MEP Completion Schedule

The document outlines a maintenance completion schedule for an American school in Dubai. It details 30 maintenance activities to be completed, including replacing flush fittings, lights, ceiling tiles, air handling unit parts, split unit compressors, wall tiles, blinds, and more. Each activity is assigned a work period between 1 to 14 days to be completed by the specified start date. The schedule aims to complete all 30 maintenance activities by their assigned finish dates to fulfill the maintenance work for the school.

Uploaded by

Hm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
850 views1 page

MEP Completion Schedule

The document outlines a maintenance completion schedule for an American school in Dubai. It details 30 maintenance activities to be completed, including replacing flush fittings, lights, ceiling tiles, air handling unit parts, split unit compressors, wall tiles, blinds, and more. Each activity is assigned a work period between 1 to 14 days to be completed by the specified start date. The schedule aims to complete all 30 maintenance activities by their assigned finish dates to fulfill the maintenance work for the school.

Uploaded by

Hm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project: Maintenance Work for Amrican Shool of Creative , Dubai

Client : Beam Group Shr

MAINTENANCE COMPLETION SCHEDULE


Plan
Sl Activity Description Unit Qty Manpower Days % Plan % Done Remarks
Start Date Work Period Finish Date

Replacment of 3 Flush fittings of HandiCap Toilet & 6 Commencemnt Date 2 Days - 3 100% 0%
1 Lot 9
Flush fittings of toilet

Supply and replacment of LED lamp Class Room LED


2 Lamps- 34 Nos Lights Coridoor - 11 Nos Lights Toilet- Lot 1 Commencemnt Date 3 Days - 4 100% 0% MATERIAL WILL SUBBMIT TO APPROVAL
5 No Light Sensors - 12 Nos light Switch - 18 Nos

Expansion joints to be cleaned, sealed & fixed where Commencemnt Date 2 Days - 2 100% 0%
3 Lot 1
missing
Ceiling tiles to be aligned & any dented or damaged Commencemnt Date 3 Days - 4 100% 0%
4 Lot 1
tiles replaced throughout

▪FAHU 1
    LOCATION- PRINCIPAL CORRIDOOR
1. SUPPLY FAN IS NOT WORKING
  2. DAMAGE ON DUCT
3. COMPRESSOR B2 AND CONTACTOR
4. THERE IS ISSUE WITH DISPLAY
▪ FAHU 2
     LOCATION- GF 1- inspection will be done by Specalist
         1. FILTER DOOR HANDLE DAMAGE 2- Electrical inspection will be done
▪FAHU 3 3- Mechinecal Inspection will be done
     LOCATION- FF 4- Replace the part where required
         1. SUPPLY FAN AND RETURN FAN 5 -Repair part where required
5          2.CONDENSOR B1 AND B2 IS HAVING Lot 1 Commencemnt Date 13 Days - 7 100% 0% 6 -Testing the machine
▪FAHU 4 7- Handing over the sestyem
    LOCATION- FF
          1. SUPPLY FAN IS NOT WORKING
          2. FILTER DOOR HANDLE DAMAGE   

▪PACU 1
    LOCATION- MAIN RECEPTION
           1. SUPPLY FAN AND COMPRESSOR
▪PACU 2
     LOCATION- INDOOR PLAY AREA
Replacment of Split unit compressor - 1 no &
repairing of 2 split units leakage

Replace damaged wall tileswhere cracks and holes Commencemnt Date 2 Days - 2 100% 0%
6 Lot 1
are presnet all areas
Ensure blinds clean & in working order,replace Commencemnt Date 3 Days - 1 100% 0%
7 Lot 1
damaged & ensure chain is fixed to wall
Covers required on network cable holes in all Commencemnt Date 1 Day 1 - 2 100% 0%
8 Lot 1
classrooms
9 Any damaged skirting to be replaced Lot 1 Commencemnt Date 2 Days - 3 100% 0%
10 Any damaged grout to be redone for tiling Lot 1 Commencemnt Date 3 Days - 2 100% 0%
Proper corner guards to be applied throughout all Commencemnt Date 7 Days - 3 100% 0%
11 Lot 1000 Approved MATERIAL WILL ORDER AND SUPPLY
corners 
Supply and replacment of Faulty Control Panel of Commencemnt Date 1 Day - 2 100% 0%
12 Lot 1
Genset
Supply and replacment of Faulty Display of Capacitor Commencemnt Date 1 Day - 2 100% 0%
13 Lot 1
Bank
Supply and replacment of Faulty Access Control of Commencemnt Date 1 Days - 3 100% 0%
14 Each 2
doors - 2 Nos

15 Removal of ASCS Signage in the Swimming Pool Area Lot 1 Commencemnt Date 3 Days - 3 100% 0%
Re painting of the external -road Commencemnt Date 4 Days - 10 100% 0%
16 Lot 1
markings,arrows/curb stones etc. JOUTIN EPOXY PAINT WILL APPLY
Levelling of all interlocks where trip hazards are Commencemnt Date 5 Days - 5 100% 0%
17 Lot 1
presented

18 Dead trees to replace with new one- 3 Nos Palm Tree Nos 3 Commencemnt Date 2 Days - 3 100% 0%
Security cabin door to be replaced with Aluminium Commencemnt Date 14 Days - 4 100% 0%
19 Nos 2
door with Half Glass - 2 Nos Door Cabin will order and fixed on site

20 Security cabin Kitchen cabinets to be replaced - 2 Nos Nos 2 Commencemnt Date 13 Days - 3 100% 0%
Cabin Will order , supply and fixed
Supply and fixing of Pole protector in the Play Area - Commencemnt Date 4 Days - 2 100% 0%
21 Lot 1
Wherever Damaged 
22 Expansion joint cover required LM 1 Commencemnt Date 3 Days - 2 100% 0%
23 Cable entries opening requires sealing  Lot 1 Commencemnt Date 2 Days - 2 100% 0%
24 All cracks on roofs requires repair Lot 1 Commencemnt Date 1 Days - 4 100% 0%
25 All shaft openings to seal  Lot 1 Commencemnt Date 1 Days - 4 100% 0%

All ac and electrical cables requires proper foster Commencemnt Date 3 Days - 7 100% 0%
26 RM 1000
insulation- Repaint with Oil paint- Approx 1000 RM

27 Damaged insulation needs replacement Lot 1 Commencemnt Date 3 Days - 7 100% 0%


Damaged GI trunking to be replaced and secured Commencemnt Date 3 Days - 7 100% 0%
28 Lot 1
properly
29 Replace rusted deluge system fittings & paint Lot 1 Commencemnt Date 2 Days - 3 100% 0%
*Swimming pool Filteration pump system replacment
- 1 No - 2 HP, Filter Lid with O ring - Europa
30 Filter                                                     Lot 1 Commencemnt Date 3 Days - 3 100% 0%
*Replacment of Sump pump- Submersible pump KP
250- Grundfos with PVC fittings- 1 No Will contact with belhasa for maintenace and finalize

Domestic Water -Booster pumps on roof not working Commencemnt Date 1 Days - 2 100% 0%
31 Lot 1
to be fixed along with required repair work
Repair or replace the exisiting pump
32 Damaged ducts on roof to be repaired Lot 1 Commencemnt Date 3 Days - 7 100% 0%
Repair of the Canopies & Pole with Paint Touch Up Commencemnt Date 2 Days - 7 100% 0%
33 Lot 1
wherever Applicable & rusted Area
Supply steel wooden outdoor garbage bin. Size: 100 Commencemnt Date 7 Days - 1 100% 0%
34 Nos 4
* 200 cm. Material will order and supply