Lean Manufacturing Case Study
Lean Manufacturing Case Study
How to cite: Santos, D. M. C., Santos, B. K., & Santos, C. G. (2021). Implementation of a standard
work routine using Lean Manufacturing tools: A case Study. Gestão & Produção, 28(1), e4823.
https://doi.org/10.1590/0104-530X4823-20.
Abstract: Due to technological advances, trade politicies and society's consumption patterns,
competitiveness among companies has increased considerably, requiring practices that provide
a constant improvement in production indicators and product quality. In this context, the use of
Toyota Production System tools, also known as Lean Manufacturing, have a fundamental role in
the elimination of waste and continuous improvement of industrial production levels. Thus, this
work aims to implement a standardized work routine among employees working in a market of
parts in an Agricultural Machinery industry, which lacks production methods. To represent this
situation, real data were used, which correspond to the needs of the assembly line, and which
served as the basis for the analysis and implementation of a new work routine. The results
obtained enabled the creation of a standardized work routine, which was obtained by balancing
activities between operators and eliminating activities that did not add value to the product.
Keywords: Takt time; Standardized work; Productivity; Lean manufacturing; Yamazumi board.
1 Introduction
With the growing competitiveness among organizations because of technological
advancements, trade policies and consumption patterns, the employment of practices
that enable the continuous improvement of production indicators becomes a differential
for organizations. However, many companies end up not having an adequate control
of the activities performed during their production process. In this scenario,
organizations searching for a differential in face of their competitors are constantly
focused in reducing costs, improving their products’ quality whilst increasing their
productivity with focus on meeting their clients’ needs.
Lean Manufacturing system, also known as Toyota Production System, positively
revolutionized automobile industry in Japan during the 1950’s. The practices defended
by Toyota System Production have been adopted by the most varied industrial
branches around the world. This Production System is based on the elimination of
waste to improve production levels in companies. To enable the elimination of waste,
specific tools are used in order to manage processes and other activities performed
inside the company (Liker & Meier, 2007).
In this context, this article aims at implementing a standard work routine through the
use of Lean Manufacturing tools, searching to optimize the distribution of activities
among operators in the Logistics Sector of an agricultural machinery manufacturing
company.
2 Literature review
The literature review approaches concepts and theories relating to the company’s
goals. Fundamental concepts such as Lean Manufacturing, Takt Time, Value Stream
Mapping, and Standardized Work. These are fundamental concepts to apply Lean
Manufacturing methodology in an industrial environment.
work time available by shift ( minutes )
TAKT TIME = (1)
units to be produced ( machines )
If each process exceeds Takt time, the results are scarcity of products; but if it faster,
there will be an oversupply. When Takt Time is correctly observed, both activities in the
work stations flow in the same pace, only producing the number of parts that were
demanded for (Imai, 2014).
According to Peinado & Graeml (2007) and Slack et al. (2002), processes hardly
present the same volume of work employed in each work station, that is, operations
are not in perfect balance. This means that in a specific part of the production process,
there will be a slower operation, and it will determine the production speed in all of the
assembly line. This slower operation is called a bottleneck.
For Wilson (2010), the implementation of the Operator Balance Chart enables the
visualization of important information on the analyzed process, such as:
• Waste of time: the vertical distance of the Takt Time line in relation to time
cycle of the work station represents waiting time, that is, time wasted in this
work station.
• Degree of balance reached: comparing the height of the bars, the
balance/imbalance of the process may be observed and, later, the balance
between operations can be enhanced through the task redistribution.
• Process bottleneck: in case the higher bar exceeds the Takt Time line, it is
indicating which of the operators is under overload, causing delays and even
stops in the process.
According to Sabadka et al. (2017), Yamazumi board consists of an ideal tool to
enhance productivity in an industrial environment, because its implementation is able
to significantly reduce the production time, enhancing the efficiency of the operator and
enabling the balance among the assembly cells.
Standardized work
Standardized work establishes precise work procedures for each of the operators
in a production process based on three elements: Takt Time, the work sequence, and
the standard inventory (Lean Enterprise Institute, 2003).
