Office of The Municipal Engineer Improvement of Multi-Purpose Hall/ Repair and Rehabilitation
Office of The Municipal Engineer Improvement of Multi-Purpose Hall/ Repair and Rehabilitation
III Window Glass and Pre -Fabricated Grills With Finish Painted
a. Materials
Quantity Unit Description Unit Cost Amount
8.00 pcs Pre-Fabricated Window Grills with Finish Painted (3.00m x 1.7m) 5,700.00 45,600.00
2.00 pcs Pre-Fabricated Window Grills with Finish Painted (0.80m x 0.80m) 2,200.00 4,400.00
8.00 sets 6mm THK. Tinted Glass Sliding Window on Anolok Frame (3.0mx1.70m) 10,000.00 80,000.00
4.00 sets 6mm THK. Tinted Glass Sliding Window on Anolok Frame (1.80mx1.33m) 6,000.00 24,000.00
2.00 sets 6mm THK. Tinted Glass Sliding Window on Anolok Frame (0.80mx0.80m) 2,000.00 4,000.00
Sub-Total Php 158,000.00
b. Manpower
Quantity Description No. of Days Unit Cost Amount
2.00 Installer 3.00 500.00 3,000.00
2.00 Laborer 3.00 350.00 2,100.00
Sub-Total Php 5,100.00
IV 6mm THK. Glass Partition Wall and Crown Moulding with Finish Plastering
a. Materials
Quantity Unit Description Unit Cost Amount
1.00 set 6mm THK. Tinted Glass Fixed Partition with Sliding Window(2.35m x 2.4m) 8,500.00 8,500.00
1.00 set 6mm THK. Tinted Glass Fixed Partition with Sliding Window and Door(3.7 x 2.4) 16,000.00 16,000.00
1.00 set 6mm THK. Tinted Glass Fixed Partition with Sliding Door(3.45mx 2.40m) 14,500.00 14,500.00
1.00 set 6mm THK. Tinted Glass Fixed Partition on anolok frame(3.70mx 2.40m) 18,500.00 18,500.00
1.00 kg # 1-1/2" Finishing Nails 95.00 95.00
116.00 sheet 1"x4ftx8ft Marine Plywood 2,500.00 290,000.00
55.00 pcs Crown Moulding with Finish Painted (1"x3"x8') 250.00 13,750.00
Sub-Total Php 361,345.00
b. Manpower
Quantity Description No. of Days Unit Cost Amount
2.00 Installer 10.00 500.00 10,000.00
4.00 Laborer 10.00 350.00 14,000.00
V Parking Space
a. Materials
Quantity Unit Description Unit Cost Amount
3.00 length G.I Pipe 3" 4,950.00 14,850.00
12.00 length Tubular 2x3x6mx1.0mm 600.00 7,200.00
1.00 load Fine Aggregates 1,400.00 1,400.00
4.00 load coarse Aggregates 1,500.00 6,000.00
28.00 bags Cement 250.00 7,000.00
6.00 length Tubular 2x3x6mx1.5mm 1,350.00 8,100.00
10.00 sheet 0.40mm thk. Pre-Fabricated Gutter with finish Painted 450.00 4,500.00
3.00 gal Epoxy Primer 850.00 2,550.00
1.00 gal Paint Thinner 550.00 550.00
3.00 pcs Paint Brush #3 50.00 150.00
41.40 ln.m 0.40mm thk. Pre-Painted Rib Type Color Roofing 250.00 10,350.00
1.00 box Rivets 380.00 380.00
11.00 length 1/4"x1"x1" Flat Bar Senep 400.00 4,400.00
1.00 box N6013 Welding Rod 900.00 900.00
6.00 length 3" Dia PVC Pipe Series 900 Downspout 250.00 1,500.00
1.00 l.s 3" Dia PVC Fittings & Accessories 500.00 500.00
1.00 can Solvent 65.00 65.00
