Flood Engineering
Flood Engineering
Prepared for:
Prepared by:
Woidt Engineering & Consulting, PC
11 South Washington Street
Binghamton, New York 13903
Dear Reader,
On June 10, 2014 the Olive Town Board established the Flood Advisory Committee (FAC) to produce a
Flood Mitigation Plan for the Town. A first step in recommending priority strategies and actions for Olive
was to conduct Local Flood Analysis, which was made possible with funding from the Ashokan Watershed
Stream Management Program.
To that end, the Committee followed several key values while finding solutions to reduce or remove flood
hazards. Solutions must be:
cost‐effective for the Town to build and to maintain
cost‐effective for individuals and businesses directly involved
maintain, as much as possible, the sense of community and the "flavor" of our business and
residential areas
reviewed in public meetings and be accepted by the community as realistic and desirable
thoroughly researched and analyzed with proper engineering methods and professional expertise
implemented with care and economy by professionals experienced in flood hazard mitigation
following permitted town‐approved plans
protect our natural resources, especially the streams and wildlife.
Best Regards,
The Town Of Olive Flood Advisory Committee
Table of Contents
1.0 Executive Summary ........................................................................................................................... 5
2.0 Statement of Purpose and Scope ..................................................................................................... 6
3.0 Local Flood Analysis Methodology Summary ................................................................................... 9
3.1 Data Gap Analysis Summary and Purpose ...................................................................................... 10
3.2 Data Gap Analysis Approach ........................................................................................................... 10
3.3 Data Gap Analysis Results: Boiceville Study Area .......................................................................... 14
3.3.1 Rapid Geomorphic Assessment ................................................................................................. 14
3.3.2 Esopus Creek Stream Feature Inventory (SFI) Review ............................................................... 16
3.3.3 Public Flooding Hazards and FAC Flooding Hazards .................................................................. 17
3.3.4 Hydraulic and Hydrologic Model Review: Hydrology ............................................................... 17
3.3.5 Hydraulic and Hydrologic Model Review: Hydraulics ............................................................... 19
3.3.6 Preliminary Water Depth Maps ................................................................................................. 22
3.3.7 Water Quality Assessment Data Review .................................................................................... 23
3.3.8 Identified Data Gaps and Proposed Field Methodology ............................................................ 24
3.4 Data Gap Analysis Results: West Shokan Study Area...................................................................... 25
3.4.1 Rapid Geomorphic Assessment ................................................................................................. 25
3.4.2 Bushkill Stream Feature Inventory Review ................................................................................ 26
3.4.3 Public Flooding Hazards and FAC Flooding Hazards .................................................................. 27
3.4.4 Hydraulic and Hydrologic Model Review: Hydrology ............................................................... 27
3.4.5 Hydraulic and Hydrologic Model Review: Hydraulics ............................................................... 29
3.4.6 Preliminary Water Depth Maps ................................................................................................ 30
3.4.7 Identified Data Gaps and Proposed Field Methodology ........................................................... 31
4.0 Boiceville Study Area....................................................................................................................... 34
4.1 Watershed Characteristics that Impact Flooding Hazards .................................................................. 34
4.1.1 Topography and Climate ........................................................................................................... 34
4.1.2 Surficial Geology........................................................................................................................ 34
4.1.3 Anthropogenic........................................................................................................................... 34
4.1.4 Flooding History ........................................................................................................................ 35
4.1.5 Floodplain Development Ordinance and Related Town Planning Documents. ........................ 35
4.2 Boiceville Study Area Local Flood Analysis Summary ...................................................................... 36
2
4.3 Boiceville Mitigation Area Summary ................................................................................................ 36
4.3.1 Hydraulic Approach ................................................................................................................... 36
4.3.2 Existing Hydraulic Conditions and Water Depths ..................................................................... 37
4.3.3 Flood Hazard Mitigation Solution Summary: ............................................................................ 37
4.3.4 Plan #4 - Floodplain Benches Only ............................................................................................ 41
4.3.5 Plan #5 - Floodplain Benches and Flood Levee System ............................................................ 44
4.3.6 Plan #7-Floodplain Benches and Relocation of Route 28A Bridge............................................ 49
4.3.7 Plan #9 - Flood Levee System Only ........................................................................................... 52
4.3.7 Plan #9A - Flood Levee System Only ......................................................................................... 57
4.3.8 Plan #10 - Dredging ................................................................................................................... 62
4.3.9 Plan #11 - Relocate Route 28A Bridge and Waste Water Facility. ............................................ 65
4.3.10 Plan #12 - Planning and Relocation......................................................................................... 68
4.3.11 Plan #13 - Structural Interventions (Property Protection) ...................................................... 71
4.4 Upper Boiceville Road Mitigation Area Summary............................................................................ 73
4.4.1 Hydraulic Approach ................................................................................................................... 74
4.4.2 Existing Hydraulic Conditions and General Site Conditions ...................................................... 74
4.4.3 Plan #14 - Three Sided Box Culvert ........................................................................................... 76
4.5 DeSilva Road Mitigation Area Summary .......................................................................................... 79
4.5.1 Hydraulic Approach ................................................................................................................... 80
4.5.2 Existing Hydraulic Conditions and General Site Conditions ...................................................... 80
4.5.3 Plan #15 - Wider Clear Span Three Sided Box Culvert .............................................................. 82
4.6 State Route 28 Ponding Mitigation Area Summary ......................................................................... 85
4.6.1 Hydraulic Approach ................................................................................................................... 86
4.6.2 Existing Hydraulic Conditions and General Site Conditions ...................................................... 87
5.0 West Shokan Study Area ................................................................................................................. 89
5.1 Watershed Characteristics that Impact Flooding Hazards. .............................................................. 89
5.1.1 Topography and Climate ........................................................................................................... 89
5.1.2 Surficial Geology........................................................................................................................ 89
5.1.3 Anthropogenic........................................................................................................................... 90
5.1.4 Flooding History. ....................................................................................................................... 91
5.1.5 Floodplain Development Ordinance and Related Town Planning Documents ......................... 92
5.2 West Shokan Study Area Local Flood Analysis Summary ................................................................ 92
5.3 Bushkill Mitigation Area Summary ................................................................................................... 93
3
5.3.1 Hydraulic Approach ................................................................................................................... 93
5.3.2 Existing Hydraulic Conditions and Water Depths ...................................................................... 94
5.3.3 Flood Hazard #2 - Watson Hollow Bridge ................................................................................. 95
5.3.4 Flood Hazard #5 - Homes Along Watson Hollow Road ............................................................. 98
5.3.5 Flood Hazard #3 and #1: Man-made Levee and Erosion Hazards to Watson Hollow Road .. 101
5.3.6 Flood Hazard #4 - Erosive Damage to Route 28A Southern Approach ................................... 105
5.3.7 Plan #5 - Bushkill Debris Removal ........................................................................................... 108
5.4 Dry Brook Mitigation Area Summary ............................................................................................. 109
5.4.1 Hydraulic Approach ................................................................................................................. 109
5.4.2 Existing Hydraulic Conditions and Water Depths .................................................................... 109
5.4.3 Plan #16 - Burgher Road Crossing ........................................................................................... 110
5.5 Maltby Hollow Mitigation Area Summary ..................................................................................... 114
5.5.1 Hydraulic Approach ................................................................................................................. 114
5.5.2 Existing Hydraulic Conditions and Water Depths .................................................................... 116
5.5.3 Flood Hazard Mitigation Solution Summary: Plan #17-Maltby Hollow Crossing ................... 118
5.5.4 Plan #2 - Maltby Hollow Debris Removal ................................................................................ 122
6.0 Summary and Recommendations ................................................................................................. 123
6.1 Summary ........................................................................................................................................ 123
6.2 Recommendations .......................................................................................................................... 125
7.0 Local Flood Mitigation Implementation Strategy ............................................................................ 130
8.0 References .................................................................................................................................... 132
9.0 Acronyms ...................................................................................................................................... 133
4
1.0 Executive Summary
The Town of Olive has experienced three 3 major flooding events within the last twenty years, the most
severe and recent being Hurricane Irene in 2011. These floods have caused significant property loss and
severely disrupted community life. This Local Flood Analysis report is the first step in identifying what
could be done to reduce or remove causes of flooding and calculate a general cost of the most
acceptable solutions. It will be used to inform the residents of the Town of Olive, to guide decision-
making by the town, and to provide essential data for projects in the future.
The audience for this analysis includes officials of the Town of Olive, future consultants, future funding
agencies, contractors for mitigation projects, and the residents of the town.
The expected outcome of the Town of Olive’s Local Flood Analysis (LFA) is an understanding of flooding
hazards within the Town’s population centers of Boiceville and West Shokan and to identify the highest
priority flood mitigation solutions for these hazards. This understanding is captured in the Local Flood
Analysis report (LFA) and the solutions presented in the LFA were driven by the Town’s Flood Advisory
Committee’s (FAC) decisions on recommendations developed using engineering and geomorphic
technical analyses. These solutions were then vetted by the FAC, the Town Board and the community
using each solution’s benefit to cost ratio, impact to the community’s character, influence on existing
and future economic opportunities and public safety as prioritization metrics.
The LFA is a standalone report that summarizes all of the work undertaken to identify and prioritize
flood mitigation solutions as part of the Town’s LFA. The community will use the LFA to select the
mitigation solutions that will be implemented and identify strategies to move these solutions forward
(funding, planning documents, etc.)
The Boiceville Study Area and West Shokan Study Area were the two areas within the Town of Olive that
were studied in the LFA and in these two study areas, a total of sixteen (16) flooding hazards were
characterized and thirteen (13) mitigation solutions were developed.
In the Boiceville Study Area, seventeen (17) buildings are prone to flooding at moderately occurring
flood events (25-year return interval flood). Various mitigation scenarios were evaluated with the
proposed three arch Route 28A bridge in place to protect these buildings. The community must decide
if: they want to do nothing, protect their community in place or begin moving buildings out of flood
prone area. The “do nothing approach” leaves these buildings exposed to future flooding and high flood
insurance premiums which suppress the building’s property values. Protecting the buildings in place will
require significant annual costs to be paid by the Town. Relocating buildings out of the flood prone area
will change the character of Boiceville. In the West Shokan Study Area, no flood inundation hazards
were found under clear water conditions (i.e. no obstructions) or during obstructed conditions.
However, there are several locations where erosion hazards will lead to significant road and bridge
closures and major impediments to emergency response times. The erosion hazard condition at the
Watson Hollow Bridge should be addressed immediately as well as the failing road embankment along
Watson Hollow Road downstream of the bridge. Permanent monitoring stations are recommended to
be established at areas sensitive to obstructions that could exacerbate existing erosive conditions.
5
2.0 Statement of Purpose and Scope
Major floods have become more frequent, and government resources for recovery have decreased.
These floods have caused significant property loss and severely disrupted community life. While a single
property owner cannot take on the tasks necessary to reduce or remove flood hazards of this
magnitude, the Town can.
The two study areas for the Town of Olive’s LFA are in the Boiceville hamlet (referred to as the Boiceville
Study Area) and the second area in the West Shokan hamlet (referred to as the West Shokan Study
Area). The Boiceville Study Area extends from the Town Boundary to approximately 2.3 river miles
downstream on Esopus Creek, which is approximately 1.2 miles downstream of the Route 28A Bridge
near the Esopus-Ashokan Reservoir confluence.
6
7
The West Shokan Study Area extends approximately 1.2 miles upstream of the Bushkill-Ashokan Reservoir confluence to the confluence with
Maltby Hollow Brook on the Bushkill, and on Dry Brook, from its confluence with the Bushkill to approximately 0.7 miles upstream of the
confluence.
8
Both study areas are located within the New York City Department of Environmental Protection (DEP)
Ashokan Reservoir’s watershed. Since DEP provides drinking water to New York City, the incoming
water quality to the Ashokan Reservoir is an important management strategy. Both study areas are
located in an area with a town-adopted Stream Management Plan (SMP) (CCEUC 2007). The SMP is a
managerial document that guides water quality preservation and enhancement. There are five long
term goals of an SMP: Flooding and Erosion, Water Quality, Aquatic Ecology, Recreation and
Management Coordination). The SMP includes a physical assessment to provide a baseline
characterization of the watershed which will inform improvements of these goal areas. The LFA utilized
the SMP’s data and management strategies while developing LFA solutions to ensure continuity
between the two management plans.
Flood hazard mitigation strategies for the Town of Olive were developed from an adapted methodology
presented in the Local Flood Analysis’s Scope of Work. This protocol included collecting existing
electronic and hard copy data from town, county, state and federal governments to characterize the
causes of flooding in the Town. If this information was insufficient, then a Data Gap Analysis was
completed that provided recommendations of what and how additional information should be collected
in order to explain the Town's flooding hazards. These recommendations were presented to the Flood
Advisory Committee (FAC) for approval. The FAC is a group of individuals, appointed by the Olive Town
Board with technical advisors from the Ashokan Watershed Stream Management Program, the Catskill
Watershed Corporation, NYC Department of Environmental Protection and NYS Department of
Conservation. The FAC’s purpose is to act as a representation of the community and involved agencies
to discuss, vet and approve of flood mitigation solutions.
Next, a series of existing hydraulic modeling runs were completed to identify flood hazards. There were
two categories of flood hazards that were identified in this LFA. The first is an inundation flood hazard
where flood waters submerge important areas to the community. The second hazard category are
areas sensitive to floodwater obstructions that could worsen flood conditions. These areas were
referred to as flood debris hazards. Once an initial round of modeling runs was completed, the results
were presented to the FAC and the Town of Olive Board. During these presentations, additional areas
important to the community were identified and information about historical flooding damage was
collected.
Over the course of several meetings, preliminary flood mitigation strategies were developed. These
strategies were hydraulically modeled to understand their efficacy (benefits) in reducing or eliminating
flood hazards. If a strategy was beneficial and realistic, the cost of implementing it was estimated. The
mitigation strategies and their preliminary benefit to cost ratios (BCR) were presented to the FAC to
understand if the community would consider their implementation. Then, using preliminary BCR’s and
other prioritization metrics, the mitigation strategies were ranked and the strategies most feasible to
the FAC were selected to be further analyzed for implementation. The most feasible implementation
strategies are presented in the Local Flood Analysis report along with their supporting prioritization
metrics. The LFA has identified the highest priority strategies that have formed the Town’s road map for
flood resiliency.
9
3.1 Data Gap Analysis Summary and Purpose
Data was collected during the “windshield site visit” in April 2015 and from soliciting several data
sources. Collected data can be seen in Appendix Figure A-1. This is considered “existing” data. The goal
of collecting existing data was to be able to sufficiently characterize flooding hazards in the LFA
boundary without the need of more detailed field surveys which could be time consuming. The data
was categorized into four main subjects for each study area and are as follows:
Next a Data Gap Analysis was completed on the existing data to identify preliminary flooding hazards.
Preliminary flooding hazards include areas that are inundated by floodwaters up to a 500-year return
interval flood (500-year). Preliminary flooding hazards also include locations where high water velocities
destabilize streambanks or streambeds, causing debris to enter the water body that create or worsen
flooding hazards downstream. These flooding hazards were referred to as “preliminary” because it was
unknown at the time if these hazards were important to the community and therefore warranted
further analysis.
Using computer programs HEC-RAS (version 4.1.0, RAS) and ArcGIS (version 10.1), the location of
preliminary flooding hazards were identified in the two Study Areas and placed on maps. The Flood
Advisory Committee (FAC) flooding hazards and public flooding hazards were digitized using ArcGIS and
placed on the preliminary flooding hazard maps allowing for their location to be compared. If a FAC
flooding hazard or a public flooding hazard were in the same location as a preliminary flooding hazard
then the flooding hazard was deemed important to the community and therefore warranted further
analysis. Also, if a FAC flooding hazard or a public flooding hazard were in the same location as a
preliminary flooding hazard it meant there was sufficient data to satisfactorily characterize the hazard
using only existing data. If the FAC or public flood hazards could not be satisfactorily explained then
there was a “gap” in the existing data. These gaps were filled using field collected data or subsequent
requests of information from the FAC or the public.
The Data Gap Analysis used a series of geomorphic assessments, hydraulic modeling runs and public
meetings to characterize the flooding hazards within the LFA boundary.
10
1. A river’s ability to flood into proximal terrestrial areas (floodplain) which causes flood
inundation hazards if there is infrastructure within this area.
2. The geomorphic successional stage of a water body (a surrogate for stream stability) which
can be used to identify reach-based causes of erosion hazards.
3. A river’s historic and future channel migration patterns which can predict reach-based
causes of erosion hazards if the river’s alignment is moving towards sensitive areas.
A TAFT map (Figure 1) is created by developing a vertical datum of the average daily water surface
elevation (ADWSE) profile through a study area. Next, this vertical datum is subtracted from the digital
terrain model (DTM) of the surrounding land forms. The resultant datum is divided into intervals usually
defined by flood water depths above the ADWSE (i.e. the water depth above the ADWSE during a 2-year
return interval flood, 10-year return interval flood, etc.). These intervals show the location and size of
the approximate 2-year floodplain, 10-year floodplain, etc. on one map.
The TAFT map can also be used as a guide to mitigate future flood hazards by restricting development in
low lying floodplain areas. By keeping these areas clear of buildings or other sensitive infrastructure,
rivers can naturally migrate into low lying floodplains or send floodwaters into these areas thereby
avoiding hazards to existing buildings, roads, and bridges.
• Riverine Flood Hazard: A location where overflow from a river, stream or creek channel
(damages assets and often results in a federal disaster declaration. This type of flooding
generally occurs more than six hours after peak rainfall.
• Flash Flood Hazard: A location where a rapid and extreme flow of high water overflows from a
river, stream or creek channel into a normally dry area beginning within six hours of an
intense rainfall event. Ongoing flooding can intensify to flash flooding in cases where intense
rainfall results in a rapid surge of rising flood waters i.e. a minor flooding event rapidly
becomes a larger flooding event after another burst of intense rain.
11
• Stormwater Flood Hazard: A location where damage to asset occurs resulting from insufficient
capacity of private or municipal stormwater drainage infrastructure. This includes ditches,
catch basins and piping systems.
• Debris Jam Flood Hazard: A location where damage to assets occurs resulting from flooding or
erosion that is caused by debris reducing the capacity of water corridors, bridges, culverts or
stormwater drainage infrastructure. Debris can be wood, bedload (stones moved by water in
streams) or manmade (sofas, car parts).
• Erosion Hazard: Eroding Banks that threaten public or private infrastructure. Threatened
infrastructure is near an actively eroding bank (notable movement of bank over the last five
years) and the rate of erosion could threaten infrastructure within the next five years.
• Ice-Jam Flood Hazard: A location where damage to assets occur resulting from flooding or
erosion caused by ice jams. An ice jam is an accumulation of ice that acts as a natural dam
and restricts flow of a body of water. Ice jams may build up to a thickness great enough to
raise the water level and cause flooding.
• High Groundwater Level Flood Hazard: An area where damage occurs in areas not connected
to recognizable drainage channels. Through a combination of infiltration and surface runoff
(sheet flow) water may accumulate and cause flooding problems generally in concave basins.
The two LFA Study Areas are located within the updated FEMA modeled Ashokan Reservoir watershed
and the pertinent electronic hydraulic models (HEC-RAS version 4.1) were obtained. The models and
their supporting reports were reviewed. Two hydraulic models were developed for the West Shokan
Study Area and one hydraulic model for the Boiceville Study Area. The first West Shokan Study Area
model starts at the Bushkill-Ashokan Reservoir confluence and extends 4.9 miles upstream (referred to
as the Bushkill model) and the second model begins at the Dry Brook-Bushkill confluence and extends
3.3 miles upstream (referred to as the Dry Brook model). The hydraulic model for the Esopus Creek
Study area begins at the Esopus Creek-Ashokan Reservoir confluence and extends 23.3 miles upstream
(referred to as the Esopus model).
12
A rainfall runoff model (HEC-HMS) was developed for the entire Ashokan Reservoir watershed to
calculate flood discharges whose discharge values for the 10-year, 25-year, 50-year, 100-year and 500-
year return interval floods were input into the HEC-RAS models. Calibration runs were completed for
some models to increase the accuracy of the calculated water surface profiles. These runs were done
for models where there were known high water mark elevations and known discharges. The Bushkill
model and Esopus model had calibration runs completed.
Several assumptions in the hydraulic models were reviewed to ensure the models accurately capture
existing conditions since several years have passed since they were developed. If model conditions
accurately capture the existing conditions, then the calculated floodwater elevations were assumed to
be accurate. These assumptions will be explained in each Study Area’s results section.
