1000-09-04 (A.
S)
REGISTERED OFFICE: QUESTIONNAIRE AND
1 1/4, Saddar Road, PROPOSAL FOR ERECTION
P.0. Box No. ALL RISKS INSURANCE
44, Peshawar.
25000 NO.
GENERAL (lncorporated in Pakistan)
Established 1932
The issuing of this form is not to be taken as admission of liability by the lnsurance
1. Title ot contract
(if project consists of
several sections, specify
section(s) to be insured)
2. Location of erection site
Country
City, town,village
3. Principal
Name and address
4. Main contractor(s)
Name(s) and address(es)
5. Subcontractor(s)
Name(s) and address(es)
6. Manufacturers of main items
Name(s) and address(es)
7. Firm supervising erection
Name(s) and
address(es)
8. Consulting engineer
Name(s) and
address(es)
9. Proposer Please indicate which of the parties Nos 3 to 8 above is the Proposer of the insurance and which
parties are to be declared as insured in the Policy.
Proposer No. lnsured No(s)
10. Exact description of the
property to be erected (if
second hand items are to be
erected,
please state) In case of
machines: manufacturer's name,
number, type, size,capacity,
weight, pressure, temperature,
revolutions, year of construction
of major units.
In case of complete factories:
general drawing of plant, nature
of civilengineering work (if any).
11. Period of lnsurance Commencement of insurance
Ouration of pre-storage months prior to beginning of erection work
Commencement of erection work
Duration of erection/construction months
lf maintenance coverage required Duration of testing weeks
Duration of maintenance months
Type of coverage required Termination of insurance
a previous constructions? D yes D no
12. Have plans, designs and
materials of the kind used in this b previous constructions by the contractor(s)? D yes D no
project been used and/or
tested in
lt so, please give details of similar projects
carried out by contractor(s)
13. ls this an extension of an
existing plant?
D yes D no
II so, will operation of existing plant continue
during erection period? Enclose plans. D yes D no
14. Have the buildings and civil
D yes D no
engineering works already
been completed?
15. Work to be carried out by subcontractors
Please also give answers to Nos 16 to 21 as tar as information obtainable:
16. ls there any aggravated risk fire? D yes D no
of
explosion? D yes D no
ls so, give details.
17. Ground water level
18. Nearest river, lake, sea etc
Name distance from site
Levels of such river, lake, sea
etc Low water mean water highest level recorded
Mean level of site
19. Meteorological conditions Rainy seasons from to
Max rainfall (mm) per hour per day per month
Max wind velocity storm frequency D low D medium D high
20. Hazards of earthquake,
volcanism, tsunami
ls there a history of volcanism, tsunami at the site? D yes D no
Have earthquakes, etc. been observed in this area? D yes D no
lf so, please state intensity magnitude
Subsoil conditions ls the design of the structure to be insured based on
regulations regarding earthquake resistant structures? D yes D no
D rock D gravel D sand D clay D filled site
other types
Do geological faults exist in the vicinity? D yes D no
21. Estimate, if possible, the a. due to earthquake b. due to fire
probable maximum loss,
expressed as a percentage
c. due to other cause (please specify)
of the sum insured, in a
single occurrence
22. ls coverage of construction/ D yes D no
erection equipment
(scaffolding, huts, tools, etc.)
required? Please give bri.ef description and state new replacement value under No 28.3.
23. ls coverage of D yes D no
construction/
erection machinery
(excavators, cranes, etc)
required? Please attach list of major machines showing individual new replacement values and state total value.
24. Are existing buildings and/or
D yes D no
structures on or adjacent to
the site, owned by or held in
care, custody or control of lf so, give exact description of these buildings/structures .
the contractor(s) or the
principal, to be insured
against loss or damage
arising out of or in
connection with the contract
works? State limit under
No 28.5.
25. ls third party liability to
D yes D no
be included?
IIso, give briet description of
surrounding and existing
buildings and/or structures
not belonging to the principal
or contractor(s) (enclose
maps, if possible). State
limits under No 28 , Section II.
26. Do you wish cover to express freight, overtime , night work ,
work on public holidays? D yes D no
include extra charges
(in case of loss) for
air freight? D yes D no
27. Give details of any special
extension of cover required.
_/
28. Please state hereunder the amounts you wish to insure or where applicable
Currency
the limits of indemnity required (see Policy wording, Section 1,Memo 1 and Section II)
Section 1 -
-----
ltems to be insured Sums to be insured
Material damage (state below separately)
1Erection works, split up to follows ;
ltems to be erected
Freight
Customers duties and dues
Cast of erection
Civil engineering works
Construction/erection equipment
4. Clearance of debris (limit of indemnity)
5. Property located an the principal's premises or an the site,belonging to the principal or held in care,custody or control (limit of indemnity see Memo 4 of policy)
Total sum to be insured under Section 1
Please indicate limits of indemnity required for the following perils:
Risk Limits of indemnity1
Earthquake, volcanism, tsunami
Storm, cyclone,flood, inundation,landslide .
Section 11
lnsured items Limits of indemnity2
-
Third Party liability
Bodily injury-any one p,erson
Bodily injury - total
Property damage
Or alternatively
Combined single limit of
Limit of indemnity in respect of each and every lass or damage and/or series of lasses or
damage arising out of any one event.
Limit of indemnity in respect of any one accident or series of accidents arising out of one event.
We hereby declare that the
statements made by us in this Proposal forms the basis and lnsured will not lodge any modify any quotation made
Questionm11re and Proposal is part of any policy issued in other claims of whatever in the light of such
are, to the best of our connection with the above nature. alteration.
knowledge and belief, complete risk(s). lt is agreed that the The insured undertakes to The insurers undertake to
and true,and we hereby agree insurers are liable in in/arm the insurers of any deal with this information in
that this Questionnaire and accordance with the terms of material alteration whereby the strick confidence.
the policy only and that the risk is increased, and the
lnsurers reserve the right to
Executed a, Date Signature