180.00 pcs Metal Teckscrew 1 1/2' 2.00 360.00
Sub-Total Php 70,755.00
b. Manpower
Quantity Description No. of Days Unit Cost Amount
1.00 Foreman 15.00 600.00 9,000.00
1.00 Mason 15.00 500.00 7,500.00
4.00 Laborer 15.00 350.00 21,000.00
1.00 Welder 15.00 500.00 7,500.00
Sub-Total Php 45,000.00
c. Equipment Rental
Quantity Description No. of Days Unit Cost Amount
1.00 unit Welding Machine 10.00 850.00 8,500.00
c. Equipment Rental
Quantity Description No. of Days Unit Cost Amount
1.00 unit Welding Machine 5.00 850.00 4,250.00
VIII Electrical
a. Materials
Quantity Unit Description Unit Cost Amount
12.00 pcs 3-Gang Outlet (Panasonic) 260.00 3,120.00
12.00 pcs Moulding 3/4" dia. 80.00 960.00
1.00 box 3.5mm THHN Stranded Copper Wire 4,420.00 4,420.00
1.00 box Metal screw with tox 6mm x 1" 100.00 100.00
12.00 pcs Utility surface type 45.00 540.00
2.00 pcs 4x10x10 Pull Box 1,950.00 3,900.00
4.00 pcs uPVC Pipe #1 175.00 700.00
3.00 pcs uPVC Elbow #1 135.00 405.00
2.00 pcs uPVC Pipe 3/4" 135.00 270.00
2.00 pcs uPVC Elbow 3/4" 110.00 220.00
25.00 mts #4 THW Wire 750.00 18,750.00
1.00 pc 200-Amp/5 - Jaws Milbank Meter Base 10,400.00 10,400.00
1.00 pc RSC Pipe #1 325.00 325.00
1.00 pc Entrance Cap #1 84.50 84.50
1.00 pc 2-Spool Secondary Rack 325.00 325.00
1.00 lot Meter Deposit 5,200.00 5,200.00
2.00 pcs Enclosure box 150.00 300.00
2.00 pcs 30- Amp/2 Pole Bolt on GE Circuit Breaker 1,625.00 3,250.00
40.00 mts 5.5mm THHN Stranded Copper Wire 40.00 1,600.00
Sub-Total Php 54,869.50
b. Manpower
Quantity Description No. of Days Unit Cost Amount
3.00 Electrician 5.00 500.00 7,500.00
4.00 Laborer 5.00 350.00 7,000.00
Sub-Total Php 14,500.00
c. Equipment Rental
Quantity Description No. of Days Unit Cost Amount
1.00 unit Welding Machine 3.00 850.00 2,550.00
b. Manpower
Quantity Description No. of Days Unit Cost Amount
1.00 Installer 3.00 500.00 1,500.00
2.00 Laborer 3.00 350.00 2,100.00
Sub-Total Php 3,600.00
b. Manpower
Quantity Description No. of Days Unit Cost Amount
1.00 Installer 2.00 500.00 1,000.00
2.00 Laborer 2.00 350.00 1,400.00
Sub-Total Php 2,400.00
I. DIRECT COST
a. Materials cost Php 911,468.21
b. Labor Cost Php 145,700.00
c. Equipment Cost Php 15,300.00
Total Direct Cost Php 1,072,468.21
II. INDIRECT COST
a. Overhead, Contingency, and Miscellaneous (12% of EDC) Php 128,696.19
b. Contractor Profit ( 10% of EDC ) Php 107,246.82
c. Contractor Tax 7%( EDC+OCM+Profit ) Php 91,588.79
Total Indirect Cost Php 327,531.79
% Total Amount
I. DIRECT COST:
1. Materials 84.99% 911,468.21
2. Labor 13.59% 145,700.00
3. Equipment 1.43% 15,300.00
Total Estimated Direct Cost 100.00% 1,072,468.21
II. INDIRECT COST:
a. Overhead, Contingency and Miscellaneous (12% of EDC) 128,696.19
