Ukcs Ti Goc

This document provides guidance on applying Certification requirements for maintenance and operational activities in the UK North Sea. It outlines roles and responsibilities for certifying work, describes the technical assurance process and business flows, and provides guidance for identifying certification needs for different work types, including concurrent activities. Requirements specific to the UK region are included in addendums. The goal is to demonstrate that technical integrity is achieved and maintained during work following best practices for risk management.

Uploaded by

John Dry
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
526 views27 pages

Ukcs Ti Goc

This document provides guidance on applying Certification requirements for maintenance and operational activities in the UK North Sea. It outlines roles and responsibilities for certifying work, describes the technical assurance process and business flows, and provides guidance for identifying certification needs for different work types, including concurrent activities. Requirements specific to the UK region are included in addendums. The goal is to demonstrate that technical integrity is achieved and maintained during work following best practices for risk management.

Uploaded by

John Dry
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 27

Uncontrolled when Printed

North Sea SPU (UK)

Guidance on Certification

Issuing Document Dave Madden


Authority: Authority: Commissioning Team Leader
Document Janet Ross Applicability: North Sea SPU (UK)
Administrator: OMS Advisor
Issuing Maintenance Control Tier: 2
Department:
First Issue Date: May 2001 Revision No: Issue 4/AM01
Revision Date: April 2011 Review Required By: July 2011
Revision Summary: Updated to include use of four part tag mandated in UKCS-SOP-012.
For further information contact DCC at ODL on 01224 628018 or dcc@odl.co.uk.
Document Location: Documentum/ABZ Federal/SMS

UKCS-TI-019
Guidance on Certification UKCS-TI-019

Contents

Paragraph Page

1 Terminology 1

2 Purpose 1
2.1 Risk Management 1

3 Scope 2
Uncontrolled when Printed

4 Roles and Responsibilities 2


4.1 Site Manager 2
4.2 Department Head (Operating Authority) 2
4.3 Area Authority 3
4.4 Job Officer 3
4.5 Guidance on Certification Site Focal Point 3
4.6 Site Planner 4
4.7 Certification Signatories 4

5 Technical Integrity Assurance Process and


Handover Control Gates 5

6 Business Process Flow 6

7 Identification of Certification Requirements 8

8 Multiple Scope of Work Types 9


8.1 Work Types 9
8.2 Work Managed by the Engineering, Modifications and
Maintenance Contractor 9
8.3 BP-managed Site Modifications or Maintenance
Activities 9
8.4 Concurrent Working 9

July 2009 Issue 4 i


UKCS-TI-019 Guidance on Certification

Contents (cont’d)

Paragraph Page

9 Certification Tracking 11

10 Training and Coaching 11

11 Audit 12
Uncontrolled when Printed

Figure
1 Handover Process Flowchart 5
2 Business Process Flowchart 7
3 Certification Requirements Flowchart 8
4 Technical Integrity Assurance for Multiple Concurrent Activities 10

Addendum 1 Planning Process


Addendum 2 Mnemonics as Applied to Maintenance and Operations
Addendum 3 Handover Limits as Applied to Modifications
Addendum 4 Notes on Completion of Individual Certificates
Addendum 5 Additional Requirements or Replacement Certificates
for UKCS Use
Addendum 6 Functional Certification Flowchart
Addendum 7 Terms of Reference and Assurance Protocol

ii July 2009 Issue 4


Guidance on Certification UKCS-TI-019

1 Terminology

Dispensation for Area


Covered by Term
Term Use of Term Infers
All dispensations must be
recorded and retained
Must Legislative Requirement No dispensation can be granted.
Inform SPU EA/VP S&OR via
Head of Unit
Group Standard/Practice or Authorisation above the level of
Golden Rule North Sea Unit. Forward to VP
S&OR/SPU EA for referral
Uncontrolled when Printed

to Group
Shall Minimum requirement Approval of VP S&OR/SPU EA
stipulated at SPU/UK level
Should SPU/UK Best Practice or Approval of Site Manager/OIM
Recommended/Preferred option

2 Purpose
The objective of this document is to provide guidance on how to apply Guidance on
Certification (GOC) to suit maintenance and operational needs, activities managed by
Engineering, Modifications and Maintenance (EMM) contractors and respective manning
and management structures typically found on an operating facility.

2.1 Risk Management


This document, along with Full GOC (namely intranet site http://goc.bpweb.bp.com/)
should be used on all Exploration and Production (E&P) segment projects in the United
Kingdom Continental Shelf (UKCS).
Note: The Full GOC is the federal Guidance on Certification that has been successfully
implemented on projects and Turnarounds (TARs) around the world and which
has its own intranet site containing all of the manuals and certificates in addition
to product news and information (http://goc.bpweb.bp.com/).
Some supplementary requirements for this region, which have not yet been incorporated
into the global manuals and certificates, are contained in Addendum 5.

July 2009 Issue 4 1


UKCS-TI-019 Guidance on Certification

2.1.1 Best Practice


GOC is recognised federally as ‘best practice’ for demonstrating that Technical Integrity (TI)
has been achieved and/or maintained during construction, commissioning and handover
of new plant.
Note: TI is the condition of a plant that meets its design criteria and intended purpose.
If deviations exist, these have been identified and assessed, and all changes
necessary to ensure continued safe, efficient operation have been implemented.

