Control Cable Stage-2

This document provides details of cable terminations for various equipment in a substation, including: 1. Cable sizes, routes, and lengths for connections between the isolation panel and control relay panel. 2. Phase wise cable connections from metering transformers to two different metering units, including core designations. 3. Interlock and remote operation cable connections from the isolation panel to the control relay panel and isolation transformer.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
109 views36 pages

Control Cable Stage-2

This document provides details of cable terminations for various equipment in a substation, including: 1. Cable sizes, routes, and lengths for connections between the isolation panel and control relay panel. 2. Phase wise cable connections from metering transformers to two different metering units, including core designations. 3. Interlock and remote operation cable connections from the isolation panel to the control relay panel and isolation transformer.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 36

Annexure

1.1KV PVC ARMOURED COPPER CABLE


TERMINATION DETAILS
From TO

NO. OF CABLE
Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE RUN USED PURPOSE Dia ROUTE Length

SS07, SS06,
ISO (Motor Operating SS05, SS04,
1 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS02, SS01, 175
OD01, SR3, SR4,
SR5, SR6, SR7

SS07, SS06,
ISO (Motor Control SS05, SS04,
2 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SS02, SS01, 175
OD01, SR3, SR4,
SR5, SR6, SR7
ISO-1 (132kV)

3 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 SS07, P3 27


Panel) Conduit

SS07, SS06,
SS05, SS04,
ISO (Motor Control
4 CRP 4CX2.5 mm² 1 Remote Operation 16 SS02, SS01, 175
Panel) OD01, SR3, SR4,
SR5, SR6, SR7

ISO (Motor Control


5 Panel) ISO-1 (E.S) 4CX2.5 mm² 1 Interlock 16 21

1 1a
(MPT CORE-1) SPARE
2 1n
6 MPT (R-PH) TVM-1 4CX2.5 mm² 1 16 15
3 2a
(MPT CORE-2) METERING
4 2n
1 1a
(MPT CORE-1) SPARE
2 1n
7 MPT (Y-PH) TVM-1 4CX2.5 mm² 1 16 15
3 2a
(MPT CORE-2) METERING
4 2n
1 1a
(MPT CORE-1) SPARE
2 1n
8 MPT (B-PH) TVM-1 4CX2.5 mm² 1 16 15
3 2a
(MPT CORE-2) METERING
4 2n
MPT
1 1a
(MPT CORE-1) SPARE
2 1n
9 MPT (R-PH) TVM-2 4CX2.5 mm² 1 16 15
3 2a
(MPT CORE-2) METERING
4 2n
1 1a
(MPT CORE-1) SPARE
2 1n
10 MPT (Y-PH) TVM-2 4CX2.5 mm² 1 16 15
3 2a
(MPT CORE-2) METERING
4 2n
1 1a
(MPT CORE-1) SPARE
2 1n
11 MPT (B-PH) TVM-2 4CX2.5 mm² 1 16 15
3 2a
(MPT CORE-2) METERING
MPT

TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED
11 MPT (B-PH) TVM-2 4CX2.5 mm² 1 16 15
(MPT CORE-2) METERING
4 2n
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1 1S1
(MPT CORE-1) SPARE
2 1S2
12 MCT (R-PH) TVM-1 4CX2.5 mm² 1 16 15
3 2S1
(MPT CORE-2) METERING
4 2S2
1 1S1
(MCT CORE-1) SPARE
2 1S2
13 MCT (Y-PH) TVM-1 4CX2.5 mm² 1 16 15
3 2S1
(MCT CORE-2) METERING
4 2S2
1 1S1
(MCT CORE-1) SPARE
2 1S2
14 MCT (B-PH) TVM-1 4CX2.5 mm² 1 16 15
3 2S1
(MCT CORE-2) METERING
4 2S2
MCT
1 1S1
(MPT CORE-1) SPARE
2 1S2
15 MCT (R-PH) TVM-2 4CX2.5 mm² 1 16 15
3 2S1
(MPT CORE-2) METERING
4 2S2
1 1S1
(MCT CORE-1) SPARE
2 1S2
16 MCT (Y-PH) TVM-2 4CX2.5 mm² 1 16 15
3 2S1
(MCT CORE-2) METERING
4 2S2
1 1S1
(MCT CORE-1) SPARE
2 1S2
17 MCT (B-PH) TVM-2 4CX2.5 mm² 1 16 15
3 2S1
(MCT CORE-2) METERING
4 2S2

SS06, SS05,
SS04, SS02,
ISO (Motor Operating
18 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS01, OD01, 165
SR3, SR4, SR5,
SR6, SR7

SS06, SS05,
SS04, SS02,
19 ISO (Motor Control CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SS01, OD01, 165
Panel) SR3, SR4, SR5,
ISO-2 (132kV)
SR6, SR7

20 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 40


Panel)

