CEF For Large Projects Instructional Guide V2.1: September 2009
CEF For Large Projects Instructional Guide V2.1: September 2009
September 2009                                                                                                                                     i
                                                                                               TABLE OF CONTENTS
                   6.3        C.3: Access, Storage, and Staging Contingencies................................. 6-3
                   6.4        C.4: Economies of Scale...................................................................... 6-4
SECTION SEVEN PART D: GENERAL CONTRACTOR’S OVERHEAD AND PROFIT..........................7-1
            7.1  D.1: General Contractor’s Home Office Overhead Costs ..................... 7-1
            7.2  D.2: General Contractor’s Insurance, Payment, and Performance
                 Bonds ................................................................................................... 7-1
            7.3  D.3: Contractor’s Profit ....................................................................... 7-1
SECTION EIGHT            PART E: COST ESCALATION ALLOWANCE ............................................................8-1
SECTION NINE             PART F: PLAN REVIEW AND CONSTRUCTION PERMIT COSTS ..........................9-1
                   9.1      F.1: Plan Review Fees ......................................................................... 9-1
                   9.2      F.2: Construction Permit Fees.............................................................. 9-1
SECTION TEN              PART G: APPLICANT’S RESERVE FOR CONSTRUCTION ...................................10-1
SECTION ELEVEN PART H: APPLICANT’S PROJECT MANAGEMENT AND DESIGN COSTS .........11-1
            11.1 H.1: Applicant’s Project Management – Design Phase........................11-1
            11.2 H.2: A&E Design Contract Costs........................................................11-1
            11.3 H.3: Project Management – Construction Phase..................................11-3
Figures
Figure 1: Development and Processing of a CEF Estimate ..................................................... 2-1
Tables
Table A.1:     CSI Divisions ....................................................................................................... 4-3
Table A.2:     ADA Compliance Allowance for Category E Facilities......................................... 4-7
Table C.2:     Constructability Factors ........................................................................................ 6-3
Table C.4:     Economies of Scale............................................................................................... 6-4
Table D.3:     General Contractor’s Profit ................................................................................... 7-2
Table E.1:     Estimated Design and Construction Times Based on Project Cost ......................... 8-3
Table G.1:     Applicant’s Reserve for Construction.................................................................. 10-1
Table H.3:     Project Management – Construction Phase.......................................................... 11-3
Appendices
Appendix A         CEF Spreadsheet V2.1
Appendix B         Examples of Completed CEF Spreadsheets
       Example 1 Category C – Roads and Bridges – Simmonds Arch Bridge
       Example 2 Category F – Utilities – River Park Elevated Water Tank
       Example 3 Category E – Buildings and Equipment – Planning Commission Office –
                 Repair vs. Replacement Analysis
Appendix C         CEF – Large Project Report
Appendix D         Hazard Mitigation Measures for Large Projects
September 2009                                                                                                                        ii
                                                                 TABLE OF CONTENTS
Appendix E   Standard Operating Procedure – CEF for Large Projects
Appendix F   Guidelines for Selecting Values CEF Parts B through H
Appendix G   Checklists – PA Group Supervisor, Project Specialist, and Part A
    G.1 – PA Group Supervisor Checklist for CEF Implementation
    G.2 – Project Specialist Checklist for CEF Implementation
    G.3 – Part A Checklist for CEF Implementation – Eligible Scope of Work
September 2009                                                               iv
                                                                                                  Introduction
1
 The Stafford Act provides for separate grant processes for small and large projects and set the minimum threshold
for large projects at $35,000 when it was passed in 1988. FEMA adjusts this amount at the beginning of each
Federal fiscal year to reflect changes in the Consumer Price Index for All Urban Consumers. For Federal Fiscal
Year 2009 (ending September 30, 2009), the large project threshold has been set at $64,200.
September 2009                                                                                                  1-1
                                                                                      Introduction
calculation. The teams using the CEF will be comprised of engineers, architects, and other
construction professionals who have managed key engineering projects or have extensive
experience in the construction industry, and who have experience in developing parametric or
conceptual estimates without the benefit of complete project documents.
      •   Part D accounts for the contractor’s home office overhead, insurance, bonds, and profit.
          These costs are typically not used for projects completed using the applicant’s labor,
          equipment, and materials (referred to as “force account” work).
      •   Part E accounts for cost escalation over the duration of the project and is based upon an
          inflation adjustment from the time the estimate is prepared until the mid-point of
          construction for the eligible scope of work.
      •   Part F includes fees for building permits, plan checks, and special reviews.
      •   Part G is the applicant’s reserve for potential change orders related to eligible work and
          differing site conditions.
      •   Part H accounts for the applicant’s cost to manage the design and construction of the
          project. These costs are not part of the statutory administrative cost allowance provided
          to the applicant to manage the overall recovery effort. The administrative allowance,
          which is authorized by the Stafford Act and is intended to defray the cost of requesting,
          obtaining, and administering Federal assistance, does not account for project management
          costs.
These factors are described in detail in subsequent sections of this guide and were developed
using guidance available from the Construction Specifications Institute (CSI) and the RSMeans
Company. The factors were verified using data from closed-out grants for large projects
nationwide. The CEF spreadsheet (in Microsoft Excel format) is used to apply the factors in
Parts B through H, to the Part A estimate. An electronic copy of the CEF spreadsheet is
available from the FEMA Web site (www.FEMA.gov).
Typically, an applicant (the owner or party responsible for repairs) utilizes a general contractor
and a number of subcontractors to complete a large construction project in a competitively bid
environment. The structure of the CEF mirrors the applicant-general contractor-subcontractor
relationship for eligible work in that:
      •   Part A costs are representative of the construction efforts required to directly and
          specifically complete the defined eligible work. Typically, Part A represents the trade or
          subcontractor(s) costs.
      •   Parts B, C, D, and E represent the general contractor or equivalent costs; they can be
          considered as components of “as-bid” costs and represent the costs of completing the
          work.
      •   Parts F, G, and H represent the applicant’s non-construction project costs, including
          preparation of design or contract documents, plan review and permit fees, cost escalation,
          and managing project design and construction.
developed, the base cost (Part A) must include only that work which is eligible under these
regulations.
PA grants must also comply with 44 CFR Part 13, which defines procedures for grant
administration by the State and provides specific guidance on allowable costs. The factors
included in the CEF represent only those non-construction costs that are allowable under Part 13.
The factors also represent costs that an applicant can reasonably expect to incur during
construction. Excessive mark-ups for possible contingencies are not allowable under the
provisions of Part 13.
The issues described below may also affect the manner in which the CEF is applied.
Hazard Mitigation Proposals: The Project Specialist may include an appropriate hazard
mitigation proposal when developing a large project estimate. To be approved, such a proposal
must comply with applicable statutory and regulatory requirements and with all FEMA policies.
If FEMA approves the proposal, the base cost (Part A) must include the cost of the hazard
mitigation measures. After approved mitigation measures have been included in the base cost,
the estimate is completed applying CEF factors as applicable. See Section 4.5 of this
Instructional Guide for additional information of FEMA’s policy on hazard mitigation and how
to incorporate hazard mitigation as a type of work into the CEF estimate.
For Improved Projects involving a replacement facility, at the same or new site, Section 406
(Stafford Act) hazard mitigation work items will not be eligible and therefore are excluded from
consideration in the CEF, and the PW.
For Alternate Projects, Section 406 hazard mitigation work items will not be eligible and
therefore are excluded from consideration in the CEF, and the PW.
Improved Projects: When performing permanent restoration work on a damaged facility, an
applicant may decide to use the opportunity to make improvements to the facility while still
restoring the facility to its pre-disaster function and capacity. For the most part, these are
projects for which the funding for the improvements cannot be separated from the costs for the
original repair work.
Improvements beyond restoring a facility to pre-disaster function and capacity are not eligible;
therefore, these costs will not be included in the estimated base cost.
The base cost will only reflect the work associated with the eligible disaster-related repair or
replacement. The CEF will be used to calculate the final estimate, and the Federal share of this
estimate will be forwarded to the State for disbursement through the progress payment system.
The funds are limited to the Federal share of the costs that would be associated with repairing or
replacing the damaged facility to its pre-disaster design, or to the actual costs of completing the
improved project, whichever is less. Any expenditure in excess of this amount are borne by the
applicant, as the work actually accomplished on the project will normally be quite different from
the work described on the PW. The State is responsible for ensuring project compliance with
Federal regulations.
Alternate Projects: An applicant may determine that the public welfare would not be best
served by restoring a damaged facility or its function. In this event, the applicant may use the
PA grant for that facility for other eligible purposes. The alternate project may only include
eligible work and costs to restore the damaged facility to its pre-disaster design.
The CEF will be used to calculate the final estimate. Ninety percent of the Federal share of the
final estimate will be forwarded to the State for disbursement through the progress payment
system. As with alternate projects that do not involve the CEF, the funds are capped at 90
percent of the approved Federal share of the estimated eligible costs associated with repairing the
damaged facility to its pre-disaster design, or 90 percent of the Federal share of actual costs of
completing the alternate project, whichever is less.
Replacement Projects (50 Percent Rule): A facility is eligible for replacement when the cost
of repairing the facility exceeds 50 percent of the replacement cost. This comparison must be
based on the following:
      •   The cost of repair is that which is necessary to repair disaster-damaged components using
          current methods and materials. The repair costs include non-emergency mold
          remediation associated with the damaged components and the codes and standards
          upgrades that apply to the repair of the damaged components. This cost does not include
          upgrades of other components triggered by codes and standards, design associated with
          upgrades, demolition of the entire facility, site work, or applicable project management
          costs, even though such costs may be eligible for PA. The cost of contents and hazard
          mitigation measures is not included in the repair cost.
      •   The replacement cost includes the costs for all work necessary to provide a new facility
          of the same size or design capacity and function as the damaged facility in accordance
          with all current applicable codes and standards. The cost does not include demolition,
          site work, applicable project management costs, cost of contents, and hazard mitigation
          measures.
Both the repair and replacement costs should be calculated for comparison using Part A of the
CEF. If the resultant ratio of repair to replacement is greater than 50 percent, the replacement of
the facility is eligible. The final estimate is equal to the total cost associated with the eligible
work, including items not used in the 50 percent analysis (e.g., eligible codes and standards
upgrades, demolition of existing facility for replacements, etc.) using CEF Parts B through H as
applicable.
Refer to the PA Guide, FEMA 322, and the PA Policy Digest, FEMA 321, for additional
information regarding the 50 Percent Rule and the eligibility of codes and standards for
restoration work.
estimating resources, (e.g., RSMeans, BNi Costboooks, Marshall & Swift, Sweet’s Unit Cost
Guide, etc.). Care should be taken in selecting the appropriate cost data reference for the work.
      •    Major infrastructure repair and construction projects, such as roads, railroads, bridges,
           and water control facilities, should be estimated using heavy construction cost data
           guidance.
      •    Building and structural work expected to exceed $1,000,000, such as that necessary for
           schools, hospitals, and municipal buildings, should be estimated using building
           construction cost data guidance.
      •    Building and structural work expected to be less than $1,000,000 should be estimated
           using facilities construction cost data guidance.
The following cost data references should be available in the Joint Field Office (JFO) for use by
the Project or Technical Specialists:
           •   ADA2 Compliance Pricing Guide                  •   Mechanical
           •   Building Construction                          •   Plumbing
           •   Concrete & Masonry                             •   Repair and Remodeling
           •   Electrical                                     •   Site Work and Landscape
           •   Facilities                                     •   Square Foot Costs
           •   Heavy Construction
If national cost data is used in Part A, city cost indices for each CSI division of work must be
applied to adjust the national unit prices to the nearest city for the declared counties. The PA
Group Supervisor or designee is responsible for identifying the zip codes included in the
declared area, researching references for the appropriate city cost indices, and tabulating them
for use by Project or Technical Specialists.
If the estimate is developed using an electronic estimating tool, the estimate can be developed
with the unit costs set for the applicable city. This automatically adjusts the unit cost data to the
specified location and the CEF City Adjustment Factor must be entered as 1.0.
Only if the previously mentioned sources are unavailable should FEMA Cost Codes, or other
commercial cost-data estimating resources, be used for unit prices in preparing Part A base costs.
Only unit costs from sources outlined in this Instructional Guide are acceptable data for
developing estimates using the CEF. Use of other unit price data is prohibited without written
authorization of the PA Group Supervisor or his/her designee.
Factors: The PA Group Supervisor or designee is responsible for checking the appropriateness
of individual factors and ranges (Parts B through H), and for application of these factors. This is
especially important with regard to force account efforts, use of contingencies, time frames for
escalation, post-disaster inflation adjustments in Part A, and the need for engineering design and
construction phase services. Guidance on generally appropriate conditions to use the factors and
values of factors to use is provided in Appendix F.
2
    Americans with Disabilities Act
September 2009                                                                                         2-4
                                          The Cost Estimating Format Development Process
The type of damage experienced will dictate the need for, and relative ranges of many of the
factors. For example, visual identification of damage may be less difficult after a flood once
floodwaters have receded than after a severe earthquake. The PA Group Supervisor may decide
that the contingency factors in Part C should therefore be higher than recommended in the CEF
for an earthquake. The PA Group Supervisor or his/her designee will be responsible for
justifying in writing any changes to the factors, if changes are warranted.
Plan Review and Construction Permit Costs: The PA Group Supervisor or designee is
responsible for obtaining documentation related to plan review and construction permit costs and
for distributing this documentation to the Project or Technical Specialists. These costs will be
determined directly from the controlling jurisdictions in the declared counties. Typical sources
include the City Building Department or the Office of the State Architect. Important
considerations are listed below.
      •   How is the plan review or construction permit cost defined?
      •   What cost item (construction cost or total project cost) serves as the basis for calculation
          of plan review and construction permit costs?
      •   What percentage(s) is applied to the base cost?
      •   Are these percentages on a sliding scale?
      •   Are these fees ever waived by the State or local jurisdiction in post-disaster situations?
procedures. The general guidelines are to allow no more than 3 to 4 days between the transfer of
funds to the grantee’s account and disbursement to the subgrantee.
Upon completion of a large project, the grantee must submit supporting documentation and an
accounting of all eligible costs incurred for the project to FEMA for a final determination of
eligible project costs. The grantee must certify that the reported costs were incurred in the
performance of eligible work and that the project was completed in accordance with FEMA
approval. The grantee may perform inspections and audits as it deems necessary to make this
certification. FEMA will review the reported costs to determine if the costs are eligible, and may
conduct inspections or audits as necessary to verify eligible costs. Upon completing this review,
FEMA will reconcile final costs for eligible work against the original estimate and prepare a
supplemental PW to adjust the approved amount upward or downward as necessary. If
additional funds are approved by FEMA, the grantee may then make an additional drawdown of
any funds remaining for that project.
Within 90 days following completion of the last large project, the grantee must submit a final
progress report that includes the final amount paid for each large project. If FEMA determines
that the grantee has drawn Federal funds for ineligible costs, then the grantee must return those
funds to FEMA.
Refer to Appendix E (Standard Operating Procedure – CEF for Large Projects) for additional
information relating to the cost reconciliation process.
A sample copy of the report has been included in Appendix C, and an electronic copy has been
included with this guide. The PA Group Supervisor should submit the report to the address
included in Appendix G, PA Group Supervisor Checklist for CEF Implementation.
   •   Hazard mitigation: measures taken to reduce or eliminate future damage from hazards
       similar to that which caused the damage, or from multiple hazards.
   •   Other work: activities that are typically undertaken outside of the typical applicant-
       general contractor-subcontractor relationship. Examples include hazardous material
       abatement, selective demolition, and force account activities.
A project can consist of one type of work, or multiple types, depending upon how the restoration
activities match the requirements of the PA Program. Under certain circumstances the estimate
may use separate types of work to accurately apply cost factors to reflect the applicant-contractor
relationships, e.g., a trade contractor acting as the general contractor thus not requiring general
contractor mark-ups on his/her own work.
The user should select the work type(s) to be analyzed and enter it into the Fact Sheet. Once the
fact sheet is completed, a CEF Spreadsheet tailored specifically for this analysis is created. Each
“Type of Work” entered on the Fact Sheet populates a column title on the Summary of
Completed Work and Summary of Uncompleted Work sheets. To change the prepared format,
the user must return to the Fact Sheet and redefine the type of work.
Work Completion: Projects being analyzed will likely have completed and uncompleted work
elements. Since several of the CEF factors are based upon unknowns that result from the level of
completion, the spreadsheet is structured to analyze completed and uncompleted work
separately. Therefore, it is recommended that the user separate completed and uncompleted
work in Part A.
Mixing completed costs with estimated costs in mid-construction can lead to inaccurate
estimates, unless the completed work is a discrete, stand-alone portion of the project without the
potential for change orders. For example, cost inaccuracies can result by using unit costs
applicable to cast-in-place concrete in bridge abutments for concrete used for deck pavement.
Therefore, to be considered completed work, a project work element must be:
   •   A specific type of work (repair, retrofit, new construction, hazard mitigation, or other) for
       which actual incurred costs documentation for eligible work can be easily obtained
   •   A discrete work activity (such as grading or laying foundations) that is complete and has
       no potential for future change orders
In some cases, an applicant may have solicited bids for the project before the CEF is prepared.
The lowest qualified bid amount obtained through a competitive bid process can be accepted for
purposes of developing an estimate, as long as the bid conforms substantially to the eligible
scope of work, the qualified bidder has been given the notice to proceed, and a cost analysis has
been conducted to evaluate the reasonableness of the bid as required in 44 CFR Part 13. The
application of the CEF to document the reasonableness of bid costs in such cases is described in
Section 4.10 of this Instructional Guide.
Preparers’ Notes: The purpose of the Scope/Prepares Notes section is to document the basis of
the CEF estimate. The CEF user should use this section to document, as a minimum:
   •   A clear, concise description of the project, including a summary of the eligible scope of
       work
      •   The status of the project at the time of the estimate, i.e., percent of design and/or
          construction complete
      •   The anticipated project delivery method, i.e., design-bid-build, force account, etc.
      •   The source of unit cost data
Care must be exercised in determining the applicability of Parts B through H if Part A is based
on actual costs for completed work.
4.1       BACKGROUND
Part A contains the “base costs” for the project. It includes costs for all eligible permanent and
non-permanent trade work required to directly complete the eligible scope of work. These costs
represent the “complete and in-place” cost components, i.e., the cost of all labor, equipment,
materials, small tools, incidentals, and hauling costs necessary to complete an item of work.
Each of these components, as they apply to permanent and non-permanent work, is discussed
below. As stated above, the preparation of a precise base cost estimate in Part A is critical to the
accuracy of the total project estimate developed with the CEF.
The Project Specialist, in partnership with State and local representatives, develops the eligible
scope of work. The Project Specialist is also responsible for developing the CEF estimate and
must ensure that Part A does not contain ineligible work. The application of the CEF is the last
step in the large project formulation process; therefore, any eligibility conflicts involving scope
of work items must be resolved before the CEF is prepared.
All construction work activities must be itemized and quantified. As lump-sum construction cost
estimates do not meet the requirement for quantitative estimates, lump sums are not acceptable
for preparing the CEF estimate. If eligible unforeseen site conditions are present or eligible
hidden damage is discovered and the scope of work must be revised, unit costs lend themselves
to this task more readily than lump-sum items.
Using this system, a project may be broken into a series of separate sub-estimates for each major
item of work. This facilitates:
      •   Application of the city cost factors by CSI division
      •   Checking the estimate
      •   Analyzing the work to determine if alternative solutions exist
      •   Use of the estimate for policy determinations
      •   Future changes in scope without requiring that the estimate be recalculated
Once the user has developed estimates for completed and uncompleted work, the user must enter
these estimates in the Summaries of Completed Work and Uncompleted Work, respectively.
The estimates are entered in the appropriate fields under Part A on each summary sheet. The
distinction between permanent and non-permanent work must be maintained when completing
the summary sheets.
Examples of completed Part As can be found in Appendix B. Permanent and non-permanent
work is discussed in more detail in Sections 4.8 and 4.9.
Refer to the PA Guide, FEMA 322, and the PA Policy Digest, FEMA 321, for additional
information relating to the 50 Percent Rule and the eligibility of codes and standards for
restoration work.
In most cases, the criteria outlined in Table 2: Repair/Replacement in the PA Guide, FEMA 322,
June 2007, are adequate for repair and replacement projects. However, particular attention
should be paid to the repair of damaged historic buildings. Such repair could trigger a
requirement to upgrade a structure to new construction standards, while at the same time
maintaining historic features. The total restoration cost, in this situation, may exceed
replacement cost, as in condition 3 found in the referenced Table 2, but the excess over the
replacement cost is not eligible.
The regulations [44 CFR 206.226(f)(3)] contain an exception to the funding limitation depicted
in the table that applies only when a facility is eligible for listing or is listed in the National
Register of Historic Places. If an applicable standard that requires a facility to be restored in a
certain manner and disallows other options, such as leaving the facility un-restored, the eligible
cost to complete the restoration may exceed the replacement cost.
The repair vs. replacement calculation is begun by completing two separate Part A base cost
estimates using the CEF (do not apply parts B through H). The user prepares one estimate for
each of the repair and replacement scenarios. The “Total Part A Base Construction Cost” from
the estimates is used in calculating the actual repair vs. replacement fraction. The two Part A
estimates can be completed using a single CEF to facilitate review of the repair vs. replacement
analysis. The resulting percentage determines whether the type of work will be repair or
replacement. Once the type of work has been selected for a project (i.e., either repair or
replacement), then the project is estimated using CEF in the standard manner (including adding
additional eligible costs in Part A and applying the appropriate B through H factors for the
project) as illustrated in Appendix B, Example 3.
Costs approved for project-specific mitigation measures under Section 406 of the Stafford Act
may not be applied to improved projects that will involve the replacement of the disaster-
damaged facility, whether on the same site or an alternate site. However, funds recommended
for mitigation measures may be approved for an improved project, which will include the work
required to repair the disaster-damaged facility and restore its function, as well as improvements.
The cost caps (15 percent or 100 percent) for Section 406 hazard mitigation measures will be
based on the total cost of damage to: 1) the damaged element, and 2) the affected building
contents.
developed using a line item estimate in Part A. For example, highway and bridge work
undertaken by State DOTs typically include separate work items for ADA compliance, such as
wheelchair ramps and utility pole setbacks. Alternatively, set factors for specific cost items may
also be used. Reference should be made to nationally accepted or locally set standards for such
factors, such as the most recent ADA Compliance Pricing Guide.
For Category E buildings that sustain structural damage, ADA compliance costs are less site-
specific but are more easily quantified, and therefore less variable. If the damaged portion of the
building does not comply with ADA, and a detailed scope of work for completing ADA
upgrades is not available to be included in Part A, an allowance for ADA compliance can be
estimated using Table A.2. The ranges provided cover the inherent differences between less
complex facilities (warehouses, factories, garages) and facilities where ADA compliance could
be more costly (historic and monumental buildings). This allowance should be applied only on
the basis of the eligible structural damage to the facility. ADA allowances cannot be applied on
the basis of damage to non-structural elements or architectural finishes. The allowances given in
Table A.2 should be applied to buildings (Category E) with eligible structural damage only.
When using Table A.2 to select the ADA compliance factor, the user should consider the need
for ADA compliance based on local requirements, then the facility’s use and function. The user
should also compare the selected factor to other, similar projects undertaken by the applicant, if
the information is available.
In all cases, the Project or Technical Specialist should ensure that the components of unit cost
data are fully understood. Each unit cost must represent a complete and in-place cost that
includes all labor, equipment, materials, small tools, incidentals, and hauling costs necessary to
complete the work. Unit costs should not include surveying and construction inspection costs.
The Project or Technical Specialist should understand cost elements that could potentially be
duplicated in Parts B through H, such as general contractor’s overhead and profit.
The unit costs in Part A should be “base costs,” that is, they should include the subcontractor’s
overhead and profit, but should not include general contractor overhead and profit. Factors for
general contractor overhead and profit are included in Part D.
   •   Cost estimating publications provide unit cost data with and without overhead and profit.