3 Scope
This document applies to all North Sea Strategic Performance Unit (SPU) assets in the
UKCS and onshore in the UK.
Uncontrolled when Printed

The following main elements of the GOC process, as it is applied to maintenance and
operations, are addressed:
 The TI assurance process and handover control gates
 The business process flow (including prerequisites for GOC implementation)
 Roles and responsibilities
 Identification of certification requirements
 GOC implementation for multiple scopes of work
 Certification tracking and archiving
 Training and coaching
 Audit

4 Roles and Responsibilities


4.1 Site Manager
The Site Manager is the overall owner of the TI process and will ensure that
maintenance and operations are appropriately controlled by certification, utilising the
GOC process.
The Site Manager will be accountable for signing as Accepting Authority for all System
Handover Certificates (SH1s).

4.2 Department Head (Operating Authority)


The Department Head will ensure that GOC requirements are identified at the Long
Term Planning meeting and that all aspects of:
 GOC are planned and executed to ensure that TI is maintained
 The GOC System employed will be fully auditable

2 July 2009 Issue 4


Guidance on Certification UKCS-TI-019

4.3 Area Authority


The Area Authority will ensure that certification being used for maintenance tasks is
adequate for the work being carried out and that the correct cross-references are
indicated within the certification pack.
He/she will also ensure that the performing bodies have taken all steps to ensure that
the system/equipment is safe, by raising the System Safe Certificate (SS1) prior to work
commencing. He/she must be assured that all statutory and legislative requirements are
complied with, and that the certification is fully signed by a Competent Person(s) prior to
acceptance of the equipment from the Job Officer. The Area Authority will be required to
sign as Accepting Authority for all Mechanical Completions Certificates (MC1s).

4.4 Job Officer


Uncontrolled when Printed

The Job Officer will be responsible for ensuring that the Limits of Systems Handover
(LOSH), Discipline Certificates and Handover Certificates (SS1, MC1 and SH1) have been
specified for jobs which have been approved and scheduled in the Long Term Plan (refer
to Addendum 1).
In addition, he/she will:
 Accept the SS1 prior to work commencing and ensure that all certificates are
correctly completed by the pre-designated responsible engineer/technician
 Maintain the GOC database as appropriate
 Ensure that the certification pack will guarantee TI
If an additional certificate is added to the certification package, the Job Officer will
ensure that the data is added to the database. The database will be updated on
completion of the task, after all signatures have been added to the certification.

4.5 Guidance on Certification Site Focal Point


The GOC Site Focal Point will:
 Ensure that the site maintains all prerequisites to ensure ease of GOC implementation
 Assist the Job Officer to generate handover mnemonics and certification
requirements specific to each scope of work
 Maintain and oversee the update of the GOC database
 Ensure that a full training and competence record is maintained
 Keep the master list of approved certification signatories
Initially the GOC Site Focal Point will maintain the database until personnel become
familiar with the simple inputs on a day-by-day basis. He/she should also hold a briefing
session leading up to, and following, implementation. Coaching will be on a one-to-one
basis as and when certification packs are being compiled.

July 2009 Issue 4 3


UKCS-TI-019 Guidance on Certification

4.6 Site Planner


The Site Planner will be responsible for ensuring that:
 All jobs are identified in the Long Term Plan
 All jobs approved are detailed in the Short Term Plan
 The Job Officer has been notified of the forthcoming certification requirement
and implementation

4.7 Certification Signatories


It is the responsibility of signatories to ensure they are familiar with, and understand,
what they are signing and that the certificates are signed at the appropriate time.
Uncontrolled when Printed

4.7.1 Guidance on Certification Signatory Matrix

Certification From To Comments

SS1 Area Authority Job Officer

Certification Technician/Engineer Job Officer Punch List to be


Non-energised raised
(Blue Tower in GOC)
MC1 Job Officer Area Authority
Certification Technician/Engineer Area Authority Punch List to be
Energised raised
(Green Tower in GOC)
SH1 Area Authority Site Manager

4 July 2009 Issue 4


Guidance on Certification UKCS-TI-019

5 Technical Integrity Assurance Process and


Handover Control Gates
The TI assurance process consists of two phases (planning and TI assurance), which are
underpinned by three handover control gates (refer to Figure 1).

