Acceptance Test Guide: Operation Appendixes

Uploaded by

Adrian Carmona
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
188 views14 pages

Acceptance Test Guide: Operation Appendixes

Uploaded by

Adrian Carmona
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 14

Overview

Operation

Appendixes

HUAWEI NE40E Metro Service Platform


V800R009C10
Acceptance Test Guide

Issue 01

Date 2020-08-20

Huawei Proprietary and Confidential


Copyright © Huawei Technologies Co.,
Ltd.
Copyright © Huawei Technologies Co., Ltd. 2020. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.

Notice
Your purchased products, services, and features shall be restricted by Huawei commercial contract and
conditions. All or certain of products, services, or features described in this document may not be included
in what you purchased or used. Unless other statements in the contract, all statements in this document do
not constitute the warranty of any kind, express or implied.
The information in this document is subject to change without notice. Unless other statements, every effort
has been made in the preparation of this document to ensure accuracy of the contents, but all statements,
information, and recommendations in this document do not constitute the warranty of any kind, express or
implied.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base Bantian, Longgang, Shenzhen, People's Republic of China
Postal Code: 518129

Website: http://www.huawei.com

Email: support@huawei.com

Huawei Proprietary and Confidential


Copyright © Huawei Technologies Co.,
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide Contents

Contents

1 Introduction.................................................................................................................................1-1
1.1 About This Document.....................................................................................................................................1-1
1.1.1 Product Version.....................................................................................................................................1-1
1.1.2 Organization..........................................................................................................................................1-1
1.1.3 Revision History....................................................................................................................................1-1
1.2 Definition of and Grounds for Acceptance.....................................................................................................1-2
1.3 Acceptance Process........................................................................................................................................1-2
1.3.1 Factory Acceptance...............................................................................................................................1-3
1.3.2 Acceptance Upon Arrival......................................................................................................................1-3
1.3.3 Installation Acceptance.........................................................................................................................1-4
1.3.4 Preliminary Acceptance.........................................................................................................................1-5
1.3.5 Trial Running.........................................................................................................................................1-5
1.3.6 Final Acceptance...................................................................................................................................1-6

2 Preliminary Acceptance............................................................................................................2-1
2.1 Packaging Description of Acceptance Items..................................................................................................2-1
2.2 Principles for Using Acceptance Packages.....................................................................................................2-3
2.3 On-site Customization of Acceptance Manual...............................................................................................2-3
2.3.1 Quick Customization Through the Automatic Filtration Tool..............................................................2-3
2.3.2 Manual Customization..........................................................................................................................2-3
2.4 Numbering of Acceptance Items....................................................................................................................2-4
2.5 Requirements for Preliminary Acceptance.....................................................................................................2-4
2.6 Environment for Preliminary Acceptance......................................................................................................2-5
2.7 Precautions for Preliminary Acceptance........................................................................................................2-5

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., i
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Introduction

1 Introduction

1.1 About This Document


1.1.1 Product Version
The product version related to this document is the HUAWEI NE8000
The matched NetworkManager version is the NCE-IP V100R020C00

1.1.2 Organization
This document describes contents related to engineering acceptance. The following table lists
the contents of this document.

Section… Describes…

Part 1 Overview The acceptance process, acceptance packages, and numbering of


acceptance items. This part focuses on the methods for operating
and using acceptance packages in preliminary acceptance
Part 2 Operation How to test items in the basic package, extended package A, and
Guide extended package B
Part 3 Appendixes The performance indexes of the product, connection diagrams used
in project acceptance, recommended tools and Instruments, and the
signature list cover and acceptance item list for confirmation

1.1.3 Revision History


Updates between document issues are cumulative. Therefore, the latest document version
contains all updates made to previous versions.

Document Version 01 (2020-03-20)


All network sub-product lines can adjust the contents and structure of this document based on
actual situation

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 1
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Introduction

1.2 Definition of and Grounds for Acceptance


Passing acceptance indicates success of contracted delivery.
Acceptance is the activity that a contractor checks the deliverables using the process, method,
and standards provided by a customer, to complete the contract between the two parties.
Acceptance is involved in the entire process from bidding based on customers' requirements,
to contract negotiation, to project delivery, and to contract completion. Therefore, acceptance
is a key milestone for ensuring contract payment.
Acceptance is performed based on the ITU-T Recommendations, IETF standard, national
standards, and the standards issued by the Information Industry Ministry, and based on the
actual conditions of Huawei equipment. An acceptance team composed of a customer,
installation personnel, and commissioning personnel perform acceptance on equipment.
Through acceptance, the customer confirms the receipt of the equipment that meets the
requirements and specified indexes.

