BILL B - Infrastructure
BILL B - Infrastructure
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Notes :
1. The amount of excavation is given as a provisional
quantity. The actual amount shall be measured by
Meridian Survey and paid by Contractor. The amount
measured shall be final
Earthworks
1.2 Cut, fill and compact from existing ground level and
slope including preparation of surfaces, trim to level,
well rolled, consolidated, remove top soil and deposit
in spoil heaps within the site as directed by the
Engineer
m3 59,000
m2 21,500
1.5 Filling
Provisional for Import, fill, spread and compact
approved excavated materials to fill ground level as
shown on the drawing or as directed by the S.O.
Rate to include haulage of excavated materials and
forming benches to fill embankment m3 1000
TO COLLECTION RM
B - 1/37
OPTION 1
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
TURFING
Supply and lay turfing with approved turf of not less
than 200mm square and laid at 380mm centers both
ways from approved source. Rate to including all
necessary surface preparation, vegetable soil,
watering, tending, caring, protection and maintenance
a
Gravel Carpark
Supply, lay, spread 50mm thick sand blanket and
300mm thick compacted approved gravel for gravel
carpark. m2 7,000
External road
a) 75mm thick binder course and 50mm thick wearing
course including a layer of tack coat m2 6,150
TO COLLECTION RM
B - 2/37
OPTION 1
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Road Kerbs
2.2 Precast concrete kerb grade 20 c/w discharge opening
together with 230mm concrete pipe at every 5m
interval as per drawing. Prepare and apply one coat
alkali resisting and 2 coats of emulsion paint of black
and white colors alternately at 600mm length to sides
and on top of kerb
m 4,000
TO COLLECTION RM
B - 3/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
b) Stop at intersection no 5
c) T-Junction no 5
d) No-Entry no 5
e) Give way no 2
f) Road Narrows no 2
g) Chevron no 1
e) Others no 20
Sign Board
2.5 To supply and install double sided road sign board
with overall height of 1500mm. Rate to include
excavation, backfilling, concrete foundation,
formwork and etc, including M.S. hollow 62.5mm x
62.5mm Galvanised Hot Dipped (grey finishes).
no 10
B - 4/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Note :
1. All pipes at road crossing shall be Mild Steel pipe
with concrete lining internally and bitumen coating
externally. Size equivalent to connect with HDPE
pipe. Rate to include supply and lay the MS pipe
complete with sand surround as per detail.
B - 5/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
S-Bend
3.5 Ditto 150mm ND M.S pipes PN16 for exposed pipe No 5
(S-bend). Rate to include 50mm ND Double Orifice
Air Valve c/w isolating valve as per drawing. Rate to
include subsequent painting with approved SAJH
paint. Ditto.
B - 6/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
B - 7/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Water Meter
3.12 Supply and install one (1) set of approved SAJH water L.sum
meter complete with 150mm ND D.I pipeworks,
strainer, 2 nos of sluice valve, coupling, adaptors,
fittings (etc bends, tee, taper), thrust block, all
accessories as detail in the drawings. Rate to include
all testing and etc.
Pipe Marker
3.13 Concrete pipe marker at every 100m interval complete No 35
including all excavation and backfilling as detail
shown in the drawing
Miscellaneous
3.17 Supply 750mm long galv. MS tee key for operate No 2
valve
B - 8/37
OPTION 1
TO COLLECTION RM
Reinstatement
3.18 Reinstatement of existing metalled road as per detail M 200
PIPE JACKING
3.19 Design, liaise with approval authority, excavate, L.sum
construct, maintain jacking and receiving pits
including sheet piling,bracing, wailing, concrete thrust
wall, anchor foundation, guide rails, etc. for jacking
the pipes efficiently and safely.
3.21 Supply, deliver, install and weld external collar joint for m 12
150mm dia MS pipe and carry out 100% ultrasonic
scanning of welding at joint. Rate to include supply
of collar and all necessary accessories.
3.22 Excavate in all materials other than rock within the jacked L.sum
pipes, remove and dispose off the site to approved tips.
