4/Budgeting the Project
Chapter 4
                              Budgeting the Project
This chapter continues the topic of project planning and focuses specifically on project
budgeting. With the technical aspects of project planning discussed in the previous
chapter, this chapter addresses the need to develop a budget in order to obtain the
resources needed to accomplish the project’s objectives. The chapter begins with an
overview of budgeting methods and discusses both the top-down and bottom-up
approaches. In comparing these approaches, it is noted that top-down budgeting is
usually accurate overall but may include significant errors for low-level tasks. Bottom-
up budgeting, on the other hand, is usually accurate for low-level tasks but risks
overlooking tasks. Following this overview of budgeting methods, the chapter next
addresses the issues of cost estimation and improving cost estimates. The need for PMs
to thoroughly understand the organization’s accounting system is emphasized. Also the
issue of budget cuts is addressed. In terms of improving cost estimates, techniques such
as the use of learning curves and tracking signals are presented. Finally, the chapter
concludes with a discussion of budget uncertainty and risk management.
Cases and Readings
Some cases appropriate to the subject of this chapter are:
Harvard: 9-193-071 Porsche AG This 20-page case illustrates how traditional cost
measurement systems operate in an R&D department but offer little information for
managing projects.
Harvard: 9-690-051 Campbell Soup Co. This 23-page case describes the cost-
justification of a new engineering project to develop a microwavable package and
product for the growing convenience foods market segment. A 28 page teaching note (5-
690-094) is available for this case.
A reading appropriate to the subject of this chapter is:
D.H. Hamburger. The Three Perceptions of Project Cost (Project Management
Journal, June 1986). This article clearly describes the importance and impact of cost-
related issues on a project. These issues can significantly alter the profitability and even
success of a project. Costs are discussed from three viewpoints: that of the project
manager, the accountant, and the controller. Not only are the amounts of expenditures
and encumbrances important, but their timing is critical also. Perhaps most important is
having a project cost system that accurately reports costs and variances in a way that can
be useful for managerial decisions.
                                             39
4/Budgeting the Project
Answers to Review Questions
1. The main disadvantages of top-down budgeting are that significant errors may be
   made for low-level tasks, a lower level of budget acceptance is likely due to limited
   participation, and it provides little training opportunities in budgeting for junior
   managers. The main disadvantage of bottom-up budgeting is the risk of overlooking
   tasks.
2. Charging administrative costs based on total project completion time is based on the
   assumption that administrative costs increase in proportion to the length of the
   project. In other words, longer projects are expected to require more administrative
   resources than shorter projects.
3. The learning rate corresponds to the reduction in time or cost as output doubles.
   Therefore, a lower learning rate actually translates into a faster rate of learning.
   Generally speaking, people have the ability to learn while machines do not. Thus, if
   we assume by complex we mean automated, then the plant would have a slower
   learning rate of perhaps 95 percent. On the other hand, if by complex it is assumed
   that workers need a great deal of skill to operate the equipment, then a faster learning
   rate of 70 percent would be expected.
4. Tracking signals can help identify systematic biases in cost and other estimates.
   Knowledge of such biases can be used in preparing future estimates. Knowledge of
   biases also allows estimators to understand and correct their biases.
5. The three basic causes listed in Section 4.4 would appear to capture the vast majority
   of change in projects. As the question hints, however, two or more of these causes
   may occur at the same time. For example, new knowledge of a competitor’s new
   product may change the performance goal of a project and also require a change in
   how the tasks are achieved.
6. Highly probable risks have a high probability or likelihood of occurring. The
   consequences of these risks can be negligible (a data entry person quits) to very
   serious (the drug fails in the Phase I clinical trial). Extremely serious risks are risks
   that have very significant consequences although their probability of occurrence may
   be very low to very high. Highly vulnerable areas refer to risks that are both highly
   probable and extremely serious.
Suggested Answers to Discussion Questions
7. The accountant would likely assume that the $3,000,000 is to be allocated evenly
   over the six month duration of the task or $500,000 per month. However, most of the
   $3,000,000 will likely be incurred at the beginning of the task when the equipment
   must be acquired and paid for. The problem for the PM is that the accountant will
   expect a $500,000 charge in the first month of this task but will see an expenditure of
                                             40
                                                                        4/Budgeting the Project
     close to $3,000,000! Based on this the accountant and top management may become
     alarmed in terms of the project being completed on budget.
