Hockey Turf Construction Estimate
Hockey Turf Construction Estimate
PREPARATION (Rate based on SOR 2019 Mizoram PWD) - Rates are inclusive of GST
2 4.80
Water bound macadam specification including spreading in uniform
thickness, hand packing, rolling with vibratory roller 8-10 tonnes in
stages to proper grade and camber, applying and brooming requisite
type of screening/binding materials to fill up the interstices of coarse
aggregate, watering and compacting to the required density.)
3 5.10 Prime Coat : Providing and applying primer coat with bitumen
emulsion on prepared surface of granular base including cleaning of
road surface and spraying primer at the rate of 0.60 kg/sqm using
mechanical means)
i) Low porosity
1 97.00 59.00 5723.00 sqm 53.76 307668.48
4 5.20 Tack Coat : (Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.20 kg per sqm on
the prepared bituminous/granular surface cleaned with mechanical
broom)
(iii) Granular Surface Treated with Primer
1 97.00 59.00 5723.00 sqm 32.48 185883.04
5 5.80
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical
means using HMP of appropriate capacity not less than 75
tonnes/hour. Providing, laying and rolling of close-graded premix
surfacing material of 20mm thickness composed of 11.2mm to
0.09mm (Type-a) or 13.2mm to 0.09mm (Type-b) aggregates using
penetration grade bitumen to the required line, grade and level to
serve as wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a Smooth wheeled
roller 8-10 tonne capacity, and finishing to required level and grade)
6 5.90 Seal Coat : Providing and laying seal coat sealing the voids in a
bitumen surface laid to the specified level, grade and cross fall using
Type A, Type B and Type C as per Technical Specification Clause
510.
S/No SOR Description No and L
Seal Coat : Providing B coat sealing
laying seal H the voids
Qtty in a Unit Rate (Rs) Amount (Rs)
bitumen surface laid to the specified level, grade and cross fall using
Type A, Type B and Type C as per Technical Specification Clause
510.
Case - I : Type A
1 97.00 59.00 5723.00 sqm 127.68 730712.64
ton.
ii) Sand refer qty table 2747.04
km
14.78 40612.24
B. Installation of Turf
11
Providing and laying of perforated PVC drain pipes of 10" inner dia
and 10mm thick gauge, with staggered perforations of 1" dia, at
every 6" intervals and 2" spacing, and across a curvature of 160*
and solidly bedded in backfill material in the perimeter drain as per
slope and design. Provide full bearing for each pipe section
throughout its length to its true grades and alignment and
continuous slope 1:100 in the direction of flow
1 550.00 550.00 rm 800.00 440000.00
13
Providing and laying of compacted 100mm thick with 40mm metal
(Coarse Rubble Granite Stone) combined with a downgraded stone
upto 30mm to form a contour and elevations to the desired level as
per drawings including all carriages upto site of work.
1 97.00 59.00 0.25 1430.75 cum 1450.00 2074587.50
15
Providing and laying in position cement concrete of specified grade
M20 (1:1.5:3) (1 cement : 1.5 sand : 3 well graded stone aggregate
of 20mm) including shuttering and centering for construction
concrete curbing of cross-section 0.3m x 0.1m, providing 'L' bed at
the top for turf glueing as and where required. Scope also includes
excavation of 0.2m on both sides of proposed curbing and refilling
S/No SOR Description No L B H Qtty Unit Rate (Rs) Amount (Rs)
Providing and laying in position cement concrete of specified grade
M20 (1:1.5:3) (1 cement : 1.5 sand : 3 well graded stone aggregate
of 20mm) including shuttering and centering for construction
concrete curbing of cross-section 0.3m x 0.1m, providing 'L' bed at
the top for turf glueing as and where required. Scope also includes
excavation of 0.2m on both sides of proposed curbing and refilling
after construction including all carriages upto site of work.
17
Supply and infilling of silica sand as per desired quality, infill ratio
and particle size recommended by turf manufacturer with motorized
spreader in layers.
1 250.00 250.00 ton 18500.00 4625000.00
18
Installation of turf including unloading and staging of rolls, sewing of
seams, infilling with appropriate dispensing, spreading and levelling
equipment, brushing of fibres with all poly hydraulic controlled
equipment, painting of any lines with approved synthetic turf paint.
