A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
1 1 TO 2A 8345.8 603, 604
2 1 TO 2B 8345.8 602, 608
3 1 TO 3B 2509.5 604, 608
4 1 TO 3D 2509.5 608
5 2A TO 3B 2509.5 604 ---------
6 2A TO 3D 2509.5 605 ---------
7 2A TO 3A 7628.4 604, 605 ---------
8 2B TO 3B 2509.5 603 ---------
9 2B TO 3D 2509.5 603 ---------
10 2B TO 3C 7628.4 603 ---------
11 3A TO 3B 1440.9 603 ---------
12 3B TO 3C 1440.9 603 ---------
13 3C TO 3D 1440.9 603 ---------
14 3D TO 3A 1440.9 603, 605 ---------
15 3A TO 4F 1656.9 601, 605 ---------
16 3A TO 4A 6627.2 601, 602, 605 ---------
17 3A TO 4B 1656.9 611 ---------
18 3B TO 4B 4970.3 609, 611 ---------
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|1
A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
19 3B TO 4C 4970.3 605 ---------
20 3C TO 4C 1656.9 605 ---------
21 3C TO 4D 6627.2 604, 611 ---------
22 3C TO 4E 1656.9 602, 611 ---------
23 3D TO 4E 4970.3 601, 602, 611 ---------
24 3D TO 4F 4970.3 601, 602, 605 ---------
25 4A TO 4B 2343.1 611 ---------
26 4B TO 4C 2343.1 605 ---------
27 4C TO 4D 2343.1 604, 605 ---------
28 4D TO 4E 2343.1 601, 605 ---------
29 4E TO 4F 2343.1 611 ---------
30 4F TO 4A 2343.1 611 ---------
31 4A TO 5S 608.75 611 ---------
32 4A TO 5T 2435.0 611 ---------
33 4A TO 5A 2435.0 609, 611 ---------
34 4A TO 5B 2435.0 609, 611 ---------
35 4A TO 5C 608.75 609, 611 ---------
36 4B TO 5C 1826.25 609, 611 ---------
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|2
A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
37 4B TO 5D 2435.0 609, 611 ---------
38 4B TO 5E 2435.0 609, 611 ---------
39 4B TO 5F 1217.5 609, 611 ---------
40 4C TO 5F 1217.5 605 ---------
41 4C TO 5G 2435.0 605 ---------
42 4C TO 5H 2435.0 605 ---------
43 4C TO 5I 1826.25 605 ---------
44 4D TO 5I 608.75 604, 605 ---------
45 4D TO 5J 2435.0 604, 605 ---------
46 4D TO 5K 2435.0 604, 605 ---------
47 4D TO 5L 2435.0 604, 605 ---------
48 4D TO 5M 608.75 604, 605 ---------
49 4E TO 5M 1826.25 601, 605 ---------
50 4E TO 5N 2435.0 602, 605 ---------
51 4E TO 5O 2435.0 602, 605 ---------
52 4E TO 5P 1217.5 602, 605 ---------
53 4F TO 5P 1217.5 611 ---------
54 4F TO 5Q 2435.0 601, 611 ---------
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|3
A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
55 4F TO 5R 2435.0 601, 611 ---------
56 4F TO 5S 1826.25 611 ---------
57 5A TO 5B 9372.4 608, 611 ---------
58 5B TO 5C 9372.4 611 ---------
59 5C TO 5D 9372.4 604, 610 ---------
60 5D TO 5E 9372.4 610
61 5E TO 5F 9372.4 607 ---------
62 5F TO 5G 9372.4 607 ---------
63 5G TO 5H 9372.4 611, 612 ---------
64 5H TO 5I 9372.4 602 ---------
65 5I TO 5J 9372.4 602, 605 ---------
66 5J TO 5K 9372.4 605, 609 ---------
67 5K TO 5L 9372.4 604 ---------
68 5L TO 5M 9372.4 604 ---------
69 5M TO 5N 9372.4 605 ---------
70 5N TO 5O 9372.4 608 ---------
71 5O TO 5P 9372.4 608, 611 ---------
72 5P TO 5Q 9372.4 605 ---------
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|4
A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
73 5Q TO 5R 9372.4 606, 611 ---------