PLANNING PHASE TI ASSURANCE PHASE

FUNCTIONAL
SYSTEM

NON-ENERGISED STATE ENERGISED STATE

LIMITS OF SYSTEMS
IDENTIFY WORK CERTIFICATES CERTIFICATES
HANDOVER (LOSH)

LONG TERM CERTIFICATION JOB READY


Uncontrolled when Printed

SS1 MC1 SH1


PLAN PACK TO EXECUTE

GATE 1 GATE 2 GATE 3

MINIMUM PL1 PL1


CERTIFICATES
INSPECTION AND
TEST SUMMARY (ITS)

GUIDANCE ON CERTIFICATION (GOC) DATABASE, THROUGH LIFE DATA CAPTURE

UKCSTI019_001.ai

Figure 1 Handover Process Flowchart

The planning phase ensures that all requirements have been fully defined and approved,
within the site Long Term Plan, and that the job is ready to execute.
The TI assurance phase ensures that the job is executed safely and is fully installed and
tested prior to energisation or introduction of hydrocarbons.
The three handover control gates are:
 Safety: System Safe Certificate (SS1)
 Installation: Mechanical Completions Certificate (MC1)
 Ready to Operate: System Handover Certificate (SH1)

July 2009 Issue 4 5


UKCS-TI-019 Guidance on Certification

6 Business Process Flow


Maintaining TI of process plant and utilities, during maintenance and operations, is made
easy by following the four basic steps defined below and translated into the Handover
Process Flowchart (Figure 1) and the Business Process Flowchart (refer to Figure 2).
For each new scope of work, the site shall implement the GOC requirements within
these four guiding principles:
(1) Plan Requirements:
 Establish a Long Term Plan for Turnarounds (TARs) and maintenance activities
 Establish site-specific system mnemonics based upon the guidelines within Full
GOC (http://goc.bpweb.bp.com/) (refer to Addendum 2 for an overview)
 Generate a set of composite site Piping and Instrumentation Diagrams (P&IDs)
Uncontrolled when Printed

fully marked up into Functional Systems (a method for breaking down a


complete plant into operational systems, which can logically be constructed and
commissioned together. This approach enables the commissioning plan to
integrate the construction work to the benefit of the overall execution plan)
 Define the LOSH, including isolations
(2) Perform the Work:
 Identify and generate the required certification
 Assign responsibilities and authorities for certification completion
 Implement the supportive test procedures specific to each certificate within
GOC during installation and testing
 Record satisfactory completion of the inspection or test on the GOC Certificate
or instigate remedial action
 Implement the Handover Process Gates, ie SS1, MC1 and SH1
(3) Measure the Work:
 Provide an audit trail to demonstrate that all activities have been closed out,
by ensuring that all tagged items have been completed and certified by entering
completion dates into the GOC database
(4) Improvements:
 Continuous development of BP and contractor personnel through training
 GOC System improvement feedback to UKCS Single Point of Contact (SPC) and
site focal points
 GOC System improvements to meet changing legislation and BP Health,
Safety, Security and Environment (HSSE) requirements
 Periodic audit of TI process, initiated by UKCS SPC and performed by QEDi
Technical Authority (Aberdeen) Inspection Service and/or others
The business process flow and responsibilities for each stage and activity within the
GOC process for maintenance and operations are defined in Figure 2.

6 July 2009 Issue 4


Guidance on Certification UKCS-TI-019

The process to identify the certification requirements is defined in Paragraph 7.

Guidance on Certification (GOC)


Activity and Responsibility Flowchart

Objective: To define the key steps and responsibilities of GOC interaction and group responsibility

Legend: Handover and Information and Review or


Action
accepts responsibility participation action

Job Office/Technician

Site GOC Focal Point

Assigned Personnel
Department Head
Formal Meetings
Responsibility

Area Authority
Site Manager

Site Planner
Notes

Activity
Uncontrolled when Printed

Plan Workscope
Verify asset mnemonics and functional
1.1 systemisation compliance with GOC Annual confirmation review
and operations requirements

1.2 Identify GOC requirements at Long Term Meeting


Planning meeting

1.3 Generate LOSH mnemonics for As per Figure 3


Workscope: SH1, MC1 and SS1

Perform Workscope
Identify certification requirement: GOC Functional Certification
2.1 Green Tower Certificates JI1, SL1 etc Flowchart (Addendum 7)
– Blue Tower Certificates MP1, CC1 etc

2.2 Job confirmed and approved for schedule


and inserted in to Short Term Plan

2.3 Confirm responsibility matrix to reflect Ensure training has been


manning at time of implementation provided for assigned personnel

Measure Workscope

3.1 Complete System Safe Certificate

3.2 Complete Blue Tower Installation Ensure as-built drawings marked


Certificate requirements and Punch List up if appropriate
Job officer to decide upon GOC
3.3 Update GOC database database update method/
resource

3.4 Complete Mechanical Completion


Certificate MC1

3.5 Complete Green Tower Energisation Test Ensure as-built drawings marked
Certificate and Punch List up if appropriate
Job Officer to decide upon GOC
3.6 Update GOC database database update method/
resource
Site Manager may delegate to
3.7 Complete System Handover Certificate SH1 Department Head to ensure
correct process has been applied

3.8 Complete JI1 activities post SH1

3.9 Close out GOC database

3.10 Archive certification package

Improvements

4.1 Capture Lessons Learned and system End of process


improvements or queries

UKCSTI019_002.ai

Figure 2 Business Process Flowchart

July 2009 Issue 4 7


UKCS-TI-019 Guidance on Certification

7 Identification of Certification Requirements


The Certification Requirements Flowchart (refer to Figure 3) is to be used as guidance to
direct the GOC Site Focal Point and Job Officer to identify the minimum certification and
handover gates required.

