HUAWEI NE40E Metro Service Platform
V800R009C10
Acceptance Test Guide
Issue   01
Date    2020-08-20
                     Huawei Proprietary and Confidential
                     Copyright © Huawei Technologies Co.,
                                    Ltd.
Copyright © Huawei Technologies Co., Ltd. 2020. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.
Trademarks and Permissions
     and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
Your purchased products, services, and features shall be restricted by Huawei commercial contract and
conditions. All or certain of products, services, or features described in this document may not be included
in what you purchased or used. Unless other statements in the contract, all statements in this document do
not constitute the warranty of any kind, express or implied.
The information in this document is subject to change without notice. Unless other statements, every effort
has been made in the preparation of this document to ensure accuracy of the contents, but all statements,
information, and recommendations in this document do not constitute the warranty of any kind, express or
implied.
Huawei Technologies Co., Ltd.
Address:           Huawei Industrial Base Bantian, Longgang, Shenzhen, People's Republic of China
                   Postal Code: 518129
Website:           http://www.huawei.com
Email:             support@huawei.com
                                      Huawei Proprietary and Confidential
                                      Copyright © Huawei Technologies Co.,
                                                     Ltd.
 HUAWEI NE40E Metro Service Platform                                                                                                               Part 1 Overview
 Acceptance Test Guide                                                                                                                                     Contents
                                                                                                                                              Contents
1 Introduction.................................................................................................................................1-1
         1.1 About This Document.....................................................................................................................................1-1
              1.1.1 Product Version.....................................................................................................................................1-1
              1.1.2 Organization..........................................................................................................................................1-1
              1.1.3 Revision History....................................................................................................................................1-1
         1.2 Definition of and Grounds for Acceptance.....................................................................................................1-2
         1.3 Acceptance Process........................................................................................................................................1-2
              1.3.1 Factory Acceptance...............................................................................................................................1-3
              1.3.2 Acceptance Upon Arrival......................................................................................................................1-3
              1.3.3 Installation Acceptance.........................................................................................................................1-4
              1.3.4 Preliminary Acceptance.........................................................................................................................1-5
              1.3.5 Trial Running.........................................................................................................................................1-5
              1.3.6 Final Acceptance...................................................................................................................................1-6
2 Preliminary Acceptance............................................................................................................2-1
         2.1 Packaging Description of Acceptance Items..................................................................................................2-1
         2.2 Principles for Using Acceptance Packages.....................................................................................................2-3
         2.3 On-site Customization of Acceptance Manual...............................................................................................2-3
              2.3.1 Quick Customization Through the Automatic Filtration Tool..............................................................2-3
              2.3.2 Manual Customization..........................................................................................................................2-3
         2.4 Numbering of Acceptance Items....................................................................................................................2-4
         2.5 Requirements for Preliminary Acceptance.....................................................................................................2-4
         2.6 Environment for Preliminary Acceptance......................................................................................................2-5
         2.7 Precautions for Preliminary Acceptance........................................................................................................2-5
                                                          Huawei Proprietary and Confidential
 Issue 01 (2020-08-20)                                    Copyright © Huawei Technologies Co.,                                                                            i
                                                                         Ltd.
HUAWEI NE40E Metro Service Platform                                                             Part 1 Overview
Acceptance Test Guide                                                                             2 Introduction
                                                                      1           Introduction
1.1 About This Document
1.1.1 Product Version
                  The product version related to this document is the HUAWEI NE8000
                  The matched NetworkManager version is the NCE-IP V100R020C00
1.1.2 Organization
                  This document describes contents related to engineering acceptance. The following table lists
                  the contents of this document.
                    Section…                Describes…
                    Part 1 Overview         The acceptance process, acceptance packages, and numbering of
                                            acceptance items. This part focuses on the methods for operating
                                            and using acceptance packages in preliminary acceptance
                    Part 2 Operation        How to test items in the basic package, extended package A, and
                    Guide                   extended package B
                    Part 3 Appendixes       The performance indexes of the product, connection diagrams used
                                            in project acceptance, recommended tools and Instruments, and the
                                            signature list cover and acceptance item list for confirmation
1.1.3 Revision History
                  Updates between document issues are cumulative. Therefore, the latest document version
                  contains all updates made to previous versions.