The Work Standards Sheet contains work elements in sequence of operation,
monitoring the length of each activity. As a reference, one has the Takt Time line which
represents the limit time in which activities must be performed, as it can be seen in
Figure 2.
The work standards sheet is a tool for analysis that can be considered as set of
instructions for the operator in which it is possible to analyze and understand losses in
each operation. The use of this tool will provide information referring to the balanced
workflow during the creation of a continuous flow. As a tool for analysis, Standardized
Work will help employees identifying movements (walking, arriving) and waiting times
(when the work cycle is below Takt Time) (Liker & Meier, 2007).
In this context, Wilson (2010) adds that standardized work is a fundamental tool in
the assessment and the assistance of the synchronized production process, used to
review performance of the process, including its cycle time.
By means of implementing this tool, it is possible to distribute workloads in Takt
Time, meeting the client’s demand without the necessity of extra hours. If work
elements of one or more operators exceed Takt Time, it is possible to transfer these
elements for other operators, distributing activities in a balanced way. With the
reduction of the workload following Takt Time, it is possible to eliminate idleness and
waste in waiting time (Kishida et al., 2006).
Total Value Stream comprehends all sectors of the company, from negotiations with
suppliers to the delivery of the product to clients. However, as it is illustrated in Figure 4,
this article will approach the implementation of Lean Manufacture in the Logistics area,
specifically focusing in a market of parts.
The implementation of the proposed model in the company’s supply chain may
result in the enhancement of performance indicators, even within a brief time since it
begins. The proposed model maximizes advantages of the systems under study at the
same time that it minimizes their limitations, resulting in the accomplishment of
managers’ needs in the search for success in their companies (Santos & Alves, 2015).
3. METHODOLOGY
The work was carried out in the logistics area of an agricultural machinery industry
located in the northwestern region of the Rio Grande do Sul state. The logistical activities
of this company are based on the input of material (Figure 5a) and the supply of parts to
the assembly line via restocking boxes that are later returned empty from the assembly
line (Figure 5b). After the boxes are loaded, stock routes are carried out in a way that
answer the assembly line without causing any supply problems in workstations.
The material is received in pallets of KLT boxes (Klein Lagerung und Transport or
Conditioning and Transportation of Small Components). In accordance to Figure 5b,
KLT boxes allow for a higher volumetric capacity in the transportation of parts. Bin
boxes, on the right side of Figure 5b, present lower volumetric capacity than KLT boxes,
and both are used to restock the assembly line.
The starting point to carry out this work was the full compliance with the demands
of the assembly line which must always be taken in consideration in the standardized
work of the activities. In case the demands are revised, shifts in the activities among
operators are necessary. In the case in point, the client (the assembly line) has two
specific needs: payment routes in defined hours and the supply of boxes according to
the needs of the assembly line.
Through the bibliographical research in books, theses, and scientific papers, tools
to be used in this work were defined: Value Stream Mapping, Operator Balance Chart,
and Work Standards Sheet.
In this manner, the work was divided in six stages among which the following can be
highlighted: data collection of activities performed by each operator, VSM, Takt Time calculus,
the balancing of activities and the implementation of a standard work routine for each operator.
Column ‘day’ refers to the weekday in which data were collected, with 1 referring to
Monday and 5 to Friday. Column ‘quantity’ refers to the number of boxes that must be
restocked and sent again to the assembly line. Time is presented in minutes and it
refers to the necessary timing for an activity to be concluded. Arithmetical mean is the
ratio of time and the quantity of boxes (minutes per box).
Throughout one week (five working days), data were collected referring to the timing
of each activity developed in order to guarantee the supply of the production line. In the
data collection, day 1 refers to Monday and day 5 to Friday, as it can be seen in Table 2.