REFER TO THE CONTROL


YES OF HIRED AND
PORTABLE
TRANSPORTABLE
EQUIPMENT?
EQUIPMENT
(UKCS-SOP-005)

NO

DOES
ACTIVITY INVOLVE
BREAKING PRESSURE NO
CONTAINMENT, BREAKING CIRCUITRY
OR ADDING NEW
SOFTWARE?

YES
Uncontrolled when Printed

NO IS ACTIVITY MECHANICAL
ELECTRICAL AND
MANAGED BY BP DISCIPLINE –
CONTROL DISCIPLINES
(CORE CREW)? VESSELS AND PIPING

YES

PART OF POTABLE
EMERGENCY HYDROCARBON, WATER, HEAT/COOLING
IS ACTIVITY NO YES SHUTDOWN (ESD)/FIRE AND HYDRAULIC, METHANOL, NO NO
MEDIUM, SEAWATER, FIREWATER,
A MODIFICATION GAS (F&G) SYSTEM OR PROTECTION WATER INJECTION (WI), HIGH COMPRESSED AIR, LOW PRESSURE
SCOPE? SYSTEM (EXCLUDING PRESSURE (HP) N2, DIESEL (LP) N2, FOAM OR
FIELD DEVICES)? OR HELIFUEL? CHEMICALS?
YES
NO YES YES

YES
IS TASK MULTI-
USE FULL GOC
DISCIPLINE?

NO

DISCIPLINE CERTIFICATES DISCIPLINE CERTIFICATES SYSTEM SAFE (SS1)


SYSTEM SAFE (SS1) SYSTEM SAFE (SS1) JOINT INTEGRITY (JI1) JOINT INTEGRITY (JI1)
SYSTEM CONTROL FUNCTION TEST (SC1) MECHANICAL COMPLETION (MC1) LEAK TEST (SL1) PUNCH LIST (PL1) GOC CERTIFICATION UNLIKELY TO BE
PUNCH LIST (PL1) JOINT INTEGRITY (JI1) PUNCH LIST (PL1) SYSTEM HANDOVER (SH1) REQUIRED (BUT TO BE ASSESSED ON
SYSTEM HANDOVER (SH1) LEAK TEST (SL1) SYSTEM HANDOVER (SH1) MECHANICAL COMPLETION (MC1) A CASE-BY-CASE BASIS)
MECHANICAL COMPLETION (MC1) PUNCH LIST (PL1) MECHANICAL COMPLETION (MC1) IS OPTIONAL
IS OPTIONAL SYSTEM HANDOVER (SH1) IS OPTIONAL

UKCSTI019_003.ai

Figure 3 Certification Requirements Flowchart

It is essential that each job activity is assessed on an individual basis, depending upon its
technical complexity and service.
(1) All modifications and/or work carried out under EMM contractor management will
use the GOC database and Full GOC (http://goc.bpweb.bp.com/) (and the
TI assurance flowcharts therein).
(2) BP-managed activities will utilise facility-specific mnemonics and the appropriate
GOC certification requirements of Figure 3.
(3) A TAR can be a combination of (1) and (2).

8 July 2009 Issue 4


Guidance on Certification UKCS-TI-019

8 Multiple Scope of Work Types


8.1 Work Types
There are three work types that may be carried out on a site at any one time:
 Modifications
 Multi-discipline maintenance activities
 Single-discipline maintenance activities
These can be managed by BP or by the EMM contractor. This process facilitates all three
work types taking place at the same time, under both types of management.

8.2 Work Managed by the Engineering, Modifications and


Uncontrolled when Printed

Maintenance Contractor
Most construction work on a site is managed through the EMM contractor and,
therefore, the EMM, construction and commissioning authorities must demonstrate that
TI has been achieved.
Full GOC is ideal for construction projects (both green and brown field) due to the way in
which it controls and monitors TI from the project SS1, through MC1, to completion and
SH1 (refer to http://goc.bpweb.bp.com/). This, along with the accessibility to the GOC
database, provides the necessary auditable trail which makes Full GOC the correct tool
to demonstrate that TI has been achieved.
The contractor must therefore use the Full GOC and apply the TI assurance flowcharts
defined therein.

8.3 BP-managed Site Modifications or Maintenance Activities


Each site will have a GOC database that registers and allocates the next operations and
maintenance raised handover mnemonics.
By applying the certification requirements (Figure 3), the correct application of GOC can
be identified for most activities.
This enables the site to use the certification required to control and demonstrate that
TI has been maintained, relative to the task at hand.

8.4 Concurrent Working


TARs and other situations may have both BP and EMM contractor-managed work
occurring simultaneously, which will result in different work parties applying for work on
the same systems within the same timeframe. It is essential that the contractor and
BP maintenance and operations personnel work together, to create a coherent,
unified certification package.
Figure 4 demonstrates how EMM contractor-managed work can be undertaken
simultaneously with BP-managed work, utilising the correct level of TI planning and
assurance.