20
Site Survey, Soil Test, Contour Map on AutoCAD
Lumpsum 200000.00
Total Rs 44709544.21
Say Rs 44710000.00
(Rupees One Crore Forty Five Lakhs Ninety Thousand Only)
QUANTITY REQUIREMENTS
Loose qnty
Qnty factor
Total of Coarse Qnty factor
Sl. No. Item/Particulars Unit of Coarse
Quantity Aggregate of sand
Aggregate
(m3)
1 WBM - Grading I 572.3 cum 1.73 990.079
2 WBM - Grading II 572.3 cum 1.73 990.079
3 Prime Coat 5723 sqm
4 Tack Coat 5723 sqm
5 Close-graded Pre-mix Carpet 5723 sqm 0.027 154.521
6 Seal Coat 5723 sqm 0.006
TOTAL = 2134.68
Loose qnty Qnty factor Loose qnty of
of sand (m3) of bitumen bitumen (ton)
1 5.723
3.5 20.0305
2 11.446
34.338 0.68 3.89164
34.34 41.091
LAYING OF HOCKEY TURF AT SALEM VENG, LUNGLEI
Sh 1: Mild steel fencing with RCC column and brick wall upto skirting
(Rate based on Mizoram PWD Schedule of Rates 2019)
(Items rate are including GST,loading, unloading and transportation for a lead of 5km within the district)
SL.N SOR
Description No Length Breadth Height Quantity Unit Rate Amount
o No.
Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1.5m
in width or 10sqm on plan) including dressing of sides and ramming of bottoms, lift
1 2.07
upto 1.5m including getting out excavated soil and disposal of surplus excavated
soil as directed within a lead of 50 metres.
b)Hard Soil(pick
work)
-F1 240 0.60 0.60 1.20 103.68 m3 629.90 65308
Providing and laying in position cement concrete of specified grade excluding cost
2 4.03
of centering and shuttering - All work upto plinth level:
(a)1:3:6(1 cement :3 course sand :6 stone aggregate 20mm nominal size)
Footing 240 0.600 0.600 0.10 8.64 m3 7350.60 63509
Providing and laying in position machine batched, machine mixed and machine
3 5.28 vibrated design mix M-20 grade reinforced cement concrete excluding cost of
centering and shuttering and reinforcement in -
a) All work upto plinth level.
Footing - F1 240 0.60 0.600 0.15 12.96
Column below
Plinth 120 0.20 0.200 1.15
5.52
Tie Beam 239 2.00 0.200 0.2019.12
37.60 m3 10678.70 401519
Providing and laying in position machine batched, machine mixed and machine
4 5.28 vibrated design mix M-20 grade reinforced cement concrete excluding cost of
centering and shuttering and reinforcement in -
b)All work above plinth level upto floor V level.
Column 240 0.200 0.200 0.750 7.20
7.20 m3 11443.00 82390
Providing and laying in position machine batched, machine mixed and machine
5 5.04 vibrated design mix M-20 grade reinforced cement concrete excluding cost of
centering and shuttering and reinforcement in -
b)All work above plinth level upto floor V level.
Tie Beam above
0.75m 239 2 0.2 0.2 19.12
TOTAL 3562711.23
G. TOTAL 3562000.00
(Rupees twenty seven lakhs fifty five thousand) only
DETAILED ESTIMATE FOR CONSTRUCTION OF APPROACH ROAD
Total Rs 2413702.50
Say Rs 2414000.00
(Rupees Fourteen Lakhs Thirteen Thousand Only)
DETAILED ESTIMATE FOR CONSTRUCTION OF SIDE DRAIN
1 2.06
Earthwork in excavation over areas (exeeding 30cm in depth,1.5m in width
as well as 10sqm on plan) including disposal of excavated earth, lead upto
50m and lift upto 1.5m, disposed earth to be levelled and neatly dressed.
3 5.28 Providing and laying in position machine batched, machine mixed and
machine vibrated design mix M-20 grade reinforced cement concrete
excluding cost of centering and shuttering and reinforcement in -
a) All work upto plinth level.
1 180.00 0.40 0.13 9.36 cum
2 180.00 0.40 0.13 18.72 cum
Total 28.08 cum 10678.70 299857.90
Total Rs 717830.50
Say Rs 718000.00
(Rupees Eight Lakhs Fourteen Thousand Only)
DETAILED ESTIMATE FOR CONSTRUCTION OF PAVILLION
1.2 2.07 Earthwork in excavation in foundation trenches etc. not exceeding 2m depth
a) Ordinary Soil
Foundations
F1 10 1.50 1.50 1.80 40.50 cum
F2 2 1.20 1.20 1.50 4.32 cum
Total 44.82 cum 419.90 18819.92
1.3 2.17 Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundations etc. in layers not exceeding 20cm in depth, consolidating each
deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
2.1 4.03 Providing and laying in position cement concrete of specified grade excluding
cost of centering and shuttering - All work upto plinth level:
(a)1:3:6(1 cement :3 course sand :6 stone aggregate 20mm nominal
size)
Foundations
F1 10 1.50 1.50 0.10 2.25 cum
F2 2 1.20 1.20 0.10 0.29 cum
GF Gallery 4 7.50 0.75 0.08 1.80 cum
2 7.50 0.45 0.08 0.54 cum
FF Gallery 3 18.00 1.00 0.08 4.32 cum
2 4.60 1.00 0.08 0.74 cum
Total 9.93 cum 7350.60 73020.86
3.1 5.28 Providing and laying in position machine batched, machine mixed and
machine vibrated design mix M-20 grade reinforced cement concrete
excluding cost of centering and shuttering and reinforcement in -
a) All work upto plinth level.