13
3.3 Data Gap Analysis Results: Boiceville Study Area
The TAFT map in Appendix Figure A-2 and in Figure 1 shows two general relationships between the
Esopus and its floodplains within the Study Area. A 300’ average valley width begins at the upstream
Study Area boundary and extends approximately 3,000’ downstream to the Boiceville Market area. In
this section of the Esopus, there are nominal increases in floodplain width between the 2-year
floodplain and 100-year floodplain which means most of the floodwaters are being contained within the
river corridor. This constriction causes fast moving water and erosive conditions during flooding. At the
Boiceville Market, the valley widens to 1,600’ reducing its flood water speed and erosive energy. The
Boiceville Market and other buildings are located within the 10-year to 25-year floodplain (8.5’ -10.5’
ADWSE). These valley widths are notably narrower and wider than the range of valley widths noted in
the Upper Esopus Stream Management Plan that are upstream of the Study Area which range from
656’-1,300’.
A much larger valley width is present 200’ upstream of the Study Area (floodplain width is 1,950’) where
a low lying floodplain (2.5’-6.5’ above ADWSE) on both sides of the Esopus exists. Other areas of low
lying floodplain exist downstream of the railroad bridge crossing of the Esopus. There are other smaller
areas of lower floodplain in the Study Area where the Little Beaver Kill and an unnamed tributary meet
the Esopus. These floodplains were probably created by the deposit of alluvial material from the
tributaries and do not pose a flooding hazard since there is no infrastructure in these areas.
Upstream of the project site, the low lying floodplain (2.5’-6.5’ above ADWSE) is a location where the
historic river alignment has migrated. The thin blue lines shown on the TAFT map in the right bank
floodplain are very close to the ADWSE meaning that at some point in the past, the Esopus’ alignment
ran through the floodplain and has since migrated towards the left bank and State Route 28. As such, a
reach-based erosion hazard due to channel migration is high in this location.
14
Figure 1: Terrace and Floodplain Terrain Map of Boiceville Mitigation Area
Erosion hazards due to the lateral migration of the Esopus are unlikely through much of the study area
where the flooding extents are limited by the narrow valley walls (300’ +/- wide). Conversely, in areas
with wider floodplains, the possibility for channel migration is more likely. For example, it is possible
that the historic Esopus alignment (pre-European settlement) ran through the area between the
Boiceville Market and Fire House Co. #5 since there is moderate lying floodplain on the east bank.
However, since the floodplain height is 8.5’-10.5’ above ADWSE, the probability of this erosion hazard
occurring is low because only large floods can reach this height and the area is protected by the Route
15
28A bridge approaches. Just downstream of the Route 28A bridge along the east bank, the TAFT map
shows a thin blue line that is more parallel with the present day Esopus alignment than it is parallel with
the present day unnamed tributary alignment. This could indicate the location of a historic Esopus
alignment channel. If the Route 28A approaches are widened, this historic alignment should be taken in
consideration since it is within reason that the Esopus may try to recapture parts of its historic alignment
creating an erosion hazard. At the low lying floodplain 800’ downstream of the bridge, the Esopus
becomes anabranched (multithread) which is an indication of where a combination of sediment
deposition and channel migration has occurred.
In the Study Area there was little SFI data that documented any concern for flooding hazards as shown
on the TAFT map (Appendix Figure A-2). SFI features that were notably lacking were the dearth of
deposition features which would suggest infilling that can exacerbate flooding hazards. Since this
information was collected almost 10 years ago, this should be confirmed during the field investigations.
There is an eroding bank between the railroad bridge and Route 28A bridge but there is little
infrastructure proximal to this bank so this hazard was deemed of little importance. Upstream of Study
Area adjacent to the low lying floodplain (2.5’-6.5’ above ADWSE), the left bank has been protected by a
revetment. The protection was probably installed to protect the road and homes from an erosion
hazard and the status of this revetment is unclear. This hazard was included in this assessment because
of the level of consequence this hazard poses and it may be warranted to extend the Study Area’s
boundaries. This stream feature supports the TAFT findings which predicted there would be a high
probability of an erosion hazard occurring in this area since the Esopus was migrating to the left (east).
Outside the study area there are three large woody debris mapped SFI features in the Study Area which
could cause localized flood hazards or erosion hazards and should be assessed during the field
investigations.
The Upper Esopus Stream Management Plan was also reviewed to identify and to understand the
conditions that may cause potential flooding hazards. The Esopus Creek channel alignment has changed
little over the last several decades in and around the Boiceville Study Area. The only notable change
occurred near the upstream limits of the study area (in the low lying floodplain area as noted above)
where it has shifted towards the left bank over the last several years. There is a several thousand foot
right bank rip rap revetment leading up to the Boiceville Market protecting the adjacent railroad which
is located high above on the hillside and is not inundated by the 100-year flood. The structural status of
16
this revetment was found to be stable and therefore the revetment does not impact flooding hazards in
the Boiceville Study Area.
The three overbank flooding hazards are located at the Boiceville Market and are explained by the TAFT
map in Figure 1 which shows these buildings to be located in a moderate lying floodplain (8.5’-10.5’
above ADWSE) connected to the Esopus. This floodplain begins to flood around the 25-year return
interval storm. The debris jams at hazard #3 and hazard #4 were not marked on the SFI inventory and
will be explored in the field investigations to characterize if they could potentially cause flooding
hazards. The last hazard is an eroding bank (hazard #5). This was not marked in the SFI inventory and it
will be measured and its potential impacts assessed during the field investigation.
17
Figure 2: Location of USGS Stream Gage and Boiceville Market
Figure 3: Comparison of Rainfall Runoff Discharges versus Measured Discharge (FEMA 2012)
18
Table 1: Comparison of Bulletin 17B Flood Discharge Values versus Rainfall Runoff Model Values
The first reviewed assumption was the appropriateness of the downstream boundary condition. In the
HEC-RAS model, a normal depth calculation was used to set the boundary condition at the downstream
cross section which is an acceptable approach for non-backwater flow conditions. A review of the DEP
Ashokan Reservoir data show that reservoir levels can range from 540’ to 590’ in elevations. The Esopus
channel bottom is lower than 590’ for several hundred feet upstream of the Ashokan Reservoir-Esopus
confluence meaning that several of the most downstream cross sections in the model would be filled
with reservoir water creating a backwater condition. Therefore, the normal depth calculation is not the
optimal downstream boundary condition. However, the hydraulic report does not address how the
boundary condition was selected nor how reservoir levels may influence the boundary condition. The
Boiceville Study Area is located approximately a mile upstream (river slope 0.005ft/ft) of the Ashokan-
Esopus confluence so it is assumed that any backwater effect from the Reservoir is negligible and the
river is flowing under non-backwater conditions. As such, it is unlikely the uncertainty of the
appropriateness of the downstream boundary condition will influence the modeling results in the
Boiceville Study Area.
The second assumption checked was the calibration of the model. Several modeling variables can be
manipulated to adjust the model’s calculated water surface to a known (and measured) high water
mark. These variables include ineffective flow area and relative roughness (Manning’s “n” values). In
the Esopus model, the most downstream high water mark that the model was calibrated to was in the
Boiceville Study Area near the Boiceville Market and Fire House Company #5 (see Figure 4), about 1.0
mile upstream of the reservoir. This high water mark was surveyed after the 2011 floods (75,800 cfs).
The Esopus model’s variables were then adjusted until the calculated water surface was within 0.5’ of
the surveyed water surface elevation at Fire House Co. #5 (FEMA 2012) which is acceptable difference.
However, at the USGS Coldbrook stream gage located 2,300’ upstream, the difference is 3.0’ as seen in
Figure 5 (FEMA 2012) which is not an effective calibration. Since the model was calibrated using high
water marks within the LFA boundary and appears to be more conservative/overestimates, the model is
assumed to be reliable.
19
Figure 4: High Water Mark at Fire House Co. #5 (The line between light and dark bricks)
655.0
645.0
635.0
625.0
615.0
0 50,000 100,000 150,000 200,000
Flow (cfs)
Figure 5: Comparison of Measured Discharges and Modeled Discharge in FEMA Models (FEMA 2012)
The third reviewed assumption was the application of ineffective flow areas (inundated areas where the
velocity of water is assumed to be zero). Areas in an ineffective flow area do not convey water
longitudinally and therefore are not used in the calculations for water surface elevations. Figure 6
shows the cross section from the Esopus model through the Boiceville Market Area. The green hatch
areas are ineffective flow areas. Flood waters inundate the area around the Boiceville Market area
(between station 800 and 1000) starting at the 25-year flood event. The cross section shows that this
area does not convey flood waters. The TAFT Map in Figure 1 shows that the Route 28A bridge
approaches jut out and forms an east to west high location. This obstruction blocks that conveyance of
floodwaters running north to south and the use of ineffective flow areas in the Study Area are
appropriate. Lateral flow direction is considered negligible.
20
Figure 6: HEC RAS Cross Section through the Boiceville Market Area.
Areas with green hatch are Ineffective Flow Areas near the Market.
The last reviewed assumption was the topography used to build the model. Several cross sections were
surveyed in the Study Area from stream top of bank to top of bank after the 2011 floods and spliced into
the 2009 LIDAR information to create the cross sections used in the hydraulic model. The FAC felt that
there were no notable changes in topography in the Study Area which means the topography is
acceptable. This assumption was reinforced by comparing the recently surveyed channel (winter
2014/15) sections obtained as part of the Route 28A bridge replacement work with the channel sections
in the duplicate HEC-RAS model. The only notable change in topography occurred near the bridge.
There is an increase in channel bed elevation near the bridge since the survey information for the
duplicate model was obtained (Figure 7). This increase is slight, when compared to the overall water
depth during the 10-year flood (average water depth 10’) and the 100-year water depth (average water
depth 20’). Therefore, the topography in the duplicative HEC-RAS model was updated with the newer
survey data and the remaining topographic information was determined to be acceptable.
21
Figure 7: Cross Section of Duplicated and Corrected Model. Note Slight Changes in Channel Topography
10-Year Return Interval Flood (Appendix Figure A-6): Floodwaters are generally contained within the
Esopus channel banks. Over bank flooding appears to only occur immediately upstream and
downstream of the Route 28A (Five Arch) bridge. There is some inundation predicted to the east of
State Route 28 along the unnamed tributary but no overland connection is visible. The map was edited
after the FAC was consulted to understand flooding in this area.
25-Year Return Interval Flood (Appendix Figure A-7): Notable increase in flooding in the Boiceville
Market area. It appears there are “threads” that connect the Esopus to the floodplain. A thread is
located between the Sewage Treatment Plant and the Market and just to the south of the treatment
plant. Shallow water depths are present over State Route 28 (1.1’-2.5’) and floodwaters begin to
surround the Boiceville Market Building (0.1’-1.0’). It appears overbank flooding occurs on the right
bank across from Fire House Company #5 upstream of Route 28A but not downstream of Route 28A.
Fire House Company #5 is completely surrounded by water (depth 0.1’-2.5’). The map was edited after
the FAC was consulted to understand flooding in this area.
50-Year Return Interval Flood (Appendix Figure A-8): Flooding extents remain relatively unchanged
except for downstream of Route 28A along the right bank. The ground elevation around the Market is
under water (1.1’-2.5’). The first floor elevation of the Market is between 0.5’ and 1.0’ above the
ground elevation so it is assumed there is water in the Boiceville Market building during this flooding
event. All the businesses in this area have the same depth of water in them except for the building to
22
the north of the Boiceville Market which is mostly dry. There is more water depth over State Route 28
(2.6’-4.5’) and most of the buildings between it and the unnamed tributary to the east have between
2.6’ to 6.5’ water depth around them. The map was edited after the FAC was consulted to understand
flooding in this area.
100-Year Return Interval Flood (Appendix Figure A-9): Flooding in the Boiceville Market, Fire House
Company #5 and State Route 28 area is deep (>8.5’). The business to the north of the Market has water
surrounding it and most likely enters the building. There is now water in the floodplains, upstream and
downstream of Route 28A along both banks. The map was edited after the FAC was consulted to
understand flooding in this area.
500-Year Return Interval Flood (Appendix Figure A-10): In general, the 500-year water surface elevation
is twelve feet higher than the 100-year water surface elevation which is an unusually large difference
between the two flood frequencies. Flooding in the entire area surrounding the Boiceville Market
including the business to the north is deeper than 8.5’. State Route 28 is under water beginning at the
Route 28A intersection to the school. There is a distinct high area about 100’ wide, parallel with State
Route 28 starting adjacent to the school. All buildings to the west of this high area are under 6.6’ to 8.5’
of water.
When overbank flooding occurs several buildings will become inundated starting around the 25-year
flood return interval. These are commercial and residential buildings which may contain chemicals and
hazardous waste that create water quality concerns. Around the 50-year flood event, floodwaters reach
petroleum storage tanks about 200’ northwest of the market (see Figure 8). If these tanks are not
anchored properly they can cause water quality and public safety issues.
23
3.3.8 Identified Data Gaps and Proposed Field Methodology
The review of existing data identified several gaps that cannot fully explain existing or potential flood
hazards or allow for informed mitigation solutions to be developed. The following outlines the
questions that were raised, the methodology used to answer the questions and the results as
determined from information collected in the field.
1. What is function of Mount Pleasant and Mount Tremper Flood Control Projects? The FAC was
consulted and these facilities were built 60 years ago and do not have an impact on flooding
conditions in the Study Area.
2. Are there any deposition features in the Study Area that may have caused infilling? There are
no depositional features in the Stream Feature Inventory. The FAC was consulted and field data
was collected using a Trimble 6000 handheld GPS device (accuracy <1.0’) on July 2015 and using
SFI methodology. No depositional areas were found.
3. Besides the submitted erosion hazards and in the SFI, are there any eroding banks of concern in
or proximal to the Study Area, for example just upstream? The FAC was consulted and field data
was collected using a Trimble 6000 handheld GPS device on July 2015 using SFI methodology.
No additional erosion hazards were found.
4. What is the status of the revetment upstream of the low lying floodplain just upstream of the
LFA boundary where the Esopus is migrating left (east) (Appendix Figure A-2)? Is this a concern
for the FAC? The FAC was consulted and field data was collected using a Trimble 6000 handheld
GPS device on July 2015 using SFI methodology. The revetment is being undermined but this is
not within the scope of the LFA and therefore should be omitted.
5. Are there buildings along the Little Beaver Kill and are they occupied structures? Is the flooding
around them from the Esopus or Little Beaver Kill? The FAC was consulted and there are no
homes between State Route 28 and the Esopus Creek. There are no homes upstream of State
Route 28 along the Little Beaver Kill that are within a Special Flood Hazard Area (a FEMA
delineated floodplain). There are no flooding hazards along the Little Beaver Kill.
6. When, how and where does the flooding for stormwater hazards #6, #7 and #8 occur (Appendix
Figure A-3)? Are there constrictions in the floodplain that create these flooding hazards? The
FAC was consulted and data was collected using traditional surveying methods for hazard #8
(culvert under State Route 28 and upstream floodplain) in July 2015, hazard #7 (DeSilva Road
culvert) in July 2016 and Hazard #6 (culvert under State Route 28) in July 2016. These locations
are considered important to the FAC and should be considered in the LFA.
7. Do the debris jams at Hazard #3 and Hazard #4 (Appendix Figure A-3) cause flooding problems
or cause local erosion? The FAC was consulted and field data was collected using a Trimble 6000
handheld GPS device on July 2015 using SFI methodology. Hazard #3 was the old Coldbrook
Bridge that was destroyed in the 2011 floods. It is located high up on the floodplain and does
not pose a flooding hazard. Hazard #4 is the damaged railroad bridge over the Esopus; it does
not pose any flooding hazards in the Boiceville Study Area.
24
3.4 Data Gap Analysis Results: West Shokan Study Area
3.4.1 Rapid Geomorphic Assessment
Using the same methodology as was used for Esopus Creek, TAFT maps were created for the West
Shokan Study Area. The TAFT map was extended 1,800’ upstream of the Study Area to characterize the
portion of the river leading into the study area. Two thousand feet is 27.0 times the bankfull width
(width is 67’) (USGS 2015) which is an adequate distance to characterize an adjacent reach.
The TAFT map in Figure 9 depicts a typical relationship between a river that cuts through an alluvial fan
and the river’s floodplains. The floodplain width is narrower along the beginning of the alluvial fan and
the upstream reaches of the Bushkill where the floodplain averages about 400’. Floodplain width
increases further downstream (and downslope) along the fan. Near the most downstream bridge on
Watson Hollow Road (referred to as the Watson Hollow Road bridge) and close to the halfway point
along the fan, the floodplain width expands to approximately 1,750’. The floodplain width exceeds 4,000
feet as it approaches the confluence with the Ashokan Reservoir near Route 28A.
Figure 9: Terrace and Floodplain Terrain Map of West Shokan Study Area
Another alluvial fan characteristic is the amount of low lying area that is close to the channel bottom
elevation. Using the TAFT map, this characteristic is shown in blue (area between 0.1’-6.0’ above the
ADWSE). There are long blue threads (0.1’-6.0’ above the ADWSE) that parallel the present day channel
alignments (both the Bushkill and Dry Brook). These threads represent historic alignments of the Bushkill
and Dry Brook. This characteristic is first observed near the Watson Hollow Road Bridge and continues
downstream towards the reservoir. Two recent channel alignments were digitized on aerial
photography taken in 2001 and again in 2009 to capture the change in channel alignment over the
course of eight years. The 2001 and 2009 Bushkill alignments begin to diverge downstream of the
25
Watson Hollow Road Bridge and notably separate adjacent to Olive’s town offices. It is at this point that
the 2009 alignment takes a dramatic turn to the south. It is reasonable to assume that over the last
millennium the Bushkill and Dry Brook alignments have traversed back and forth across the alluvial fan’s
low lying floodplain (area shown in blue in Figure 9 on previous page).
Potential flood hazards exist in this Study Area because it is reasonable that the Bushkill or Dry Brook
could avulse (change direction) and reoccupy their historic alignments in the low lying floodplains areas.
Potential flood hazards exist where there are buildings or other sensitive infrastructure located in these
areas. If the channels were to avulse and follow historic flow paths, land that had been normally dry
could become suddenly inundated and the land adjacent to these flow paths could be eroded. There
are several existing locations exposed to these types of potential flood hazards. The first is east of the
town offices along Lang Road where there are several buildings in a blue area as seen in the TAFT map.
A blue area is an area vertically proximal to the Average Daily Water Surface Elevation (ADWSE). There
is a blue thread that extends up the valley slope (to the west) towards Watson Hollow Road that could
be a historic flow path. The most western portion of this blue thread (closest to Watson Hollow Road)
will be investigated during field investigations to confirm if this potential flood hazard exists. Another
potential hazard is located parallel with Watson Hollow Road, 300’ northeast of the Town Hall. A blue
thread runs parallel with the road until it meets Route 28A where it ends. This thread ends at the road,
probably due to the embankment fill that was used to build the road. This was assumed since
immediately downstream of the road, the blue thread continues. If the Bushkill were to avulse and run
along this thread, it could pose an erosional hazard at this section of road.
This TAFT map also can be used as a guide to mitigate future flood hazards by restricting development in
low lying floodplain areas (areas in blue). These areas may be prone to future channel migration or
water inundation. By keeping these areas clear of buildings or other sensitive infrastructure, the
channels can naturally migrate and would not pose a hazard to buildings.
Number Length
Feature Type
of Observations (ft)
Depositional 4 N/A
Features
Fine Sediment 2 N/A
Sources
Eroding Banks 9 1,820
Obstruction Caused 2 N/A
By Large Woody Debris
26
The West Shokan Study area is located within the Bushkill Stream Management Plan area. The Plan
identified a distinct break between the lower and upper reaches of the West Shokan Study Area in terms
of the relationship between sediment transport and sediment storage. In the lower reaches there is
more sediment deposition and storage and the stream becomes braided with multiple flow pathways.
This description aligns well with the previous findings that the West Shokan Study Area has the potential
for multiple reach-based flood hazards, primarily erosion and channel migration that could change
inundation extents.
The valley slope along an alluvial fan is much flatter than the steeper headwaters draining to the fan.
Stream slope is a key component for calculating shear stress (the physical process of moving a
submerged object in a fluid). If the slope decreases (in this example the valley slope is used as a
surrogate for the energy slope) an object that was moved by water in the steeper headwaters would
cease to be carried by the water in the flatter alluvial fan valley slope. This physical process leads to
deposition (cessation of movement) of bedload (gravels, cobbles and boulders) in certain locations along
the alluvial fan. Deposited bedload can build up over time and form obstructions to flow redirecting
flow towards stream banks and causing erosion. The redirection of water into a stream bank caused by
an obstruction is an example of a site-based cause of an erosion failure mechanism. Other site-based
causes include log jams that also redirect water into unwanted locations.
