EJN-00625 Installation of Manual Pull Valves in Deluge Systems For SOLPE

This document outlines the installation of manual pull valves in deluge systems for SOLPE. The project involves bidding, procurement, shop works, and site works activities across multiple areas including PCA, Train 01 and Train 02 areas from November 2020 through April 2022. Key activities include materials procurement, fabrication, scaffolding erection, pipe installation and tie-ins, testing and commissioning. The project is currently 58.77% complete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
105 views4 pages

EJN-00625 Installation of Manual Pull Valves in Deluge Systems For SOLPE

This document outlines the installation of manual pull valves in deluge systems for SOLPE. The project involves bidding, procurement, shop works, and site works activities across multiple areas including PCA, Train 01 and Train 02 areas from November 2020 through April 2022. Key activities include materials procurement, fabrication, scaffolding erection, pipe installation and tie-ins, testing and commissioning. The project is currently 58.77% complete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE

Activity ID Activity Name Original Budgeted Start Finish Units %


Duration Labor Units Complete

EJN-00625 Installation of Manual Pull Valves


EJN-0062 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%

Sadara C
Chemical Company 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%

PCA Plastics
Plasti 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%
Gulf Asia Contracting Company 398d 11575h 30-Nov-20 07:00 AM A 11-May-22 09:00 AM 58.77%
Bidding & Contract Award 17d 170h 30-Nov-20 07:00 AM A 07-Dec-21 06:00 PM A 100%
A1000 Contract Award Notification 1d 10h 30-Nov-20 07:00 AM A 30-Nov-20 06:00 PM A 100%
A1010 Receipt of Purchase Order 1d 10h 30-Nov-20 07:00 AM A 30-Nov-20 06:00 PM A 100%
A1020 GIH Training 10d 100h 07-Dec-21 07:00 AM A 07-Dec-21 06:00 PM A 100%
A1030 Kick off Meeting 1d 10h 15-Feb-21 07:00 AM A 15-Feb-21 06:00 PM A 100%
A1040 Document Submission 4d 40h 16-Feb-21 07:00 AM A 20-Feb-21 06:00 PM A 100%
Project M
Milestones 388d 0h 30-Nov-20 07:00 AM A 01-May-22 09:00 AM 0%
A1050 Project Start 0d 0h 30-Nov-20 07:00 AM A 0%
A1060 Project Finish 0d 0h 01-May-22 09:00 AM 0%
Procurement Works
Procurem 282d 215h 20-Feb-21 07:00 AM A 28-Dec-21 05:00 PM A 100%
A1070 Piping Materials Procurement 60d 60h 20-Feb-21 07:00 AM A 29-Apr-21 05:00 PM A 100%
A1080 Support Materials Procurement 60d 60h 20-Feb-21 07:00 AM A 29-Apr-21 05:00 PM A 100%
A1090 Sadara Free Issue Materials (Manual Pull Valves) 15d 15h 28-Dec-21 07:00 AM A 28-Dec-21 05:00 PM A 100%
A1100 Third Party PO Issue. 80d 80h 20-Feb-21 07:00 AM A 23-May-21 06:00 PM A 100%
Shop Works
Wo 199d 1420h 01-May-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
Piping 199d 880h 01-May-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1110 Piping Materials Receiving Inspection 1d 40h 01-May-21 07:00 AM A 08-May-21 06:00 PM A 100%
A1120 Pipe Marking // Cutting // Fit up // Threading 15d 600h 01-Dec-21 07:00 AM A 08-Dec-21 06:00 PM A 100%
A1150 Pipe Spools Painting 4d 200h 08-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1160 Inspection and Release 1d 40h 26-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
Support 16d 540h 01-May-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1170 Support Materials Receiving Inspection 1d 40h 01-May-21 07:00 AM A 01-May-21 06:00 PM A 100%