SS06, SS05,
SS04, SS02,
21 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 SS01, OD01, 165
Panel)
SR3, SR4, SR5,
SR6, SR7
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
22 4CX2.5 mm² 1 16 10
3 2S1
(CT1 CORE-2) METERING
4 2S2
CT (200/1-1-1-1A) CT-JB (R-PH)
5 3S1
SPARE
6 3S2
23 4CX2.5 mm² 1 16 10
5 3S1
SPARE
6 3S2
1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
24 4CX2.5 mm² 1 16 10
3 2S1
(CT1 CORE-2) METERING
4 2S2
CT (200/1-1-1-1A) CT-JB (Y-PH)
5 3S1
SPARE
132kV CT-1 6 3S2
25 4CX2.5 mm² 1 16 10
SPARE

1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
26 4CX2.5 mm² 1 16 10
3 2S1
(CT1 CORE-2) METERING
4 2S2
CT (200/1-1-1-1A) CT-JB (B-PH)
5 3S1
SPARE
6 3S2
27 4CX2.5 mm² 1 16 10
SPARE

28 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-1) PROTECTION 16 SS07, SS06, 145
SS05, SS04,
SS02, SS01,
29 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-2) METERING 16 OD01, SR3, SR4, 145
SR5, SR6, SR7
SS06, SS05,
30 CB-52 (Line) CRP 1 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SS04, SS02, 155
31 132kV CB-1 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-1 26 SS01, OD01, 155
32 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-2 26 SR3, SR4, SR5, 155
SR6, SR7
SS06, SS05,
SS04, SS02,
ISO (Motor Operating
33 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS SS01, OD01, 150
SR3, SR4, SR5,
SR6, SR7

SS06, SS05,
ISO (Motor Control SS04, SS02,
34 CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS SS01, OD01, 150
Panel)
ISO-3 (132kV) 26 SR3, SR4, SR5,
SR6, SR7

ISO (Motor Control


35 Panel) CB 4CX2.5 mm² 1 Interlock 27
TERMINATION DETAILS
From TO
ISO-3 (132kV) 26

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

SS06, SS05,
SS04, SS02,
ISO (Motor Control SS01, OD01,
36 Panel) CRP 4CX2.5 mm² 1 Remote Operation 150
SR3, SR4, SR5,
SR6, SR7
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1 1a
(BPT CORE-1) Protection
2 1n
37 BPT BPT-JB (R-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
1 1a
(BPT CORE-1) Protection
2 1n
38 BPT BPT-JB (Y-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
132kV Line 1 1a
PT (BPT CORE-1) Protection
1n
39 BPT BPT-JB (B-PH) 4CX2.5 mm² 1 16 10
1 2a
(BPT CORE-2) METERING
2n

40 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-1) METERING 16 SS06, SS05, 160
SS04, SS02,
SS01, OD01,
SR3, SR4, SR5,
41 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-2) Protection 16 SR6, SR7 160

1 1a
(BPT CORE-1) Protection
2 1n
42 BPT BPT-JB (R-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
1 1a
(BPT CORE-1) Protection
2 1n
43 BPT BPT-JB (Y-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
132kV BPT 1 1a
(BPT CORE-1) Protection
1n
44 BPT BPT-JB (B-PH) 4CX2.5 mm² 1 16 10
1 2a
(BPT CORE-2) METERING
2n

45 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-1) METERING 16 SS06, SS05, 160
SS04, SS02,
SS01, OD01,
SR3, SR4, SR5,
46 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-2) Protection 16 SR6, SR7 160

47 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS05, SS04, 140
Mechanism) SS02, SS01,
OD01, SR3, SR4,
ISO (Motor Control SR5, SR6, SR7
48 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 140

ISO-4 (132kV) ISO (Motor Control


49 CB 4CX2.5 mm² 1 Interlock 16 40
Panel)

SS05, SS04,
ISO (Motor Control SS02, SS01,
50 CRP 4CX2.5 mm² 1 Remote Operation 16 140
Panel) OD01, SR3, SR4,
SR5, SR6, SR7
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

ISO (Motor Operating SS06, SS05,


51 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS04, SS02, 150
SS01, OD01,
SR3, SR4, SR5,
52 ISO (Motor Control CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SR6, SR7 150
Panel)

ISO-5 (132kV) ISO (Motor Control


53 Panel) CB 4CX2.5 mm² 1 Interlock 16 27

SS06, SS05,
SS04, SS02,
54 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 SS01, OD01, 150
Panel) SR3, SR4, SR5,
SR6, SR7
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
55 CT (100/1-1-1-1A) CT-JB (R-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 60
7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
56 CT (100/1-1-1-1A) CT-JB (Y-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
132kV CT-2 7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
57 CT (100/1-1-1-1A) CT-JB (B-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
58 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-1) METERING 16 SS06, SS05, 160
SS04, SS02,
59 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-2) PROTECTION 16 SS01, OD01, 160
SR3, SR4, SR5,
60 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-3) 87 16 SR6, SR7 160

