TABLE OF CONTENTS
22KC0001 CONTRACTUAL DATA
(Rehabilitation/ Reconstruction of National Roads with Slips, Slope
Collapse and Landslide along Sayre Highway K1459+735 - K1459+798)
Contract Amount: 3,818,382.02
Effectivity Date: February 10, 2022
Calendar Days: 96
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: May 16, 2022
DPWH Project Engineer: Orlando V. Mancao Jr.-PE I (4372)
DPWH Materials Engineer: Khem M. Oche-ME II (D2-00114)
MMEI Bid Project Engineer Noelleen R. Frias
MMEI Project Engineer: Crisanto Egargin
MMEI Materials Engineer: Marilie A. Magahud-ME I (6737)
A Quality Control Program
B Monthly Materials Progress Report
C Sample Cards
D DPWH/3RD Party Test Results
E Laboratory Test Results
F Concrete Mix Design
G Accreditation of Materials Engineer
H Transmittals
TABLE OF CONTENTS
22KC0004 CONTRACTUAL DATA
(Preventive Maintenance along Sayre Highway K1470+026 - K1470+920)
Contract Amount: 31,358,938.23
Effectivity Date: March 15, 2022
Calendar Days: 102
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: June 24, 2022
DPWH Project Engineer: Erna Lou B. Amores - PE I
DPWH Materials Engineer: Loreto L. Mahilum-ME II (D2-00556)
MMEI Bid Project Engineer Nessan Apilan
MMEI Project Engineer: Lea Jean Achacoso
MMEI Materials Engineer: Marilie A. Magahud-ME I (6737)
A Quality Control Program
B Monthly Materials Progress Report
C Sample Cards
D DPWH/3RD Party Test Results
E Laboratory Test Results
F Concrete Mix Design
G Accreditation of Materials Engineer
H Transmittals
TABLE OF CONTENTS
22KC00013 CONTRACTUAL DATA
(Road Widening along Kibawe-Kadingilan-Kalilangan Rd. K1611+895 - K1612+944)
Contract Amount: 46,397,780.05
Effectivity Date: February 10, 2022
Calendar Days: 268
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: November 4, 2022
DPWH Project Engineer: Ramil Giovanni T. Kintanar - PE III (4077)
DPWH Materials Engineer: Intan O. Carim - ME II (D2-00705)
MMEI Bid Project Engineer Irve C. Licardo
MMEI Project Engineer: Sunshine Binahon
MMEI Materials Engineer: Kezia B. Lasquite (4193)
A Quality Control Program
B Monthly Materials Progress Report
C Sample Cards
D DPWH/3RD Party Test Results
E Laboratory Test Results
F Concrete Mix Design
G Accreditation of Materials Engineer
H Transmittals
TABLE OF CONTENTS
22KC00014 CONTRACTUAL DATA
(Road Widening along Sayre Highway K1447+900 - K1449+420)
Contract Amount: 84,354,363.58
Effectivity Date: March 3, 2022
Calendar Days: 336
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: February 1, 2023
DPWH Project Engineer: Bernard D. Apolinario - PE 1 (5730)
DPWH Materials Engineer: Khem M. Oche - ME II (D2-00114)
MMEI Bid Project Engineer Ian Butch M. Tipan
MMEI Project Engineer: Crisanto Egargin
MMEI Materials Engineer: Kathlyn Elizabeth A. Chan (6896)
I Quality Control Program
J Monthly Materials Progress Report
K Sample Cards
L DPWH/3RD Party Test Results
M Laboratory Test Results
N Concrete Mix Design
O Accreditation of Materials Engineer
P Transmittals
TABLE OF CONTENTS
22KC0035 CONTRACTUAL DATA
(Widening of Permanent Bridge Nabaliwa Br. (B01089MN) along Barandias-
Dominorog Road)
Contract Amount: 23,549,944.60
Effectivity Date: March 15, 2022
Calendar Days: 296
Revised CD no. 1: _____
Revised CD no. 2: _____
Original Expiry Date: January 4, 2023
DPWH Project Engineer: Michael J. Doligol - JPE (5749)
DPWH Materials Engineer: Helen H. Moneva - ME I (D1-00768)
MMEI Bid Project Engineer Kristel Mae C. Cadungon
MMEI Project Engineer: Nelda Simudlan
MMEI Materials Engineer: Excellee Joy N. Caseres (6890)
A Quality Control Program
B Monthly Materials Progress Report
C Sample Cards
D DPWH/3RD Party Test Results
E Laboratory Test Results
F Concrete Mix Design
G Accreditation of Materials Engineer
H Transmittals
TABLE OF CONTENTS
22KC0036 CONTRACTUAL DATA
(Construction of Flood Control Structure along Maramag-Maradugao Rd
(Downstream), Macapantig Bridge with Slope Protection)
Contract Amount: 39,004,699.96
Effectivity Date: February 21, 2022
Calendar Days: 262
