Ukcs Ti Goc
Ukcs Ti Goc
Guidance on Certification
UKCS-TI-019
Guidance on Certification UKCS-TI-019
Contents
Paragraph Page
1 Terminology 1
2 Purpose 1
2.1 Risk Management 1
3 Scope 2
Uncontrolled when Printed
Contents (cont’d)
Paragraph Page
9 Certification Tracking 11
11 Audit 12
Uncontrolled when Printed
Figure
1 Handover Process Flowchart 5
2 Business Process Flowchart 7
3 Certification Requirements Flowchart 8
4 Technical Integrity Assurance for Multiple Concurrent Activities 10
1 Terminology
to Group
Shall Minimum requirement Approval of VP S&OR/SPU EA
stipulated at SPU/UK level
Should SPU/UK Best Practice or Approval of Site Manager/OIM
Recommended/Preferred option
2 Purpose
The objective of this document is to provide guidance on how to apply Guidance on
Certification (GOC) to suit maintenance and operational needs, activities managed by
Engineering, Modifications and Maintenance (EMM) contractors and respective manning
and management structures typically found on an operating facility.
3 Scope
This document applies to all North Sea Strategic Performance Unit (SPU) assets in the
UKCS and onshore in the UK.
Uncontrolled when Printed
The following main elements of the GOC process, as it is applied to maintenance and
operations, are addressed:
The TI assurance process and handover control gates
The business process flow (including prerequisites for GOC implementation)
Roles and responsibilities
Identification of certification requirements
GOC implementation for multiple scopes of work
Certification tracking and archiving
Training and coaching
Audit
The Job Officer will be responsible for ensuring that the Limits of Systems Handover
(LOSH), Discipline Certificates and Handover Certificates (SS1, MC1 and SH1) have been
specified for jobs which have been approved and scheduled in the Long Term Plan (refer
to Addendum 1).
In addition, he/she will:
Accept the SS1 prior to work commencing and ensure that all certificates are
correctly completed by the pre-designated responsible engineer/technician
Maintain the GOC database as appropriate
Ensure that the certification pack will guarantee TI
If an additional certificate is added to the certification package, the Job Officer will
ensure that the data is added to the database. The database will be updated on
completion of the task, after all signatures have been added to the certification.
FUNCTIONAL
SYSTEM
LIMITS OF SYSTEMS
IDENTIFY WORK CERTIFICATES CERTIFICATES
HANDOVER (LOSH)
UKCSTI019_001.ai
The planning phase ensures that all requirements have been fully defined and approved,
within the site Long Term Plan, and that the job is ready to execute.
The TI assurance phase ensures that the job is executed safely and is fully installed and
tested prior to energisation or introduction of hydrocarbons.
The three handover control gates are:
Safety: System Safe Certificate (SS1)
Installation: Mechanical Completions Certificate (MC1)
Ready to Operate: System Handover Certificate (SH1)
Objective: To define the key steps and responsibilities of GOC interaction and group responsibility
Job Office/Technician
Assigned Personnel
Department Head
Formal Meetings
Responsibility
Area Authority
Site Manager
Site Planner
Notes
Activity
Uncontrolled when Printed
Plan Workscope
Verify asset mnemonics and functional
1.1 systemisation compliance with GOC Annual confirmation review
and operations requirements
Perform Workscope
Identify certification requirement: GOC Functional Certification
2.1 Green Tower Certificates JI1, SL1 etc Flowchart (Addendum 7)
– Blue Tower Certificates MP1, CC1 etc
Measure Workscope
3.5 Complete Green Tower Energisation Test Ensure as-built drawings marked
Certificate and Punch List up if appropriate
Job Officer to decide upon GOC
3.6 Update GOC database database update method/
resource
Site Manager may delegate to
3.7 Complete System Handover Certificate SH1 Department Head to ensure
correct process has been applied
Improvements
UKCSTI019_002.ai
NO
DOES
ACTIVITY INVOLVE
BREAKING PRESSURE NO
CONTAINMENT, BREAKING CIRCUITRY
OR ADDING NEW
SOFTWARE?
YES
Uncontrolled when Printed
NO IS ACTIVITY MECHANICAL
ELECTRICAL AND
MANAGED BY BP DISCIPLINE –
CONTROL DISCIPLINES
(CORE CREW)? VESSELS AND PIPING
YES
PART OF POTABLE
EMERGENCY HYDROCARBON, WATER, HEAT/COOLING
IS ACTIVITY NO YES SHUTDOWN (ESD)/FIRE AND HYDRAULIC, METHANOL, NO NO
MEDIUM, SEAWATER, FIREWATER,
A MODIFICATION GAS (F&G) SYSTEM OR PROTECTION WATER INJECTION (WI), HIGH COMPRESSED AIR, LOW PRESSURE
SCOPE? SYSTEM (EXCLUDING PRESSURE (HP) N2, DIESEL (LP) N2, FOAM OR
FIELD DEVICES)? OR HELIFUEL? CHEMICALS?