Document Version 01 (2020-03-20)
                  All network sub-product lines can adjust the contents and structure of this document based on
                  actual situation
                                        Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                   Copyright © Huawei Technologies Co.,                                    1
                                                       Ltd.
HUAWEI NE40E Metro Service Platform                                                               Part 1 Overview
Acceptance Test Guide                                                                               2 Introduction
1.2 Definition of and Grounds for Acceptance
                  Passing acceptance indicates success of contracted delivery.
                  Acceptance is the activity that a contractor checks the deliverables using the process, method,
                  and standards provided by a customer, to complete the contract between the two parties.
                  Acceptance is involved in the entire process from bidding based on customers' requirements,
                  to contract negotiation, to project delivery, and to contract completion. Therefore, acceptance
                  is a key milestone for ensuring contract payment.
                  Acceptance is performed based on the ITU-T Recommendations, IETF standard, national
                  standards, and the standards issued by the Information Industry Ministry, and based on the
                  actual conditions of Huawei equipment. An acceptance team composed of a customer,
                  installation personnel, and commissioning personnel perform acceptance on equipment.
                  Through acceptance, the customer confirms the receipt of the equipment that meets the
                  requirements and specified indexes.
1.3 Acceptance Process
                  Generally, the acceptance process is divided into four stages: factory acceptance, installation
                  acceptance, preliminary acceptance, and final acceptance.
                  The acceptance process involves the procedures from commissioning during production to the
                  issuance of the acceptance certificate. Following figure shows the acceptance process.
                                      Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                 Copyright © Huawei Technologies Co.,                                          2
                                                     Ltd.
HUAWEI NE40E Metro Service Platform                                                             Part 1 Overview
Acceptance Test Guide                                                                             2 Introduction
                  Figure 1-1 Process of equipment installation, commissioning, and acceptance
                           Commissioning during production
                                 Factory acceptance
                                     Shipment
                               Acceptance upon arrival
                                Equipment installation
                               Installation acceptance
                          Commissioning during deployment
                               Preliminary acceptance
                                    Trial running
                                  Final acceptance
                         Issuance of final acceptance certificate
1.3.1 Factory Acceptance
                  As required by a customer, factory acceptance is performed at the production site of
                  equipment to check whether the functions and specifications of the equipment conform to
                  those specified in a contract.
                  A factory test report is a certificate of equipment quality delivered with the equipment whose
                  functions and specifications are strictly tested by Huawei according to the requirements of the
                  quality control system.
1.3.2 Acceptance Upon Arrival
                  Generally, acceptance upon arrival consists of two stages: inspection of the packing case
                                         Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                    Copyright © Huawei Technologies Co.,                                  3
                                                        Ltd.
HUAWEI NE40E Metro Service Platform                                                                 Part 1 Overview
Acceptance Test Guide                                                                                 2 Introduction
                  quantity and inspection of the packing list.
Inspection of the Packing Case Quantity
                  Inspection of the packing case quantity refers to inspecting the delivered goods based on the
                  delivery list and BOQ in a contract. This aims to verify whether all equipment and materials
                  ordered in the contract are delivered to the delivery site specified in the contract. The
                  inspection method is to inspect whether the quantity of outer packing cases conforms to that
                  on the delivery list. If necessary, a few packing cases can be opened to inspect whether the
                  goods in the packing cases conform to that on the packing list. After the inspection,
                  representatives of a customer and Huawei sign a delivery note.
                  Generally, a contract regulates that arrival payment is received according to the delivery note.
Inspection of the Packing List
                  Inspection of the packing list refers to inspecting goods after the goods arrive at the
                  installation site, which is also called unpacking inspection. Representatives of a customer and
                  Huawei inspect the unpacked equipment and materials according to the packing list. If no
                  error is found, both parties sign on the packing list. In case of missing or damaged goods, both
                  parties need to sign a memorandum of unpacking inspection. The inspection is conducted
                  along with the project implementation. The inspection ends after the last site is installed.
                  Therefore, it is forbidden to receive payment according to the unpacking inspection.
1.3.3 Installation Acceptance
                  Installation acceptance is performed after the equipment is installed. The acceptance aims to
                  check the installation of the equipment, peripheral terminals, cable routing, grounding cables,
                  power supply, and hardware, to ensure that the installation quality meets the design
                  requirements.