8. A straight-line project life cycle means that the impact of a budget cut would be
   constant throughout the project’s life. A slope greater (less) than 45 degrees means a
   change in the budget would have a proportionally larger (smaller) impact on the
   project’s completion. Of course it is unlikely in reality to observe a straight-line life
   cycle.
9.   Activity budgets segregate costs by types of expenditures-- phone, labor-- whereas
     program budgets group costs according to the task or job that uses resources of all
     types to accomplish that task. Program budgets, therefore, relate expenditures
     directly to the project's action plan and simplify the project manager problem of
     managing the budget and making trade-offs.
10. According to the “mythical man month” the three new engineers hired would
    probably not hit the ground running and would require training. This training would
    likely take time away from other members of the project team. Thus, the extra
    capacity created by adding these three engineers was likely more than used up by the
    other engineers who spent some of their time now training the new team members.
11. The purchasing manager’s assistant’s solution only addressed the symptom of the
    problem and not the cause for why the company was short in the first place. In this
    case the solution created another problem, namely, that the organization is no longer
    cost competitive.
12. The managers should consider both the average cost and variance of the cost for each
    plan. Often the tendency is to focus solely on the average cost. However, depending
    on an organization’s need to avoid risk, in some situations it might be better to
    sacrifice and select a project with a higher average cost but a smaller variance. By
    selecting a project with a lower variance, the probability of the actual cost greatly
    exceeding the average cost is reduced.
Incidents for Discussion Suggested Answers
A Budgeting Novice: Since the precedent has been set that a top-down approach to
budgeting is used at this company, Alex should do the same. Alex could approach his
boss with sound estimates and assure the boss that he has involved all the experts in
preparing the budget. Most likely, the boss will still re-work the numbers, but he should
be more comfortable that Alex did his homework in preparing it. Alex must make timely
communications to the boss on the project status, including thorough budget reports.
In the past, Alex has had autonomy to manage both performance and schedule, but has
not been permitted to develop the budget. Thus, it might be helpful for Alex to share
documents with his boss that demonstrate his competency in handling both schedule and
performance (assuming his boss is not familiar with these). In addition to documenting
                                             41
4/Budgeting the Project
his previous experience, it would be useful for Alex to share with the boss his WBS and
demonstrate how this drove his cost estimates. Finally, Alex might find it useful to share
with his boss how having responsibility for only schedule and performance and not
budget, limits his effectiveness as a project manager. Another advantage for Alex’s boss
is that more of his or her time would be freed up if Alex were permitted to work on
budget issues with clients.
Major Dynamic Ground Systems: Careful monitoring of all costs is critical for the
success of this project. The PM must monitor waste, scrap, and spoilage costs. These
should be tied to performance so that low numbers do not hide low levels of progress.
The controller must be able to identify all of the costs, such as those listed above, so that
nothing can be hidden or rolled up under such things as “work-in-process inventory” and
a true assessment can’t be ascertained until the end of the project.
General Sensor Company: The most relevant factors are the seriousness of the error,
Justin’s experience, and the fact that only one stage is affected, but it represents 50% of
the cost. Justin should combine the top-down approach with selected bottom-up inputs
and checks on the 50% of cost stage. He is experienced and comfortable with a top-down
approach and this makes sense for the majority of the project. Selective inputs from
lower level workers involved in the tasks would confirm his estimates, or indicate where
more information is needed.
Suggested Case Analyses and Solutions
St. Dismas Assisted Living Facility Project Budget Development -- 2
Teaching Purpose: This installment of the St. Dismas case requires students to address
issues related to identifying and dealing with cost uncertainty
1. The cost per square foot for the units is given in the text together with its standard
   deviation. What other areas of cost or revenue are likely to have cost uncertainty?
   How should these uncertainties be handled?
    Other areas of cost and revenue that are likely to be uncertain are the contingency
    allowances, marketing costs, personnel replacement, resource costs, GS&A, overhead
    allocation to budget, influences such as weather on the construction, cost increases for
    equipment or furniture, and labor cost increases.