July 2009 Issue 4 9


UKCS-TI-019 Guidance on Certification

DEFINE JOB
ACTIVITY

SCOPE OF WORKS
eg TAR

CONFIRM IN LONG
TERM PLAN

RISK ASSESSMENT
SCOPE
YES MANAGED BY NO
Uncontrolled when Printed

BP BUSINESS
UNIT (BU)?

MULTI-DISCIPLINE SINGLE DISCIPLINE


MODIFICATION
ACTIVITY ACTIVITY

REFER TO REFER TO
FULL GOC FULL GOC
FIGURE 3 FIGURE 3

SPECIFY SPECIFY SPECIFY * COMPONENT CHANGE-OUT SPECIFY


CERTIFICATION CERTIFICATION CERTIFICATION AND/OR SERVICE MAY NOT CERTIFICATION
REQUIRE AN MC1

** BP AND CONTRACTOR
CONCURRENT ACTIVITIES
IN THE SAME SYSTEM WITH
ONE SS1, MC1 UNDER A
SS1 SS1 SS1 SS1
COMMON SH1

IMPLEMENTATION

MC1 MC1* MC1* MC1** MC1

SH1 SH1 SH1 SH1

FINAL SH1 WHICH WILL SIGNIFY THAT ALL WORKSCOPES ARE


SH1 FULLY CERTIFIED IN ACCORDANCE WITH GOC REQUIREMENTS
AND THAT TECHNICAL INTEGRITY HAS BEEN ACHIEVED.

START-UP

UKCSTI019_004.ai

Figure 4 Technical Integrity Assurance for Multiple Concurrent Activities

10 July 2009 Issue 4


Guidance on Certification UKCS-TI-019

9 Certification Tracking
GOC certification will be tracked utilising the GOC database, which will be used for both
BP-managed and EMM contractor-managed workscopes.
It will be the responsibility of the Job Officer to raise and control certification associated
with the task that he/she is controlling. Initially, this will be carried out with coaching by
the GOC Site Focal Point until such time as individuals are competent to carry out this
task on a stand-alone basis.
The tracking of certification serves two purposes:
(1) To provide information of the current state of any particular task and to provide
Platform personnel, not directly involved with a particular task, with up-to-date
information regarding the task status.
Uncontrolled when Printed

It is the responsibility of the Job Officer to update the GOC database, at the end of
each shift, to reflect the certification status.
It is the responsibility of individuals, who are required to sign a certificate, to
ensure that they have contacted the Job Officer to sign the certificate(s) in
question prior to going off shift and under no circumstances are they to demobilise
leaving any certification unsigned.
It is the responsibility of the Job Officer to ensure that certification signatures
are obtained and that the GOC database and process is closed out, unless an
‘Assigned Person’, according to Figure 2, has been appointed to this function.
(2) To provide an auditable trail of all certification, Punch Lists and handover status.
The GOC database is constructed for the purpose of tracking certification and to
store information with regard to completed certification.
The method of archiving of hard copy certificates, as either electronic CD-ROM
files or hardback original certification dossiers, will form part of the documentation
strategy for the site. This must, however, comply with BP HSSE and technical
requirements, in addition to current legislation.

10 Training and Coaching


The coaching role adopted by the GOC Site Focal Point is to ensure that individuals are
fully supported until they are competent to compile and control a certification pack. It is
recommended that personnel attend a 1-day refresher course every 3 years in order to
be made aware of developments, updates and revisions to the GOC.
The GOC Site Focal Point will maintain a competence register, to demonstrate that all
individuals have attended the 1-day, company-specific GOC training course.
The expectation is that the version of GOC described in this document will be
much easier to use for maintenance and operations activities than the Full GOC
(http://goc.bpweb.bp.com/), but the Site Focal Point must ensure that those requiring a
refresher course are offered this as part of their ongoing professional development.

July 2009 Issue 4 11


UKCS-TI-019 Guidance on Certification

To ensure that personnel fully understand the process, the following will be carried out,
post-job implementation by the Site Focal Point:
 A method of encouraging constructive feedback to be set up, to determine if the
process is working correctly and effectively
 Regular TI meetings to be set up, to monitor progress

11 Audit
Periodic audits will be scheduled by the UKCS SPC and performed by QEDi and/or
others, to ensure that TI compliance is achieved and that GOC is being correctly
implemented.
The UKCS SPC shall manage quarterly review meetings with Site Focal Points and
Uncontrolled when Printed

QEDi, to ensure that lessons learned and improvements are captured and implemented.
QEDi shall ensure that all lessons learned and improvements are shared with BP
Global SPCs.

12 July 2009 Issue 4


Guidance on Certification UKCS-TI-019

Addendum 1
Planning Process

1 Planning
Jobs appearing on the Long Term Plan will indicate if a Guidance on Certification (GOC)
certification pack is required. The Job Officer will ensure that a complete pack is
compiled prior to a task moving to the Short Term Plan. Jobs which occur after the Short
Term Plan has been issued will be added after the certification pack has been compiled.
The Job Officer will ensure that the certification pack details the correct Maximo
cross-references.
Uncontrolled when Printed

Jobs requiring certification, or without a certification pack, should not appear on the
3-day plan, unless it is a high priority job for which permission is given by the
Department Head.
The final review of a task at the permit meeting should determine if a job without a
required certification pack is to be allowed to go ahead.