Foundations
Rectangular portions
F1 10 1.50 1.50 0.15 3.38 cum
F2 2 1.20 1.20 0.20 0.58 cum
Trapezoidal portions
F1
n 10
h 0.4
A1 1.50 1.50 2.25
A2 0.75 0.75 0.56
0.5(A1+A2)*h*n 5.63 cum
F2
n 2
h 0.38
A1 1.20 1.20 1.44
A2 0.75 0.75 0.56
0.5(A1+A2)*h*n 0.76 cum
S.Total= 10.34 cum
Plinth Beam
2 18.00 0.215 0.35 2.71 cum
5 4.50 0.210 0.35 1.65 cum
Total 4.36 cum
G.Total 14.70 cum 10678.70 156973.69
Stair
landing 2 2.60 1.50 0.15 1.17
flight 4 3.25 1.30 0.15 2.54
step 18 1.30 0.30 0.200 1.40 cum
Total 5.11 cum
G. Total 50.75 cum 11443.00 580756.57
3.2 5.18 Steel reinforcement for RCC work including straighthening, cutting, bending,
placing in position and binding all complete.
b) TMT bars of grade Fe-500 or more
Foundations @ 100.00 kg/cum 10.34 1033.70 kg
Columns @ 310.00 kg/cum 6.77 2099.67 kg
Beams @ 270.00 kg/cum 9.06 2445.53 kg
Slabs @ 100.00 kg/cum 29.81 2981.25 kg
Staircase @ 120.00 kg/cum 5.11 613.08 kg
Total Rebar= 9173.22 kg 101.60 931999.03
3.3 5.10 Centering and shuttering including strutting,propping etc. And removal of form
for:
a) Foundations, footings, bases of columns etc. for mass concrete.
Foundations
A=n*(2L+2B)*t n L B t Area
F1 10 1.5 1.5 0.15 9.00 sqm
F2 2 1.2 1.2 0.20 1.92 sqm
Total 10.92 sqm 359.10 3921.37
(e)Suspended floors, roofs, landings, shelves and their support, balconies and chajjaj,etc.
Slabs Area =n*L*B
Slabs n L B
1 18.00 4.850 87.30
1 18.00 7.000 126.00
Total 213.30 sqm 673.30 143614.89
Stair
landing 2 2.60 1.50 7.80 sqm
flight 4 3.25 1.30 16.90 sqm
step 36 1.30 0.30 14.04 sqm
Total 38.74 sqm 673.30 26083.64
Sub Head 3 Total 1979805.29
4.1 6.06 Half brick masonry with first class brick in superstructure above plinth level
upto floor V level.
a) in cement moratar 1:4 ( 1 cement : 4 coarse sand )
Ground Floor
External W 2 7.50 3.00 45.00 sqm
2 8.70 3.50 60.90 sqm
4 2.40 3.50 33.60 sqm
GF Gallery 2 7.50 0.30 4.50 sqm
4 0.75 0.30 0.90 sqm
2 7.50 0.60 9.00 sqm
4 0.75 0.60 1.80 sqm
2 7.50 0.90 13.50 sqm
4 0.75 0.90 2.70 sqm
FF Gallery 3 18.00 0.25 13.50 sqm
2 4.60 0.50 4.60 sqm
Parapet 1 18.35 1.00 18.35 sqm
2 6.00 1.00 12.00 sqm
Toilet wall 2 2.30 3.20 14.72 sqm
5.1 7.03 Coursed rubble masonry (First sort) with hard stone in foundation and plinth
with:
a) in cement mortar 1 : 3 ( 1cement : 3 coarse sand)
Step 1 18.35 0.30 0.15 0.83 cum
1 18.35 0.30 0.30 1.65 cum
1 18.35 0.60 0.40 4.40 cum
Total 6.88 cum 6863.50 47229.46
6.1 9.06 Providing 1st class local wood dressed in frames of chaukat for doors,
windows,
D 2 2x(1.0+2) 0.10 0.10 0.12 sqm
D1 2 2x(.9+2) 0.10 0.10 0.12 sqm
Total 0.24 sqm 51372.80 12329.47
6.2 9.31 Providing and fixing 40mm thick panelled door shutter comprising of
styles and
D 2 0.90 1.80 3.24 rm
D1 2 0.80 1.80 2.88 rm
Total 6.12 rm 5970.10 36537.01
8.1 20.49 Applying one coat of cement primer of approved brand and manufacture on
wall surface.