    To handle the uncertainty, the estimators need to gain more knowledge of the areas of
    uncertainty and clearly define all the assumptions that were used to determine the
    budget. Furthermore, they need to review the project plans thoroughly to identify
    areas of risk. Finally, instituting a change order process, in case there is a change
    during the project would also be worthwhile.
    Assuming cost or revenues are normally distributed, statistical and probability theory
    could be used to gain additional insights. Of course, it is important that the PM,
    working with the accounting department, closely monitors all of the project costs.
                                             42
                                                                                   4/Budgeting the Project
2. How would you suggest the team handle the issue of Dr. Link’s supposedly inflated
   medical equipment costs?
   Since these are costly items, the CFO should recommend using a bottom-up approach
   to budgeting. The CFO should facilitate a team with experts and the differing doctors
   to determine the actual equipment needs and costs. This would enable buy-in from
   both parties. This would also ensure a more accurate estimate of needs. If there is
   sufficient data, the CFO can also include a tracking signal to identify if bias is in the
   estimates.
Photstat Inc.
Teaching Purpose: This case provides students with an opportunity to analyze the risk of
a project with several uncertain parameters. Students are asked to simulate the
completion of this project 100 times and create a risk profile for the project. Based on
this, students are asked to comment on the implications of using an average value versus
the risk profile. Case can also be analyzed using Crystal Ball.
1. What is the expected value of the project?
   The spreadsheet on the following page was created to calculate the expected value for
   this project. It is worth noting that one simplification was made. Namely, only the
   cash flows for the first six years as opposed to the first six-and-a-half years were
   discounted in calculating the NPV of the project. According to the spreadsheet, the
   expected value of this project is $1,221,361. The expected value would be have been
   perhaps $100,000 to $200,000 higher had the cash flows for the first half of the
   seventh year also been included.
2. Simulate this project 100 times and compute the average profit over the 100
   replications. Plot a histogram of the outcomes of the 100 replications.
   A portion of a spreadsheet that was created to simulate this project 500 times is
   shown on the following page. There are two major differences between this
   spreadsheet and the one discussed earlier to calculate the expected value of the
   project. First, the values in columns B-I (beginning in row 20) were generated
   randomly using Excel’s Random Number Generation tool. Secondly, a conditional
   formula was entered to calculate the NPV based on the useful life randomly generated
   in column I. For example, the NPV for the first replication (cell T20) was calculated
   as:
       =IF(I20=3,NPV(T$18,J20:L20),IF(I20=6,NPV(T$18,J20:O20),IF(I20=8,NPV(T$18,J20:Q20),NPV(T$18,J20:S20))))
                                                   43
4/Budgeting the Project
Spreadsheet for Calculating Project’s Expected Value
             A             B        C         D              E         F       G        H        I        J           K          L           M          N          O          P
 1
 2                  Market Selling                                                   Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow
 3                    Size     Price Market Market        VC           Equip Useful     Year      Year      Year      Year      Year      Year     1 1 .1 1 %
 4     Replication   Year 1 Year 1 Share Growth Year 1 Inflation        Cost    Life     1         1         1         1         1         1         NPV
 5    Expected Vaue 1 00 ,000 $12 .50 30 .00 % 1 0 .00 % $3.00 3.00 % $500 ,000 6. 5 -$215 ,000 $322 ,905 $365,851  $414 ,510 $469,639  $532,101 $1 ,221 ,361
 6
 7   Key Formulas:
 8   Cell J5       =($B5*(1 +$E5)^(J$4-1 ))*$D5*(($C5-$F5)*(1 +$G5)^(J$4-1 ))-$H5
 9   Cell K5       =($B5*(1 +$E5)^(K$4-1 ))*$D5*(($C5-$F5)*(1 +$G5)^(K$4-1 )) {Copy to cells L5:O5}