A1180 Support Fabrication as per Site Condition 10d 400h 04-Dec-21 07:00 AM A 14-Dec-21 06:00 PM A 100%
A1190 Support Galvanizing 4d 80h 14-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
A1200 Inspection and Release 1d 20h 26-Dec-21 07:00 AM A 26-Dec-21 06:00 PM A 100%
Site Works
Work 288d 9430h 08-Dec-21 07:00 AM A 26-Apr-22 09:00 AM 53%
Scaffolding Works - PCA Area
Scaffold 54d 1540h 08-Dec-21 07:00 AM A 22-Dec-21 06:00 PM A 100%
A1210 Scaffolding Materials Mobilization 4d 40h 08-Dec-21 07:00 AM A 11-Dec-21 06:00 PM A 100%
A1220 Scaffolding Erection as required. 50d 1500h 12-Dec-21 07:00 AM A 22-Dec-21 06:00 PM A 100%
Piping A
Activity - PCA Area 77d 1580h 26-Dec-21 07:00 AM A 24-Mar-22 05:00 PM 78.48%
A1230 Pipe Supports Installation as per Site Condition. 10d 400h 26-Dec-21 07:00 AM A 05-Jan-22 06:00 PM A 100%
A1240 New Piping Spools Erection as per Site Condition. 15d 600h 26-Dec-21 07:00 AM A 11-Jan-22 06:00 PM A 100%
A1250 New Manual Pull Valve Installation. 15d 240h 26-Dec-21 07:00 AM A 11-Jan-22 06:00 PM A 100%
A1260 Tie-In Connections. 6d 240h 13-Mar-22 07:00 AM 19-Mar-22 06:00 PM 0%
A1270 Field Leak Testing & Commissioning. 4d 80h 20-Mar-22 07:00 AM 23-Mar-22 06:00 PM 0%
A1280 Inspection and Release. 1d 20h 24-Mar-22 07:00 AM 24-Mar-22 05:00 PM 0%
Scaffolding Works - Train 01
Scaffold 24d 1540h 02-Jan-22 07:00 AM A 14-Mar-22 06:00 PM 90.26%
A1460 Scaffolding Materials Mobilization 4d 40h 05-Jan-22 07:00 AM A 05-Jan-22 07:00 AM A 100%
A1470 Scaffolding Erection as required. 20d 1500h 02-Jan-22 07:00 AM A 14-Mar-22 06:00 PM 90%
Piping A
Activity - Train -01 Area 67d 1180h 10-Jan-22 07:00 AM A 29-Mar-22 09:00 AM 70.17%
A1290 Pipe Supports Installation as per Site Condition. 8d 320h 10-Jan-22 07:00 AM A 13-Mar-22 04:00 PM 90%
A1300 New Piping Spools Erection as per Site Condition. 12d 480h 10-Jan-22 07:00 AM A 14-Mar-22 09:00 AM 90%
A1310 New Manual Pull Valve Installation. 12d 120h 10-Jan-22 07:00 AM A 14-Mar-22 09:00 AM 90%
A1320 Tie-In Connections. 4d 160h 19-Mar-22 09:00 AM* 23-Mar-22 09:00 AM 0%
A1330 Field Leak Testing & Commissioning. 4d 80h 23-Mar-22 09:00 AM 28-Mar-22 09:00 AM 0%
A1340 Inspection and Release. 1d 20h 28-Mar-22 09:00 AM 29-Mar-22 09:00 AM 0%
Scaffolding Works - Train 02
Scaffold 24d 1540h 19-Mar-22 09:00 AM 16-Apr-22 09:00 AM 0%
A1480 Scaffolding Materials Mobilization 4d 40h 19-Mar-22 09:00 AM* 23-Mar-22 09:00 AM 0%
A1490 Scaffolding Erection as required. 20d 1500h 23-Mar-22 09:00 AM 16-Apr-22 09:00 AM 0%
Piping A
Activity - Train -02 Area 20d 1100h 31-Mar-22 09:00 AM 24-Apr-22 09:00 AM 0%
A1350 Pipe Supports Installation as per Site Condition. 7d 280h 31-Mar-22 09:00 AM 09-Apr-22 09:00 AM 0%
A1360 New Piping Spools Erection as per Site Condition. 11d 440h 31-Mar-22 09:00 AM 13-Apr-22 09:00 AM 0%

Actual Level of Effort R Page 1 of 4 TASK filter: All Activities


Actual Work C © Oracle Corporation
EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE

2021 2022
e Feb
Oct Nov Dec Jan

07-Dec-21 06:00 PM A, Bidding & Contract Award

GIH Training

28-Dec-21 05:00 PM A, Procurement Works

Sadara Free Issue Materials (Manual Pull Valves

26-Dec-21 06:00 PM A, Shop Works


26-Dec-21 06:00 PM A, Piping

Pipe Marking // Cutting // Fit up // Threading


Pipe Spools Painting
Inspection and Release
26-Dec-21 06:00 PM A, Support

Support Fabrication as per Site Condition


Support Galvanizing
Inspection and Release

22-Dec-21 06:00 PM A, Scaffolding Works - PCA Area


Scaffolding Materials Mobilization
Scaffolding Erection as required.