During subsequent FAC meetings and field investigations, it will be determined if the submitted hazards
were caused by either site-based causes or reach-based causes. This distinction is important for
developing an informed design of how to mitigate these hazard types. For example, debris can be
manipulated to accumulate in certain areas and not others mitigating unwanted flow deflections. If the
hazards are reach-based caused, then removing the infrastructure out of the way of the migrating
channel or developing a mitigation solution that extends further upstream or downstream of the hazard
location are preferred solutions.
27
measured discharge at the USGS gage (6,240cfs) differed by 13% as seen in Figure 11 (FEMA 2012).
Calibration was not completed in the Dry Brook or Maltby Hallow watershed.
Figure 10: Location of USGS Stream Gage along Bushkill at West Shokan (01363382)
Figure 11: Comparison of Rainfall Runoff Discharges versus Measured Discharge (FEMA 2012)
28
A calibration run was completed only for the Bushkill model to increase the accuracy of the calculated
water surface elevation profiles using the August 2011 flood discharge. The results were compared to
known water surface elevations at the USGS stream gage (#01363382 Bushkill below Maltby Hollow
Brook at West Shokan).
The first reviewed assumption was the appropriateness of the downstream boundary condition which
was normal depth calculation (slope of 0.0113ft./ft.). As discussed in section 3.3.5, the Bushkill empties
into the reservoir approximately 1,110’ downstream of the Route 28A bridge over the Bushkill. The
fluctuating reservoir levels influence on hydraulics is not discussed in the FIS. Since the most
downstream area of interest in the LFA boundary is located more than a thousand feet upstream, has a
channel bed elevation greater than 606’ and is on a relatively steep slope (>1%), it is unlikely reservoir
levels impact hydraulics in the study area.
The second assumption checked was the calibration of the model. None of the three models were
calibrated to any measured discharges (FEMA (2) 2013). The Bushkill modeling results were only
compared to measured water surface elevations at USGS #01363382 downstream of the Maltby Hollow
and Bushkill confluence. These numbers compared reasonably well during discharges less than 5,000 cfs
(less than a 50-year return interval flood) but the difference increased with larger events (>2.0’). Note,
the discharges are erroneously listed in Table 15 in the FEMA report and are for the Bushkill upstream of
the Bushkill/Maltby Hollow confluence, not for the gage which is located downstream of the confluence.
Since there are no calibration data nor enough peak annual discharge data to complete a Bulletin 17B
analysis (a statistical analysis using a Log Pearson III distribution), the discharges and the model are
considered adequate for this exercise.
The third assumption checked ineffective flows and Manning’s “n” values and all seemed adequate.
The last reviewed assumption was the topography. Supplemental cross sections were surveyed in the
West Shokan Study Area from stream top of bank to top of bank after the 2011 floods and spliced into
the 2009 LIDAR information to create the cross sections used in the HEC-RAS hydraulic models for the
Bushkill and Dry Brook. Eight cross sections were surveyed along the Bushkill and five cross sections
were surveyed along Dry Brook. Due to the depositional nature of an alluvial fan it was recommended
cross sections be resurveyed to see if there have been notable changes in topography. Notable changes
in the topography could change inundation extents during flood conditions. A section near critical
infrastructure such as the fire house near the Town offices (HEC RAS section 3395) and near Watson
Hollow Road Bridge (HEC RAS section 4690) were recommended to be resurveyed.
29
Bush Kill, USGS stream gage 01363382
698
Water Surface Elevation (NAVD 88, ft)
696
694
692
690
688
Observed (2001 - 2011)
686
Model (Interpolated at Gage)
684
0 5,000 10,000 15,000 20,000
Discharge (cfs)
Figure 12: Comparison of Modeled Water Surface Elevations vs. Measured Water Surface Elevations.
10-Year Return Interval Flood (Appendix Figure A-16): Floodwaters are generally contained within the
Bushkill and Dry Brook channels. Over bank flooding appears to only occur to the north of the Bushkill
near the confluence with Dry Brook. This overbank flooding could be the exchange of floodwaters
between the two streams. Also, the confluence area between the two streams is inundated (section
2721) but there is high area between this location and Route 28A. All bridges and culverts along the
Bushkill and Dry Brook are able to pass the 10-year flood. The map was edited after the FAC was
consulted to understand flooding in this area.
25-Year Return Interval Flood (Appendix Figure A-17): Floodwaters continue to be contained within
the main channels of the Bushkill until section 4564 where they begin to spread out. It does not appear
that any buildings are within the inundation area. The area just upstream of the Route 28A bridge is
almost completely inundated. All bridges on the Bushkill are able to pass the 25-year flood with minor
backwater influence. The culvert along Burgher Road along Dry Brook is overtopped during the 25 year
flood and causes backwater conditions. The map was edited after the FAC was consulted to understand
flooding in this area.
50-Year Return Interval Flood (Appendix Figure A-18): Flooding extents do not appear to inundate any
roads or buildings along the Bushkill during this flood. There does appear to be a connection between
overbank flooding and adjoining floodplain at section 1167 in the Dry Brook model. There is a home
near this section that may be at risk of flooding. The area upstream of Route 28A is completely
inundated. All bridges on the Bushkill are able to pass the 50-year flood. The culvert along Burgher Road
30
along Dry Brook causes the road to overtopped by a 0.5’ of water. The map was edited after the FAC
was consulted to understand flooding in this area.
100-Year Return Interval Flood (Appendix Figure A-19): Flooding extents inundate several buildings
along the Bushkill but no roads. The building along Watson Hollow Road near the Town Office is
inundated by 0.6’ of water. Two homes between the Bushkill and Mulrooney Road are also inundated
but it appears there is a berm between the Bushkill and these homes so in the refined Water Depth
map, these buildings may not be inundated if the berm keeps the 100-year floodwaters away from these
homes. Along Dry Brook, no buildings are inundated and one road (the Burgher Road crossing over Dry
Brook) is overtopped by more than a 1.0’ of water. The map was edited after the FAC was consulted to
understand flooding in this area.
500-Year Return Interval Flood (Appendix Figure A-20): The depth grid shows flooding has not crossed
the Watson Hollow Road but the FIRM map shows that several buildings near the town offices are
inundated during this flood event. This contradiction is due to the cross section in the model not being
extended far enough to capture the full floodplain width. This will be adjusted per direction of the FAC.
The buildings just north of this area across the road are inundated with up to 4.0’ of water. The
buildings south of Mulrooney Road have a 1.0’-4.0’ of water around them. The culvert along Burgher
road is overtopped by greater depths. The map was edited after the FAC was consulted to understand
flooding in this area.
There were six erosion hazards submitted by the public and the FAC. It is unclear if these erosion
hazards are eroding banks which would provide a sediment source for water quality concerns or if the
hazards are potential erosion hazards at bridge abutments. This will be clarified during subsequent FAC
meetings and field investigations. Once the SFI data becomes available it will be reviewed to determine
if there are other water quality concerns in the Study Area.
1. When were the stream spoil berms built (near the Town offices) and do they serve a purpose?
The FAC was consulted and field data was collected using a Trimble 6000 handheld GPS device
on July 2015 using SFI methodology. These were debris piles made by stream work completed
by the US Army Corps of Engineers in 1985 and do not serve a purpose. These features do not
protect infrastructure so they should be omitted from the LFA.
31
2. Near Hazard #5, is there a man-made feature that separates the low lying area between the
Bushkill and Mulrooney Road? The FAC was consulted and field data was collected using a
Trimble 6000 handheld GPS device (accuracy <1.0’) on July 2015 using SFI methodology. This is a
manmade berm built to protect the homes to the north and it should be considered in the LFA’s
recommendation for protection.
3. Is the potential flood hazard (the blue thread) on the south shore of the Watson Hollow Road
bridge real? A total station survey was completed on July 2015 that measured the elevation
profile of this depression and compared it to the channel elevation profile of the adjacent
Bushkill. The elevation of the flow path and the road profile suggest that during the
construction of the road, fill was placed in a historic flood path isolating it from the Bushkill. It is
unlikely the Bushkill’s flood waters will be able to inundate this path due to the height of the
road. This potential flood hazard should be omitted.
4. Is the potential flood hazard (the blue thread) that runs parallel along Watson Hollow Road
heading towards Route 28A real? A total station survey was completed on July 2015 to compare
the Bushkill elevation profile with the elevations of the old flow path profile. The elevations
between the two profiles suggest that floodwaters could occupy this flow path and it is a
possibility that the Bushkill could migrate into this flow path which could then damage Route
28A. This flood hazard should be considered in the LFA.
5. What is the history of stream management practices in the Study Area? In particular: bank
protection, channel excavation, bridge repair particularly on the Bushkill and how have they
fared over time? The FAC was consulted and it is understood that overall stream management
activities have been completed in the Study Area in recent memory. Most recently was a
dredging and bulldozing exercise completed by the US Army Corps of Engineers in 1985 to
remove debris. There was large wood removal in this area after Tropical Storm Irene as well.
6. How many houses were impacted by the culvert backing up on Burgher Road (hazard #0)? The
FAC was consulted and several homes were isolated when the road overtopped. This hazard
should be considered in the LFA.
7. Are there any buildings the FAC is aware of in the 100 year floodplain that are not shown? The
FAC was consulted and no other buildings were known. During the July 2015 field visits, no
other buildings were observed.
8. Are the erosion hazards along Watson Hollow Road or near the bridge abutments? The FAC was
consulted and field data was collected using a Trimble 6000 handheld GPS device on July 2015
using SFI methodology. There were several vertical and lateral instabilities mapped during the
field visits. These were deemed important and were considered in the LFA.
32
9. Which cross sections should be resurveyed? A section near critical infrastructure such as the
fire house near the town offices (cross section Busk_04) and near the 1st Watson Hollow Bridge
(Busk_07x) are recommended to be resurveyed. A total station survey was completed on July
2015 to collect the information and was inputted into the duplicative HEC-RAS model to correct
it.
10. Cross section 3000 in the Bushkill model was not extended far enough and this could show more
or less area being inundated around the Town Office. Should this be corrected in the model to
see if the 500-year water surface elevation drops? HEC-GeoRAS was used to extend the cross
section.
33
4.0 Boiceville Study Area
4.1.3 Anthropogenic
The Esopus Creek watershed has been altered by human behavior (anthropogenic). European
settlement of the watershed began in the 1700’s and by the late 1800’s, 80%-90% of the original forests
were gone (Kudish 2000) for tanneries and kiln enterprises. The loss of original forest cover increased
the amount of rainfall runoff from the stripped lands while decreasing the vegetation that held fragile
soils together causing the land to erode. The increased amount of water and sediments rushed down
the mountains slopes into the river valleys below. The resulting intersection of this wall of water and
sediments at the valley floor caused the streams there to undergo severe changes due to increased rain
runoff and the denuded stream banks consisting of highly erodible glacial outwash. Typical changes
during this kind of instability are steep eroding stream banks, narrower water corridors (i.e. little to no
connection to low lying floodplains) and often poor water quality.
Present day streams and rivers in the watershed are in some phase of recovery from the anthropogenic
impacts. For example, the Stream Management Plan’s baseline characterization was completed in 2005-
2006 and showed river sections upstream of the Study Area had upwards of 26% to 53% of their stream
banks actively eroding. Sands, gravels and cobbles (referred to as sediments), exposed by eroding banks
and unstable streams, are moved downstream and deposited in certain areas. This condition, referred
to as “infilling”, results in the space that once was occupied by water now being occupied by these
34
transported sediment. This often results in higher water surface elevations during flooding events
because there is inadequate space within the river to move floodwaters.
Recent anthropogenic activities influencing the creek are infrastructure encroachments into the active
floodplain. An example of this is the Route 28A (Five Arch) bridge approaches along the eastern stream
bank which cut off upstream and downstream floodplains as seen in the TAFT map in Appendix Figure A-
2.
The discharges used in the HEC-RAS model were reviewed to determine the flood return interval of the
discharges shown in Table 4. A return interval is a statistical term that describes the frequency a certain
discharge will occur. For example, a 10-year return interval flood will statistically occur once in ten years.
The discharges for the study area used in the HEC-RAS model are shown in the Table 4 below. The
largest flood recorded at this station was the 2011 flood. This event was between the 50-year and the
100-year return interval flood. A FEMA Schedule Bulletin 17B analysis of the USGS stream gage
(#01362500) data was completed using the Weibell plotting method and the station skew to compare to
the discharges used in the duplicated HEC-RAS model. The 2011 flood was determined to be roughly a
75-year flood event. Another recent flood event occurred in 2005 and this flood was roughly a 35-year
flood. Both of these flood events caused damage in the Boiceville Market area which further supports
that the Market is located in a floodplain that is flooded during moderately sized floods.
35
FEMA floodplain and FEMA floodway. The ordinance meets the minimum federal standards for
development within a delineated FEMA floodplain. The preliminary Flood Insurance Rate Map for the
Study Area can be seen in Appendix Figure A-21. The area around the Boiceville Market is within a
delineated FEMA floodplain. The Town of Olive does not have an official comprehensive planning
document. A draft version was developed in 1975, 1995 and 2011 but none were adopted by the Town
Board.
The presented mitigation solutions assume the three span bridge will be in place. Consequently, the
proposed mitigation solution conditions were compared to future “existing conditions” which assumed
the proposed three span bridge is in place. The procedures for developing the future “existing
conditions” can be reviewed in the WEC 2016 report. The efficacy of the proposed mitigation solutions
compare the proposed water surface elevations to the future “existing conditions” water surface
elevations.
36
4.3.2 Existing Hydraulic Conditions and Water Depths
The water depth maps as seen in Figure 13 and (Appendix Figures B-2 through Figure B-7) were
developed using the WEC corrected model.
As seen in Appendix Figure B-6, (the 100 year water depth map, there are 17 buildings surrounded by
water during the 100-year flood and most of the buildings are shown to have water around the
foundations starting at the 25-year flood (Appendix Figure B-3). Figure 13 is a close up of Appendix
Figure B-3 and shows there is approximately 1-2’ of water in the Boiceville Market (Building B-16) during
the 25-year flood. Interviews of community members reported around 2’ of water during the 2005
flood which closely matches the 25-year flood water depth map.
Figure 13: Water Depths Around the Boiceville Market (B-16) during the 25 year flood.
37
Only the mitigation solutions that work in tandem with the proposed three-span bridge were included in
this report. To avoid confusion from mitigation solution plan names during the LFA process, the original
mitigation solution plan names were retained and therefore the plan names may not be in numerical
order. A complete list of solutions is presented in Table 5.
Proposed mitigation solutions included Flood Damage Prevention, Property Protection, Structural
Projects and Community Pollution Prevention. The lowering of adjacent land, referred to a floodplain
bench is an example of a Flood Damage Prevention solution that was modeled and vetted by the FAC.
Increasing the clear span (the bridge width) of the three arches bridge (a Structural Project) was
modeled to understand the relationship between bridge width and flood water elevation. Property
Protection solutions included raising first floor elevations of certain buildings or the potential for
buyouts and buyouts with possible relocations.
For each solution a table will be presented outlining the priority metrics for the solution. The metrics
are summarized in Table 6 on page 40.
38
Table 5: List of Preliminary Mitigation Solutions
39
Mitigation Benefit Cost
Mitigation Plan Description Hydraulic Analysis?
Plan # Analysis?
11 Relocate 28A bridge and waste water Yes No
treatment plant and install wider floodplain
benches than in Mitigation Plans #4, #5 and #7.
12 Town to complete a plan to identify new Yes Yes
developable land and zoning changes (if
applicable) to relocate buildings out of flood
prone areas
13 Structural improvements (raise first floor Yes Yes
elevations) of qualified buildings.
Numerical Value 5 3 1
of Scores
40
4.3.4 Plan #4 - Floodplain Benches Only
Summary: The floodplain will be lowered starting 350 ft downstream of the existing Route 28A bridge
and ending 1,600 ft upstream of the bridge. The average width of this cut area will be 90’ and it will be
lowered on average 2.5’. This cut will form a floodplain bench which will be seeded with native grasses
and lined along the stream bank with willows and other herbaceous native shrubs. The goal of the
floodplain bench is to increase the available volume to pass flood waters. The top of the bench will be
set at an elevation such that it will be inundated during frequent flood events (less than a 2.0 year
flood).
Results: This plan will reduce water surface elevations during the 25-year return flood by on average of
0.3’ (~4”). This will eliminate flooding during this return interval flood in the Boiceville Market. This can
be observed in the Figure 14 (25-year flood) and in Appendix Figure B-9 (100 year flood). This plan has
minimal impact to water surface elevations during moderate to large floods as seen by the continued
water depths during the 25-year flood in Figure 14. The difference between the two water surface
elevations before and after the mitigation solution remains the same.
Despite the increased conveyance in flood water volume created by the floodplain bench, the buildings
in Boiceville remain inundated during moderate and large flood events. These buildings are located in a
moderately low lying floodplain (Figure 1) and in an unusually wide part of the valley (1,600’ of active
floodplain) when compared to the creek upstream (<500’ of active floodplain) as described in Section
3.3.1. Floodwaters, when flowing through a constrained area (upstream of Boiceville) flow much faster
than the floodwaters at a proximal wider area (at Boiceville). When this happens, water surface
elevations tend to rise as the water spreads out into the floodplain. In these cases, increasing flood
water conveyance alone may not solve the inundation hazard.
Benefit to Cost Ratio: The cost of construction is estimated to be $2,449,600 (including building
relocation which was the sum of all improvement values to the parcels where buildings are proposed to
be relocated). The estimate is shown in Appendix Figure B-10. Using the FEMA’s BCA version 5.1.0 short
form, the preliminary benefit to cost ratio was 0.15 as shown in Table 9 and in the summary reports
(Appendix Figures B-11 and B-12). The low preliminary BCR was due to the continued inundation of the
buildings beginning at the 25-year return interval flood.
Implementation Challenges and Opportunities: Two buildings (B14, B15) will need to be relocated to
complete the floodplain bench construction. One of the buildings is an active business, the other is a
vacant building. The proposed floodplain bench also crosses several private land parcels and permanent
easements that would need to be obtained to allow the construction and maintenance of the floodplain
bench. The floodplain bench would need to be maintained (brush hogged and cleared) to prevent large
trees from growing that could reduce flood water conveyance.
Funding Sources: With a low preliminary BCR score (0.15) and continued inundation to buildings,
funding for this project will be difficult to obtain.
Water Quality Protection: Continued inundation under proposed conditions will not reduce water
quality pollution.
41
Prioritization:
42
Figure 14: Conceptual Layout of Plan 4
43
4.3.5 Plan #5 - Floodplain Benches and Flood Levee System
This plan would mirror Plan #4 and include a flood protection facility (an earthen berm) which would
protect the majority of buildings from flooding hazards. The alignment of the earthen berm allows the
Esopus to flood into its floodplains unimpeded during a moderate flood event (10-year flood event)
while minimizing the number of buildings that would need to be relocated.
Buildings B1, B14 and B15 would need to be relocated in order to construct the flood protection facility.
Funds are available through CWC and DEP for the purchase of the existing structures and property and
assistance with some of the potential relocation costs for these properties.
The proposed flood protection system should meet FEMA certification requirements for flood
protection systems to ensure building owners landward of the berm would receive discounts on flood
insurance premiums. As such, the elevation of the top of the earthen levee was set to meet NFIP
regulation 65.10(b) which states the levee elevation should exceed the BFE (base flood elevation also
referred to as the 100-year flood event) by three feet, 3.5’ at the upstream end of the levee. The crest
of the levee would be 10’ wide with three horizontal to one vertical side slopes (for mowing). The base’s
footprint would be 70’ wide where it meets the downstream high ground near the Route 28A and State
Route 28 intersection and be 50’ wide where it meets upstream high ground northwest of building B17
(Figure 15 on page 48). It would be on average 6’ high between the upstream high ground and building
B11 and on average 9’ high between B11 and the downstream high ground.