10   Cell P5       =NPV(P3,J5:O5)
Spreadsheet to Simulate Project’s Completion 500 Times
            A            B           C               D             E       F       G        H        I        J       K              L           M          N       O          P
 1   Input Data
 2                 Distribution   Param. 1        Param. 2
 3   Selling Price   Uniform         10               15
 4   Market Share    Normal          30                 3
 5   Total Market    Normal       1 00 ,000        1 0 ,000
 6   VC              Normal           3              0 .2 5
 7   Useful Life     Discrete
 8                        3          0 .1
 9                        6          0 .6
10                        8          0 .2
11                       10          0 .1
12   Market Growth   Normal       1 0 .00 %        0 .30 %
13   Equip. Cost     Normal       500 ,000         60 ,000
14   Inflation       Normal        3.00%           0 .50 %
15
16
17                    Market      Selling                                                               Cash Flow Cash Flow    Cash Flow    Cash Flow Cash Flow Cash Flow Cash Flow
18                      Size       Price          Market         Market     VC             Equip Useful    Year      Year         Year         Year      Year      Year      Year
19    Replication     Year 1      Year 1           Share         Growth Year 1 Inflation Cost      Life     1          1            1           1          1         1        1
20         1           932 47     $10 .77         30 .35%         9 .98 % $2 .91  2 .71 % 491 ,705  6   -$269 ,138 $251 ,416    $284 ,004    $320 ,815 $362,399  $409 ,372 $462 ,434
21         2          1 06357     $11 .23         2 8 .65%       1 5.81 % $3.05   3.40 % 487,1 26   3   -$237,968  $298 ,366    $357,294     $427 ,859 $512 ,361 $613 ,552 $734,728
22         3           9541 6     $13 .65         2 9 .67%        7.28 % $2 .74 2 .36% 478 ,2 22    6   -$169 ,089 $339,477     $372 ,800    $409 ,394 $449,579  $493,709  $542 ,171
23         4          1 1 5040    $11 .99         2 6.44%        1 4.44% $3.53 2 .1 4% 477,333      6   -$219 ,998 $300 ,788    $351 ,579    $410 ,946 $480 ,338 $561 ,447 $656,252
24         5          1 1 971 8   $11 .73         2 6.2 5%        7.57% $3.17     3.66% 458 ,354    6   -$189 ,544 $299 ,741    $334,230     $372 ,688 $415 ,571 $463,388  $516 ,707
25         6          1 0922 1    $11 .11         2 8 .87%        8 .99 % $3.04   3.38 % 485,704    8   -$231 ,192 $286 ,772    $323 ,122    $364,080  $410 ,229 $462,227  $520 ,817
26         7           71 856     $11 .20         2 6.1 4%       1 1 .71 % $2 .89 3.27% 505,887     8   -$349,862  $180 ,006    $207 ,674    $239 ,593 $276,419  $318 ,906 $367,922
27         8           9871 6     $11 .60         30 .2 5%        8 .01 % $2 .87  2 .1 7% 486,020   3   -$225 ,044 $288 ,017    $317 ,861    $350,797  $387,145  $427,260  $471 ,531
28         9           80465      $14 .74         2 8 .37%        7.74% $3.03     3.48 % 42 8 ,483  6   -$161 ,139 $298 ,063    $332 ,312    $370,497  $413 ,069 $460,533  $513 ,451
29        10          1 01 383    $10 .69         2 5.52 %        5.69 % $3.36 3.65% 445,723        6   -$256,289  $207 ,528    $227 ,350    $249 ,065 $272 ,855 $298 ,916 $327 ,467
                                                                                                                                            44
                                                                      4/Budgeting the Project
Spreadsheet to Simulate Project’s Completion 500 Times (continued)
        Q           R            S            T
 1 7 Cash Flow Cash Flow Cash Flow
 18    Year        Year        Year      1 1 .1 1 %
 19      1           1          11         NPV
 2 0 $522 ,373 $590 ,082    $666,567 $851 ,709
 2 1 $879 ,837 $1 ,053,604 $1 ,261 ,691 $298 ,689
 2 2 $595,390   $653,833    $718 ,013 $1 ,244,393
 2 3 $767,066   $896 ,592 $1 ,047,990 $1 ,208 ,590
 2 4 $576,161   $642,457 $716 ,380 $1 ,100 ,677
 2 5 $586,834   $661 ,218   $745,032 $1 ,574,923
 2 6 $424,472   $489 ,715   $564,985    $888 ,853
 2 7 $520 ,389  $574,310    $633,819    $272 ,259
 2 8 $572,449   $638,226    $711 ,562 $1 ,119 ,011
 2 9 $358,745 $393,010      $430,548 $617 ,600
A histogram (risk profile) summarizing the 500 replications is shown below.