74 5R TO 5S 9372.4 601, 611 ---------
75 5S TO 5T 9372.4 603 ---------
76 5T TO 5A 9372.4 603 ---------
77 6A TO 5A 1217.5 604 ---------
78 6A TO 5B 2435.0 604 ---------
79 6A TO 5C 2435.0 604 ---------
80 6A TO 5D 1826.25 604 ---------
81 6B TO 5D 608.75 604 ---------
82 6B TO 5E 2435.0 604 ---------
83 6B TO 5F 2435.0 602 ---------
84 6B TO 5G 2435.0 602 ---------
85 6B TO 5H 608.75 601, 602 ---------
86 6C TO 5H 1826.25 601, 602 ---------
87 6C TO 5I 2435.0 602 ---------
88 6C TO 5J 2435.0 602 ---------
89 6C TO 5K 1217.5 606, 609 ---------
90 6D TO 5K 1217.5 606, 609 ---------
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|5
A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
91 6D TO 5L 2435.0 606 ---------
92 6D TO 5M 2435.0 606 ---------
93 6D TO 5N 1826.25 606 ---------
94 6E TO 5N 608.75 606 ---------
95 6E TO 5O 2435.0 606, 609 ---------
96 6E TO 5P 2435.0 602, 609 ---------
97 6E TO 5Q 2435.0 602, 609 ---------
98 6E TO 5R 608.75 602, 612 ---------
99 6F TO 5R 1826.25 602, 612 ---------
100 6F TO 5S 2435.0 604, 612 ---------
101 6F TO 5T 2435.0 604, 612 ---------
102 6F TO 5A 1217.5 604 ---------
103 6A TO 6B 2343.1 611 ---------
104 6B TO 6C 2343.1 602, 611 ---------
105 6C TO 6D 2343.1 606 ---------
106 6D TO 6E 2343.1 601, 604 ---------
107 6E TO 6F 2343.1 606 ---------
108 6F TO 6A 2343.1 602, 611 ---------
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|6
A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
109 7A TO 6F 4970.3 601, 602, 607 ---------
110 7A TO 6A 4970.3 602 ---------
111 7B TO 6A 1656.9 602 ---------
112 7B TO 6B 6627.2 606, 608 ---------
113 7B TO 6C 1656.9 606, 608 ---------
114 7C TO 6C 4970.3 606, 608 ---------
115 7C TO 6D 4970.3 606, 608 ---------
116 7D TO 6D 1656.9 606, 608 ---------
117 7D TO 6E 6627.2 602 ---------
118 7D TO 6F 1656.9 602 ---------
119 7A TO 7B 1440.9 603 ---------
120 7B TO 7C 1440.9 603 ---------
121 7C TO 7D 1440.9 603 ---------
122 7D TO 7A 1440.9 603 ---------
123 8A TO 7D 2509.5 601 ---------
124 8A TO 7A 7628.4 601, 603 ---------
125 8A TO 7B 2509.5 601, 603 ---------
126 8B TO 7B 2509.5 603 ---------
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|7
A Visual Examination Report pages : 08
Aali Alneel For Report Date : 10/10/2016
Construction L.T.D Report Report No. : M047-KA-VT-01
:Aali Alneel For
CLIENT : Heavy Engineering Equipment (HEESCO) Contractor
Construction L.T.D
MATERIAL / : A537 C-1 / 44.0 –
Project Name : LPG Spherical Tank (T-101B) – Karbala
THICKNESS (mm) 46.0 mm
Reference
: VT Procedure # AN-NDE-PR-001 DRAWING NO. : T-101-M005-C
Procedure
Acceptance Criteria : ASME VIII – DIV 2, 2010 ATTACHMENTS : WELD MAP
: Outside – Shell to
WPS No. : SM – P.1(1.1) – P200 Examined Part
Shell Joints
Evaluation
Sr. Joint No. Length, mm Welder Stamp Remarks
ACC. REJ.
127 8B TO 7C 7628.4 603 ---------
128 8B TO 7D 2509.5 603 ---------
129 9 TO 7B 2509.5
130 9 TO 7D 2509.5
131 9 TO 8A 8345.8
132 9 TO 8B 8345.8
Aali Al-Neel
HEESCO QC MTI TPI
Inspector
Name Hatem Ragab AHMED OMER
Signature
Date
Page|8