Main Trailer Setup: Iwp Installation Work Package 020

Uploaded by

HowardWright
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
464 views9 pages

Main Trailer Setup: Iwp Installation Work Package 020

Uploaded by

HowardWright
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

GE Power & Water

Distributed Power TM2500+

IWP INSTALLATION WORK PACKAGE 020


MAIN TRAILER SETUP
Effectivity: TM2500+ / Gen VI & VII

PURPOSE & SCOPE:


This work package provides instructions for positioning & setup of the Main Trailer prior to
installation of equipment, including foundation preparation; trailer positioning, elevation and
leveling; turbine platform support adjustments; and trailer grounding.

DURATION:
1 day (based on 10 hour days)
* Number of personnel and duration may vary with skill level, productivity, and site conditions.

RECOMMENDED PERSONNEL:
• GE Mechanical TA • 2 Mechanics
• Truck Driver • Forklift Operator
• 2 Riggers • 2 Helpers

RECOMMENDED TOOLS, MATERIALS, & EQUIPMENT:


• Air‐Ride Trailer Truck • Standard Forklift
• Transit & Level • Support for Elevated Work (up to 15’)
• Hydraulic Jack Rams (50t/portable) • Mechanical Hand Tools (US & Metric)

REFERENCE DOCUMENTS:
751200 – General Arrangement, Main Trailer 751202 – Plot Plan, Trailer Mount
751222 – Foundation Loading, Main Trailer 751294 – Interface Drawing, Main Trailer
TP1000 – Trailer Transport Instruction

©2014, GE Power & Water – Distributed Power – Aero Energy. All Rights Reserved.
This document is the proprietary property of GE Aero Energy, and is loaned in strict confidence, with the understanding that it will not be
reproduced, nor used for any purpose except that for which it is intended. It shall be immediately returned on demand, and is subject to all
other terms and conditions of any written agreement or purchase order which incorporates or relates to this document.
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

Figures 1, 2 and 3: Main Trailer Configurations

IWP020_Rev.1.0 Page 2 of 9
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

A FOUNDATION PREPARATION Initials / Date


Verify the foundation has been prepared to receive the main trailer.
Reference drawings:
1
‐ 751202 – Plot Plan, Trailer Mount and;
‐ 751222 – Foundation Loading, Main Trailer
2 The foundation must be clean, level, and allow for proper drainage.

Figure 4: Landing Gear Support Locations (On‐Site Positioning)

Figure 5: Landing Gear Station Identification

IWP020_Rev.1.0 Page 3 of 9
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

B TRAILER POSITIONING Initials / Date


NOTE: The truck must remain on‐site until trailer positioning and elevation are complete.
Move the main trailer into position on the foundation in accordance
1
with the site plan.
Ensure the landing gear support locations are clean, flat, level and
2
sufficient to handle the loads.
Position the (10) landing gear support blocks underneath each
3
landing gear.

NOTE:
LANDING GEAR SUPPORT BLOCKS
It is recommended that a support block 8” to 10” thick be placed under each landing gear to minimize
travel. Minimal extension of the landing gear improves their support strength.
If the landing gear support blocks are not supplied by GE, they must be fabricated in accordance with GE
specifications.

Figure 6: Landing Gear Support Block

IWP020_Rev.1.0 Page 4 of 9
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

C TRAILER ELEVATION & LEVELING Initials / Date


NOTE: Reference TP1000 – Trailer Transport Instruction for on‐site positioning and setup
instructions prior to performing leveling procedures, including Jeep, Stinger, and Gooseneck
removal, and instruction on how to operate pneumatic systems and landing gear.
1 Uncouple and remove the Stinger.
2 Lower the trailer and remove the rear axle suspension pins.
Raise the trailer, until the generator support pads are at a nominal
3 height greater than 73” (± ½”), and the turbine enclosure support
pads are at a nominal height greater than 51” (± ½”).
Lower the landing gear onto to the support blocks at Stations #1, #2,
#3 and #4 using the high gear crank.
4
Continue loading the landing gear by rotating five more turns using
the low gear crank until they take up weight.
Lower the landing gear at Station #5 until they are fully loaded.
5 Continue loading the landing gear by rotating five more turns using
the low gear crank until they take up weight.
Verify that the Station #1, #2, #3, and #4 pads are still level and within
6
tolerance.
7 Bleed the air brakes (first) and the air bags (last).
8 Uncouple and remove the Jeep and Gooseneck.