A) ready mix white primer
Qtty vide 15mm plaster area 476.96
Qtty vide 6mm plaster area 758.36
Total 1235.32 sqm 96.90 119702.51
8.2 20.74 Wall paiting with water and weather proof paint (Latex Emulsion
base) on cement
Item 1/20.49 1235.32
Total 1235.32 sqm 152.90 188880.43
8.3 20.51 Applying priming coat with ready mixed pink or Grey primer of approved brand
and manufacture on wood work and plywood complete.
Chaukhats
4 1.00 0.10 0.40
8 2.00 0.10 1.60
Total 2.00 sqm 74.40 148.80
8.4 20.72 Painting with synthetic enamel paint of approved brand and manufacture in all
shades on new work (two or more coats).
b) High gloss
As per item no 3/20.51 2.00 sqm 142.90 285.80
9.1 10.08
Steel work in tubular trusses etc. including cutting, hoisting in position etc.
Truss-1
R1-PIP 63.70 kg
603m
R1-PIP 25.15 kg
483m
R1-PIP 11.55 kg
424m
R1-PIP 1.99 kg
269m 4 Nos. 409.56 kg
Truss-2
R1-PIP 66.09 kg
603m
R1-PIP 26.88 kg
483m
R1-PIP 12.30 kg
424m
R1-PIP 1.99 kg
269m
Truss-3
Beam-1
R1-PIP 90.61 kg
603m
R1-PIP 48.88 kg
424m
Truss-4
Beam-2
R1-PIP 16.00 kg
483m
R1-PIP 13.78 kg
337mm
R1-PIP 16.00 kg
483m
R1-PIP 13.78 kg
337mm
Purlin
R1-PIP 495.00 kg
424m
Column
R1-PIP 83.75 kg
889m
Total 1294.62 kg
Add 10% for plate etc. 129.46 kg
G. Total 1424.08 kg 176.40 251208.06
9.2 9.16 Supplying and fixing MS decorative railing 80cm high in staircase consiting of
1 40.00 40.00 m
Total 40.00 m 2278.50 91140.00
Sub Head 9 Total 342348.06
10.1 11.01 Providing and fixing anodised aluminium work for doors, windows, ventilators
and
(a) 2 - track sliding windows/ventilators.
W/V 6 1.00 1.80 10.80
V 2 1.00 0.45 0.90
G Total 11.70 kg 4481.60 52434.72
10.2 11.02 Supplying of glass panes at site.
a) 4mm thick plate sheet glass
W/V 6 1.00 1.80 10.80 rm
V 1 1.00 0.45 0.45 rm
Total 11.25 rm 654.80 7366.50
11.1 16.11 Providing Trapezoidal Polyester Coated Galvanised Steel Sheets Roofing of
any colour
11.2 16.12 Providing and fixing of Polyester Coated Galvanised Steel Sheets of any
colour
Total Rs 3827641.82
S Total Rs 3827641.82
Add 5% Internal Water Supply & Sanitary Installation Rs 191382.09
Add12.5% Internal Electrification Rs 478455.23
Add External Services (5% of internal) Rs 33491.87
Fire Fighting (Wet riser system) @ Rs 768.4 per sqm of floor area (702 sqm) Rs 539416.80
Total Rs 5070387.80
G Total Rs 5070387.80
Say Rs 5070000.00
(Rupees Fifty Lakhs Seventy Thousand Only)
DETAILED ESTIMATE FOR CONSTRUCTION OF RETAINING WALL/BREAST WALL
1.1 2.07 Earthwork in excavation in foundation trenches or drains etc. (not exceeding
1.5m in width or 10sqm on plan) including dressing of sides and ramming of
bottoms, lift upto 1.5m including getting out excavated soil and disposal of
surplus excavated soil as directed within a lead of 50 metres.
2.1 4.03 Providing and laying in position cement concrete of specified grade excluding
cost of centering and shuttering - All work upto plinth level:
(a)1:3:6(1 cement :3 course sand :6 stone aggregate 20mm nominal
size)
Retaining Wall (New 1 145.00 1.20 0.20 34.80 cum
Wall)
Total 34.80 cum 7350.60 255800.88
3.1 7.08 Coursed masonry with rectangular sized hard stone in foundation upto one
storey above and below ground level including curing etc. complete
a) in cement mortar 1 : 3 ( 1cement : 3 fine sand)
Retaining Wall (New
1 145.00 1.00 3.30 478.50 cum
Wall)
Total 478.50 cum 9190.40 4397606.40
3.2 7.17 Back filling behind abutment, wing wall and return wall complete as per
drawing and technical specification.
a) gravelly material
1 145.00 1.20 3.30 574.20 cum
Total 574.20 cum 1086.00 623581.20
Total Rs 5390975.18
Say Rs 5391000.00
(Rupees Fourteen lakhs Six Thousand only)