       The overhead and profit included in the total unit price is for the installing trade or
       subcontractor only and should be used for most projects.
   •   If a source other than industry standard construction cost estimating resources is used,
       such as contract or bid unit costs, costs obtained from that source should be analyzed to
       determine if general contractor overhead and profit are included in the unit cost.
   •   Overhead and profit are normally part of the unit price for an item of work within a
       contract (if the contract was let in a bid environment), or as a separate line item in a
       written quote (if obtained from the contractor in a non-bid environment). As previously
       indicated, all contractor bid costs must be analyzed for reasonableness as required by
       44 CFR Part 13.
   •   If a prime contractor and subcontractor relationship is anticipated during completion of
       the work, then the Part A costs should include the subcontractor overhead and profit and
       the Part D factor should also be included to cover general contractor overhead and profit.
   •   The prime contractor and subcontractor relationship is generally used for more complex
       facilities in which prime contractors subcontract specialized work. In all cases, the
       Federal-State-local team should verify the relationship before the Project Specialist
       prepares the CEF.
Disaster conditions may cause shortages of skilled labor, building materials, and energy sources,
resulting in fluctuations in costs. When these conditions prevail, the available unit cost data may
not be accurate. The Project or Technical Specialist should identify and document such
conditions during large project formulation and adjust unit cost data before applying the CEF.
Any changes in standard cost data must be documented in writing and approved in writing by the
PA Group Supervisor or his/her designee.
The following paragraphs describe various scenarios that may be encountered when developing
costs in Part A. All assumptions or the basis for development of Part A must be recorded in the
CEF Notes Sheet.
a) Development of an estimate when no work has been completed by the applicant:
    i. Define all work activities required to complete the work and determine the quantities and
       units associated with each work item. As stated above, lump-sum work items should be
       avoided.
    ii. If the applicant intends to use force account labor, equipment, and materials to complete
      the project, these costs should be treated as contractual work and included in Part A. As
      stated above, not all CEF factors are applicable to force account work. Home office
      overhead and profit factors represented in Part D should not be included for force account
      work.
  iii. Using the appropriate cost data source, as recommended above, determine the unit cost
       for each work item. List the item number, item description, cost code, quantity, and unit
       price on the Part A worksheet. Care should be taken to avoid combining multiple
       definable work items in a single loaded unit cost.
      •   A critical factor in developing cost estimates is the appropriateness of using
          assembled (as opposed to non-assembled) costs. Using an assembled cost for work
          activities that can be represented by a single unit of measurement is acceptable, as
          long as the source of the assembled costs is valid.
      •   For example, some cost estimating publications provide assemblies cost tables for a
          variety of construction components. These assembled cost tables have unique
          identification numbers; illustrations, descriptions, and design criteria; listing of
          system components, their quantities, and units of measure; derived assembly unit
          costs for materials and installation; and total costs. If the eligible scope of work
          deviates from the assumed condition upon which the assembly cost is based, the
          estimate must be based on unit cost data. The assembly description can be used for
          reference to ensure all components of work are included in the estimate.
      •   Assembled costs are most applicable for new or replacement type projects. On the
          other hand, repair projects are typically characterized by a number of discrete
          unrelated work activities (represented by different units of measurement); therefore,
          assembly costs should not be used and a detailed line item cost estimate should be
          prepared
  iv. After itemizing each work item required to complete the project in Part A, apply the
      appropriate city adjustment factor from the cost estimating publication to each line in Part
      A. If local average weighted unit prices (local costs derived from actual contract history)
      are used, the city cost adjustment must be entered as 1.0. Similarly, if cost estimating is
      completed with cost data settings to the applicable local area, the city cost adjustment in
      the CEF is 1.0.
  v. Enter the totals for permanent and non-permanent work in the appropriate fields at the top
     of the summary for uncompleted work.
b) Estimate based on an Architect and Engineering (A&E) report:
   If an A&E report with a construction cost estimate for uncompleted work is available check
   the reasonableness (44 CFR Part 13) of the estimate as follows:
    i. Verify that all items of work included in the estimate are eligible.
   ii. Check a minimum of six of the ten largest cost items against local average weighted unit
       prices or industry standard construction cost data, (e.g., RSMeans, BNi Costboooks,
       Marshall & Swift, Sweet’s Unit Cost Guide, etc.). Note that the largest cost items should
       consist of systems (e.g., heating, ventilation, and air conditioning systems) or subsystems
       (e.g., plumbing piping or air distribution duct) and not individual components. The
        selected cost items must represent a minimum of 25 percent of the CSI Divisions
        included in the eligible scope of work.
   iii. Check a minimum of 25 percent of the remaining cost items against local average
        weighted unit prices or industry standard construction cost data. The cost items should
        consist of systems or subsystems representing an additional 25 percent of the CSI
        Divisions included in the eligible scope of work.
   iv. If the item costs checked in the A&E construction cost estimate are within 10 percent of
       the local average weighted unit prices or industry standard construction cost data, use the
       A&E construction cost estimate in Part A.
   v. If the item costs checked in the A&E construction cost estimate are not within 10 percent
      of the local average weighted unit prices or industry standard construction cost data,
      assume the entire estimate is not comparable and develop a new Part A. Care should be
      exercised to ensure that the scope of work used to develop the new Part A contains
      eligible items only.
        •   All work items specified in the report must be listed in Part A and quantified; lump-
            sum items may not be used. Each work activity should be reviewed to determine if
            the estimate reflects costs that could be duplicated by factors in Parts B through H.
            Examples include contingencies, which could be included in the quantities that would
            be duplicated by Part C; overhead and profit that could be duplicated in Part D; and
            escalation that could be duplicated in Part E.
   vi. After completing Part A, enter totals in the appropriate fields at the top of the Summary
       for Uncompleted Work.
c) Estimate based on a bid or construction contract:
   If an appropriately procured construction contract or bid for uncompleted work is available, it
   can be used in the CEF if a cost analysis concludes that the contract cost is reasonable
   (44 CFR Part 13). The cost analysis must check the contract cost for eligibility,
   reasonableness, and applicability.
   i.   Prepare an objective line item estimate of the work to compare it with the bid. This can
        be done using the verification process explained in (b) (ii) and (b) (iii) above. If the bid
        or construction contract is reasonable and the scope of work is eligible, use that value in
        Part A.
   ii. After completing Part A, enter totals in the appropriate fields at the top of the Summary
       for Uncompleted Work.
   iii. Identify those factors in Parts B through H that might already be included in the
        construction contract bid amount. The contractor’s unit costs probably include part or all
        of the contractor’s overhead and profit reflected in Part D, allowance for contingencies
        reflected in Part C, and escalation reflected in Part E. These unit costs could even include
        permit and plan review fees (Part F), and allowances for change orders (Part G).
        Therefore, the CEF should be adjusted to reflect the inclusion of these factors in the
        contractor’s unit costs as appropriate.
d) Developing an estimate when the applicant has partially completed the work:
   Mixing actual costs with estimated costs in mid-construction can result in significant
   inaccuracies, unless the completed work is a discrete, stand-alone portion of the project.
   Complete the Part A spreadsheet as follows:
   i. Separate completed and uncompleted work.
   ii. If the applicant had an estimate prepared before the work was completed, compare the
       actual costs against that estimate and reconcile any differences. Enter the result in Part
       A, Summary for Completed Work.
  iii. If no estimate exists, prepare a CEF Part A estimate of the eligible completed work
       activity as outlined in the preceding paragraph c, and compare it against the actual costs
       and reconcile any differences. Enter the result in Part A, Summary for Completed Work.
   iv. Prepare a Part A estimate for uncompleted work as outlined in the preceding paragraphs
       a) or b). Enter the result in Part A, Summary for Uncompleted Work.
   v. Using the values that are most applicable to the eligible scope of work will minimize
      questions on the application of Parts B through H.
inspection service with expertise specific to the project scope of work. Examples include
concrete strength testing, water quality testing, and non-destructive examination of welds. These
costs typically range from 0.5 percent to 1.0 percent of the installation or trade construction cost.
The recommend value for typical projects is 0.5 percent, and toward 1.0 percent as the overall
project or specific complexities increase (e.g., a broader spread footing required on one side of a
building project because of unforeseen, unstable soil conditions at that location).
Submittals: This factor includes the contractor’s costs for preparation of shop drawings,
materials certifications, and instructions; providing samples and product data; and preparation of
construction progress schedules. The recommended value for a typical project is 5 percent.
time. The recommended values range from 15 to 20 percent to allow some differentiation
between simple and more complex projects.
Working Drawing Stage: At this stage of design, the design requirements are better defined,
concepts are determined, details are more complete, and work tasks and quantities have been
readily defined. Contractors are likely to assume a low to medium level of risk in bidding this
type of project. The recommended values range from 2 to 10 percent to allow for differentiation
depending on the level of completeness of working drawings. A project in the early stage of
working drawing (e.g., less than 60 percent complete), which would have an average level of
detail and readily identifiable quantities, should be assigned a factor at the upper end of the
range. A project in the final working drawing stage should be assigned a factor at the lower end
of the range.
The C.1 contingency is intended to represent the state of the project design development at the
time that the CEF is prepared. Only a single C.1 value representing the status of project design is
used for each work type. The Project or Technical Specialist should obtain all information
necessary to prepare the CEF for the current state of project development. As stated above, all
assumptions or the basis for selecting factors must be recorded in the CEF Notes Sheet.
      •   Environmental considerations
The applicant’s requirements and restrictions must be reasonable; that is, they must apply to the
specific services related to the eligible scope of construction. For example, specific tolerances
related to sports facility floors and seating; end user and/or environmental requirements for
hospitals and museums; and special site-specific construction requirements, or restrictions,
mandated by State or local regulatory agencies. Such requirements or restrictions could include,
for example, access restrictions during normal business hours to portions of the facility being
repaired.
If possible, project complexity issues should be addressed in Part A. If all complexity issues are
addressed in Part A, the C.2 factor should not be used. However, if certain project conditions
cannot be identified or quantified, select a suitable factor from the range of values given in Table
C.2.
Simple construction projects should be assigned a C.2 factor of 0 or 1 percent; projects with a
combination of features that increase complexity should be assigned factors at the upper end of
the appropriate range. For example, two bridges may require the same materials and equipment.
However, if unstable soil conditions exist at one of the bridges, the work at this bridge will
require more detailed sequencing and greater supervision. As stated above, all assumptions for
selecting factors must be recorded in the CEF Notes Sheet.
such as barges, cranes, or forklifts; off-site parking for workers; restricted material delivery
hours at operational facilities; and obstructions created by utilities or exposed systems.
Storage: This factor addresses the storage of construction materials and equipment on site to
support proper staging and construction activities. Examples include remote or off-site storage
of materials due to space constraints; temporary easements; and lot, sidewalk, or roadway space
rental costs.
Staging: This contingency addresses the timing and execution of the work, which could be
complicated by occupation of facilities, lack of space, and access to the facility. This factor
should be used for sites that have work access limitations because services must continue to run
in spite of the construction, such as hospitals and city halls.
The recommended values for C.3 factors range from 1 to 4 percent. The CEF user should assign
the appropriate value according to the impact each of these factors has on project cost. All
assumptions for selecting factors must be recorded in the CEF Notes Sheet.
The CEF calculates the value of C.4 based on an interpolation between percentage points.
Interpolation is based on a natural logarithmic formula derived from the values shown in Table
C.4.
The CEF calculates the value of D.3 based on an interpolation between percentage points.
Interpolation is based on a natural logarithmic formula derived from the values shown in Table
D.3.
Before further discussing the cost escalation allowance to the mid-point of uncompleted
construction, a design and/or construction timeline needs to be developed and analyzed for
eligibility, reasonableness, and applicability to the type of construction activity being
contemplated.
The applicant is responsible for submitting their design and/or construction timeline (as
appropriate) to the Project Specialist during the project formulation stage. The timeline must
include start and finish dates for both the design and/or construction phases. The timeline must
be referenced to the eligible scope of work only, and the criterion also applies to improved and
alternate projects as well. For further information, reference the Applicant Handbook, FEMA
323, Chapter 6, Handling Large Projects. This reference describes subgrantees’ large project
roles and responsibilities.