61 CB-52 (Trafo-1) CRP 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 130


SS05, SS04,
62 132kV CB-2 CB-52 (Trafo-1) CRP 19CX2.5 mm² 1 TC-1 26 SS02, SS01, 130
OD01, SR3, SR4,
SR5, SR6, SR7
63 CB-52 (Trafo-1) CRP 19CX2.5 mm² 1 TC-2 26 130
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

SS05, SS04,
64 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS02, SS01, 140
Mechanism) OD01, SR3, SR4,
SR5, SR6, SR7

SS05, SS04,
ISO (Motor Control SS02, SS01,
65 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 OD01, SR3, SR4, 140
ISO-6 (132kV) SR5, SR6, SR7

ISO (Motor Control


66 CB 4CX2.5 mm² 1 Interlock 16 27
Panel)

SS05, SS04,
ISO (Motor Control SS02, SS01,
67 CRP 4CX2.5 mm² 1 Remote Operation 16 140
Panel) OD01, SR3, SR4,
SR5, SR6, SR7

1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
68 CT (100/1-1-1-1A) CT-JB (R-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
69 CT (100/1-1-1-1A) CT-JB (Y-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
132kV CT-3 7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
70 CT (100/1-1-1-1A) CT-JB (B-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
71 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-1) METERING 16 135
SS05, SS04,
72 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-2) PROTECTION 16 SS02, SS01, 135
OD01, SR3, SR4,
SR5, SR6, SR7
73 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-3) 87 16 135
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

74 CB-52 (Trafo-2) CRP 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 130


SS05, SS04,
75 132kV CB-3 CB-52 (Trafo-2) CRP 19CX2.5 mm² 1 TC-1 26 SS02, SS01, 130
OD01, SR3, SR4,
SR5, SR6, SR7
76 CB-52 (Trafo-2) CRP 19CX2.5 mm² 1 TC-2 26 130

ISO (Motor Operating SS03, SS02,


77 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 115
SS01, OD01,
SR3, SR4, SR5,
ISO (Motor Control SR6, SR7
78 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 115

79 ISO-7 (132kV) ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 27


Panel)

SS03, SS02,
ISO (Motor Control SS01, OD01,
80 CRP 4CX2.5 mm² 1 Remote Operation 16 115
Panel) SR3, SR4, SR5,
SR6, SR7

1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
81 CT (100/1-1-1-1A) CT-JB (R-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
82 CT (100/1-1-1-1A) CT-JB (Y-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
132kV CT-4 7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
83 CT (100/1-1-1-1A) CT-JB (B-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
84 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-1) METERING 16 130
SS05, SS04,
85 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-2) PROTECTION 16 SS02, SS01, 130
OD01, SR3, SR4,
SR5, SR6, SR7
86 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-3) 87 16 130
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

87 CB-52 (Trafo-2) CRP 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 110


SS03, SS02,
88 132kV CB-4 CB-52 (Trafo-2) CRP 19CX2.5 mm² 1 TC-1 26 SS01, OD01, 110
SR3, SR4, SR5,
89 CB-52 (Trafo-2) CRP 19CX2.5 mm² 1 TC-2 26 SR6, SR7 110

SS03, SS02,
90 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS01, OD01, 115
Mechanism) SR3, SR4, SR5,
SR6, SR7

SS03, SS02,
ISO (Motor Control SS01, OD01,
91 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SR3, SR4, SR5, 115
ISO-8 (132kV) SR6, SR7

ISO (Motor Control


92 Panel) CB 4CX2.5 mm² 1 Interlock 16 27

SS03, SS02,
93 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 SS01, OD01, 115
Panel) SR3, SR4, SR5,
SR6, SR7
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
94 CT (100/1-1-1-1A) CT-JB (R-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
95 CT (100/1-1-1-1A) CT-JB (Y-PH)
5 3S1
(CT CORE-3) 87
6 3S2
132kV CT-5 4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
1 1S1
(CT CORE-1) METERING
2 1S2
4CX2.5 mm² 1 16 10
3 2S1
(CT CORE-2) PROTECTION
4 2S2
96 CT (100/1-1-1-1A) CT-JB (B-PH)
5 3S1
(CT CORE-3) 87
6 3S2
4CX2.5 mm² 1 16 10
7 4S1
(CT CORE-4) Spare
8 4S2
97 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-1) METERING 16 SS03, SS02, 110
SS01, OD01,
98 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-2) PROTECTION 16 SR3, SR4, SR5, 110
SR6, SR7
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia SS03, SS02,
ROUTE Length
RUN USED SS01, OD01,
SR3, SR4, SR5,
99 CT-JB CRP 4CX2.5 mm² 1 (CT CORE-3) 87 16 SR6, SR7 110
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