b. Contractor Profit (10% of EDC) 107,246.82
c. Contractor Tax 7% (EDC+OCM+Profit) 91,588.79
Total Estimated Indirect Cost 327,531.79
TOTAL ESTIMATED PROJECT COST 1,400,000.00
MARIE
___ROLAN
CHRIS
M. AGUANTA
NEÑERIA ___ ___OSCAR JAN M. MASILLONES___
Engineer
Engineering I
Aide Engineer Assistant
Name of Project -
Location Barangay Poblacion, Governor Generoso, Davao Oriental
Structure Capacity Err:509
Err:509
Calendar Days to Complete : 120 Calendar Days 0.15
Source of Funds : CY 2016 DA-Pamana Fund
Implementation Scheme : By Contract
Subject : Approved Budget for the Contract (ABC)
I General Requirements
a. Mobilization/Demobilization 1.00 lot 15,500.00 1,860.000 1,550.00 1,323.70 4,733.70 20,233.70 20,233.70
b. Occupational Health and Safety 1.00 lot 10,000.00 1,200.000 1,000.00 854.00 3,054.00 13,054.00 13,054.00
c. Project Billboard 1.00 lot 5,500.00 660.000 550.00 469.70 1,679.70 7,179.70 7,179.70
d. Temporary Facilities 1.00 lot 10,000.00 1,200.000 1,000.00 854.00 3,054.00 13,054.00 13,054.00
II Doors and Demolition Work 33.82 sq.m 126,400.00 15,168.000 12,640.00 10,794.56 38,602.56 165,002.56 4,879.29
III Window Glass and Pre -Fabricated Grills With Finish Painted 93.74 sq.m 163,100.00 19,572.000 16,310.00 13,928.74 49,810.74 212,910.74 2,271.39
IV 6mm THK. Glass Partition Wall and Crown Moulding with Finish Plaste 170.88 sq.m 385,345.00 46,241.400 38,534.50 32,908.46 117,684.36 503,029.36 2,943.76
V Parking Space 36.00 sq.m 124,255.00 14,910.600 12,425.50 10,611.38 37,947.48 162,202.48 4,505.62
VI Storage Area & Warehouse Works 19.89 sq.m 88,315.00 10,597.800 8,831.50 7,542.10 26,971.40 115,286.40 5,796.20
VII Tile Works 18.00 sq.m 29,440.00 3,532.800 2,944.00 2,514.18 8,990.98 38,430.98 2,135.05
VIII Electrical 187.50 sq.m 69,369.50 8,324.340 6,936.95 5,924.16 21,185.45 90,554.95 482.96
IX Flower Box 5.58 sq.m 21,950.00 2,634.000 2,195.00 1,874.53 6,703.53 28,653.53 5,135.04
X Covering of Gutter Between Conference & Annex Building 23.04 sq.m 9,040.00 1,084.800 904.00 772.02 2,760.82 11,800.82 512.19
XI Repair of Comfort Room @ Conference Office 1.00 l.s 14,253.71 1,710.445 1,425.37 1,217.27 4,353.08 18,606.79 18,606.79
TOTAL 1,072,468.21 128,696.19 107,246.82 - 91,588.79 327,531.79 1,400,000.00
Err:509
1,699,780.59
Prepared by: Checked by: Recommending Approval: Approved by: 299,780.59
300,000.00
I. Partition
Labor
40% 30000 30000
180000
Cubicle
Qty description Unit cost Amount
110 pcs Marine plywood 0.5" 860
112 pcs Laminate wood adhesive sticker 75
1.296 sq.m Glass 10000
1 lot Miscellaneous 57980
Storage
Qty Unit description Unit cost Amount
6 sheet B.I Steel Matting ga.#6 620.00 3720
2 pcs Tubular 2x3x6mx1.5mm 1300.2 2600.4
