LPG Bottling Plant HAZOP Report
LPG Bottling Plant HAZOP Report
Sept’2020
                  PREPARED BY
         SV ENVIRO LABS & CONSULTANTS
     Recognized by GOI, MOEF, QCI Accredited
    Enviro House, B-1, Block –B, IDA, Autonagar,
             Visakhapatnam-530012
                 Andhra Pradesh
                                                                Page 60
                 HAZARD & OPERABILITY STUDIES
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT        HAZOP REPORT
CONTENTS
                                                                      Page 2
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT   HAZOP REPORT
LIST OF FIGURES
                                                                 Page 3
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT           HAZOP REPORT
                                                                      Page 4
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                              HAZOP REPORT
1.0      INTRODUCTION:
         This Hazard and Operability Studies report has been prepared for the LPG Bottling
         Plant of Energon Petro Products Pvt. Ltd. The LPG Bottling Plant of Energon Petro
         Products Pvt. Ltd is situated at Sy.No: 9/2 & 10/1, Golagamudi Village,
         Venkatachalam Mandal, SPSR Nellore District . Noticing the damage potential and
         thus risk arising due to transportation, storage and handling of the flammable LPG
         Energon Petro Products Pvt. Ltd. retained SV Enviro Labs & Consultants,
         Visakhapatnam, to undertake the Hazard and Operability Studies for the LPG Bottling
         Plant.
         The Total site area of the LPG Plant is 22136.48 Sq.mt. The activity of the plant is to
         receive Liquefied Petroleum Gas (LPG) in bulk quantities from refineries / storage
         points through tank trucks, store the same, bottle the LPG into cylinders and distribute
         to the dealers network. The capacity of the Mounted Storage vessel (bullets) is 30 MT
         x 3 Bullets bottling to a capacity of 30000MT LPG Per annum.
         Activities of Plant:
         1. To receive Liquefied Petroleum Gas (LPG) in bulk quantities from refineries
         2. Storage of the LPG in Mounded bullets
         3. Bottling of LPG into cylinders
         4. Inspection and testing of filled cylinders
         5. Dispatch of filled cylinders
                                                                                              Page 5
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                        HAZOP REPORT
10) Unloading of the empty cylinders in the feeding conveyor for carousel filling.
12) After filling of the cylinders check for leaks and load it into conveyor for loading.
13) Filled cylinders are loaded into the empty trucks and weighed.
  There will be no chemical process involved and the operation carried out will be receipt
  of LPG (Liquid Petroleum Gas) by Bullet tankers from HPCL. After receiving of bulk
  LPG in isolated storage vessels filling of LPG into domestic and non-domestic cylinders
  using electronic carousel and associated systems. The cylinders filled will be checked for
  quality and then transported with packed trucks to distributors, where filled cylinders are
  transported to individual customers. In the LPG bottling plant, the storage will be in
  pressurized form in mounded storage.
  Transport and handling through piping system, handling techniques, specific equipment
  used and standard operating procedures etc. the details are given below:
                                                                                         Page 6
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                     HAZOP REPORT
  pressurization takes place from the other bullet to this delivery bullet with help of LPG
  compressors.
                                                                                     Page 7
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT   HAZOP REPORT
Figure 1: 2 KM TopoMap
                                                              Page 8
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                         HAZOP REPORT
                                                                                        Page 9
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                             HAZOP REPORT
C. Reactivity Classification
4       Materials, which in themselves are readily capable of detonation or of explosive
        decomposition or reaction at normal temperature and pressures.
3       Materials, which in themselves are capable of detonation or explosive reaction but
        require a strong initiating source or which must be heated under confinement before
        initiation or which react explosively with water.
2       Materials, which in themselves are normally unstable and readily undergo violent
        chemical change but do not detonate. Also materials, which may react violently with
        water or which may from potentially explosive mixtures with water.
1       Materials which in themselves are normally stable, but which can become unstable at
        elevated temperature and pressure or which may react with water with some release
        of energy but not violently.
0       Materials which in themselves are normally stable, even under fire exposure
        conditions, and which are not reactive with water.
       i.   Toxicity Hazard
       Health hazard for the LPG is equal to one (Nh=1). Adequate safety arrangements are
       provided to facilitate a Quick First Aid for the worker exposed to the chemicals.
      ii.   Flammability Hazard
       The highest flammability rating is reported for LPG. (Nf=4) according to NFPA.
     iii.   Reactivity Hazard
       Reactivity hazard rating for LPG is zero.
       Following elements/events which can be lead to a major accident:
               Large scale fire and explosion in storage area due to damage of the bulk
                storage MSV pipeline.
               Over turning of LPG road tankers and other transport hazard.
               Flash fire due to leakage of LPG.
               Equipment failure/malfunction like relief valve failure, flange gasket failure,
                pumps mechanical seals etc. resulting in leakage of LPG to atmosphere.
               Accident due to overfilled cylinders or fire in the vicinity.
               Lack of adequate fire protection facilities available at different places of LPG
                unloading, loading and usage.
               Experience level of personnel involved and their capacity to cope with
                emergency situation.
                                                                                        Page 10
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                      HAZOP REPORT
                                                                                     Page 11
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                         HAZOP REPORT
                                                                                           Page 12
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                        HAZOP REPORT
     These definitions are an important part of the basic HAZOP premise that the process
     does not have inherent hazards or operating problems when the unit is operating as
     designed, and as defined by the basic documents such as the process flow diagrams,
     equipment specifications, and operating procedures. In other words, if there are no
     deviations from the norm, there are no problems.
                                                                                      Page 13
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                       HAZOP REPORT
                                                                                   Page 14
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                        HAZOP REPORT
        o The ability of the team to use the approach as an aid to their imagination in
            visualizing deviations, causes, and consequences.
        o The ability of the team to concentrate on the more serious hazards which are
            identified.
     The process is systematic and it is helpful to define the terms that are used:
        a. STUDY NODES - The locations (on piping and instrumentation drawings and
            procedures) at which the process parameters are investigated for deviations.
        d. CAUSES - These are the reasons why deviations might occur. Once a
            deviation has been shown to have a credible cause, it can be treated as a
            meaningful deviation. These causes can be hardware failures, human errors, an
            unanticipated process state (e.g., change of composition), external disruptions
            (e.g., loss of power),etc.
        e. CONSEQUENCES - These are the results of the deviations should they occur
            (e.g., release of toxic materials). Trivial consequences, relative to the study
            objective, are dropped.
        f. GUIDE WORDS - These are simple words which are used to qualify or
            quantify the intention in order to guide and stimulate the brainstorming
            process and so discover deviations. The guide words shown in the following
            table are the ones most often used in a HAZOP; some organizations have
            made this list specific to their operations, to guide the team more quickly to
            the areas where they have previously found problems. Each guide word is
            applied to the process variables at the point in the plant (study node) which is
            being examined.