1.3 Acceptance Process


Generally, the acceptance process is divided into four stages: factory acceptance, installation
acceptance, preliminary acceptance, and final acceptance.
The acceptance process involves the procedures from commissioning during production to the
issuance of the acceptance certificate. Following figure shows the acceptance process.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 2
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Introduction

Figure 1-1 Process of equipment installation, commissioning, and acceptance

Commissioning during production

Factory acceptance

Shipment

Acceptance upon arrival

Equipment installation

Installation acceptance

Commissioning during deployment

Preliminary acceptance

Trial running

Final acceptance

Issuance of final acceptance certificate

1.3.1 Factory Acceptance


As required by a customer, factory acceptance is performed at the production site of
equipment to check whether the functions and specifications of the equipment conform to
those specified in a contract.
A factory test report is a certificate of equipment quality delivered with the equipment whose
functions and specifications are strictly tested by Huawei according to the requirements of the
quality control system.

1.3.2 Acceptance Upon Arrival


Generally, acceptance upon arrival consists of two stages: inspection of the packing case

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 3
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Introduction

quantity and inspection of the packing list.

Inspection of the Packing Case Quantity


Inspection of the packing case quantity refers to inspecting the delivered goods based on the
delivery list and BOQ in a contract. This aims to verify whether all equipment and materials
ordered in the contract are delivered to the delivery site specified in the contract. The
inspection method is to inspect whether the quantity of outer packing cases conforms to that
on the delivery list. If necessary, a few packing cases can be opened to inspect whether the
goods in the packing cases conform to that on the packing list. After the inspection,
representatives of a customer and Huawei sign a delivery note.
Generally, a contract regulates that arrival payment is received according to the delivery note.

Inspection of the Packing List


Inspection of the packing list refers to inspecting goods after the goods arrive at the
installation site, which is also called unpacking inspection. Representatives of a customer and
Huawei inspect the unpacked equipment and materials according to the packing list. If no
error is found, both parties sign on the packing list. In case of missing or damaged goods, both
parties need to sign a memorandum of unpacking inspection. The inspection is conducted
along with the project implementation. The inspection ends after the last site is installed.
Therefore, it is forbidden to receive payment according to the unpacking inspection.

1.3.3 Installation Acceptance


Installation acceptance is performed after the equipment is installed. The acceptance aims to
check the installation of the equipment, peripheral terminals, cable routing, grounding cables,
power supply, and hardware, to ensure that the installation quality meets the design
requirements.

Table 1-1 Example of signature list for installation acceptance


SN Item Name Standard and Requirement

1 Equipment (1) The location for installing equipment meets the


requirements.
(2) The equipment is installed stably.
(3) The equipment is neatly arranged.
(4) Markings of equipment are in readiness.
(5) All fixtures are fastened.
(6) Exterior of the equipment is well painted.
2 Peripheral (1) The location for installing NM terminals meets the
terminal requirements.
(2) Configuration is in readiness.
(3) Cabinets are neatly arranged.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 4
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Introduction

SN Item Name Standard and Requirement

3 Cable routing (1) Routing and binding of internal fibers meet the
requirements.
(2) Routing and binding of communication cables meet the
requirements.
(3) Power wires and cables are neatly arranged.
4 Grounding cable (1) The connection of the grounding cable meets standards.
(2) Routing and binding of the grounding cable meet the
requirements.
(3) The grounding resistance is smaller than 1 ohm.
5 Power supply (1) Internal power cables are not grounded.
(2) Power cables are neatly routed.
(3) Connectors of DC power cables meet requirements.
(4) The insulation resistance of the DC feeder cables meets
requirements.
6 Hardware check (1) Boards can be removed and inserted smoothly.
(2) Retainers of plug boards are safe and reliable.
(3) Alarm equipment meets requirements.
(4) After programs are loaded, the hardware is normal.
Conclusion:
Signatures of both parties

Inspection date

1.3.4 Preliminary Acceptance


Preliminary acceptance is performed to test the basic functions and specifications of
equipment and network services on site or in a central equipment room after the equipment is
considered deliverable for use after commissioning. This ensures that the commissioned
project quality meets the design requirements.