2 Summary
 No job requiring certification will be allowed to go ahead without permission of
management
 Certification packs are to be compiled as a normal part of job planning
 Priority 1 jobs will be treated on an individual basis dependent on the criticality
It should be noted that, in most cases, a certification pack can be compiled in less
time than the decision-making process takes.

Planning Process
July 2009 Issue 4 Add 1-1/2
Guidance on Certification UKCS-TI-019

Addendum 2
Mnemonics as Applied to
Maintenance and Operations

Guidance on Certification (GOC) mnemonics (mnemonics being the Greek word for memory)
detail the nine Primary ‘Functional’ Systems on any one facility. The nine Primary Systems can
be further sub-divided into a 2-digit Secondary System. A set of composite Piping and
Instrumentation Diagrams (P&IDs) or Single Line Diagrams (SLDs) detail the limit of each
Primary and Secondary System, therefore creating a ‘Road Map’ of the facility, detailing all the
‘A’ roads (Primary Systems) and all the ‘B’ roads (Secondary Systems).
Uncontrolled when Printed

By having this functional system map of the facility, BP can pinpoint exactly all of the
equipment to be worked upon and, equally important, identify all the Primary and Secondary
Systems that will be affected by the work. By knowing this data, BP can plan efficiently when
and how to carry out the work.
Systems are divided into Functional Systems, which then can be sub-divided into a 2-digit
Secondary System.

Handover Identifier

A 2 12 S 0139 +01

FACILITY MC1 No

PRIMARY IDENTIFIER SH1 SEQUENTIAL No

SECONDARY IDENTIFIER HANDOVER TYPE

UKCSTI019_005.ai

Mnemonics as Applied to Maintenance and Operations


July 2009 Issue 4 Add 2-1/2
Guidance on Certification UKCS-TI-019

Addendum 3
Handover Limits as Applied to Modifications

As previously stated, Engineering, Modifications and Maintenance (EMM) contractors are to


use Full Guidance on Certification (GOC) (http://goc.bpweb.bp.com/). Therefore, where a
maintenance task falls within a construction project modification, the maintenance task will be
aligned to the construction project handover by giving the maintenance task the next
Mechanical Completions Certificate (MC1) number and linking the Maintenance MC1 to the
Project System Handover Certificate (SH1) number.
All site works will be system-based. To this end, GOC for maintenance and operations is ideally
aligned to this scenario. Again, where a construction project encapsulates a maintenance
Uncontrolled when Printed

routine or task, the maintenance routine or task will be linked to the Construction SH1 number
as previously described. Any maintenance work that is to be completed within the SH1
boundary will be captured by an MC1. The SH1 flowchart in Figure 1 demonstrates this
principle.

MODIFICATION

SYSTEM 1 SYSTEM 2 SYSTEM 3


(MAINTENANCE SH1) (MAINTENANCE SH1) (MAINTENANCE SH1)

ISOLATIONS ISOLATIONS

CONSTRUCTION PROJECT
SYSTEM SH1 FOR SH1 BOUNDRY
MAINTENANCE TASKS

MAINTENANCE
CONSTRUCTION
TASKS SYSTEM 2
PROJECT (SH1)
MAINTENANCE SH1

MAINTENANCE TASK No1


MAINTENANCE TASK No1
WITHIN BOUNDARY
SYSTEM 2MTCSH1+01
CONST SH1/MC1+01

MAINTENANCE TASK No1


MAINTENANCE TASK No1
WITHIN BOUNDARY
SYSTEM 2MTCSH1+02
CONST SH1/MC1+02

MAINTENANCE TASK No1


MAINTENANCE TASK No1
WITHIN BOUNDARY
SYSTEM 2MTCSH1+03
CONST SH1/MC1+02

UKCSTI019_006.ai

Figure 1 Application of MC1 within a System Outage, which Incorporates


a Construction Project or Modification

Handover Limits as Applied to Modifications


July 2009 Issue 4 Add 3-1/2
Guidance on Certification UKCS-TI-019

Addendum 4
Notes on Completion of Individual Certificates

In order to ensure that original Guidance on Certification (GOC) certificates for site maintenance
tasks can be easily used, the following manual changes can be undertaken:
 Isolation Control Certificate Reference (ICC-xxxxx) can be inserted into any blank boxes or
comments field

JI1 Joint Integrity Certificate


For breaking of containment, the Certification Requirements Flowchart (refer to Figure 3 in the
Uncontrolled when Printed

main text) is very specific with regard to what/if GOC should be applied. Where no System
Safe Certificate (SS1)/System Handover Certificate (SH1) is required, mnemonics will be issued
and cross-referenced to the Maximo job card to provide a clear, auditable trail. Technicians
must ensure that a reference to the mnemonic number is entered on the job card.