Pipe Supports Installation as per Site


New Piping Spools Erection a
New Manual Pull Valve Install

Scaffolding Materials Mobilization

Actual Level of Effort R Page 2 of 4 TASK filter: All Activities


Actual Work C © Oracle Corporation
EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE

Activity ID Activity Name Original Budgeted Start Finish Units %


Duration Labor Units Complete

A1370 New Manual Pull Valve Installation. 11d 120h 31-Mar-22 09:00 AM 13-Apr-22 09:00 AM 0%
A1380 Tie-In Connections. 4d 160h 13-Apr-22 09:00 AM 18-Apr-22 09:00 AM 0%
A1390 Field Leak Testing & Commissioning. 4d 80h 18-Apr-22 09:00 AM 23-Apr-22 09:00 AM 0%
A1400 Inspection and Release. 1d 20h 23-Apr-22 09:00 AM 24-Apr-22 09:00 AM 0%
Scaffolding Works - Train 04
Scaffold 11d 410h 03-Apr-22 09:00 AM 16-Apr-22 09:00 AM 0%
A1560 Scaffolding Materials Mobilization 1d 10h 03-Apr-22 09:00 AM 04-Apr-22 09:00 AM 0%
A1570 Scaffolding Erection as required. 10d 400h 04-Apr-22 09:00 AM 16-Apr-22 09:00 AM 0%
Piping A
Activity - Train -04 9d 540h 16-Apr-22 09:00 AM 26-Apr-22 09:00 AM 0%
A1500 Pipe Supports Installation as per Site Condition. 4d 160h 16-Apr-22 09:00 AM 20-Apr-22 09:00 AM 0%
A1510 New Piping Spools Erection as per Site Condition. 4d 160h 16-Apr-22 09:00 AM 20-Apr-22 09:00 AM 0%
A1520 New Manual Pull Valve Installation. 4d 80h 16-Apr-22 09:00 AM 20-Apr-22 09:00 AM 0%
A1530 Tie-In Connections. 2d 80h 20-Apr-22 09:00 AM 23-Apr-22 09:00 AM 0%
A1540 Field Leak Testing & Commissioning. 2d 40h 23-Apr-22 09:00 AM 25-Apr-22 09:00 AM 0%
A1550 Inspection and Release. 1d 20h 25-Apr-22 09:00 AM 26-Apr-22 09:00 AM 0%
Walkdown and Punch Clearance
Walkdow 4d 160h 26-Apr-22 09:00 AM 01-May-22 09:00 AM 0%
A1410 MC Walkdown and Punch Clearance 2d 80h 26-Apr-22 09:00 AM 28-Apr-22 09:00 AM 0%
A1420 PSSR Walkdown and Punch Clearance 2d 80h 28-Apr-22 09:00 AM 01-May-22 09:00 AM 0%
Hand Over
Ove 9d 180h 01-May-22 09:00 AM 11-May-22 09:00 AM 0%
A1430 Document Submission 7d 140h 01-May-22 09:00 AM 09-May-22 09:00 AM 0%
A1440 Construction Completion. 1d 20h 09-May-22 09:00 AM 10-May-22 09:00 AM 0%
A1450 Hand Over 1d 20h 10-May-22 09:00 AM 11-May-22 09:00 AM 0%

Actual Level of Effort R Page 3 of 4 TASK filter: All Activities


Actual Work C © Oracle Corporation
EJN-00625 Installation of Manual Pull Valves in Deluge Systems for SOLPE

2021 2022
e Feb
Oct Nov Dec Jan

Actual Level of Effort R Page 4 of 4 TASK filter: All Activities