The Project Specialist will verify eligibility, reasonableness, and applicability of the design
and/or construction timeline submitted by the applicant against the appropriate local data or the
industry standard construction time data, (e.g., RSMeans, BNi Costboooks, Marshall & Swift,
Sweet’s Unit Cost Guide, etc.) prior to application of the CEF, as follows:
   i.   Check a minimum of six of the ten largest cost item work activities against the local data
        or the industry standard construction schedule data.
   ii. Check a minimum of 25 percent of the remaining cost item work activities at random
       against the local data or the industry standard construction schedule data.
   iii. If the line-item work activities checked within the applicant timeline are within 10
        percent of the local data or the industry standard data, use the applicant timeline for
        determining the mid-point of uncompleted construction.
   iv. If the line-item work activities checked in the applicant timeline are not within 10 percent
       of the local data or the industry standard cost data, assume the entire timeline is not
       comparable, and attempt to resolve discrepancies with the applicant. If discrepancies
       cannot be resolved and the design and/or construction timeline include ineligible items of
       work (as agreed by the PAC Crew Leader or PA Group Supervisor) use the Project
       Specialist developed timeline. Care should be exercised to ensure that the work activities
       used to develop the timeline contain eligible items of work only.
In the absence of an applicant-submitted design and/or construction timeline, the Project
Specialist will develop the timeline considering the following elements described in items 1
through 3. The number of months in the escalated cost formula is referenced to the mid-point of
uncompleted construction, based on the durations necessary to complete the following timelines,
as applicable:
1. Preparation of design and bid documents: The duration for design can be estimated using
   data provided by the applicant for completion of similar projects (local data). If this
   information is not available, the design time will have to be estimated. Use the appropriate
   industry standard construction cost estimating resources (e.g., RSMeans, BNi Costboooks,
   Marshall & Swift, Sweet’s Unit Cost Guide, etc.), according to the type of infrastructure
   being analyzed for estimating design times.
   •   For example, RSMeans’ Facilities Cost Data recommends estimating the design time for
       different building types at 25–40 percent of the construction duration (see “Construction
       Time Requirements,” R01-020). For this example, the lower bound should be used for
       typical flood and hurricane wind disasters where the damage necessitates less complex
       design; the upper bound would be applicable to major seismic and hurricane disasters
       where greater damage necessitates more complex analysis and design.
   Repair and replacement activities that are based on a facilities “As-Built” drawing will
   typically not require a design duration similar to that of a new construction project.
   •   For this example, the design effort may be limited to updating applicable permits,
       assembling General Condition’s contract documents, assembling applicable construction
       standards and specifications, tabulating work activity descriptions and quantities with
       their itemized unit prices, and deriving an engineer’s estimate for the eligible scope of
       work prior to bid solicitation.
   In all cases, the Project Specialist should ensure that the components of the design effort are
   fully understood, and are reasonable and applicable to the type of construction activity being
   contemplated for the eligible scope of work.
2. Solicitation of bids, review of bids, and award of contract: The duration for bidding and
   award can be estimated using data provided by the applicant for completion of similar
   projects (local data). If this information is not available, the estimated bidding and award
   time will have to be estimated. A period of 2 to 3 months for bidding and award duration is
   typical. Extremely large projects (over $5 million) may need additional time for the bidding
   and award process.
3. Construction start and completion dates: The duration for construction can be estimated
   by one of two methods.
   •   For the first method, the Project Specialist may use information provided by the applicant
       for completion of similar projects (local data).
   •   For the second method, the Project Specialist should prepare an outline of the major
       construction tasks, and determine the duration and linkages (critical paths and
       dependencies) associated with each of these tasks to arrive at a total construction time.
   The construction start date is determined from the date that the applicant gives notice to
   proceed to the contractor.
   The construction completion date occurs when the owner accepts the project and agrees to
   pay any outstanding retainage due the contractor (normally after project punch-list work has
   been completed and accepted).
   Use the appropriate cost data book according to the type of infrastructure being analyzed and
   reference the “Construction Time Requirements” section to determine the total eligible
   construction value for eligible work only.
It is important that the construction timeline reflect only eligible items of work. For example,
owner activities, such as maintenance, capital improvement planning efforts, ineligible facility
improvements, and ineligible code upgrades, are not considered part of the eligible scope of
work and should be excluded from the construction timeline.
For improved projects involving a replacement facility, at the same or new site, Section 406
hazard mitigation work items are not eligible and therefore are excluded from the construction
timeline. For alternate projects, Section 406 hazard mitigation work items are not eligible and
therefore are excluded from the construction timeline. When evaluating improved or alternate
projects, the construction duration should reflect the eligible items of work only.
If detailed information is not sufficient to develop a reasonable project schedule, design and
construction times may be estimated using the expenditure or “burn” rates in table E.1.
        Table E.1: Estimated Design and Construction Times Based on Project Cost
                                              Monthly
                      Design and                              Ramp-Up and
                                             Burn Rate
                    Construction Fees                        Close-Out Time
                                             Assumption
                   Design
                   Fee < $200,000                 $75,000        2 Months
                   Fee > $200,000               $115,000         3 Months
                   Construction Estimate
                   < $2 million                 $200,000         3 Months
                   $2 to $10 million            $400,000         4 Months
                   $10 to $20 million           $750,000         5 Months
                   > $20 million               $1,000,000        6 Months
Time estimate calculations resulting in fractional months should be rounded to the next higher
whole month.
Once the eligibility, reasonableness, and applicability of the design and/or construction timeline
(whether applicant or Project Specialist developed) to the construction activity being
contemplated is confirmed, the cost escalation allowance to the mid-point of uncompleted
construction can be computed as follows:
The escalation factor is based on a 2-year average of either the Building Cost Index (BCI) or the
Construction Cost Index (CCI) according to the ENR (Engineering News Record). Definitions
for the BCI and CCI can be found in this publication. The appropriate index should be chosen
September 2009                                                                                    8-3
                                                            Part E: Cost Escalation Allowance
according to the nature of the project. The 2-year average of the appropriate index should be
used to calculate an average, monthly cost escalation percentage. The PA Group Supervisor or
designee is responsible for calculating this percentage at the beginning of a disaster. BCI or CCI
information can be obtained from the ENR Web site located at
http://www.enr.com/cost/cost2.asp (access to historical cost indices data may be limited to ENR
subscribers). The escalation factor should be calculated annually and distributed to the Project
Specialists for application within the CEF for disasters of longer duration.
   •   For example, a disaster is declared in August 2009. For large building projects, the PA
       Group Supervisor references the BCI for August 2007 (4512) and July 2009 (4762).
   •   The index has risen 250 points, meaning that the 2-year escalation can be calculated as
       (250/4512) x 100 = 5.54 percent.
   •   For CEF purposes, the escalation factor used is a linear interpolation rather than a
       compound rate.
   •   The average monthly value can be calculated by dividing the 2-year escalation by 24 (the
       number of months accounted for in the 2-year average).
   •   This equates to a rate of 0.231 percent per month.
To apply the Part E factor, the monthly escalation rate and the number of months to the midpoint
of uncompleted construction should be entered. Example 1 in Appendix B shows the monthly
escalation factor being applied to a project where the work is uncompleted. In the example, the
time for completing the outstanding eligible scope of work was calculated. This value, in
months, was then multiplied by the monthly escalation rate and divided by two to escalate to the
midpoint of construction. The factor was then applied to each work type for the sum of Parts A
through D. All assumptions for selecting the escalation factor must be recorded in the CEF
Notes Sheet.
If the Part A estimate is based on an A&E report or validated contract price, escalation is
typically included. The CEF user should verify that escalation is or is not included in the unit
cost data before adding it a second time.
The CEF calculates the value of G.1 based on an interpolation between percentage points.
Interpolation is based on a natural logarithmic formula derived from the values shown in Table
G.1.
Curve A applies to projects with above-average complexity and non-standard design. Examples
include:
   •   Airports with extensive terminal facilities
   •   Water, wastewater, and industrial waste treatment plants
   •   Hospitals, schools, and office buildings
   •   Power plants
   •   Large dams and complicated small dams
   •   Highway and railway tunnels
   •   Pumping stations
   •   Incinerators
   •   Complicated waterfront and marine terminal facilities
Curve B applies to projects of average complexity. Examples include:
   •   Industrial buildings, warehouses, garages, hangars, and comparable structures
   •   Bridges and other structures of conventional design
   •   Simple waterfront facilities
   •   Roads and streets
   •   Conventional levees, floodwalls, and retaining walls
   •   Small dams
   •   Storm sewers and drains
   •   Sanitary sewers
   •   Water distribution lines
   •   Irrigation works, except pumping plants
   •   Airports, except as classified for Curve A
The user must select the appropriate project complexity curve and check the box for that curve
on the spreadsheet. The spreadsheet automatically calculates the percentage to be applied. If a
box is not checked, the factor is set to 0.
In addition to the basic services described above, the following special services may be required
and are not usually included in the fee for basic engineering services. These services should be
specifically described and justified in Part A, and the cost estimated, before the services are
included in the CEF. Examples include:
   •   Engineering surveys
   •   Soil investigations
   •   Resident engineer services
   •   Feasibility studies
When the nature of work requires only basic construction inspection services, a fee that does not
exceed 3 percent of construction cost should be used to cover the following items:
   •   Review of bids
   •   Work site inspection visits
   •   Checking and approval of material samples
   •   Review of shop drawings and change orders
   •   Review contractors request for payment
   •   Acting as the applicant’s representative
The user must enter the percentage for basic construction services. If the box for this factor is
not checked, the factor will be set to 0.
Part H.2 is not applicable in those situations for which design, construction inspection, or other
basic services are not required. All assumptions for selecting factors should be recorded in the
CEF Notes Sheet.
To apply the H.3 factor, select the box under each work type to which the factor is to be applied.
The values will be automatically calculated. If a box is not checked, the factor will be set to 0.
All assumptions or the basis for selecting factors must be recorded in the CEF Notes Sheet.
The CEF calculates the value of H.3 based on an interpolation between percentage points.
Interpolation is based on a natural logarithmic formula derived from the values shown in Table
H.3.
Date of Estimate:
FEMA Region:
Preparer(s):
Applicant Name:
Project Title:
Damaged Facility:
Declaration Number:
Project Number:
PA ID No.:
Date of Inspection:
Event Date(s)
Work Category:
Type of Work:
(Enter New, Repair, etc.)
Preparer's Notes:
Part A Total $ - $ - $ - $ - $ - $ -
Part B Total $ - $ - $ - $ - $ - $ -
                                                  Guide
C.3 Access, Storage & Staging                  Low to High                                       Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%
     Storage Contingencies                       0%      4.0%
     Staging Contingencies                       0%      4.0%
                                                                   $       -       $             -       $            -       $   -       $            -       $           -
$ - $ - $ - $ - $ - $ -
Part C Total $ - $ - $ - $ - $ - $ -
New Construction
    Repair/Retrofit
                                                         $           -       $             -       $    -       $   -       $            -       $           -
Part D Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part H Total $ - $ - $ - $ - $ - $ -
Part A Total $ - $ - $ - $ - $ - $ -
Part B Total $ - $ - $ - $ - $ - $ -
                                                  Range
C.3 Access, Storage & Staging
                                               Low to High                                        Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%
     Storage Contingencies                       0%      4.0%
     Staging Contingencies                       0%      4.0%
                                                                   $       -       $              -       $            -       $   -       $            -       $           -
$ - $ - $ - $ - $ - $ -
Part C Total $ - $ - $ - $ - $ - $ -
    New Construction
    Repair/Retrofit
                                                         $           -       $              -       $   -       $   -       $            -       $           -
Part D Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part H Total $ - $ - $ - $ - $ - $ -
                                                          Summary
                                                                   -
                                                                                  Completed   Uncompleted          Total
PART A   "Base Costs" for Construction Work In Trades                         $           -   $          -    $            -
         A.1 Permanent Work                                                   $           -   $          -    $            -
         A.2 Non-Permanent Job Specific Work (CEF Part A)                     $           -   $          -    $            -
This example illustrates the use of unit prices from industry standard construction cost estimating
resources for uncompleted work in the preparation of the CEF.