                          Histogram
               1 00
   Frequency
                 80
                 60
                 40
                 20
                  0
                            e
                  , 5 51
                  , 0 51
                  , 4 51
                  , 9 51
                  , 3 51
                  , 8 51
                  , 3 51
                           51
                     2 1
                  , 0 51
                         or
                 $ 6 , 25
               $1 5 ,2
               $2 5,2
               $2 5 ,2
               $2 5,2
               $3 5 ,2
               $3 5,2
               $4 5,2
                        ,2
               $1 5 ,2
                       M
                     05
                     65
                     8
                     4
                     8
                     2
                 $1
                                     Bin
3. How does the average of the simulation compare to the expected value you
   calculated? What are the managerial implications of this difference?
   The average of the simulation was $1,423,668 which is relatively close to the
   expected value. However, the range of values observed in the simulation experiment
   varied from a loss of almost $65,000 to a profit of over $4.5 million. Thus, the
   simulation experiment demonstrates the uncertainty of the actual outcome of this
   project.
Using Crystal Ball: The use of Crystal Ball can greatly speed up the development and
analysis of the simulation model for this case. To illustrate this, the spreadsheet shown
on the following page was created. With Crystal Ball, values for the random parameters
are generated by defining cells as Assumption Cells rather than using Excel’s Random
                                            45
4/Budgeting the Project
        Using Crystal Ball to Simulate Project Costs
                B       C      D       E      F       G        H       I       J          K          L         M          N          O         P
          1
          2   Market Selling                                                 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow
          3     Size     Price Market Market       VC          Equip Useful     Year      Year      Year      Year      Year      Year     1 1 .1 1 %
          4    Year 1 Year 1 Share Growth Year 1 Inflation      Cost    Life     1         1         1         1         1         1         NPV
          5   1 00 ,000 $12 .50 30 .00 % 1 0 .00% $3.00 3.00% $500 ,000 6.5  -$215 ,000 $322 ,905 $365,851  $414 ,510 $469,639  $532,101 $1 ,221 ,361
        Number Generation tool. In this particular case, cells B5 to I5 were defined as assumption cells. For example, cell B5
        corresponds to the market size in the first year of the product’s introduction. From the case, it is estimated that the market size
        follows a normal distribution with a mean of 100,000 units and standard deviation of 10,000 units. To define cell B5 as an
        assumption cell, first the cursor was placed in this cell. Next, the Define Assumption button was selected. Then the Normal
        distribution was selected from the Distribution Gallery that appeared. In the next window, 100,000 was entered in the Mean
        field and 10,000 was entered in the Std Dev field and the OK button selected. Cells C5 to H5 were specified in a similar
        fashion.
        Cell I5 was a little different in that the useful life of the equipment does not follow a continuous distribution. In this case, the
        Custom distribution was selected from the Distribution Gallery. Next 3 was entered in the Value field and .1 entered in the
        Prob. field and the Enter button clicked. In a similar fashion, 6 was then entered in the Value field, .8 in the Prob. field and
        the Enter button clicked. This was repeated for the probabilities of 8 year and 10 year useful lives, respectively. After all this
        information was entered, OK was clicked.
        Finally, cell P5 was defined as the Forecast Cell. NPV was entered as a descriptive name in the Forecast Name field and
        Dollars in the Units field. The formulas in cells J5:O5 are the same as was previously discussed. To run the simulation, the
        Start Simulation button was selected.
        The Frequency Chart and Statistics views are shown below. The average cost of the project is within 1 to 2 percent of the
        results obtained using Excel’s Random Number Generation tool. Additional details about the use of Crystal Ball can be found
        in Appendix C.
                                                                                                   46
                                           4/Budgeting the Project
Crystal Ball’s Frequency Chart View
Crystal Ball’s Statistics View
                                      47
4/Budgeting the Project
Test Questions
                            True/False and Multiple Choice
F 1. ___ The project’s budget is merely the sum of its resource costs.
F 2. ___Overhead and indirect charges should not be assigned to a project.
T 3. ___ Most organizations use top-down budgeting.
