Commisioning Report-Dx/Package: Project Villa No. & Type Location Report Date Customer Comm. Date

This commissioning report summarizes the installation and testing of a new HVAC system at a villa. It documents the equipment details, pre-commissioning checks including leak and vacuum tests, and electrical inspection results. Upon completion of testing, the contractor signs off to certify that the installation meets Daikin standards.

Uploaded by

Mohammed Javid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
702 views1 page

Commisioning Report-Dx/Package: Project Villa No. & Type Location Report Date Customer Comm. Date

This commissioning report summarizes the installation and testing of a new HVAC system at a villa. It documents the equipment details, pre-commissioning checks including leak and vacuum tests, and electrical inspection results. Upon completion of testing, the contractor signs off to certify that the installation meets Daikin standards.

Uploaded by

Mohammed Javid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

COMMISIONING REPORT-DX/Package

PROJECT VILLA NO. & TYPE


LOCATION REPORT DATE
CUSTOMER COMM. DATE

Equipment's Details Pre Commissioning Details


Location Total Pipe Length (m)
Outdoor/ Package Unit Model No. Vertical Pipe Length (m)
Outdoor / Package Unit Serial No. Nitrogen Pressure Test Readings for 24 Hours
Indoor Unit Model No. Leak Test Result ( OK / NG )
Indoor Unit Serial No. Vacuum of the System ( Yes / No )
Piping Connections (Liquid / Gas) Additional Gas Charge ( if applicable)
General Inspection Electrical Inspection
Ambient Temperature ( ̊C) Rated Voltage (V)
Supply Air Temperature ( ̊C) Actual Voltage (V)
Room Temperature ( ̊C) Rated Ampere (A)
Running Fan Speed ( H/M/L/Auto) Actual Ampere (A)
High Pressure Readings (PSIG) Electrical Cable Size
Low Pressure Readings (PSIG) Electrical Breaker Rating (A)
Ventilation Space for ODU(OK/NG)
Remarks

Thermostat Set Point = _____ ̊C

Tadmur -Seyana

SIGNATURE :

NAME :
DATE :
* By signing this Commissioning sheet, the contractor/installer certifies that the installation is based on Daikin Standard installation and practice. Daikin reserves the right
to void warranty in case there is any discrepancy on the information
* Field Electrical Safety components such as ELCB/RCCB are responsibility of the installer and should be installed to avoid risk of fire or human injury.