                                                                                      Page 15
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                        HAZOP REPORT
      HAZOP study involves a set of standardized GUIDE WORDS, which are used to
      initiate the discussion in the team. All possible deviations in process parameters in a
      reactor or a pipeline are considered to determine their causes and consequences. If a
      hazard is identified, first the existing protective measures are analyzed with respect to
      the intensity of the hazard. If the protective measures are not adequate,
      recommendations are given to mitigate the hazard.
                                                                                       Page 16
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                         HAZOP REPORT
      Other than what else can happen apart from normal operation, e.g. start-up, shutdown,
      up rating, low rate running, alternative operation mode, failure of plant services,
      maintenance, catalyst change, etc.
      Hazard & Operability Study require prior understanding of the behavior and hazards
      of the hazardous chemicals being used in the plant, which mainly includes:
         Physical & Chemical Properties
         Fire & Explosion Characteristics
         Toxicological Properties, if any
      First HAZOP sheets are prepared and then the team discusses on possibilities of
      occurrence of various deviations from the intended operating conditions by employing
      the guidewords; thereafter responses of the control equipments for these deviations
      are analyzed. Then, consequences of the deviations are examined for vulnerability
      towards occurrence of unsafe situations and suggestions are made to improve system
      reliability, if required.
                                                                                       Page 17
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                    HAZOP REPORT
      To carry out HAZOP, a team was formed to carry out the assessment for effective and
      systematic study of the LPG storage and bottling process. Accordingly following team
      was formed.
         Plot plan
         Process Manuals & Process flow Diagrams
         P&I diagrams
                                                                                  Page 18
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT   HAZOP REPORT
                                                                                         Page 60
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT   HAZOP REPORT
Fig 2.2P&ID
                                                                                   Page 20
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                            HAZOP REPORT
                                                                                                                    Recommendations
 Guide Word      Deviation       Parameter            Causes                   Consequences                                                         Status/Action taken
                                                                                                           Recommendations/Action required
No             No Flow        Flow           1 No LPG left in tanker        Transfer    pipe   line   There        should       be           Will be provided
                                                                            under pressure            provision for Suction
                                                                                                      pressure             tripping
                                                                                                      system for compressor
                                             3 Loading     Arms/     pipe   Transfer    pipe   line   There        should       be           Will be Provided
                                                line blockage               under pressure            provision      for      high
                                                                                                      discharge        pressure
                                                                                                      tripping     system       for
                                                                                                      compressor
                                             4 Unloading arm failure        Transfer    pipe   line   Excess      Flow Check                 EFCV will be provided
                                                                            under pressure            Valve on tanker side
                                                                                                      as well as on hose
                                                                                                      side       should      close
                                                                                                      automatically
                                             5 Any    of   the     valves   Transfer    pipe   line   There        should       be           Will be Provided
                                                between road tanker         under pressure            provision      for      high
                                                and MSV is closed                                     discharge        pressure
                                                                                                      tripping     system       for
                                                                                                      compressor
Less           Low Flow       Flow           1 Pressure differential is     More       time     for   Excess      Flow Check                 Will      be     checked
                                                less between the MSV                                                                         frequently     during the
                                                                                                                                                                          Page 21
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                HAZOP REPORT
Node: 1. Liquid Line Section from Tank Lorry Decanting Shed to Mounded Storage Vessels
                                                                                                                      Recommendations
 Guide Word      Deviation       Parameter               Causes                   Consequences                                                       Status/Action taken
                                                                                                              Recommendations/Action required
Less           Less/Low       Pressure       1 Some        leakage       or    Fire Hazards                Ensure proper working                Self explanatory
               Pressure                         compressor not able to                                     of LPG compressor
                                                create           adequate
                                                differential pressure
Less           Less/Low       Temperature    1 Very       low     ambient      None. Since boiling         None                                 Self explanatory
               Temperature                      temperature                    point of LPG is -9
                                                                               deg. C and freezing
                                                                               conditions     in    LPG
                                                                               pipelines     will   not
                                                                               occur          because
                                                                               lowest      temperature
                                                                               at Energon does not
                                                                               reach -9 deg. C
More           More/High      Flow           1 Not possible                    None                        None                                 EFCV will be provided
               Flow
                                                                                                                                                                           Page 22
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                     HAZOP REPORT
Node: 1. Liquid Line Section from Tank Lorry Decanting Shed to Mounded Storage Vessels
                                                                                                                             Recommendations
 Guide Word      Deviation       Parameter              Causes                          Consequences                                                         Status/Action taken
                                                                                                                    Recommendations/Action required
More           More/High      Pressure       1 Isolation valves closed            Transfer              line   In     case     of     high            Auto tripping system will
               Pressure                         in        error           while   subjected              to    pressure               stop            be provided
                                                compressor running                pressure                     operation and check
                                                                                                               the transfer line
More           More/High      Temperature    1 LPG            at         higher   If temperature rise          Cool the pipeline by                   Will be followed
               Temperature                      temperature due to fire           not           controlled     water      spray       and
                                                in vicinity                       transfer pipeline will       regular patrolling is
                                                                                  rupture     hence     fire   desired
                                                                                  hazards
Other than     Corrosion      Corrosion      1 Pure       LPG       is     not    Pipeline           failure   Periodic         internal              Periodic           internal
                                                corrosive                  but    hence      release     of    inspection of pipeline                 inspection will be done
                                                mercaptan added to it             LPG       vapour     may     should be done to                      & thickness of pipeline
                                                may corrode pipeline              occur leading to Fire        detect any corrosion                   will be measured ultra
                                                                                  hazards       in      the                                           sonically
                                                                                  presence of ignition
Other than     Maintenance    Maintenance    1 During maintenance of              LPG        vapour/liquid     Proper purging/water                   Will be followed
               Hazards                          valves/pumps/compres              may        come       out    flushing             before
                                                sors/Testing                 of   causing Fire hazards         maintenance
                                                Mounded                 Storage
                                                vessels
Other than      Start-        Start-         1 Leakage from flange                LPG        vapour/liquid     Strict supervision to                  Will       be
                up/Shutdown up/Shutdown         joints at the time of             may        come       out    be followed at the                     followed
                hazards                         connection/disconnecti            causing Fire hazards         time       of        Start-
                                                on                                                             up/Shutdown
                                                                                                               operations
                                                                                                                                                                                    Page 23
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                            HAZOP REPORT
Node: 1. Liquid Line Section from Tank Lorry Decanting Shed to Mounded Storage Vessels
                                                                                                             Recommendations