F 4. ___ Because project budgeting is for a special case and the organization’s budgeting
         process is for routine work, the project manager need not be familiar with the
         organization’s accounting system.
T 5. ___ Budget cuts are usually disastrous to an exponential life-cycle project.
F 6. ___ Activity budgets show expenses by task, time period, and expense category.
F 7. ___ There is no way other than guessing to estimate the impact of learning on a
         project’s task.
T 8. ___ Calculating the Tracking Signal can not only reveal if estimates are biased, it
         can also tell how severe the bias is.
F 9. ___ By very careful planning, a project manager can do away with cost uncertainty.
T 10. ___ Expected value is a tool for risk analysis.
F 11. ___ Traditional organizational budgets are task-oriented, rather than activity-
          oriented.
F 12. ___ Learning curve theory states that performance of labor per unit will improve
          by a percentage each time production increases by the same percentage.
T 13. ___ Learning curve theory states that performance of labor per unit will improve
          by a fixed percentage each time production doubles.
T 14. ___ Individual elements of project budgets are generally more accurate in bottom-
          up budgeting.
T 15. ___The project budget acts a project control.
T 16. ___ A budget is a plan for allocating resources.
F 17. ___ Individual budgets are constructed using the work breakdown structure in the
          top-down budgeting method.
                                            48
                                                                      4/Budgeting the Project
T 18. ___ Budgetary gaming is a fact of life using either or both the bottom-up and
          top-down method.
a 19. ___Why is it necessary to consider the learning curve of resources on a project?
          a. to estimate labor costs properly
          b. to improve project team morale
          c. because it always takes less time to do a task after someone has done it a
             few times.
          d. collective bargaining contracts require it
          e. All of the above
e 20. ___ Sources of risk on a project include:
           a. acts of nature
           b. the client
           c. the skills of the project team
           d. senior management
           e. only a and b
e 21. ___ A requirement of top-down budgeting is:
          a. involvement of the project team
          b. estimating the detailed level of the project’s tasks
          c. applying the learning curve to labor time estimates
          d. all of the above
          e. none of the above
a 22. ___ A problem with bottom-up budgeting is:
          a. individual team members overstate their budget needs
          b. lack of involvement from the project team
          c. underestimating the project task’s budget requirements
          d. all of the above
          e. none of the above
e 23. ___ A project budget is:
          a. an expression of organizational policy
          b. a plan for allocating resources
          c. a means of assigning cost to the project
          d. all of the above
          e. only b and c
a 24. ___ The most important consideration in budgeting is:
          a. cost control
          b. maximizing project’s return on investment
          c. meeting the project’s schedule
          d. estimating project resource costs
          e. all of the above
                                            49
4/Budgeting the Project
b 25. ___ The budget strategy based on collecting information from middle managers
          based on their prior experience is called.
           a. bottom-up budgeting
           b. top-down budgeting
           c. earned value budgeting
           d. zero-based budgeting
           e. none of the above
d 26. ___ The name given to the budget process that aggregates income and expenditures
          across projects is:
           a. activity-oriented budget
           b. top-down budget
           c. bottom-up budget
           d. program-oriented budget
           e. activity-based costing
                                     Short Answer
27. Define Top-down and Bottom-Up budgeting?
    Top-down budgeting is an estimate of high level tasks of the project by senior and/or
    middle managers. A bottom-up budget is when budget estimates are made based on
    the project’s action plan resource requirements made by those responsible for
    executing the tasks.
28. List some reasons why you would take on a project that was forecast to lose money.
    Allow for a follow-up project, improve competitive position, acquire knowledge, get
    firm’s name out, broaden a product line.
29. Define the term learning rate.
    The percentage by which the time required to accomplish a task decreases each time
    the number of task repetitions is doubled.
30. Risk management includes what three areas?
    Risk Identification, Risk Analysis, and Response
31. What is the Game Theory approach?
    This is when you operate on the assumption that the worst will happen. The
    assumption is that competitors and the environment are your enemies. You take on a
    pessimistic mind-set in making estimates and take action that will minimize harm.
32. List some of the factors commonly left out of cost estimation.
    Inflation, Learning curve, Waste and spoilage, Risk, Potential delays.