BILL NO. 4 - EXTERNAL WORKS (ALL PROVISIONAL)
0 DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM)
ELEMENT NO. 3 - STORM WATER DRAINAGE (ALL
PROVISIONAL)
Block drain
Supply, construct and complete drains with precast concrete
block drain laid to falls, jointing and pointing in cement and
sand (1:3) including 50mm thick sand blinding,150mm thick
concrete base with a layer of BRC A6, 340mm concrete and
225mm thick cement and sand brickwall on both sides of
drain with 20mm thick cement and sand plastering at
exposed surfaces , 75mm diameter PVC pipe weephole and
125mm x 125mm RC struts at 1000mm centres , 50mm thick
drain cover and including all necessary excavation and part
return fill in and ram and cart away surplus material and
deposit, spread and level as specified all as per drawing No,
ZNA/200106/RD/02
A 300mm block drain m 81 337.63 27,347.84
Half round glazed drain
225mm (internal) Wide half round precast concrete as
described surface water drain channel including hoisting,
bedding, jointing in cement and sand and aggregate (1:3:6)
and laid to falls including all necessary excavation, 100mm
concrete bed (Grade 15) as described base and half
brickwall 500mm high (average) with and including all
necessary cement and sand (1:3) plastering to wall complete,
all as per drawing No. ZNA/200106/RD/02
B 225mm Wide drain with average depth 1200mm deep m 102 -
Brick sump
Supply, construct and complete brick sumps, constructed of
225mm thick concrete base Grade 20 with a layer of BRC
A6, 150mm thick lean concrete, 225mm thick brickwall in
common bricks with 20mm thick (1:6) cement and sand
plastering internally with 225mm thick concrete slab Grade
25 on top with and including galvanised steel grating
complete with swivel hinges and achored framing and all
necessary excavation and moulds disposal of surplus
excavated earth in within site all as shown in Drawing No.
ZNA/200106/RD/02
C Brick sumps size 450mm x 450mm (internal) not exceeding No. 9 -
exceeding 1000mm deep
B4/BQ
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISIONAL)
TO COLLECTION : 27,347.84
ELEMENT NO. 3 - STORM WATER DRAINAGE (ALL
PROVISIONAL) (Cont'd)
Sump grating
Hot dipped galvanised iron grating overall size 900mm x
900mm constructed of 55mm x 55mm x 6mm L-shape mild
steel framing mitred and filled of 55mm x 10mm thick mild
A Sump grating size 900mm -
steel flats including paintingx and
900mm to brick
setting sump infill at
in position No. 9
50mm centres complete with 12mm diamter galvanised iron
bar and including
Connection all jointed
to existing and welded galvanised iron
drainage
angle frame all round and cast to concrete with mild steel
fishtail and all necessary accessory and fitting works to
B Allow for connecting to existing surface water drainage Item - -
complete the grating as per Drawing No. ZNA/200106/RD/02.
including excavation, hacking, jointing and making good all
defected works and leave in perfect working order
Cleaning and testing
C Allow for cleaning and desilting the whole storm water Item - -
drainage system and make good all defects on completion all
to the satisfaction of the S.O.