 Guide Word      Deviation         Parameter            Causes                 Consequences                                               Status/Action taken
                                                                                                   Recommendations/Action required
As well as      Flow of          Contamination 1 Water present in LPG     No         hazardous   Water draining from                 Water draining is done
                foreign                          road   tanker   coming   consequences           MSV       desired   and             as   per    established
                material along                   with LPG                                        draining be done as                 procedure
                with LPG                                                                         per the established
                                                                                                 procedure            to
                                                                                                 minimize            LPG
                                                                                                 release
                                                                                                                                                                Page 24
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                               HAZOP REPORT
Recommendations
No             No Flow       Flow           1 The          MSV         is   Knocking             of     High       liquid     level   Liquid    level      tripping
                                             accidentally filled up         compressor                  tripping            system    system        will        be
                                             and      no     space   for                                should be provided in         provided. Further high
                                             vapour                                                     suction side                  level    alarm    will    be
                                                                                                                                      provided in MSV and
                                                                                                                                      hence no chance of
                                                                                                                                      overfilling in MSV
                                            2 The      vapour        line   Compressor cylinder         Low suction tripping          Will be Provided
                                             blockage/valve            is   heated up                   system      should      be
                                             closed                                                     provided
Less           Less Flow     Flow           1 Sudden decrease of            Vapour formation too        No action required as         Self explanatory
                                             temperature                    low           resulting     this condition is not
                                                                            decrease in storage         likely     occurred     as
                                                                            pressure                    temperature in winter
                                                                                                        is always more than 2
                                                                                                        deg. C (as per 30
                                                                                                        years IMD data) and
                                                                                                        boiling point of LPG
                                                                                                        is less than 0 deg. C
                                                                                                        (-9 deg. C)
Less           Less/Low      Temperature    1 Very     low       ambient    If            ambient       No action required as         MSV will be inspected
               Temperature                   temperature (below 0           temperature      goes       this condition is not         by third party
                                             deg. C)                        below boiling point of      likely     occurred     as
                                                                            LPG, the gas may be         temperature in winter
                                                                            freezed    and   bullet     is always more than 2
                                                                                                                                                                      Page 25
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                           HAZOP REPORT
Node: 2. Vapour Line between Mounded Storage Vessels and Compressor Suction side
Recommendations
More           More/High      Flow          1 Valve leak                  Vapour LPG release           Inspect      the      valve      Inspection will be done
               Flow in case                                               hence     asphyxiation       before start         up     of
               excess flow                                                problems     and Fire        compressor
               check valve                                                hazards
               not working
                                            2 Pipeline leak due to        Vapour LPG release           Inspection      of        line   Inspection will be done
                                             impact        or     other   hence     asphyxiation       required             before
                                             reasons                      problems     and Fire        starting                  the
                                                                          hazards                      compressor
                                            3 Heat or flame on bullet     Vapour LPG release           If fire is grave the fire        Auto medium velocity
                                                                          hence     asphyxiation       hydrant       can          be    sprinkler system will be
                                                                          problems     and Fire        operated. Hence the              provided     and     fire
                                                                          hazards                      fire     hydrant          ring   fighting will be done as
                                                                                                       should always remain             per            Disaster
                                                                                                       pressurized.              Fire   Management Plan
                                                                                                       should        also         be
                                                                                                       controlled by DCPs
More           More/High      Pressure      1 High pressure in bullet     Vapour     line    burst     Excess     flow      check       Will be Provided
               Pressure                                                   and release of LPG           valve      should          be
                                                                          may result into fire         provided on bullet
                                            2 Fire/     heating      on   LPG vapour release           If fire is grave the fire        Jockey pump shall be
                                             external      surface   of   in fire near the safety      hydrant       can          be    installed
                                             bullet                       valve or a jet fire          operated. Hence the
                                                                          may ensure                   fire     hydrant          ring
                                                                                                       should always remain
                                                                                                                                                                    Page 26
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                            HAZOP REPORT
Node: 2. Vapour Line between Mounded Storage Vessels and Compressor Suction side
Recommendations
pressurized.
More           More/High     Temperature    1 Some fire in the vicinity   Vapour        pressure/        Proper     maintenance         SRV shall be installed
               Temperature                                                internal pressure rise         of SRV's desired. Fire         that will actuate and
                                                                          in bullet due to fire in       control       measures         auto-medium         velocity
                                                                          the vicinity. It may           should work properly.          sprinkler system will be
                                                                          cause SRV actuation            Auto-medium velocity           provided        which      will
                                                                          hence fire hazards             water              sprinkler   bring       down           the
                                                                                                         system      should       be    temperature to normal
                                                                                                         operated.
Other than     Corrosion     Corrosion      1 Pure    LPG      is   not   Pipeline           failure     Periodic            internal   Inspection will be done
                                             corrosive              but   hence      release     of      inspection of major            and     bullets    will     be
                                             mercaptan added to it        LPG       vapour      may      piping      and        LPG     hydraulically tested by
                                             may               corrode    occur leading to Fire          bullets after each five        CCE      approved         third
                                             pipeline/bullet              hazards       in      the      years should be done           party
                                                                          presence of ignition           to        detect        any
                                                                                                         corrosion
                                                                                                                                                                          Page 27
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                            HAZOP REPORT
Recommendations
No             No Flow       Flow          1 Compressor          not   Tank lorry cannot be          LPG        pumps         and     Preventive     maintenance
                                             working                   decanted                      compressors              are     schedule will be followed
                                                                                                     most                  critical
                                                                                                     equipment        of    plant
                                                                                                     therefore              there
                                                                                                     should be preventive
                                                                                                     maintenance              and
                                                                                                     daily     inspection       of
                                                                                                     equipment
                                           2 Power failure             Same as explained             The D.G. set should              D.G. set installed will be
                                                                       above                         be regularly tested for          operated
                                                                                                     fool proof operation.
