Progress Measurement Installation Hvac PB Switchgear Room

This document outlines a plan for installing HVAC equipment in a power switchgear room over 28 activities from January 4th to February 28th. It provides details of each activity including duration, man hours, and weekly progress targets shown as percentages. A chart shows the planned progress curve versus actual progress to date, which is currently 0% completed for all activities. Limitations noted are that the work is being done by a team of 3 people but one person cannot attend.

Uploaded by

Aditya Suardi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views4 pages

Progress Measurement Installation Hvac PB Switchgear Room

This document outlines a plan for installing HVAC equipment in a power switchgear room over 28 activities from January 4th to February 28th. It provides details of each activity including duration, man hours, and weekly progress targets shown as percentages. A chart shows the planned progress curve versus actual progress to date, which is currently 0% completed for all activities. Limitations noted are that the work is being done by a team of 3 people but one person cannot attend.

Uploaded by

Aditya Suardi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

Cum Plan 2.5% 7.5% 12.5% 17.5% 22.5% 27.5% 32.5% 37.5% 42.5% 47.5% 52.5% 57.5% 62.

62.5% 67.5% 72.5% 77.5% 82.5% 87.5% 92.5% 97.5% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
PROGRESS MEASUREMENT INSTALLATION HVAC PB Switchgear Room Cum Actual - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PO No. Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Date 4-Jan 5-Jan 6-Jan 7-Jan 8-Jan 9-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan
Total
No Description MP MP Qty Unit Duration Total Man Weight Week 1 Week 2 Week 3 Week 4
(hour) Hour Hours (%) % Complete
I Instalation Unit Baru
1 Transfer AHU 1,2 dan Panel dari Barge ke PB 4 4 1 lot 8 8 32 2.87%
2 Pembongkaran wooden box AHU 1,2 2 2 2 unit 2 4 8 0.72%
3 Pembongkaran wooden box Panel 2 2 2 unit 1 2 4 0.36%
4 Knock Down AHU 4 4 4 unit 2 8 32 2.87%
5 Transfer AHU dari PB Deck ke Roof Switchgear 4 4 2 unit 8 16 64 5.73%
6 Transfer Panel unit dari PB Deck ke Roof Switchgear 4 4 2 unit 2 4 16 1.43%
7 Re-Assy AHU 4 4 4 unit 8 32 128 11.47%
8 Install panel baru 2 2 2 unit 4 8 16 1.43%
9 Transfer PF unit 1,2 & ducting dari Barge ke PB 4 4 1 lot 8 8 32 2.87%
10 Bongkar wooden box PF unit 1,2 & ducting 2 2 2 unit 4 8 16 1.43%
11 Knock Down PF 2 2 1 unit 4 4 8 0.72%
12 Transfer PF dan ducting dari PB Deck ke Roof Switchgear 4 4 1 unit 4 4 16 1.43%
13 Re-Assy PF 2 2 1 unit 8 8 16 1.43%
14 Install ducting PF 4 4 1 lot 16 16 64 5.73%
15 Transfer Outdoor unit 1,2 dari Barge ke PB 4 4 1 lot 8 8 32 2.87%
16 Bongkar wooden box outdoor unit 1,2 2 2 4 unit 2 8 16 1.43%
17 Knock Down Outdoor unit 1,2 4 4 4 unit 4 16 64 5.73%
18 Transfer outdoor unit 1,2 dari Deck ke Roof Switchgear 4 4 2 unit 4 8 32 2.87%
19 Re-Assy Out door unit 1,2 4 4 2 unit 8 16 64 5.73%
20 Pengukuran kebutuhan instalasi pipa dan support pipa refrigerant (isometric) 2 2 4 unit 4 16 32 2.87%
21 Pabrikasi support untuk kabel tray 2 2 2 lot 4 8 16 1.43%
22 Install kabel tray 2 2 2 lot 4 8 16 1.43%
23 Pulling cable (power & accessories) Outdoor, Indoor, PF 2 2 2 lot 8 16 32 2.87%
24 Test insulation resistan and continuity motor, compressor 2 2 2 lot 4 8 16 1.43%
25 Glanding, Splicing, Terminasi, Grounding, Bonding, Tagging 2 2 2 lot 8 16 32 2.87%
26 Instalasi pipa drain 2 2 1 lot 8 8 16 1.43%
27 Instalasi support Pipa reffrigerant 2 2 4 unit 2 8 16 1.43%
28 Instalasi Pipa reffrigerant 2 2 4 unit 8 32 64 5.73%
29 Leak Test (test kebocoran system) and monitoring 2 2 4 unit 8 32 64 5.73%
30 Vaccum dan isi freon R 417A (monitoring) 2 2 4 unit 4 16 32 2.87%
II Commissioning dan Test Online
31 Persiapan test run unit 4 2 4 unit 1 4 8 0.72%
32 Internal test panel (dry test) 2 2 2 unit 2 4 8 0.72%
33 De isolasi energi 1 & 2 2 2 2 unit 0.5 1 2 0.18%
34 Test arah putaran dari motor CU dan Blower AHU unit 1 & 2 dan PF 2 2 2 unit 2 4 8 0.72%
35 De isolasi energi 3 & 4 2 2 2 unit 0.5 1 2 0.18%
36 Test arah putaran dari motor CU dan Blower AHU unit 3 & 4 dan PF 2 2 2 unit 2 4 8 0.72%
37 Preparation start up unit 1 & 2 + PF (check power, setting HP - LP, Valve, OL) 2 2 2 unit 2 4 8 0.72%
38 Start up HVAC unit 1 & 2 dan Monitoring 2 2 1 lot 1 1 2 0.18%
39 Record data running unit 1 & 2 dan monitoring 2 2 1 unit 16 16 32 2.87%
40 Preparation start up unit 3 & 4 + PF (check power, setting HP - LP, Valve, OL) 2 2 2 unit 2 4 8 0.72%
41 Start up HVAC unit 3 & 4 dan Monitoring dan Switch Over 2 2 1 lot 1 1 2 0.18%
42 Record data running unit 3 & 4 dan monitoring 2 2 1 unit 16 16 32 2.87%
Sub Total 213 414 1116 100.00%

Activity to day:
1
2
3
4
5

Kendala jika ada:


1 Pekerjaan dilakukan oleh man power 3 ORANG, ( 1 orang tdk bisa berangkat )
CURVA PROGRESS MEASUREMEN
Start: 4 Jan - Feb, 2014

100%

95%

90%

85%

80%

75%

70%

65%

60%

55%

50%

45%

40%

35%

30%

25%

20%

15%

10%

5%

0%
1 2 3 4 5 6 7 8 9 10 11
MEASUREMENT PROGRESS INSTALATION HVAC PB SWITCHGEAR "PLAN vs

Cum Plan
Cum Actual

9 10 11 12 13 14 15 16 17 18 19 20
GEAR "PLAN vs ACTUAL"

19 20 21 22 23 24 25 26 27 28