1.3.5 Trial Running


The operation quality of network equipment is the best criterion to inspect the equipment.
Therefore, faults that occur on hardware and software during trial running must be recorded,
to evaluate whether the performance of the network equipment is stable and reliable.
Generally, the trial running lasts three months.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 5
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Introduction

1.3.6 Final Acceptance


Final acceptance is performed when the three-month trial running ends. The acceptance aims
to check whether the outstanding problems found in preliminary acceptance are solved and
whether new problems occur during the trial running. If the equipment fails to pass the final
acceptance, an agreement of extending the trial running period should be reached by both
parties, and the final acceptance should be performed again when the extended trial running
period ends. If the equipment passes the final acceptance, the final acceptance report should
be filled out and the acceptance certificate should be issued. After the final acceptance, the
equipment is put into normal operation.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 6
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Preliminary Acceptance

2 Preliminary Acceptance

2.1 Packaging Description of Acceptance Items


Based on features of network products, acceptance items are classified into three packages.
Following table lists the packaging principles and package selection priorities.

Table 1-2 Packaging description of acceptance items


Type of Packaging Principle Priority of Business
Acceptance Item Selecting Items Strategy
Package

Basic package The basic package contains the  Remote The price of
items that can be accepted acceptance the basic
remotely through simple or  Simple or package is
cheap meters. The items in the cheap meters included in
basic package are used to the quotation
ensure normal running of the
 Ensuring basic of
basic services and functions of services and engineering
the equipment and network. functions services.
Extended package A Extended package A contains  Acceptance at a The items in
the items that can be accepted single site extended
at a single site through simple  Simple or package A
or cheap meters. The items in cheap meters are test
extended package A are used services.
to ensure normal running of
 Ensuring basic Therefore, the
the basic services and services and price of
functions of the equipment and functions extended
network. package A
must be
quoted
independently
based on the
requirements
for work
hours and
meters.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 1
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Preliminary Acceptance

Type of Packaging Principle Priority of Business


Acceptance Item Selecting Items Strategy
Package

Extended package B Extended package B contains  Ensuring basic The items in


time-consuming and services and extended
complicated items or items functions package B are
that must be tested through  Expensive test services.
complicated or expensive meters Therefore, the
meters. Based on additional price of
requirements of customers,
 Remote extended
items in extended package B acceptance or package B
can be selected to ensure acceptance at a must be
normal running of the basic single site quoted
services and functions of the independently
equipment and network. based on the
requirements
for work
hours and
meters.

Basic Package
Items in the basic package are used to test the quality of manual commissioning part at project
delivery, and are accepted remotely through the network management system (NMS) or
central equipment room. Items in the basic package include power commissioning and
control, normal running of various hardware and software functions, and BER tests on end-to-
end services. The acceptance of these items ensures the quality and availability of the network
that is delivered to a customer.

Extended Packages A and B


Extended packages A and B are used to test hardware or function indexes. The acceptance of
the items in the two packages requires expensive meters or is performed on site. Therefore,
extended packages A and B are charged as services. Most items in extended packages A and B
are controlled through the production quality control system and factory acceptance during
production. The tested indexes cannot be controlled or adjusted manually during on-site
commissioning.
Therefore, it is not recommended to perform on-site tests on the items in extended packages A
and B. If a customer strongly requires that the items should be tested on site, you can do as
follows:
 Help the customer to recognize Huawei's quality control system and after-sales service.
 Provide the customer with the factory acceptance report and entry test report on these
items.
 Recommend the customer to accept these items independently.
 Recommend the customer to pay for the on-site acceptance of these items.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 2
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Preliminary Acceptance