                                                                                                     Compressor can be
                                                                                                     started                 after
                                                                                                     transferring plant load
                                                                                                     from     state    grid     to
                                                                                                     D.G. set
Less           Less/Low      Pressure      1 Compressor          not   Desired results not           Proper     maintenance           Preventive     maintenance
               Pressure                      working properly          obtained        pertaining    of          compressor           schedules will be followed
                                                                       to      decantation     of    desired
                                                                       lorry     but    no   fire
                                                                       hazards
                                                                                                                                                                       Page 28
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                              HAZOP REPORT
Recommendations
Less           Less/Low      Temperature   1 LPG at low ambient          None                            None                         Self explanatory
               Temperature                   temperature
More           More/High     Temperature   1 Cylinder    jacket     of   The           compressor        There       should     be    Cooling water interlocking
               Temperature                   compressor not being        heats      up     and     it    regular      check     for   pressure    switch   will     be
                                             cooled properly             fails/trips                     proper cooling water         provided in the return line
                                                                                                         line and its operation
                                           2 The discharge line of       The pipeline/ hose              The       fire    fighting   Fire fighting arrangement
                                             compressor heated up        may fail due to heat            arrangements           be    will be checked at regular
                                             due to external fire or     radiation          hence        inspected            and     intervals
                                             flame                       asphyxiation                    checked      at   regular
                                                                         problems        and Fire        intervals
                                                                         hazards
Other than     Corrosion     Corrosion     1 Pure    LPG      is   not   Pipeline           failure      Periodic          internal   Periodic internal inspection
                                             corrosive             but   hence         release    of     inspection of pipeline       will be done & thickness of
                                             mercaptan added to it       LPG      vapour         may     should be done to            pipeline will be measured
                                             may corrode pipeline        occur                           detect any corrosion         ultra sonically
                                                                                                                                                                         Page 29
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                              HAZOP REPORT
Recommendations
No              No Flow        Flow           1 Any of the valve from      Operational delay            Regular               and    Preventive
                                                MSV to LPG pump                                         preventive                   maintenance of valves
                                                suction or TLD shed to                                  maintenance            of    will be done as per
                                                bullet closed                                           valves desired               schedules formulated
                                              2 Pipeline blockage          LPG pumps heats up           The pipeline should          Line strainer      will be
                                                                           due to wearing and           be cleaned after each        provided     on    suction
                                                                           increased      vibration     two years                    side of pump
                                                                           level on account of
                                                                           cavitation developed
                                                                           in the pump
                                              3 No LPG in MSV              LPG pump heats up            Some          interlocking   Low pressure tripping
                                                                                                        system be provided           device will be provided
                                                                                                        so that if there is no
                                                                                                        flow   of     LPG    from
                                                                                                        bullet to pipeline it
                                                                                                        should trip
Less            Less Flow      Flow           1 Blockage        in   the   LPG pump will lose           Clear blockage open          A tripping system will
                                                pipeline or the valves     its     NPSH       (Net      valve fully                  be provided
                                                are not fully open         Positive        Suction
                                                                           Head)
                                                                                                                                                                  Page 30
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                   HAZOP REPORT
Node: 4. Inlet/Outlet Liquid LPG pipeline from MSV to LPG pump suction
Recommendations
More            More/High        Flow          1 Not possible                   None                           None                          EFCV will be provided
                Flow
More            More/High        Temperature   1 External       fire      on    Pipeline failure and           The hydrant should            Fire hydrant valves &
                Temperature                     pipeline                        LPG pool formation             be operated to kill the       DCP will be used to kill
                                                                                on ground hence fire           fire in the incipient         the fire
                                                                                hazards                        stage
                                               2 External fire on bullets       The    high    intensity       The SRV should start          Yearly       inspection/
                                                                                may       cause     shell      functioning     if      the   testing of SRV will be
                                                                                rupture           hence        pressure in bullet is         done by the competent
                                                                                vapour              cloud      equivalent      to      its   person
                                                                                formation     and     fire     design        pressure.
                                                                                hazards                        Hence                proper
                                                                                                               functioning of SRV be
                                                                                                               ensured
Other than      Corrosion        Corrosion     1 Internal corrosion on          Flammable           LPG        Periodic        internal      Inspection will be done
                                                piping and pipe fittings        vapour release                 inspection of pipeline        during Operation phase
                                                                                                               should be done to
                                                                                                               detect any corrosion
Reverse/        Reverse/         Flow          1 Not possible due to            None                           None                          Self explanatory
Misdirected     Misdirected                     presence of NRV (Non
                Flow of LPG                     return valve) on bullet
                                                side as well as on
                                                pump suction side
As well as      Flow of foreign Flow           1 Flow of water along            No            hazardous        Water      draining     for   Water draining will be
                material along                  with       LPG.        Water    consequences                   each new parcel id            done as per established
                with LPG                        draining not done for                                          desired                       procedure
                                                each        new        parcel
                                                received
                                                                                                                                                                        Page 31
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                 HAZOP REPORT
Recommendations
No             No Flow       Flow              1 Pump not working             Bottling process will        Check motor faults,          The       pumps         and
                                                                              be              stopped      Impeller     mechanical      machineries      will    be
                                                                              automatically                seal failure in other        maintained as per their
                                                                                                           words                good    maintenance schedule.
                                                                                                           maintenance of pump
                                                                                                           and motor is desired
                                               2 All liquid LPG going         Same as explained            Regular checking of          Regular checking will
                                                back to suction line          above                        pump      and     pipeline   be done
                                                through circulation line                                   desired
                                               3 Some valve erratically       Bottling operation in        Proper     maintenance       Valve will be properly
                                                closed                        filling shed stops           of valve is required         maintained. Schedules
                                                                                                                                        formed for maintenance
                                                                                                                                        will be strictly followed
                                               4 Sudden power failure         Bottling process will        If   power      failure is   D.G. set installed will be
                                                                              be              stopped      prolonged the D.G.           operated
                                                                              automatically                set may be used
Less           Less Flow     Flow              1 Some      obstruction   in   LPG pump will lose           Clear the blockage           A tripping system will
                                                pipeline      or    some      its     NPSH.        The                                  be provided
                                                leakage                  in   leaked     LPG       may
                                                pipeline/LPG pump             cause       fire      &
                                                                                                                                                                      Page 32
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                               HAZOP REPORT
Recommendations
explosion hazards
Less           Less/Low      Pressure          Some         leakage    in   Fire and explosion         Operate fire fighting            Adequate fire fighting
               Pressure                        discharge line               hazard                     system                           arrangements        will   be
                                                                                                                                        provided
More           More/High     Flow              Throttling     valve   not   The        downstream      LPG pump being a                 Self explanatory
               Flow                            functioning properly         discharge line will be     centrifugal pump only
                                                                            under pressure             churning         will     take
                                                                                                       place and discharge
                                                                                                       pressure will increase
                                                                                                       than rated pressure.