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: November 9, 2022
DPWH Project Engineer: Ramil Giovanni T. Kintanar - PE III (4077)
DPWH Materials Engineer: Helen H. Moneva - ME I (D1-00768)
MMEI Bid Project Engineer Ronald Peñas
MMEI Project Engineer: James Peter Olinan
MMEI Materials Engineer: Lloyd B. Banzon (1916)
I Quality Control Program
J Monthly Materials Progress Report
K Sample Cards
L DPWH/3RD Party Test Results
M Laboratory Test Results
N Concrete Mix Design
O Accreditation of Materials Engineer
P Transmittals
TABLE OF CONTENTS
22KC0049 CONTRACTUAL DATA
(Preventive Maintenance of Road; Asphalt Overlay along Sayre Highway
K1446+154 - K1447+652)
Contract Amount: 49,897,148.23
Effectivity Date: March 21, 2022
Calendar Days: 132
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: July 30, 2022
DPWH Project Engineer: Orlando V. Mancao Jr. - PE I (4372)
DPWH Materials Engineer: Khem M. Oche - ME II (D2-00114)
MMEI Bid Project Engineer Willah Mae V. Saligumba
MMEI Project Engineer: Lea Jean Achacoso
MMEI Materials Engineer: Ronald C. Bongocan (0418)
Q Quality Control Program
R Monthly Materials Progress Report
S Sample Cards
T DPWH/3RD Party Test Results
U Laboratory Test Results
V Concrete Mix Design
W Accreditation of Materials Engineer
X Transmittals
TABLE OF CONTENTS
22KC0050 CONTRACTUAL DATA
(Preventive Maintenance of Road; Asphalt Overlay Along Sayre Highway
K1472+388 - K1474+090)
Contract Amount: 56,156,516.90
Effectivity Date: March 21, 2022
Calendar Days: 138
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: August 5, 2022
DPWH Project Engineer: Erna Lou B. Amores - PE I
DPWH Materials Engineer: Loreto L. Mahilum - ME II (D2-00556)
MMEI Bid Project Engineer Leonardo G. Paulican
MMEI Project Engineer: Lea Jean Achacoso
MMEI Materials Engineer: Myrna M. Valenzuela (5323)
I Quality Control Program
J Monthly Materials Progress Report
K Sample Cards
L DPWH/3RD Party Test Results
M Laboratory Test Results
N Concrete Mix Design
O Accreditation of Materials Engineer
P Transmittals
TABLE OF CONTENTS
22KC0056 CONTRACTUAL DATA
(Widening of Permanent Bridge - Huwagon Br. (B01092MN) along Barandias -
Dominorog Rd.)
Contract Amount: 21,713,054.85
Effectivity Date: February 21, 2022
Calendar Days: 295
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: December 12, 2022
DPWH Project Engineer: Michael J. Doligol - JPE (5749)
DPWH Materials Engineer: Helen H. Moneva - ME I (D1-00768)
MMEI Bid Project Engineer Marjorie R. Dacut
MMEI Project Engineer: Nelda Simudlan
MMEI Materials Engineer: Lloyd B. Banzon (1916)
Q Quality Control Program
R Monthly Materials Progress Report
S Sample Cards
T DPWH/3RD Party Test Results
U Laboratory Test Results
V Concrete Mix Design
W Accreditation of Materials Engineer
X Transmittals
TABLE OF CONTENTS
22KC0008 CONTRACTUAL DATA
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Sayre
Highway K1456+688 – K1457+363, K1458+305 – K1458+686, K1463+689 – K1463+794
Contract Amount: 23, 285, 404.44
Effectivity Date: April 11, 2022
Calendar Days: 198
Revised CD no. 1: ______
Revised CD no. 2: ______
Original Expiry Date: October 25, 2022
DPWH Project Engineer: Orlando V. Mancao Jr. - PE I (4372)
DPWH Materials Engineer: Khem M. Oche - ME II (D2-00114)
MMEI Bid Project Engineer Ofelia A. Adlaon
MMEI Project Engineer: John Michael Montecalvo
MMEI Materials Engineer: Odessa Jed Dag-o (6915)
A Quality Control Program
B Monthly Materials Progress Report
C Sample Cards
D DPWH/3RD Party Test Results
E Laboratory Test Results
F Concrete Mix Design/ Job Mix Design
G Accreditation of Materials Engineer
H Transmittals
A I Q A I Q A I Q
B J R B J R B J R
C K S C K S C K S
D L T D L T D L T
E M U E M U E M U
F N V F N V F N V
G O W G O W G O W
H P X H P X H P X
A I Q A I Q A I Q
B J R B J R B J R
C K S C K S C K S
D L T D L T D L T
E M U E M U E M U
F N V F N V F N V
G O W G O W G O W
22KC0008
22KC0004
22KC0013
22KC0014
22KC0035
22KC0036
22KC0049
22KC0050
22KC0056
H P X H P X H P X