Sprint Start Date                      Days         Progress
Kanban Board                                                       12/4/2017                            14           43.5%                 ⚑⚑⚑⚑⚑⚑⚐⚐⚐⚐⚐⚐⚐⚐⌛🏁
     Type     Who / Role [1]        Feature or Activity                   Reason                       Priority    Pts [2]       Hrs [3]                                Details
     😴         Backlog
                                                          The backlog is where you stick the to-dos                                        Some ideas may not lead to deliverables, but time may need to
Research            All       Add ideas to the backlog                                                  Low          2
                                                          that you might work on later.                                                    be allocated to researching them.
                                                          User Story: As a [Role] I want [Feature]
    Feature                   Be specific                                                               High         6
                                                          so that [Reason]
                              Articles, White Papers,                                                                                      We use the Content type for writing blog posts, preparing
    Content                                                                                            Medium        3
                              Documentation                                                                                                marketing materials, and support content.
^               Hide backlog items above this row
                                                                                                                                                                                                            ^
                                                                                                                                                                                                                {42}
     😐         To Do                                                                                                6.5           0.0
                              Customize Headings and      Edit the Legend in the Type column as                                            Look at the conditional formatting rules to see how the color-
    Update                                                                                              Low         0.5
                              Card Types                  needed.                                                                          coding works.
                                                          To decide what you are going to work on
     Task           All       Move Backlog cards here                                                                3
                                                          during this sprint.
                              Decide how much we can      The total estimated Pts cannot be higher
     Task           All                                                                                              3
                              get done                    than X, based on past performance.
     😃         In Progress                                                                                          0.0           0.0
                              Move tasks between lanes Google Sheets: select the row # and
    Update          All
                              to track completion      drag it with the hand cursor.
     😅         Test / Verify                                                                                        0.0           0.0                                                    © 2017 Vertex42.com
                                                          Take joy in accomplishment, Don't be                                             Make sure that challenges are worth trying to overcome, so that
    Update                    Test and Refine             afraid to scrap what isn't working.                                              you don't waste time on useless stuff.
     Task           All       Is the Process Helping?     Don't add unnecessary work.
     😎         Done                                                                                                  5             0
                                                          Moving stuff to DONE deserves a high
     Task           All       Congratulations                                                           High         5
                                                          five or fist bump.
               Total This Sprint                                                                                   11.5           0.0
 TYPE                               SPRINT CHART
                                                                                                      PRIORITY LEGEND
LEGEND                                LEGEND                                                                                                         Kanban Board Template © 2017 Vertex42.com
                                                                                                                                        https://www.vertex42.com/ExcelTemplates/agile-kanban-board.html
    Feature                    ⚐ days in sprint                                                         High
    Content                    ⚑ progress                                                              Medium
    Update                     ⌛ current day                                                            Low
                                                                                                                          [42]
     Task                      🏁 finish / end
Research
                                                                                                      PROGRESS CALCULATIONS
                                                                                                       Progress: 43.48% ⚑⚑⚑⚑⚑⚑⚐⚐⚐⚐⚐⚐⚐⚐⌛🏁
                                                                                                      Complete:       6
                                                                                                           Time:     14
Summary
 Who / Role   Pts (Not Done)   Pts (Done)
     All            6              5
  Name 1            0              0
  Name 2            0              0
  Name 3            0              0
  Name 4            0              0
  Name 5            0              0
  Name 6            0              0
  Name 7            0              0
                    0              0
                    0              0
                    0              0
                    0              0
                    0              0
Sprint Record Book
Sprint Start Date   Sprint Days   Pts Planned   Pts Done   Velocity   Most Notable Achievements
   11/27/2017           8             48          24          3
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
                                                              -
HELP                                                                                        © 2017 Vertex42.com
https://www.vertex42.com/ExcelTemplates/agile-kanban-board.html
Copyright & Terms of Use (Limited Private Sharing)
          This spreadsheet, including all worksheets and associated content is copyrighted. Do not submit
          copies or modifications of this template to any website or online template gallery. Please review the
          following license agreement to learn how you may or may not use this template. Thank you.
          License Agreement
          https://www.vertex42.com/licensing/EULA_privateuse.html
About This Template
          This worksheet was designed as an online collaborative Kanban board for use in Agile Project
          Management where the team members may be working remotely. Instead of columns for Backlog,
          To Do, In Progress, Testing, and Done, the spreadsheet uses horizontal lanes. Rows within the
          worksheet represent cards or sticky notes. Create new "cards" by inserting rows. Move cards
          between lanes by dragging and dropping the entire row.
          Create New Cards / Tasks
          Just insert a new row below or above an existing card or task. Note: In Google Sheets, when you
          insert a row above or below the selected line, the formatting in the newly inserted row is based on
          the row you have selected.
          Move Cards to new Lanes
          Select the row, then drag and drop the row by dragging the row number (the row number on the far
          left of the spreadsheet).
          Show/Hide rows
          You'll probably want to show/hide the rows in the Backlog. You can do that by just selecting the
          rows, right-clicking on the row numbers, and selecting Hide Rows. Google Sheets will display
          up/down arrows when rows are hidden, so to show them, click on the arrows.
          Sprint Progress Chart
          The progress bar at the top of the worksheet is called a "sprint progress chart" and represents the
          number of days in the sprint. Filled-in flags represent the progress in terms of % complete and the
          hourglass shows what day it is.
          Summary Worksheet
          The Summary worksheet tab can be used for (1) editing the list of names or roles that show up in
          the drop-down data validation lists and (2) summarizing the number of points currently assigned to
          each person or role.
After Each Sprint
          1) Update the RecordBook worksheet with the results of the sprint.
          2) Create a copy of this spreadsheet and rename the copy based on the date of the sprint (e.g.
          "Sprint - 2017 11 27") and store the copy in an archived folder. You could duplicate the Kanban
          worksheet instead and rename the duplicate to store previous sprints within the same workbook.
          3) Begin a new sprint by removing the tasks in the Done section and adding, moving and
          reprioritizing the tasks that you will focus on for the next sprint.
IMPORTANT note about File Sharing via Google Sheets
          When sharing the spreadsheet with somebody else, share it with a specific email address only (i.e.
          an email associated with a Google Account). Using the "Public on the web" or "Anyone with the link"
          option can comprise the security of your information and will also be a violation of the terms of use
          for this template.
          Do not use the "Public on the Web" option
          Do not use the "Anyone with the link" option
Like this Template?
          Share the following link to vertex42.com via email, facebook, linkedin, etc. You may share this
          spreadsheet among your team members and management, but to recommend the template to
          people outside your company, please only share the link to vertex42.com, not the actual
          spreadsheet. Thank you!
          https://www.vertex42.com/ExcelTemplates/agile-kanban-board.html
[1] This can be a person responsible for the task or the role for describing the user story.
USER STORY: As a [role], I want [feature] so that [reason].
[2] Estimated Effort Points:
Enter the estimated effort, in terms of points or hours, that you have budgeted or allocated to this task.
[3] Actual Hours:
You can use this column to keep track of the actual time spent on a task.