To be a FEMA accredited flood levee, besides meeting the height requirements, the levee must protect
critical infrastructure landward of the flood protection system. Buildings B1 and B11 (Fire House
Company #5 and the wastewater treatment plant, respectively) are the two pieces of critical
infrastructure in Boiceville. At building B1, the 500-year flood elevation is 16.5’ higher than the 100 year
flood elevation. FEMA requires critical infrastructure to be protected to the BFE plus 3’ feet freeboard or
the 500 1 year flood elevation, whichever is higher. Therefore, it is unrealistic to protect B1 so it should
be relocated to an area that is not prone to flooding. Building B11 is so close to the floodway (<15’), it is
not possible to put the levee riverward of this building so this building cannot be protected. The levee
could be put landward of the building which would require the driveway to building B11 to be graded
over the levee. By having the levee landward of the wastewater treatment plant, the levee could be
accredited by FEMA (i.e. flood insurance premiums for the landowners landward of the levee would go
down) but the treatment plant itself would not be protected.
The levee would tie into the parking lot of building B11. It is assumed that the fill built to the parking lot
and the waste water treatment plant was compacted to industry standard to prevent settling which is
similar to the compaction rate requirements for FEMA levees. The base of the wastewater treatment
plant is 150’ wide which is more than double the width of the levee and it is assumed that this is
adequate to meet hydrostatic design criteria.
Two pumping stations would be needed to drain the landward side of the levee. The purpose of the
pumps is to protect the buildings landward of the levee if interior flooding were to occur at the same
time as exterior flooding conditions. To meet FEMA accreditation guidelines, the pumps must keep inlet
1
As noted in section 3.3.4 and 3.3.5, there is uncertainty with the 500-year discharge and its predicted water surface elevation using the
corrected effective hydraulic model but it was assumed that the predicted 500-year water surface elevation is reasonable for use in the LFA.
44
water depths to a foot or less during the design flooding conditions of the levee (when floodwater
elevations match the levee’s top elevation). If the levee elevation is exceeded by floodwaters, the
pumps are no longer required to meet their design conditions. The first pumping station (Pumping
station “A”) is located near building B1 where an existing stormwater drainage ditch would be
reconfigured to drain underneath the levee in a culvert with flap gate. This pumping station would drain
approximately 10 acres west of State Route 28. East of State Route 28, as described in Section 4.6, there
is a tributary that flows through a culvert underneath the highway. The tributary features a wetland
between it and the highway. Assuming a flap gate is constructed on the culvert under State Route 28
which would cause the tributary to backwater if the flap gate was closed during flooding on the Esopus,
it is desirable to avoid flooding the proximal buildings. Under existing conditions, this wetland stores a
large volume of water during flooding conditions (a 500-year flood on the tributary) resulting in only one
building, B3, being inundated by 0.9’ of water (as described in Section 4.6). Therefore with modest
grading, a pumping station could keep all the proximal buildings dry when the tributary is flooding. A
three foot earthen berm would to be placed between the buildings and wetland to maintain freeboard
requirements. The cumulative length of all berms is 1,900’.
Results: The proposed levee provides protection to all landward buildings at the 100-year flood event
(Figure 15 on page 48). The additional freeboard above the water surface elevation also protects the
buildings from larger flood events. It does not protect from inundation during the 500-year flood since
the water surface elevation during this event is notably higher.
Benefit to Cost Ratio: The cost of Plan #5 is estimated to be $3,905,300 (including building relocation,
constructing the flood protection system and floodplain benches, engineering costs, etc.). The estimate
can be seen in Appendix Figure B-14. Using FEMA’s BCA version 5.1.0 short form, the preliminary
benefit to cost ratio was 0.63 (Table 12 on page 47) and the summary report can be seen in Appendix
Figures B-15 and B-16. The short form BCR does not allow for annual maintenance costs to be included
in the BCR calculation but it is assumed the annual costs will not reduce the BCR cost to a degree that
would influence a decision about this plan. The BCR includes the relocation of buildings B1, B14 and B15
and their associated demolition costs.
Implementation Challenges and Opportunities: The proposed flood protection system crosses several
private land parcels and a NYSDOT right of way. Permanent easements would need to be obtained to
allow the construction and maintenance to be completed.
Accrediting a flood levee system can be an arduous task which requires involvement with state and
federal governments. The length of time from implementation to end of construction is usually at least
5 years.
A primary benefit would include the reduction of flood insurance premiums since the buildings on the
landward side of the levee would be rezoned from a Zone AE to a Zone X. This reduction could exceed
50% savings in annual premiums. Also, buildings landward of an accredited levee system maintain more
resale value than buildings in Zone AE.
45
The flood levee system will require maintenance to remain FEMA accredited such as mowing,
engineering inspection, etc. Interior pumping stations also require annual maintenance to ensure the
pumps are working properly. The annual maintenance cost is expected to range between $6,400 (3
dollars per linear foot of levee and 700 dollars for pump station maintenance) to $15,000 (2% of the
construction cost for levees and pump stations). In case of damage to the levee and pumps, the US
Army Corps of Engineers has a Rehabilitation Assistance Program for FEMA accredited levees that costs
shares (80% federal, 20% local) the repair cost. The 20% local match can be in-kind contribution i.e.
labor, etc.
Funding Sources: The preliminary BCR score of 0.65 does not meet the typical minimal threshold of 1.0
for submission of a grant for FEMA hazard mitigation sources. Neither the CWC FHMIP nor the Ashokan
Stream Management Program will fund the construction of a flood protection system. Costs of
purchase, structural demolition, and relocation of B1, B14, and B15 may be eligible under the NYCFFBO
and the CWC FHMIP. Other potential funding sources may be with State flood hazard mitigation
programs. Municipal bonds may be another source of capital to build the berms, but interest costs
should be incorporated as part of the cost analysis.
Water Quality Protection: Inundation to the 100-year flood elevation does not exist. Sources of water
pollution from seventeen buildings will be substantially mitigated.
Prioritization:
46
Table 12: Plan 5 BCR Results
47
Figure 15: Conceptual Layout of Plan 5
48
4.3.6 Plan #7-Floodplain Benches and Relocation of Route 28A Bridge
Summary: Plan 7 would also build upon Plan 4 by proposing the removal of the Route 28A bridge
crossing and all its’ related approach fill. The purpose of Plan 7 is to see what would be the potential
reduction to flood water elevations if all the obstructions related to the Route 28A bridge were
removed. This includes the bridge, the earthen fill from the bridge eastwards to the Route 28A/State
Route 28 “Y” intersection and the fill associated with the approach on the western stream bank. The
proposed floodplain bench dimensions are roughly the same as Plan 4. The proposed relocation for the
Route 28A bridge crossing could be near the State Route 28 and Piney Point Road intersection or
approximately 1,500 ft north of the Winnie Road and State Route 28 intersection.
Results: The proposed actions reduce water surface elevations notably. In Appendix Figure B-3 (25-
year flood), note the shallow water depths around all the buildings and inundation to the buildings east
of State Route 28 occurs from the backwatering of the Esopus up the unnamed tributary. This could be
completely eliminated with installation of a flap gate on the culvert underneath State Route 28. From
Figure 16 on page 51, it appears the water around building B12 and B13 could be completely eliminated
by filling in a low lying area between the sewage treatment plant and the Boiceville Market. Water
depths are still on average greater than 3.0’ during the 100-year flood (Appendix Figure B-18) and are
over 5’ at Point of Analysis #3 (see Table 11 on page 46). This solution will eliminate nuisance flooding
up to the 25-year flood but the mitigation area will still be inundated at larger flood events (50-year
flood or greater). The water surface elevations during the 500-year flood are reduced by more than
seven feet on average, which shows the impact of the bridge crossing on extreme flood events. On
average, relocating the bridge reduces the 100-year water surface elevations 1.5’. However, removing
the bridge obstructions and increasing floodwater conveyance (floodplain benches) does not solve the
flooding problems in Boiceville during more extreme flood events.
Benefit to Cost Ratio: The cost of construction is estimated to be $2,588,000 (including building
relocation) and the estimate can be seen in Appendix Figure B-19. Using the FEMA’s BCA version 5.1.0
short form, the preliminary benefit to cost ratio was 0.37 (Table 15) and the summary report can be
seen in Appendix Figures B-20 and B-21. The construction cost assumed all the costs associated with
removing the bridge infrastructure and its approach fill and the required costs to upgrade Cold Brook
Road to be the new Route 28A would be part of the Route 28A bridge relocation. The low preliminary
BCR was due to the continued inundation of the buildings beginning at the 25-year return interval flood.
Implementation Challenges and Opportunities: Two buildings (B14, B15) will need to be relocated to
complete the floodplain bench construction. One of the buildings is an active business, the other is a
vacant building. The proposed floodplain bench also crosses several private land parcels and permanent
easements would need to be obtained to allow the construction and maintenance to be completed. The
Flood Advisory Committee did not believe DEP (the funding agency for the Route 28A bridge rebuild)
would consider moving the bridge out of the way without a significant reduction in water surface
elevations. Plan 7’s floodplain benches alone do notably reduce water surface elevations during
moderate and large events but relatively deep water elevations do remain during the 50-year and 100-
year flooding events so it is unlikely this activity is feasible. For this reason other interactions that
assume the bridge would be removed (such as adding a flap gate to the State Route 28 culvert) were not
completed.
49
Funding Sources: With a low preliminary BCR score (0.37) and continued inundation to buildings,
funding for this project will be difficult to obtain.
Water Quality Protection: Continued inundation under proposed conditions beginning approximately
when inundation under existing conditions will not reduce water quality pollution.
Prioritization:
50
Figure 16: Conceptual Layout of Plan 7
51
4.3.7 Plan #9 - Flood Levee System Only
Summary: Plan 9 would mirror Plan 5 but would not include floodplain benches. This plan would
feature an earthen berm (flood levee system) to be constructed that would protect the majority of
buildings from flooding hazards. The alignment of the earthen berm allows the Esopus to flood into its
floodplains unimpeded during a moderate flood event (10-year flood event) while minimizing the
number of buildings that would need to be relocated.
Buildings B1, B14 and B15 would need to be relocated in order to construct the flood protection facility.
Funds are available through CWC and DEP for the purchase of the existing structures and property and
assistance with some of the potential relocation costs for these properties.
The proposed flood protection system should meet FEMA certification requirements for flood
protection systems to ensure building owners landward of the berm would receive discounts on flood
insurance premiums. As such, the elevation of the top of the earthen levee was set to meet NFIP
regulation 65.10(b) which states the levee elevation should exceed the BFE (base flood elevation also
referred to as the 100-year flood event) by three feet, 3.5’ at the upstream end of the levee. The crest
of the levee would be 10’ wide with three horizontal to one vertical side slopes (for mowing). The base’s
footprint would be 70’ wide where it meets the downstream high ground near the Route 28A and State
Route 28 intersection and be 50’ wide where it meets upstream high ground northwest of building B17
(Figure 18 on page 56). It would be on average 6’ high between the upstream high ground and building
B11 and on average 9’ high between B11 and the downstream high ground.
To be a FEMA accredited flood levee, besides meeting the height requirements, the levee must protect
critical infrastructure landward of the flood protection system. Buildings B1 and B11 (Fire House
Company #5 and the wastewater treatment plant respectively) are the two pieces of critical
infrastructure in Boiceville. At building B1, the 500-year flood elevation is 16.5’ higher than the 100 year
flood elevation. FEMA requires critical infrastructure to be protected to the BFE plus 3’ feet freeboard or
the 500 2 year flood elevation, whichever is higher. Therefore, it is unrealistic to protect B1 so it should
be relocated to an area that is not prone to flooding. Building B11 is so close to the floodway (<15’), it is
not possible to put the levee riverward of this building, so this building cannot be protected. The levee
could be put landward of the building which would require the driveway to building B11 to be graded
over the levee.
The levee would tie into the parking lot of building B11. It is assumed that the fill built to the parking lot
and the waste water treatment plant was compacted to industry standard to prevent settling which is
similar to the compaction rate requirements for FEMA levees. The base of the wastewater treatment
plant is 150’ wide which is more than double the width of the levee and it is assumed that this is
adequate to meet hydrostatic design criteria.
Two pumping stations would be needed to drain the landward side of the levee. The purpose of the
pumps is to protect the buildings landward of the levee if interior flooding were to occur at the same
time as exterior flooding conditions. To meet FEMA accreditation guidelines, the pumps must keep inlet
water depths to a foot or less during the design flooding conditions of the levee. If the levee elevation is
2
As noted in section 3.3.4 and 3.3.5, there is uncertainty with the 500-year discharge and its predicted water surface elevation using the
corrected effective hydraulic model but it was assumed that the predicted 500-year water surface elevation is reasonable for use in the LFA.
52
exceeded by floodwaters, the pumps are no longer required to meet their design conditions. The first
pumping station (Pumping station “A”) is located near building B1 where an existing stormwater
drainage ditch would be reconfigured to drain underneath the levee in a culvert with flap gate. This
pumping station would drain approximately 10 acres west of State Route 28. East of State Route 28, as
described in section 4.6, there is a tributary that flows through a culvert underneath the highway. The
tributary features a wetland between it and the highway. Assuming a flap gate is constructed on the
culvert under State Route 28 (which would cause the tributary to backwater if the flap gate was closed
during flooding on the Esopus), it is desirable to avoid flooding the proximal buildings. Under existing
conditions, this wetland stores a large volume of water during flooding conditions (a 500-year flood on
the tributary) resulting in only one building, B3, being inundated by 0.9’ of water (as described in Section
4.6). Therefore with modest grading, a pumping station could keep all the proximal buildings dry when
the tributary is flooding. A three foot earthen berm would need to be placed between the buildings and
wetland to maintain freeboard requirements. The cumulative length of all berms is 1,900’.
Results: The proposed levee provides protection to all landward buildings at the 100-year flood event
(Figure 18 on page 56). The additional freeboard above the water surface elevation also protects the
buildings from larger flood events. It does not protect from inundation during the 500-year flood since
the water surface elevation during this event is notably higher. The proposed activities increase velocity
modestly (<0.2 ft/sec as seen in Table 18 on page 55) which does not increase erosional concerns at the
waste water treatment plant which is armored by large stone (Figure 17 on page 55).
Benefit to Cost Ratio: The cost of Plan #9 is estimated to be $2,548,600 (including building relocation,
constructing the flood protection system, engineering costs, etc.) and the estimate can be seen in
Appendix Figure B-23. Using the FEMA’s BCA version 5.1.0 short form, the preliminary benefit to cost
ratio was 0.97 (Table 19 on page 55). The summary report can be seen in Appendix Figures B-24 and B-
25. The short form BCR does not allow for annual maintenance costs to be included in the BCR
calculation but it is assumed the annual costs will not reduce the BCR cost to a degree that would
influence a decision about this plan. The BCR includes the relocation of buildings B1, B14 and B15 and
their associated demolition costs.
Implementation Challenges and Opportunities: The proposed flood protection system crosses several
private land parcels and a NYSDOT right of way. Permanent easements would need to be obtained to
allow the construction and maintenance to be completed.
Accrediting a flood levee system can be an arduous task which requires involvement with state and
federal governments. The length of time from implementation to end of construction usually is at least
5 years. The Federal Emergency Management Agency (FEMA) website contains a “Levee Resources
Library”, which can be accessed online at https://fema.gov/fema-levee-resources-library.
A primary benefit would include the reduction of flood insurance premiums since the buildings on the
landward side of the levee would be rezoned from a Zone AE to a Zone X. This reduction could exceed
50% savings in annual premiums. Also, buildings landward of an accredited levee system maintain more
resale value than buildings in Zone AE.
The flood levee system will require maintenance to remain FEMA accredited such as mowing,
engineering inspection, etc. Interior pumping stations also require annual maintenance to ensure the
pumps are working properly. The annual maintenance cost is expected to range between $6,400 (3
53
dollars per linear foot of levee and 700 dollars for pump station maintenance) to $15,000 (2% of the
construction cost for levees and pump stations). In case of damages to the levee and pumps, the US
Army Corps of Engineers has a Rehabilitation Assistance Program for FEMA accredited levees that costs
shares (80% federal, 20% local) the repair cost. The 20% local match can be in-kind contribution i.e.
labor, etc.
Funding Sources: The preliminary BCR score of 0.97 does not meet the typical minimal threshold of 1.0
for submission of a grant for FEMA hazard mitigation sources; however, it is close to the threshold and
may improve if a long form BCA is completed to support a funding grant application. Neither the CWC
FHMIP nor the Ashokan Stream Management Program will fund the construction of a flood protection
system. Costs of purchase, structural demolition, and relocation of B1, B14, and B15 may be eligible
under the NYCFFBO and the CWC FHMIP. If these buildings were to be addressed as described in Plan
#9A, the BCR would become 1.89, which may increase opportunities for grant funding. Other potential
funding sources may be with State flood hazard mitigation programs. Municipal bonds may be another
source of capital to build the berms, but interest costs should be incorporated as part of the cost
analysis.
Water Quality Protection: Inundation to the 100-year flood elevation does not exist. Sources of water
pollution from seventeen buildings will be substantially mitigated.
Prioritization:
54
Table 18: Comparison of Existing and Plan 9 Water Surface Elevation and Velocity
Figure 17: Looking Upstream at Rip Rap Embankment at Waste Water Treatment Plant (Building B11)
55
Figure 18: Conceptual Layout of Plan 9
56
4.3.7 Plan #9A - Flood Levee System Only
Summary: Plan 9A would mirror Plan 9 but is broken into two phases to increase the Benefit to Cost
Ratio to improve the competiveness of a grant application for federal or state funding sources. Buildings
B1, B14 and B15 would be relocated using funds available through CWC and DEP for the purchase of the
existing structures and property and assistance with some of the potential relocation costs for these
properties. Once this activity is completed, the Town could then seek and apply for funding to build the
remainder of the planned work.
The proposed flood protection system should meet FEMA certification requirements for flood
protection systems to ensure building owners landward of the berm would receive discounts on flood
insurance premiums. As such, the elevation of the top of the earthen levee was set to meet NFIP
regulation 65.10(b) which states the levee elevation should exceed the BFE (base flood elevation also
referred to as the 100-year flood event) by three feet, 3.5’ at the upstream end of the levee. The crest
of the levee would be 10’ wide with three horizontal to one vertical side slopes (for mowing). The base’s
footprint would be 70’ wide where it meets the downstream high ground near the Route 28A and State
Route 28 intersection and be 50’ wide where it meets upstream high ground northwest of building B17
(Figure 20 on page 61). It would be on average 6’ high between the upstream high ground and building
B11 and on average 9’ high between B11 and the downstream high ground.
To be a FEMA accredited flood levee, besides meeting the height requirements, the levee must protect
critical infrastructure landward of the flood protection system. Buildings B1 and B11 (Fire House
Company #5 and the wastewater treatment plant, respectively) are the two pieces of critical
infrastructure in Boiceville. At building B1, the 500-year flood elevation is 16.5’ higher than the 100 year
flood elevation. FEMA requires critical infrastructure to be protected to the BFE plus 3’ feet freeboard or
the 500 3 year flood elevation, whichever is higher. Therefore, it is unrealistic to protect B1 so it should
be relocated to an area that is not prone to flooding. Building B11 is so close to the floodway (<15’), it is
not possible to put the levee riverward of this building so this building cannot be protected. The levee
could be put landward of the building which would require the driveway to building B11 to be graded
over the levee.
The levee would tie into the parking lot of building B11. It is assumed that the fill built to the parking lot
and the waste water treatment plant was compacted to industry standard to prevent settling which is
similar to the compaction rate requirements for FEMA levees. The base of the wastewater treatment
plant is 150’ wide which is more than double the width of the levee and it is assumed that this is
adequate to meet hydrostatic design criteria.
Two pumping stations would be needed to drain the landward side of the levee. The purpose of the
pumps is to protect the buildings landward of the levee if interior flooding were to occur at the same
time as exterior flooding conditions. To meet FEMA accreditation guidelines, the pumps must keep inlet
water depths to a foot or less up during the design flooding conditions of the levee (when floodwater
elevations match the levee’s top elevation). If the levee elevation is exceeded by floodwaters, the
pumps are no longer required to meet their design conditions. The first pumping station (Pumping
station “A”) is located near building B1 where an existing stormwater drainage ditch would be
3
As noted in section 3.3.4 and 3.3.5, there is uncertainty with the 500-year discharge and its predicted water surface elevation using the
corrected effective hydraulic model but it was assumed that the predicted 500-year water surface elevation is reasonable for use in the LFA.
57
reconfigured to drain underneath the levee in a culvert with flap gate. This pumping station would drain
approximately 10 acres west of State Route 28. East of State Route 28, as described in section 4.6, there
is a tributary that flows through a culvert underneath the highway. The tributary features a wetland
between it and the highway. Assuming a flap gate is constructed on the culvert under State Route 28
(which would cause the tributary to backwater if the flap gate was closed during flooding on the
Esopus), it is desirable to avoid flooding the proximal buildings. Under existing conditions, this wetland
stores a large volume of water during flooding conditions (a 500-year flood on the tributary) resulting in
only one building, B3, being inundated by 0.9’ of water (as described in Section 4.6). Therefore, with
modest grading, a pumping station could keep all the proximal buildings dry when the tributary is
flooding. A three foot earthen berm would to be placed between the buildings and wetland to maintain
freeboard requirements. The cumulative length of all berms is 1,900’.
