 Concrete Countertop
                             Sub - total Steel Reinforcement Works
                                 FORMS AND SUPPORT WORKS
COLUMNS
                                   Foundation - ground Level
                                    Ground Level - Loft Level
                                    Loft Level - Roof Framing
FOUNDATION
WALL FOOTING
SLAB ON FILL
                                          Ground Floor
                                           Septic Tank
SUSPENDED SLAB
                                         Ground Floor
                                          Septic Tank
FOOTING TIE BEAMS
SUSPENDED BEAMS
                                           Loft Level
                                          Roof Beam
                                          Septic Tank
MISCELLANEOUS
Kitchen Countertop, Ledge and Stairs
                                  Sub - total Masonry Works
ARCHITECTURAL FINISHING WORKS
FLOOR FINISHES
300mm X 300mm Ceramic Floor Floor Tiles (Design 1)
300mm X 300mm Ceramic Floor Floor Tiles (Design 2)
CEILING FINISHES
6.0mm Thick Ordinary Plywood on Std. Framing
4.5mm Thick Fiber Cement Board on Std. Framing
Ceilling Painted Finish
WALL FINISHES
Paint Finish using Latex
Ceramic Wall Tiles (300mm X 300mm)
                             Sub- total for Forms and Support Works
MASONRY WORKS
CHB - 125mm Thick (10mmᴓ rebar spa. 0.8mV % 0.6mH)
CHB - 100mm Thick (10mmᴓ rebar spa. 0.8mV % 0.6mH)
Plastering Work - Interior
Plastering Work - Exterior
                                Sub total Architectural Finishing Works
MISCELLANEOUS ARCHITECTURAL FINISHES
DOORS AND FRAMES
D1 - Main Entrance - Single Leaf Flush Door 900mmW X 2100mmH
D2 - Service Entrance - Single Leaf Flush Door 700mmW X 2100mmH
D3 - T&B Door - Single Leaf PVC Door With Louver 600mm X 2100mmH
SLIDING WINDOWS AND AWNING WINDOW
W1 - Living Area - 600mm W X 1180mm H Sliding Window on Analok Frame
W2 - Service Area - 800mm W X 1000mm H Sliding Window on Analok Frame
W3 - Comfort Room - 500mm W X 380mm H Awning Window on Analok Frame
W4 - Loft Level - 800mm W X 1000mm H Sliding Window on Analok Frame
W5 - loft Level - 1800mm W X 560mm H Sliding Window on Analok Frame
HARDWARES
Hinges - 4.5" X 3" X 3.0mm thick
Lockest - Cylindrical Type
TINSMITHRY WORKS
Roofing Panels, Bended Materials & Accessories
STEELWORKS
Roof Framing
Stairs (Steel stringer and steps)
LOFT SUSPENDED SLAB
Suspended slab using 18mm thick plywood on tubular joist
ELECTRICAL WORKS
Preliminary Cost
Mobilization and Demobilization
Workrer and Staff barracks
Temporary Warehouse
Staking and Layout
Safety Provision
Anything that you think will be required during construction
                                                                      Total Cost For Preliminary
Total Cost For ( Preliminary and Scope of Work)
Safety Provision
50 pcs hard hat
50 pcs reflective vest
2 units fire extinguiser
Minor Inquiries:
How many units can you accommodate to construct once award? - 50 units (10 blocks)
How many manpower capacity do you have which can be supplied for the construction of the project? - 250 manpower
How many manpower can you allocate per block (10 units) ? - 50 Manpower
How long can you construct 1 block (10 units)? 60 days
Preffered Payment Terms :
Downpayments : 30%
Progress Billing : Weekly per Accomplishment
Retention : 10%
                                             Total Labor
                                            Contingecies
Evat
Total
                                  Contractor
      Unit    Qty
                        Unit cost    Amount
m³             89.13           400.00      35,652.00
m³             15.37           350.00       5,379.50
m³             57.27           350.00      20,044.50
                        sub total          61,076.00
kgs            692.31           37.00      25,615.47
kgs          1,170.94           37.00      43,324.78
kgs          1,081.40           37.00      40,011.80
kgs            457.14           37.00      16,914.18
kgs            582.57           37.00      21,555.09
                                                  -
kgs           813.12            37.00      30,085.44
kgs            13.69            37.00         506.53
                                                  -
kgs                                               -
kgs            20.63            37.00         763.31
kgs                                               -
                                                  -
kgs          1,387.07           37.00      51,321.59
kgs          1,072.33           37.00      39,676.21
kgs                                               -
                                                  -
kgs            163.8            37.00       6,060.60
                        sub total         275,835.00
m2             26.65                650    17,322.50
m2             70.13                650    45,584.50
m2             64.52                650    41,938.00
m2              26.4                650    17,160.00
m2              75.4                650    49,010.00
                                    650           -
m2               7.95               650     5,167.50
m2               0.62               650       403.00
                                    650           -
m2                    650           -
m2            2.2     650     1,430.00
m2                    650           -
                      650           -
m2          51.7      650    33,605.00
m2          51.7      650    33,605.00
m2                    650           -
                      650           -
m2          17.5      650    11,375.00
                            256,600.50
m2
m2           197      850   167,450.00
m2
m2            69     1200    82,800.00
m2           146      110    16,060.00
m2                                  -
m2       1,390.00     110   152,900.00
m2             61     850    51,850.00
                            471,060.00
                                         125mm
m2        612.32      600   367,392.00   chb         612.32       13
m2        301.76      580   175,020.80   cment
m2        430.05      300   129,015.00   sand         0.125    0.025
m2        676.04      300   202,812.00                  0.1       0.4
                            874,239.80
                                         chb         301.76       13
set/s         10     4000    40,000.00   cment
set/s         10     3800    38,000.00   sand         0.125    0.025
set/s         10     2500    25,000.00                  0.1       0.4
                                    -
set/s         10     3115    31,150.00
set/s         10     3520    35,200.00
set/s         10     2200    22,000.00   plasterng
set/s         20     3520    70,400.00
set/s         10     4435    44,350.00       430.5     0.05   21.525
                                    -       21.525       12    258.3
pair/s        60      250    15,000.00
set/s         20      700    14,000.00
                                    -
lot           10    15380   153,800.00
                                                                -
          set                     10           6550      65,500.00
          set                     10           8600      86,000.00
                                                                -
          lot                     10           14590    145,900.00
                                       sub total        786,300.00
          lot                     10          15500     155,000.00
                                Materials cost         2,819,035.30
                                 Labor cost            1,329,641.89
                              Labor & mat. Cost        4,148,677.19
                                Contingecies             225,522.82
                                     Evat                338,284.24
                              Total project Cost       4,148,677.19
                lot           1           40,000.00      40,000.00
                lot           1          101,440.00     101,440.00
                lot           1            9,500.00       9,500.00
                lot           1           36,500.00      36,500.00
                lot           1           50,000.00      50,000.00
                                                        237,440.00
                                                       4,386,117.19
the project? - 250 manpower
            1,329,641.89
              225,522.82
  338,284.24
1,893,448.95
                          7960.16     15 119402.4
                         952.8312    220 209622.9
   4    0.0125   7960.16    99.502              0
0.02    0.0008   7960.16 6.368128               0
                         105.8701    700 74109.09
                                         403134.3   658.372
                          3922.88     12 47074.56
                         469.5687    220 103305.1
   4    0.0125   3922.88    49.036              0
0.02    0.0008   3922.88 3.138304               0
                          52.1743    700 36522.01
                                         186901.7   619.372
700    15067.5
220      56826
       71893.5      167