                  Table 1-1 Example of signature list for installation acceptance
                   SN         Item Name            Standard and Requirement
                   1          Equipment            (1) The location for installing equipment meets the
                                                   requirements.
                                                   (2) The equipment is installed stably.
                                                   (3) The equipment is neatly arranged.
                                                   (4) Markings of equipment are in readiness.
                                                   (5) All fixtures are fastened.
                                                   (6) Exterior of the equipment is well painted.
                   2          Peripheral           (1) The location for installing NM terminals meets the
                              terminal             requirements.
                                                   (2) Configuration is in readiness.
                                                   (3) Cabinets are neatly arranged.
                                       Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                  Copyright © Huawei Technologies Co.,                                       4
                                                      Ltd.
HUAWEI NE40E Metro Service Platform                                                             Part 1 Overview
Acceptance Test Guide                                                                             2 Introduction
                   SN        Item Name           Standard and Requirement
                   3         Cable routing       (1) Routing and binding of internal fibers meet the
                                                 requirements.
                                                 (2) Routing and binding of communication cables meet the
                                                 requirements.
                                                 (3) Power wires and cables are neatly arranged.
                   4         Grounding cable     (1) The connection of the grounding cable meets standards.
                                                 (2) Routing and binding of the grounding cable meet the
                                                 requirements.
                                                 (3) The grounding resistance is smaller than 1 ohm.
                   5         Power supply        (1) Internal power cables are not grounded.
                                                 (2) Power cables are neatly routed.
                                                 (3) Connectors of DC power cables meet requirements.
                                                 (4) The insulation resistance of the DC feeder cables meets
                                                 requirements.
                   6         Hardware check      (1) Boards can be removed and inserted smoothly.
                                                 (2) Retainers of plug boards are safe and reliable.
                                                 (3) Alarm equipment meets requirements.
                                                 (4) After programs are loaded, the hardware is normal.
                   Conclusion:
                   Signatures of both parties
                   Inspection date
1.3.4 Preliminary Acceptance
                  Preliminary acceptance is performed to test the basic functions and specifications of
                  equipment and network services on site or in a central equipment room after the equipment is
                  considered deliverable for use after commissioning. This ensures that the commissioned
                  project quality meets the design requirements.
1.3.5 Trial Running
                  The operation quality of network equipment is the best criterion to inspect the equipment.
                  Therefore, faults that occur on hardware and software during trial running must be recorded,
                  to evaluate whether the performance of the network equipment is stable and reliable.
                  Generally, the trial running lasts three months.
                                      Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                 Copyright © Huawei Technologies Co.,                                       5
                                                     Ltd.
HUAWEI NE40E Metro Service Platform                                                             Part 1 Overview
Acceptance Test Guide                                                                             2 Introduction
1.3.6 Final Acceptance
                  Final acceptance is performed when the three-month trial running ends. The acceptance aims
                  to check whether the outstanding problems found in preliminary acceptance are solved and
                  whether new problems occur during the trial running. If the equipment fails to pass the final
                  acceptance, an agreement of extending the trial running period should be reached by both
                  parties, and the final acceptance should be performed again when the extended trial running
                  period ends. If the equipment passes the final acceptance, the final acceptance report should
                  be filled out and the acceptance certificate should be issued. After the final acceptance, the
                  equipment is put into normal operation.
                                      Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                 Copyright © Huawei Technologies Co.,                                     6
                                                     Ltd.
HUAWEI NE40E Metro Service Platform                                                              Part 1 Overview
Acceptance Test Guide                                                                   2 Preliminary Acceptance
                                          2            Preliminary Acceptance
2.1 Packaging Description of Acceptance Items
                  Based on features of network products, acceptance items are classified into three packages.
                  Following table lists the packaging principles and package selection priorities.
                  Table 1-2 Packaging description of acceptance items
                    Type of               Packaging Principle                Priority of           Business
                    Acceptance Item                                          Selecting Items       Strategy
                    Package
                    Basic package         The basic package contains the        Remote            The price of
                                          items that can be accepted             acceptance        the basic
                                          remotely through simple or            Simple or         package is
                                          cheap meters. The items in the         cheap meters      included in
                                          basic package are used to                                the quotation
                                          ensure normal running of the
                                                                                Ensuring basic    of
                                          basic services and functions of        services and      engineering
                                          the equipment and network.             functions         services.
