Job Hazard Analysis
Project Name: TOWER RETROFITTING Start Date: Finish Date: __ __
SITE ID SITE ADDRESS REGIO AREA LONGITUDE LATITUDE TECH NAME
N
Task to be accomplished:
Tower Retrofitting
Steps To Take To Complete Hazards Required Actions To Eliminate Or ON-SITE
Task Control The Hazard Compliance
Check
Step 1.
Delivery, sorting and Weather Condition
segregation of tower Heat stress due to Allocate plenty of drinking water
retrofitting materials. direct heat from Educate workers how to avoid heat
sunlight stress/ stroke, their symptoms and
emergency procedures
Schedule workers rest periods.
Heavy Rain Apply stop work
Biological Hazard Use insect repellant (lotion, sprays)
Request owner to leash their dogs
Wear protective gears (boots for
snake, long sleeves with face/ neck
covers for mosquitoes)
Establish safe distance from the
dog/snake and do not attempt to
catch it.
Pinch Point Wear prescribe PPE
Plan work to avoid pinch point.
Use right tools.
Struck by co- Allocate sufficient space between
workers workers
Body Pain/ Back Lift with your legs and not at your
Injury back.
Step 2.
Site preparation, setting up Tools/ equipment Pre-use inspection of tools/equipment
of hoist/pulley and ropes Failure. prior to use.
Page 1 of 5
PUBLIC
For Public Use
Falling Hazard Wear fall protection at all times.
FBH and lanyard; correct wearing.
Maintain 3-point contact.
Hands free when ascending and
descending ladders.
100% tie-off
Stable anchor point
Barricade-off to prevent access
Do not drop objects
Don’t stand/walk under suspended
load.
Follow SWP
Wear prescribe PPE.
Belayer to guide and assist in site
setup.
Barricade –off to prevent access.
Rescue procedures.
Pinch Point Plan work to avoid pinch point.
Wear hand gloves.
Use right tools.
Body Pain/ Back Lift with your legs and not at your
Injury back.
Workers scheduling.
Rest Break.
Struck by co- Allocate sufficient space between co-
workers workers.
Slipping/ Tripping Remove slipping/tripping hazards
Barricade-off to prevent access.
Sharp Objects Cut away from body.
Use correct gloves.
Step 3.
Hoisting and fitting-up of Tools/ Equipment Pre-use inspection of tools/
retrofit members, tools and failure equipment prior to use.
equipment.
Falling Hazard Wear fall protection at all times.
FBH and lanyard; correct wearing.
Maintain 3-point contact.
Hands free when ascending and
descending ladders.
Page 2 of 5
PUBLIC
For Public Use
100% Tie-off
Stable anchor point.
Barricade-off to prevent access.
Do not drop objects.
Don’t stand/walk under suspended
load.
Follow SWP.
Belayer to guide and assist site setup.
Rescue procedure.
Pinch Point Plan work to avoid pinch point.
Wear hand gloves.
Use right tools.
Body Pain/ Back Lift with your legs and not at your
Injury back.
Rest Break
Workers Scheduling
Struck by co- Allocate sufficient space between co-
workers workers
Protruding Objects Remove protruding objects.
Step 4.
Bolt Tightening Tools/ Equipment Pre-use inspection of tools/equipment
Failure prior to use.
Falling Hazard Wear fall protection at all times.
FBH and lanyard; correct wearing.
Maintain 3-point contact.
Hands free when ascending and
descending ladders.
100% Tie-off
Stable anchor point.
Barricade off to prevent access.
Do not drop objects
Don’t walk/stand under suspended
load.
Belayer to guide and assist site setup.
Rescue procedures.
Follow SWP.
Pinch Point Plan work to avoid pinch point.
Use right tools.
Wear hand gloves.
Page 3 of 5
PUBLIC
For Public Use
Sharp Objects Cut away from the body.
Remove /cover sharp edges
Use correct gloves
Body Pain Schedule workers rest periods.
Protruding Objects Remove protruding objects.
Step 5.
Lowering down of Tools/equipment Pre-use inspection of tools/
equipment/ materials. Failure equipment prior to use.
Falling Hazard Wear fall protection at all times.
FBH and lanyard; correct wearing.
Maintain 3-point contact.
Hands free when ascending and
descending.
100% Tie-off
Stable anchor point.
Barricade-off to prevent access.
Do not drop objects.
Don’t walk/stand under suspended
load.
Belayer to guide and assist site setup.
Rescue procedures.
Follow SWP.
Back Pain/ Back Lift with your legs and not at your
Injury back.
Schedule workers rest period.
Sharp Objects Remove/cover sharp edges.
Cut away from body.
Use correct gloves.
Step 6.
Site clearing, cleaning up and Slipping/Tripping Housekeeping must be done during
demobilization before and after work activities.
Protruding Objects Remove protruding objects.
Sharp Objects Remove/cover sharp edges
Cut away from body
Use correct gloves
Page 4 of 5
PUBLIC
For Public Use
This JHA must be reviewed with all workers involved prior to starting any work.
Work Supervisor: ________________________
Workers:
Page 5 of 5
PUBLIC
For Public Use