Project Background
The estimate was developed for the replacements of the Simmonds Arch Bridge located near Winchester,
VA. The bridge was destroyed by heavy thunderstorms resulting in a declared flood disaster. The
applicant is River College, a public university that owns and maintains the bridge. Public universities are
eligible applicants and the bridge is an eligible facility. The facility includes the bridge, four wing-walls,
and about 25 feet of roadway on each end of the bridge. Observations by the project formulation team at
the time of inspection concluded that the bridge was approximately 80 percent destroyed. The guardrails
and bridge railing were not salvageable. Because the bridge was more than 50 percent damaged, the
bridge is eligible for replacement based on the original function and capacity. The estimate was
developed using industry standard building cost data and the associated electronic cost data format.
The Simmonds Arch Bridge is located approximately 150 feet from the Lundberg Dam on Spout Run
Creek. The bridge was approximately 15 years old and functional at the time of the declared disaster.
The earth-covered reinforced concrete arch was 24 feet long (across the stream) and 26 feet wide (along
the stream line). The bridge included two lanes of traffic and a paved walkway. The waterway opening
was 24 feet at the base, 3 feet high at the sides, and 5 feet high at the center. Each abutment, including
the upstream and downstream wing-walls, was supported on a continuous strip footing 5 feet wide and 2
feet thick. The approach roadway on each side of the bridge consisted of 4 inches of asphalt concrete
pavement over a six-inch base course. Bridge postings included a speed limit of 15 miles per hour and a
weight limit of 15 tons. Traffic volume on the bridge was 50 vehicles per day.
Removal of debris resulting from the bridge failure was accomplished under a pre-existing facilities
maintenance contract with a local contractor. A separate PW was prepared for removing debris from the
stream.
Preparer's Notes:
Floodwaters during a declared strom event destroyed the Simmonds Arch Bridge across Spout Run Creek. The
bridge consisited of a roadway and backfill over a reinforced concrete arch.
The eligible scope of work constructing a new bridge having the same function and capacity as the destroyed
bridge. Simmonds Arch Bridge was 26 feet wide and 24 feet long with reinforced concrete abutments and wing-
walls at each end. The project damage description and scope of work is detailed in the Project Worksheet.
The replacement bridge will be completed using a design-bid-build process. Engineering drawings will be based
on the original design and are about 50 percent complete.
Estimate developed using RSMeans Building Cost Data and CostWorks. Cost data was updated to 2nd quarter
2009.
B.2 - General conditions costs have been included for site supervsion and coordination.
Part C Notes:       C.1 - Estimate includes a contingency of 5% for design uncertainty, slightly below the
                          average recommended value for the working drawing stage. Although drawings are
                          only 50% complete, design is based on available original design, which reduces
                          uncertainty. However, there are uncertainties in the cost because of a lack of
                          design data for shoring and dewatering requirements during placement of the
                          concrete arch culvert and construction of the abutment and wing-walls.
                    C.2 - No constructability issues are expected for the new construction. Therefore, no
                          costs for constructability are included in the estimate.
                    C.3 - Estimate includes a cost of 1%, the lowest recommended value, for site access.
                          The site is close to Winchester, VA, with good access to labor and materials. Traffic
                          delays and limited access to the project site due to loss of the bridge are expected
                          to have an impact on project cost.
                          Estimate includes a cost of 1% each, the lowest recommended value for storage
                          and staging. The project boundaries are confined to the road right-of-way and one
                          side of Spout Run Creek. Those limitations are expected to have a minor impact on
                          costs as a result of having to handle some materials multiple times from delivery to
                          installation.
                    C.4 - Based on the size of the project, no economies of scale are anticipated.
          Compaction, 2 passes, 6" lifts, towed vibrating roller                  312323236200   75.00    E.C.Y $             0.82   1.0000     $               61.50
          Fine grading, finish grading, small area, to be paved with
                                                                                  312216100012   220.00   S.Y.    $           3.24   1.0000     $           712.86
          grader
          Base course drainage layers, aggregate base course for
          roadways and large paved areas, crushed stone base,                     321123230302   220.00   S.Y.    $          11.05   1.0000     $          2,430.97
          compacted, crushed 1-1/2" stone base, to 6" deep
          Plant-mix asphalt paving, for highways and large paved areas,
                                                                                  321216130480   220.00   S.Y.    $          17.05   1.0000     $          3,750.96
          wearing course, 4" thick
          Sidewalks, driveways, and patios, side walks, asphaltic
                                                                                  320610100100   15.00    S.Y.    $          13.70   1.0000     $           205.50
          concrete, 2-1/2" thick, excludes base
          Painted pavement markings, acrylic waterborne, white or
                                                                                  321723130200   225.00   L.F.    $           0.43   1.0000     $               96.74
          yellow, 6" wide
          Vehicle guide rails, corrugated steel, galvanized steel posts,
                                                                                  347113260012   80.00    L.F.    $          33.00   1.0000     $          2,639.98
          steel posts 6'-3" O.C., 6" x 8" posts
          Vehicle guide rails, corrugated steel, galvanized steel posts,
                                                                                  347113260300    4.00     Ea.    $         231.00   1.0000     $           924.01
          install wrap around end section
          Rip-rap and rock lining, random, broken stone, 50 lb. average,
                                                                                  313713100300   10.00    Ton     $          41.00   1.0000     $           410.00
          dumped
Part A Total $ - $ - $ - $ - $ - $ -
Part B Total $ - $ - $ - $ - $ - $ -
                                                  Guide
C.3 Access, Storage & Staging                  Low to High                                             Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%
     Storage Contingencies                       0%      4.0%
     Staging Contingencies                       0%      4.0%
                                                                   $                 -   $             -       $            -       $   -       $       -       $           -
$ - $ - $ - $ - $ - $ -
Part C Total $ - $ - $ - $ - $ - $ -
New Construction
    Repair/Retrofit
                                                         $                 -   $              -       $   -       $   -       $       -       $           -
Part D Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part H Total $ - $ - $ - $ - $ - $ -
                                                  Range
C.3 Access, Storage & Staging                  Low to High                                              Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%            1.0%
     Storage Contingencies                       0%      4.0%            1.0%
     Staging Contingencies                       0%      4.0%            1.0%
                                                                   $            2,852    $              -       $            -       $   -       $       -       $       2,852
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
$ 18,906 $ - $ - $ - $ - $ 18,906
                                                          Summary
                                         River College - Simmonds Arch Bridge
                                                                                  Completed   Uncompleted        Total
PART A   "Base Costs" for Construction Work In Trades                         $           -   $     84,315   $       84,315
         A.1 Permanent Work                                                   $           -   $     66,685   $       66,685
         A.2 Non-Permanent Job Specific Work (CEF Part A)                     $           -   $     17,630   $       17,630
Complete Project Total for Completed and Uncompleted Work $ - $ 164,421 $ 164,421
This example illustrates the use of unit prices from industry standard construction cost estimating
resources for uncompleted work in the preparation of the CEF.
Project Background
The estimate was developed for the replacement of a 100,000-gallon water storage tank located near
Mobile, AL. The water tank collapsed as a result of a tornado that caused area-wide damage resulting in
a disaster declaration. The elevated water tank was owned by the Lower Alabama Water Authority. The
public authority is an eligible applicant and the water tank is an eligible facility. The tank shell was
severely damaged by the collapse, and falling debris damaged pumps, the emergency generator, and
foundations, requiring that they be replaced.
Removal of debris is being accomplished by Authority employees as Category A – Debris Removal. That
work is included on a separate PW.
Preparer's Notes:
A tornado during a declared event destroyed the River Park elevated water tank.
The eligible scope of work includes replacement of a 100,000-gallon elevated water tank, an emergency
generator, supply pump, and associated piping. Piping consists of a network of short sections located above
grade. The falling tank pulled anchor bolts from the foundations. The new tank manufacturer requires new
foundations as a condition of validating the warrenty. Facility damage description and scope of work is detailed
in the PW.
Rubble is being removed by Lower Alabama Water Authority staff. Costs associated with that work are being
included is a separate Catagory B PW.
The replacement water tank will be completed using a design-bid-build process. Engineering drawings will be
based on the origninal design and are about 25 percent complete.
Estimate developed using RSMeans Building Cost Data and CostWorks. Cost data updated to 1st quarter 2009.
B.2 - General conditions costs have been included for site supervsion and coordination.
Part C Notes:       C.1 - Estimate includes a contingency of 10% for design uncertainty, the low range of
                          recommended values during the preliminary design phase. Drawings are only 25%
                          complete resulting in uncertainties about foundation details and water tank erection
                          requirements.
                    C.2 - No constructability issues are expected for the new construction. Therefore no
                          costs for constructability are included in the estimate.
                    C.3 - Estimate includes a cost of 2%, the average recommended value, for site access.
                          The site is close to Mobile, AL, with good access to labor and materials. Traffic
                          delays and rough access into the project site, particularly relative to delivery of the
                          elevated tank and supporting structure, is expected to have an impact on project
                          cost.
                          Estimate includes a cost of 2% each, the average recommende value, for storage
                          and staging. The project site is expected to be too congested to store all materials
                          until after the elevated tank is erected, requiring some materials to be stored off site
                          and only be staged as needed. Those limitations are expected to have an impact on
                          costs as a result of having to handle some materials multiple times from delivery to
                          installation.
                    C.4 - Based on the size of the project, no economies of scale are anticipated.
Part D Notes:       D.1 - The project is expected to employ a General Contractor. Therefore, GC home office
                          overhead is included in the estimate.
                    D.2 - The project is expected to employ a General Contractor. Therefore, GC costs for
                          project insurance on bonds is included in the estimate.
          Grounding rod, copper clad, 10' long, 1/2" diameter                260526800080          2      Ea.     $          86.01   1.0000     $           172.01
          Rigid galvanized steel conduit, 4" diameter, to 15' high, incl
                                                                             260533100680         400     L.F.    $          36.00   1.0000     $         14,399.20
          couplings only
          Wire, copper, stranded, 600 volt, 3/0, type XHHW, in raceway       260519903200          12    C.L.F.   $         815.02   1.0000     $          9,780.28
                                                                                                                  $            -                $               -
                                                                                                        Uncompleted - Permanent Total $                 551,955.05
Add Row   Uncompleted Non-Permanent Items
                                                                                                                  $            -                $               -
                                                                                                                  $            -                $               -
                                                                                                                  $            -                $               -
                                                                                                                  $            -                $               -
                                                                                                   Uncompleted - Non-Permanent Total $                          -
Part A Total $ - $ - $ - $ - $ - $ -
Part B Total $ - $ - $ - $ - $ - $ -
                                                  Guide
C.3 Access, Storage & Staging                  Low to High                                     Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%
     Storage Contingencies                       0%      4.0%
     Staging Contingencies                       0%      4.0%
                                                                   $         -   $             -       $            -       $   -       $       -       $           -
$ - $ - $ - $ - $ - $ -
Part C Total $ - $ - $ - $ - $ - $ -
New Construction
    Repair/Retrofit
                                                          $           -    $             -       $       -       $   -       $       -       $           -
Part D Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part H Total $ - $ - $ - $ - $ - $ -
                                                  Range
C.3 Access, Storage & Staging                  Low to High                                             Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%          2.0%
     Storage Contingencies                       0%      4.0%          2.0%
     Staging Contingencies                       0%      4.0%          2.0%
                                                                   $           35,095   $              -       $            -       $   -       $       -       $      35,095
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
$ 98,867 $ - $ - $ - $ - $ 98,867
                                                          Summary
                    Lower Alabama Water Authority - River Park Elevated Water Tank
                                                                                  Completed   Uncompleted         Total
PART A   "Base Costs" for Construction Work In Trades                         $           -   $    511,955    $     511,955
         A.1 Permanent Work                                                   $           -   $    511,955    $     511,955
         A.2 Non-Permanent Job Specific Work (CEF Part A)                     $           -   $         -     $           -
Complete Project Total for Completed and Uncompleted Work $ - $ 1,020,047 $ 1,020,047
This example illustrates the use of unit prices from industry standard construction cost estimating
resources for conducting a repair vs. replacement analysis and completing the eligible work estimate.