                    Extended package A    Extended package A contains           Acceptance at a   The items in
                                          the items that can be accepted         single site       extended
                                          at a single site through simple       Simple or         package A
                                          or cheap meters. The items in          cheap meters      are test
                                          extended package A are used                              services.
                                          to ensure normal running of
                                                                                Ensuring basic    Therefore, the
                                          the basic services and                 services and      price of
                                          functions of the equipment and         functions         extended
                                          network.                                                 package A
                                                                                                   must be
                                                                                                   quoted
                                                                                                   independently
                                                                                                   based on the
                                                                                                   requirements
                                                                                                   for work
                                                                                                   hours and
                                                                                                   meters.
                                      Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                 Copyright © Huawei Technologies Co.,                                         1
                                                     Ltd.
HUAWEI NE40E Metro Service Platform                                                                Part 1 Overview
Acceptance Test Guide                                                                     2 Preliminary Acceptance
                    Type of                Packaging Principle                Priority of           Business
                    Acceptance Item                                           Selecting Items       Strategy
                    Package
                    Extended package B     Extended package B contains           Ensuring basic    The items in
                                           time-consuming and                     services and      extended
                                           complicated items or items             functions         package B are
                                           that must be tested through           Expensive         test services.
                                           complicated or expensive               meters            Therefore, the
                                           meters. Based on additional                              price of
                                           requirements of customers,
                                                                                 Remote            extended
                                           items in extended package B            acceptance or     package B
                                           can be selected to ensure              acceptance at a   must be
                                           normal running of the basic            single site       quoted
                                           services and functions of the                            independently
                                           equipment and network.                                   based on the
                                                                                                    requirements
                                                                                                    for work
                                                                                                    hours and
                                                                                                    meters.
Basic Package
                  Items in the basic package are used to test the quality of manual commissioning part at project
                  delivery, and are accepted remotely through the network management system (NMS) or
                  central equipment room. Items in the basic package include power commissioning and
                  control, normal running of various hardware and software functions, and BER tests on end-to-
                  end services. The acceptance of these items ensures the quality and availability of the network
                  that is delivered to a customer.
Extended Packages A and B
                  Extended packages A and B are used to test hardware or function indexes. The acceptance of
                  the items in the two packages requires expensive meters or is performed on site. Therefore,
                  extended packages A and B are charged as services. Most items in extended packages A and B
                  are controlled through the production quality control system and factory acceptance during
                  production. The tested indexes cannot be controlled or adjusted manually during on-site
                  commissioning.
                  Therefore, it is not recommended to perform on-site tests on the items in extended packages A
                  and B. If a customer strongly requires that the items should be tested on site, you can do as
                  follows:
                       Help the customer to recognize Huawei's quality control system and after-sales service.
                       Provide the customer with the factory acceptance report and entry test report on these
                        items.
                       Recommend the customer to accept these items independently.
                       Recommend the customer to pay for the on-site acceptance of these items.
                                       Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                  Copyright © Huawei Technologies Co.,                                       2
                                                      Ltd.
HUAWEI NE40E Metro Service Platform                                                               Part 1 Overview
Acceptance Test Guide                                                                    2 Preliminary Acceptance
2.2 Principles for Using Acceptance Packages
                  The principles for using the acceptance packages are as follows:
                       When selecting acceptance items, select fewer items from the basic package in priority,
                        thus ensuring that the items pass the acceptance quickly and the network and services are
                        basically available.
                       If a customer strongly requires that items other than items in the basic package be tested,
                        help the customer to recognize the quality control system and after-sales service, provide
                        the customer with the factory report and entry test report on these items, or recommend
                        the customer to accept the additional items independently.
                       If the preceding recommendations cannot meet the customer's requirement, select fewer
                        items from extended packages A and B and recommend the customer to pay for the work
                        hours for accepting these items and usage of meters.
                       If the customer refuses to pay for the acceptance of the additional items, present the
                        acceptance items based on actual conditions.