2.2 Principles for Using Acceptance Packages


The principles for using the acceptance packages are as follows:
 When selecting acceptance items, select fewer items from the basic package in priority,
thus ensuring that the items pass the acceptance quickly and the network and services are
basically available.
 If a customer strongly requires that items other than items in the basic package be tested,
help the customer to recognize the quality control system and after-sales service, provide
the customer with the factory report and entry test report on these items, or recommend
the customer to accept the additional items independently.
 If the preceding recommendations cannot meet the customer's requirement, select fewer
items from extended packages A and B and recommend the customer to pay for the work
hours for accepting these items and usage of meters.
 If the customer refuses to pay for the acceptance of the additional items, present the
acceptance items based on actual conditions.
Engineers are recommended to fully understand the significance and methods of acceptance
and the functions of all acceptance items. To deliver projects with high efficiency and high
quality, engineers need to fully communicate with customers and prepare proper acceptance
standards based on this document.

2.3 On-site Customization of Acceptance Manual


On-site engineers may customize acceptance manuals through tools or manually.

2.3.1 Quick Customization Through the Automatic Filtration Tool


Prerequisite
On-site engineers have the tool that can be used to filtrate or select acceptance items
automatically.

Function
The auto selection tool can be used to automatically generate operation guide (typeset
acceptance items), customer signature list, meter list, and acceptance and work hour list. If a
customer is not satisfied with the result, engineers can adjust (delete or add) the items quickly
and repeatedly through the tool.

Method for Customization


See the Acceptance Test assistant Tool.

2.3.2 Manual Customization


Prerequisite
On-site engineers do not have the tool for filtrating acceptance items automatically; or it is
easy and quick to select acceptance items manually.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 3
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Preliminary Acceptance

Method for Customization


The method for manual customization is the same as the traditional method for manual
editing. That is, select acceptance items from the acceptance packages, manually copy and
paste the acceptance items to a destination document, renumber and typeset the acceptance
items in the destination document, and then prepare the corresponding customer signature list,
meter list, and acceptance work hour list. For the customer signature list, see the Acceptance
Items and Tables in part 3 Appendixes.

2.4 Numbering of Acceptance Items


For easy management and search, all acceptance items are numbered. The following describes
the numbering plan:
Numbering plan:
 If only a few acceptance items are used, a four-digit numbering template can be used. If
many acceptance items are used, a six-digit numbering template can be used to arrange
the acceptance items in multi-level contents, for example, a template for the NMS. Only
one template can be used in the same manual. Unused templates must be deleted.
The format of four-digit numbers is Txx-xx.
The meaning of the numbers is as follows:
Txx-xx

Number of an acceptance sub-item

Number of an acceptance type

The format of six-digit numbers is Txx-xxxx.


The meaning of the numbers is as follows:
Txx-xxxx

Number of an acceptance sub-item

Number of an acceptance item

Number of an acceptance type

2.5 Requirements for Preliminary Acceptance


Preliminary acceptance is performed after the installation process and equipment appearance
is checked and system commissioning is performed.

Huawei Proprietary and Confidential


Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., 4
Ltd.
HUAWEI NE40E Metro Service Platform Part 1 Overview
Acceptance Test Guide 2 Preliminary Acceptance

The preliminary acceptance should be performed based on the plan and acceptance items in
this document. An application for preliminary acceptance must be submitted before the
preliminary acceptance.
If any item does not pass the preliminary acceptance, the item must be commissioned based
on actual conditions.
The final result of the preliminary acceptance must conform to the standard provided by a
customer. Both parties need to sign on the signature list of the acceptance items.

2.6 Environment for Preliminary Acceptance


Generally, preliminary acceptance is performed remotely. The environment and preset
conditions must be prepared based on the required meters and other requirements to ensure
smooth acceptance of all items.

2.7 Precautions for Preliminary Acceptance


Before the test, make sure that the required test cables are available, that the connector type is
adaptable for the test meters, and that the connector is properly connected to the test meters.
Prepare fiber cleaning box to clean connectors during the test of optical interface
characteristics, to ensure the accuracy of test data.
Do not look directly into the optical interface during the test, to prevent the laser beam from
damaging your eyes.
In the 24-hour BER test, ensure that the test is free from interference (including artificial
factors and power failure) during the entire test process. If anomalies occur, record the
accurate time when the anomalies occur, or perform the test again.