DPG-0031/CW-LS-07-LANDSCAPE WORKS FOR PA11 Code Description Total No.
A Approved 0
AN Approved as Noted 10
UR Under Review 0
RR Revised Resubmit 0
R Rejected 0
Total 10
METHOD STATEMENT LOG
Date of (Rev-0) Date of (Rev-1) Date of (Rev-2)
S.No. MS NO. Title Status
Submission Return Submission Return Submission Return
1 DPG-0031-PA11-ZAH-MSS-0001 Method Statement for Swimming pool (Civil Works) 1-Sep-20 9-Sep-20 10-Nov-20 23-Nov-20 AN
2 DPG-0031-PA11-ZAH-MSS-0002 Method Statement for Swimming pool (MEP Works) 1-Sep-20 4-Oct-20 AN
3 DPG-0031-PA11-ZAH-MSS-0004 Method Statement for Automatic Irrigation System 13-Oct-20 15-Nov-20 AN
4 DPG-0031-PA11-ZAH-MSS-0005 Method Statement for Hardscape works 13-Oct-20 14-Nov-20 AN
5 DPG-0031-PA11-ZAH-MSS-0006 Method Statement for Soft Scape works 13-Oct-20 14-Nov-20 AN
6 DPG-0031-PA11-ZAH-MSS-0007 Method Statement for Play Equipment and Fitness Equipment Installation 15-Oct-20 15-Nov-20 AN
7 DPG-0031-PA11-ZAH-MSS-0008 Method Statement for Supplly and Installation of Rubber Flooring 15-Oct-20 15-Nov-20 AN
8 DPG-0031-PA11-ZAH-MSS-0009 Method Statement for Street Furniture 15-Oct-20 15-Nov-20 AN
Method Statement for Fabrication, Supply and Installation of Shade
9 DPG-0031-PA11-ZAH-MSS-0010 15-Oct-20 15-Nov-20 AN
Structure
10 DPG-0031-PA11-ZAH-MSS-0011 Method Statement for Supply and Installation of Chain Link Fence 15-Oct-20 14-Nov-20 AN
Page 1 of 3
Balance Method Statement Plan %
Prepare & Submit Method statements - Etisalat/DU Works 100%
Prepare & Submit Method statements - Security Network 100%
Prepare & Submit Method statements - Electrical Works 100%
Prepare & Submit Method statements - Street Lighting Works 0%
Prepare & Submit Method statements - Road Crossing duct Works 0%
Prepare & Submit Method statements - Road Works 10.71%
BL Project Start BL Project Finish
23-Jul-18 27-Aug-18
31-Jul-18 4-Sep-18
5-Sep-18 8-Oct-18
16-Dec-18 17-Jan-19
11-Nov-18 15-Dec-18
9-Oct-18 10-Nov-18