Allow all necessary permits, licenses, etc. required from the Item - -
D relevant authorities in connection with the carrying out the
works and paid all fees, royalties on completion therewith
E Allow for any other works not listed above but shown on the
Drawings or necessary to ensure Completion of Storm Water
Drainage
a) _________________________________ Item -
b) _________________________________ Item -
c) _________________________________ Item -
TO COLLECTION : -
ELEMENT NO. 3 - STORM WATER DRAINAGE (ALL
PROVISIONAL) (Cont'd)
COLLECTION
Page No. B4/3/1 27,347.84
B4/BQ
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISIONAL)
Page No. B4/3/2 -
TOTAL ELEMENT NO.3 - STORM WATER DRAINAGE
(ALL PROVISIONAL)
- CARRIED TO SUMMARY: 27,347.84
B4/BQ
SUMMARY OF RATES BY ITEM
ITEM RATE
1 Excavation in trench RM 12.17
2 50mm sand blinding RM 6.51
3 150mm thick concrete base (1:3:6) RM 54.26
4 Concrete to both sides of drain RM 49.86
5 BRC A6 RM 18.20
6 Formwork to sides of concrete RM 18.60
7 Precast concrete block drain RM 30.43
8 225mm thick brickwall RM 43.08
9 20mm thick cement and sand (1:6) plastering RM 8.10
10 75mm diameter weephole at 1m interval RM 10.88
11 125mm x 125mm precast RC struts RM 26.11
12 PC cover slab RM 15.40
Total rate for block drain = RM 293.59
Allow 15% profit and overhead = RM 44.04
RM 337.63
Average depth for block drain = 600mm
Average width for trench = 100+340+300+300+340+100
= 1480 mm
1. Excavation in trench
Source JKH 2019
1) Adjustment to cost index
CURRENT INDEX
BASE YEAR BASE INDEX BASE PRICE CURRENT PRICE
(YEAR 2020)
2019 171.90 171.90 RM 13.70 RM 13.70
Adjusted rate = RM13.70/m3 x 171.90
171.90
= RM 13.70 /m3
2) Rate/m
Average depth for block drain = 600mm
Average width for trench = 100+340+300+300+340+100
= 1480 mm
Cost of excavation/m = Rate/m3 Quantity New rate
RM 13.70 x 1m x 1.48m x 0.6m = RM 12.17
2. Sand blinding: 50mm thick sand blinding
Source JKH 2019
1) Adjustment to cost index
CURRENT INDEX
BASE YEAR BASE INDEX BASE PRICE CURRENT PRICE
(YEAR 2020)
2019 171.90 171.90 RM 4.40 RM 4.40
Adjusted rate = RM4.40/m2 x 171.90
171.9
= RM 4.40 /m2
2) Rate/m
Width for sand blinding = 1480mm
Cost of sand blinding/m = Rate/m2 Quantity New rate
RM 4.40 x 1m x 1.48m = RM 6.51
3. Concrete base : 150mm thick concrete base
Source JKH 2019
1) Adjustment to cost index
CURRENT
INDEX
BASE YEAR BASE INDEX BASE PRICE CURRENT PRICE
(YEAR
2020)
2019 171.90 171.90 RM 244.40 RM 244.40
Adjusted rate = RM268.00/m3 x 171.90
171.9
= RM 244.40 /m3
2) Rate/m
Thickness of concrete base = 150mm
Width for concrete base = 1480mm
Cost of concrete base/m = Rate/m3 Quantity New rate
RM 244.40 x 1m x 1.48m x 0.15m = RM 54.26
4. Concrete to both sides of drain : 340mm concrete on both sides of drain
Source JKH 2019
1) Adjustment to cost index
CURRENT INDEX
BASE YEAR BASE INDEX (YEAR 2020) BASE PRICE CURRENT PRICE
2019 171.90 171.90 RM 244.40 RM 244.40
Adjusted rate = RM244.40/m3 x 171.90
171.9
= RM 244.40 /m3
2) Rate/m
Average height of concrete = 300mm
Width for concrete = 340mm
