0 ratings0% found this document useful (0 votes) 239 views5 pagesEot Claim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
We use cookies to ensure we glve you the best experience on our website, You can find out about our cookies and how to disable cookies in our Privacy
Policy. Ifyou continue to use this website without disabling cookies, we will assume you are happy to receive them. Close.
Designing Buildings Wiki
Share your construction industry knowledge
www designingbuidings.co.uk
IHBC pe
Last edited 20 Jul 2021
Variations in construction contracts
Contents
1 Introduction
| 2 Valuation of variations
3 Source of confit
4 Extension of time
| 5 Conelusion
|B 6 Related articles on Designing Buildings Wiki
7 External references
Introduction
‘A vatiation (sometimes referred to asa variation instruction, variation order (VO) or change
Corder), is an alteration to the scope of works in @ construction contract inthe form of an
‘adktion, substitution of omission from the original scope of works.
‘Atmost al construction projects vary rom the original design, scope and defntion, Whether
‘small or large, construction projects will inevitably depart from the original tender design,
specifications and drawings prepared by the design team.
This can be because of technological advancement, statutory changes or enforcement, change
In conditions, geological anomalies, non-avallabllty of speciied materials, or simply because of
the continued development ofthe design after the contract has been awarded. In large civil
engineering projects variations can be very significant, whereas on small building contracts,
they may be relatively minor.
Variations may incude:
Alterations tothe design
‘Alterations to quanties.
Alterations to quay
‘Alterations to warking conditions
1H Alterations tothe sequence of work
Variations may also be deemed to occur the contract dacuments do not propery describe the
works actually required.
Related articles
Extension of ime EOT in construction
contracts
Architoets instruction
Campaign for cash retentions reform.
Change order for construction contracts
Alterations to existing buildings
Prime cost sum
Liquidated damages in construction contracts,
Construction contract
Want complements o
writing?
complimeVariations may not (witout the contractors consent)
Change the fundamental nature ofthe works.
(Omit work so that it ean be carried out by anther contractor.
Be instructed atter practical completion
Require the contractor to cary out work that was the subject of a prime cost sum.
Inlegal terms, a variation is an agreement supported by consideration to alter some terms of
the contract. No power to order variation fs implied, and so there must be express terms in
Contracts which give the power instruct variations. In the absence of such express terms the
contractor may reject instructions for variations without any legal consequences.
‘Standard forms of contract generally make express provisions forthe contract administrator
(generally the architect or engineer) to instruct variations (for example, FIDIC Clause 51.1).
‘Such provisions enable the continued, smooth administration of the works without the need for
another contract,
Variation instructions must be clear as to what is ands not included, and may propose the
‘method of valuation.
Valuation of variations
Variations may give ris to additons or deductions from the contract sum. The valuation of
‘variations may include not just the work which the variation instructon describes, but other
‘expenses that may result from the variation, such as the impact on other aspacts of the works.
Variations may also (out not necessarily) require adjustment of the completion date.
Variations may be valued by:
‘Agreement between the contractor and the client.
The cost consultant.
‘A atlaton quotation prepared by the contractor and accepted by he cent
By some other method agreed by the contractor and the cent.
Valuations of variations are often based on the
les and prlces provided by the contractor In
‘heir lender, provided the workis ofa similar nature and carted out in similar conditions. This
's true, even ftbecames apparent that the rates provided by the contractor were higher or
lower than otherwise available commercial rates,
‘The contractor's rates do nol become reasonable or unreasonable by the execution of
variations, as stipulated by the ruling in the case of Henry Boot Construction Lid v Alstom
(1999),
If simitar types of works to those instructed by a variation cannot be found in the drawings,
specification or bils of quantities, then fair valuation ofthe contractor's direct costs, overheads
‘and proftis necessary
However, NEC contracts do not value variations based on rates in the tender. Guidance on
assessing compensation events states:
‘Assessment of compensation events as they affect Prices is based on their effect on Defined
Cost plus the Fae. This is diferent from some standard forms of contract where variations are
valued using the rates and prices in the contract as a basis. The reason for this polley is that no
‘compensation event for which a quotation is require is due to the fault of the Contractor or
‘olates to a matter whichis at his risk under the contract. tis therefore appropriate to
reimburse the Contractor his forecast addtional costs (or actual costs i the work has already
been done) arising from the compensation event,
Featured articles and news
"Newsnight report - Trapped: the UK's building
safety esis
CCIOB responds to programme broadcast on 2
September 2021,
Remotely piloted aircraft
Using drones for inspection and survey of
historic structures,
Seaside piersIn other words, the contractor can ignore thei tender pricing and claim cost plus on vaiatons. 7
However, there may be cisagreements about ems suchas factory overheads and THE ARCHITECTURE
‘management which ae very hard o evaluat. In adston, given the complexty and length of OF BRITISH
‘he supply chain in major buldng works, getting forecast pricing from athe partes afected
takes time, often beyond the date by which the contract administatr has to make the decsion
as to wheter or nt instruct the variation
They may then have to decide whether or not to proceed witha variation based on estimates
‘rom the cost consultant which in due course get replaced by the actual cost. thas been
argued that this practicality defeats the some of the rationale ofthe NEC contracts in relation to
cost control and decision making,
Source of conflict
Conflict can arise when work is not mentioned in the bills of quantities, drawings or
specifications. In common law this silence does not mean the contractor has an automatic right
te claim for extra payment. The client is not bound to pay for things that a reasonable
Contractor must have understood were to be done but which happen tobe omitted from the
bills of quantities,
Walking on water. Book review.
Where there are tems that, whist thay are not expressly mentioned, are nonetheless required EWS! guidance from CIAT
in order to complete the works, then the contractor should have included them in thet price
‘The bills of quantities and specification do not necessary have to inlude ‘every nal to be
punched in: For example, in king GRC facades itis necessary to have steel supports, and a
reasonably experienced contractor must make provision for this in the contract price. Unless
‘expressly excluded, such supports are not paid for asa variation.
Conflict can also arse when a sub-contractor qualifies that, for example, ‘Supply & Fixing of
oor is included! but ‘Supply & Fixing of Ironmongery is excluded! A reasonable sub-contractor
should foresee that a door cannot be fixed without hinges — which is a part of the ironmongery.
‘So even if ronmongery is excluded, the sub-contractor cannot expecta variation for any ofthe
items requited to fix the doors,
Pil coverage recommendations offered to
architectural technologists
|Also, under the pretext of variation, the contract administrator cannot change the nature of
‘works. For example, ifthe contract provides for secant pile shoring, they cannot ask for
siaphragm wall sharing as it wll entirely change the nature ofthe work Burrell Collection reapens in March
Further, ifthe contract administrator omits work from contractor's scope, such an omission
‘must be genuine: thats, the work omitted must be omitted from the contract entirely, it cannot
be used to take work away from the contractor to give it to another (for example, see FIDIC
Clause 51.1) Similar, the contract administrator is not empowered to order variations to help
‘he contractor ifthe contract works are proving too dificult or expensive for ther.
Extension of time
Many construction contracts alow the construction period to be extended where there are
delays that ae not the contractor's fault, This is described as an extension of time (EOT).
£68 millon refure nears completion.
Variations may (but do not necessarily) constitute relevant events that can merit an extension ‘high road! skits dovelopment
of time and so adjustment of the completion date. See Extension of ime for more information.
ConclusionVariations are often sources of clsoute, elther in valuing the variation, or agreeing whether part
of the works constitute a variation at all, and can cost a lat of time and money during the
course of 8 contract. Whilst some variations are unavoidable, itis wise to minimise potential
variations and subsequent claims by ensuring that uncertainties are eliminated before
‘awarding the contract.
This can be done by:
= Undertaking thorough site investigations and condition surveys,
Ensuring thatthe project brief is comprehensive and is supported by stakeholders.
Ensuring that legislative requirements are properly integrated into the projec.
Ensuring that risks are properly identified.
Ensuring that designs are properly coordinated before tender.
Ensuring the contract ls unambiguous and expt
Ensuring the contractors rates are clear.
1B Preparing concise drawings, bills of quantites and specifications, providing fo all situations
‘hich are reasonably foreseeable,
pI} ¢-134
PMI'S GUIDE to
Strategic Ris!
Management
read
Related articles on Designing Buildings Wiki
Extension of time EOT in construction contracts
Architects instruction
‘Campaign for cash retentions reform.
Change order for construction contracts
‘Alterations to existing buildings
Prime cost sum
Liguidates damages in construction contracts,
Construction contract
Change control procedure for building design and construction
‘Compensation event
Aborive workin building design and construction
Payment for extra work
Bil of quantities BOQ
Confirmation of verbal instruction
‘Scope of work
Dayworks in construction
How to prepare a claim for an extension of time
Contract sum
FIDIC
Loss and expense
Contract documents for construction
Relevant event
Fluctuations in construction contracts
Valuation
Valuation of interim payments
External references
= The JCT 05 Standard Building Contract: Law and Administration By Issaka Ndekugr,
Michael Rycrot
Investing in talent through ongoing training
Demolition, infting and historic ral structures.
Proposing more sensiive treatment of outdated
infrastructure.
Enhancing user experience with assisted realty
Ths handsfree technology projects information
into the user's fel of vision
PAS 2038 and historic buildings
How the standard will impact energy retrofits for
older buildings.
Construction Knowledge Task GroupHow digital krowedge can catch up with data
{and information.
‘See more features and news,
© Designing Buildings Ltd, 2021