YES
NO YES YES
YES
IS TASK MULTI-
USE FULL GOC
DISCIPLINE?
NO
UKCSTI019_003.ai
It is essential that each job activity is assessed on an individual basis, depending upon its
technical complexity and service.
(1) All modifications and/or work carried out under EMM contractor management will
use the GOC database and Full GOC (http://goc.bpweb.bp.com/) (and the
TI assurance flowcharts therein).
(2) BP-managed activities will utilise facility-specific mnemonics and the appropriate
GOC certification requirements of Figure 3.
(3) A TAR can be a combination of (1) and (2).
Maintenance Contractor
Most construction work on a site is managed through the EMM contractor and,
therefore, the EMM, construction and commissioning authorities must demonstrate that
TI has been achieved.
Full GOC is ideal for construction projects (both green and brown field) due to the way in
which it controls and monitors TI from the project SS1, through MC1, to completion and
SH1 (refer to http://goc.bpweb.bp.com/). This, along with the accessibility to the GOC
database, provides the necessary auditable trail which makes Full GOC the correct tool
to demonstrate that TI has been achieved.
The contractor must therefore use the Full GOC and apply the TI assurance flowcharts
defined therein.
DEFINE JOB
ACTIVITY
SCOPE OF WORKS
eg TAR
CONFIRM IN LONG
TERM PLAN
RISK ASSESSMENT
SCOPE
YES MANAGED BY NO
Uncontrolled when Printed
BP BUSINESS
UNIT (BU)?
REFER TO REFER TO
FULL GOC FULL GOC
FIGURE 3 FIGURE 3
** BP AND CONTRACTOR
CONCURRENT ACTIVITIES
IN THE SAME SYSTEM WITH
ONE SS1, MC1 UNDER A
SS1 SS1 SS1 SS1
COMMON SH1
IMPLEMENTATION
START-UP
UKCSTI019_004.ai
9 Certification Tracking
GOC certification will be tracked utilising the GOC database, which will be used for both
BP-managed and EMM contractor-managed workscopes.
It will be the responsibility of the Job Officer to raise and control certification associated
with the task that he/she is controlling. Initially, this will be carried out with coaching by
the GOC Site Focal Point until such time as individuals are competent to carry out this
task on a stand-alone basis.
The tracking of certification serves two purposes:
(1) To provide information of the current state of any particular task and to provide
Platform personnel, not directly involved with a particular task, with up-to-date
information regarding the task status.
Uncontrolled when Printed
It is the responsibility of the Job Officer to update the GOC database, at the end of
each shift, to reflect the certification status.
It is the responsibility of individuals, who are required to sign a certificate, to
ensure that they have contacted the Job Officer to sign the certificate(s) in
question prior to going off shift and under no circumstances are they to demobilise
leaving any certification unsigned.
It is the responsibility of the Job Officer to ensure that certification signatures
are obtained and that the GOC database and process is closed out, unless an
‘Assigned Person’, according to Figure 2, has been appointed to this function.
(2) To provide an auditable trail of all certification, Punch Lists and handover status.
The GOC database is constructed for the purpose of tracking certification and to
store information with regard to completed certification.
The method of archiving of hard copy certificates, as either electronic CD-ROM
files or hardback original certification dossiers, will form part of the documentation
strategy for the site. This must, however, comply with BP HSSE and technical
requirements, in addition to current legislation.
To ensure that personnel fully understand the process, the following will be carried out,
post-job implementation by the Site Focal Point:
A method of encouraging constructive feedback to be set up, to determine if the
process is working correctly and effectively
Regular TI meetings to be set up, to monitor progress
11 Audit
Periodic audits will be scheduled by the UKCS SPC and performed by QEDi and/or
others, to ensure that TI compliance is achieved and that GOC is being correctly
implemented.
The UKCS SPC shall manage quarterly review meetings with Site Focal Points and
Uncontrolled when Printed
QEDi, to ensure that lessons learned and improvements are captured and implemented.
QEDi shall ensure that all lessons learned and improvements are shared with BP
Global SPCs.
Addendum 1
Planning Process
1 Planning
Jobs appearing on the Long Term Plan will indicate if a Guidance on Certification (GOC)
certification pack is required. The Job Officer will ensure that a complete pack is
compiled prior to a task moving to the Short Term Plan. Jobs which occur after the Short
Term Plan has been issued will be added after the certification pack has been compiled.
The Job Officer will ensure that the certification pack details the correct Maximo
cross-references.
Uncontrolled when Printed
Jobs requiring certification, or without a certification pack, should not appear on the
3-day plan, unless it is a high priority job for which permission is given by the
Department Head.
