Telecom Infrastructure Inventory

The document provides a summary of materials for a fiber optic cable project in Asahan, North Sumatra. It lists the types and quantities of materials needed, including over 92,000 meters of FO cable, poles ranging from 7-9 meters, outdoor cabinets, fiber patch cords, hardware for suspending cables, and other accessories. The summary also indicates the quantities of materials received on site and installed to date.

Uploaded by

Hantu Nasionalis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views5 pages

Telecom Infrastructure Inventory

The document provides a summary of materials for a fiber optic cable project in Asahan, North Sumatra. It lists the types and quantities of materials needed, including over 92,000 meters of FO cable, poles ranging from 7-9 meters, outdoor cabinets, fiber patch cords, hardware for suspending cables, and other accessories. The summary also indicates the quantities of materials received on site and installed to date.

Uploaded by

Hantu Nasionalis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

REGION_WEST - AREA_SUMATERA UTARA_ASAHAN - RING 3

Data Material On Site

Cluster Area Deskripsi UOM Plan

Sumatera Utara Asahan FO Cable G652D 12 Core (Aerial) Mtr 92,034


Sumatera Utara Asahan ODP Outdoor 16 Core Unit 10
Sumatera Utara Asahan OTB SC/PC 12 core & accessories Unit 26
Sumatera Utara Asahan Dome Closure Capacity 12 core Unit 28
Sumatera Utara Asahan Patch Cord SC/PC-SC/PC SMFO-DX-1m Unit 144
Sumatera Utara Asahan Tiang 7m Batang 1,065
Sumatera Utara Asahan Tiang 9m Batang 71
Sumatera Utara Asahan Dead End Clamp Buaya Set 16/25 Unit 1,244
Sumatera Utara Asahan Suspension Spie Set 6/24 Unit 1,304
Sumatera Utara Asahan Stoping Unit 4,212
Sumatera Utara Asahan Fixing slack 80x80 Tebal 5mm Unit 180
Sumatera Utara Asahan Steinless Steel 0.7mm x 20mm Roll 24
Sisa Material Sisa Material
Onsite Install
Onsite Terinstal
94,000 1,966 92,034
-10 10
-26 26
-28 28
-144 144
460 -605 1,065
24 -47 71
928 -316 1,244
672 -632 1,304
2,632 -1,580 4,212
180 0 180
16 -8 24
Remark

24.000 (Per Husble 4.000m), 12.000 (Per Husble 3.000m), 58.000 (Per Husble 2.000 m)
Date Material Date Material Date Material
Onsite Batch 1 Onsite Batch 2 Onsite Batch 3
18-Aug-21

7-Aug-21
29-Aug-21 1-Sep-21 4-Sep-21
18-Aug-21
18-Aug-21
18-Aug-21
18-Aug-21
18-Aug-21
Item Material Qty Sisa Material
Unit PIC Keterangan
UOM Masuk Tanggal Masuk Keluar Tanggal Keluar di WH
Pole 7 460 07-Aug-21 460 07-Aug-21 Batang 0 serah terima ke mandor
8 8 29-Aug-21 Batang - di pickup dari gudang ebtel
Pole 9 8 8 01-Sep-21 Batang - di pickup dari gudang ebtel
8 8 04-Sep-21 Batang - di pickup dari gudang ebtel
1 29-Aug-21 Husbel 5 serah terima ke mandor
1 31-Aug-21 Husbel 4 serah terima ke mandor
1 02-Sep-21 Husbel 3 serah terima ke mandor
FO Cable G652D 12 Core (Aerial) 4000m 6 18-Aug-21

1 31-Aug-21 Husbel 3 serah terima ke mandor

FO Cable G652D 12 Core (Aerial) 3000m 4 18-Aug-21

FO Cable G652D 12 Core (Aerial) 2000m 29 18-Aug-21 Husbel 29


18-Aug-21 150 29-Aug-21 Set 778 serah terima ke mandor
Dead End Clamp Buaya Set 16/25 928
150 02-Sep-21 Set 628 serah terima ke mandor
276 29-Aug-21 Set 396 serah terima ke mandor
Suspension Spie Set 6/24 672 18-Aug-21
236 02-Sep-21 serah terima ke mandor
Stoping 2632 18-Aug-21 2632 29-Aug-21 Buah 0 serah terima ke mandor
Fixing slack 80x80 Tebal 5mm 180 18-Aug-21 30 29-Aug-21 Batang 150 serah terima ke mandor
Steinless Steel 0.7mm x 20mm 16 18-Aug-21 16 29-Aug-21 Roll 0 serah terima ke mandor