Project Background
Severe flooding in Galveston, TX, caused by a subtropical storm resulted in a Presidential disaster
declaration. The flooding heavily damaged the offices of the Coastal Texas Planning Commission. The
Coastal Texas Planning Commission is an eligible applicant, and the Commission-owned office building
is an eligible facility.
The facility consists of a 4,100-square-foot, one-story, pile-supported office building.
Preparer's Notes:
Heavy rain from a subtropical storm caused extensive flooding in the Galveston, Texas area. The storm caused
flooding received a disaster declaration.
The main office building of the Coastal Texas Planning Commision received extensive exterior and interior
damage as a result of the flooding. The main office building is a one-story, timber pile supported, wood frame
structure encompassing approximately 4,100 SF.
Based on the extent of the building damage, a repair vs. replacement analysis was performed. As shown in this
CEF, the estimated Part A repair cost is $306,743, and the estimated Part A replacement cost is $491,268. The
repair/replacement ratio is 62.4% which is greater than 50% making replacement the eligible scope of work.
The repair estimate is based on RSMeans Buidling Construction and Assembly unit cost data, and the
replacement estimate is based on RSMeans Square Foot and Assembly unit cost data. Both estimates are
based on 2nd quarter 2009 data adjusted to Galveston Texas.
An architect has been retained but design work is just begining. The project is expected to use the design-bid-
build delivery method.
Applicant intends to award a single contract for demolition of the damaged building and construction of new building. Eligible d
Damage description and eligible work for the repalcement building is detailed on the Project Worksheet.
                     A.2 -
 Part B Notes:       B.1 - Estimate includes a cost of 5%, the average recommended value, for safety and
                           security. Demoliton work will require special safety and security barriers. Other work
                           will require typcial construction safety measures, and measures to secure
                           equipment and materials during non-working hours.
                           Estimate includes a cost of 0.5%, the average recommended value, for temporary
                           services and utilties. Contractor willl be required to provide all site services including
                           temproary power, communications, potable water, and sanitation.
                           Estimate includes a cost of 0.5%, the average recommended value, for qualtiy
                           control. Field testing and inspection is anticipated for pile installation, concrete, and
                           compacted fill.
                           Estimate includes a cost of 5%, the recommended value, for submittals. Project
                           speficiations are expected to require submittals of shop drawings, samples of
                           maerials, and manufacturer certifications that materials meet specification
                           requirements.
B.2 - General conditions costs have been included for site supervision and coordination.
 Part C Notes:       C.1 - Estimate includes a contingency of 12% for design uncertainty, slighlty below the
                           average recommended value during the preliminary design stage. An A&E has
                           been selected but design has not started. Uncertainties include potential presence
                           of hazardous materials, such as asbestos in the existing buiding being demolished,
                           and type and capacity of piles for the foundations.
                     C.2 - No constructability issues are expected for the new construction. Therefore no
                           costs for constructability are included in the estimate.
                     C.3 - Estimate includes a cost of 2%, the average recommended value, for site access.
                           The site is close to Galveston, TX, with good access to labor and materials. Site
                           access for new construction will be impacted by demolition work during the initial
                           stages of construction.
                           Estimate includes a cost of 2% each, the average recommended value for storage
                           and staging. The site is relatively small requiring off-site storage of most
                           construction materials. Those limitations are expected to have an impact on costs
                           as a result of having to handle some materials multiple times from delivery to
                           installation.
                     C.4 - Based on the size of the project, no economies of scale are anticipated.
 Part D Notes:       D.1 - The project is expected to employ a General Contractor. Therefore, GC home office
                           overhead is included in the estimate.
                     D.2 - The project is expected to employ a General Contractor. Therefore, GC costs for
                           project insurance on bonds is included in the estimate.
          Polymer-based exterior insulation and finish system, v-groove         072401000370        200.00    L.F.
                                                                                                                        $0.67          1.0000     $           134.20
          shape in panel face
          Vapor Retarders, building paper, aluminum and kraft                   072601000020         22.00     Sq.
                                                                                                                       $14.45          1.0000     $           317.89
          laminated, foil 1 side
          APP modified bituminous membrane, base sheet, #15 glass               075505000040         41.00     Sq.
                                                                                                                       $30.00          1.0000     $          1,229.98
          fiber felt, fully mopped to deck
          SBS modified bituminous membrane, granule surface cap                 075505001100       4,096.00   S.F.
                                                                                                                        $2.16          1.0000     $          8,848.59
          sheet, polyester reinforced, 160 mils, mopped
          Sheet metal flashing, aluminum, flexible, mill finish, .050" thick,   076506000300        496.00    S.F.
                                                                                                                        $4.96          1.0000     $          2,460.36
          including up to 4 bends
          Doors, commercial, steel, flush, full panel, hollow core, hollow      081102000640          2.00     Ea.
                                                                                                                       $410.00         1.0000     $           820.00
          metal, 20 ga., 3'-0" x 7'-0" x 1-3/4" thick
       Frames, steel, knock down, hollow metal, single, 16 ga., up to      081108200100         20.00     Ea.
                                                                                                                  $164.00         1.0000     $          3,280.00
       5-3/4" deep, 7'-0" h x 3'-0" w
       Doors, wood, architectural, flush, interior, hollow core, 7 ply,    082109000180         18.00     Ea.
                                                                                                                  $139.01         1.0000     $          2,502.13
       birch face, 3'-0" x 6'-8" x 1-3/8" thick
       Storefront Systems, aluminum frame, monumental grade, clear         084101400700        189.00    S.F.
       3/8" plate glass, 3' x 7' door with hardware, 400 SF max wall,                                             $45.50          1.0000     $          8,599.29
       wall height to 12' high
       Door hardware, school, single, interior, regular use, excl. lever   087101502500         20.00 Door
                                                                                                                  $357.50         1.0000     $          7,150.00
       Stucco, 3 coats, float finish, with mesh, on wood frame, 1"      092202000015           240.00    S.Y.
                                                                                                                  $34.50          1.0000     $          8,278.99
       thick
       Expansion joint, 3/4" grounds, limited expansion, 1 piece, galv. 092057001800             8.00 C.L.F.
                                                                                                                  $210.00         1.0000     $          1,680.00
       Partition wall, interior, standard, taped both sides, installed on 092601003800        4,330.00   S.F.
       & incl. 25 ga, NLB metal studs, 3 5/8" wide, 16" O.C., 8' to 12'                                            $3.11          1.0000     $         13,468.12
       high, 5/8" gypsum drywall
       Ceramic tile, sanitary cove base, mud set, 6" x 4-1/4" h           093101001200          108.00   L.F.      $8.90          1.0000     $           961.22
       Paints & Coatings, walls & ceilings, interior, concrete, drywall 099109201200          6,507.00   S.F.
       or plaster, oil base, 3 coats, smooth finish, brushwork                                                     $0.67          1.0000     $          4,359.69
       Paints & Coatings, int. latex, doors, flush, both sides, roll &     099103100110         20.00     Ea.
                                                                                                                  $28.00          1.0000     $           559.92
       brush, primer, incl. frame & trim
       Ceramic tile, walls, interior, thin set, 4-1/4" x 4-1/4"            093101005400       1,467.00   S.F.      $4.81          1.0000     $          7,055.24
       Ceramic tile, exterior walls, frostproof, crystalline glazed, mud   093101006700          14.00   S.F.
                                                                                                                   $9.60          1.0000     $           134.41
       set, scored, 4-1/4" x 4-1/4"
       Suspended Acoustic Ceiling Tiles, fiberglass boards, film           095107000400        843.00    S.F.
                                                                                                                   $2.47          1.0000     $          2,082.17
       faced, 2' x 2' or 2' x 4' x 3/4" thick
       Cove base, rubber or vinyl, standard colors, 4" h, .080" thick      096512001150        745.00    L.F.
                                                                                                                   $1.82          1.0000     $          1,355.97
       Resilient Flooring, vinyl composition tile, solid, 12" x 12" x      096581007300       1,472.00   S.F.
                                                                                                                   $2.88          1.0000     $          4,239.30
       3/32"
       Carpet, commercial grades, direct cement, nylon, plush, 60          096808003340         34.00    S.Y.
                                                                                                                  $72.50          1.0000     $          2,465.04
       oz., heavy traffic
       Paints & Coatings, int. latex, doors, flush, both sides, roll &     099103100120         20.00     Ea.
                                                                                                                  $29.00          1.0000     $           579.91
       brush, finish coat, incl. frame & trim
       Entrance screens, toilet, floor mounted, plastic laminate on        101651004300          2.00     Ea.
                                                                                                                  $579.99         1.0000     $          1,159.98
       particle board, 58" h x 48" w
       Shower doors, tempered glass door, economy, 24" w,                   101851004200         1.00      Ea.
                                                                                                                   $245.98         1.0000     $           245.98
       excludes plumbing
       Lockers, steel, baked enamel, single tier box, 12" x 15" x 72"       105055000110         3.00      Ea.
                                                                                                                   $260.98         1.0000     $           782.94
       Lavatory, wall hung, porcelain enamel on cast iron, white,           154184504040         6.00      Ea.
                                                                                                                   $510.02         1.0000     $          3,060.13
       single bowl, 16" x 14", includes trim
       Carriers/supports, urinal, wall-mounted, plate type system           154102006300        10.00      Ea.     $300.01         1.0000     $          3,000.10
       Faucets/fittings, lavatory faucet, center set with porcelain cross   154103002220         3.00      Ea.
                                                                                                                   $189.00         1.0000     $           567.01
       handles, polished chrome, with pop-up drain
       Faucets/fittings, flush valves, with vacuum breaker, water           154103000860         3.00      Ea.
                                                                                                                   $182.01         1.0000     $           546.04
       closet, exposed rear spud
       Faucets/fittings, flush valve, urinal, concealed stall               154103000960         1.00      Ea.     $190.00         1.0000     $           190.00
       Faucets/fittings, flush valve, automatic flush sensor and            154103000972         1.00      Ea.
                                                                                                                   $465.00         1.0000     $           465.00
       operator for urinals or waterclosets
       Faucets/fittings, shower thermostatic mixing valve, concealed        154103004200         1.00      Ea.
                                                                                                                   $374.99         1.0000     $           374.99
       Shower, head, water economizer                                       154185005500         1.00      Ea.     $67.50          1.0000     $               67.50
       Drain, floor, medium duty, cast iron, deep flange, 7" diameter       151503002040            1      Ea.
                                                                                                                   $204.99         1.0000     $           204.99
       top, 2" and 3" pipe size
       Water heater, residential, electric, glass lined tank, double        154802001180             1     Ea.
                                                                                                                  $1,499.97        1.0000     $          1,499.97
       element, 5 year, 120 gallon
       Pipe, copper, tubing, solder, 1/2" diameter, type L, includes        151074202140             50   L.F.
                                                                                                                    $8.75          1.0000     $           437.42
       coupling & clevis hanger assembly 10' O.C.
       Sink, kitchen, counter top style, porcelain enamel on cast iron,     154186002000             1     Ea.
                                                                                                                   $404.98         1.0000     $           404.98
       single bowl, 24" x 21", includes faucet and drain
       Faucets/fittings, kitchen sink faucets, top mount, cast spout        154103001000             1     Ea.
                                                                                                                   $95.49          1.0000     $               95.49
       A/C packaged, DX, air cooled, electric heat, VAV, 60 ton             D30502021060             1     Ea.    $87,323.54       1.0000     $         87,323.54
       Service installation, includes breakers, metering, 20' conduit &     D50101200520             1     Ea.
                                                                                                                  $32,218.90       1.0000     $         32,218.90
       wire, 3 phase, 4 wire, 120/208 V, 1600 A
       Feeder installation 600 V, including RGS conduit and XHHW            D50102300520             50   L.F.
