Method Statement Document
Method Statement
for
HV Cables Relocation at
Multi Storey Car Park Building at BWTC
Complex
Multi Storey Car Park Building at
Project Title:
BWTC Complex
Contractor: Dadabhai Construction
Document Title: Method Statement
Document Reference: JAH-S-EL-MS-005/Revision 00
Date: 10 October 2021
JAH-S-EL-MS-005 Revision 00 P a g e 1|5
Method Statement Document
TABLE OF CONTENTS
SECTION TITLE PAGE
1 INRODUCTION 3
2 SCOPE OF WORK 3
3 LOCATION 3
4 REFERENCES 3
5 RESOURCES 6
5.1 MANPOWER 6
5.2 MATERIALS 6
5.3 TOOLS & EQUIPMENTS 6
6 SEQUENCES/STAGE OF WORK 7
JAH-S-EL-MS-005 Revision 00 P a g e 2|5
Method Statement Document
1) INTRODUCTION
The purpose of this Method Statement is to provide methodology for 11kV cables relocation at
‘Multi Storey Car Park Building at BWTC Complex’ in compliance with Standard Specifications EDD
– MTC August 2015 and specification for the project.
2) SCOPE OF WORK
This Method Statement will define the scope of works for 11kV cables relocation, which
describes details of activities & execution involve in procedure under project specifications &
approved drawings.
3) LOCATION
As shown in the latest shop drawings.
- JAH-SI-INFRA-HV-101 Rev. 2, Existing Cable Rerouting Layout Ground Floor
4) REFERENCE
EDD MTC – August 2015
IFC Drawings, Shop Drawings, RFI’s (if any), STQ’s (if any), ESI’s (if any).
5) RESOURCES
5.1 Manpower
Project Manager
Project Engineer
Site Supervisor
Safety Officer
Forman
Cable Jointers
Electricians
Helpers
JAH-S-EL-MS-005 Revision 00 P a g e 3|5
Method Statement Document
5.2 Materials
Cable Tray and accessories – Approved by GEMAC
Solid concrete support blocks – Approved by Engineers
5.3 Tools & Equipment
Portable generator
General tools
Drill machine
Metal cutting machine
PPE
Barricades
Safety sign boards & warning lights
6) SEQUENCE/STAGE OF WORKS
Arrange cable trays, tray accessories & concrete support blocks at site prior to shutdown
date.
Shutdown will be agreed and work permit shall be issued by MODA team.
Mark the roof demolishing line
Provide new route marking (2 mtr away from demolishing line)
Request for Permit to work to be submitted to Moda Mall facility Team.
After approval of work permit arrange to dismantle existing unused cable tray and pipes
and make the route for cable tray clear.
Co-ordinate with Moda Mall Facility for disconnection of power to Feeder Pillar cables and
disconnection.
Install the new cable trays and make ready the cable tray needed for the tie in with existing
cable tray
Obtain final approval from consultant and Moda Mall Facility Team.
Request for another work permit to work on the existing 11KV cable at roof.
Make loose the existing cable tray covers by removing the screws
Request for shutdown. Duration – 6Hrs.
JAH-S-EL-MS-005 Revision 00 P a g e 4|5
Method Statement Document
Organize manpower/ material/machines etc. on the day of approved shutdown.
Co-ordinate with Moda Mall HV Engineer for switching activities.
The above activities need to be completed prior to the shutdown
Provide shutdown and issue “Permit To Work”
Once it’s done immediately lift the cable from existing tray and move to new tray
Install the covers
Re-energize the cable
House keeping
JAH-S-EL-MS-005 Revision 00 P a g e 5|5