Construc Tion: The Fullerton Bay Hotel

The Fullerton Bay Hotel project involved the construction of a 6-story hotel block and other facilities over Marina Bay in Singapore. Key challenges included construction over water and managing activities in the busy downtown area. Materials were delivered just-in-time due to site congestion. Stringent safety and environmental standards were implemented during the 32-month construction period. Innovative construction methods like using precast components and a temporary deck minimized hazards of working over water.

Uploaded by

Danny Espinosa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views1 page

Construc Tion: The Fullerton Bay Hotel

The Fullerton Bay Hotel project involved the construction of a 6-story hotel block and other facilities over Marina Bay in Singapore. Key challenges included construction over water and managing activities in the busy downtown area. Materials were delivered just-in-time due to site congestion. Stringent safety and environmental standards were implemented during the 32-month construction period. Innovative construction methods like using precast components and a temporary deck minimized hazards of working over water.

Uploaded by

Danny Espinosa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

O N S T R C E L L E N E C O N S T S T R U C T I T RU C T I O E XC E L L E N E XC E L

I O N E X L L E N C C E C O N C O N S C T I O N U C T I O
STRUCTTRUCTION EXCTEION EXCELLENO N E XC E L L E N C E
E N C E CO N S T R U
L L E N C E C O N S T R
CONS AWARD N S T R U C S T R U C T I N E X C E L L I O N E XC E
C E C O E C O N U C T I O R U C T
ELLEN N EXCELLENC ENCE CONSTR LENCE CONST
RUCTIOCTION BECXA CELLRUCTION EXE CAWEALRD
O N S T R U E C O N S T L L E N C
L E N C E XC E
N EXCEL
Key Features
The Fullerton Bay Hotel
Commercial / Mixed Development Builder Quantity Surveyor • A commercial / hotel development comprising the conservation of the Clifford Pier and former Custom
Buildings Category Kim Seng Heng Davis Langdon KPK Building Branch, as well as the construction of a 6-storey hotel block, single story Café, landing area,
Engineering Construction (Singapore) Pte Ltd North Deck, promenades and other ancillary facilities over Marina Bay.
(Pte) Ltd
• Main constraints were the managing of heavy activities in the Central Business District as well as the
Landscape Consultant
challenges of construction over Marina Bay and along the existing seawall. Special attention was also
Developer Ong&Ong Pte Ltd required to avoid affecting existing underground services.
Precious Quay Pte Ltd
Lighting Consultant • Materials and equipment were delivered on a just-in-time basis due to site congestion.
Principal Consultant Light Cibles Pte Ltd
DP Architects Pte Ltd • The coordination of high end interior finishes required careful planning and installation as most materials
Construction Cost were imported.
Architectural Consultant S$134.9 million
DP Architects Pte Ltd • Stringent safety standards and special environmental control measures were implemented e.g. installation
Construction Period of perimeter underwater silt/debris control fence to prevent water pollution.
Structural Consultant 32.0 months
• Adopted a top-down construction and converted some structural components to precast to minimise
Beca Carter Hollings &
hazards of working above water.
Ferner (S.E. Asia) Pte Ltd Gross Floor Area
10,000 m2 • Constructed a robust temporary construction deck for construction vehicles, material storage and steel
M&E Consultant framing supports for “hanging” formwork.
Beca Carter Hollings &
Ferner (S.E. Asia) Pte Ltd • Converted spun piles to micro piles for the North Deck Promenade where the micro piles also support the
extension of the temporary construction deck over water.

• Converted spun piles to bored piles with left-in fiberglass-reinforced plastic casing for higher loading
capacity and protection against deterioration.

• System formworks were used for construction of round columns for better finishing.