COMPANY PROFILE PT.
GALANG SOLUSI TEKNIK
Contact us :
Head Office : Branch Office : Branch Office : Branch Office : Branch Office :
Jl. Symphoni Raya Blok HX-1 Jl lokasi no 27 Desa Bangun Sari Jl. Duren Tiga Buntu No. Jl. Pajar Permai KM 11 Komplek Jl. Mangga III/E366
No.127 Kec.Tanjung Morawa Kab.Deli 38A RT.5/RW.3, Kec. Perubahan Bumi Semaja Indah no 9, Sidoarjo - Jawa Timur
Bekasi-Jawa Barat 17214 Serdang, Sumatera Utara Pancoran,Jakarta Selatan Alang - alang Lebar Kota Palembang
Email :
Telp : 021 - 89441890 GalangSolusiTeknik ptgst.id @gstofficial__ @gstofficial__
galang.solusi.teknik@gmail.com
COMPANY
INTRODUCTION
PT.GALANG SOLUSI TEKNIK is managed by an The qualify of our services stems from our
experienced management team with minimum ability to fulfill and exceed our client’s
20 years of experience in handling electrical, expectation, with high regard for health, safety,
instrumentation, telecommunication, and and the environment.
mechanical project, from engineering thru
commissioning phase.
OUR VISION & MISSION :
The ideas to set up this company was to provide the most valuable deliverables projects
to the customer while pursuing the company’s growth.
MANAGEMENT
The experience of the management teams with the Multi-National Companies
telecommunication, Civil construction companies and Power Electricity such as SIEMENS, NSN,
NOKIA, ZTE, ERICSON, ALU, NEC AND HUAWEI, ABB, SCHNEIDER, TORISHIMAGUNA provide an
assured capability in handling project in all business environment.
OCCUPATIONAL HEALTH, SAFETY AND ENVIRONMENT POLICY
Committed to Occupational Health, Safety and Environment (OHSE) as a core value of the
corporation and as an integral part of our business activities in protecting employees, customers
and stake holders.
We adopt the international standards methodology and its implementation of Safety, Health and
Environment in our daily operations.
CONTINUOUS QUALITY IMPROVEMENT POLICY
Committed to continuous quality improvement, by using continuous quality improvement
methodology and implementing the best practices across disciplines and business area.
BUSINESS ORGANIZATION
● President Director : Sawaluddin Toelle
● Marketing and
Sales Director : Ir. Happy Salawangi, PMP
● Project Director : Misno
● Project Manager : Suhadi Efendi ● VP Project : Heru Seven Susanto, ST, PMP, CSM
● Sales Respentative : Dedi Armen ● Civil Engineeer : Fernando Simangunsong.STA
● Technical Manager : - Misno ● HSE : Hermayadi
- Tata Supriyatna ● QAQC Manager : Budi Kurniawan
● Head Engineer : Yulianto ● Human Resources : Johnny Pattipeilohy
● Field Engineer : Habib Nur Hamdi ● Finance Manager : Teddy Pribaddy
● Logistic & ● Commercial : Reza Hadi
Warehouse : Suba ● Field Personnel : Wiwin Saputra
● Project Control : Afrizal S. E
LEGAL CERTIFICATION
NO Description Remarks
1 Notary Decree EVA SARI HUTAJULU, SH, Mkn
2 Notary Deed No. 11
3 Tax No (NPWP) 74.442.853.3-121.000
4 Trade License (SIUP) 0298 / 0052 /1. 1.2107/01/2016
5 Company Registration (TDP) 02.12.1.46.24161/0081/0457/01/2016
6 Ministry of Law & Human Right AHU-3584916. AH. 01. 11.TH.2015
7 Telekomunikasi, Electrical, Civil Scope: Telecommunication, Low,
Construction and General Supplier Medium and High Voltage Electrical,
Tower Civil Construction Planning,
Installation, Integration, Maintenance
and main power supply
POWER PROJECT EXPERIENCE LIST CLIENT END USER
PT Cikarang Listrindo Extension Phase IVB
1 Installation of additional MV Panels & Commissioning 150kV Switchyard PT. SIEMENS PT. Cikarang
Phase IVB, Transformer, Relay, Safety & Control Devices INDONESIA Listrindo
150 kV Substation Semen Tuban PT. SIEMENS PT. SEMEN
2 Construction, Test and commissioning 150 kV Substation INDONESIA TUBAN
PTDH
PT Cikarang Listrindo Extension Phase VI PT. SIEMENS PT. Cikarang
Construction & Commissioning 150 kV Switchyard, MV/LV Power INDONESIA Listrindo
3 Distribution System ( Transformer, Busduct, MV Switchgear, LV
Switchboard), Substation Automation System
115 kV GIS Siemens type 8DN8-2 PT. SIEMENS Freeport
4 6 Bays at Amole Site and 5 bays at Power Plant C Construction and Testing INDONESIA Indonesia
POWER PROJECT EXPERIENCE LIST CLIENT END USER
Paiton Power Generation Unit 5 & 6 Power, East Java PT. Siemens YTL JAVA
