EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE
Activity ID Activity Name Original Budgeted Start Finish Units %
Duration Labor Units Complete
EJN-00625 Installation of Manual Pull Valves
EJN-0062 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%
Sadara C
Chemical Company 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%
PCA Plastics
Plasti 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%
Gulf Asia Contracting Company 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%
Bidding & Contract Award 17d 170h 30-Nov-20 07:00 AM A 07-Dec-21 06:00 PM A 100%
A1000 Contract Award Notification 1d 10h 30-Nov-20 07:00 AM A 30-Nov-20 06:00 PM A 100%
A1010 Receipt of Purchase Order 1d 10h 30-Nov-20 07:00 AM A 30-Nov-20 06:00 PM A 100%
A1020 GIH Training 10d 100h 07-Dec-21 07:00 AM A 07-Dec-21 06:00 PM A 100%
A1030 Kick off Meeting 1d 10h 15-Feb-21 07:00 AM A 15-Feb-21 06:00 PM A 100%
A1040 Document Submission 4d 40h 16-Feb-21 07:00 AM A 20-Feb-21 06:00 PM A 100%
Project M
Milestones 388d 0h 30-Nov-20 07:00 AM A 01-May-22 09:00 AM 0%
A1050 Project Start 0d 0h 30-Nov-20 07:00 AM A 0%
A1060 Project Finish 0d 0h 01-May-22 09:00 AM 0%
Procurement Works
Procurem 282d 215h 20-Feb-21 07:00 AM A 28-Dec-21 05:00 PM A 100%
A1070 Piping Materials Procurement 60d 60h 20-Feb-21 07:00 AM A 29-Apr-21 05:00 PM A 100%
A1080 Support Materials Procurement 60d 60h 20-Feb-21 07:00 AM A 29-Apr-21 05:00 PM A 100%
A1090 Sadara Free Issue Materials (Manual Pull Valves) 15d 15h 28-Dec-21 07:00 AM A 28-Dec-21 05:00 PM A 100%
A1100 Third Party PO Issue. 80d 80h 20-Feb-21 07:00 AM A 23-May-21 06:00 PM A 100%
Shop Works
Wo 199d 1420h 01-May-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
Piping 199d 880h 01-May-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1110 Piping Materials Receiving Inspection 1d 40h 01-May-21 07:00 AM A 08-May-21 06:00 PM A 100%
A1120 Pipe Marking // Cutting // Fit up // Threading 15d 600h 01-Dec-21 07:00 AM A 08-Dec-21 06:00 PM A 100%
A1150 Pipe Spools Painting 4d 200h 08-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1160 Inspection and Release 1d 40h 26-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
Support 16d 540h 01-May-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1170 Support Materials Receiving Inspection 1d 40h 01-May-21 07:00 AM A 01-May-21 06:00 PM A 100%
A1180 Support Fabrication as per Site Condition 10d 400h 04-Dec-21 07:00 AM A 14-Dec-21 06:00 PM A 100%
A1190 Support Galvanizing 4d 80h 14-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1200 Inspection and Release 1d 20h 26-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
Site Works
Work 288d 9430h 08-Dec-21 07:00 AM A 26-Apr-22 09:00 AM 53%
Scaffolding Works - PCA Area
Scaffold 54d 1540h 08-Dec-21 07:00 AM A 22-Dec-21 06:00 PM A 100%
A1210 Scaffolding Materials Mobilization 4d 40h 08-Dec-21 07:00 AM A 11-Dec-21 06:00 PM A 100%
A1220 Scaffolding Erection as required. 50d 1500h 12-Dec-21 07:00 AM A 22-Dec-21 06:00 PM A 100%
Piping A
Activity - PCA Area 77d 1580h 26-Dec-21 07:00 AM A 24-Mar-22 05:00 PM 78.48%
A1230 Pipe Supports Installation as per Site Condition. 10d 400h 26-Dec-21 07:00 AM A 05-Jan-22 06:00 PM A 100%
A1240 New Piping Spools Erection as per Site Condition. 15d 600h 26-Dec-21 07:00 AM A 11-Jan-22 06:00 PM A 100%
A1250 New Manual Pull Valve Installation. 15d 240h 26-Dec-21 07:00 AM A 11-Jan-22 06:00 PM A 100%
A1260 Tie-In Connections. 6d 240h 13-Mar-22 07:00 AM 19-Mar-22 06:00 PM 0%
A1270 Field Leak Testing & Commissioning. 4d 80h 20-Mar-22 07:00 AM 23-Mar-22 06:00 PM 0%
A1280 Inspection and Release. 1d 20h 24-Mar-22 07:00 AM 24-Mar-22 05:00 PM 0%
Scaffolding Works - Train 01
Scaffold 24d 1540h 02-Jan-22 07:00 AM A 14-Mar-22 06:00 PM 90.26%
A1460 Scaffolding Materials Mobilization 4d 40h 05-Jan-22 07:00 AM A 05-Jan-22 07:00 AM A 100%
A1470 Scaffolding Erection as required. 20d 1500h 02-Jan-22 07:00 AM A 14-Mar-22 06:00 PM 90%
Piping A
Activity - Train -01 Area 67d 1180h 10-Jan-22 07:00 AM A 29-Mar-22 09:00 AM 70.17%
A1290 Pipe Supports Installation as per Site Condition. 8d 320h 10-Jan-22 07:00 AM A 13-Mar-22 04:00 PM 90%