SL1 Leak Test Certificate


Whenever a Joint Integrity Certificate (JI1) is used on high risk pipe work, a leak test and Leak
Test Certificate (SL1) will normally be required. The exception to this rule is when a leak test
cannot be achieved; in this case, a controlled service test will be performed (refer to
Paragraph 6.14 of Safe Isolation and Reinstatement of Plant (NSSPU-GP-44-40-1) and the details
of this will be captured on the JI1.
The Job Officer will fill in the certificate header details. For maintenance and operations
certification, an SL1 with the task details is to be passed to the Area Authority, or his delegate,
who will identify the limits of leak test and test points. The Area Authority will also attach a
marked up Piping and Instrumentation Diagram (P&ID), which will then be added to the
certification pack.
The contractor will include a completed SL1, with the leak test details populated and the test
limits highlighted on a P&ID that clearly shows the test points. The leak test details will be part
of the preliminary work pack which is sent to site; the Area Authority, or his delegate, will
confirm/amend the limits of leak test and test points accordingly. The Area Authority will also
attach a marked up P&ID to the preliminary work pack and pass this back to the construction
contractor for inclusion in the Rev C1 AFA work pack.
Prior to leak testing, the technician who will carry out the leak test will check the SL1 limits and
confirm that the test limit envelope captures all areas that break containment.

PL1 Punch List


Where a Punch List (PL1) is used for maintenance, or for an operations project, the job limits
will be walked by the Job Officer and the Area Authority (or designate if the Area Authority is
not technically competent to punch out the job in question).

Notes on Completion of Individual Certificates


July 2009 Issue 4 Add 4-1
UKCS-TI-019 Guidance on Certification

A single PL1 will be used to cover all disciplines. As with Full GOC, all ‘A’ items will require
rectification prior to final commissioning; any outstanding ‘B’ items will be cleared from the PL1
by raising Maximo jobs to carry out the remedial work (http://goc.bpweb.bp.com/).
All disciplines will sign the PL1; if no items are found within a particular discipline, the PL1 will
read ‘No Items Found’ or similar, to indicate that the work carried out has been reviewed and
that no ‘A’ or ‘B’ items have been identified.
Raising Maximo jobs must not be used to transfer contractor construction PL1 ‘B’ items.
All outstanding heat tracing and insulation will be controlled by PL1s.
Uncontrolled when Printed

Notes on Completion of Individual Certificates


Add 4-2 July 2009 Issue 4
Guidance on Certification UKCS-TI-019

Addendum 5
Additional Requirements or Replacement
Certificates for UKCS Use

Paragraph Page

1 JI1 Joint Integrity Certificate 1

2 EE18 Hazardous Area Equipment (Ex) Inspection


and Test Certificate 7
Uncontrolled when Printed

Additional Requirements or Replacement Certificates for UKCS Use


July 2009 Issue 4 Add 5-i/ii
Guidance on Certification UKCS-TI-019

This addendum contains supplementary requirements for this region, which have not yet been
incorporated into the global manuals and certificates.

1 JI1 Joint Integrity Certificate


The following certificate has been amended to capture more details on the assembling
and tightening of bolted joints.
For a usable version of this certificate, please click here.
Uncontrolled when Printed

Additional Requirements or Replacement Certificates for UKCS Use


July 2009 Issue 4 Add 5-1/2
Guidance on Certification UKCS-TI-019
Uncontrolled when Printed

Additional Requirements or Replacement Certificates for UKCS Use


April 2011 Issue 4/AM01 Add 5-3/4
Guidance on Certification UKCS-TI-019
Uncontrolled when Printed

Additional Requirements or Replacement Certificates for UKCS Use


April 2011 Issue 4/AM01 Add 5-5/6
Guidance on Certification UKCS-TI-019

2 EE18 Hazardous Area Equipment (Ex) Inspection


and Test Certificate
The following certificate has been introduced to record and confirm completion of initial
inspections of equipment in compliance with BS EN 60079 Electrical Apparatus for
Explosive Gas Atmospheres 1997, Part 17 Inspection and Maintenance of Electrical
Installations within Hazardous Areas (other than mines).
For a usable version of this certificate, please click here.

Project Title:
FORM EE18
Maintenance No:
SITE:
Work Pack No: SH1 No:
MC1 No:
SLD No: SHEET OF
Hazardous Area Equipment (Ex)
Inspection and Test Certificate
Uncontrolled when Printed

(Includes all electrical, instrument and telecommunication


equipment which is an ignition source potential in the event of a
hydrocarbon release.)