(seconds)
(seconds)
(seconds)
Quantity
Quantity
Quantity
Quantity
quantity
quantity
quantity
quantity
Time /
Time /
Time /
Time /
(unit)
(unit)
(unit)
(unit)
Time
Time
Time
Time
Day
Day
Day
Day
For the data collection, each operator developed their activities according to their
daily work routine. That allowed for the identification of the time that it took the operator
to finish up their activities. At the end of each day, the amount of work performed in a
determinate period of each activity performed was obtained. As it is shown in Table 2,
the amount of work presented constant oscillations among the number of boxes for
each week day. Therefore, the week average was used as a standard time for each
activity.
When finishing the work shift and the data collection of the week, it was possible to
calculate the arithmetical means of the weekly time for each activity, as it is approached
in Table 3.
The averages of time related to the supply of four kinds of boxes (Bin A, Bin B, Klt
A, Klt B) correspond to the necessary time to carry out the supply of an empty box and
its load in the tow. In the case of reception, average time represents the storage of only
one box in its correct place in the market. As for replenishment, average time is linked
to the separation of one part and its shipment to dispatch. Time related to routes of
payment correspond to the average time that it takes the operator to carry the last box
restocked in dispatch until its return to the market of parts, after the supply of parts in
the assembly line.
Figure 7- Data collection: boxes that return empty from the assembly line.
Source: Authors.
According to the data presented in Table 2, the number of boxes that returned from
the assembly line presented constant variations, even if the number of machines
manufactured daily in the assembly line was kept at three machines per day. It is
evident by this that the lack of standardized work in this logistics sector affected the
pace of the assembly line directly because the boxes were not delivered in the right
moment. As it can be seen in Figure 7, there was a variation of 157 Bin A boxes
between Tuesday and Friday. The other kinds of boxes also presented considerable
variations throughout the week. With this information it was possible to calculate the
rate of variation for each type of box throughout five days, with the results of 31,44%
for Bin A boxes and 12,47% for Bin B boxes. KLT A and KLT B boxes presented a rate
of variation of 38,56% and 16,46%, respectively.
The company defined that a route of payment to each machine leaving the
assembly line should be carried out. To calculate Takt Time, where the demand to be
met by the assembly line was of three routes per day, it is necessary to know the work
time available. The shift begins at 7:30 and ends at 17:30. It allows 1 hour of lunch
break and 15 minutes of snack break in the morning shift and other 15 minutes in the
afternoon shift. This way, the time available per shift is of 510 minutes. With this
information, it is possible to calculate Takt Time, according to the resolution below:
510 minutes
Takt Time
= = 170 minutes / route
3 routes
Based on the Takt Time concept by Iwayama (1997), routes of payment must occur
every 170 minutes, guaranteeing that the payment of parts keeps the pace of the
assembly line.
The Operator Balance Chart, illustrated in Figure 8, enabled the division of work
load in a similar way among operators, making evident the fact that three people are
enough to meet the pace of the assembly line. The sum of activities is below takt time.
With this, it is expected that each operator performs their activities in an isolated
manner in the production cycle, where each one will perform according the time
available for the activities.
With the current Value Stream Mapping, it was possible to analyze the activities
separately, enabling idle activities or reducing idleness of the employees, as it can be
seen in Figure 9.
As Figure 9 shows, it was possible to eliminate two stages in the process. The stage
“separate full boxes” functions as follows: after they are full, boxes are placed below a
mezzanine where they are later separated in the dispatch, according to work stations
in the assembly line. In the future process, after boxes are replenished, they will be
carried directly in the dispatch, avoiding, thus, the transshipment in the mezzanine.
The second stage eliminated, “separate boxes according to the location in the
warehouse” will be performed at the moment boxes are taken from the assembly line.
In the current process, empty boxes are placed disorderly in the dispatch and separated
only after they arrive in the warehouse. This way, in this phase of the work, it was
possible to eliminate two activities that did not add value to the production cycle.
The standardized work flow among operators, shown in Figure 10, was
implemented based on information from the operator balance chart.