5 Maintenance Circuit Breaker Analyzer & Inspection GIS 500 kV : Trafo 760 MVA, Indonesia PTD POWER
Busduct 21kV & Generator Star Point Division
PT. Siemens PLTU
6 PLTU TANJUNG JATI 2
Indonesia TANJUNG
Maintenance HV Equipment, 150 kV and 500 kV GIS Switchyard
PTD JATI 2
PT. Panata Brawijaya
77 Brawijaya Hospital Saharjo Electronic - Tebet, South Jakarta Bayu Hospital
Nugraha
PT. ABB Sakti PT. PLN
8 Substation 150 kV Topoyo (New) - Topoyo, South Sulawesi Industri (PERSERO)
POWER PROJECT EXPERIENCE LIST CLIENT END USER
North Duri Cogeneration Plant, Chevron, Riau PT. Siemens
9 MCTN
1. Major Overhaul Gas Turbine Generator Unit 1,2,3 (125@MW) Infonesia
Chevron
2. Electrical & Instrument Combustion Inspection TG Unit 1,2,3 PTDH
PLTGM Payo Selincah Jambi PT. ABB Sakti PT PLN
10 Construction & Testing 150 kV Substation trafo bay Industri
TANJUNG TABALONG KALSEL PT. HEIN PT. Tanjung
2x100MW Coal Fired Power Plant Construction & Testing
GLOBAL Power
11 (Power Transformer, LV & MV Switchgear, Insulation Phase Busduct,
cable tray / cable race way, cable pulling, cable Termination, Lighting UTAMA Indonesia
system, Fire Alarm system & Instrumentation)
SORIK MERAPI GEOTHERMAL PROJECT Huadong PT. SMGP
12 150 kV Transmission Line & Substation (Civil, Mechanical, Electrical China
erection & Testing Commissioning
POWER PROJECT EXPERIENCE LIST CLIENT END USER
PT. ABB Sakti PT. Supreme
13 MUARA LABOH, SOLOK - West Sumatera
Industri Energy Muara
Geothermal Power Plant, 150kV Substation (Erection, Testing & Commis Laboh (SEML)
PT. Sarulla
Sarula Geothermal Power Plant-Sarula North Sumatra
14 Electrical Maintenance Sarula NIL - 1 & 2 Project
Torishimaguna Operation Ltd
NIL-North
Sumatera
PT. Sarulla
Sarulla Geothermal Power Plant-Sarula North Sumatra
15 Electrical Maintenance Sarula SIL Project
Torishimaguna Operation Ltd
SIL-North
Sumatera
PT. ABB Sakti PT. PLN
16 150 kV EXTENSION GI New Balaraja - Tangerang West Java
Industri (PERSERO)
POWER PROJECT EXPERIENCE LIST CLIENT END USER
150 kV Substation - CVT Hotspot : PT.ABB Sakti PT.PLN
● 150 kV Ciamis Substation Industri (PERSERO)
17
● 150 kV Pandean Lamper Substation - Semarang
● 150 kV Tambak Lorok Substation - Semarang
● 150 kV Blora Substation
● 150 kV Karawang Substation
● 150 kV Haurgelis Substation
● 150 kV banjar Substation
● 150 kV Cianjut Substation
Coal Fired Power Plant Cirebon 2 - West Java : WIFGASINDO PT. Cirebon
18 DINAMIKA Power
● Transformer Assembly for 1000MVA/500kV
INSTRUMENT
● Oil Purification ENGINEERING.
● Testing PT
For : GSUT - 1000MVA-22kV/500kV, SAT1 65MVA-22kV/11kV,
SAT2 65MVA-500kV/11kV
POWER PROJECT EXPERIENCE LIST CLIENT END USER
GIS 150kV Geothermal Rantau Dedap, South Sumatera : PT.ABB PT. Supreme
● GIS Container + Accessories Sakti Energy
19
● Steel Structure, Gantry, Conductor, String Set and Steel Support Industri Rantau Dedap
● 150kV LA & 150 kV CVT
● LV - MV Control Cable Work & Fiber Optic
● CRP, SAS, Telecommunication Equipment, DFR, Energy Meter Panel
● Fiber Optic Installation and Splicing
● Grounding Work
● Test and Commisioning
500kV HV Apparatus, Klaten - Central Java : PT. ABB Power PT. PLN
20 Grides (PERSERO)
Installation Include Individual Test Indonesia
66kV Pad AA Substation Sorik Marapi : HDEC Power Sorik Marapi
21 China Geothermal
Installation and Testing Power
POWER PROJECT EXPERIENCE LIST CLIENT END USER
Gitet 500kV Deltamas
PT. PERFECT PT. PLN
22 Dismantling & Re-Packing HV Apparatus Diameter 5 & 6 CIRCLE (PERSERO)
ENGINERING
Gitet 500kV Bandung Selatan PT. PERFECT PT. PLN
23 CIRCLE (PERSERO)
Dismantling & Re-Packing Line Trap & Accessories ENGINERING
Gitet 500kV Mandirancan - Ext PT. ABB Power PT. PLN
24 Grides (PERSERO)
Construction Mechanical Electrical Diameter 7, 8, & 9 Indonesia
T/L 150kV Marisa - Moutong PT. PT. PLN
25 Citramasjaya (PERSERO)
Foundation, Erection & Stringing TIP 103 - TIP 208 Teknikmandiri
GIS (Gas Insulated Switchgear) - Erection &
Test Commissioning
❏ SIEMENS - 8DN8-II
(FREEPORT-PROJECT) 115kV GIS
Power project photos Installation & Commissioning
Power project photos
AIS (Air Insulated
Switchgear) -
Erection & Test
Commissioning
CIKARANG
LISTRINDO PROJECT
PHASE-VB/150 kV
Gantry/Beam
assembly/CB/Trafo.