Location
Equipment Description

Description of Inspections and Tests Carried Out:


The initial detailed inspection of ‘Ex’ equipment as defined in IEC 60079-17 and GOC Section 9.0,
Procedures 9.15 and 9.19.
Note: This task should be carried out by suitably qualified compex personnel.
* delete as appropriate

Has the equipment passed the detailed Ex inspection criteria *Yes/No


(see GOC Section 9.0, Procedure 9.19, Tables 1, 2 and 3)
Tag Number:
Equipment Class
Equipment Sub-class
Manufacturer
Model Number
Serial Number
Asset Location
Ex Area
Environmental Category
Hazardous Area Classification
Equipment Ex Classification
Equipment Ex Gas Group
Equipment Ex Temperature Class
Equipment Ex Certification Body
Equipment Ex Certification Number
Equipment Ingress Protection
Access Requirement
Cable Entry Position
ATEX Certified
ATEX Notified Body
ATEX Equipment Category
ATEX Certification No
Remarks:

Completed By: Approved By:


Company:
Signature:
Print Name:
Date:
UKCSTI019_009

Additional Requirements or Replacement Certificates for UKCS Use


July 2009 Issue 4 Add 5-7/8
Guidance on Certification UKCS-TI-019

Addendum 6
Functional Certification Flowchart

Functional Certification Flowchart


FABRICATION ACTIVITIES FUNCTIONALITY CHECKING ACTIVITIES
JI1 Part A Complete – Data Carried Forward
JI1 Part B Complete – Data Carried Forward
MECHANICAL – GOC 2-7 MW1 MP1
PIPING JI1 SF1 SL1 JI1

VESSELS MV1 JI1 SL1 JI1


Uncontrolled when Printed

MACHINERY MM1 JI1 MM2 SL1 JI1 JI1 Part B

HANDLING
MH1 MH2 JI1 Part A
EQUIPMENT

HVAC MM1 SP2 JI14

MS2
MW1
STRUCTURAL MS1

ARCHITECTURAL AS1
JI1 Part C
SERVICES AS2

SS11
IRN Non-fabrication Activities SH1 PP1
PC13
NO
CONTROL – GOC 8 SP1
INSTRUMENTS FIRE AND GAS CC1 MC1
TELECOMMUNICATIONS SC1

ELECTRICAL – GOC 9 EE1


PL12 PL1 NP1
EE2
SC1
1
Note on SS1 Certificate EE3
2
Note on PL1 3
Note on PC1 Certificate
The System Safe Certificate Certificate If a 'NO' response to any of the
(SS1) facilitates the handover EE4 As part of the EE13 questions on the PC1 is noticed
of the system from the EE5 continual review EE14 then raise an unique PUWER
Operating Authority to the and clearance Punch List (PL1) and categorise
Construction Authority to EE6 process of agreed EE15 'A' and 'B' as appropriate.
confirm the system is isolated punch list items.
EE7 EE16
and is in a safe condition ready Carry existing 'B' 4
Note on JI1 Certificate
for construction to commence. EE8 items forward to EE17 All flanges, joints, compression
PC1 and SH1 stage. fittings or plugs in ported blanks,
EE9 EE18
in pipework containing process
EE10 hydrocarbons, diesel, process
chemicals, hydraulic fluids,
EE11
lubrication oil systems, water
EE12 injection, water re-injection must
be tagged and recorded on an JI1
EE18 certificate. Apply SL1 and JI1
Certificates.
Refer to GOC Piping Section for full details
VENDORS/
SUPPLIERS CONSTRUCTION COMMISSIONING OPERATIONAL
WORKS POWER DOWN POWER UP PHASE
Handover Management Control Installation Mechanical Testing
IRN: Inspection Release Note CC1: Control Completion Certificate SF1: System Flush
SS1: System Safe Certificate SL1: System Leak or Service Test
Electrical Installation
MC1: Mechanical Completion Certificate JI1: Joint Integrity Certificate
PL1: Punch List EE1: LV Cable Test Certificate MM2: Pre-operations Alignment
PC1: PUWER Compliance Certificate EE2: HV Cable Test Certificate MH2: Mechanical Handling Load Test
SH1: System Handover Certificate EE3: Switch Board and Bus-bar Test MS2: Architecural Completion
PP1: Plant Performance Certificate EE4: Circuit-breaker Test SP2: System Performance Tests
NP1: Non-performance Report EE5: Contactor Starter Test
EE6: Fuse Switch Test Control Testing
Mechanical Installation
EE7: Power Transformer Test SC1: System Control (Funtion) Test(s)
MW1: Welding Completion Summary EE8: Trace Heating Test SP1: System Performance Test (HIPs)
MP1: Piping Completion EE9: Current Transformer Magnetising Curve
Electrical Testing
MV1: Pre-operations Inspection EE10: Primary Injection Test
MM1: Machinery Installation EE11: Secondary Injection (General Relay) Test EE13: Electric Motor/Generator Test
MH1: Mechanical Handling Installation EE12: General Test Certificate EE14: Batteries/Battery Charger Test
MS1: Structural Completion EE18: Hazardous Area Equipment (Ex) EE15: Uninterruptible Power Supply (UPS) Test
AS1: Final Paint Completion Inspection and Test Certificate EE16: Lighting and Small Power Test
AS2: Final Coating/Insulation Completion EE17: Navigational Aids Test
UKCSTI019_007.ai

Functional Certification Flowchart


July 2009 Issue 4 Add 6-1/2
Guidance on Certification UKCS-TI-019

Addendum 7
Terms of Reference and Assurance Protocol

1 Terms of Reference
To view the Terms of Reference, please click HERE.

2 Assurance Protocol
To view the Assurance Protocol, please click HERE.
Uncontrolled when Printed

Terms of Reference and Assurance Protocol


July 2009 Issue 4 Add 7-1/2