Results: The proposed levee provides protection to all landward buildings at the 100-year flood event
(Figure 20). The additional freeboard above the water surface elevation also protects the buildings from
larger flood events. It does not protect from inundation during the 500-year flood since the water
surface elevation during this event is notably higher. The proposed activities increase velocity modestly
(<0.2 ft/sec as seen in Table 22 on page 60) which does not increase erosional concerns at the waste
water treatment plant which is armored by large stone (Figure 19 on page 60).
Benefit to Cost Ratio: Under scenario 9A, the buyout and potential relocation costs for buildings B1,
B14 and B15 have not been included as project costs assuming they were funded separately under the
CWC FHMIP and NYCFFBO. The cost of Plan #9A is estimated to be $1,169,000 (Appendix Figure B-27).
Since buildings B1, B14 and B15 have been removed, the benefits also have been reduced to
$2,209,200. Using FEMA’s BCA version 5.1.0 short form, the preliminary benefit to cost ratio was 1.89
(Table 23 on page 60, Appendix Figures B-28 and B-29). The short form BCR does not allow for annual
maintenance costs to be included in the BCR calculation but it is assumed the annual costs will not
reduce the BCR cost to a degree that would influence a decision about this plan.
Implementation Challenges and Opportunities: The proposed flood protection system crosses several
private land parcels and a NYSDOT right of way. Permanent easements would need to be obtained to
allow the construction and maintenance to be completed.
Accrediting a flood levee system can be an arduous task which requires involvement with state and
federal governments. The length of time from implementation to end of construction usually is at least
5 years. The Federal Emergency Management Agency (FEMA) website contains a “Levee Resources
Library”, which can be accessed online at https://fema.gov/fema-levee-resources-library.
A primary benefit would include the reduction of flood insurance premiums since the buildings on the
landward side of the levee would be rezoned from a Zone AE to a Zone X. This reduction could exceed
50% savings in annual premiums. Also, buildings landward of an accredited levee system maintain more
resale value than buildings in Zone AE.
The flood levee system will require maintenance to remain FEMA accredited such as mowing,
engineering inspection, etc. Interior pumping stations also require annual maintenance to ensure the
pumps are working properly. The annual maintenance cost is expected to range between $6,400 (3
dollars per linear foot of levee and 700 dollars for pump station maintenance) to $15,000 (2% of the
construction cost for levees and pump stations). In case of damages to the levee and pumps, the US
58
Army Corps of Engineers has a Rehabilitation Assistance Program for FEMA accredited levees that costs
shares (80% federal, 20% local) the repair cost. The 20% local match can be in-kind contribution i.e.
labor, etc.
Funding Sources: The preliminary BCR score of 1.89 does meet the typical minimal threshold of 1.0 for
submission of a grant for FEMA hazard mitigation sources. This BCR score may improve if a long form
BCA is completed to support a funding grant application. Neither the CWC FHMIP nor the Ashokan
Stream Management Program will fund the construction of a flood protection system. Costs of
purchase, structural demolition, and relocation of B1, B14, and B15 may be eligible under the NYCFFBO
and the CWC FHMIP. Other potential funding sources may be with State flood hazard mitigation
programs. Municipal bonds may be another source of capital to build the berms, but interest costs
should be incorporated as part of the cost analysis.
Water Quality Protection: Inundation to the 100-year flood elevation does not exist. Sources of water
pollution from seventeen buildings will be substantially mitigated.
Prioritization:
59
Table 22: Comparison of Existing and Plan 9A Water Surface Elevation and Velocity
Figure 19: Looking Upstream at Rip Rap Embankment at Waste Water Treatment Plant (Building B11)
60
Figure 20: Conceptual Layout of Plan 9A
61
4.3.8 Plan #10 - Dredging
Summary: The purpose of mitigation solution Plan 10 is to reduce floodwater elevation reduction by
lowering the Esopus Creek channel bottom. This practice is commonly referred to as dredging. Dredging
was a common flood mitigation strategy for decades since it was believed that lowering the river
bottom would also lower flood water elevations. The proposed dredging extents start at the Route 28A
bridge crossing and extends 1,500 feet upstream. The proposed creek bottom would be lowered 5’
which is roughly the amount of water depth around many buildings during the 100-year flood. The
dredging activities would create a 5’ deep trench that is 110’ wide along the channel bottom and 130’
wide on top. Since a drinking water reservoir is located less than a mile downstream, it was assumed
protecting water quality conditions would be required while completing the dredging activities. Per site
observations, the material to be dredged would consist mostly of gravel size or larger material. This size
of material would not need a complex dewatering system and could be immediately hauled off site.
Some sands and silty material would also be excavated and would need an onsite dewatering system to
remove water from the material before it is hauled off site. Porous geotubes have been proposed as
the preferred dewatering method. Once all the material is hauled off site, the construction site would
be stabilized with seed and mulch.
Results: As seen in Figure 21 on page 64 (25-year flood) and Appendix Figure B-30 (100-year flood)
inundation still occurs starting at the 25-year flood event for most buildings. Flooding would occur from
Esopus floodwater directly from overbank flooding on the Esopus and backwater up the unnamed
tributary that flows underneath State Route 28. The Boiceville Market would be dry during the 25-year
flood and on average the flooding depths would be reduced by a half foot around the remaining
buildings. There is less water surface reductions during the larger floods (50-year and 100-year) as seen
in Table 25.
Benefit to Cost Ratio: The cost of construction is estimated to be $3,231,500. Using the similar water
surface reductions in Plan 4 (Table 8 on page 42) as a guide and comparing the construction costs
between Plan #4 ($2,015,000), it is reasonable to judge that the preliminary benefit to cost ratio for Plan
#10 would be at or lower than Plan 4’s BCR (0.14). Using this guidance, a BCR was not completed for
Plan #10 because it is assumed the Plan 10 BCR will be low enough to realize that Plan 10 is not
financially justifiable.
Implementation Challenges and Opportunities: The major challenge for this proposed activity will be
acquiring environmental permits. Dredging has fallen out of favor for permitting agencies such as the
NYSDEC and USACE unless there are justifiable financial incentives or public safety reasons. The main
concern these agencies have is the impact to the aquatic environment. Excavating material from the
creek destroys macro invertebrate habitat and fish habitat such as spawning redds. Another concern is
the sustainability of the gains achieved through dredging. A dredging trench will fill in with gravels and
cobbles being transported through the dredged area from upstream sources. As the trench fills in, the
benefits gained are reduced requiring ongoing dredging, another reason why the permitting agencies do
not favor dredging in streams.
62
Funding Sources: With an assumed low BCR score (less than 0.14) the proposed activity would not be
competitive for a FEMA application. It is unlikely New York State or NYCDEP funding would be available.
Municipal bonds may be the only source of capital to complete these activities. Dredging activities
would need to be repeated because the excavated trench would fill in with sediments being transported
from upstream requiring additional financial resources.
Water Quality Protection: Inundation under proposed conditions continues. Water pollution from the
inundated areas will continue.
Prioritization:
63
Figure 21: Conceptual Layout of Plan 10
64
4.3.9 Plan #11 - Relocate Route 28A Bridge and Waste Water Facility.
Summary: The purpose of mitigation solution Plan 11 is to investigate the removal of all potential
obstacles to flood water conveyance. As seen in the Terrace and Floodplain Terrain map in Figure 1, the
wastewater treatment plant (B11) is a notable fill spot in the floodplain. This fill spot is one of three
obstacles that also constrain the width of the proposed floodplain benches, the other two being building
B14 and B15. The proposed activities for Plan 11 completely remove buildings B11, B14 and B15 and
widen the floodplain bench through this area from 100’ on average to 190’ to demonstrate what the
maximum reduction of water surface elevations could be assuming no obstructions. The width of Plan
11’s floodplain bench is governed by the Boiceville Market. Since the market is the main anchor business
in the Boiceville mitigation area, it is assumed to stay in place. The excavation depth will remain the
same for the benches as seen in Plans 4 and 5, on average 2.5’
Results: As seen in Figure 22 on page 67 (25-year flood) and Appendix Figure B-31 (100-year flood),
inundation still occurs starting at the 25-year flood event for most buildings. Flooding would occur from
Esopus floodwater directly from overbank flooding on the Esopus or backwater up the unnamed
tributary that flows underneath State Route 28. The Boiceville Market would be dry during the 25-year
flood and on average the flooding depths would be reduced by a half foot around the remaining
buildings. There are less water surface reductions during the larger floods (50-year and 100-year) as
seen in Table 27. It is possible to eliminate flooding completely during the 25-year flood for all buildings
by installing a flap gate to the culvert under State Route 28 and filling in low areas. Again, during larger
flooding events, the buildings would remain inundated.
Benefit to Cost Ratio: Using the similar water surface reductions in Plan 4 (Table 8 on page 42) as a
guide and understanding that relocating the waste water treatment plant will result in considerable cost
(cost of construction in 2010 was $12 million dollars), it is reasonable to judge that the preliminary
benefit to cost ratio for Plan 11 would be at or lower than Plan 4’s BCR (0.14). Using this guidance, a
BCR was not completed for Plan 11 because it is assumed the Plan 11 BCR will be low enough to know
that Plan 11 is not financially justifiable.
Implementation Challenges and Opportunities: There may not be suitable locations for relocating the
wastewater treatment plant given the required elevation the plant needs to be able to receive
wastewater under gravity flow. Two buildings (one an active business, B15, the other a vacant
commercial building, B14) would need to be relocated. Also, the floodplain benches would cross several
private parcels so temporary and permanent easements would need to be obtained to construct and
maintain the benches. In addition, the proposed bridge to replace the existing bridge has been
approved by DEP and will be constructed proximal to the existing bridge so this plan may not be realistic
to implement.
Funding Sources: With an assumed low BCR score (less than 0.14) the proposed activity would not be
competitive for a FEMA application. It is unlikely state or NYCDEP funding would be available since the
major cost of the project would be relocating a multimillion dollar sewage treatment plant that was just
built. In addition, the proposed activities do not fully solve the flooding problems.
Water Quality Protection: Inundation under proposed conditions continues. Water pollution from the
inundated areas will continue.
65
Prioritization:
66
Figure 22: Conceptual Layout of Plan 11
67
4.3.10 Plan #12 - Planning and Relocation
Summary: The Town could pursue community planning that identifies future economic growth centers
and critical community facility locations outside of flood prone areas. There are three tools that are
available to the Town in order to reduce its flood losses. These include the voluntary flood buyout
programs, planned relocation of businesses and residences, and a community planning process to help
guide these decisions. The NYCFFBO and CWC FHMIP are designed to help communities move critical
facilities, anchor businesses, residences, and other businesses to areas outside the floodplain.
The highest priority building type to relocate is the critical community facility. Fire House Company #5
(Building B1) in Figure 22 on page 67, is a critical community facility that becomes isolated by
floodwaters during moderate flood events, thus posing a public safety risk. The other critical
community facility located within the study area is the waste water treatment plant (B11) which was
built to be flood resistant and is not a priority at this time.
The second highest priority building(s) type that is considered for relocation with planning are the
identified anchor businesses. An anchor business is defined as a business that if damaged or destroyed
would immediately impair the health and/or safety of a community. Examples of these businesses are
gas stations, grocery stores, doctor’s offices or pharmacies. The Boiceville Market and Boiceville
Pharmacy (B16) (Tax Parcel ID 36.11-1-34), and the Maverick West building (B7) (Tax ID 36.11-1-16.200)
a professional medical office, are anchor businesses that can be relocated.
The third type of building(s) eligible as flood hazard mitigation projects are individual properties that
have experienced or may experience significant damage from flooding. This analysis shows that
seventeen buildings located in the Boiceville mitigation area will be inundated during moderate flood
events (25-year return interval flood). It is also noteworthy that some of these structures have had
flood damage twice within the last 15 years (2005 and 2011). Per NYCFFBO rules, an inundation
damaged property is eligible for the NYCFFBO if, 1) it has been substantially damaged, 2) or based on
analysis, is likely to be substantially damaged in a flood with a high probability of recurrence (greater
than 1% annual chance recurrence), or 3) has been identified by FEMA as a repetitive losses or severe
repetitive loss property. Substantially damaged means that flooding has caused structural damage of
50% or more of the building value. If a property meets any of these criteria then the property could be
eligible for buyout or buyout with relocation.
The Town has the option to support flood buyout with or without relocation. The Town supports
relocation within the Town when possible, and will work with the property owner to assist with
relocation. For the buyout programs, the Town will consider, on a case by case basis, all properties in
the LFA study area, within the 500-year floodplain. To be eligible, all properties must meet the
substantial damage criteria, and have a willing buyer, willing seller, and town approval.
There are several underutilized suitable parcels for relocating anchor businesses and other private
buildings suitable for development in the vicinity of Boiceville. It is recommended that the Town pursue
funding under the CWC Sustainable Communities Planning Program to identify and plan for the
development of relocation properties.
68
Results: Implementation of this plan would gradually reduce the number of buildings being threatened
by future flood inundation. The relocation of buildings would change the character of Boiceville by
physically relocating them away from the business district. The Town recognizes the property owner
may not wish to relocate within the Town. The Town may support flood buyout with or without
relocation. However, the Town supports relocation within the Town of Olive when possible. The Town
will work with the property owner to assist with relocation.
Benefit to Cost Ratio: The relocation cost was calculated using the town taxable value (2013
assessment year) for the particular parcel the building is located on. If multiple buildings exist on the
property, the town taxable value was divided equally between the buildings. Using the FEMA’s BCA
version 5.1.0 short form, a preliminary BCR of 0.62 was calculated as shown in Table 28. The BCR report
can be seen in Appendix Figures B-32 and Figure B-33. From parcel data for building B1, (Fire Company
#5) the value of the building was assumed to be $230,000.
Implementation Challenges and Opportunities: There may be community resistance to changing the
hamlet’s character by moving buildings to new locations. This step, should they choose to move and
protect their property values, will ensure that they will not be flooded again. .
69
Funding Sources: The NYC Funded Flood Buyout Program (NYCFFBO) and the CWC’s Flood Hazard
Mitigation Implementation Program (FHMIP) provide resources for buyout and relocation of buildings
within the LFA area. Additionally, the CWC’s Sustainable Communities Grant Program is available to
communities that wish to update their zoning, ordinances, and planning efforts to better accommodate
flood hazard mitigation measures.
Water Quality Protection: Floodwater inundation and the water pollution sources would continue until
these buildings were relocated out of the flood zone.
Prioritization:
70
4.3.11 Plan #13 - Structural Interventions (Property Protection)
Summary: There are several buildings in the flood prone area of Boiceville that can be either
structurally changed to raise the first floor elevation and/or relocate mechanics (furnace, water heater,
etc.) out of basements. The buildings that are structurally able to be elevated have either crawl spaces
or have existing basements (finished or unfinished). Table 30 shows the buildings that can potentially be
elevated to avoid continued damage from flood inundation. Buildings built on slabs would likely need to
be completely demolished and then rebuilt. In general, raising a building that is constructed on a slab
will require demolishing the existing building, constructing an earthen pad to place the new building on
(to raise the new slab higher than floodwaters) and then constructing the new building. To avoid filling
in the floodplain and causing unwanted negative impacts to flood waters, it is recommended that
buildings with slabs be relocated.
Results: Implementation of this plan would lead to construction within the flood prone areas as the
eligible buildings are lifted and a higher foundation is built. The foundation would allow for floodwaters
to pass through using flood vents. Six of the seventeen buildings located within the flood prone area are
structurally eligible to have both their first floor elevations and the building mechanics (boilers, water
heaters, etc.) raised. Building B17 has its first floor elevation (finished basement) below the Base Flood
Elevation (BFE) but the majority of its business is conducted on the 2nd floor. The finished basement
area could be removed and added to the 2nd floor or as an additional floor. The basement of this
structure could be wet floodproofed at a fairly minimal cost, which would allow the space to be used for
parking and storage as needed.
Benefit to Cost Ratio: The opinion of probable construction cost to raise these structures is summarized
in Table 30 and a detailed construction cost estimate can be seen in Appendix Figure B-34. The cost of
relocating the finished basement in building B17 to the 2nd story or higher was assumed to be the same
as lifting the entire first floor.
The buildings have been proposed to be elevated to 2.0’ above the 100 year water surface elevation
(known as the BFE). Using the FEMA’s BCA version 5.1.0 short form, the preliminary BCR of 0.49 was
calculated (Table 31). The BCA printout report can be seen in Appendix Figures B-35 and B-36.
Implementation Challenges and Opportunities: When buildings are lifted, utilities and ingress/egress
also need to be changed to match the higher first floor elevation. This may pose challenges to the
buildings east of State Route 28 where the distance between the highway and the entranceways is
short, which may be challenging in making the buildings accessible. The eight buildings that have been
built on slabs will be very difficult and expensive to raise and would likely need to be demolished and
relocated on higher ground.
Funding Sources: Following a Presidentially declared disaster, FEMA’s Hazard Mitigation Grant Program
offers property protection grants to buildings with a high BCR score such as building B4 or building B8.
FEMA’s Flood Mitigation Assistance Grant Program is a program made available to States with the
purpose of reducing risk of flood damages to structures that are insured under the NFIP. The Catskill
Watershed Corporation’s (CWC) FHMIP also has funding available, up to 75% of the total cost, to assist
with elevating qualified buildings.
71
Water Quality Protection: Raising buildings will improve water quality by removing some of the water
pollution sources from floodwaters but some buildings and activities cannot be elevated, therefore
some water pollution sources will exist as long as those building remain.
Opinion of
Building ID Basement Type Probable
Construction Cost
B2 Unfinished $61,400
B4 Unfinished $191,560
B6 Unfinished $81,920
B7 Crawl $259,840
B8 Unfinished $71,920
B14 Crawl $665,600
B17 Finished $1,468,000
Prioritization:
72
4.4 Upper Boiceville Road Mitigation Area Summary
Upper Boiceville Road mitigation area contains one location of interest. This is the stream crossing of
Upper Boiceville Road over an unnamed tributary to the Ashokan Reservoir. It is located approximately
one mile southeast of the Boiceville Market as seen in Figure 23 below. There is a community concern
that this town road that crosses a perennial stream can be overtopped during a flooding event. This
condition would make the road impassable and could damage the crossing, requiring the road to be
closed for a long period until it is repaired or replaced. This is a community concern because Upper
Boiceville road is the auxiliary north to south traffic corridor if State Route 28 is impassable due to an
emergency such as a traffic accident or flooding near the State Route 28 and Route 28A intersection. If
the Upper Boiceville Road crossing is closed, it could cause lengthy detours and added travel time for
emergency response vehicles, commerce and daily commuters.
73
4.4.1 Hydraulic Approach
Hydrology: The unnamed tributary is an ungaged stream which means there is no available discharge
data to complete a flood discharge frequency analysis. The drainage area of the unnamed tributary is
2.01 square miles (see drainage area map - Appendix B-37). As such, flood discharges were developed
using the Soil Conservation Service (SCS) Unit hydrograph method imbedded in the proprietary
HydroCAD, Version 10.0 software package. Curve Numbers (CN) values were estimated from review of
land use, aerial photography and Ulster County Soil Mapping. Predominant soil types consist of
Hydrologic Soil Group C/D soils for the inflow area of the drainage area. Land cover primarily consists of
wooded areas.
The 24 hour precipitation values for the 2, 10, 25, 50, 100 and 500-year return interval storms were
obtained from the Northeast Regional Climate Center (NRCC) precipitation data for the project vicinity.
Lag time’s (Tlag) for the inflow hydrographs were computed utilizing the Miller-Folmar methodology from
NRCS procedures, as defined below:
Tlag = L0.65/180.5
Where Tlag = Lag time, in hours
L = Longest hydraulic length of watershed, in feet
The individual peak discharge values for the tributary are shown in Table 33.
Table 33: Flood Discharges for Return Intervals on Upper Boiceville
Return Discharge
Interval (Years) (cfs)
2 130
10 289
25 425
50 561
100 726
500 1,257
Channel topographic data was collected by a laser survey and floodplain topography was obtained from
the 2009 LiDAR survey. The information was joined and then input into a USACE HEC-RAS hydraulic
model. Cross section locations can be been in Appendix Figure B-38. Relative roughness values were
developed from site observation and published values.