                                                                                                       No       fire         hazards
                                                                                                       anticipated
More           More/High     Pressure          Suction line pressure        The discharge line         Control the discharge            Maintenance        of      DP
               Pressure                        higher than normal           subjected to higher        pressure by using the            valve,   TSV       (Thermal
                                                                            pressure                   valve           on         the   Safety Valve) and Pop
                                                                                                       circulation               line   action     valve    (Safety
                                                                                                       provided in pump, as             Relief Valve) will be
                                                                                                       well            as         DP    done                through
                                                                                                       (differential pressure)          maintenance schedule
                                                                                                       valve provided in the            formulated
                                                                                                       discharge line may
                                                                                                       be used. Pop action
                                                                                                       relief     valves         are
                                                                                                       provided             in    the
                                                                                                       pipeline segments to
                                                                                                       take care of higher
                                                                                                                                                                        Page 33
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                   HAZOP REPORT
Recommendations
discharge pressure
More            More/High        Temperature   1 The pipeline is at a            The pipeline may fail        Stop pump and auto          Procedure mentioned in
                Temperature                     higher         temperature       if fire is severe and        medium           velocity   last column is followed
                                                due to flame or fire             there may be fire            water sprinkler to be
                                                                                 hazards                      operated to kill the
                                                                                                              fire. If fire is severe
                                                                                                              then      fire   hydrant
                                                                                                              water discharge can
                                                                                                              also be used
Other than      Corrosion        Corrosion     1 Pure     LPG      is     not    Pipeline         failure     Periodic         internal   Periodic           internal
                                                corrosive                 but    hence      release    of     inspection of pipeline      inspection will be done
                                                mercaptan added to it            LPG     vapour       may     should be done to           & thickness of pipeline
                                                may corrode pipeline             occur                        detect any corrosion        will be measured ultra
                                                                                                                                          sonically
Reverse/Misdi   Reverse/Misdir Flow            1 Not possible due to             None                         None                        Self explanatory
rected          ected Flow                      NRV       (Non          return
                                                valve)    at     discharge
                                                side of LPG pump and
                                                filling machines
As well as      Flow of          Contamination 1 Water     draining       not    No          hazardous        Water      draining   for   Water draining will be
                foreign                         done      in     MSV       on    consequences                 each new parcel is          done as per established
                material along                  regular        basis      and                                 desired                     procedure
                with LPG                        water is pumped along
                                                with LPG
                                                                                                                                                                        Page 34
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                HAZOP REPORT
Recommendations
No            No Flow          Flow          1 No LPG in MSV                 Compressor cylinder               Low      level     suction    Will be Provided
              to/from bullet                                                 heats        up         and       tripping for pump and
                                                                             damages         to      LPG       compressor             are
                                                                             pump                              desired to prevent the
                                                                                                               damage
                                             2 Inlet line/ Outlet line       More       pressure        in     Fire hydrant valves           Dedicated fire fighting
                                              closed                         transfer     hose       and       and     fire     protection   system provided
                                                                             pipeline and this may             measures            should
                                                                             cause transfer hose               work fail safe
                                                                             rupture     hence        fire
                                                                             hazards
Less          Less flow to     Flow                                          Leakage         in       the      Regular patrolling of         Regular        patrolling
              and from MSV                                                   valves or pipeline. It            pipeline desired and          maintenance of valves
                                                                             may        cause         fire     proper     maintenance        will be done as per
                                                                             hazards                           of valves desired             maintenance schedules
                                                                                                                                             formulated
                                                                                                                                                                         Page 35
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                            HAZOP REPORT
Recommendations
More          More/High     Pressure       1 High Liquid level             Liquid    may       knock       High      liquid       level    Will be Provided
              Pressure                                                     compressor                      suction     tripping     for
                                                                                                           compressor desired
                                           2 Some fire or heat from        SRV (Safety Relief              Control      fire       and     Fire control done as per
                                            vicinity                       Valve) may operate              ensure              proper      DMP and SRVs will be
                                                                           hence       fire      may       maintenance of SRVs             tested    annually        and
                                                                           aggravate                                                       records are maintained
More          More Level    Level          1 Rochester Gauge not           LPG       may        pass       Preventive                      Preventive
                                            showing value (weigh           through SRVs and                maintenance               of    maintenance        will    be
                                            scale)                         hence fire and toxic            Rochester           Gauge       done     as   per         the
                                                                           hazards. No damage              desired                         schedule
                                                                           to LPG pump and
                                                                           compressor because
                                                                           these will trip due to
                                                                           high     level     tripping
                                                                           system
More          More/High     Temperature    1 External    fire   in   the   SRVs      actuate and           Adequate                 fire   The fire fighting system
              Temperature                   vicinity                       passes large vapour             protection         facilities   will be provided as per
                                                                           flow                            required and fail safe          OISD requirements.
                                                                                                           working      of       these
                                                                                                           facilities required             Temperature        indicator
                                                                                                                                           will be provided
Other than    Corrosion     Corrosion      1 Leakage of LPG due to         Fire Hazards                    All pipelines should            The pipeline thickness
                                            corrosion                                                      be     subjected          to    will     be   measured
                                                                                                           thickness                       ultrasonically and these
                                                                                                           measurements            and     are also subjected to
                                                                                                           hydrostatic tests to            hydrostatic           tests.
                                                                                                           determine strength              Record of thickness will
                                                                                                                                           be maintained
                                                                                                                                                                           Page 36
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                       HAZOP REPORT
Recommendations
As well as    Other than    Contamination 1 Water may come along       None hazardous     Water          draining     Water draining will be
              LPG                          with   LPG   if     water                      should be done for          done as per established
                                           draining not done                              each     new       parcel   procedure
                                                                                          received
                                                                                                                                                Page 37
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                               HAZOP REPORT
Recommendations
No             No Flow       Flow          1 LPG pump not working           Filling operation at          Rectify the pump          Self explanatory
                                                                            carousel will stop
                                           2 LPG       discharge     line   Fire and explosion            Stop pump and repair      Necessary      hydrostatic
                                             leakage                        hazard                        leakage.     Patrolling   tests for pipeline will be
                                                                                                          desired                   done. Regular patrolling
                                                                                                                                    will also be taken up
                                           3 Filling     gun       hose     Fire and explosion            Proper     maintenance    LPG    hoses     will   be
                                             rupture                        hazard                        of hoses desired          subjected               to
                                                                                                                                    hydrostatic, pneumatic
                                                                                                                                    and electrical continuity
                                                                                                                                    tests once in 4 months
                                           4 Filling gun detached           LPG vapour release            Proper      functioning   Self explanatory
                                             from cylinder                                                and maintenance of
                                                                                                          carousel desired
Less           Less Flow     Flow          1 Some        leakage       in   If    leakage persists        Regular patrolling of     Regular patrolling will
                                             pipeline                       for     longer      time      pipeline desired          be taken up
                                                                            fire/explosion
                                                                            hazards may occur
                                           2 LPG pump not running           The filling time for          The                pump   Will be maintained
                                             at its rated capacity          cylinders            will     maintenance desired
                                                                            increase
Less           Less/Low      Temperature   1 Very       low    ambient      None. Since boiling           None                      Self explanatory
               Temperature                   temperature                    point of LPG is -9
                                                                            deg. C and freezing
                                                                            conditions    in    LPG
                                                                            pipelines    will    not
                                                                            occur         because
                                                                                                                                                                 Page 38
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                HAZOP REPORT
Recommendations
                                                                              lowest     temperature
                                                                              at Energon does not
                                                                              reach -9 deg. C
Less           Less/Low      Pressure       1 LPG pump not running            Less flow resulting in         Proper     maintenance        Maintenance schedules
               Pressure                       at its rated capacity           slow rate of LPG               of pump desired               of     pumps     will         be
                                                                              filling at carousel                                          followed
More           More/High     Temperature    1 Some fire in the vicinity       Pipeline may rupture           Ensure              proper    Fire                 fighting
               Temperature                    causing               higher    causing     fire      and      functioning       of   fire   arrangements         will     be
                                              pressure        on        LPG   explosion                      fighting systems              provided        as           per
                                              pump discharge line                                                                          statutory requirements.
