AMT 20604 : Construction
Value Estimation and
Procurement (W2-
Introduction to Contract and
Tendering II )
Sr. Dr. Norsyakilah Romeli
(Professional QS, MRISM, BQSM)
PhD in Built Environment (UiTM)
Msc in Integrated Construction Project Management (UiTM)
Degree in Quantity Survey (UiTM)
Diploma in Quantity Survey (UiTM)
SCOPE OF WORKS &
CLIENT’S NEED STATEMENT
Project
Client
Need of statement to own the building,
for public purpose and private purpose
Can be the one who finance the project
and the one who gather all of the funding
to implement the projects
The one who appoint consultant, current
practice consultant must compete as well
Construction team in client side provide
general details of construction
Client’s Need Statement
To own as per required building/
infrastructure, cost saving and satisfied with
the delivery of the product.
Risk in building construction are high in
especially in design and cost
The procurement approach tend to deal
with risk management that clients may need
to understand
Therefore, the document tender need to be
precise and spell out everything so that
client can calculate their cost of risk.
SCOPE OF WORKS
Contractor
During tenderer process, the contractor
bid the tender with reasonable amount that
he wished to go through
The quantity surveyor in contractor side
will aware of their rate, their supplier rate,
and overhead for the company
Profit and attendance were pre determined
before getting into the tender
Contractor’s Objective
Usually bound and ready for any risk to be taken.
Clear scope of work so that the risk has been
calculated as well
Contractor need to be firm on what scope of
work and area of limitation to execute the work,
especially when the work is impossible to be
implement
Contractor is concern on the optimization of
their profit.
Hence, contract has been formulated to ensure
the controlled payment from the client to the
contractor
Consultant
Appointed by the client to assist with the
pre contract and post contract usually
lead by architect as the superintending
officer
The architecture and structure design,
specification, approval were pre
determined before tender document
produced
Quantity surveyor assist with legal
documentation on behalf of the client
Types of Contract
Lump sum – based on specification and
drawings, bills of quantity
Unit Price – bills of quantity, schedule of
daywork rate
Cost reimbursement – fee percentage, fix
fee, Cost plus with guaranteed maximum
price (GMP) contract
Time and Materials - time and materials
contracts define an hourly or daily rate
for builders
Pre Contract Process
Feasibility
Preparation of
studies and Preliminary Detail
Project Brief preliminary
project estimates design
design
inception
Preparation Tender Tender
Preparation
to sign the evaluation and invitation and
of tender
document letter of tender
documents
contract acceptance acceptance
POST CONTRACT START
(Syed Abdul Haris & Bushral , 2007)
ELEMENTS OF DOCUMENT
CONTRACTS, STANDARD FORM
OF CONTRACTS
Evolution of tender document
Table Tender
Document (TTD) Tender Document (TD)
Preliminary Tender Contract
Estimate (PTE)
document
Preliminary Tender Estimate
Estimation done by quantity surveyor
with rate given and agreed by consultant
and client
Based on clients statement of needs,
design approved by C&S, M&E consultant
As reference for tender evaluation
Private and confidential
Table Tender Document
A tender document without rate
Spell out the specification
Material used
Scope of work in bill of quantities
Document Tender
Document that portrayed the physical
projects into a paper
Design according to details spells out inside
the document tender
Document tender will be sell to the
contractor
Contract Document
Tender that has winning the bidding,
agreed by the contractor through letter
of acceptance
Signed by contractor
Pre agreement in between contractor and
client to produce/ construct the building
within stipulated time in within the
contract sum agreed.
Purposed of tendering procedure :
• Select a competence contractor for a
particular project according to the
expertise and class
• Obtain for an offer at a reasonable price
form relevant and competence contractor
• Tendering may taken account on the
construction period bid by the tenderer
however current practice; clients
indicated the time frame to complete the
project
Purpose of converting tender
document into contract document
Element of contract is existed
As an evidence to ensure that during the
construction project, everyone falls in to
the responsibility written in the contract
Defend mechanism for all parties when
construction undergo dispute
Guideline for contractor for constructing
Rate issues, usage for claim the work
done
Content of Tender Document :
Specification
Written description, the quality and aspect
of the construction project.
