Construction Schedule Solar PV Project Koa: Ii. Mechanical Construction Work

The construction schedule outlines 5 phases of work to build a solar PV project over 165 days. Phase I involves building a cable tray bridge structure over 80 days. Phase II is 50 days of mechanical construction including installing mounting brackets and solar panels. Phase III is electrical work like transformers, inverters, and wiring over 50 days. Phase IV installs surveillance equipment in 18 days. Phase V tests the system over 22 days before handover. The schedule provides task durations and identifies necessary equipment and staff needed to complete each task.

Uploaded by

haha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
195 views1 page

Construction Schedule Solar PV Project Koa: Ii. Mechanical Construction Work

The construction schedule outlines 5 phases of work to build a solar PV project over 165 days. Phase I involves building a cable tray bridge structure over 80 days. Phase II is 50 days of mechanical construction including installing mounting brackets and solar panels. Phase III is electrical work like transformers, inverters, and wiring over 50 days. Phase IV installs surveillance equipment in 18 days. Phase V tests the system over 22 days before handover. The schedule provides task durations and identifies necessary equipment and staff needed to complete each task.

Uploaded by

haha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

CONSTRUCTION SCHEDULE SOLAR PV PROJECT KOA

ID TASK DESCRIPTION TIME PLAN PLAN END Contact '20 19 Apr '20 03 May '20 17 May '20 31 May '20 14 Jun '20 28 Jun '20 12 Jul '20 26 Jul '20 09 Aug '20 23 Aug '20 06 Sep '20 20 Sep '20
START

0 TOTAL PROCESS MFT S W S T MF T S W S T MF T S W S T M F TSWS TMFT S W S T MF T SWSTM


165 days Wed 15/04/20 Sun 27/09/20
1 TOTAL CONSTRUCTION PROCESS KOA
165 days Wed 15/04/20 Sun 27/09/20
2 I. CABLE TRAY BRIDGE STRUCTURE
80 days Wed 15/04/20 Sat 04/07/20
3 Install Concrete steel, Reinforced concrete Worker [500%], Engineer Crane, Pile Hammer, Excavator
10 days Wed 15/04/20 Sat 25/04/20
4 Foundation Cable Bridge + Transformers Workers [1,500%], Excavators, Engineers
10 days Sat 25/04/20 Tue 05/05/20 3
5 Production and Erection Structural steel Cable Bridge Workers [1,500%], Engineers, Truck Cranes
45 days Mon 20/04/20 Thu 04/06/20
6 Install mounting bracket Inverter + Cable Tray Workers [1,500%], Engineers,Truck Cranes
30 days Thu 04/06/20 Sat 04/07/20 5
7 II. MECHANICAL CONSTRUCTION WORK
50 days Wed 10/06/20 Thu 30/07/20
8 Installing Mounting Brackets for PV Workers [4.000%],Engineers,[200%],Truck Cranes
35 days Wed 10/06/20 Wed 15/07/20
9 Installing PV Solar Panel Workers [3.000%],Engineer[200%],Cranes[200%]
40 days Mon 15/06/20 Sat 25/07/20 8SS+5 da
10 Installing cable tray + protection tube + sole + Box Workers[1.000%],Truck Cranes
40 days Sat 20/06/20 Thu 30/07/20 9SS+5 da

11 III. CONSTRUCTION WORK M&E 50 days Mon 29/06/20 Tue 18/08/20


12 Installing Transformers + Boxes
5 days Mon 29/06/20 Sat 04/07/20 Workers [1.000%],Engineers,Truck Cranes
13 Installing Inverters
10 days Sat 04/07/20 Tue 14/07/20 12 Workers [1.000%],Engineers,Truck Cranes
14 Wiring AC+DC
45 days Sat 04/07/20 Tue 18/08/20 12SS+5 d Worker [1.000%],Engineer,Cranes
15 Installing Ground Wire for Lightning Protection
45 days Sat 04/07/20 Tue 18/08/20 14SS Workers [400%]
16 Connection + Complete
45 days Sat 04/07/20 Tue 18/08/20 14SS Workers [600%],Engineers
17 IV. INSTALL SURVEILLANCE EQUIPMENT
18 days Tue 18/08/20 Sat 05/09/20
18 Install Surveillance Equipment
18 days Tue 18/08/20 Sat 05/09/20 16 Workers [400%],K
19 V. Testing , Handover
22 days Sat 05/09/20 Sun 27/09/20
20 No load testing
5 days Sat 05/09/20 Thu 10/09/20 18 Worker [400

21 Load testing
15 days Thu 10/09/20 Fri 25/09/20 20 Côn

22 Handover testing
2 days Fri 25/09/20 Sun 27/09/20 21 Kỹ

Task Project Summary Inactive Summary Manual Summary External Milestone


Split External Tasks Manual Task Start-only Progress
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks

Project Management Unit Supervision Consultant Construction Contractor