                                              connected to carousel                                                                        TSV provided between
                                                                                                                                           two flanges
Other than     Corrosion     Corrosion      1 Pure      LPG        is   not   Pipeline           failure     Periodic          internal    Periodic             internal
                                              corrosive                 but   hence      release     of      inspection of major           inspection will be done
                                              mercaptan added to it           LPG      vapour       may      piping      and        LPG    & thickness of pipeline
                                              may corrode pipeline            occur                          bullets after each five       is      measured            ultra
                                              or bullet                                                      years should be done          sonically to detect any
                                                                                                             to       detect        any    corrosion
                                                                                                             corrosion
As well as Flow of foreign Contamination 1 Water draining not No hazardous Water draining for Water draining will be
                                                                                                                                                                               Page 39
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                            HAZOP REPORT
Recommendations
                material along                done      in     MSV     on   consequence      only     each    new       parcel   done as per established
                with LPG                      regular        basis    and   water will go along       received desired in        procedure
                                              water is pumped along         with LPG in cylinders     MSV
                                              LPG and it will go to
                                              cylinders
Reverse/Misdi   Reverse/Misdi Flow           1 Not possible due to          None                      None                       Self explanatory
rected          rected Flow                   presence of NRV (non
                                              return         valve)    at
                                              discharge        of     LPG
                                              pump and at carousel
                                                                                                                                                           Page 40
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                              HAZOP REPORT
Recommendations
No             No Flow        Flow          1 The      vapour      line    Compressor cylinder          Low      level      suction    Low suction tripping will
                                             blockage/valve           is   heated up                    tripping            system     be provided
                                             closed                                                     should be provided
                                            2 No      LPG       vapour     Knocking              of     High       liquid      level   High liquid level tripping
                                             available for suction in      compressor                   tripping            system     system will be provided
                                             mounded            storage                                 should be provided in
                                             vessel                                                     suction side
                                            3 Compressor         failure   The        decantation       If power failure is for        D.G.    sets    will   be
                                             due to power failure or       operation of Tanker          longer time D.G. sets          operated
                                             other reasons                 Lorry stops                  should be operated.
Less           Less Flow      Flow          1 Sudden decrease of           Vapour formation too         No action required as          Self explanatory
                                             temperature                   low            resulting     this condition is not
                                                                           decrease in storage          likely     occurred      as
                                                                           pressure                     temperature in winter
                                                                                                        is always more than 2
                                                                                                        deg. C (as per 30
                                                                                                        years IMD data) and
                                                                                                        boiling point of LPG
                                                                                                        is less than 0 deg. C
                                                                                                        (-9 deg. C)
More           More/High      Flow          1 Pipeline leak due to         Vapour LPG release           Inspection       of     line   Inspection will be done
               Flow in case                  impact       or      other    hence      asphyxiation      required              before
               excess flow                   reasons                       problems      and Fire       starting                 the
               check valve                                                 hazards                      compressor
                                                                                                                                                                    Page 41
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                              HAZOP REPORT
Recommendations
               not working                  2 Valve leak                     Vapour LPG release             Inspect     the      valve    Inspection will be done
                                                                             hence      asphyxiation        before start up         of
                                                                             problems     and Fire          compressor
                                                                             hazards
                                            3 Heat     or     flame     on   Vapour LPG release             If fire is grave the fire     Auto medium velocity
                                             mounded             storage     hence      asphyxiation        hydrant      can        be    sprinkler            system
                                             vessels        (MSV       and   problems     and Fire          operated. Hence the           provided       and       fire
                                             compressors)                    hazards                        fire     hydrant      ring    fighting will be done as
                                                                                                            should always remain          per                 Disaster
                                                                                                            pressurized.          Fire    Management Plan
                                                                                                            should      also        be
                                                                                                            controlled by DCPs
More           More/High      Pressure      1 Higher        pressure    in   Vapour      line    burst      Excess     flow     check     Excess       flow      check
               Pressure                      connection          vessels     and release of LPG             valve      should       be    valve will be provided
                                             such as MSV                     may result into fire           provided     on      bullet
                                                                                                            side
                                            2 Fire/heating             on    LPG vapour release             If fire is grave the fire     Jockey pump shall be
                                             external        surface    of   due to actuation of            hydrant      can        be    installed
                                             storage vessels                 the safety relief valve        operated. Hence the
                                                                             or a jet fire may              fire     hydrant      ring
                                                                             ensure                         should always remain
                                                                                                            pressurized.
Other than     Corrosion      Corrosion     1 Pure     LPG       is    not   Pipeline           failure     Periodic           internal   Periodic            internal
                                             corrosive                 but   hence      release     of      inspection of major           inspection will be done
                                             mercaptan added to it           LPG      vapour      may       piping and equipment          & thickness of pipeline
                                             may corrode pipeline/           occur                          (after each five years)       is      measured        ultra
                                             and storage vessels                                            should be done to             sonically to detect any
                                                                                                            detect any corrosion          corrosion.          Storage
                                                                                                                                          vessels are inspected
                                                                                                                                          and        subjected       to
                                                                                                                                                                          Page 42
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT   HAZOP REPORT
Recommendations
                                                                                                                        Page 43
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                          HAZOP REPORT
Recommendations
No             No Flow        Flow          1 Compressor          not   Tank lorry cannot be        LPG       pumps          and     Preventive
                                             working                    decanted                    compressors              are     maintenance schedule
                                                                                                    most                  critical   will be followed
                                                                                                    equipment        of    plant
                                                                                                    therefore              there
                                                                                                    should be preventive
                                                                                                    maintenance              and
                                                                                                    daily     inspection       of
                                                                                                    equipment
                                            2 Power failure             Same as explained           The D.G. set should              D.G. sets      shall be
                                                                        above                       be regularly tested for          operated
                                                                                                    fool proof operation.
                                                                                                    Compressor can be
                                                                                                    started                 after
                                                                                                    transferring plant load
                                                                                                    from     state    grid     to
                                                                                                    D.G. set
Less           Less/Low       Pressure      1 Compressor          not   Desired results not         The                   proper     Preventive
               Pressure                      working properly           obtained     pertaining     maintenance                of    maintenance schedules
                                                                        to    decantation    of     compressor desired               will be formulated and
                                                                                                                                                               Page 44
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                            HAZOP REPORT
Recommendations
More           More/High      Temperature   1 Cylinder   jacket     of   The           compressor         There       should    be    Cooling                water
               Temperature                   compressor not being        heats      up     and     it     regular      check    for   interlocking        pressure
                                             cooled properly             fails/trips                      proper cooling water        switch will be provided
                                                                                                          line and its operation
                                            2 The discharge line of      The pipeline/ loading            The       fire   fighting   Fire                 fighting
                                             compressor heats up         arms may fail due to             arrangements          be    arrangement         will   be
                                             due to external fire or     heat radiation hence             inspected            and    checked        at    regular
                                             flame                       asphyxiation                     checked at regular          intervals
                                                                         problems        and Fire         intervals
                                                                         hazards
Other than     Corrosion      Corrosion     1 Pure   LPG      is   not   Pipeline           failure       Periodic         internal   Periodic             internal
                                             corrosive             but   hence         release    of      inspection            of    inspection will be done
                                             mercaptan added to it       LPG      vapour         may      pipeline should be          & thickness of pipeline
                                             may corrode pipeline        occur                            done to detect any          will be measured ultra
                                                                                                          corrosion                   sonically
                                                                                                                                                                      Page 45
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                             HAZOP REPORT
Recommendations
                                            2 Power failure               Same as explained              The D.G. set should         D.G.   set     shall   be
                                                                          above                          be regularly tested         operated
                                                                                                         for       fool      proof
                                                                                                         operation.
