0% found this document useful (0 votes)
35 views1 page

WBS of The Project

The document outlines the work breakdown structure for constructing a G+2 building, breaking it down into site preparation and then floors including the plinth portion, first floor, second floor, and top floor which details the various construction activities involved in each.

Uploaded by

Abi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views1 page

WBS of The Project

The document outlines the work breakdown structure for constructing a G+2 building, breaking it down into site preparation and then floors including the plinth portion, first floor, second floor, and top floor which details the various construction activities involved in each.

Uploaded by

Abi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

WBS of the Project:

G+2 Building Construction

Site Preparation

Plinth Portion First Floor Second Floor Top Floor

- Termite - Column & - Slab - Slab


treatment Slab
- Flooring - Flooring
and water
- Flooring - Parapet wall
treatment - Brick work
- Brick Work - Overhead
- Beam - Plaster
work - Plaster tank
- Kitchen &
Chimney work