Nos. of conrete = 2 sides of drain
Cost of concrete base/m = Rate/m3 Quantity New rate
RM 244.40 x 2 (1m x 0.34m x 0.3m) = RM 49.86
5. BRC : 150mm thick concrete base with a layer of BRC A6
Source JKH 2019
1) Adjustment to cost index
CURRENT
BASE YEAR BASE INDEX INDEX (YEAR BASE PRICE CURRENT PRICE
2020)
2019 171.90 171.90 RM 12.30 RM 12.30
Adjusted rate = RM12.30/m2 x 171.90
171.9
= RM 12.30 /m2
2) Rate/m
Width for BRC = 1480mm
Cost of BRC/m = Rate/m2 Quantity New rate
RM 12.30 x 1m x 1.48m = RM 18.20
6. Formwork
Source JKH 2019
1) Adjustment to cost index
CURRENT
BASE YEAR BASE INDEX INDEX (YEAR BASE PRICE CURRENT PRICE
2020)
2019 171.90 171.90 RM 31.00 RM 31.00
Adjusted rate = RM31.00/m2 x 171.90 1m
171.9
= RM 31.00 /m2
2) Rate/m 0.3m
Cost of Formwork/m = Rate/m2 Quantity New rate
RM 31.00 x 2(1m x 0.3m) = RM 18.60
6. Precast block drain: 300mm precast concrete block drain laid to falls, jointing and pointing in cement and sand (1:3)
Source Quotation from supplier Source JADUAL ANGGRAN HARGA 2019
1) Adjustment to cost index
BASE YEAR BASE INDEX CURRENT INDEX BASE PRICE CURRENT PRICE BASE YEAR BASE INDEX CURRENT INDEX BASE PRICE CURRENT PRICE REMARK
(YEAR 2020) (YEAR 2020)
2017 165.18 171.9 RM 11.60 RM 12.07 RM 80.00 RM 80.00 Drainlayer wage
2019 171.90 171.90 RM 65.00 RM 65.00 General worker wage
RM 18.30 RM 18.30 Cost of cement/bag
2) Rate/m RM 52.50 RM 52.50 Cost of sand /m3
Mortar
a) Material cost
1m3 cement = (1400kg/50kg) x RM 18.30/bag = RM 512.40
3m3 sand = 3 x RM 52.50/m3 = RM 157.50
RM 669.90
Allow 50% shrinkage & wastage = RM 669.90 x 50% = RM 334.95 /m3
Cost for 4m3 mortar = RM 1,004.85
Material cost/m3 for mortar = RM 1004.85 / 4m3 = RM 251.21 /m3
b)Labour cost
General worker for mixing mortar = 2hrs x RM 65.00/8hrs = RM 16.25 /m3
Total cost/m3 for mortar = RM 251.21+RM 16.25 = RM 267.46
Material cost
Drain = (1m/0.6m) x RM 12.07/pc = RM 20.12
Mortar = 0.025m3 x RM 267.46/m3 = RM 6.69
RM 26.80
Labour cost
Drainlayer = 0.2 hr xRM 80.00/8hrs = RM 2.00
General worker = 0.2 hr xRM 65.00/8hrs = RM 1.63
Cost for labour RM 3.63
Total cost for 1m block drain = RM 30.43
8. Brickwall : 225mm thick cement and sand brickwall on both sides of drain
Source JKH 2019
1) Adjustment to cost index
CURRENT
BASE YEAR BASE INDEX INDEX (YEAR BASE PRICE CURRENT PRICE
2020)
2019 171.90 171.90 RM 71.80 RM 71.80
Adjusted rate = RM71.80/m2 x 171.90
171.9
= RM 71.80 /m2
2) Rate/m
Avarage height of brickwall = 300mm
Position of brickwall = Both sides of drain
Cost of brickwall/m = Rate/m2 Quantity New rate
RM 71.80 x 2(1m x 0.3m) = RM 43.08
9. Plastering: 20mm thick cement and sand plastering at exposed surfaces
Source JKH 2019
1) Adjustment to cost index
CURRENT
BASE YEAR BASE INDEX INDEX (YEAR BASE PRICE CURRENT PRICE
2020)
2019 171.90 171.90 RM 11.30 RM 11.30
Adjusted rate = RM11.30/m2 x 171.90
171.9
= RM 11.30 /m2
2) Rate/m
Height of brickwall = 300mm
Cost of brickwall/m = Rate/m2 Quantity New rate
RM 11.30 x 2(1m x 0.3m) = RM 6.78
Source JADUAL ANGGRAN HARGA 2019
1) Adjustment to cost index
CURRENT