74
:
75
4.4.3 Plan #14 - Three Sided Box Culvert
Summary: The Upper Boiceville Road hazard mitigation solution design criteria was to pass the 50-year
flood event which matches the NYS Department of Transportation’s design criteria for principal arterials.
This design criteria included a foot of freeboard (height between 50-year water surface elevation and
top of culvert) to pass floating debris. To avoid complications with the road’s vertical curve profile,
maintaining the existing road profile’s elevation was desirable.
Results: Increasing the clear span from 7’ to 12’ will pass the 50-year storm and meet the desired
freeboard requirements. The proposed dimensions will also pass the 100-year storm. Increasing the
clear span 5’ does not appear to have notable construction constraints since there is adequate space on
either side of the existing bridge to widen the crossing. The proposed crossing can be seen in section
view in Figure 26 below and in profile view in Appendix Figure B-41. The proposed structure would be a
three sided box culvert (natural stream channel bottom) with concrete wing walls.
Benefit to Cost Ratio: The conceptual construction cost estimate for replacing the Upper Boiceville
Road Bridge with a three sided box culvert (design life of 50 years) is $132,100 and a detailed
construction cost estimate can be seen in Appendix Figure B-42. In addition to the upfront capital costs
the assumed annual maintenance costs was $750 (paving, abutment repair, etc.). This costs is rolled
into the final mitigation project cost which is $142,451.
The value of Upper Boiceville Road to the community is an axillary north to south route towards Shokan
and Kingston if State Route 28 is closed. Using FEMA’s BCA Version 5.1.0’s frequency damage
assessment tool, the preliminary benefit to cost ratio was calculated assuming State Route 28 was
closed just north of the Route 28A/State Route 28 intersection and Upper Boiceville Road was needed as
the primary north to south transportation corridor. Due to water depth and velocity occurring at the 50-
year event and the existing structural condition of the crossing, it was assumed the crossing would be
76
damaged beyond repair and would need to be closed until it was replaced and the assumed time for
replacing the bridge (closure length) was 120 days. The detour starts at the closure and requires a
vehicle to travel northwards to Mt. Tremper, turn north on State Route 212, turn southeast onto
Wittenberg Road, continue on Yankeetown Road until it joints with State Route 28. The length of detour
was measured at 10.5 miles and estimated to take an additional 20 minutes of time. A 2013 NYSDOT
Roadway Traffic County Hourly Report counted an average weekday daily traffic (AWDT) count of 5,325
vehicles traveling southbound on State Route 28 between 4/23/13 and 4/29/13. This AWDT count was
used for the BCA traffic trips per day.
Per Figure 13 (page 37), State Route 28 is inundated with water during the 25-year flood event
(probability of this flood event is 0.04 occurring any given year) on the Esopus and is assumed closed.
The Upper Boiceville Road bridge is damaged beyond repair during the 50-year flood event (probability
of this flood event is 0.02 occurring any given year) on the unnamed tributary. The probability of these
two independent events occurring around the same time as each other is 0.008. This probability was
converted into a recurrence interval for the BCA. The preliminary BCR was 7.7 (Table 34) and the
summary report can be seen in Appendix B-43 and B-44.
Table 34: BCA Input and Results for Upper Boiceville Road Plan #14
Using Damage-Frequency Assessment
Implementation Challenges and Opportunities: There are no driveways or utility conflicts that would
interfere with the project. Upper Boiceville Road could be reduced to one lane while one half of the
crossing was built and then the lane would be switched to finish the other half of the crossing.
Funding Sources: This project has a high BCR and may be eligible for funding through the Catskill
Watershed Corporation’s Flood Hazard Mitigation Program, the Ashokan Watershed Stream
Management Program’s SMIP funding, or FEMA hazard mitigation grants after a Presidential disaster
declaration.
77
Water Quality Protection: Not Applicable
Prioritization:
Table 35: Prioritization Score for Upper Boiceville Road Plan #14
78
4.5 DeSilva Road Mitigation Area Summary
DeSilva Road Mitigation Area contains one area of interest. There are two crossings of an unnamed
tributary underneath DeSilva Road and State Route 28 as seen in Figure 27. This area is located
downstream of the Upper Boiceville Road crossing as described in section 4.4 and is located
approximately 0.5 mile southeast of the Boiceville Market. DeSilva Road is a town road connecting
Upper Boiceville Road to the east and State Route 28 to the west.
79
4.5.1 Hydraulic Approach
Hydrology: Since the drainage area upstream of DeSilva Road is essentially the same drainage area for
Upper Boiceville Road, the discharges from Upper Boiceville Road were used for DeSilva Road.
Hydraulics: Channel topographic data was collected by a laser survey and floodplain topography was
obtained from the 2009 LiDAR survey. The information was joined and then input into the USACE HEC-
RAS hydraulic model. Cross section locations can be been in Figure 28. Relative roughness values were
developed from site observation and published values.
Figure 28: Location of Surveyed Cross Section for DeSilva Mitigation Area
80
Figure 29: Section View of Existing Hydraulic Conditions at DeSilva Road Crossing
81
Figure 31: Section View of Existing Hydraulic Conditions at State Route 28 Crossing
4.5.3 Plan #15 - Wider Clear Span Three Sided Box Culvert
Summary: The DeSilva Road hazard mitigation solution design criteria was to pass the 50-year flood
event at the State Route 28 crossing which matches the NYS Department of Transportation’s design
criteria for principal arterials. Since DeSilva Road met typical design standards for town roads, (passing
the 10-year flood) no changes at this crossing were required. The design criteria for the State Route 28
crossing included a foot of freeboard (height between 50-year water surface elevation and top of
82
culvert) to pass floating debris. To avoid complications with the road’s vertical curve profile,
maintaining the existing road profile’s elevation was desirable.
Results: Replacing the existing arch with a three sided box culvert (natural stream channel bottom)
with concrete wing walls and concrete head wall with a clear span of 10 feet (7.5’ rise) will pass the 50-
year flood with a freeboard greater than one foot as seen in Figure 33. The profile under proposed
conditions can be seen in Appendix Figure B-46. To note, a clear span of 12 feet was the narrowest clear
span that would pass the 100-year flood event. Neither the 10 foot wide nor the 12 foot wide box
culvert would improve the hydraulic condition at the DeSilva Road crossing.
Benefit to Cost Ratio: The conceptual construction cost estimate for replacing the DeSilva Road crossing
with a 3 sided box culvert is $297,200 and a detailed construction cost estimate can be seen in Appendix
Figure B-47.
Using FEMA’s BCA Version 5.1.0’s frequency damage assessment tool, the preliminary benefit to cost
ratio was calculated assuming State Route 28 was at the crossing of the tributary. Due to water depth
(0.2’) and velocity occurring at the 50-year event, only modest clean up would be needed. During the
100-year flood event, it was assumed the crossing would be damaged beyond repair and would need to
be closed until it was replaced. Assumed closure length was 120 days. The detour starts at the closure
and requires a vehicle to travel northwards to Mt. Tremper, turn north on State Route 212, turn
southeast onto Wittenberg Road, continue on Yankeetown Road until it joints with State Route 28. The
length of detour was measured at 10.5 miles and estimated to take an additional 20 minutes of time. A
2013 NYSDOT Roadway Traffic County Hourly Report counted an average weekday daily traffic (AWDT)
count of 5,325 traveling southbound on SR 28 between 4/23/13 and 4/29/13. This AWDT count was
used at the BCA traffic trips per day. The preliminary BCR was 4.88 (Table 36) and the summary report
can be seen in Appendix Figure B-48 and Figure B-49.
83
Table 36: BCA Input and Results for DeSilva Mitigation Area Plan #15-Crossing Under State Route 28
Implementation Challenges and Opportunities: DeSilva Road could be closed without much disturbance
to traffic due to low traffic volumes and proximal short detours. Since the road profile can be
maintained, there will be negligible impact to adjacent driveways or the intersection with State Route
28.
Funding Sources: This project has a high BCR and may be eligible for funding through Catskill Watershed
Corporation’s Flood Hazard Mitigation Implementation Program, the Ashokan Watershed Stream
Management Program’s SMIP funding, or FEMA hazard mitigation grants after a Presidential disaster
declaration. Since the existing crossing meets typical NYSDOT design standards for principle arterials,
this project may not be seen as a high priority.
Prioritization:
84
4.6 State Route 28 Ponding Mitigation Area Summary
This mitigation area is located 100’ due east of the State Route 28 and Route 28A intersection as seen in
Figure 34. There is an unnamed tributary running from north to south which flows under State Route 28
where it eventually joins the Esopus a couple hundred feet downstream. There are two flooding hazard
concerns that are caused by the tributary’s floodwaters. The first is the stormwater hazard at the
crossing under State Route 28 which is believed to be undersized causing flooding into the adjacent
homes and businesses to the west of the tributary and east of State Route 28. The second flooding
hazard concern is when the Esopus’ water levels are high due to flooding and how this may result in a
rise in the tributary’s floodwaters if a later rainstorm causes flooding on the tributary. The FAC
suggested there may be up to six buildings that could be impacted from these flooding hazards. The
buildings can be seen in Appendix Figure B-2 (buildings B2 through B7) which shows the buildings are
not inundated by floodwater during the Esopus' 10-year flood event. Compare Appendix Figure B-2 (10-
year flood on the Esopus) to Figure Appendix B-3 (25-year flood on the Esopus) which shows inundation
around the buildings during the 25-year flood event is caused by overbank flooding from the Esopus.
85
4.6.1 Hydraulic Approach
Hydrology: The unnamed tributary is an ungaged stream which means there is no available discharge
data to complete a flood discharge frequency analysis. The respective drainage area of the unnamed
tributary is 0.65 square miles (as seen in Appendix Figure B-50). As such, flood discharges were
developed using the Soil Conservation Service (SCS) Unit hydrograph method imbedded in the
proprietary HydroCAD, Version 10.0 software package. Curve Numbers (CN) values were estimated from
review of land use, aerial photography and Ulster County Soil Mapping. Predominant soil types consist
of Hydrologic Soil Group C/D soils for the inflow areas of the two drainage areas. Land cover primarily
consists of wooded areas.
The 24 hour precipitation values for the 2, 10, 25, 50, 100 and 500-year return interval storms were
obtained from the Northeast Regional Climate Center (NRCC) precipitation data for the project vicinity.
The individual peak discharge values for the tributary are shown in Table 38.
Table 38: Flood Discharges for Unnamed Tributary to State Route 28 Ponding Area
Return Discharge
Interval (Years) (cfs)
2 98
10 199
25 282
50 363
100 459
500 760
Channel topographic data and crossing dimensions were collected by a laser survey and floodplain
topography was obtained from the 2009 LiDAR survey. The information was used to calculate a stage
volume curve and the information was input into HydroCAD model.
Water Surface elevations for several flood events on the Esopus were obtained from the Corrected WEC
HEC-RAS model and can be seen in Table 39. The development of the Corrected WEC HEC-RAS model is
described in the 2016 “Town of Olive Local Flood Analysis 28A bridge replacement and Boiceville Study
Area Flood Mitigation Strategies” report (WEC 2016). Since the flooding of the homes occurs via Esopus
overbank flooding beginning at the 25-year flooding event, only the 2-year and 10-year water surface
elevations were used in this analysis because these are the studied flood events on the Esopus whose
water elevations could influence the unnamed tributary’s water surface elevations.
86
Table 39: Water Surface Elevations on Esopus to
Determine Backwater Effect on State Route 28 Ponding Area
Water Surface Elevation
Return
On the Esopus
Interval (Years)
(Cross Section 8250, in ft)
2 616.7
10 621.1
Table 40: Water Surface Elevation Results In State Route 28 Ponding Area
Table 41: First Floor Elevations and Highest Adjacent Grade of Buildings Near State Route 28 Ponding
87
Results: Not Applicable, no flooding hazard exists
Water Quality Protection: Please refer to discussion in section 4.1 on page 34 about water quality
pollution sources caused by over bank flooding and backwater effects from the Esopus.
88
5.0 West Shokan Study Area
5.1 Watershed Characteristics that Impact Flooding Hazards.
5.1.1 Topography and Climate
The Bushkill watershed drains 19.4 mi2 to the study area beginning at its furthest point 7.2 miles away at
Mombaccus Mountain (elevation 2,631’). The Bushkill watershed drains rugged Catskill terrain with the
highest elevation occurring at High Point which lies southwest of the West Shokan Study area at
elevation 3,400’. The channel elevation at the downstream extent of the West Shokan Study Area near
where the Bushkill meets the Ashokan reservoir is 586’. This creates a steep gradient as water and
sediment make a quick descent to the Study Area. The average channel slope is 5.0% and is classified as
a mountainous stream. A review of the 2013 United States Geological Service (USGS) West Shokan, NY
topographic map show the headwaters of the Bushkill consisting of narrow and steep valleys which
drain to a flat and wide valley in the Study Area. This flat wide valley is an alluvial fan which starts about
1.0 mile upstream of the Maltby Hollow/Bushkill confluence along Maltby Hollow Creek and 0.25 miles
upstream of the Maltby Hollow/Bushkill confluence along the Bush Kill. The average channel slope in
the alluvial fan is 2% which is a notable decrease than the average channel slope in the steeper
headwaters.
An alluvial fan is a fan or cone shaped sediment deposit built up by streams. Alluvial fans are a notable
geomorphic feature in flood mitigation planning because sediments (sands, gravels and cobbles) are
expected to deposit along an alluvial fan and infilling may occur. Infilling results in the space that once
was occupied by water that is now occupied by deposited sediments. This often results in higher water
surface elevations during flooding events because there is now inadequate space within the river to
move floodwaters.
The climate in the watershed is characterized as humid continental with the amount of precipitation
varying based on orographic lifting (at increasing elevations, more rainfall occurs) and annual
precipitation varies from 36” to 60” elevation dependent. This elevation gradient combined with the
potential for large intense rainstorms can transport water and debris (rocks and trees) into the Study
Area creating flooding hazards quickly.
In the Bushkill watershed, the dominant surficial geology feature is unsorted glacial sediment commonly
referred to as glacial till. These features are a heterogeneous mix of silts, sands, gravels and cobbles
and are compacted. Glacial till is not as erodible as glacial outwash since the silts and clays provide
cohesive strength. However, once exposed to moving water the silts and clays become suspended in
the water solution creating turbidity problems. Also if a stream bank consisting of glacial till becomes
overly steepened by erosion along the stream bank toe, it will fail in large sections causing erosion
hazards and ongoing turbidity issues. Sediments from the last ice age’s glacial outwash and continued
89
erosion of the glacial till lining valley floors are probably the main source of sediments that have created
the alluvial fan in the Study Area.
5.1.3 Anthropogenic
The Ashokan Reservoir watershed has been altered by human behavior (anthropogenic). European
settlement of the watershed began in the 1700’s and by the late 1800’s, 80%-90% of the original forests
were gone (Kudish 2000) for tanneries and kiln enterprises. The loss of original forest cover increased
the amount of rainfall runoff from the stripped lands while decreasing the vegetation that held fragile
soils together causing the land to erode. The increased amount of water and sediments rushed down
the mountains slopes into the river valleys below. The resulting intersection of this wall of water and
sediments at the valley floor caused the streams there to undergo severe changes due to increased rain
runoff and the denuded stream banks consisting of highly erodible glacial outwash. Typical changes
during this kind of instability are steep eroding stream banks, narrower water corridors (i.e. little to no
connection to low lying floodplains) and often poor water quality.
Continued anthropogenic activities in the Study Area influence the Bushkill and its tributaries by either
controlling their channel alignments or separating their floodplains from the channel. Long stretches of
rip rap were observed during the windshield survey in an attempt to prevent the creeks and streams
from moving into unwanted areas as seen in Figure 35 below. Stream spoil berms were observed in
multiple locations. A stream spoil berm is a man-made feature created by excavating material from the
stream and dumping them along the side of the stream. The berm’s original purpose could have been
to prevent floodwaters from entering sensitive areas or to lower the creek bed elevation in an attempt
to reduce floodwater elevation or a combination of the two. The size of the vegetation growing on the
stream spoil berms is an indicator of how old the berms may be (less than 25 years). Due to the
geological and geomorphic nature of alluvial fans which are traditionally areas where large amounts of
sediment deposition occur and where channel alignment migration often occurs, it is anticipated more
human interventions will be needed to protect sensitive infrastructure from flood hazards.
Figure 35: Looking upstream of the Maltby Hollow Brook Bridge at rip rap revetment.
Note stream spoil berms upstream of revetment on left bank
90
Figure 36: Looking upstream on Bushkill adjacent to Town Offices.
Looking at right bank stream spoil berms.
Note the tree diameter on berm is smaller than tree diameters landward
5.1.4 Flooding History.
The flow gage data was obtained from the USGS stream gage (ID# 01363382) located on the Bushkill just
downstream of its confluence with Maltby Hollow Brook. This gage has been recording peak discharges
for 14 Water Years (beginning in 2000). The top five flood events are listed below.
Table 42: Top five recorded discharges at USGS Stream Gage #0136382
The discharges used in the HEC-RAS model were reviewed to determine the flood return interval of the
discharges shown in Table 42. A return interval is a statistical term that describes the frequency a
certain discharge will occur. For example, a 10-year return interval flood will statistically occur once in
ten years. The discharges for the study area used in the HEC-RAS model are seen in Table 43. The
largest flood recorded at this station was the 2011 flood. This event was approximately a 50-year return
interval flood. There was no reported damage caused by inundation from overbank flooding in the West
Shokan Study Area but there were several locations that needed repair from erosion after the 2011
flood.
91
Table 43: Flood Discharges From Preliminary FEMA Hydrologic Model
MALTBY HOLLOW
BRIDGE
Figure 37: Location map of the three mitigation areas in The West Shokan Study Area
92
5.3 Bushkill Mitigation Area Summary
Five flooding hazards were identified from the submitted FAC flooding hazards, public flooding hazards
and from the data gap analysis in the Bushkill mitigation area. The cause of all these flooding hazards is
the buildup of debris (logs or stone) deposited during times of high flow. As discussed in section 3.4.1
on page 25, the Bushkill mitigation area is within an alluvial fan and is prone to deposition of gravels,
cobbles and logs. The flooding hazards are locations where buildup and the consequential obstruction
could cause undesirable rises in flood water elevations that could inundate homes, bridges or roads.
Also, the community was concerned the obstructions could also cause undesirable changes in the speed
of water (velocity) that could remove stream bank material (erode) causing bridges or roads to fail.
Figure 38: Location Map of Cross Sections Used in the Hydraulic Analysis and Flood Hazards
93
Figure 39: Section View of the Corrected and Duplicated Topography in the Bushkill
94
5.3.3 Flood Hazard #2 - Watson Hollow Bridge
Summary: The Watson Hollow Road crossing over the Bushkill is a vital transportation route for the
citizens who live in the hamlet of West Shokan. If the bridge were to be rendered unusable, the
residents of 183 homes would need to make a one hour detour of sixty miles to access eastern travel
destinations such as Shokan or Kingston for emergency services, provisions, school and work. If this
bridge were rendered unusable for long periods of time because it was damaged beyond repair and
needed to be replaced, the financial hardships to the several hundred residents living west of the bridge
would be severe.
The left side of the Watson Hollow Bridge (looking downstream) is filled with sediments from a large
depositional feature (gravel/cobble bar). This blockage has reduced flood conveyance volume along the
left bank and forced most of the flood flows along the right bank. With more water being forced along
the right bank, the speed of water (velocity) has increased, resulting in erosion of the Bushkill’s channel
bottom. Evidence of the erosion can be seen in Figure 41. Figure 40 shows there is only 6’ of freeboard
(the space between the bottom of the bridge and the channel bottom) along the left bank. Figure 41
shows that there is over 14’ feet of freeboard along the right bank. Figure 41 also shows the channel
bottom has eroded enough that the bottom of the bridge abutment is hanging in air and that the rip rap
(large stone protection) has been compromised (there are many large stones missing). This condition
should be noted by the county and corrected immediately before the condition worsens.
The concern is if this bridge were to be compromised, it would leave 183 homes without quick access to
emergency services. The most common reasons for the bridge to become compromised are the
overtopping of the bridge or abutment failure due to ongoing erosion.
Figure 40 Looking Downstream at Watson Hollow Bridge Figure 41: Looking at Right Bank at Watson Hollow Bridge
This flood hazard mitigation solution modeled a large obstruction upstream of the bridge to calculate
the change in water surface elevation and water velocity. The FAC selected an obstruction size that
would block 50% of the bridge opening area assuming a larger obstruction blocking more of the opening
area would be removed before the next flood. The obstruction was modeled on the left bank because
there is a large gravel bar forming here with woody vegetation growing on it. These conditions are
95
conducive for a naturally occurring obstruction to form on the left side of the creek as opposed to the
right side of the pier which is open to flow.
