e-Support Filename: TP10 287.
pdf
Date: 10-19-10
PRODUCTS AFFECTED / SERIAL NUMBERS AFFECTED:
iPF650/655/750/755
SUBJECT:
Purge Unit
GENERAL:
This Technical Publication describes the changes made in the shape of the waste ink joint section of the
Purge Unit for improved cleaning function.
DETAILS:
The shape of the waste ink joint section of the Purge Unit has been changed so that there is no elevated area
in the drain route.
This will improve the ink drainage in the ink tubes and, therefore, will improve the cleaning function.
Before After
Area of elevated waste
ink drain tubes
Ink drain route after change
New ink drain route
QC3-1931-000 TUBE CLAMP
QC3-1928-000 DRAIN JOINT
BASE
QC3-1928-000 DRAIN JOINT A
QC3-1930-000 DRAIN JOINT B
THIS TECHNICAL PUBLICATION IS THE PROPERTY OF CANON U.S.A. INC. AND CONTAINS CONFIDENTIAL INFORMATION OWNED BY OR LICENSED TO,
CANON U.S.A., AUTHORIZED CANON U.S.A., DEALERS MAY USE THIS TECHNICAL PUBLICATION FOR REFERENCE PURPOSES ONLY. ANY OTHER USE
BY AN AUTHORIZED CANON USA DEALER, OR USE BY ANY THIRD PARTY, IS PROHIBITED.
For additional technical information, please visit the Canon Systems and Technical Support Division website at:
www.support.cusa.canon.com. You can also call the Technical Support Center at 1-800-528-2830 or contact your Regional Support Office.
Page 1 of 6
e-Support Filename: TP10 287.pdf
Date: 10-19-10
1. Parts
Purge Kit (QM3-5988-000) No. 1 in the table below, which contains the parts in No. 2-6; have been
assigned as service parts. These parts are for retaining the compatibility with the old joints.
Note:
For the main body with the old joint, when replacing the Purge Unit, the said bundled parts
should also be replaced at the same time.
For the main body with new joint installed, there is no need to replace the joint afterwards.
FIGURE&
No. Part name Part no. Q’ty Remarks
KEY NO
O PURGE UNIT QM3-5834-010 1 → 0 Fig5-11
1
Parts 2-6 are
N PURGE KIT QM3-5988-000 0 → 1 Fig5-11
included
Included in the
2 N DRAIN JOINT BASE QC3-1928-000 0→1
PURGE KIT
Included in the
3 N DRAIN JOINT A QC3-1929-000 0→1
PURGE KIT
Included in the
4 N DRAIN JOINT B QC3-1930-000 0→1
PURGE KIT
Included in the
5 N TUBE CLAMP QC3-1931-000 0→1
PURGE KIT
Included in the
6 N DRAIN JOINT TAPE QC3-1939-000 0→1
PURGE KIT
2. Installation procedure of new Purge Unit
A. Remove the Purge Unit.
(See Chapter 4 Purge Unit, in the Service Manual).
Page 2 of 6
e-Support Filename: TP10 287.pdf
Date: 10-19-10
B. Install the Drain Joint Base (QC3-1928-000) to the frame with the Drain Joint Tape (QC3-
1939-000)
C. Position to affix the double-sided tape
QC3-1939-000 Area where joint should be placed.
DRAIN JOINT TAPE
Area
Note: Tape should not stick out
past the base.
Page 3 of 6
e-Support Filename: TP10 287.pdf
Date: 10-19-10
D. Remove the transparent tubes from the old joint connected to the main body.
Remove transparent
tubes from old joint
connector.
E. Cut the tubes to the appropriate length.
No. Tube identification Cut length
(1) Small tube internal 38mm±1 mm from the
diameter - Black side leading end
(2) Large tube internal 13mm±1 mm from the
diameter - Color side leading end
Page 4 of 6
e-Support Filename: TP10 287.pdf
Date: 10-19-10
F. Tube Clamp (QC3-1931-000) should only be mounted to the large diameter Color side tube.
Tube Clamp (QC3-1931-000)
Large tube internal
diameter - Color side
Small tube internal
diameter - Black side
G. Install the new Purge Unit.
H. Install each joint to the Drain Joint Base as described above.
Note: Ensure the tubes are fully inserted.
Tube installation position.
(1) Black tube from new Purge Unit: no marking at the leading end → Color side
(2) Black tube from new Purge Unit: white marking at the leading end → Black side
(3) Transparent tube connected to main body: large internal diameter → Color side
(4) Transparent tube connected to main body: small internal diameter → Black side
(1) (3)
(2)
(4)
Page 5 of 6
e-Support Filename: TP10 287.pdf
Date: 10-19-10
3. Precautions for Purge Unit replacement.
When removing the Purge Unit, remove the tubes from the joint sections that are indicated below.
When installing the new Purge Unit, install the tubes at the joint sections in the same order. Ensure
that the tube with the white mark is installed under the other tube.
Tubes should be removed
and replaced in the same
order. (Color side)
Tube with white mark
should be below the
other tube. (Black side)
Serial numbers of switch over,
iPF650 AACF0001 and later
iPF650 AAAP1185 and later
iPF655 AACU0001 and later
iPF655 AAAW0138 and later
iPF750 AABY0001 and later
iPF750 AAAB2534 and later
iPF755 AACM0001 and later
iPF755 AAAH1268 and later
Page 6 of 6