100 CB-52 (Trafo-2) CRP 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 110


SS03, SS02,
101 132kV CB-5 CB-52 (Trafo-2) CRP 19CX2.5 mm² 1 TC-1 26 SS01, OD01, 110
SR3, SR4, SR5,
102 CB-52 (Trafo-2) CRP 19CX2.5 mm² 1 TC-2 26 SR6, SR7 110
1
2
3
4
5
6
7
8 19CX2.5 mm² 1 26 100
9
10
SS15, SS14,
OLTC Terminal (18MVA 11 SS12, SS10,
103 Trafo.-1 RTCC-1
Trafo.-1) 12 SS08, SS01,
OD01, SR3
13
14
15
16
17
18
19 10CX2.5 mm² 1 22 100
20
21
22
1
2
3
4
5
6
7
8 19CX2.5 mm² 1 26 90
9
10
SS13, SS12,
OLTC Terminal (20MVA 11 SS10, SS08,
104 Trafo.-2 Trafo.-2) RTCC-2 SS01, OD01,
12
SR3
13
14
15
16
17
18
19 10CX2.5 mm² 1 22 90
20
SS13, SS12,
104 Trafo.-2 OLTC Terminal (20MVA RTCC-2 SS10, SS08,
Trafo.-2) SS01, OD01,
SR3

TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
10CX2.5 mm² RUN 1USED 22 90

21
22
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1
2
3
4
5
6
7
8 19CX2.5 mm² 1 26 75
9
10
OLTC Terminal (20MVA 11 SS11, SS10,
105 Trafo.-3 RTCC-3 SS08, SS01,
Trafo.-3) 12 OD01, SR3
13
14
15
16
17
18
19 10CX2.5 mm² 1 22 75
20
21
22
1
2
3
4
5
6
7
8 19CX2.5 mm² 1 26 65
9
10
11 SS09, SS08,
OLTC Terminal (18MVA
106 Trafo.-4 Trafo.-4) RTCC-4 SS01, OD01,
12 SR3
13
14
15
16
17
18
19 10CX2.5 mm² 1 22 65
20
21
22
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1
WTI (Alarm)
2
3
WTI (Trip)
4
10CX2.5 mm² 1 22 125
7
OTI (Alarm)
8
9
OTI (Trip)
10
11
BR (Alarm)
12 SS15, SS14,
Marshaling Box (18MVA 13 SS12, SS10,
107 Trafo.-1 CRP BR (Trip) SS08, SS01,
Trafo.-1) 14 OD01, SR3, SR4,
15 SR5, SR7, SR8
12CX2.5 mm² 1 MOG (Alarm) 22 125
16
17
PRV (Trip)
18
19
OSR (Trip)
20
21
NCT
22
4CX2.5 mm² 1 16 125
23
NCT
24
1
WTI (Alarm)
2
3
WTI (Trip)
4
10CX2.5 mm² 1 22 115
7
OTI (Alarm)
8
9
OTI (Trip)
10
11
BR (Alarm)
12 SS13, SS12,
13 SS10, SS08,
Marshaling Box (20MVA
108 Trafo.-2 Trafo.-2) CRP BR (Trip) SS01, OD01,
14 SR3, SR4, SR5,
15 SR7, SR8
12CX2.5 mm² 1 MOG (Alarm) 22 115
16
17
PRV (Trip)
18
19
OSR (Trip)
20
21
NCT
22
4CX2.5 mm² 1 16 115
23
NCT
24
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1
WTI (Alarm)
2
3
WTI (Trip)
4
10CX2.5 mm² 1 22 100
7
OTI (Alarm)
8
9
OTI (Trip)
10
11
BR (Alarm)
12
SS11, SS10,
Marshaling Box (20MVA 13 SS08, SS01,
109 Trafo.-3 CRP BR (Trip)
Trafo.-3) 14 OD01, SR3, SR4,
SR5, SR7, SR8
15
12CX2.5 mm² 1 MOG (Alarm) 22 100
16
17
PRV (Trip)
18
19
OSR (Trip)
20
21
NCT
22
4CX2.5 mm² 1 16 100
23
NCT
24
1
WTI (Alarm)
2
3
WTI (Trip)
4
10CX2.5 mm² 1 22 90
7
OTI (Alarm)
8
9
OTI (Trip)
10
11
BR (Alarm)
12
SS09, SS08,
Marshaling Box (18MVA 13 SS01, OD01,
110 Trafo.-4 Trafo.-4) CRP BR (Trip) SR3, SR4, SR5,
14
SR7, SR8
15
12CX2.5 mm² 1 MOG (Alarm) 22 90
16
17
PRV (Trip)
18
19
OSR (Trip)
20
21
NCT
22
4CX2.5 mm² 1 16 90
23
NCT
24
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1
WTI (Alarm)
2
3
WTI (Trip) SS18, SS17,
4 Conduit, SS01,
10CX2.5 mm² 1 22 OD01, SR3, SR4, 85
7
OTI (Alarm) SR5
8
250 kVA Marshaling Box (250 11kV HT 9
111 OTI (Trip)
Trafo. kVA Trafo.-1) Switchgear 10
11
BR (Alarm)
12
SS18, SS17,
13 Conduit, SS01,
10CX2.5 mm² 1 BR (Trip) 22 85
14 OD01, SR3, SR4,
SR5
15
MOG (Alarm)
16
1
WTI (Alarm)
2
3
WTI (Trip) SS18, SS17,
4 Conduit, SS01,
10CX2.5 mm² 1 22 80
7 OD01, SR3, SR4,
OTI (Alarm) SR5
8
250 kVA Marshaling Box (250 11kV HT 9
112 Trafo. kVA Trafo.-2) Switchgear OTI (Trip)
10
11
BR (Alarm)
12
SS18, SS17,
13 Conduit, SS01,
10CX2.5 mm² 1 BR (Trip) 22 80
14 OD01, SR3, SR4,
SR5
15
MOG (Alarm)
16
1
NO
11kV HT 2
113 LPBS-1 4CX2.5 mm² 1 16 PH02, SR5, SR4 40
Switchgear 3
NC
4
1
NO
11kV HT 2 PH04, SR6, SR5,
114 LPBS-2 Switchgear 4CX2.5 mm² 1 16 SR4 45
3
NC
4
1
NO
11kV HT 2 PH06, SR7, SR6,
115 LPBS-3 4CX2.5 mm² 1 16 50
Switchgear 3 SR5, SR4
NC
4
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1
NO
11kV HT 2 PH08, SR8, SR7,
116 LPBS-4 Switchgear 4CX2.5 mm² 1 16 SR6, SR5, SR4 55
3
NC
4
1
NO PH10, SR9, SR8,
11kV HT 2
117 LPBS-5 4CX2.5 mm² 1 16 SR7, SR6, SR5, 60
Switchgear 3
NC SR4
4
3
Feedback
4
3600kW 11kV FCMA 11kV HT 5
118 10CX2.5 mm² 1 Start PermiSS0ive 22 SR6, SR5, SR4 34
Soft Starter-1 Switchgear 6
7
Shunt Trip Ckt.
8
3
Feedback
4
3600kW 11kV FCMA 11kV HT 5
119 10CX2.5 mm² 1 Start PermiSS0ive 22 SR6, SR5, SR4 34
Soft Starter-2 Switchgear 6
7
Shunt Trip Ckt.
8
3
Feedback
4
3600kW 11kV FCMA 11kV HT 5
120 Soft Starter-3 Switchgear 10CX2.5 mm² 1 Start PermiSS0ive 22 SR6, SR5, SR4 34
6
7
Shunt Trip Ckt.
8
3
Feedback
4
3600kW 11kV FCMA 11kV HT 5
121 Soft Starter-4 Switchgear 10CX2.5 mm² 1 Start PermiSS0ive 22 SR6, SR5, SR4 34
6
7
Shunt Trip Ckt.
8
3
Feedback
4
3600kW 11kV FCMA 11kV HT 5
122 Soft Starter-5 Switchgear 10CX2.5 mm² 1 Start PermiSS0ive 22 SR6, SR5, SR4 34
6
7
Shunt Trip Ckt.
8
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