The workday begins at 7:30 a.m. when every employee starts their activities, always
considering the time for dedication to each operation. Operator 1 will begin their work
routine with the route of payment in the assembly line. After finishing their route, they
will perform the replenishment of KLT “A”, in sequence, replenishment of Bin “A” boxes
must be concluded. Operator 2 begins their shift, receiving material and will have as
next activity the stocking of Bin “B” boxes. Operator 3 also begins their activities with
focus on receiving the material. Later, stocking of KLT B boxes is performed and, finally,
the separation of items of replenishment.
It is object of verification that when Operator 1 performs the payment route, other
operators are focused in receiving material. Once the route is completed, all boxes that
returned from the assembly line are restocked and will return full to the assembly line,
in the next payment route. This work routine will be repeated three times daily if there
is no change in the demand by the assembly line.
If case of any changes in the client’s demand, values in the electronic spreadsheet
may be altered at any moment so that a new operator balance chart or a new work
standards sheet is organized.
After the definition of tools to be used and which stages would be approached, a
one-week training was carried with operators aiming at the use of the tools
implemented in this work. In the first day, operators were presented to basic
fundamentals of lean manufacturing and how this methodology could enhance the
performance of their daily routines by optimizing time and organizing activities. They
were also instructed about the tools revised in the literature review and each operator
received a work map and specific times in which activities should be performed. At this
point, it is important to highlight that the first reaction by operators was of doubt,
because they didn’t believe the implementation of these tools would be able to optimize
time and allow activities to be performed in a more dynamic and organized manner.
Throughout the whole of the first week, doubts that came up were properly clarified so
that the activity could be performed according to the plan from then on.
After the training period, activities continued to be monitored so that possible
improvements of the new work maps could be identified. As it can be observed in
Figure 11, the implementation of this work provided a decrease on the oscillation in
number of boxes that returned empty form the assembly line, in comparison to Figure 7.
This result is confirmed by the decrease of the coefficient of variation among the
boxes. Bin A boxes presented a coefficient of variation of 7,4% while Bin B boxes
presented 4,4%. KLT A boxes presented 14,6% variation and KLT B presented a
coefficient of variation of 12,9%. With this, it was possible to guarantee the demands
of the assembly line consistently and in a standard manner, carrying out payment of
parts according to the necessary demand, so that the daily assembly of three machines
was kept without any delays in sending boxes to the assembly line.
5. FINAL CONSIDERATIONS
The implementation of the Lean Manufacturing system made evident the
importance of this production system. It can be followed in several sectors of the
company as well as in any area of the industry, enabling the continuous enhancement
of productions processes.
With the Value Stream Mapping, it was possible to eliminate two operations that did
not add value to the product. The sum of time of both eliminated activities was around
8 seconds per box. As the daily average of boxes returned from the assembly line is
around 371 boxes, total time gained with the elimination of both activities was of
49,5 minutes per day. Time gained per month corresponds to around 18 hours.
Data collection enabled the definition of average time for each activity, based on
boxes that return empty from the assembly line and in the quantity of material received
in the warehouse. These quantities may suffer alterations according to the seasonality
or because of changes in the clients’ necessities. This way, with the information raised
in this work, if there is any change in the assembly line, it is enough that values of input
for each activity are changed. Instantly, the operator balance chart will show the current
status of the process.
To control the pace within which activities should be performed, in order to
guarantee full accomplishment in the assembly line, Takt Time and the operator
balance chart were important to indicate when routes should be carried out and the
definition of which activities each operator must perform.
The work standards sheet provided more harmony among operators throughout the
development of their activities. In each operator’s activity it is necessary that routes are
sent to the assembly line in the right moment and with the right number of stocked
boxes, avoiding supply problems.
Before carrying out this work, activities were performed disorderly, without any
standard. This generated constant bottlenecks in the area of reception and supply. With
this work, it was possible to indicate standards for activities developed and the times of
performance for each activity.
According to coefficients of variation calculated, alterations for the number of boxes
that returned empty from the line decreased in about 24% of Bin A boxes while the
variation rate in Bin B boxes reduced in 8,07%. For the cases of KLT A and KLT B
boxes, their decrease was of 23,96% and 3,56%, respectively. This way, it is evident
that there was a development of standardization and stability in the process as well as
enhancement in the continuous flow of materials, and more speed and quality when
meeting the needs of the assembly line.