Technical details of the standard
workmanship, quality of materials
The information which not easily shown on
a project drawing
Technical specification content :
General – the scope of work to be performed within
the specification section or work item included in
pricing
Material – describe the product (materials,
equipment, accessories, component, fixture) and the
development and manufacturing process to be used in
producing them
Execution – describes the preparation, workmanship,
installation, erection and application procedures to be
employed along with quality requirements and
performance criteria that must be satisfied
Content of Tender Document : Bills
of Quantities
The contract sum spell out
Formed from the taking off QS produce
according to drawing/ design/
specification/ materials
Scope of Work details in the description
Item, Description, Quantity, Unit, Rate
Unit can be in m2, m3, numbers, lump sum
Content of Tender Document : Bills
of Quantities
To provide a uniform tendering basis and
determine the price.
BQ normally covers this matters :
Preliminaries, Measured Item, Prime Cost
Sum and Provisional Sum
Preliminaries – describing contractor’s
general obligation and management
arrangement
Measured Item – detailed quantification of
the works which are usually group into
trades of works section
Content of Tender Document : Bills
of Quantities
Prime Cost Sum : for works which are to
be carried out by nominated sub-
contractors or for goods to be supplied
by nominated suppliers or statutory
authority, under the direction of the main
contractors.
Provisional Sum : for work which cannot
be entirely foreseen, defined or detailed
at the time of tendering
Content of Tender Document
:Standard Form of Contracts
PWD 203A and PAM 2006
FIDIC (Civil & Infrastructure Projects)
For public and private projects
The law enforce along the construction projects
Claims and dispute can be refer to the standard
form of contract as the intention and need are
clearly stated
Procedure and guideline
Item is different from one to another standard
form of contracts, in terms of time frame and
procedure
Content of Tender Document
:Standard Form of Contracts
PWD 203A usually preferred by
government
MAHB, MBSA, Putrajaya Development
using their own standard form of contract
but taking the content derived from PWD
203A
Client usually bound to construct the
public construction
Content of Tender Document
:Standard Form of Contracts
PAM 2006 usually used by the private
client
Sime Darby, KPJ Healthcare, Glomac
Housing works, convention center, hotel
and amenities, shopping complex
For private purpose, investment for the
client to gain profit after the project done.
For individual and personal used eg ;
construction of bungalow
Differences
Time for each of the procedure, EOT,
LAD calculation
Terms and definition of works
Authorized personnel as per named in
the contract
Requirement for contract document
As-built drawings and maintenance works
Content of Tender Document :
Instruction to Tenderer
The general instruction for the tenderer
Where to buy the tender?
What should be in the tender?
How many pages ?
What would be the requirement?
When will be the dateline to submit ?
Tender box, site visit date ?
Content of Tender Document :
Letter of Acceptance
Tender evaluation done, the client
selected the best tenderer.
The tenderer required to sign on the
letter of acceptance (compulsory strictly)
The contract is invalid as long as the
contractor didn’t sign the letter of
acceptance
Indicating the both parties agree for a
contract.
Content of Tender Document
:Preliminaries
Before contractor enter the site, the
preliminaries works has to be done
Preliminaries divided into initial, recurring,
completion
Example, electrical, site investigation, site
office, access road, hoarding
Content of Tender Document :
Form of Tender
Form of tender require to be sign
Mandatory information : contact sum,
name of the project, duration of the
project, sign / verification from the
correct personnel
Must be the director of the company
Not valid if the personnel not pass the
mandatory regulation to form a contract
Content of Tender Document :
Condition of Contract
Conditions and requirement before
undergo into a contract
Contractor must read
Mentioned about regulation, responsibility
and legal action taken if the certain
situation happened.
Content of Tender Document
:Schedule of Daywork Rate
The labour rate must be based on the
Schedule of Daywork Rate.
Usually the rate based on JKR Schedule of
Daywork Rate and Siaran Khas according
to Jabatan Statistic Negara (recent years)
The contractor must do Built Up Rates
base
Content of Tender Document :
Preamble
Trades of the craftsman works
Material that has been usually rarely
found in the common construction
Required to be stated including the
methodology of construction
Brief method statement required to be
stated in preamble.
Content of Tender Document :
Drawings
Show graphically in details works to be
done.