3
Start PermiSS0ive
4
1200kVAr Capacitor 11kV HT 5 SR9, SR8, SR7,
123 Bank-1 Switchgear 10CX2.5 mm² 1 Shunt Trip Ckt. 17 SR6, SR5, SR4 50
6
7
Feedback
8
3
Start PermiSS0ive
4
1200kVAr Capacitor 11kV HT 5 SR9, SR8, SR7,
124 Bank-2 Switchgear 10CX2.5 mm² 1 Shunt Trip Ckt. 17 SR6, SR5, SR4 50
6
7
Feedback
8
3
Start PermiSS0ive
4
1200kVAr Capacitor 11kV HT 5 SR9, SR8, SR7,
125 10CX2.5 mm² 1 Shunt Trip Ckt. 17 50
Bank-3 Switchgear 6 SR6, SR5, SR4
7
Feedback
8
3
Start PermiSS0ive
4
1200kVAr Capacitor 11kV HT 5 SR9, SR8, SR7,
126 Bank-4 Switchgear 10CX2.5 mm² 1 Shunt Trip Ckt. 17 SR6, SR5, SR4 50
6
7
Feedback
8
3
Start PermiSS0ive
4
1200kVAr Capacitor 11kV HT 5 SR9, SR8, SR7,
127 Bank-5 Switchgear 10CX2.5 mm² 1 Shunt Trip Ckt. 17 SR6, SR5, SR4 50
6
7
Feedback
8
3
Start PermiSS0ive
4
150kVAr Capacitor 11kV HT 5 SR9, SR8, SR7,
128 Bank-1 Switchgear 10CX2.5 mm² 1 Shunt Trip Ckt. 17 SR6, SR5, SR4 45
6
7
Feedback
8
3
Start PermiSS0ive
4
150kVAr Capacitor 11kV HT 5 SR9, SR8, SR7,
129 Bank-2 Switchgear 10CX2.5 mm² 1 Shunt Trip Ckt. 17 SR6, SR5, SR4 45
6
7
Feedback
8
3 XCT-33
O/C & E/F PROT. RELAY
4 XCT-34
11kV HT Switchgear 1 XCT-25 SR4, SR5, SR6,
130 CRP Panel 10CX2.5 mm² 1 TAFO. DIFFERENTIAL RELAY 17 42
(Trafo-1 Feeder) 2 XCT-26 SR7, SR8
3 XCT-27
Feedback
TERMINATION DETAILS
From TO

