NCC LIMITED,
KIMS-MADIKERI
A-BLOCK PLANNING AS PER LOP-( FROM 15.02.2015 TO 15.05.2015)-3 MONTHS
Feb-15 Mar-15 Apr-15 May-15
Sl
No. Description of works 3rd Week 4th Week 1st Week 2nd Week 3rd Week 4th Week 1st Week 2nd Week 3rd Week 4th Week 1st Week 2nd Week 3rd Week 4th Week Remark
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Medical College
1 A-Block
Cellar-1-(A/c)-Further works
1 RCC M25 for Column up to Plinth Lvl incl. shuttering
2 Earth filling in foundation & Plinth
3 RCC M25 for Plinth Beam incl.shuttering & steel fab.
4 RCC M25 for Staircase incl. shuttering & Steel Fab
5 RCC M25 for Retaining Wall incl. shuttering & Steel Fab
6 RCC M25 for Column up to Roof Lvl incl. shuttering & steel fab.
7 RCC M25 for Roof slab & beam incl. shuttering & steel Fab.
Cellar-2-(A/b)-Further works
1 RCC M25 for Column Footing-( Balance works)
2 RCC M25 for Pedestral incl. shuttering & Steel fab.
3 RCC M25 for Column up to Plinth Lvl incl. shuttering
4 Earth filling in foundation & Plinth
5 RCC M25 for Plinth Beam incl.shuttering & steel fab.
6 RCC M25 for Staircase incl. shuttering & Steel Fab
7 RCC M25 for Retaining Wall incl. shuttering & Steel Fab
8 RCC M25 for Column up to Roof Lvl incl. shuttering & steel fab.
9 RCC M25 for Roof slab & beam incl. shuttering & steel Fab.
Sl Description of works 3rd Week 4th Week 1st Week 2nd Week 3rd Week 4th Week 1st Week 2nd Week 3rd Week 4th Week 1st Week 2nd Week 3rd Week 4th Week Remark
No.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Ground Floor-( Further works)
1 RCC M25 for Column Footing-( Balance works)
2 RCC M25 for Pedestral incl. shuttering & Steel fab.
3 RCC M25 for Column up to Plinth Lvl incl. shuttering
4 Earth filling in foundation & Plinth
5 RCC M25 for Plinth Beam incl.shuttering & steel fab.
6 RCC M25 for Staircase incl. shuttering & Steel Fab
7 RCC M25 for Retaining Wall incl. shuttering & Steel Fab
8 RCC M25 for Column up to Roof Lvl incl. shuttering & steel fab.
9 RCC M25 for Roof slab & beam incl. shuttering & steel Fab.
NCC Limited,
KIMS-Madikeri
Blockwise Tentative Physical Planning & Achivement for the Month of December-2014
Target Planned & Footing & Earth Refilling Plum Columns up to Columns up to
Sl No. Name of Blocks Achieved Earthwork PCC Pedestral up to Plinth Retaining Wall Concrete Plinth Plinth Beam Roof level
1 2 3 4 5 6 7 8 9 10 11 12
Medical College
1 A-Block
A/c Planned Plinth Beam Level
Achieved 100% 100% 45%
A/b Planned
Achieved 100% 80%
A/a-GF Planned
Achieved 100% 80%
2 B-Block Planned Columns up to Roof level
Achieved 100% 100% 100% 100% 100% NA 100% 100% 70%
3 C-Block
C/c Planned Columns up to Roof level
Achieved 100% 100% 100% 60% 50% 60% 90% 75%
C/b Planned All Columns Footing
Achieved 100% 70%
C/a-GF Planned All Columns Footing
Achieved 100% 60%
Page 3 of 8
Target Planned & Footing & Earth Refilling Plum Columns up to Columns up to
Sl No. Name of Blocks Achieved Earthwork PCC Pedestral up to Plinth Retaining Wall Concrete Plinth Plinth Beam Roof level
1 2 3 4 5 6 7 8 9 10 11 12
4 Boys Hostel
BH/B Planned Plinth beam level
Achieved 100% 100% 100%
BH/A-(GF) Planned Plinth beam level
Achieved 100% 100%
5 Girls Hostel
GH/B Planned Plinth Beam level
Achieved 100% 100% 90%
GH/A(G.F) Planned All Columns Footing
Achieved 100% 100%
6 Doctor's Quarters Planned All Columns Footing
Achieved 100% 65% 50%
7 NTS Quarters
Page 4 of 8
NCC Limited,
KIMS-Madikeri
ing & Achivement for the Month of December-2014
Remark
13
Page 5 of 8
Remark
13
Page 6 of 8
NCC Limited,
KIMS-Madikeri
Blockwise Tentative Financial Planning for the Month of December-2014
Footing & Earth Refilling Plum Columns up to Columns up to
Sl No. Name of Blocks Target for Dec-2014 Earthwork PCC Pedestral up to Plinth Retaining Wall Concrete Plinth Plinth Beam Roof level Total Planned Remark
1 2 3 4 5 6 7 8 9 10 11 12 13
In lacs In lacs In lacs In lacs In lacs In lacs In lacs In lacs In lacs
Medical College
1 A-Block
A/c Up to Plinth Level
A/b All Column footing
A/a All Column footing
2 B-Block All Columns up to Roof Lvl
3 C-Block
C/c All Columns up to Roof Lvl
C/b All Column footing
C/a All Column footing
4 Boys Hostel
BH/B Up to Plinth Level
BH/A-(GF) All Column footing
Sl No. Name of Blocks Target for Dec-2014 Earthwork PCC Footing & Earth Refilling Retaining Wall Plum Columns up to Plinth Beam Columns up to Total Planned Remark
Pedestral up to Plinth Concrete Plinth Roof level
1 2 3 4 5 6 7 8 9 10 11 12 13
5 Girls Hostel
GH/B Up to Plinth Level
GH/A(G.F) All Column footing
6 Doctor's Quarters All Column footing
7 NTS Quarters