Brawijaya Saharjo Hospital - Tebet,
South Jakarta PT.PANATA BAYU
NUGRAHA
Mechanical Electrical Installation
TANJUNG TABALONG KALSEL
PROJECT
150 kV KALSEL Switchyard &
Transmission
Line / Tower Foundation
GIS (Gas Insulated
Switchgear) - Erection &
Test Commissioning
Siemens-8DN8 Switchgear
(OKI-PULP & PAPER PROJECT)
Power project photos
AIS (AIR INSULATED SWITCHGEAR) - ERECTION & TEST
Power project photos COMMISSIONING
CIKARANG LISTRINDO PROJECT PHASE-VB / MV CABLE / 150 kV
CABLE/ TRAFO / GCB
500 kV GIS Refurbishment Work -
Erection & Test Commissioning
Hitachi GIS 500 kV - PT.PAITON ENERGY - IPMOMI
Power project photos
Power project photos SORIK MARAPI SARULLA OPERATION LTD-GEOTHERMAL
GEOTHERMAL PROJECT POWER PLANT
150 kV SMGP Switchyard & Transmission 150 kV SMGP Switchyard & Transmission
Line / Tower Erection Line / Tower Erection
SARULLA OPERATION LTD-GEOTHERMAL POWER PLANT
Electrical Inspection & Maintenance Sarulla SIL -
Power project photos Project
Power project photos
150 kV Extension GI
New Balaraja -
Tangerang - West
Java PT. ABB Sakti
Industri
Mechanical
Electrical
installation
SUBSTATION 150 kV TOPOYO (new) SOUTH
SULAWESI PT.ABB SAKTI INDUSTRI
Mechanical Electrical Installation
Power
project
photos
Project : Cirebon 2, 1x1000MW Coal Fired Power project
Project, Indonesia
1000MVA Transformer Installation, Oil Purification and Testing photos
Power project 150 kV CVT HOTSPOT - 150 kV
SUBSTATION PT. ABB SAKTI
photos INDUSTRI
Mechanical Electrical Installation & Testing
Power project Project : Rantau Dedap
Geothermal Power Project
Installation & Testing GIS 150kV
photos
500kV HV Apparatus,
Power Installation Include
Individual Test - Klaten (
project Central Java )
photos
Installation & Testing
66kV Pad AA
Power
Substation
Sorik Marapi
project
photos
Power
project Gitet 500kV Deltamas
photos
Power
project Gitet 500kV
Bandung Selatan
photos
Power
Gitet 500kV
Mandirancan project
photos
Power project
T/L 150kV Marisa - Moutong
photos
GST Fiber Optic Experience List : AREA DISTANCE
MORATEL (PT. GAMA PRATAMA) BSD 24 KM
1
2003
INDOSAT (PT. MITRA SINERGI) CIPUTAT 17 KM
2
2007
LINK NET (PT. HAVIEST CIPTA MANDIRI) CIBUBUR 26 KM
3
2011
XL COMINDO (PT.MANDALA) CIREBON - 250 KM
4
2011 YOGYA
LINK NET (PT.INEO) BEKASI 7 KM
5
2014
GST Fiber Optic Experience List : AREA DISTANCE
LINK NET (PT. CKK) BINTARO 14 KM
6
2014
IBS (PT. FAJAR MITRA) GRESIK - 180 KM
7
2017 SURABAYA
MORATEL (PT. JIG) GRESIK - 180 KM
8
2018 SURABAYA
CCTV PEMDA KOMINFO (PT. TAMATEL) SURABAYA 12 KM
9
2018
COMPANY
Certificate and
Legalicy
COMPANY
Certificate and
Legalicy
COMPANY
Certificate and
Legalicy
COMPANY
Certificate
and
Legalicy
COMPANY
Certificate
and
Legalicy
COMPANY
Certificate
and
Legalicy
COMPANY
Certificate
and
Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
COMPANY Certificate and Legalicy
Hopefully we can be
“We believe that by
partner in future
providing valuables
deliverables to
customers will creates Thanks for
company’s growth” your time
Find us on : ptgst.id GalangSolusiTeknik @gstofficial__ @gstofficial__