A1300 New Piping Spools Erection as per Site Condition. 12d 480h 10-Jan-22 07:00 AM A 14-Mar-22 09:00 AM 90%
A1310 New Manual Pull Valve Installation. 12d 120h 10-Jan-22 07:00 AM A 14-Mar-22 09:00 AM 90%
A1320 Tie-In Connections. 4d 160h 19-Mar-22 09:00 AM* 23-Mar-22 09:00 AM 0%
A1330 Field Leak Testing & Commissioning. 4d 80h 23-Mar-22 09:00 AM 28-Mar-22 09:00 AM 0%
A1340 Inspection and Release. 1d 20h 28-Mar-22 09:00 AM 29-Mar-22 09:00 AM 0%
Scaffolding Works - Train 02
Scaffold 24d 1540h 19-Mar-22 09:00 AM 16-Apr-22 09:00 AM 0%
A1480 Scaffolding Materials Mobilization 4d 40h 19-Mar-22 09:00 AM* 23-Mar-22 09:00 AM 0%
A1490 Scaffolding Erection as required. 20d 1500h 23-Mar-22 09:00 AM 16-Apr-22 09:00 AM 0%
Piping A
Activity - Train -02 Area 20d 1100h 31-Mar-22 09:00 AM 24-Apr-22 09:00 AM 0%
A1350 Pipe Supports Installation as per Site Condition. 7d 280h 31-Mar-22 09:00 AM 09-Apr-22 09:00 AM 0%
A1360 New Piping Spools Erection as per Site Condition. 11d 440h 31-Mar-22 09:00 AM 13-Apr-22 09:00 AM 0%
Actual Level of Effort R Page 1 of 4 TASK filter: All Activities
Actual Work C © Oracle Corporation
EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE
2021 2022
e Feb
Oct Nov Dec Jan
07-Dec-21 06:00 PM A, Bidding & Contract Award
GIH Training
28-Dec-21 05:00 PM A, Procurement Works
Sadara Free Issue Materials (Manual Pull Valves
26-Dec-21 06:00 PM A, Shop Works
26-Dec-21 06:00 PM A, Piping
Pipe Marking // Cutting // Fit up // Threading
Pipe Spools Painting
Inspection and Release
26-Dec-21 06:00 PM A, Support
Support Fabrication as per Site Condition
Support Galvanizing
Inspection and Release
22-Dec-21 06:00 PM A, Scaffolding Works - PCA Area
Scaffolding Materials Mobilization
Scaffolding Erection as required.
Pipe Supports Installation as per Site
New Piping Spools Erection a
New Manual Pull Valve Install
Scaffolding Materials Mobilization
Actual Level of Effort R Page 2 of 4 TASK filter: All Activities
Actual Work C © Oracle Corporation
EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE
Activity ID Activity Name Original Budgeted Start Finish Units %
Duration Labor Units Complete
A1370 New Manual Pull Valve Installation. 11d 120h 31-Mar-22 09:00 AM 13-Apr-22 09:00 AM 0%
A1380 Tie-In Connections. 4d 160h 13-Apr-22 09:00 AM 18-Apr-22 09:00 AM 0%
A1390 Field Leak Testing & Commissioning. 4d 80h 18-Apr-22 09:00 AM 23-Apr-22 09:00 AM 0%
A1400 Inspection and Release. 1d 20h 23-Apr-22 09:00 AM 24-Apr-22 09:00 AM 0%
Scaffolding Works - Train 04
Scaffold 11d 410h 03-Apr-22 09:00 AM 16-Apr-22 09:00 AM 0%
A1560 Scaffolding Materials Mobilization 1d 10h 03-Apr-22 09:00 AM 04-Apr-22 09:00 AM 0%
A1570 Scaffolding Erection as required. 10d 400h 04-Apr-22 09:00 AM 16-Apr-22 09:00 AM 0%
Piping A
Activity - Train -04 9d 540h 16-Apr-22 09:00 AM 26-Apr-22 09:00 AM 0%
A1500 Pipe Supports Installation as per Site Condition. 4d 160h 16-Apr-22 09:00 AM 20-Apr-22 09:00 AM 0%
A1510 New Piping Spools Erection as per Site Condition. 4d 160h 16-Apr-22 09:00 AM 20-Apr-22 09:00 AM 0%
A1520 New Manual Pull Valve Installation. 4d 80h 16-Apr-22 09:00 AM 20-Apr-22 09:00 AM 0%
A1530 Tie-In Connections. 2d 80h 20-Apr-22 09:00 AM 23-Apr-22 09:00 AM 0%
A1540 Field Leak Testing & Commissioning. 2d 40h 23-Apr-22 09:00 AM 25-Apr-22 09:00 AM 0%
A1550 Inspection and Release. 1d 20h 25-Apr-22 09:00 AM 26-Apr-22 09:00 AM 0%
Walkdown and Punch Clearance
Walkdow 4d 160h 26-Apr-22 09:00 AM 01-May-22 09:00 AM 0%
A1410 MC Walkdown and Punch Clearance 2d 80h 26-Apr-22 09:00 AM 28-Apr-22 09:00 AM 0%
A1420 PSSR Walkdown and Punch Clearance 2d 80h 28-Apr-22 09:00 AM 01-May-22 09:00 AM 0%
Hand Over
Ove 9d 180h 01-May-22 09:00 AM 11-May-22 09:00 AM 0%
A1430 Document Submission 7d 140h 01-May-22 09:00 AM 09-May-22 09:00 AM 0%
A1440 Construction Completion. 1d 20h 09-May-22 09:00 AM 10-May-22 09:00 AM 0%
A1450 Hand Over 1d 20h 10-May-22 09:00 AM 11-May-22 09:00 AM 0%
Actual Level of Effort R Page 3 of 4 TASK filter: All Activities
Actual Work C © Oracle Corporation
EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE
2021 2022
e Feb
Oct Nov Dec Jan
Actual Level of Effort R Page 4 of 4 TASK filter: All Activities
Actual Work C © Oracle Corporation