Less           Less/Low      Pressure       1 Compressor            not   Desired results not            The              proper     Preventive
               Pressure                       working properly            obtained       pertaining      maintenance            of   maintenance schedules
                                                                          to    decantation      of      compressor desired          shall be formulated and
                                                                          Evacuation       vessels                                   followed
                                                                          but no fire hazards
More           More/High     Temperature    1 Cylinder     jacket    of   The        compressor          There      should     be    Cooling            water
               Temperature                    compressor not being        heats     up     and    it     regular     check     for   interlocking   pressure
                                                                                                         proper cooling water
                                                                                                                                                                 Page 46
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                             HAZOP REPORT
Recommendations
cooled properly fails/trips line and its operation switch will be provided
                                            2 The discharge line of         The pipeline may fail            The    fire      fighting   Fire                fighting
                                              compressor heats up           due to heat radiation            arrangements          be    arrangement        will     be
                                              due to external fire or       hence      asphyxiation          inspected           and     checked       at    regular
                                              flame                         problems         &      fire     checked at regular          intervals
                                                                            hazards                          intervals
Other than     Corrosion     Corrosion      1 Pure      LPG      is   not   Pipeline             failure     Periodic      internal      Periodic            internal
                                              corrosive               but   hence         release    of      inspection            of    inspection will be done
                                              mercaptan added to it         LPG      vapour         may      pipeline should be          & thickness of pipeline
                                              may corrode pipeline          occur                            done to detect any          is      measured          ultra
                                                                                                             corrosion                   sonically to detect any
                                                                                                                                         corrosion
                                                                                                                                                                           Page 47
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                  HAZOP REPORT
Recommendations
No              No relief valve     Isolation of a relief valve   Possibility   of    over     Interlocks should be        Double relief valves will
                in use              for     maintenance      or   pressurization of the        provided so that in         be provided on the tanks
                                    testing.                      vessels                      case a relief valve is
                                                                                               isolated              for
                                    No provision of multiple
                                                                                               maintenance            or
                                    relief valves.
                                                                                               testing       remaining
Not             Vent pipe fitted    - Improper height of the      In case of ignition of       -   Maintained        the   Will be followed
                with relief         vent outlets                  discharging gas the          condition      of    vent
                valves not of                                     jet fire may become          pipes provided with
                                    - Vent pipes bent down
                proper design                                     the source of heat to        loose      fitting   rain
                                    wards
                                                                  the same tank or to          caps
                                                                                                                                                          Page 48
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                HAZOP REPORT
Recommendations
No               No Flow        Flow          1 LPG pump not working         Filling operation at          Rectify the pump          Self explanatory
                                                                             carousel will stop
                                              2 LPG discharged line          Fire and explosion            Stop     pump       and   Necessary        hydrostatic
                                                leakage                      hazard                        repair       leakage.     tests for pipeline will be
                                                                                                           Patrolling desired        done. Regular patrolling
                                                                                                                                     will be taken up
                                              3 Filling     gun       hose   Fire and explosion            Proper maintenance        LPG      hoses     will   be
                                                rupture                      hazard                        of hoses desired          subjected                 to
                                                                                                                                     hydrostatic, pneumatic
                                                                                                                                     and electrical continuity
                                                                                                                                     tests once in 4 months
                                              4 Filling gun detached         LPG vapour release            Proper     functioning    Self explanatory
                                                from cylinder                                              and maintenance of
                                                                                                           carousel desired
Less             Less Flow      Flow          1 Some        leakage     in   If    leakage persists        Regular patrolling of     Regular patrolling will
                                                pipeline                     for     longer      time      pipeline desired          be taken up
                                                                             fire/explosion
                                                                             hazards may occur
                                              2 LPG pump not running         The filling time for          The                pump   Proper    functioning     of
                                                at its rated capacity        cylinders            will     maintenance desired       pumps will be ensured
                                                                             increase                                                through     maintenance
                                                                                                                                     schedules formulated
Less             Less/Low       Temperature   1 Very       low    ambient    None. Since boiling           None                      Self explanatory
                 Temperature                    temperature                  point of LPG is -9
                                                                             deg. C and freezing
                                                                             conditions    in    LPG
                                                                             pipelines    will    not
                                                                                                                                                                    Page 49
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                  HAZOP REPORT
Recommendations
                                                                                occur         because
                                                                                lowest     temperature
                                                                                at Energon does not
                                                                                reach -9 deg. C
Less             Less/Low       Pressure      1 LPG pump not running            Less flow resulting in         Proper     maintenance        Maintenance schedules
                 Pressure                       at its rated capacity           slow rate of LPG               of pump desired               of     pumps     will         be
                                                                                filling at carousel                                          followed
More             More/High      Temperature   1 Some fire in the vicinity       Pipeline may rupture           Ensure              proper    Fire                 fighting
                 Temperature                    causing               higher    causing     fire      and      functioning       of   fire   arrangements         will     be
                                                pressure        on        LPG   explosion                      fighting systems              provided        as           per
                                                pump discharge line                                                                          statutory requirements
                                                connected to carousel
Other than       Corrosion      Corrosion     1 Pure      LPG        is   not   Pipeline           failure     Periodic          internal    Periodic             internal
                                                corrosive                 but   hence      release     of      inspection of major           inspection is done &
                                                mercaptan added to it           LPG      vapour       may      piping      and        LPG    thickness of pipeline will
                                                may corrode pipeline            occur                          bullets after each five       be      measured            ultra
                                                or bullet                                                      years should be done          sonically to detect any
                                                                                                               to       detect        any    corrosion
                                                                                                               corrosion
As well as Flow of foreign Contamination 1 Water draining not No hazardous Water draining for Water draining will be
                                                                                                                                                                                 Page 50
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                               HAZOP REPORT
Recommendations
                 material along                  done      in     MSV     on   consequence      only     each    new       parcel   done as per established
                 with LPG                        regular        basis    and   water will go along       received desired in        procedure
                                                 water is pumped along         with LPG in cylinders     MSV
                                                 LPG and it will go to
                                                 cylinders
Reverse/Misdi     Reverse/        Flow          1 Not possible due to          None                      None                       Self explanatory
rected            Misdirected                    presence of NRV (non
                  Flow                           return         valve)    at
                                                 discharge        of     LPG
                                                 pump and at carousel
                                                                                                                                                              Page 51
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                        HAZOP REPORT
Recommendations
No NA
Less NA
More NA
Other than NA
As well as NA
Reverse/Misdirect   NA
ed
Other               Filled cylinder   Cylinder received     Fire and Dispersion     Return the cylinder    Will be followed
                    received          without      proper   of LPG                  for proper degassing
                                      evacuation
                                                                                                                                    Page 52
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                          HAZOP REPORT
Recommendations
Less            Less/Low            Pressure      Empty cylinder          Process disturbance     Check the water filling
                Pressure                          Leaky cylinder                                  of cylinder.