11kV HT Switchgear NO. OF1CABLE SR4, SR5, SR6,


Sl.130
NO Equipment FROM
(Trafo-1 Feeder)
CRPTO
Panel TB NO FERRULE NO FERRULE NO TB NO 10CX2.5
SIZE mm²
OF CABLE RUN USED PURPOSE 17
Dia ROUTE
SR7, SR8
42
Length

Feedback
4 XCT-28
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

3 XCT-33
O/C & E/F PROT. RELAY
4 XCT-34
11kV HT Switchgear 1 XCT-25 SR4, SR5, SR6,
131 (Trafo-2 Feeder) CRP Panel 10CX2.5 mm² 1 TAFO. DIFFERENTIAL RELAY 17 SR7, SR8 42
2 XCT-26
3 XCT-27
Feedback
4 XCT-28

Conduit, SS26,
SS25, SS24,
ISO (Motor Operating SS19, SS17,
132 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 Conduit, SS01, 142
OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS26,
SS25, SS24,
ISO (Motor Control SS19, SS17,
133 CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 Conduit, SS01, 142
Panel) OD01, SR3, SR4,
ISO-1 (66kV)
SR5, SR6, SR7,
SR8

134 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 30


Panel)

Conduit, SS26,
SS25, SS24,
SS19, SS17,
ISO (Motor Control
135 Panel) CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 142
OD01, SR3, SR4,
SR5, SR6, SR7,
SR8
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

Conduit, SS27,
SS24, SS19,
ISO (Motor Operating SS17, Conduit,
136 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS01, OD01, 154
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS27,
SS24, SS19,
ISO (Motor Control SS17, Conduit,
137 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SS01, OD01, 154
ISO-2 (66kV) SR3, SR4, SR5,
SR6, SR7, SR8

138 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 30


Panel)

Conduit, SS27,
SS24, SS19,
139 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 SS17, Conduit, 154
Panel) SS01, OD01,
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS24,
SS19, SS17,
140 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 Conduit, SS01, 144
Mechanism) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS24,
SS19, SS17,
ISO (Motor Control Conduit, SS01,
141 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 OD01, SR3, SR4, 144
ISO-3 (66kV) SR5, SR6, SR7,
SR8

142 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 40


Panel)

Conduit, SS24,
SS19, SS17,
143 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 144
Panel) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

Conduit, SS25,
SS24, SS19,
ISO (Motor Operating SS17, Conduit,
144 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS01, OD01, 137
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS25,
SS24, SS19,
ISO (Motor Control SS17, Conduit,
145 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SS01, OD01, 137
ISO-4 (66kV) SR3, SR4, SR5,
SR6, SR7, SR8

146 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 40


Panel)

Conduit, SS25,
SS24, SS19,
147 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 SS17, Conduit, 137
Panel) SS01, OD01,
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS24,
SS19, SS17,
148 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 Conduit, SS01, 128
Mechanism) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS24,
SS19, SS17,
ISO (Motor Control Conduit, SS01,
149 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 OD01, SR3, SR4, 128
ISO-5 (66kV) SR5, SR6, SR7,
SR8

150 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 50


Panel)

Conduit, SS24,
SS19, SS17,
151 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 128
Panel) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

Conduit, SS24,
SS19, SS17,
ISO (Motor Operating Conduit, SS01,
152 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 OD01, SR3, SR4, 137
SR5, SR6, SR7,
SR8

Conduit, SS24,
SS19, SS17,
ISO (Motor Control Conduit, SS01,
153 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 OD01, SR3, SR4, 137
ISO-6 (66kV) SR5, SR6, SR7,
SR8

154 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 30


Panel)

Conduit, SS24,
SS19, SS17,
155 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 137
Panel) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS24,
SS19, SS17,
156 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 Conduit, SS01, 137
Mechanism) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS24,
SS19, SS17,
ISO (Motor Control Conduit, SS01,
157 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 OD01, SR3, SR4, 137
ISO-7 (66kV) SR5, SR6, SR7,
SR8

158 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 30


Panel)

Conduit, SS24,
SS19, SS17,
159 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 137
Panel) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