The final review of a task at the permit meeting should determine if a job without a
required certification pack is to be allowed to go ahead.
2 Summary
No job requiring certification will be allowed to go ahead without permission of
management
Certification packs are to be compiled as a normal part of job planning
Priority 1 jobs will be treated on an individual basis dependent on the criticality
It should be noted that, in most cases, a certification pack can be compiled in less
time than the decision-making process takes.
Planning Process
July 2009 Issue 4 Add 1-1/2
Guidance on Certification UKCS-TI-019
Addendum 2
Mnemonics as Applied to
Maintenance and Operations
Guidance on Certification (GOC) mnemonics (mnemonics being the Greek word for memory)
detail the nine Primary ‘Functional’ Systems on any one facility. The nine Primary Systems can
be further sub-divided into a 2-digit Secondary System. A set of composite Piping and
Instrumentation Diagrams (P&IDs) or Single Line Diagrams (SLDs) detail the limit of each
Primary and Secondary System, therefore creating a ‘Road Map’ of the facility, detailing all the
‘A’ roads (Primary Systems) and all the ‘B’ roads (Secondary Systems).
Uncontrolled when Printed
By having this functional system map of the facility, BP can pinpoint exactly all of the
equipment to be worked upon and, equally important, identify all the Primary and Secondary
Systems that will be affected by the work. By knowing this data, BP can plan efficiently when
and how to carry out the work.
Systems are divided into Functional Systems, which then can be sub-divided into a 2-digit
Secondary System.
Handover Identifier
A 2 12 S 0139 +01
FACILITY MC1 No
UKCSTI019_005.ai
Addendum 3
Handover Limits as Applied to Modifications
routine or task, the maintenance routine or task will be linked to the Construction SH1 number
as previously described. Any maintenance work that is to be completed within the SH1
boundary will be captured by an MC1. The SH1 flowchart in Figure 1 demonstrates this
principle.
MODIFICATION
ISOLATIONS ISOLATIONS
CONSTRUCTION PROJECT
SYSTEM SH1 FOR SH1 BOUNDRY
MAINTENANCE TASKS
MAINTENANCE
CONSTRUCTION
TASKS SYSTEM 2
PROJECT (SH1)
MAINTENANCE SH1
UKCSTI019_006.ai
Addendum 4
Notes on Completion of Individual Certificates
In order to ensure that original Guidance on Certification (GOC) certificates for site maintenance
tasks can be easily used, the following manual changes can be undertaken:
Isolation Control Certificate Reference (ICC-xxxxx) can be inserted into any blank boxes or
comments field
main text) is very specific with regard to what/if GOC should be applied. Where no System
Safe Certificate (SS1)/System Handover Certificate (SH1) is required, mnemonics will be issued
and cross-referenced to the Maximo job card to provide a clear, auditable trail. Technicians
must ensure that a reference to the mnemonic number is entered on the job card.
A single PL1 will be used to cover all disciplines. As with Full GOC, all ‘A’ items will require
rectification prior to final commissioning; any outstanding ‘B’ items will be cleared from the PL1
by raising Maximo jobs to carry out the remedial work (http://goc.bpweb.bp.com/).
All disciplines will sign the PL1; if no items are found within a particular discipline, the PL1 will
read ‘No Items Found’ or similar, to indicate that the work carried out has been reviewed and
that no ‘A’ or ‘B’ items have been identified.
Raising Maximo jobs must not be used to transfer contractor construction PL1 ‘B’ items.
All outstanding heat tracing and insulation will be controlled by PL1s.
Uncontrolled when Printed
Addendum 5
Additional Requirements or Replacement
Certificates for UKCS Use
Paragraph Page
This addendum contains supplementary requirements for this region, which have not yet been
incorporated into the global manuals and certificates.
Project Title:
FORM EE18
Maintenance No:
SITE:
Work Pack No: SH1 No:
MC1 No:
SLD No: SHEET OF
Hazardous Area Equipment (Ex)
Inspection and Test Certificate
Uncontrolled when Printed
Location
Equipment Description
Addendum 6
Functional Certification Flowchart
HANDLING
MH1 MH2 JI1 Part A
EQUIPMENT
MS2
MW1
STRUCTURAL MS1
ARCHITECTURAL AS1
JI1 Part C
SERVICES AS2
SS11
IRN Non-fabrication Activities SH1 PP1
PC13
NO
CONTROL – GOC 8 SP1
INSTRUMENTS FIRE AND GAS CC1 MC1
TELECOMMUNICATIONS SC1
Addendum 7
Terms of Reference and Assurance Protocol
1 Terms of Reference
To view the Terms of Reference, please click HERE.
2 Assurance Protocol
To view the Assurance Protocol, please click HERE.
Uncontrolled when Printed