Last, it is important to emphasize that, after the training week, with activities now
performed according to the new work procedures, operators were surprised because
the supply of the assembly line was organized and without any delays. In the operators’
view before the implementation of this work, full supply of the assembly would only be
REFERENCES
Alvarez, R. R., & Antunes Jr., J. A. V. (2001). Takt-time: conceitos e contextualização dentro do
Sistema Toyota de Produção. Gestão & Produção, 8(1), 1-18.
https://dx.doi.org/10.1590/S0104-530X2001000100002.
Bartz, B., Paula, A., Weise, A. D., & Ruppenthal, J. E. (2013). Aplicação da manufatura enxuta
em uma indústria de equipamentos agrícolas. Ingeniare. Revista Chilena de Ingeniería,
21(1), 147-158. http://dx.doi.org/10.4067/S0718-33052013000100013.
Collatto, D. C., Souza, M. A., Nascimento, A. P., & Lacerda, D. P. (2016). Interações,
convergências e inter-relações entre Contabilidade Enxuta e Gestão Estratégica de
Custos: Um estudo no contexto da Produção Enxuta. Gestão & Produção, 23(4), 815-827.
http://dx.doi.org/10.1590/0104-530x1279-15.
Imai, M. (2014). Gemba Kaizen: uma abordagem de bom senso à estratégia de melhoria
contínua (2. ed.). Porto Alegre: Bookman.
Iwayama, H. (1997). Basic concept of just in time system, mimeo. Curitiba, PR: IBQP-PR.
Kishida, M., Silva, A., & Guerra, E. (2006). Benefícios da implantação do trabalho padronizado
na Thyssenkrupp. Retrieved in 2018 fevereiro 02, from
http://www.lean.org.br/artigos/95/beneficios-da-implementacao-do-trabalho-padronizado-
na-thyssenkrupp.aspx
Lean Enterprise Institute (2003). Léxico Lean: glossário ilustrado para praticantes do
pensamento Lean. São Paulo: Lean Institute Brasil.
Liker, J. K., & Meier, D. (2007). O modelo Toyota: manual de aplicação. Porto Alegre:
Bookman.
Peinado, J., & Graeml, A. R. (2007). Administração da produção: operações industriais e de
serviços. Curitiba: UnicenP.
Rother, M., & Shook, J. (2003). Aprendendo a enxergar: mapeando o fluxo de valor para
agregar valor e eliminar o desperdício. São Paulo: Lean Institute Brasil.
Sabadka, D., Molnar, V., Fedorko, G., & Jachowicz, T. (2017). Optimization of production
processes using the Yamazumi method. Advances in Science and Technology Research
Journal, 11(4), 175-182. http://dx.doi.org/10.12913/22998624/80921.
Santos, R. F., & Alves, J. M. (2015). Proposta de um modelo de gestão integrada da cadeia de
suprimentos: aplicação no segmento de eletrodomésticos. Production, 25(1), 125-142.
https://dx.doi.org/10.1590/S0103-65132014005000013.
Shingo, S. (1996). O sistema Toyota de produção: Do ponto de vista da engenharia de
produção (2. ed.). Porto Alegre: Artes Médicas.
Slack, N., Chambers, S., & Johnston, R. (2002). Administração da produção (2. ed.). São
Paulo: Atlas.
Walter, O. M. F. C., & Tubino, D. F. (2013). Métodos de avaliação da implantação da
manufatura enxuta: uma revisão da literatura e classificação. Gestão & Produção, 20(1),
23-45. http://dx.doi.org/10.1590/S0104-530X2013000100003.
Wilson, L. (2010). How to implement lean manufacturing. New York: McGraw-Hill.
Womack, J. P.; Jones, D. T.; Roos, D. (1992). A máquina que mudou o mundo (13. ed.). Rio de
Janeiro: Campus.