Conduit, SS23,
SS24, SS19,
ISO (Motor Operating SS17, Conduit,
160 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS01, OD01, 154
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS23,
SS24, SS19,
ISO (Motor Control SS17, Conduit,
161 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SS01, OD01, 154
ISO-8 (66kV) SR3, SR4, SR5,
SR6, SR7, SR8

162 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 40


Panel)

Conduit, SS23,
SS24, SS19,
163 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 SS17, Conduit, 154
Panel) SS01, OD01,
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS24,
SS19, SS17,
164 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 Conduit, SS01, 144
Mechanism) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS24,
SS19, SS17,
ISO (Motor Control Conduit, SS01,
165 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 OD01, SR3, SR4, 144
ISO-9 (66kV) SR5, SR6, SR7,
SR8

166 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 50


Panel)

Conduit, SS24,
SS19, SS17,
167 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 144
Panel) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

Conduit, SS21,
SS24, SS19,
ISO (Motor Operating SS17, Conduit,
168 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 SS01, OD01, 137
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS21,
SS24, SS19,
ISO (Motor Control SS17, Conduit,
169 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 SS01, OD01, 137
ISO-10 (66kV) SR3, SR4, SR5,
SR6, SR7, SR8

170 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 60


Panel)

Conduit, SS21,
SS24, SS19,
171 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 SS17, Conduit, 137
Panel) SS01, OD01,
SR3, SR4, SR5,
SR6, SR7, SR8

Conduit, SS24,
SS19, SS17,
172 ISO (Motor Operating CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 Conduit, SS01, 128
Mechanism) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS24,
SS19, SS17,
ISO (Motor Control Conduit, SS01,
173 Panel) CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 OD01, SR3, SR4, 128
SR5, SR6, SR7,
ISO-11 (66kV) SR8

174 ISO (Motor Control CB 4CX2.5 mm² 1 Interlock 16 50


Panel)

Conduit, SS24,
SS19, SS17,
175 ISO (Motor Control CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 128
Panel) OD01, SR3, SR4,
SR5, SR6, SR7,
SR8
ISO-11 (66kV)

TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

176 ISO (Motor Control ISO-1 (E.S) 4CX2.5 mm² 1 Interlock 16 21


Panel)
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

Conduit, SS22,
SS21, SS24,
ISO (Motor Operating SS19, SS17,
177 Mechanism) CRP 1 19CX2.5 mm² 2 CONTROL/ALARM/INDICATIONS 26 Conduit, SS01, 143
OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

Conduit, SS22,
SS21, SS24,
ISO (Motor Control SS19, SS17,
178 CRP 1 12CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 Conduit, SS01, 143
Panel)
OD01, SR3, SR4,
SR5, SR6, SR7,
ISO-12 (66kV) SR8

ISO (Motor Control


179 Panel) CB 4CX2.5 mm² 1 Interlock 16 33

Conduit, SS22,
SS21, SS24,
ISO (Motor Control SS19, SS17,
180 Panel) CRP 4CX2.5 mm² 1 Remote Operation 16 Conduit, SS01, 143
OD01, SR3, SR4,
SR5, SR6, SR7,
SR8

ISO (Motor Control


181 Panel) ISO-1 (E.S) 4CX2.5 mm² 1 Interlock 16 21

182 CB-52 (Line) CRP 1 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 Conduit, SS25, 40


183 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-1 26 SS24, SS19, 40
SS17, Conduit,
66kV CB-1 SS01, OD01,
184 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-2 26 SR3, SR4, SR5, 40
SR6, SR7, SR8

185 CB-52 (Line) CRP 1 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 Conduit, SS27, 150
SS24, SS19,
186 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-1 26 SS17, Conduit, 150
66kV CB-2
SS01, OD01,
SR3, SR4, SR5,
187 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-2 26 SR6, SR7, SR8 150
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1 1a
(BPT CORE-1) Protection
2 1n
188 BPT BPT-JB (R-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
1 1a
(BPT CORE-1) Protection
2 1n
189 BPT BPT-JB (Y-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
1 1a
66kV BPT-1 (BPT CORE-1) Protection
1n
190 BPT BPT-JB (B-PH) 4CX2.5 mm² 1 16 10
1 2a
(BPT CORE-2) METERING
2n

191 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-1) METERING 16 Conduit, SS27, 142
SS24, SS19,
SS17, Conduit,
SS01, OD01,
192 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-2) Protection 16 SR3, SR4, SR5, 142
SR6, SR7, SR8

1 1a
(BPT CORE-1) Protection
2 1n
193 BPT BPT-JB (R-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
1 1a
(BPT CORE-1) Protection
2 1n
194 BPT BPT-JB (Y-PH) 4CX2.5 mm² 1 16 10
3 2a
(BPT CORE-2) METERING
4 2n
1 1a
(BPT CORE-1) Protection
66kV BPT-2 1n
195 BPT BPT-JB (B-PH) 4CX2.5 mm² 1 16 10
1 2a
(BPT CORE-2) METERING
2n