BASE YEAR BASE INDEX INDEX (YEAR BASE PRICE CURRENT PRICE
2020)
2019 171.90 171.90 RM 15.70 RM 15.70
Adjusted rate = RM15.70/m2 x 171.90
171.9
= RM 15.70 /m2
2) Rate/m
Height of brickwall = 300mm
Cost of brickwall/m = Rate/m2 Quantity New rate
RM 15.70 x 2(1m x 0.3m) = RM 9.42
Average rate
Average rate = RM 6.78 + RM 9.42
2
= RM 8.10
8. Weephole: 75mm diameter PVC pipe weephole
Source Project reference (Retaining wall, 2019)
1) Adjustment to cost index
CURRENT
BASE YEAR BASE INDEX INDEX (YEAR BASE PRICE CURRENT PRICE
2020)
2019 171.90 171.90 RM 14.50 RM 14.50
Adjusted rate = RM14.50/nos x 171.90
171.9
= RM 14.50 /nos
2) Adjustment to diameter of uPVC pipe
Proposed weephole = 75mm diameter
Cost of weephole/m= Rate/m Adjustment New rate
RM 14.50 x 75mm/100mm = RM 10.88
11. RC strut: 125mm x 125mm RC struts at 1000mm centres
Source JKH 2019 Table 1 : Quantity for items in strut
Item Unit Calculation
Grade 20 concrete m3 Volume =0.7x 0.13 x 0.13
=0.01
4R10 as main bars kg Length = 4(50+700+50) =3200mm
Total kg =3.2m x 0.616kg/m
Concrete = 1.97 kg
R6 @ 100 c/c as links kg Nr= (700/100) + 1
=8
Length = 4(125) + 24(6) = 644mm
Total kg =5.15m x 0.222kg/m
=1.14 kg
Rebar Formwork to sides and soffit m2 Area = 3(0.7x 0.13) + 2 (0.13x 0.13)
=0.31
Formwork
1) Rate/m
Nos of RC strut for 1m block drain = 1 nos
Rate of RC strut in 1 nos
Item Unit Qtty (refer Table 1) Rate Cost (RM)
Grade 20 concrete m3 0.01 RM 334.00 3.34
4R10 as main bars kg 1.97 RM 3.70 7.29
R6 @ 100 c/c as links kg 1.14 RM 3.60 4.10
Formwork to sides and soffit m2 0.31 RM 36.70 11.38
26.11
Total cost for 1 RC strut at 1000mm intervals = RM 26.11
2) Adjustment to cost index
CURRENT INDEX
BASE YEAR BASE INDEX BASE PRICE CURRENT PRICE
(YEAR 2020)
2019 171.90 171.90 RM 26.11 RM 26.11
Adjusted rate = RM 26.11/nos x 171.90
171.90
= RM 26.11 /nos
Qtty
0.01
1.97
1.14
0.31
12. PC cover slab: 50mm thick drain cover
Source JKH 2019
1) Adjustment to cost index
CURRENT INDEX
BASE YEAR BASE INDEX BASE PRICE CURRENT PRICE
(YEAR 2020)
2019 171.90 171.90 RM 15.40 RM 15.40
Adjusted rate = RM15.40/m x 171.90
171.90
= RM 15.40 /m
List of reference
1. Locality factor
Source Public Works Cost Information Centre (PWCIC)
2. Cost index
Source JUBM &ARCADIS Construction Cost Handbook MALAYSIA 2020
Year Q1 Q2 Q3 Q4 Average
2017 163.1 164.7 167.8 165.1 165.18
2019 - - - 171.90 171.90
2020 - - - - 171.90
3. Reference for rates
Books
No. Project title Year
1 Jadual Kadar Harga (JKH) by Jabatan Kerja Raya 2019
2 Jadual Anggaran Harga Kerja-kerja Infra dan Bangunan by BSSB Mahajaya Resources 2019
Past project
No. PROPOSED LOCAL INFRASTRUCTURE WORKS FOR Project title
CADANGAN PEMBANGUNAN YANG MENGANDUNGI: Year
a) 132 PLOT (264 UNIT) RUMAH MAMPU MILIK JENIS 'TOWNHOUSE'(20' X 70')STRATA - PLOT 001 - PLOT
132
1 b) 1 UNIT PENCAWANG ELEKTRIK (DOUBLE CHAMBER) DI ATAS PLOT 133 2019
DI ATAS SEBAHAGIAN LOT PTD 171011,
BESTARI PERDANA, MUKIM PLENTONG, JOHOR BAHRU, JOHOR DARUL TAKZIM (MERIDIN EAST - RMMJ
1)
Quotation
No. Project title Year
1 Quotation by HSA Setiamurni Sdn.Bhd. 2017