                  Engineers are recommended to fully understand the significance and methods of acceptance
                  and the functions of all acceptance items. To deliver projects with high efficiency and high
                  quality, engineers need to fully communicate with customers and prepare proper acceptance
                  standards based on this document.
2.3 On-site Customization of Acceptance Manual
                  On-site engineers may customize acceptance manuals through tools or manually.
2.3.1 Quick Customization Through the Automatic Filtration Tool
Prerequisite
                  On-site engineers have the tool that can be used to filtrate or select acceptance items
                  automatically.
Function
                  The auto selection tool can be used to automatically generate operation guide (typeset
                  acceptance items), customer signature list, meter list, and acceptance and work hour list. If a
                  customer is not satisfied with the result, engineers can adjust (delete or add) the items quickly
                  and repeatedly through the tool.
Method for Customization
                  See the Acceptance Test assistant Tool.
2.3.2 Manual Customization
Prerequisite
                  On-site engineers do not have the tool for filtrating acceptance items automatically; or it is
                  easy and quick to select acceptance items manually.
                                       Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                  Copyright © Huawei Technologies Co.,                                        3
                                                      Ltd.
HUAWEI NE40E Metro Service Platform                                                             Part 1 Overview
Acceptance Test Guide                                                                  2 Preliminary Acceptance
Method for Customization
                  The method for manual customization is the same as the traditional method for manual
                  editing. That is, select acceptance items from the acceptance packages, manually copy and
                  paste the acceptance items to a destination document, renumber and typeset the acceptance
                  items in the destination document, and then prepare the corresponding customer signature list,
                  meter list, and acceptance work hour list. For the customer signature list, see the Acceptance
                  Items and Tables in part 3 Appendixes.
2.4 Numbering of Acceptance Items
                  For easy management and search, all acceptance items are numbered. The following describes
                  the numbering plan:
                  Numbering plan:
                       If only a few acceptance items are used, a four-digit numbering template can be used. If
                        many acceptance items are used, a six-digit numbering template can be used to arrange
                        the acceptance items in multi-level contents, for example, a template for the NMS. Only
                        one template can be used in the same manual. Unused templates must be deleted.
                  The format of four-digit numbers is Txx-xx.
                  The meaning of the numbers is as follows:
                   Txx-xx
                            Number of an acceptance sub-item
                            Number of an acceptance type
                  The format of six-digit numbers is Txx-xxxx.
                  The meaning of the numbers is as follows:
                   Txx-xxxx
                                Number of an acceptance sub-item
                                Number of an acceptance item
                                Number of an acceptance type
2.5 Requirements for Preliminary Acceptance
                  Preliminary acceptance is performed after the installation process and equipment appearance
                  is checked and system commissioning is performed.
                                        Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                   Copyright © Huawei Technologies Co.,                                   4
                                                       Ltd.
HUAWEI NE40E Metro Service Platform                                                                Part 1 Overview
Acceptance Test Guide                                                                     2 Preliminary Acceptance
                  The preliminary acceptance should be performed based on the plan and acceptance items in
                  this document. An application for preliminary acceptance must be submitted before the
                  preliminary acceptance.
                  If any item does not pass the preliminary acceptance, the item must be commissioned based
                  on actual conditions.
                  The final result of the preliminary acceptance must conform to the standard provided by a
                  customer. Both parties need to sign on the signature list of the acceptance items.
2.6 Environment for Preliminary Acceptance
                  Generally, preliminary acceptance is performed remotely. The environment and preset
                  conditions must be prepared based on the required meters and other requirements to ensure
                  smooth acceptance of all items.
2.7 Precautions for Preliminary Acceptance
                  Before the test, make sure that the required test cables are available, that the connector type is
                  adaptable for the test meters, and that the connector is properly connected to the test meters.
                  Prepare fiber cleaning box to clean connectors during the test of optical interface
                  characteristics, to ensure the accuracy of test data.
                  Do not look directly into the optical interface during the test, to prevent the laser beam from
                  damaging your eyes.
                  In the 24-hour BER test, ensure that the test is free from interference (including artificial
                  factors and power failure) during the entire test process. If anomalies occur, record the
                  accurate time when the anomalies occur, or perform the test again.
                                       Huawei Proprietary and Confidential
Issue 01 (2020-08-20)                  Copyright © Huawei Technologies Co.,                                         5
                                                      Ltd.