Conduit, SS22,
196 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-1) METERING 16 SS21, SS24, 143
SS19, SS17,
Conduit, SS01,
OD01, SR3, SR4,
197 BPT-JB CRP 1 4CX2.5 mm² 1 (BPT CORE-2) Protection 16 SR5, SR6, SR7, 143
SR8
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

198 CB-52 (Line) CRP 1 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 Conduit, SS24, 137
SS19, SS17,
199 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-1 26 Conduit, SS01, 137
66kV CB-3 OD01, SR3, SR4,
SR5, SR6, SR7,
200 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-2 26 SR8 137

201 CB-52 (Line) CRP 1 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 Conduit, SS21, 150
SS24, SS19,
SS17, Conduit,
202 66kV CB-4 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-1 26 SS01, OD01, 150
SR3, SR4, SR5,
203 CB-52 (Line) CRP 1 19CX2.5 mm² 1 TC-2 26 SR6, SR7, SR8 150

1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
204 CT (200/1-1-1A) CT-JB (R-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
205 CT (200/1-1-1A) CT-JB (Y-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
66kV CT-1 1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
206 CT (200/1-1-1A) CT-JB (B-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2

207 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-1) PROTECTION 16 Conduit, SS24, 137
SS19, SS17,
Conduit, SS01,
OD01, SR3, SR4,
SR5, SR6, SR7,
208 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-2) METERING 16 SR8 137
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
209 CT (200/1-1-1A) CT-JB (R-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
210 CT (200/1-1-1A) CT-JB (Y-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
66kV CT-2 1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
211 CT (200/1-1-1A) CT-JB (B-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2

212 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-1) PROTECTION 16 Conduit, SS27, 145
SS24, SS19,
SS17, Conduit,
SS01, OD01,
SR3, SR4, SR5,
213 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-2) METERING 16 SR6, SR7, SR8 145
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
214 CT (200/1-1-1A) CT-JB (R-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
215 CT (200/1-1-1A) CT-JB (Y-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
66kV CT-3 1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
216 CT (200/1-1-1A) CT-JB (B-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2

217 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-1) PROTECTION 16 Conduit, SS24, 137
SS19, SS17,
Conduit, SS01,
OD01, SR3, SR4,
SR5, SR6, SR7,
218 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-2) METERING 16 SR8 137
TERMINATION DETAILS
From TO

Sl. NO Equipment FROM TO TB NO FERRULE NO FERRULE NO TB NO SIZE OF CABLE NO. OF CABLE PURPOSE Dia ROUTE Length
RUN USED

1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
219 CT (50/1-1-1A) CT-JB (R-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
220 CT (50/1-1-1A) CT-JB (Y-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
66kV CT-4 6 3S2
1 1S1
(CT1 CORE-1) PROTECTION
2 1S2
4CX2.5 mm² 1 10
3 2S1
221 CT (50/1-1-1A) CT-JB (B-PH) (CT1 CORE-2) METERING 16
4 2S2
5 3S1
4CX2.5 mm² 1 SPARE 10
6 3S2
Conduit, SS23,
222 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-1) PROTECTION 16 SS24, SS19, 145
SS17, Conduit,
SS01, OD01,
223 CT-JB CRP 1 4CX2.5 mm² 1 (CT1 CORE-2) METERING 16 SR3, SR4, SR5, 145
SR6, SR7, SR8

224 CB-52 (B/C) CRP 1 10CX2.5 mm² 1 CONTROL/ALARM/INDICATIONS 22 Conduit, SS23, 150
SS24, SS19,
225 CB-52 (B/C) CRP 1 19CX2.5 mm² 1 TC-1 26 SS17, Conduit, 150
66kV CB-5 SS01, OD01,
SR3, SR4, SR5,
226 CB-52 (B/C) CRP 1 19CX2.5 mm² 1 TC-2 26 SR6, SR7, SR8 150
5 CRP- Wall
4 FFL FGL
4 Riser to panel
25 Outside Wall - Bend
4 Riser to JB
42
Equipment Structure Total
Weight Weight Weight
Net Weight of the Isolator without E.S.
Metalics 345 500 845
Net Weight of the Isolator with one E.S.
Metalics 405 500 905

66kV MCT, 60/1-1A 200 190 390


66kV CT, 100/1-1-1A 200 190 390
66kV CT, 100/1-1-1-1A 200 190 390
66kV MPT,66kV/√3/110V/√3/110V/√3 250 190 440
66kV PT,66kV/√3/110V/√3/110V/√3 250 190 440
72.5kV Circuit Breaker 650 101 751
Data
SIZE OF CABLE Sum - Length Sum - Glands Sum - Lugs
10CX2.5 mm² 2946 72 720
12CX2.5 mm² 3265 48 576
19CX2.5 mm² 5689 128 2512
4CX2.5 mm² 9426 320 1280
(empty)
Total Result 21326 568 5088