5 pcs Tubular 2x2x6mx1.0mm 550 2750
510 pcs CHB 6" 11 5610
25 bags Cement 250 6250
3 load Sand 1650 4950
3 load Gravel 1800 5400
22 ln.m Corrugated ga.24 180 3960
35,240.40
Labor 15,858.18
Carport
Qty Unit description Unit cost Amount
6 ls G.I Pipe 3" 5200 31,200.00
7 ln.m Corrugated ga.26 180 1,260.00
12 L's Metal Studs 32mmx76mm,0.5mm 150 1,800.00
16 sq.m Bricks 1600 25,492.32
2 load Sand 1650 3,300.00
5 bags Cement 250 1,250.00
3 ls Tubular 2x3x6mx1.5mm 1300.2 3,653.56
67,955.88
labor 33,977.94
Flower stand
399,350.60
Other computation
Cubicle 278,304.00
Glass Frame 180,000.00
Flower Stand 5,000.00
463,304.00
Roofing
6 sq.m Polycabonate 6mmx1.22mx2.44 1350 8163.13
3 ls Flat bar 25mmx6mmx6m 450 1350.00
3 ls Tubular 2x3x6mx1.5mm 1350 4050.00
6 ls Tubular 2x2x6mx1.0mm 550 3300.00
100 pcs Metal teckscrew 1" 3 300.00
Crown moulding
16 ls Crown moulding
Flower box
estimates
Cubicle partition
L w H plywood
0.91 0.6 1.12 3.3824 sq.meter
0.91 0.6 0.75 2.265 1.22 2.44
5.6474
Qty 1.897138 2.466279
41.83259 54.38237
Gutter
Plainsheet
steel matting
1.73 8.28 14.3244 4.892213 2.928
5.870656
CHB
0.2 0.4 0.08 27.9036 348.795 418.554
3.31 1.8 5.958 74.475 89.37
507.924
Cement
wall 27.9036 5.958 2.708928
slab 10.55 1.8 0.1 1.899 13.6728
13.76278 17.89161
0.629826 0.089975
0.539851 0.593836 0.83 1.423836
2.135754
Gravel
1.65 2.475
carport
1.89 8.43 15.9327
roofing
8.43 6.909836
8.28 16.56 25.1712 20.63213
metal studs
1.78
1.72
1.66
1.6
1.54
1.48
1.42
1.37
1.31
1.26
1.2
1.15
1.09
1.04
0.98
0.92
0.87
0.81
23.2 3.866667
Polycarbonate
2.4 7.5 18 6.046762
Flat bar
15 2.5
Tubular
15 2.5
2x2
15 36 6
7.5 12.5 80 16
1.08 8 112
1.296
Republic of the Philippines
Province of Davao Oriental
MUNICIPALITY OF GOVERNOR GENEROSO
V- Electrical Works
VI. Doors
2 sets 2 panel Sliding glass Door @ Php 15,000.00 Php 30,000.00
1 set Sliding grills door @ Php 15,000.00 Php 15,000.00
Cost of Materials Php 45,000.00
V-I. Labor Requirements
40% of Materials Cost @ Php 18,000.00 Php 18,000.00
VII. Windows
8 sets 1.7m x 3m sliding glass windows @ Php 10,000.00 Php 80,000.00
2 sets 0.9m x 0.9m sliding glass window @ Php 5,500.00 Php 11,000.00
14 pcs Window Grills @ Php 7,500.00 Php 105,000.00
4 sets Fixed Window @ Php 4,000.00 Php 16,000.00
Cost of Materials Php 212,000.00
V-I. Labor Requirements
40% of Materials Cost @ Php 84,800.00 Php 84,800.00
Partiton Wall
60 pcs Plyboard (3/4") @ Php 1,700.00 Php 102,000.00
60 sq.m 12mm thick clear glass @ Php 1,500.00 Php 90,000.00
192,000.00
40% of Materials Cost @ Php 76,800.00 Php 76,800.00
V Parking Space
Sand
Concrete
Bricks
Roofing
Approved:
parking space
l w h
7 8.5 0.2 59.5 11.9
22.17 7.39
Tile Grout 2.015455 5
OMPUTATION
PROTECTION-CB CONDUIT
CONDUCTORS
AT AF P (mm)