                                                  Testing pump failure                            Scrap the leaky
                                                                                                  cylinder.
                                                                                                  Check testing pump
                                                                                                  regularly.
                                                                                                  Calibrate pressure
                                                                                                  gauge regularly.
More            More/High           Pressure      Breaking of Pipeline.   Spillage                Test periodically         Over pressure safety
                Pressure                          Cylinder Rupture.                                                         device shall be installed
Other than NA
As well as NA
Other           Cylinder received                 Failure of cylinder                             Return the cylinder for   Will be followed
                without degassed                                                                  proper degassing.
                                                                                                                                                        Page 53
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                   HAZOP REPORT
Recommendations
No              No Flow          Flow          No paint            Process disturbance     Paint gun nozzle        Pressure gauge and SRV
                                               No air pressure                             properly checked.       shall be installed
                                               Paint gun nozzle                            The air pressure
                                               chocked                                     properly checked.
                                                                                           Pressure gauge and
                                                                                           SRV calibrated and
                                                                                           checked.
Less            Less Flow                      Improper painting   Process disturbance     Paint gun nozzle
                                               Nozzle chocked                              properly checked.
                                               Less air flow                               The air pressure
                                                                                           properly checked.
More            More/High        Flow          More painting       Wastage of paint        Air pressure properly   Over pressure safety
                Flow                                               Breakage of air gun     checked.                device will be installed
                                                                   pipe                    Pressure gauge
                                                                                           properly checked.
Other than NA
As well as NA
Reverse/Misdi   NA
rected
                                                                                                                                              Page 54
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                          HAZOP REPORT
Recommendations
                                          2 Power failure              Same as explained            The D.G. set should             D.G.   sets      will   be
                                                                       above                        be regularly tested for         operated
                                                                                                    fool proof operation.
                                                                                                    Compressor can be
                                                                                                    started                after
                                                                                                    transferring plant load
                                                                                                    from    state    grid     to
                                                                                                    D.G. set
Less          Less/Low      Pressure      1 Compressor          not    Bottling     operation      The               proper         Preventive
              Pressure                     working properly            hindrance                   maintenance              of      maintenance schedules
                                                                                                   compressor desired               will be formulated and
                                                                                                                                    being followed
More          More/High     Pressure        Compressor                Potential             for    Make sure the vendor Self explanatory
              Pressure                      deadheaded                 equipment       damage      package                  has
                                                                                                   appropriate
                                                                                                                                                                 Page 55
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                      HAZOP REPORT
Recommendations
More          More/High     Temperature   The discharge line of     Potential          for    The      fire     fighting        Fire             fighting
              Temperature                 compressor heats up       equipment    damage       arrangements           be         arrangement          are
                                          due to external fire or   and possible failure      inspected             and         checked     at   regular
                                          flame                                               checked at regular                intervals
                                                                                              intervals
Other than NA
                                                                                                                                                            Page 56
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                                HAZOP REPORT
Recommendations
                                          Field                    circuit
                                          open/reverse
                                          No      fuel      (HSD)      in
                                          reserve tank of DG set
Ring/Gear problem
                                          Coupling of generator
                                          is detached
Less         Less/Low       Voltage       Unequal distribution of            Operational problem          Sustained      routine    Preventive
             Voltage                      fuel (HSD) in all the                                           maintenance to be         maintenance schedules
                                                                             Due to less voltage
                                          fuel injector                                                   followed                  shall be formulated and
                                                                             line, current will be
                                                                                                                                    being followed
                                          Partial clogging of the            high and if the line
                                          fuel (HSD) filter                  current is high than
                                                                             the     rated   current-
                                          Due        to       defective
                                                                             Insulation failure may
                                          governor
                                                                             occur      resulting   in
increased
More         More Voltage   Voltage        RPM throttle/governor             Load of power will be        High voltage relay to Self explanatory
                                           failure                           affected                     be provided
                                                                                                                                                              Page 57
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT     HAZOP REPORT
Recommendations
                                                 Temperature will be
                                                 high
Other than NA
                                                                                                                      Page 58
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                         HAZOP REPORT
Recommendations
Less            Less/Low            Pressure     Empty cylinder          Process disturbance       Check testing pump
                Pressure                         Testing pump failure                              regularly.
                                                                                                   Calibrate pressure
                                                                                                   gauge regularly.
More            More/High           Pressure     Breaking of Pipeline.   Damage to equipment       Test periodically         Over pressure safety
                Pressure                                                                                                     device shall be installed
Other than NA
As well as NA
Other           Cylinder received                Failure of cylinder     LPG leakage               Return the cylinder for   Will be followed
                without degassed                                                                   proper degassing.
                                                                                                                                                         Page 59
ENERGON PETRO PRODUCTS PVT LTD – LPG BOTTLING PLANT                       HAZOP REPORT
2.6   RECOMMENDATIONS
      Based on worksheets of Energon Petro Products Pvt. Ltd, LPG Plant, recommendations
      to be followed during the construction and Operation Phase are:
      1. All the operations should be carried out under the supervision of designated
         competent supervisor and carryout NDT as per schedule for weld joints at nozzle and
         pipe along with valve examination and replace immediately if found any
         inconformity.
      2. Ensuring timely Statutory testing of MSV as per SMPV (The Static and Mobile
         Pressure Vessels) rule.
      3. Ensuring replacement of fasteners, studs, gaskets etc. during hydro testing of vessels.
      4. Start of smooth LPG flow during unloading should be ascertained.
      5. Inspection of pipes for internal & external corrosion shall be carried out with special
         attention.
      6. During bottling operation one personnel should be present at each stage of operation.
      7. Work permit system to be strictly followed.
      8. Electrical fitting/earthing should be checked regularly.
      9. Sprinkler system, tripping of compressors and LPG pumps, ROVs, LPG supply and
         return lines, actuation of deluge valve should be checked regularly to ensure their
         desired operation at the time of actual emergency and this should be followed strictly.
      10. Adequate training to be provided to Operators at the time of evacuation of the unit.
Page 60