Results: Figure 42 shows the obstruction at the upstream side of the Watson Hollow Road crossing
over the Bushkill. This obstruction was 720 square feet which blocked roughly 50% of the 1,450 square
feet opening underneath the bridge. The obstruction caused a rise in all water surface profiles;
however, none exceeded the deck elevation meaning that all floodwaters occurring at the 100-year
flood and during more frequent floods pass under the bridge as shown in Figure 42. The water surface
profile can be seen in Appendix Figure B-51. The water velocities through the bridge increase with the
obstruction (see Table 44). This is more notable during a moderate flood event (the 10-year flood) and
less so during the larger flood events (100-year).
Table 44: Hydraulic Results of the Clear Water Condition vs. Obstructed at Watson Hollow Bridge
96
A sizable obstruction at the Watson Hollow Road crossing over the Bushkill does not cause inundation
hazards but does increase the water velocity through the bridge. This is noteworthy considering the
already compromised right bank abutment. Since no inundation hazards occur at this mitigation
solution, no conceptual design or BCR was completed.
The proposed mitigation solution would be part of the debris management strategy (stable alluvial fan
channel design and engineered sediment depositional areas and engineered log debris entrainment
areas). This would begin ~200’ upstream of the Watson Hollow Bridge and end 100’ downstream of
Potential Flood Hazard location #4. Since this solution does not solve an inundation flood hazard it is
not considered part of the LFA scope and therefore needs to be addressed under a different program.
Funding Sources: The solution’s design and construction budget for protecting the Watson Hollow
Bridge is not covered under the LFA program. However, other resources such as the Ashokan
Watershed’s Stream Management SMIP grants or New York Rising Community Reconstruction Program
funds could be used to address this erosion hazard.
97
5.3.4 Flood Hazard #5 - Homes Along Watson Hollow Road
Summary: Between the Bushkill and Watson Hollow Road there are three homes located proximal to
the Town of Olive town offices located on the Bushkill’s right bank. One of these homes is within the
Special Flood Hazard Area (B100 in Figure 44) and has a first floor elevation (FFE) at approximately 628.
The home is inundated (0.5’) during the 100-year return interval flood. The other homes FFE are
approximately a foot higher and they are located 100’ upstream (west) and 100’ downstream (east) of
B100. The FAC is concerned that the inundation depth could rise rapidly if an obstruction were to form,
blocking floodwater flow near cross section 3000 as shown in Figure 44 (on page 99).
In addition to this concern, the Bushkill has migrated away from its recent centerline and moved
towards the right bank. Evidence of this can be seen in the inundated tree in Figure 43. This tree would
not have grown in the middle of the river and it is leaning, suggesting the supportive soil has been
washed away. The channel migration has also created a headcut. A headcut is a relatively sudden
change in elevation or a knick point in a stream. For example, the headcut in the area where the
Bushkill has migrated features a drop of more than 5’ over a distance of 40’ whereas along the Bushkill’s
centerline there was a drop of about a foot over the same distance. The headcut and the presence of
faster moving waters along the right bank pose a concern to the stream bank protection (rip rap) that is
protecting the three homes along the bank. Headcuts migrate upstream and this headcut could
undermine the scour protection of these homes and could cause an erosion hazard to the homes.
98
Figure 44: Location Map of Cross Sections and Buildings Near Flood Hazard #3 and #5
An obstruction was modeled in the duplicated HEC-RAS model by inserting an obstruction along the left
bank (the area most prone to debris accumulation). The obstruction’s size was increased until a
moderate flood (the 25-year) began to inundate the home (FFE=642.5) which also means the 100-year
flood would then cause moderate damage. The FAC considered it realistic that an obstruction could
block approximately 50% of the active channel. Any larger obstruction would more than likely be
removed. Therefore, a flooding hazard under obstructed conditions occurs if an obstruction blocking
50% or less of the active channel results in a rise in water surface elevation (WSEL) inundating building
B100 during the 25-year return interval flood.
Results: A left bank obstruction was added to section 3000 at station 162 and increased towards the
right bank until the desired rise of the 25-yr WSEL was achieved. The resulting obstruction that achieved
this rise ended at station 667 (a length of 500’) as seen in Figure 45. The channel is approximately 60%
blocked between bank stations, and approximately 73% between the stations of 159 and 874 where the
25-yr WSE reaches the extents of the cross section. The water surface profile comparison between clear
water and obstructed water can be seen in Appendix Figure B-52 and in Table 45 on page 100.
The obstruction size exceeded the threshold to consider Hazard #5 a flood hazard. Appendix Table B-53
does show that velocities increase because of the obstruction which will cause further destabilization of
the area causing the head cut as discussed in the summary to migrate upstream posing an erosion
hazard to the homes along the right bank.
99
Figure 45: Section View of Plugged Cross Section for Hazard #2
Point of Interest 25 Year Water Surface Elevation 100 Year Water Surface Elevation
Plug 2 Corrected Difference Plug 1 Corrected Difference
4689 666.31 666.31 0 Plug 2 Corrected Difference
4113 657.91 657.46 0.45 668.31 668.31 0
3395 644.8 642.86 1.94 659.98 659.78 0.2
3000* 642.53 639.84 2.69 646.97 644.91 2.06
All Values in Feet
*Cross Section Located Adjacent to Building B100 on Watson Hallow Road
(Height of Adjacent Grade is 641.0, First Floor Elevation is 642.5)
Funding Sources: The solution’s design and construction budget for protecting the Watson Hollow
Road Bridge is not covered under the LFA program. However, other resources such as the Ashokan
Watershed’s Stream Management SMIP grants or New York Rising Community Reconstruction Program
funds could be used to address this erosion hazard.
100
5.3.5 Flood Hazard #3 and #1: Man-made Levee and Erosion Hazards to Watson Hollow Road
Summary: This site is located 450’ downstream of the Watson Hollow Bridge along the left bank. There
is a man-made berm at this site as seen in Figure 46 below (hazard #3 in Figure 38, page 93). The
preliminary FIRM (Map# 36111C0410E) does not show this feature so it is not a certified FEMA levee. It
appears this feature was built to provide flood protection from the Bushkill for three homes that are
north of the berm between the Bushkill and Mulrooney Road as seen in Figure 38 on page 93. It is
unclear if this berm was engineered and built following good construction practices (engineered fill,
compaction, etc.) It appears the berm is being maintained by evidence of recent mowing. However,
small woody vegetation is starting to grow which is contra-indicated for the maintenance of flood
protection facilities.
The riverward side of the earthen berm is protected from erosion using rip rap. This can be seen with
the evidence of large stones along the rock toe in Figure 47. In some locations large stones are missing
and could have rolled out of place and been buried. The FAC’s concern is that if this berm fails, then the
adjacent homes could be flooded. The FAC is also concerned that the berm has cut off floodplain access
resulting in increased velocities and water surface elevations proximal to the berm. If this is true and
the problem is corrected, it could reduce water velocities along Watson Hollow Road (Hazard #1 in
Figure 38 on page 93) alleviating the existing erosion of the road embankment and along the berm itself.
Figure 46: Photo Taken at Photo Point #4. Looking Downstream at Man Made Berm
101
Missing Large
Stones
To model a berm failure and to see what its impacts are to water velocities and water surface
elevations, the ground was lowered in the model to below the 10-year WSEL (the lowest flood
modeled). This was completed for section 4113 (seen in Figure 48) and section 3808 (seen in Appendix
Figure B-54).
Figure 48: Cross Section View of Existing Conditions and Failed Berm (or Removed Berm) Conditions
102
Results: The removal of the berm does lower the 100-year water surface elevation (WSE) notably, (0.9’)
at the 100-year flood and modestly at the 25-year flood (0.3’). The reason for this decrease is with the
berm removed, a historic flow channel can receive floodwaters, which had been blocked off by the berm
as seen in Figure 44 on page 99. This increases the area available for flow and reduces WSEL as shown
in Table 46. As shown in Table 47 (page 104), the 100-year WSEL is below the highest adjacent grade
(HAG) of buildings B101-B103 when the berm is removed meaning the berm is not needed to prevent
inundation against the 100-year flood. Interestingly, the 500-year WSEL overtops the berms at sections
4113 and 3808 (661.6’ and 656.5’ respectively) so the berm only protects the buildings for a flood
between the 100-year and 500-year flood. Removing the berm does lower the 500-year WSEL at
sections 4113 and 3808 to 661.1’ and 655.1’ respectively. This means buildings B101 and B102 are not
inundated with or without the berm and building B103 has 1.4’ less water depth if the berm is removed
during the 500-year flood.
There is a notable reduction in water velocities in section 3808 during the 25-year and 100-year floods,
0.47 ft/sec and 1.44 ft/sec when the berm is removed as seen in Table 46. Removing the berm will
reduce the erosive energy along the Watson Hollow road embankment, which is important since
eroding banks along the road were observed and mapped as seen in Appendix Figure A-11. However
there are increases in water velocities immediately upstream and downstream of the berm breached
cross sections due to floodwaters expanding and contracting as they flow into and out of wider areas.
If the berm were to fail, there are no inundation hazards to buildings B101 and B102. Building B103
would be inundated by more water for flood events between the 100-year and 500-year flood which is
so infrequent that it is not considered a hazard. Therefore, it can be concluded that inundation hazards
do not exist at this mitigation site.
Table 46: Velocity Under Existing and Berm Removed Conditions for Hazard #3
103
Table 47: Water Surface Elevations Under Existing and Breached Berm Conditions for Hazard #3
Point of Interest 25 Year Water Surface Elevation 100 Year Water Surface Elevation
Corrected Breached Berm Difference Corrected Breached Berm Difference
4832 668.15 668.15 0 670.54 670.54 0
4689 666.31 666.31 0 668.31 668.31 0
4492 663.34 663.33 -0.01 664.97 664.88 -0.09
4113* 657.46 657.19 -0.27 659.78 658.95 -0.83
3808* 651.94 651.91 -0.03 653.33 651.94 -1.39
3395 642.86 642.76 -0.1 644.91 644.68 -0.23
All Values in Feet
*Lowered Unaccredited Berm at sections 3808 and 4113 down to 10 year water surface elevation)
HAG Elevations: B101-663.0, B102-664.0, B103-653.2
The proposed mitigation solution would be part of the debris management strategy (stable alluvial fan
channel design and engineered sediment depositional areas and engineered Large Wood entrainment
areas). This would begin ~200’ upstream of the Watson Hollow Bridge and end 100’ downstream of
Potential Flood Hazard location #4. Since this solution does not solve an inundation flood hazard it is
not considered part of the LFA scope therefore needs to be addressed under a different program.
Funding Sources: Resources such as the Ashokan Watershed’s Stream Management SMIP grants or
New York Rising Community Reconstruction Program funds could be used to address this hazard.
104
5.3.6 Flood Hazard #4 - Erosive Damage to Route 28A Southern Approach
Summary: This site is located 920 feet upstream of the 28A bridge crossing. A historic flow channel
exists along the right bank and is separated from the active flood waters by a gravel berm as seen in
Figure 49 It appears the berm was created from side-casted gravels and cobbles when the Bushkill was
dredged last and is similar to the side case berm seen in Figure 50 below. It is likely this berm was not
engineered and not built following good construction practices (engineered fill, compaction, etc.)
Large log obstructions and sediment obstructions have begun to form at this location. The concern is
that continued growth of these obstructions could raise water elevations and increase velocities along
the side cast berm. These two potential conditions could cause the side-cast berm to fail and moving
water could reoccupy the historic flow channel. At the downstream end of the historic flow channel is
the Route 28A parking lot and the Route 28A bridge approach. Neither of these facilities are protected
against fast moving water and could become damaged if the side-cast berm fails, allowing the Bushkill to
reoccupy its historic flow path.
105
Figure 50: Looking Downstream at Side Cast Berm
The obstruction was modeled in the duplicated HEC-RAS model by inserting an obstruction along the left
bank (the area most prone to debris accumulation). The obstruction’s size was increased until a
moderate flood (the 10-year) overtopped the berm and floodwaters could enter the historic side
channel leading to possible damage at the parking area pulloff at the Route 28A southern bridge
approach and the approach itself. This damage would occur more frequently with the obstruction in
place since there is less area for water to flow through in the Bushkill, requiring more water to flow in
the side channel towards an area of Route 28A which is not protected against fast moving water. An
obstruction could cause the Bushkill to migrate into the historic channel which would cause increase the
amount of damage to the southern Route 28A approach since the majority of the water would be aimed
there. The FAC considered it realistic that an obstruction could block approximately 50% of the active
channel. Any larger obstruction would more than likely be removed.
Results: An obstruction was inserted at station 200 and ended at station 235 resulting in blocking 113
square feet of the channel area (458 square feet channel area). The obstruction blocks 25% of the
channel resulting in the 10-year WSEL to rise and enter the historic flow channel as seen in Figure 51.
This means that a relatively small amount of blockage could shift more water towards the southern
Route 28A approach leading to its damage.
106
Side Cast
Berm
Historic flow
channel
The rise in water surface elevation does go away before the Route 28A bridge as seen in profile in
Appendix Figure B-55. The obstruction does not cause an inundation hazard at the 28A bridge and its
approach but would cause an erosion hazard at the southern approach pull out.
The proposed mitigation solution would be part of the debris management strategy (stable alluvial fan
channel design and engineered sediment depositional areas and engineered Large Woody Debris
entrainment areas). This would begin ~200’ upstream of the Watson Hollow Bridge and end 100’
downstream of Potential Flood Hazard location #4. Since this solution does not solve an inundation
flood hazard, it is not considered part of the LFA scope therefore needs to be addressed under a
different program.
Funding Sources: The solution’s design and construction budget for protecting the Route 28A approach
is not covered under the LFA program. However, other resources such as the Ashokan Watershed’s
Stream Management SMIP grants or New York Rising Community Reconstruction Program funds could
be used to address this erosion hazard.
107
5.3.7 Plan #5 - Bushkill Debris Removal
Summary: It may be difficult to achieve funding sources for the proposed bridge crossing as discussed in
section 5.5.3. While these funding sources are being secured, it would be optimal to establish
permanent monitoring stations at cross sections 4832, 4689, 300 and 2507 as seen in Figure 38 (page
93) in Section 5.3. After notable flood events, at a regular time interval (annual) or whichever comes
first, the monitoring stations would be surveyed. The topographic data would then be compared to the
data obtained in 2015. When the obstruction blocks 40% or more of the cross sectional area, the
municipality should remove the obstruction.
Implementation Challenges and Opportunities: There may be permitting challenges to complete these
activities. However, most of the obstruction would be removed above the average daily water surface
elevation therefore not disturbing the river bed. These activities are more favorable to permitting
agencies than a complete “dredging” of the stream. The results of the LFA can also accompany a permit
application showing the permitting agencies the importance of this activity which is required to prevent
damage to a piece of critical infrastructure.
Funding Sources: The Catskill Watershed Corporation has resources available for stream debris
removal, other than gravel, but only after storm events. Also, SMIP may fund critical activities to protect
infrastructure.
108
5.4 Dry Brook Mitigation Area Summary
There is one flooding hazard located in the Dry Brook mitigation area located at the Burgher Road
crossing over Dry Brook as seen in Figure 52. The culvert there was a public flooding hazard and a FAC
flooding hazard because there is a concern that it is frequently inundated isolating seven homes to the
north of the crossing.
Figure 52: Location Map of Dry Brook Mitigation Area and Hazard #1
109
Figure 53: Section View of Existing Hydraulic Conditions at Burgher Road
Results: The proposed crossing that passed the 50-year flood was a 7.7 foot rise, 18 foot span three
sided box culvert. It was desirable to maintain the road profile hence maintaining the same vertical rise.
There is enough cover over the crossing and the road to use a three sided box culvert. This box culvert
passes the 50-year flood and has water depth and slower channel velocities during the 100-year flood as
seen in Figure 54 and Table 48. The water surface profile can be seen in Appendix Figure B-57.
110
Figure 54: Section View of Hydraulic Conditions Under Proposed Conditions at Burgher Road
Table 48: Hydraulic Conditions Under Existing and Proposed Conditions at Burgher Road
Benefit to Cost Ratio: Since the FEMA BCA software version 5.1.0 does not have an input if a road is
closed and there is no other detour option, a delay of 5 hours was assumed for private transportation
with a 0.5 mile detour. Road would be closed for 0.5 day after a 25 year flood for clean up by the
municipal department of public works. Burgher Road would be damaged beyond repair starting at a 50-
year flood event because of water depths (>1.25’) and water velocity (<5ft/sec) and it would be 60 days
before road could be replaced. The 100-year flood does overtop the proposed crossing so it is assumed
the road would be closed for a half day after a 100-year flood for cleanup. The proposed crossing would
not be damaged during this event because velocities are much less and road embankment would be
sufficiently armored. The planning level construction cost for this project is $94,000 and a detailed cost
estimate can be seen in Appendix Figure B-58. The BCR was found to be 0.39 and can be seen in Table
49 below and output report summary in Appendix Figure B-59. One of the limitations of the BCA
software is the lack of options it gives to the user to account for the complete lack of access of
emergency response. It should be noted that the seven homes north of the crossing would be
completely isolated from emergency response which should increase the importance of this project.
111
Table 49: BCA Inputs and Results for Dry Brook Mitigation Solution Plan #16
Burgher Road Crossing Replacement
Implementation Challenges and Opportunities: There are driveways to the north and south (<20’) of
the crossing. This would prevent the proposed crossing from being built offset and parallel with the
existing crossing because the horizontal curve needed for the crossover from the Burgher Road to the
proposed crossing would interfere with the driveways. For this reason, it was assumed the proposed
crossing would occupy some of the existing footprint of the crossing.
Funding Sources: The BCA score is too low to make a competitive FEMA mitigation grant; however, the
CWC’s Flood Hazard Mitigation Implementation Program or Ashokan Watershed Management SMIP
grants may be applied for because of the threat these homes could be isolated from emergency
services.
112
Prioritization:
113
5.5 Maltby Hollow Mitigation Area Summary
The Maltby Hollow mitigation area begins at the confluence and extends upstream approximately 400’
as seen in Figure 55. There is one flood hazard in this area which was submitted by the FAC and by the
public and this is located at the Watson Hollow Road crossing over Maltby Hollow. This will be referred
to as the Maltby Hollow Bridge. The concern is that this crossing could be prone to obstruction
formation that could either elevate flood waters that would inundate the bridge or cause high velocities
that could erode bridge abutments and the approaches. This is a critical crossing because there are
dozens of homes west of the crossing that would face a long detour if this bridge was damaged.
Since there was notable difference in geometry, the corrected model’s water surface profile is different
than the duplicate model’s water surface profile as seen in Appendix Figure B-61. A summary table
comparing the two models can be seen in Table 51. It is assumed that some channel modification had
occurred between the time the LiDAR and supplemental cross sections were surveyed in 2011 (post
114
tropical storm Irene) which were used to develop the HEC-RAS model and when the summer 2015 data
was collected. Since the corrected model contains more up to date topographic information, this model
was used as the “existing conditions model”.
Cross Section 10 Year Water Surface Elevation 100 Year Water Surface Elevation
Corrected Duplicate Difference Corrected Duplicate Difference
924 721.43 721.43 0 724.55 724.55 0
626 712.09 713.31 -1.22 715.85 716.27 -0.42
537 710.37 N/A N/A 713.15 N/A N/A
303 704.07 705.44 -1.37 706.85 707.39 -0.54
176 698.89 701.27 -2.38 704.91 704.88 0.03
40 695.19 695.19 0 699.22 699.22 0
All Values in Feet
The FAC was concerned that an obstruction would inundate the bridge causing damage that would force
the bridge to close. This is a serious concern given the number of people (estimated to be several
hundred) who live west of the bridge. The associated vehicle trips (687 Average Annual Daily Traffic)
(ULTC 2014) would face an hour plus detour to get to frequently traveled points east.
The large topographic feature seen in Figure 56 and Appendix Figure B-60 could have been a large gravel
bar that had formed during high flows. It is also possible that large trees could have been caught up on
this gravel bar so it is realistic that an obstruction could form upstream of the bridge. Also, the Ashokan
Watershed Stream Management program was completing the Stream Feature Inventory of Maltby
Hollow during the LFA to map sources of debris in the watershed. However, with an understanding of
the surficial geology, anthropogenic impacts and the stability of the watershed in the neighboring
Bushkill watershed (where 13% of all stream banks are eroding) (AWSMP 2015), it is reasonable to
115
assume that another obstruction could form at the Maltby Hollow crossing that shares similar
watershed characteristics to the Bushkill.