B - 9/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
m 600
Manhole
4.2 Supply and construct the following approved JPP
sewer manhole c/w cover. Rate to include all
necessary excavation, backfilling, precast R.C.
manhole, concrete base, lean concrete, reinforcement,
heavy duty ductile iron frame and cover, stainless steel
steps and all details as per drawing and as per
specification:-
B - 10/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Brickwall To Drain
5.10 Supply and construct 230mm thick to brickwall to
both sides of precast concrete drain to match the
ground level. Rate to include 75mm diameter PVC
weep hole with rubble packing 1525 centre to centre
(bothsides), plastering, 125mm x 125mm concrete
struts 1500 centre to centre and other necessary works
as per drawing
m2 2000
B - 11/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Brick sump
5.13 Construct and complete varies type and size of
bricksump. Rate to include all labour, excavation, lean
concrete, Grade 25 concrete, reinforcement, Class F2
formwork, Class U2 finish concrete, bricks, 20mm
thick plastering on exposed surfaces, galvanised M.S.
step iron, galvanised mild steel grating, forming of
rebate and all necessary materials as shown on the
drawing.
no 80
Wingwall
5.14 Supply, lay & construct 225mm thk x 300mm height
brickwall with 20mm thick cement render no 30
Rubbish Trap
5.15 To supply and install rubbish trap at the drainage brick
sump outlet discharge, compised of 20mm dia. M.S.
bars welded at 50mm c/c, 10mm thk x 50mm wide
m.S. plate at 450mm c/c max c/w 13mm dia. Holes,
10mm thk x t5mm wide M.S. flat plate to be suit on
site and as per specification.
no 5
c) 900mm (b) x 900mm (h) not exceeding 3.5m deep m Rate Only
c) 900mm (b) x 1200mm (h) not exceeding 3.5m deep m Rate Only
B - 12/37
OPTION 1
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
RC Pipe Culvert
5.17 Supply, lay and joint complete 450mm diameter rc
pipe culvert class 'Y' including spigot and socket,
jointing with rubber ring to required level gradients
c/w well-compacted hardcore, 50mm thk lean
concrete, 150mm thk reinforced concrete bedding with
one layer of BRC A7, 230mm thk haunched, all
including excavation and backfilling, cement mortar
plaster, jointing, bends, junction, connections and etc.
as per drawing and spesification
m 120
m 300
B.7 OTHERS
7.1 Other item not mentioned above but stated in drawing
and necessary to complete the works
a. ……………………………………
b. ……………………………………
c. ……………………………………
d. ……………………………………
e. ……………………………………
B - 13/37
OPTION 1
TO COLLECTION RM
PAGE………………..B - 1/14 RM
PAGE………………..B - 2/14 RM
PAGE………………..B - 3/14 RM
PAGE………………..B - 4/14 RM
PAGE………………..B - 5/14 RM
PAGE………………..B - 6/14 RM
PAGE………………..B - 7/14 RM
PAGE………………..B - 8/14 RM
PAGE………………..B - 9/14 RM
PAGE………………..B - 10/14 RM
PAGE………………..B - 1114 RM
PAGE………………..B - 12/14 RM
PAGE………………..B - 13/14 RM
B - 14/37
OPTION 1
B - 15/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
PAGE………………..B - 1/14 RM
PAGE………………..B - 2/14 RM
PAGE………………..B - 3/14 RM
PAGE………………..B - 4/14 RM
PAGE………………..B - 5/14 RM
PAGE………………..B - 6/14 RM
PAGE………………..B - 7/14 RM
PAGE………………..B - 8/14 RM
PAGE………………..B - 9/14 RM
PAGE………………..B - 10/14 RM
PAGE………………..B - 1114 RM
PAGE………………..B - 12/14 RM
PAGE………………..B - 13/14 RM
B - 16/37
B - 17/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
TO COLLECTION RM
B - 18/37
TO COLLECTION RM
B - 19/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Road Kerbs
B Supply and fix complete precast concrete G20 road as M 5,000
per drawings and/or approved design by the local
authorities. Rate to include round opening at every
6m, concrete bedding, setting, jointing, painting, etc
and including discharge pipe to nearest drain/
TO COLLECTION RM
B - 20/37
TO COLLECTION RM
B - 21/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
TO COLLECTION RM
B - 22/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Pillar Hydrant
C Supply and install pillar hydrant including, flanged No 10
extension pipe, r.c. duct foot bend and all necessary
accessories, excavation and disposal
Pipe Crossing
D Supply and lay M.S Pipe sleeves for crossing the
track/metalled road .