                                                                                                                   $421.91         1.0000     $         21,095.58
       wire, 1600 A
       Receptacles and wall switches, 400 SF, 6 receptacles                 D50201200560        4,100     S.F.      $2.14          1.0000     $         8,759.81
       Fluorescent fixtures, type D, 12 fixtures per 600 SF                 D50202081640        4,100     S.F.      $7.13          1.0000     $        29,219.80
       Central air conditioning power, 8 watts                              D50201400360        4,100     S.F.      $0.75          1.0000     $         3,059.01
       Miscellaneous power, 2 watts                                         D50201350440        4,100     S.F.      $0.35          1.0000     $         1,415.48
       REPAIR SUBTOTAL                                                                                                                        $       306,742.83
                                                                                                                                           $              -
       REPLACEMENT ESTIMATE                                                                                                                $              -
       Wood piles, 25' long, 50K load, friction type, 3 pile cluster       A10201602240           25   Ea.      $1,549.79       1.0000     $        38,744.75
       Grade beam, 15' span, 28" deep, 12" wide, 8 KLF load                A10202102220          640   L.F.      $81.00         1.0000     $        51,841.34
       Slab on grade, 5" thick, light industrial, reinforced               A10301203400        4,100   S.F.       $5.40         1.0000     $        22,128.93
       Roof Construction                                                      B1020           4,100    S.F        $7.12         1.0000     $        29,192.00
       Exterior Walls                                                         B2010           4,100    S.F        $6.88         1.0000     $        28,208.00
       Exterior Windows                                                       B2020           4,100    S.F        $5.02         1.0000     $        20,582.00
       Exterior Doors                                                         B2030           4,100    S.F        $2.22         1.0000     $         9,102.00
       Roof Coverings                                                         B3010           4,100    S.F        $1.70         1.0000     $         6,970.00
       Partitions                                                             C1010           4,100    S.F        $3.88         1.0000     $        15,908.00
       Interior Doors                                                         C1020           4,100    S.F        $3.95         1.0000     $        16,195.00
       Fittings                                                               C1030           4,100    S.F        $0.46         1.0000     $         1,886.00
       Wall Finishes                                                          C3010           4,100    S.F        $1.07         1.0000     $         4,387.00
       Floor Finishes                                                         C3020           4,100    S.F        $6.95         1.0000     $        28,495.00
       Ceiling Finishes                                                       C3030           4,100    S.F        $5.10         1.0000     $        20,910.00
       Plumbing Fixtures                                                      D2010           4,100    S.F        $4.07         1.0000     $        16,687.00
       Domestic Water Distribution                                            D2020           4,100    S.F        $1.48         1.0000     $         6,068.00
       Terminal & Package Units                                               D3050           4,100    S.F       $16.34         1.0000     $        66,994.00
       Sprinklers                                                             D4010           4,100    S.F        $2.20         1.0000     $         9,020.00
       Standpipes                                                             D4020           4,100    S.F        $0.95         1.0000     $         3,895.00
       Electrical Service/Distribution                                        D5010           4,100    S.F        $8.71         1.0000     $        35,711.00
       Lighting and Branch Wiring                                             D5020           4,100    S.F        $8.46         1.0000     $        34,686.00
       Communications and Security                                            D5030           4,100    S.F        $5.59         1.0000     $        22,919.00
       Other Electrical Systems                                               D5090           4,100    S.F        $0.18         1.0000     $           738.00
       REPLACEMENT SUBTOTAL                                                                                                                $       491,268.01
                                                                                                                                           $              -
       Repair/Replacement Analysis: Repair Cost ($306,743)/Replacement Cost ($491,268) = 0.6244 = 62.4%. Exceeds 50%, replacement is
                                                                                                                                           $               -
       eligible.
       Additional Eligible Work for Replacment                                                                                             $               -
       Building demolition, small buildings or single buildings,
       concrete, includes 20-mile haul, excludes salvage, foundation        022201100600    5,750      C.F.       $0.37         1.0000     $          2,127.73
       demolition or dump fees
       Bldg. footings and foundations demolition, floors, concrete slab
       on grade, concrete, wire mesh reinforced, 4" thick, excludes         022201300280    4,096      S.F.       $3.86         1.0000     $         15,806.46
       disposal costs and dump fees
Part A Total $ - $ - $ - $ - $ - $ -
Part B Total $ - $ - $ - $ - $ - $ -
                                                  Guide
C.3 Access, Storage & Staging
                                               Low to High                                              Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%
     Storage Contingencies                       0%      4.0%
     Staging Contingencies                       0%      4.0%
                                                                   $            -   $                   -   $                   -     $   -       $       -       $           -
$ - $ - $ - $ - $ - $ -
Part C Total $ - $ - $ - $ - $ - $ -
New Construction
    Repair/Retrofit
                                                         $             -   $                   -   $                   -     $   -       $       -       $           -
Part D Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part H Total $ - $ - $ - $ - $ - $ -
                                                  Range
C.3 Access, Storage & Staging                  Low to High                                              Enter % in Appropriate Column
     Access Contingencies                        0%      4.0%                                 2.0%                      2.0%
     Storage Contingencies                       0%      4.0%                                 2.0%                      2.0%
     Staging Contingencies                       0%      4.0%                                 2.0%                      2.0%
                                                                   $            -   $                32,645   $                21,483   $   -       $       -       $      54,128
$ - $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -
Part F Total $ - $ - $ - $ - $ - $ -
                                                          Summary
           Coastal Texas Planning Commission - Planning Commission Office Building
                                                                                  Completed   Uncompleted         Total
PART A   "Base Costs" for Construction Work In Trades                         $           -   $    814,565    $     814,565
         A.1 Permanent Work                                                   $           -   $    814,565    $     814,565
         A.2 Non-Permanent Job Specific Work (CEF Part A)                     $           -   $         -     $           -
Complete Project Total for Completed and Uncompleted Work $ - $ 1,721,869 $ 1,721,869
Instructions for Completion (APPLY THE “SAVE-AS” <document name> FEATURE, FOR ADDITIONAL USE, WHEN THE REPORT HAS BEEN COMPLETED):
Starting at the top-middle field, enter the required information and press the tab key
to progress to the next field (or the shift-tab key to return to the previous field) –
1-  Enter the disaster number and the name of PA Group Supervisor preparing the report
2-  Enter the disaster declaration date and the date that this report was prepared
3-  Enter the Applicant Name
4-  Enter the PA ID # for the Applicant
5-  Enter the Project Worksheet number for each large project estimated using CEF
6-  Enter the large project category for permanent work                                                                             SUBMIT THIS REPORT TO:
7-  Enter the estimated large project cost for eligible work (from the CEF template)
8-  Enter the actual, final post-construction cost for eligible work                                                                Anthony Ndum, P.E.
9-  Enter the cost reconciliation calculation. Use the minus sign for negative numbers                                              Disaster Assistance Directorate
    (will display $ in parenthesis).                                                                                                Infrastructure Support Division
10- Enter a short description of the reason for cost reconciliation (i.e. the variation                                             Federal Emergency Management Agency
    between estimated and actual costs). Use a separate, attached sheet of paper                                                    Federal Center Plaza
    if more space is needed and so note in the comment field as necessary.                                                          500 C Street S.W., Room 414
11- Enter a short description of the function of the facility                                                                       Washington, D.C. 20472
        Appendix D
Hazard Mitigation Measures for
       Large Projects
The following potential mitigation measures (reference: paragraph VII.B.2) are determined to be
cost-effective if they:
   •   do not exceed 100% of project cost,
   •   are appropriate to the disaster damage,
   •   will prevent future similar damage,
   •   are directly related to the eligible damaged elements,
   •   do not increase risks or cause adverse effects to the property or elsewhere,
   •   are technically feasible for the hazard and location, and
   •   otherwise meet requirements stipulated in this policy, including environmental, historic,
       and mitigation planning considerations.
This list will continue to be evaluated and will evolve over time as new information becomes
available.
General
  I.   Drainage/crossings and bridges
          A.   Drainage structures - When drainage structures are destroyed, replacing the
               structure with multiple structures or a larger structure. Sizing of replacement
               culverts can be made using in-place state/local drainage criteria (nomographs).
               However, structures need to be considered with regard to a total drainage system
               and should not be upgraded without a watershed hydrology study with an
               emphasis on downstream effects and NFIP regulations.
          B.   Culverts – Where the alignment of culverts is inconsistent with streams flowing
               through them (because it has been blown-out), realign or relocate the culverts to
               improve hydraulics and minimize erosion. However, realignment of structures
               must be considered in regard to a total drainage system and shall not be replaced
               without a hydrology study with an emphasis on downstream erosion effects.
          C.   Headwalls and wing walls - Installation to control erosion.
          D.   Low-water crossings – When bridges are destroyed and where traffic counts are
               low, replacing bridges with carefully placed low-water crossings.
          E.   Gabion baskets, riprap, sheet-piling, and geotextile fabric installation - Installation
               to control erosion.
          F.   Roadways – Where roadways shoulders are damaged by overflow from adjacent
               water courses, stabilize shoulders and embankments with geotextile fabric.
                 2.   Dry flood-proofing.
 V.    Electric power distribution
        A.     Pad-mounted transformers - elevating above the base flood elevation.
         B.    Using multiple poles to support transformers.
         C.    Anchoring or otherwise protecting fuel tanks from movement in a disaster.
        D.     Replacing damaged poles with higher-rated poles, of the same or different
               material such as replacing wood poles with precast concrete or steel.
         E.    Adding guy wire or additional support to power lines.
         F.    Removing large diameter lines from poles.
        G.     Providing looped distribution service or other redundancies in the electrical
               service to critical facilities.
VI.    Above ground storage tanks
        A.     Strengthening or stiffening base connections.
         B.    Installation of self-initiating disconnects and shut-off values between tanks and
               distribution lines to minimize damage and leaks.
VII.   Underground pipelines - Installation of shut-off valves so that damaged sections of
       pipeline can be isolated.
Buildings:
  I.   General effects of flood damage –
        A.     Buildings substantially damaged under NFIP regulations - Repair, dry flood-
               proofing, or elevation so they are protected to meet minimum NFIP regulations. If
               the building is replaced, rather than repaired, minimum NFIP requirements are
               generally in place as codes and standards in participating communities and are
               applicable in both repair and replacement situation. Section 406 mitigation should
               be considered in those cases where these standards either fall short or provide no
               protection against other hazards.
         B.    Buildings not substantially damaged under NFIP regulations - If technically
               feasible, dry flood-proofing. Electrical panels, machinery rooms, emergency
               generators can be elevated above the BFE or dry flood-proofed. If dry flood-
               proofing is not feasible, these buildings should be wet flood-proofed.
 II.   Roofs - Because the failure of a roof covering can lead to extensive damage to contents
       and operation, damaged roofing should be evaluated to determine cause of failure.
        A.     Low slope roofs - Replacement of the entire roof with a roof covering with a
               secondary membrane and a fully adhered roof covering, such as modified
               bitumen. Mechanically fastened insulation or membranes are not acceptable.
     This Standard Operating Procedure (SOP) provides an overview of the Cost Estimating
     Format (CEF) for Large Projects and guidance on how to use the CEF tool. The SOP
     also discusses FEMA Headquarters large project reporting requirements.
     •   The CEF Information Update (January 1999) provides an overview of FEMA’s cost
         estimating methodology for large projects.
     •   The Cost Estimating Format for Large Projects Instructional Guide, Version 2.1
         (September 2009) provides application guidance to users responsible for developing
         large project cost estimates.
     For which Large Projects can the CEF be used to estimate costs?
     The CEF should only be used on large projects for which the permanent restorative work
     (categories C, D, E, F, and G) is less than 90 percent complete. Percent complete for all
     types of projects (including improved and alternate projects) is calculated by dividing the
     amount of approved contractor invoices for eligible work by the approved construction
     contract amount for eligible work and multiplying the resulting decimal by 100.
What is the process for preparing an estimate for a Large Project using the CEF?
     •   The CEF tool is to be used for developing estimates of eligible costs for certain
         permanent work large projects as described below. The primary objective is ensure
         FEMA develops sound and reasonable estimates of eligible costs based on the
         numerous factors, complexities, and local considerations related to the geographic
         area and circumstances arising from the declared event. In order to develop the most
         accurate and sound estimates, FEMA depends on a strong partnership with grantees
         and subgrantees. The local officials and local technical professionals (i.e. engineers
         and architects) commonly are in the best position to develop the estimates of eligible
         costs once FEMA, the State, and local officials have agreed upon eligible scopes of
         work. The role of FEMA is often to validate the estimates of eligible costs developed
         by the locals, ensure the costs address only eligible disaster-related work, and that
         appropriate CEF factors are applied to the base costs.