Drawings covers architectural, structural,
mechanical and electrical
There are normally grouped in location of
the drawing ( masjid, dewan makan,
hostel)
Assembly drawing (IBS drawing)
Component drawings
Tender Notice and Condition of
Tendering
Time and place for the submission of tender
Site visit
The form of tender – matters must be included
Tender period and closing date
Tender validity period – a specified period during
which a tender should remain open for
acceptance, although the tenderer may revoke it
at any time
Necessary fees and deposit
Requirement to be fulfill before/ execution of
contract
Formation of Contract Document
Contractor – submit
Client – offer contract,
tender document, sign LA,
needs statement to have a
perform regulatory
building. Verify consultant
responsibility as verified
judgement
by S.O on site
Consultant – lead by S.O
(architect) prepare PTE,
advise client, perform
mandatory checking, select
the best tenderer to
proceed for contract
management
TENDERING TYPES
TENDERING PROCEDURE AND
MODE OF TENDERING
Purpose of tendering : to select a suitable
contractors at time appropriate to the
circumstances of the project
Selection of the contractors : optimum
resources, financial, manpower, material,
contractors input on the design, cost saving
alternative through value engineering,
allocation of risk
Mode : Open tender, direct negotiation,
selective tendering
Open tender
Any contractors who meets the specified requirement to carry
out a proposed construction project may submit a tender for
the work
Tenders can be invited through advertisement in the technical,
trade and or general press. For public work, an invitation to bid
is placed in the classified advertising section of one or more
national newspaper over specified period
Advertising will give outline details of the works, its scale,
programme, the form of contract and other relevant matters
Commonly used bt government agencies to ensure
accountability of public funds
Complete design documentation is necessary to enable accurate
bidding
Open tender (cont’d)
Attract large number of tenders and the bids are expected to be more
competitive. However, it is inefficient used of the industry used.
Lowest possible price will be obtained, although the experience and the
financial standing of such contractor are suspected. Highly risk of choice
Low tenders from contractor as a consequences of making the most
errors or who cut price at the initial stage with a view of recouping the
losess by means of corner- cutting and claims
Tendering can be expensive and cost of unsuccessful tenders tend to
inflate prices for future work
The method allows for new firm the chances of tendering for works
The method allows for new firm the chance of tendering for work
Tenderers have no assurances about the quality of their competitors
A higher cost of administration of tenders, duplicating document
Problem of selecting best tender from a wide range of tenders
Direct negotiation
The tendering method is without a call or
competition. The clients selects a contractor
directly and then negotiates with the terms
of agreement and form of payment
This approach maybe appropriate when the
client believed that the contractor possesses
skills or experience relevant to the project
based on the latter’s reputation and
recommendation
Negotiation may based on schedule of
prices, or approximate bills of actual costs
plus agreed profit margin.
Direct negotiation (cont’d)
Contractor must prepared a budget quotation for
the work based on limited information
Client and contractor’s representative work on
the and negotiate on the rates and prices and
finally agree to a tender price
In negotiation with the chosen contractor, main
item can be roughly quantified and price as basis
of agreement, with additional less costly items
agreed later in a consensual rather than
adversarial negotiation
Competitive – client negotiates the term with
selected bidders (include a formal tender stage
prior to negotiation
Direct negotiation (cont’d)
Negotiation may be considered under these
circumstances
1. established business relationship between client
and contractor
II. Quality and not economy is major determinant
III. A continuation contract based on the first contract
IV. Additional contract where contractor is already on
site
V. the contractor have special expertise relevant to
the project
VI. Contractor’s contribution is required in relation
to design or programming
Direct negotiation (cont’d)
Cut down time and money on tendering
Completed design documentation is not
necessary for work to start, and the
contractor’s skill may be brought into the
design process
Absence of competition, so the tender sum
may be higher
But client may get think it worth paying
more in return for a quicker job, or better
quality than he may otherwise obtain.
Selective tendering
Only a limited numbers of contractors who
fulfill certain criteria are invited to tender
The selection is done prior to tender
invitation
The criteria are often the general
experience of the types of project
contemplated, financial ability and managerial
and technical capabilities
Suitable firms are invited from clients/
consultant approved list singled out by
reputation, recommendation, previous
contact with client or consultants.
Selective tendering (cont’d)
Select tendering can be approached in two
stages
In the first stage – advertisement can be
published inviting suitable firms to pre qualify
for tendering. The tenderer will have to
supply information about their previous
experience, physical resources and financial
standing
After which the client will only invited small
numbers of the pre-qualified contractors to
submit their tenders
Selective tendering (cont’d)
Can mean higher quotations because of
less competition but also because of the
higher caliber of the tenderer
This method ensure the lowest prices
from contractors who are capable of
doing the work
Cost of tendering reduced