CAUTION:
RAISING THE TRAILER
UNDER NO CIRCUMSTANCES SHOULD THE LANDING GEAR BE USED TO RAISE THE TRAILER. THE
FUNCTION OF THE LANDING GEAR IN THIS APPLICATION IS TO SUPPORT THE TRAILER ON‐SITE, AND
PERFORM LEVELING DURING GAS TURBINE‐GENERATOR ALIGNMENT. THE TRAILER AIR SYSTEM MUST
BE USED FOR ALL HEIGHT ADJUSTMENTS.
LANDING GEAR ADJUSTMENTS MUST BE MADE IN EQUAL LEFT‐RIGHT MOVEMENTS.
EQUIPMENT DAMAGE HAZARD
BLEED THE AIR BRAKES PRIOR TO BLEEDING THE AIR BAGS. IF THE AIR BAGS ARE BLED WHILE THE
BRAKES ARE STILL PRESSURIZED, THE TRAILER MAY “JUMP” FORWARD, AND BEND OR BREAK THE
LANDING GEAR.

IWP020_Rev.1.0 Page 5 of 9
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

D TURBINE PLATFORM TRANSIT MOUNT Initials / Date


During transit, the turbine platform is supported by the forward
transit mount and the turbine‐generator platform clevises.
The transit mount helps absorb shock encountered on the roadways.
1 Shims should be removed prior to transit, to allow the springs to
actuate.
Once on site, the turbine platform is supported by (4) wedge‐block
fixator mounts.

Figure 7: Turbine Platform Transit Mount

IWP020_Rev.1.0 Page 6 of 9
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

E TURBINE‐GENERATOR PLATFORM CLEVIS Initials / Date


Install and tighten the locking bolts in the turbine‐generator platform
clevis, as illustrated below.
These bolts must be removed during trailer transport to permit
flexing at the clevis.
1
The vertical, fore and aft, and lateral jackscrews in the clevis are
adjusted during turbine‐generator alignment.
Following final alignment, install shims in the clevis as required to
prevent misalignment.

Figure 8: Turbine‐Generator Platform Clevis

IWP020_Rev.1.0 Page 7 of 9
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

F TURBINE PLATFORM FIXATOR MOUNTS Initials / Date


Install (4) wedge‐blocks and shims at the right and left, forward and
aft corners of the turbine platform.
1 Tighten the wedge blocks to prevent vertical movement of the
platform. Further adjustments to shimming may be required during
alignment.
NOTE: Use 50 ton jack rams for installation of shims.
Once the turbine enclosure is being supported by the fixators,
2
remove shims from the forward transit mount.

Shims
Wedge Block

Figure 9: Turbine Platform Fixator Mount

G TRAILER GROUNDING Initials / Date


Ensure the Main Trailer is properly grounded. Reference:
1
‐ 751200 – General Arrangement, Main Trailer for details.

IWP020_Rev.1.0 Page 8 of 9
IWP020 TM2500+ Installation
Main Trailer Setup & Commissioning Manual

NOTE:
RECEIVING & INSPECTION
MISSING OR DAMAGED ITEMS MUST BE IDENTIFIED EARLY SO THEY CAN BE ORDERED AND POSSIBLE
PROJECT DELAYS ARE AVOIDED.
FAILURE TO SUBMIT THE OSD&D REPORT AND ANY WARRANTY CLAIMS MAY CAUSE DELAYS IN RECEIPT
OF REPLACEMENT COMPONENTS AND MAY IMPACT THE PROJECT SCHEDULE.

H PUNCH LIST UPDATE Initials / Date


1 Record any Punch List items identified during this work package.

WORK PACKAGE COMPLETION


Comments:

Project Name Unit Number

Start Date Completion Date

Contractor Representative Customer Representative GE Representative


Printed Name: Printed Name: Printed Name:

Printed Title: Printed Title: Printed Title:

Initials/Date: Initials/Date: Initials/Date:

Signature: Signature: Signature:

IWP020_Rev.1.0 Page 9 of 9