     •   The Public Assistance (PA) Group Supervisor or designee will determine which local
         factors to use to develop the project cost estimate. Specific factors include unit price
         sources, city cost indices (if applicable), and local costs for plan checks, building
         permits, or special reviews. The PA Group Supervisor will collect and evaluate this
         information for use in all CEF analyses at the beginning of each disaster.
     •   Project Specialists will determine the eligible scope of work and base costs (Part A of
         the CEF); including Special Considerations and appropriate Section 406 hazard
         mitigation for large projects that meet the CEF criteria. Projects Specialists will
         complete Part A of the CEF in accordance with the guidance provided in the Cost
         Estimating Format for Large Projects Instructional Guide. All work activities
         needed to perform the eligible scope of work must include a written description of the
         scope of work, the cost item reference [Construction Specifications Institute (CSI)
         based], cost code reference (if FEMA cost codes are used), the unit [linear foot (LF),
         square foot (SF), each (EA), cubic yard (CY), etc. - do not use lump sum (LS)], the
         quantity or measurement, the unit cost, and the quantity cost. Project Specialists will
         adjust each line item’s unit price and subtotal cost to reflect the city cost index where
         the work will take place.
     •   Project Specialists will document the eligible scope of work on the CEF Fact Sheet.
         Documentation must include detailed supporting backup information such as site
         maps (or location plan), photographs, sketches, calculations, measurements, insurance
         declarations, anticipated or actual insurance settlement, Section 406 Hazard
         Mitigation Proposal(s) (HMP), construction permits and clearances, force account
         summary sheets, and codes and standards described in the CEF Notes Sheet. For
         major construction activities (e.g. water control facilities and large buildings), the
         applicant should submit to the Project Specialist schematic drawings, a set of plans
     (preferably reduced to 11" x 17") containing basic information such as elevations, floor
     plans, site plan, structural plans and sections, etc., as applicable. The applicant should
     keep copies of source documents such as invoices, vouchers, timesheets, purchase orders,
     item slips, weight slips, plans and specifications, and insurance policies.
     •   After the eligible scope of work and its base costs are completed in Part A, the Project
         Specialist will complete Parts B through H (the factors applied to the base cost) of the
         CEF. The Project Specialist will develop separate summaries for completed and
         uncompleted work. The Project Specialist will document assumptions used in
         selecting factors B through H on the CEF Notes sheet.
     •   The Project Specialist will complete the Project Cost section of the PW as follows:
            Item – Enter sequential item number
            Code – #9000
            Narrative – add statement "See attached CEF spreadsheet for itemized unit-price
             estimate particulars"
            Quantity/Unit – 1 LS (lump sum)
            Unit Price – use the total estimate value from the CEF spreadsheet
            Apply appropriate cost adjustments to the CEF line-item #1 (e.g., a deduction for
             anticipated or actual insurance proceeds, salvage value/depreciation, etc.)
            The Total Project Cost will reflect the final eligible cost after any cost
             adjustments
     •   When applicants complete large projects and submit project documentation to the
         State and FEMA, FEMA will reconcile actual eligible costs against estimated costs,
         except for alternate and improved projects.
     •   If the Project Specialist requires assistance with any part of the CEF, the PAC Crew
         Leader will request a Technical Specialist (a cost estimator, engineer, environmental
         specialist, historic preservation specialist, insurance specialist, etc.) from the Ordering
         Specialist. Refer to the CEF for Large Projects Instructional Guide for more detail.
What is the process for preparing an estimate for a Large Project if CEF is not used?
     •   The Project Specialist will prepare the eligible scope of work and cost estimate using
         the standard damage assessment cost estimating procedures (see the Public Assistance
         Guide FEMA 322).
     •   The applicant should submit the same back-up and source documentation for all large
         projects formulated with or without CEF.
     •   The Data coordinator will scan all applicable supporting back-up documentation and
         attach to the PW.
     •   If the Project Specialist requires assistance with any part of the CEF, the PAC Crew
         Leader will request a Technical Specialist (a cost estimator, engineer, environmental
         specialist, historic preservation specialist, insurance specialist, etc.) from the Ordering
         Specialist.
     What are the appropriate references for unit prices in preparing Part A base costs?
     •   Project Specialists will request average weighted unit prices (local costs derived from
         actual contract history) from the applicant or relevant State/regional agency (e.g.,
         Department of Transportation) in order to develop Part A of the CEF. The Project
         Specialist should evaluate the average weighted unit price information for
         applicability to the eligible scope of work and consistency over a reasonable time
         period.
     •   The Project Specialist may use the FEMA Cost Codes, but is not required to do so.
         The FEMA Regional offices issue cost codes at the beginning of a Joint Field Office
         (JFO) operation. The cost codes represent “complete and in-place” costs (i.e., labor,
         equipment, and material costs necessary to complete installation) at the general
         contractor level (different from various industry standard cost estimating resources)
         and include overhead and profit.
     •   The Project Specialist may use the current edition of industry standard construction
         cost estimating resources (e.g., RSMeans, BNi Costbooks, Marshall & Swift, Sweet’s
         Unit Cost Guide, etc.) if the applicant does not have appropriate average weighted
         unit price data for unit prices in preparing Part A base costs.
         The PA Group Supervisor should order (at a minimum) one copy of each of the
         following cost data books for use by PA staff at the JFO:
         • ADA Compliance Pricing Guide          • Facilities
         •   Building Construction               • Heavy Construction
         •   Concrete and Masonry                • Mechanical
         •   Electrical                          • Plumbing
         •   Repair and Remodeling               • Square Foot Costs
         •   Site Work and Landscape
     •   If the Project Specialist uses national industry standard cost data in Part A, he should
         apply city cost indices to adjust the national unit prices to the nearest city for the
         declared counties. The PA Group Supervisor or designee will identify the zip codes
         included in the declared area, research industry standard cost estimating resources for
         the appropriate city cost factors and tabulate them for use by the Project Specialists.
     •   If cost estimating data is provided in an electronic format, only the appropriate city
         and/or zip codes may need to be provided. Various industry standard electronic cost
         estimating resources can be used to adjust the unit cost data to the required location
         automatically.
How are local costs for Plan Review and Construction Permits (Part F) determined?
     •   Alternatively, the Project Specialist may request this documentation from the
         applicant and provide the documentation to the PAC Crew Leader and the PA Group
         Supervisor for review and approval.
            Identification of the cost item that (construction cost, total project cost, etc.)
             serves as the basis for calculation of plan review/construction permit costs.
            The percentage applied to the base cost and these percentages may be on a sliding
             scale.
         The type of damage sustained will dictate how the values are selected for many of the
         factors. For example, visual identification of damage may be less difficult after a
         flood (once floodwaters have receded) than after an earthquake. The PA Group
         Supervisor may decide that the contingency factors in Part C should therefore be at
         the higher end of the range for an earthquake than for flooding.
     How is completed work costs included when the CEF is used for estimating the total
     cost of a Large Project that is less than 90 percent complete?
     The Project Specialist will prepare a Part A estimate using the CEF for Large Projects
     spreadsheet for the entire project. The Project Specialist is responsible for separating
     eligible work from ineligible work. If the applicant had an estimate prepared before the
     work was completed, the Project Specialist should compare the actual costs against that
     estimate, and if reasonable, reconcile the cost differences. The result should be entered in
     Part A “Summary for Completed Work.” If no applicant estimate exists, the Project
     Specialist will prepare a CEF Part A estimate of the eligible completed work activities
     and compare the actual costs against it, and if reasonable, reconcile the cost differences.
     The result should be entered in Part A ”Summary for Completed Work.” In both
     instances, the Project Specialist will also prepare a Part A CEF estimate for the
     uncompleted work portion using either average weighted unit prices or industry standard
     construction cost estimating resources (e.g. RSMeans, BNi Costbooks, Marshall & Swift,
     Sweet’s Unit Cost Guide, etc.). The Project Specialist is also responsible for completing
     Parts B through H, as appropriate, for both the completed and uncompleted work.
     •   The CEF Large Project Report is a Microsoft Word-based form that is distributed
         with the CEF Excel-based spreadsheet. Both tools are located on a CD ROM
         attached to the inside-back cover of the Cost Estimating Format for Large Projects
         Instructional Guide, Version 2.1, September 2009.
     •   For every large project FEMA estimated using CEF, the PA Group Supervisor or
         designee will prepare a CEF Large Project Report consisting of:
Applicant Name
PA ID Number
PW Number
Category of Work
     •   After applicants complete all large projects for which FEMA used CEF to estimate
         the costs, and FEMA reconciles the actual project costs with estimates, the PA Group
         Supervisor will forward the CEF Large Project Report to:
           CEF Instructional
                Guide
             (Version 2.1)
            September 2009
                                                  CEF V2.1
                                Guidelines for Application of Parts B through H
    E     Cost Escalation Factor                          Time to mid-point of construction = design time + ½ (construction time)
    E     Months              Any Number       Months     Number of months to the mid-point of uncompleted construction
          Escalation                           Refer to   Based on a 2-year average of either the Building Cost Index or the
    E                                 <1
          Factor                               CEF IG     Construction Cost Index according to the Engineering News Record.
NOTE: Interpolatation between values is acceptable. Interpolations should limit significant figures to a tenth of a percent.
To implement the CEF during the large project formulation process, the PA Group Supervisor or
designee is responsible for the actions listed below.
Set policies regarding the application of CEF, particularly with regard to:
Complete the CEF Large Project Report, as described above, and submit the report to FEMA
Headquarters:
                              Anthony Ndum, P.E.
                              Federal Emergency Management Agency
                              Federal Center Plaza
                              500 “C” Street, S.W. - Room 414
                              Washington, D.C. 20472
During the formulation and processing of large projects, the Project Specialist is responsible
for the actions listed below.
  Meet with the PAC Crew Leader to discuss the applicant’s needs.
  Meet with the applicant and the State to assess the applicant’s large projects.
 Obtain average weighted unit cost data from the applicant or relevant State or regional
   agency.
 Determine if the large project qualifies for CEF use.
 Conduct a site visit and determine the eligible scope of work.
 Identify any special considerations issues, including insurance, potential hazard mitigation
   measures, floodplain management, and compliance with environmental and historic
   preservation legislation, and executive orders. Notify the PAC Crew Leader of potential
   issues and revise the scope of work as appropriate.
 Assemble all appropriate back-up documentation, and a design/construction timeline.
 Prepare the CEF Spreadsheet. Document all assumptions on the CEF Notes Sheet.
 Review the estimate with the PAC Crew Leader.
 Complete the PW.
 Attach the CEF Spreadsheet to the PW. Submit the PW and appropriate back-up data to
   the PAC Crew Leader for processing and filing. See Appendix E – page 3.
 Assist the PAC Crew Leader in updating the Case Management File.
Assist the PA Group Supervisor in preparing the CEF Large Project Report as necessary.
   Does the scope of work address the damage caused by the disaster?
   Has a site visit by the project formulation team (Federal, State, and local members) been
    conducted?
   Is the scope of work eligible?
   Has the most effective method for accomplishing the work been selected?
   Does the scope of work include required code upgrades?
   Are upgrades for compliance with ADA eligible (for structural damage only)? If so, does the
    scope of work include ADA upgrades?
   Does the scope of work include approved hazard mitigation proposals?
   Has the applicant requested an improved or alternate project?
   Does the scope of work address special considerations such as insurance, floodplain
    management, compliance with the National Environmental Policy Act and other
    environmental laws, and compliance with the National Historic Preservation Act?
   Has special considerations clearance been obtained?
   Is the scope clearly defined in terms of repair, retrofit, new construction, hazard mitigation
    and other activities that might be contracted separately?
   Are completed work items separated from uncompleted work items?
   Are permanent and non-permanent work items clearly separated?
   Have all eligibility decisions been made and agreed upon with the applicant?
Part A Totals
   Are there separate totals for completed work and are they separated by work type (repair,
    retrofit, new construction, hazard mitigation, and other)?
   Are there separate totals for uncompleted work and are they separated by work type (repair,
    retrofit, new construction, hazard mitigation, and other)?
   Are all situations where Part A includes factors that could be duplicated in Parts B through H
    noted?
   Have all assumptions or clarifying notes been included in the CEF Notes Sheet?