FACADE
TILE CLADDING WORKS AT PANORAMA TOWER
AT EMAAR CRESCENT BAY, DHA KARACHI
Activity Name Start Finish Original 2023 2024
Duration
ov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Total 25-Jan-23 12-Sep-24 502 25-Jan-23 12-Sep-24
1-2 FACADE TILE CLADDING WORKS PACAKAGE 25-Jan-23 12-Sep-24 502 25-Jan-23 12-Sep-24
1-2.1 Start of Project 25-Jan-23 12-Sep-24 502 25-Jan-23 12-Sep-24
Project Initate 25-Jan-23 0 Project Initate
Sub-Con Mobilization 25-Jan-23 18-Feb-23 22 25-Jan-23 18-Feb-23
1-2.1.1 BASE TOWER ( RAFT ~ L-08 04-Feb-23 15-Sep-23 185 04-Feb-23 15-Sep-23
Facade & Glazing Works 04-Feb-23 15-Sep-23 185 04-Feb-23 15-Sep-23
1-2.1.2 HIGH RISE TOWER ( L-09 ~ ROOF 06-Jun-23 12-Sep-24 392 06-Jun-23 12-Sep-24
Facade & Glazing Works 06-Jun-23* 12-Sep-24 392 06-Jun-23* 12-Sep-24
Date Revision Checked Approved Actual Work Critical Remaining Work Summary
Page 1 of 1
Will be review after reciving IFC Drawings
Remaining Work Milestone