The FAC considered it realistic that an obstruction could block approximately 50% of the active channel.
Any larger obstruction would more than likely be removed. Therefore, a flooding hazard is defined
when an obstruction blocking 50% of the active channel results in flooding conditions that could damage
the bridge beyond repair in a flood event less than or equal to a 100-year return interval flood.
116
Table 52: Hydraulic Results Under Clear Water and Obstructed Conditions
117
5.5.3 Flood Hazard Mitigation Solution Summary: Plan #17-Maltby Hollow Crossing
Summary: The existing bridge could be damaged beyond repair by an obstruction forming at the bridge.
Given the sensitivity of this crossing due to the large amount of people who would be required to make
over an hour long detour, the proposed crossing should pass the 100-year flood with the obstruction in
place. The proposed bridge crossing’s clear span would need to be increased from 55’ feet to 100’ to
improve the amount of area available to convey flood waters. Due to the clear span width, a possible
bridge design was modeled as a two span concrete bridge with a center pier. The existing bridge
alignment could be approximately maintained if it was acceptable to reduce Maltby Hollow Bridge to
one lane during construction. The proposed crossing would also feature stream stabilization measures
(scour protection) that would protect the stream from erosion and also protect the bridge and
abutments.
Results: The proposed crossing would pass the 100-year flood and smaller floods as seen in Figure 58
and summarized in Table 53. A water surface profile comparison can be seen in Appendix Figure B-63.
It was assumed the right bank’s (looking downstream) topography would remain roughly the same while
the left bank would be moved approximately 30’ to the east and laid back to a stable 2 horizontal to 1
vertical slope. The proposed road profile would match the existing road profile. The right bank could
also be laid back (while the left bank remains roughly the same) to a stable slope but this would be
constrained by Brookside Drive which would need to be reconfigured.
Figure 58: Section View of Existing and Proposed Maltby Hollow Bridge
118
Table 53: Hydraulic Results of Existing and Proposed Conditions at Maltby Hollow Bridge
Benefit to Cost Ratio: It was assumed the bridge would be damaged and would need to be closed for 14
days to make the repairs after a 50-year flood before reopening and the bridge would be closed for 180
days after a 100-year flood. After the mitigation activity, the road would need to be closed for a half day
to complete inspections of the bridge.
The proposed detour would start on the west end of the bridge and head west along Watson Hollow
Road toward Peekamoose Road and State Route 55A in Wawarsing. The detour would then take US-209
north towards Kingston and then take head north on State Route 213 towards Olivebridge where it
would meet Route 28A heading northbound towards West Shokan and Watson Hollow Road. The detour
would be 60 miles in length and take approximately 80 minutes. Per the 2013 traffic count along
Watson Hollow Road, between 28A and High Point Mountain Road (station ID 8230) the average annual
daily traffic count is 687 (UCTC 2013).
The construction cost for the proposed bridge was $1,428,300 and a detailed construction cost estimate
can be found in Appendix Figure B-64. The BCR was 1.11 (Table 54) and the BCA summary report can be
found in Appendix Figure B-65.
119
Table 54: BCA Results for Maltby Hollow Plan #17
Implementation Challenges and Opportunities: The bridge could be built upstream of the existing
bridge parallel with the existing road alignment but this would require configuring the driveway that is
west of the crossing. The north half of the bridge could be built while reducing Watson Hallow to one
lane of traffic. Then, while the remaining existing bridge is demolished, the traffic could be shifted on
the new bridge and the rest of the proposed bridge could be built. This approach would require less
reconfiguration of the road and reduce the amount of area that would need to be acquired to build the
project.
Funding Sources: With a BCR over 1.0, the project would qualify for FEMA Hazard Mitigation Grant
Program. However, under existing clear water conditions, the bridge is not prone to damage and FEMA
often uses clear water conditions to qualify/quantify hazard damage. Therefore, the Town may want to
look towards State, CWC, and SMIP resources to pay for the bridge protection project.
120
Prioritization:
121
5.5.4 Plan #2 - Maltby Hollow Debris Removal
Summary: It may be difficult to achieve funding sources for the proposed bridge crossing as discussed in
5.5.3. While these funding sources are being investigated, it would be optimal to establish permanent
monitoring stations at cross sections 176 and 303 as seen in Figure 55 on page 114. After notable flood
events, or at a regular time interval (annual), whichever comes first, the monitoring stations would be
surveyed. The topographic data would then be compared to the data obtained in 2015. When the
obstruction blocks 40% or more of the cross sectional area, the municipality should remove the
obstruction.
Implementation Challenges and Opportunities: There may be permitting challenges to complete these
activities. However, most of the obstruction would be removed above the average daily water surface
elevation therefore not disturbing the river bed. These activities are more favorable to permitting
agencies than a complete “dredging” of the stream. The results of the LFA can also accompany a permit
application showing the permitting agencies the importance of this activity. This activity is required to
prevent damage to a piece of critical infrastructure.
Funding Sources: The Catskill Watershed Corporation has resources available through its “Stream
Debris Removal Program” and only following storm events. Also the Ashokan Watershed Stream
Management Program may fund critical activities to protect infrastructure.
122
6.0 Summary and Recommendations
6.1 Summary
There are two study areas: Boiceville, with inundation hazards, and West Shokan, with erosion hazards.
Boiceville
In the Boiceville mitigation area, this analysis showed that seventeen buildings are prone to flooding at
moderately occurring flooding events (25-return interval flood). Various mitigation scenarios were
evaluated with the proposed three arch Route 28A bridge in place to protect these buildings.
An analysis conducted for this LFA assessed all options vetted by the consultants, the community and
the Flood Advisory Committee. Some alternatives, such as those to improve the conveyance of flood
flows (Plan 4, 10) did not provide significant flood elevations reductions and were not prioritized in this
plan. Other alternatives (Plan 5, 10, 11) were deemed impractical and also are not considered as
potential options. Plan 9, 9A, 12 and 13 received the most attention as potentially viable options to
mitigate flood hazards and improve community resiliency and are further considered in the
recommendations and implementation strategy.
1. Do nothing
If the Town takes no action then individual property owners are left to their own resources to
recover after future flood events. Flood insurance premiums are rising and are projected to rise
sharply over the next decade. Current property owners may not be able to afford flood
insurance. The sale of properties within the FEMA delineated floodplain could be suppressed by
the cost of flood insurance required by lenders as a condition of a mortgage. Repetitive,
uninsured losses can result in owners closing their businesses or abandoning their homes.
123
4. Elevations and Floodproofing
For some structures, it may be possible to either elevate the entire structure or parts of the
structure such as its utilities. Increasingly, funding is becoming available for these options,
however this approach typically requires a design engineer to ensure that the structure will
withstand the stress of elevation. Not all structures, such as structures built on a slab
foundation, can be elevated, and access and aesthetics can be an issue. Elevation can reduce
flood insurance costs, but may not eliminate all future losses. Floodproofing, either to prevent
water from entering a structure (dry floodproofing) or allowing waters to flow through lower
parts of the structure such as a crawlspace (wet floodproofing), may be feasible depending on
the type and use of the structure. The services of a design engineer are typically required to
ensure the modifications are practical and meet NFIP regulations and building codes.
Floodproofing may only reduce damages and may require regular maintenance and an
operation plan.
The information provided in this report offers guidance to how the community may wish to proceed in
addressing the flooding challenges. The Town may choose to implement a combination of more than
one option listed above. A strategy for implementing the LFA is provided after the review of the
recommendations.
The proposed replacement of the Upper Boiceville Road crossing in the Upper Boiceville mitigation area
is technically feasible, financially justifiable and is needed to ensure continuous east to west access in
the event that State Route 28 is impassible.
West Shokan
In the West Shokan Study Area, no flood inundation hazards were found under clear water (no
obstructions) or obstructed conditions. However, there are notable locations where existing conditions
and obstructed conditions cause erosion hazards, some of which could cause road and bridge closures
that would require lengthy detours and pose major impediments to emergency response times. The
erosion hazard condition at the Watson Hollow Bridge should be addressed immediately as well as the
failing road embankment along Watson Hollow Road downstream of the bridge. Permanent monitoring
stations are recommended to be established at areas sensitive to obstructions exacerbating erosive
conditions.
In the Dry Brook mitigation area, the Burgher Road crossing is inundated at moderate flood levels (25-
year flood) and it is reasonable to expect it would be damaged and in need of repair at a 50-year flood.
The crossing’s replacement using FEMA’s BCA toolkit is not financially justifiable but if this crossing were
to be closed for a long period of time, it would isolate the residents to the north which should make this
crossing an important project for the Town to consider.
The Maltby Hollow Bridge passes the 100-year flood under clear water conditions. However, under
obstructed conditions, it is reasonable to assume the bridge is damaged during a 50-year flood resulting
in a short closure of the road. It is assumed that the bridge would be damaged beyond repair during a
100-year flood. A long term closure would create lengthy detours that would pose major impediments
124
to emergency response times and quality of life to the hundreds of residents who live upstream of the
bridge. The project is financially justifiable. Permanent monitoring stations are recommended to be
established at areas sensitive to obstructions exacerbating erosive conditions.
6.2 Recommendations
Recommendations for Both Study Areas:
There are a wide variety of mitigation measures that can protect public and private properties from
flood damage. While this study did look at several of the most desirable broad mitigation actions (see
Table 56 on page 129), these projects often take long periods of time and can be very costly. In these
study areas, particularly in the hamlets where many structures are at risk of flooding, elevations, and/or
wet/dry floodproofing should be explored. Additionally, residents and businesses that exist within the
regulatory floodplain (1% annual risk, FEMA-mapped Special Flood Hazard Area) should be encouraged
to carry flood insurance and make appropriate damage claims when flooding does occur. While carrying
flood insurance will not prevent damage, it will help get property owners back on their feet quickly post-
flood.
1. The Town should seek to assist in the elevation or relocation of the most flood-vulnerable
properties to areas outside of the floodplain where there is owner interest and funding available
through federal, state, or local sources, such as the voluntary NYC-Funded Flood Buyout
Program (NYCFFBO), or the Catskill Watershed Corporation’s (CWC) Flood Hazard Mitigation
Implementation program (FHMIP).
All habitable structures that have the potential to receive 3 feet or more of floodwater against
the structure should be considered a high priority for mitigation by the Town. Owners of these
properties are encouraged to seek input from the Town on possible mitigation actions. Figure 59
was provided by the NYSDEC’s Division of Floodplain Management, and indicates that once the
first floor of a structure is inundated with 4’ of floodwater, it is likely to become “substantially
damaged”. For detailed information on this subject, refer to Section 5R of FEMA’s
“ENGINEERING PRINCIPLES AND PRACTICES for Retrofitting Flood-Prone Residential Structures.”
125
Figure 59: Estimate of Percent Damage to a Structure Based Upon Depth of Inundation
2. The Town should prevent any new development in the floodplain and floodway. The Town
should continue to enforce its flood law, ensure all new construction meets all NFIP criteria, and
consider the potential impact of flooding on proposed activities in the floodprone areas.
3. Not all homes and businesses in the floodplain get flooded. Conversely, properties that are not
in a regulated floodplain can and do flood. Residents and businesses can better prepare
themselves by investing in individual property improvements. These measures may include:
a. Elevation - Home elevation involves the removal of the building structure from the
basement and elevating it to a height such that the first floor is located at least 2 feet
above the level of the 1% annual risk flood. The basement area is then abandoned and
filled no higher than the existing grade. Utilities and appliances in the basement are
relocated to the first floor or installed from basement joists or similar mechanism at an
elevation no less than 1 foot above the BFE. Elevation of homes can be implemented on
a case-by-case basis as property owners approach the Town about mitigation. For
detailed information on this subject, refer to Section 5E of FEMA’s “ENGINEERING
PRINCIPLES AND PRACTICES for Retrofitting Flood-Prone Residential Structures.”
b. “Dry” Floodproofing (Keeps Floodwaters from Entering) - Areas below the flood height
remain watertight. Walls may be coated with compound or plastic sheathing and
window and vent openings must be permanently closed or covered. Floodproofing
should only extend 2-3 feet above the top of the concrete foundation as building walls
and floors cannot withstand the pressure of deeper water. Dry floodproofing is not
allowed by FEMA for new or substantially improved or damaged residential structures
126
located in the SFHA. A structural engineer should always determine whether the wall
and floor systems can resist the hydrostatic and other loads. An operation and
maintenance plan may be required for dry floodproofing in some situations. For detailed
information on this subject, refer to Section 5D of FEMA’s “ENGINEERING PRINCIPLES
AND PRACTICES for Retrofitting Flood-Prone Residential Structures.”
Examples include:
• Installation of watertight shields for doors and windows
• Reinforcement of wall to withstand floodwater pressures and impact forces
generated by floating debris
• Use of membranes and other sealants to reduce seepage of floodwaters through
walls and wall penetrations
• Installations of drainage collections systems and sump pumps to control interior
seepage and manage hydrostatic pressure on the slab and walls
• Installation of check valves to prevent the backflow of floodwaters or sewage flows
through drains
• Anchoring of the building resist floatation and lateral movement.
127
• Install a floating floor drain plug at the lowest point of the lowest finished floor
• Elevate the electrical box or relocate it to a higher floor and elevate electric outlets
to at least 12 inches above the 1% annual risk flood elevation
4. Local officials should promote, and eligible property owners (properties within the 0.2% annual
risk floodplain) should be encouraged to take advantage of the tank anchoring / relocation
program through the Catskill Watershed Corporation.
5. The Town should undertake actions to identify and remove vacant/abandoned structures in the
floodplain to prevent potential flooding hazards.
Table 56 summarizes the prioritization of the proposed mitigation solutions which have been reviewed
by the FAC. During the review of the mitigation solutions, several standalone recommendations were
developed. A standalone recommendation is a recommendation that is supported by the results of
multiple proposed mitigation solutions or general best floodplain management practices. The three
standalone solutions are as follows:
1. Relocate Building B1 (Fire House Company #5) since it is a critical facility and cannot be
protected by any proposed mitigation solution.
2. The Town should consider how future development in the Boiceville Mitigation Area will impact
the proposed flood mitigation solutions or create potential hazards or water quality concerns
(i.e. unanchored fuel tanks or other hazardous material).
3. Any proposed building development within the Boiceville Mitigation Area should meet state
building codes for construction in a FEMA floodplain while not causing deleterious impacts
under flood conditions to neighboring buildings.
The FAC then will select which mitigation strategies and standalone recommendation to present to the
Town Board to improve the Town’s flood resiliency as described in Section 7.0, the local flood mitigation
implementation plan.
128
Table 56: Prioritization Results for Town of Olive Local Flood Analysis
Plan Prioritization
Plan Name BCR
ID Score
B04 Boiceville Plan #4 - Floodplain Benches 18 0.15
B05 Boiceville Plan #5 - Flood Levee Protection System and 16 0.63
Floodplain Benches
B07 Boiceville Plan #7 - Relocate 28A Bridge and Floodplain Benches 22 0.37
B09 Boiceville Plan #9 - Flood Levee Protection System 18 0.97
B09A Boiceville Plan #9 - Two Phased Flood Levee Protection System 20 1.89
B10 Boiceville Plan #10 - Dredging 18 Not
Calculated
B11 Boiceville Plan #11 - Relocate 28A Bridge and Waste Water 18 Not
Treatment Plant Calculated
B12 Boiceville Plan #12 - Planning and Relocation 30 0.62
B13 Boiceville Plan #13 - Structural Improvements 30 0.53
(Property Protection)
UB1 Upper Boiceville Road Plan #14 - Upper Boiceville Road Crossing 34 7.7
DS1 DeSilva Road Plan #15 - SR 28 Crossing 28 4.88
DB1 Dry Brook Plan #16 - Burgher Road Crossing 28 0.39
MB1 Maltby Hollow Plan #17 - Maltby Hollow Bridge 30 1.11
129
7.0 Local Flood Mitigation Implementation Strategy
To increase the Town of Olive’s flood resiliency, an implementation strategy for the flood hazard
mitigation recommendations as described in sections 4.0 through 6.0 are outlined in Table 57. This
implementation strategy has been informed by scientific and engineering evaluation, vetting by several
meetings with the Flood Advisory Committee and by incorporating feedback from the public and Town
Board. The strategy contains standalone recommendations and flood mitigation plans. A standalone
recommendation is a flood resiliency strategy that was common in several flood mitigation plans. The
flood mitigation plans were discussed in sections 5.0 and 6.0 and are presented in Table 56.
The Town of Olive’s Flood Advisory Committee (FAC) has prioritized the standalone recommendations
and flood mitigation plans The FAC recommends to the Town of Olive’s Town Board that the
implementation of each flood resiliency strategy be followed in order as presented in the Plan (Table
57). Reference notes have been included for each strategy so the reader can refer back to the text to
understand the strategy’s background, flood mitigation efficacy, and potential funding sources.
Flood Resiliency
Strategy Name Note
Strategy
1 Relocate Fire House #5 No flood protection system can be designed to
protect this facility to FEMA standards. It is also
within the footprint of the flood protection levee
system (section 4.3.7)
2 Boiceville Plan #12 - The Town must make a decision to protect the
Planning and Relocation hamlet of Boiceville in place or begin to relocate
buildings out of harm’s way. If the town chooses
the latter, several buildings are eligible for
relocation/buyout (section 4.3.10). The Town
should undergo a planning exercise to identify
areas that could be rezoned for building relocation
and identify what if any future growth should occur
in flood prone areas. The first priority group of
eligible buildings that could be relocated are the
three anchor businesses (Boiceville Market,
Boiceville Pharmacy, and the Maverick West Health
Building). The second priority group of eligible
buildings are buildings B14 and B15 within a
potential flood protection facility. This activity may
also be undertaken at the same time as #6
“Structural Improvements”
3 Upper Boiceville Road This is a critical alternative route to State Route 28
Plan #1 - Upper Boiceville and the crossing is in structurally “fair” condition
Road Crossing and is prone to flood damage (Section 4.4).
4 Bushkill and Maltby Establishing permanent monitoring sections will allow
Hollow Debris Removal the Town to understand if these water bodies are
filling with obstructions that could lead to worsened
flooding conditions (Sections 5.5.4 and 5.3.7).
130
Table 57 Continued: Local Flood Mitigation Implementation Plan
Flood Resiliency
Strategy Name Note
Strategy
5 Dry Brook Plan #1 – This culvert can be damaged to the point of
Burgher Road Crossing needing repair during moderately sized
flooding events. This would isolate several
homes leaving them with no vehicular
access (Section 5.4)
6 Boiceville Plan #13 - Depending on the results of Flood
Structural Improvements Resiliency Strategy #2 (Plan #12) some
(Property Protection) buildings are best for the community to
remain where they are. In this case, they
should be protected (elevated with wet
floodproofing) to prevent future flood
damage (Section 4.3.11)
7 Boiceville Plan #9 - Flood If the Town chooses to protect the hamlet
Levee Protection System of Boiceville in place, then as part of Flood
Resiliency Strategy #2, Buildings B14 and
B15 relocation should be prioritized in
relocation (Section 4.3.7). As the funding
for this system is the primary obstacle, an
effort to find funding can be initiated early
after completion of the LFA.
8 Maltby Hollow Plan #1 - This crossing would be inundated by
Maltby Hollow Bridge floodwaters during a very large flood event.
If this would occur than emergency
response times would increase to
unacceptable levels and several hundred
people would need to make a 60 mile
detour if traveling to West Shokan.
131
8.0 References
Ashokan Water Stream Management Program (AWSMP). 2015. Bushkill Stream Management Plan.
Cornell Cooperative Extension of Ulster County (CCEUC). 2007. Upper Esopus Creek Management Plan
Volume I Summary of Findings and Recommendations.
FEMA 2012. Hydrologic Analysis Technical Support Data Notebook. Task Order HSFE02-10-J-0001 for
Ashokan Reservoir Watershed Hydrologic Study, New York. FEMA Contract No. HSFEHQ-09-D-0369
FEMA (2). 2013. Hydraulic Analysis Technical Support Data Notebook. Task Order HSFE02-11-J-0001 for
Esopus Watershed Hydraulic Study, New York. FEMA Contract No. HSFEHQ-09-D-0369.
Ulster County Transportation Council (UCTC). 2013 Traffic Monitoring Report. 2014
Woidt Engineering and Consulting (WEC). 2016. “Town of Olive Local Flood Analysis 28A bridge
replacement and Boiceville Study Area Flood Mitigation Strategies”.
132
9.0 Acronyms
133