a) 200mm dia. MS Pipe M 50
b) 350mm dia. MS Pipe M 50
Water Meter
E Supply and install water meter including all necessary No 8
jointing and connection and paying all fees and
charges on connection as required by the local
Authorities for the installation
Pipe Marker
G Concrete pipe marker at every 50m interval complete No 35
including all excavation and backfilling as detail
shown in the drawing
TO COLLECTION RM
B - 23/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Manhole
B Supply and construct the following sewer manhole c/w
cover. Ratedepth
a) Manhole to include all necessary
not exceeding 2M depth excavation, No 7
backfilling, precast R.C. chamber,
b) Ditto, exceeding 2M but not exceeding concrete base,
3M depth No 3
heavy duty ductile iron frame and cover, stainless
c) Ditto,
steel stepsexceeding 3M but
and all details not drawing
as per exceeding 4Masdepth
and p No Rate Only
d) Ditto, exceeding 4M but not exceeding 5M depth No Rate Only
e) Ditto, exceeding 5M but not exceeding 6M depth No Rate Only
f) Ditto, exceeding 6M but not exceeding 7M depth No Rate Only
B - 24/37
TO COLLECTION RM
B - 25/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Brick sump
B Construct and complete varies type and size of No 70
bricksump c/w mild steel grating cover. Rate to
including excavation and backfilling, concrete base
with reinforcement and plastering to expose surfaces
as per detail drawing.
Rubbish Trap
C To supply and install rubbish trap at the drainage brick No 5
sump outlet discharge, compised of 20mm dia. M.S.
bars welded at 50mm c/c, 10mm thk x 50mm wide
m.S. plate at 450mm c/c max c/w 13mm dia. Holes,
10mm thk x t5mm wide M.S. flat plate to be suit on si
TO COLLECTION RM
B - 26/37
TO COLLECTION RM
B - 27/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Culvert
F Supply and lay r.c. culvert including concrete base and
surrounding, excavation and backfilling works
a) 900mm diameter M 20
b) 1200mm diameter M 20
B.6 TURFING
A Supply and lay turfing with approved turf of not less
than 200mm square and laid at 380mm centers both
ways from approved source. Rate to including all
necessary surface preparation, vegetable soil,
watering, tending, caring, protection and maintenance
a
B - 28/37
TO COLLECTION RM
B - 29/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Brick Fence
B Construct one brick thick 2.10M height brick fence M 2,000
complete with plaster and paint on both sides
including all necessary r.c. footing, excavation and
backfilling all as per detail drawing.
Main Gate
D Supply and install G.I. main entrance gate overall size No 1
6000mm x 2100mm high with G.I. Post, r.c. footing,
barrel bolt and all necessary accessories including
painting works
B - 30/37
TO COLLECTION RM
B - 31/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
B.12 OTHERS
A Other item not mentioned above but necessary to
complete the works
a. ……………………………………
b. ……………………………………
c. ……………………………………
d. ……………………………………
e. ……………………………………
TO COLLECTION RM
B - 32/37
TO COLLECTION RM
B - 33/37
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
PAGE………………..B - 1/10 RM
PAGE………………..B - 2/10 RM
PAGE………………..B - 3/10 RM
PAGE………………..B - 4/10 RM
PAGE………………..B - 5/10 RM
PAGE………………..B - 6/10 RM
PAGE………………..B - 7/10 RM
PAGE………………..B - 8/10 RM
PAGE………………..B - 9/10 RM
B - 34/37
B - 35/37
Bill Unit Length Width Depth Qtty Note
B1 M2 270 300 81000
M3 270 300 0
M2 270 300 81000
R/O
B2 M2 120 12 1440 entrance
300 8 2400 main road
110 8 880 stp
160 8 1280 tnb
100 8 800 surau
140 50 7000 parking (blok utama)
90 25 2250
60 50 3000 parking (dewan makan)
40 40 1600
60 8 480
21130
M 200 200 entrance
170 170 round about
280 280 parking (blok utama)
80 80
730
M 48 48 entrance
480 480 parking (blok utama)
224 224
352 352
145 145
585 585 parking (dewan makan)
1834
B3 NO 9 9
B6 M2 300 100 30000
300 10 3000
40 40 1600
90 30 2700
90 30 2700
37300
M2 25 5 125
15 10 150
15 15 225
30 5 150
650
53 5 265
26 5 130
23 5 115
15 5 75