HALFAYA PROJECT SURFACE FACILITY
Additional Tanks for CPF1
                                                                     IMCO
DETAIL DESIGN   DOC.NO.: HFY2-E1549-CPF1TA-GEN-PD-0012   REV.: 0   P AGE 2 OF
5
                                  CONTENT
          1. SCOPE………………………………………………………………………..
           2. PURPOSE……………………………………………………………………
           3. SURFACE PREPARATION……………………………………………….
           4. APPLICABLE CODE……………………………………………………….
           5. PROCEDURE……………………………………………………………….
           6. INSPECTION AND ACCEPTANCE CRITERIA…………………………
           7. REPAIR AND RETEST…………………………………………………….
           8. INSPECTION REPORT……………………………………………………
                          9. INSPECTION FORMAT……
                                 ………………
                            ………………………………
                       HALFAYA PROJECT SURFACE FACILITY
                                Additional Tanks for CPF
                       IMCO
DETAIL DESIGN       DOC.NO.: HFY2-E1549-CPF1TA-GEN-PD-0012                    REV.: 0       P AGE 3 OF
5
        1.0     SCOPE:
        This test procedure shall be used to check after the first weld pass of the weld joint of
        shell to annular plate.
        This procedure details out the requirements of kerosene leak test for single sided /
        single layer weld joints that are accessible from back side for visual examination.
        2.0     PURPOSE:
        The purpose of this procedure is provide a necessary guide line to carry out oil-chalk
        test to check the weld joint of shell to annular plate.
        3.0     SURFACE PREPARATION:
        - Weld shall be thoroughly cleaned by hand wire brush or rotary wire brush to
        remove oil, grease, slag, rust and free from any substances that may cause and
        indication during the application of the chalk.
        - Weld shall be visually inspected and unacceptable defects if any shall be repaired
        by grinding / grinding and welding.
        - Oil leak test shall be carried out only when the surface temperature of the area to be
        examined is not less than 5 qC and not more than 52 qC.
        4.0     APPLICABLE CODE AND REFERENCE:
        API 650 Sec (Clause 7.2.4 (d)) / ASME Section V article 6).
                        HALFAYA PROJECT SURFACE FACILITY
                                Additional Tanks for CPF1
                                                                                                   IMCO
DETAIL DESIGN         DOC.NO.: HFY2-E1549-CPF1TA-GEN-PD-0012                     REV.: 0       P AGE 4 OF
5
        5.0         PROCEDURE:
        After completion of root weld of the inside of the shell to bottom plate joint. Chalk
        solution will be applied to the root weld uniformly.
        Ensure chalk solution is sufficiently dry prior to application of penetrating oil (light
        diesel or high flash point oil).
        During visual examination, a minimum 1000 lux of visible light must be present.
        6.0         INSPECTION AND ACCEPTANCE CRITERIA:
        After the application of the penetrant oil, hold it as per the instruction of the Engineer-
        in-charge. (Duration time shall be minimum - 4 hrs. for light diesel, high flash point
        penetrating oil) API 650 Cl 7.2.4 (d) Edition XI
        Examine the root weld visually for the evidence of wicking.
        7.0         REPAIR AND RETEST:
        If any defect found then the same shall be repaired as per the approved procedure.
        Re- examines the repair spot and additionally minimum 150mm. for repair spot on
        both directions.
        Repeat the process until there is no evidence of leaking.
        After completion of the test thoroughly clean the joint from both sides for the further
        welding.
              9.0     INSPECTION REPORT:
        Test shall be carried out jointly with the SERT engineer in charge and the
        company's representative/inspector (PMC).
        Acceptance of the test will be to the concurrence of the PMC representative.
        Test to be recorded in the approved format.
                           HALFAYA PROJECT SURFACE FACILITY
                                  Additional Tanks for CPF1
                                                                                                              IMCO
DETAIL DESIGN         DOC.NO.: HFY2-E1549-CPF1TA-GEN-PD-0012                           REV.: 0         P AGE 5 OF
5
        9.0 INSPECTION FORMATE:
        Inspection Code:                                       NDT Conclusion:
        NDT METHOD:
        Penetrating Liquid:                                    Surface Condition:
        Cleaner:                                               Equipment Type:
        Developer:                                             Soaking Tim
        APPLICABLE CODE AND REFERENCE:
           - API 650 Sec (Clause 7.2.4 (d))
           -   / ASME Section V article 6).
           - HFY2-E1549-CPF1TA-INS-ITP-0001
                               Defect Location and Distribution Diagram:
        Location                    Result
        Weld    Material   Thickness   Defect     Defect       Defect   No Visible    Visible       Accept/
        No.                  (mm)      Location   length(mm)   Type     Indications   Indications   Reject
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
               SERT                      PMC QA/QC
                                       NAME:                            NAME:
        NAME:
                                       DATE:                            DATE:
        DATE:
                                       SIGNATURE:                       SIGNATURE:
        SIGNATURE: